www.jacobs.com | worldwide
Stakeholder Presentation Lancaster Rapid Transit Feasibility Study
23rd June 2016
Study Overview
• Description of Study:
– Feasibility Study for a Rapid Transit Route from South
Lancaster to Lancaster City Centre to Morecambe and
Heysham
• Key Aims of the study:
– Set and prioritise objectives
– Appraise different options
– Develop potential options
– Confirm optimal options / packages
– Investigate to what extent a rapid transit service can operate in
an integrated way with the Park and Ride service
2
The Study Corridor
3
Four Sections
• Heysham to Morecambe
• Morecambe to Lancaster
• Lancaster City Centre
• South Lancaster
Travel trends within the corridor
4
• Almost 2000 people travel between
Morecambe and Lancaster for work by car
(2011 Census)
• The bus mode share for Heysham to
Lancaster University is 11%, compared to
31% from Central Lancaster
• The overall cycle to work mode share from
Heysham is 3%, from Morecambe is 6%
and from Lancaster is 7%. The national
average is 3%.
Existing Bus Service
Provision & Frequency
5
• Majority of services
provided by Stagecoach
• Services don’t always stick
to main roads / direct
routes
• Peak frequency up to one
bus every 3 / 4 minutes
• End to end journey times
can be up to ~1 hour 20
minutes
Stakeholder Workshop
• Early Stakeholder Workshop held March 2016
• Stakeholders informed then voted on Study
Objectives
• Objectives were prioritised and then weighting
added to the top two when appraising Options
6
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%33.55%
12.26%
20.00%
11.61%
0.65%
7.10% 3.87%
10.97%
Option Generation
• Initial list of Options generated, including:
– Soft Measures (Low Cost)
– Soft Measures (Medium / High Cost)
– Tram / Train
– Monorail
– Bus Rapid Transit
– Recasting of existing bus network
7
Initial Option Appraisal
• Each Option appraised
using an Appraisal Tool
• Scored against:
– Weighted Objectives
– Deliverability
– Feasibility
– Cost
8
Corridor Wide Options Ranked and Sifted
9
Option Option Summary Appraisal
Score
Deliverability Practical
Feasibility
Cost
05 Bus Rapid Transit 15 Deliverable Potential
Issues £5-20m
03 Tram / Train
14 Deliverable,
but with
challenges
Potential
Issues >£20m
04 Monorail
9 Very difficult
to deliver Not Feasible >£50m
06 Recasting of existing bus network
9 Deliverable,
but with
challenges
Feasible <£250k
02 Soft measures - Med/High Cost 5 Deliverable Feasible £250k -
£1m
01 Soft measures - Low Cost 4 Deliverable Feasible <£250k
BRT Options Selected for Final Appraisal
10
• BRT Option
top scoring, rail
options to be
considered in
another study
• Various BRT
packages then
appraised for
each section of
the Corridor
• Low,
• Medium &
• High Cost
Option
Number
Option Summary
7 Heysham to Morecambe section - Low Cost Measures. May include Bus Priority through
signals, i.e. a Hurry Call and revisions to existing bus routings.
8 Heysham to Morecambe section - Medium Cost Measures. May include physical bus priority
measures such as short sections of bus lanes on existing carriageway of the A589 and signal
priority.
9 Heysham to Morecambe section - High Cost Measures. May include remodelling of junctions
to reduce delays and section of bus lanes / junction bypass lanes along the A589.
10 Morecambe to Lancaster section - Low Cost Measures. May include, Bus Priority through
signals, i.e. a Hurry Call
11 Morecambe to Lancaster section - Medium Cost Measures. May include bus lanes / priority on
Morecambe Road, relocated / improved Morecambe Bus Station and improved PT access to White
Lund.
12 Morecambe to Lancaster section - High Cost Measures. May include all Medium Cost
Measures as well as a new bridge over the River Lune (potentially bus and cycle only) and could
also include bus gate at West Road.
13
Lancaster section - Low Cost Measures. May include contraflow sections to accommodate more
direct bus movements, Bus Priority through signals, i.e. a Hurry Call.
14 Lancaster section - Medium Cost Measures. May include revisions to the existing gyratory to
accommodate more direct bus movements, physical bus priority measures.
15 Lancaster section - High Cost Measures. May include significant remodelling of the city centre,
including the gyratory, to give greatest priority to walkers, cyclists and buses.
16 Lancaster City Centre to South Lancaster and University Section - Low Cost Measures. May
include Bus Priority through signals, i.e. a Hurry Call.
17 Lancaster City Centre to South Lancaster and University Section - Medium Cost Measures.
May include physical bus priority measures (e.g A6 / Pointer roundabout), Bus lanes on A6.
18 Lancaster City Centre to South Lancaster and University Section - High Cost Measures. May
include a new 'future proofing' planned residential and commercial development areas, i.e. linking
A6 / A588 Ashton Road via public transport orientated access options.
Bus Rapid Transit Selected For Further Appraisal
• Ranked list created
following appraisal of
each Option
• Medium or High
Cost Options chosen
for further
development for
each section
• Low cost Options do
not generate
required benefits
11
Option Option Summary Appraisal
Score
Deliverability Practical
Feasibility
Cost
18 Lancaster City Centre to South Lancaster and
University Section - High Cost Measures
16 Deliverable,
but with
challenges
Potential
issues
£250k -
£1m
15 Lancaster section - High Cost Measures 15 Deliverable,
but with
challenges
Potential
issues
£1m -
£5m
12 Morecambe to Lancaster section - High Cost
Measures
15 Deliverable,
but with
challenges
Potential
issues
>£20m
11 Morecambe to Lancaster section - Medium
Cost Measures
13 Deliverable,
but with
challenges
Feasible £1m -
£5m
08 Heysham to Morecambe section - Medium
Cost Measures
7 Deliverable,
but with
challenges
Potential
issues
£250k -
£1m
09 Heysham to Morecambe section - High Cost
Measures
7 Deliverable,
but with
challenges
Potential
issues
£1m -
£5m
14 Lancaster section - Medium Cost Measures 7 Deliverable,
but with
challenges
Potential
issues
£250k -
£1m
17 Lancaster City Centre to South Lancaster and
University Section - Medium Cost Measures
7 Deliverable Potential
issues
£250k -
£1m
16 Lancaster City Centre to South Lancaster and
University Section - Low Cost Measures
5 Deliverable Feasible <£250k
10 Morecambe to Lancaster section - Low Cost
Measures
4 Deliverable Feasible <£250k
07 Heysham to Morecambe section - Low Cost
Measures
3 Deliverable,
but with
challenges
Potential
issues
<£250k
13 Lancaster section - Low Cost Measures 2 Deliverable Feasible <£250k
12
• Additional data sourced to
allow more detailed
appraisal of Options:
– Heysham – M6 Link Road
Traffic Model
– Detailed mapping
– TRACC Accessibility Analysis
– 2011 Census
– Accident Statistics
– Lancaster Air Quality Action
Plan
– Development Plans
Further Data Analysis Undertaken
Future Routing Developed / Refined
• Corridor further defined to
focus Option development
• Most direct routes between:
– Heysham to Morecambe
– Morecambe to Lancaster
– Lancaster City Centre
– Lancaster CC to Lancaster
South
– Cognisance of existing X2
service between Heysham
South & Lancaster
• Also considered Jct 34 P&R
link and potential new Lune
Bridge link 13
BRT Option Development – Heysham to Morecambe
• Medium Cost Package:
– ‘Green Wave’ signal
readjustments at:
• Oxcliffe Road
• Regent Road
• Central Drive
– Raised kerb bus stop access
– Real-time passenger
information
– Improved cycle facilities
14
BRT Option Development – Heysham to Morecambe
• High Cost Package
– As medium with:
– Reconfiguration of junctions
– Sections of bus lane
– Bus-gates / junction bypass lanes
15
BRT Option Development – Morecambe to Lancaster
• Medium Cost Package:
– Several sections of bus
lanes
• Central Drive
• Lancaster Road
• Morecambe Road
– Signal junction priority
– Bus interchange
improvements
16
BRT Option Development – Morecambe to Lancaster
• High Cost Package
– Medium package plus:
– New Lune crossing – PT &
walk / cycle only
– Bus-gate at West Road /
Lancaster Station
– Serves new Luneside
developments
– Serves Lancaster Rail
Station
– Serves Lancaster Castle
– Could serve future P&R
services 17
BRT Option Development – Lancaster City Centre
For a separate study but
indicative measures:
• Medium Cost Package:
– Re-visiting traffic circulation
/ priority in some areas:
• Bus-gates
• Bus lanes
– Signal junction priority
18
BRT Option Development – Lancaster City Centre
• High Cost Package
– Significant remodelling of city
centre:
• Revisions to gyratory
system to give highest
priority to buses,
pedestrians and cyclists
• Removal of one-way
system for buses
• Consideration of
congestion charging / low
emission zone scheme
19
BRT Option Development – Lancaster to Lancaster South
• Medium Cost Package:
– Priority to buses at signals
– Sections of bus lanes on A6 south of Pointer Roundabout
20
BRT Option Development – Lancaster to Lancaster South
• High Cost Package
– Bus priority arrangements at Pointer Roundabout
– Sections of bus lane on Ashton Road
– Bus priority infrastructure through strategic
development sites
21 * Indicative alignment only
Option Journey time saving estimates
Section Option Time saving
• Heysham to Morecambe - Medium Cost 60 seconds
• Heysham to Morecambe - High Cost 120 seconds
• Morecambe to Lancaster - Medium Cost 130 seconds
• Morecambe to Lancaster - High Cost 430 seconds
• Lancaster City Centre - Medium Cost 180 seconds
• Lancaster City Centre - High Cost 300 seconds
• Lancaster CC to Lancaster South – Medium 55 seconds
• Lancaster CC to Lancaster South - High 105 seconds
22
Option Cost estimates
Section Option High level cost
• Heysham to Morecambe - Medium Cost £100-250k
• Heysham to Morecambe - High Cost £250-500k
• Morecambe to Lancaster - Medium Cost £500-1000k
• Morecambe to Lancaster - High Cost £10-20 million
• Lancaster City Centre - Medium Cost £250-500k
• Lancaster City Centre - High Cost £1-5 million
• Lancaster CC to Lancaster South – Medium £100-250k
• Lancaster CC to Lancaster South - High £1-5 million
23
Option Combinations
• There are 16 different combinations of Option
packages, i.e:
– Medium, medium, medium, medium
– High, medium, medium, medium
– Etc.
• Different combinations of packages will have
different collective costs and benefits
• Allows cherry picking of ‘best’ overall package,
but makes appraisal complicated!
• Therefore packages appraised individually & as
packages
24
Example Time Benefit / Cost estimates of Packages
• A package of all medium cost options:
– Time Savings ~ 7 minutes
– Package Cost ~ £1.3 million
• A package of two medium and two high cost options:
– Time Savings ~ 10 minutes
– Package Cost ~ £2.7 million
• A package of all high cost options:
– Time Savings ~ 16 minutes
– Package Cost ~ £12.8 million
25
Testing of Packages – Improving Access to Employment
/ Services in Lancaster – Medium Cost
TRACC analysis – All Medium Cost Packages:
• Before
26
• After
TRACC analysis comparison –
All Medium Cost Packages:
27
Population within 30 mins
journey time:
Now: 60,886
All medium (current pop.): 62,193
All medium (future pop.): 66,559
Additional(current pop): 1,307
Additional(future pop): 5,673
Testing of Packages – Improving Access to Employment
/ Services in Lancaster – Medium Cost
TRACC analysis – All High Cost:
• Before
28
• After
Testing of Packages – Improving Access to Employment
/ Services in Lancaster – High Cost
TRACC analysis comparison –
All High:
29
Population within 30 mins
journey time:
Now: 60,886
All high (current pop.): 65,485
All high(future pop.): 69,956
Additional(current pop): 4,600
Additional(future pop): 9,070
Testing of Packages – Improving Access to Employment
/ Services in Lancaster – High Cost
Other objectives assessed:
• Safety: Investigation in accident hotspots
• High PT mode share = less vehicles on network so
likely lower accident potential
30
• Enhance sustainable modes:
– all option packages support or enhance walk / cycle
accessibility through design, particularly with:
• Morecambe interchange
• Lune Bridge
• Link through future South Lancaster development
• Maximise interchange opportunities:
– all option packages support or enhance interchange with bus,
rail, P&R and walking / cycling, particularly with:
• Morecambe interchange
• Lune Bridge
– Improve overall environment / future proof:
– All options, combined with new Link Road, should increase PT
model share = less vehicles = improved air quality
• BRT vehicles should be latest Euro standard 31
Other objectives assessed:
Way Forward / Next Steps
• Investigate funding opportunities
• Discuss with Working Group
• Further develop chosen package
• Develop Business Case
32
www.jacobs.com | worldwide June 17, 2016
© Copyright Jacobs
Any Questions?