Date post: | 08-Mar-2015 |
Category: |
Documents |
Upload: | bhavesh919 |
View: | 87 times |
Download: | 3 times |
Standard Costing
• Standard Costing system is a tool which is used to control over the cost of production,
• SC attempts to keep the cost at minimum level by planning and controlling,
• Under this system the cost of production of each unit is predetermined on some scientific basis,
• And then management try to control the actual costs not to exceed to predetermined standard,
• If actual cost exceed to standard then variance are calculated and then reason are find out to control the costs in future
Advantages of SC• Helpful in controlling,
• Helpful in measurement of operating efficiency,
• Helpful in policy making,
• Encourages for maximum utilization of resources,
• Help to reduce wastage,
• Helpful in coordination among various cost centers,
Limitations of SC• Fixation of standard is not possible for every type of
operation,
• Wrong standards may result in wastage of time, money,
• Need of services of experts for accurate determination of standards which increases total cost and thus cost of production,
• Fixation of standards are not fixed in nature but subject to review time to time as per the need of time, this makes it time consuming,
• Despite of above limitations, standard costing system is a unique system in itself and must be used for efficient control purpose.
System of Standard Costing
• Following steps are taken out for the development of a sound system of standard costing ……….
1- Establishment of a cost centre, 2- Determination of standards, 3- Setting of standards,4- Setting of time period,5- Collection of actual cost data,6- Analysis of variance
1- Establishment of a cost centre
• Under this first that cost centre is to be identified for which the standards are to be determined for cost control purpose,
• Because there are many cost centers like production centre, service departments, administrative departments, selling and distribution departments,
2- Determination of standards,
• There are various types of standards,• First it is to be determined that which type of the standard is to be used for control
purpose,• These standards are…….
1- Ideal standards: cost under such standard is determined under ideal conditions which are rarely fulfilled. For example mileage of a bike. Such standards fails to consider normal material wastage and idle labour time, power failure.
2- Attainable standards: are based on past performance and standards are set on the basis of past performance for future. Such standards may be lower than what can be achieved with reasonable efforts. Such standard consider the usual production problems such as normal material wastage and idle labour time, power failure.
3- Basic Standards: are used for basically those costs which are fixed in nature and not influenced by changes in material cost , labour cost. Thus they are used for a long period of time.
4- Normal Standards: set the costs under normal working conditions and consider the expected changes over a long period of time.
3- Setting of standards,
• After determining the type of standard to be used for comparison purpose,
• The next step is to setting of standards for various types of costs,
• These standards may be set for Material, Labour of Overheads or for all.
4- Setting of Time Period
A particular period is to be determined for which actual costs is to be compared with standard.
5- Collection of actual cost data,
The actual cost on target cost centre incurred for a particular time period is collected through cost accounting records,
6- Analysis of variance
• A variance representing the difference between standard cost and actual cost incurred is to be calculated,
• Variance ensures whether costs are being kept under control or not,
• On the basis of variance the probable causes for deviation are identified,
• And the responsibilities are assigned for deviations.
Variance Analysis
Types of Variance
Material Usage Variance
Material Yield Variance
Material Mix Variance
Material Price Variance
Material Variance
Labour Variance
Overheads Variance
Other Variance
Labour Idle time Variance
Labour Mix Variance
Labour Efficiency Variance
Labour Rate Variance
Labour Cost Variance
Variable over.Efficiency vari.
Fixed over.variance
Fixed over.Volume variance
CalendarVariance
Variable overheadsVariance
Sales valueVariance
Sales price Variance
Sales volumevariance
ProfitVariance
Material Cost Variance
• Material cost variance arises due to variance in the price of material or its usage.
• This can be calculated by using the following formula,• Material Cost Variance = (SQ x SP) – (AQ x AP) ,
• Where,SQ = Standard quantity for the actual outputSP = Standard price per unit of materialAQ = Actual quantityAP = Actual price per unit of material
• A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).
Material Price Variance
• Material cost variance may arise due to number of reasons like fluctuations in market prices, error in buying due to wrong purchasing policy etc,
• This can be calculated by using the following formula,• Material Price Variance = (SP – AP) x AQ
• Where,SP = Standard price per unit of materialAQ = Actual quantityAP = Actual price per unit of material
• A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).
Material usage Variance• Material Usage variance is the difference between the actual
quantities of raw materials used in production and the standard quantities that should have been used to produce the product,
• MUV may arise due to number of reasons like Pilferage of materials , Wastage , Sub-standard or defective materials etc,
• This can be calculated by using the following formula,• Material Usage Variance = (SQ – AQ) x SP
Material Mix Variance
• MMV is calculated when a product uses mixture of different raw materials,
• MMV is that portion of the materials quantity variance, which is due to the difference between the standard and actual composition of a mixture.
• It can be represented by the following formula:• Material mix variance =
• (Standard cost of actual quantity of the standard mixture – Standard cost of actual quantity of the actual mixture) or (SQ – AQ) x SP
Illustration 1• A manufacturing concern which has adopted standard costing furnishes
the following information;
• Standard:• Materials to be used 100 kg for 70 Kg of finished product;• Price of materials is Rs. 1 per Kg
• Actual;• Output is 2,10,000 Kgs• Materials used 2,80,000 Kgs• Cost of materials Rs. 2,52,000
• Calculate;• Material cost variance• Material price variance• Material usages variance
1- Material cost variance(SQ x SP) – (AQ x AP)(3,00,000 x 1) - (2,80,000 x 0.90) = 3,00,000 – 2,52,000= 48,000 (f)
2- Material Price Variance (SP – AP) x AQ(1- 0.90) x 2,80,000= 28,000 (f)
3- Material Usage Variance(SQ – AQ) x SP(3,00,000 – 2,80,000) x 1= 20,000 (f)
Working Note= 1- SQ = as SQ of material is 100 kg for every 70 kg and actual output is 2,10,000 kg hence SQ =
210000 x 100/70 = 3,00,000 kg.2- Actual Rate = 2,52,000 / 2,80,000 = 0.90 per kg.
Illustration-2
• Following information has been furnished to you;
• Material SQ (kg) SP (Rs) AQ (kg) AP (Rs)
A 15 6 18 4 B 12 5 10 6C 9 4 8 3
36 36
Calculate;MCV, MPV, MUV, MMV
1- Material cost variance(SQ x SP) – (AQ x AP)A= (15 x 6) - (18 x 4) = (90) - (72) = 18 (f)B= (12x 5) - (10 x 6) = (60) - (60) = NilC= (9 x 4) - (8 x 3) = (36) - (24) = 12 (f)
Total material cost variance Rs. 30 (f)
2- Material Price variance(SP – AP) x AQA= (6- 4) x 18 = 36 (f)B= (5- 6) x 10 = 36 (a)C= (4- 3) x 8 = 8 (f)
Total material Price variance Rs. 34 (f)
3- Material Mix variance(SQ – AQ) x SPA= (15- 18) x 6 = 18 (a)B= (12- 10) x 5 = 10 (f)C= (9- 8) x 4 = 4 (f)
Total material mix variance Rs. 4 (a)
4- Material Usage varianceThere is no need to calculate MUV because total standard mix and actual mix are same.
Illustration 3
• Following information has been furnished to you;
• Material SQ (kg) SP (Rs) AQ (kg) AP (Rs)
X 60 50 65 45 Y 40 40 55 50
100 120
Calculate;MCV, MPV, TMUV,
1- Material cost variance(SQ x SP) – (AQ x AP)X= (40 x 50) - (65 x 45) = (2000) - (2925) = 925 (a)Y= (60x 40) - (55 x 50) = (2400) - (2750) = 350 (a)
Total material cost variance Rs. 1275 (a)
2- Total Material Usage variance(SQ – AQ) x SPX= (40- 65) x50 = 1250 (a)Y= (60- 55) x 40 = 200 (f)
Total material mix variance Rs. 1050 (a)
(i)- Material Usage variance(SQ – RSQ) x SPX= (40 – 48) x 50 = 400 (a)Y= (60 – 72) x 40 = 480 (a)
= 880 (a)
(Ii)- Material Mix variance(RSQ – AQ) x SPX= (48 – 65) x 50 = 850 (a)Y= (72 – 55) x 40 = 680 (f)
= 170 (a)Working Note;
RSQ= as standard mix of X and Y is in 40: 60 ratio or 2:3 ratio hence actual quantity 120 Kg is to be divided in to 2:3 ratio. That is 48 of X and 72 of Y.
Labour Variance…………