+ All Categories
Home > Documents > (Standard Costing) 1

(Standard Costing) 1

Date post: 08-Mar-2015
Category:
Upload: bhavesh919
View: 87 times
Download: 3 times
Share this document with a friend
22
Standard Costing
Transcript
Page 1: (Standard Costing) 1

Standard Costing

Page 2: (Standard Costing) 1

• Standard Costing system is a tool which is used to control over the cost of production,

• SC attempts to keep the cost at minimum level by planning and controlling,

• Under this system the cost of production of each unit is predetermined on some scientific basis,

• And then management try to control the actual costs not to exceed to predetermined standard,

• If actual cost exceed to standard then variance are calculated and then reason are find out to control the costs in future

Page 3: (Standard Costing) 1

Advantages of SC• Helpful in controlling,

• Helpful in measurement of operating efficiency,

• Helpful in policy making,

• Encourages for maximum utilization of resources,

• Help to reduce wastage,

• Helpful in coordination among various cost centers,

Page 4: (Standard Costing) 1

Limitations of SC• Fixation of standard is not possible for every type of

operation,

• Wrong standards may result in wastage of time, money,

• Need of services of experts for accurate determination of standards which increases total cost and thus cost of production,

• Fixation of standards are not fixed in nature but subject to review time to time as per the need of time, this makes it time consuming,

• Despite of above limitations, standard costing system is a unique system in itself and must be used for efficient control purpose.

Page 5: (Standard Costing) 1

System of Standard Costing

• Following steps are taken out for the development of a sound system of standard costing ……….

1- Establishment of a cost centre, 2- Determination of standards, 3- Setting of standards,4- Setting of time period,5- Collection of actual cost data,6- Analysis of variance

Page 6: (Standard Costing) 1

1- Establishment of a cost centre

• Under this first that cost centre is to be identified for which the standards are to be determined for cost control purpose,

• Because there are many cost centers like production centre, service departments, administrative departments, selling and distribution departments,

Page 7: (Standard Costing) 1

2- Determination of standards,

• There are various types of standards,• First it is to be determined that which type of the standard is to be used for control

purpose,• These standards are…….

1- Ideal standards: cost under such standard is determined under ideal conditions which are rarely fulfilled. For example mileage of a bike. Such standards fails to consider normal material wastage and idle labour time, power failure.

2- Attainable standards: are based on past performance and standards are set on the basis of past performance for future. Such standards may be lower than what can be achieved with reasonable efforts. Such standard consider the usual production problems such as normal material wastage and idle labour time, power failure.

3- Basic Standards: are used for basically those costs which are fixed in nature and not influenced by changes in material cost , labour cost. Thus they are used for a long period of time.

4- Normal Standards: set the costs under normal working conditions and consider the expected changes over a long period of time.

Page 8: (Standard Costing) 1

3- Setting of standards,

• After determining the type of standard to be used for comparison purpose,

• The next step is to setting of standards for various types of costs,

• These standards may be set for Material, Labour of Overheads or for all.

Page 9: (Standard Costing) 1

4- Setting of Time Period

A particular period is to be determined for which actual costs is to be compared with standard.

5- Collection of actual cost data,

The actual cost on target cost centre incurred for a particular time period is collected through cost accounting records,

Page 10: (Standard Costing) 1

6- Analysis of variance

• A variance representing the difference between standard cost and actual cost incurred is to be calculated,

• Variance ensures whether costs are being kept under control or not,

• On the basis of variance the probable causes for deviation are identified,

• And the responsibilities are assigned for deviations.

Page 11: (Standard Costing) 1

Variance Analysis

Types of Variance

Material Usage Variance

Material Yield Variance

Material Mix Variance

Material Price Variance

Material Variance

Labour Variance

Overheads Variance

Other Variance

Labour Idle time Variance

Labour Mix Variance

Labour Efficiency Variance

Labour Rate Variance

Labour Cost Variance

Variable over.Efficiency vari.

Fixed over.variance

Fixed over.Volume variance

CalendarVariance

Variable overheadsVariance

Sales valueVariance

Sales price Variance

Sales volumevariance

ProfitVariance

Page 12: (Standard Costing) 1

Material Cost Variance

• Material cost variance arises due to variance in the price of material or its usage.

• This can be calculated by using the following formula,• Material Cost Variance = (SQ x SP) – (AQ x AP) ,

• Where,SQ = Standard quantity for the actual outputSP = Standard price per unit of materialAQ = Actual quantityAP = Actual price per unit of material

• A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).

Page 13: (Standard Costing) 1

Material Price Variance

• Material cost variance may arise due to number of reasons like fluctuations in market prices, error in buying due to wrong purchasing policy etc,

• This can be calculated by using the following formula,• Material Price Variance = (SP – AP) x AQ

• Where,SP = Standard price per unit of materialAQ = Actual quantityAP = Actual price per unit of material

• A positive result implies favorable variance and a negative result implies unfavorable variance (adverse variance).

Page 14: (Standard Costing) 1

Material usage Variance• Material Usage variance is the difference between the actual

quantities of raw materials used in production and the standard quantities that should have been used to produce the product,

• MUV may arise due to number of reasons like Pilferage of materials , Wastage , Sub-standard or defective materials etc,

• This can be calculated by using the following formula,• Material Usage Variance = (SQ – AQ) x SP

Page 15: (Standard Costing) 1

Material Mix Variance

• MMV is calculated when a product uses mixture of different raw materials,

• MMV is that portion of the materials quantity variance, which is due to the difference between the standard and actual composition of a mixture.

• It can be represented by the following formula:• Material mix variance =

• (Standard cost of actual quantity of the standard mixture – Standard cost of actual quantity of the actual mixture) or (SQ – AQ) x SP

Page 16: (Standard Costing) 1

Illustration 1• A manufacturing concern which has adopted standard costing furnishes

the following information;

• Standard:• Materials to be used 100 kg for 70 Kg of finished product;• Price of materials is Rs. 1 per Kg

• Actual;• Output is 2,10,000 Kgs• Materials used 2,80,000 Kgs• Cost of materials Rs. 2,52,000

• Calculate;• Material cost variance• Material price variance• Material usages variance

Page 17: (Standard Costing) 1

1- Material cost variance(SQ x SP) – (AQ x AP)(3,00,000 x 1) - (2,80,000 x 0.90) = 3,00,000 – 2,52,000= 48,000 (f)

2- Material Price Variance (SP – AP) x AQ(1- 0.90) x 2,80,000= 28,000 (f)

3- Material Usage Variance(SQ – AQ) x SP(3,00,000 – 2,80,000) x 1= 20,000 (f)

Working Note= 1- SQ = as SQ of material is 100 kg for every 70 kg and actual output is 2,10,000 kg hence SQ =

210000 x 100/70 = 3,00,000 kg.2- Actual Rate = 2,52,000 / 2,80,000 = 0.90 per kg.

Page 18: (Standard Costing) 1

Illustration-2

• Following information has been furnished to you;

• Material SQ (kg) SP (Rs) AQ (kg) AP (Rs)

A 15 6 18 4 B 12 5 10 6C 9 4 8 3

36 36

Calculate;MCV, MPV, MUV, MMV

Page 19: (Standard Costing) 1

1- Material cost variance(SQ x SP) – (AQ x AP)A= (15 x 6) - (18 x 4) = (90) - (72) = 18 (f)B= (12x 5) - (10 x 6) = (60) - (60) = NilC= (9 x 4) - (8 x 3) = (36) - (24) = 12 (f)

Total material cost variance Rs. 30 (f)

2- Material Price variance(SP – AP) x AQA= (6- 4) x 18 = 36 (f)B= (5- 6) x 10 = 36 (a)C= (4- 3) x 8 = 8 (f)

Total material Price variance Rs. 34 (f)

3- Material Mix variance(SQ – AQ) x SPA= (15- 18) x 6 = 18 (a)B= (12- 10) x 5 = 10 (f)C= (9- 8) x 4 = 4 (f)

Total material mix variance Rs. 4 (a)

4- Material Usage varianceThere is no need to calculate MUV because total standard mix and actual mix are same.

Page 20: (Standard Costing) 1

Illustration 3

• Following information has been furnished to you;

• Material SQ (kg) SP (Rs) AQ (kg) AP (Rs)

X 60 50 65 45 Y 40 40 55 50

100 120

Calculate;MCV, MPV, TMUV,

Page 21: (Standard Costing) 1

1- Material cost variance(SQ x SP) – (AQ x AP)X= (40 x 50) - (65 x 45) = (2000) - (2925) = 925 (a)Y= (60x 40) - (55 x 50) = (2400) - (2750) = 350 (a)

Total material cost variance Rs. 1275 (a)

2- Total Material Usage variance(SQ – AQ) x SPX= (40- 65) x50 = 1250 (a)Y= (60- 55) x 40 = 200 (f)

Total material mix variance Rs. 1050 (a)

(i)- Material Usage variance(SQ – RSQ) x SPX= (40 – 48) x 50 = 400 (a)Y= (60 – 72) x 40 = 480 (a)

= 880 (a)

(Ii)- Material Mix variance(RSQ – AQ) x SPX= (48 – 65) x 50 = 850 (a)Y= (72 – 55) x 40 = 680 (f)

= 170 (a)Working Note;

RSQ= as standard mix of X and Y is in 40: 60 ratio or 2:3 ratio hence actual quantity 120 Kg is to be divided in to 2:3 ratio. That is 48 of X and 72 of Y.

Page 22: (Standard Costing) 1

Labour Variance…………


Recommended