Date post: | 31-Mar-2015 |
Category: |
Documents |
Upload: | lillian-pasker |
View: | 226 times |
Download: | 0 times |
Standard Local Operating Standard Local Operating Procedures for Endangered Species: Procedures for Endangered Species: SLOPES-IVSLOPES-IV
Greg Apke, ODOT Aquatics Biology and Fish Passage Program Leader (Salem
Headquarters)
Topics I Will Discuss Include:Topics I Will Discuss Include:
• General ESA Overview• Exposure to a few Streamlining
Tools for ESA1. SLOPES IV: Restoration Module2. SLOPES IV: Transportation Module
• ODOT Training ESA Training Opportunities
• Questions & Answers
Endangered Species Act (ESA)Endangered Species Act (ESA)
General Overview or “Crash Course” in ESA
Mandate of the FederalMandate of the FederalEndangered Species Act Endangered Species Act (ESA)(ESA)
• The federal ESA of 1973 requires federal agencies or their representatives
“to insure that their actions are not likely to jeopardize the continued existence of endangered or threatened species or
result in the destruction or adverse modification of critical habitat of such species.”
Federal Nexus Federal Nexus →→ Triggers ESA Triggers ESA Sec 7 Sec 7
• Federal Funds ($ FHWA)
• Federal Property (USDA, BLM, etc.)
• Federal Permit (Corps)
Section 7 requires consultation with either
• National Marine Fisheries Service (NMFS) or
• US Fish and Wildlife Service (USFWS)
(ODOT is FHWA’s non-federal representative)
Consultation is Required Before a Project is Consultation is Required Before a Project is AuthorizedAuthorized
‘Take’ is Prohibited by the ESA Take’ is Prohibited by the ESA and Requires a Permit if it is and Requires a Permit if it is Expected to OccurExpected to Occur
• Take = “harm, harass, pursue, hunt, shoot, wound, kill, trap, capture, or collect”
• Harm = “significant habitat modification or degradation that results in death or injury”
• Harass = “significantly disrupts normal behavior patterns” including “breeding, feeding or sheltering”
• The The ESA permit is ESA permit is analogous to a fishing analogous to a fishing license, you must have it license, you must have it to be legal. to be legal.
•Any form of ‘Any form of ‘taketake’ is ’ is illegalillegal without a license without a license or permit.or permit.
Number of Corps Permits Issued Number of Corps Permits Issued Within the Action Area by Geographic Within the Action Area by Geographic
Domains with Endangered SpeciesDomains with Endangered Species
GEOGRAPHICDOMAIN
ESUs AFFECTED 2001(n = 143)
2002(n = 170)
2003(n=254)
Willamette/LowerColumbia
LCR Chinook, UWR Chinook, CRchum, LCR steelhead, UWRsteelhead
92 96 124
Interior Columbia SR fall-run Chinook, SR spring/summer-run Chinook, UCR spring-run Chinook, SR sockeye, UCRsteelhead, SR Basin steelhead,MCR steelhead
21 19 26
Oregon Coast OC coho 13 44 63
Southern Oregon/Northern California Coasts
SONC coho 17 11 41
SLOPES IV Programmatic SLOPES IV Programmatic Biological Opinion (PBO)Biological Opinion (PBO)
Permitting of Maintenance and Improvements of Roads, Culverts, Bridges, and Utility Lines, within the Corps.’ Authority (Section 10, Rivers & Harbors Act 1899 and Section 404 of Clean Water Act)
= NMFS Corps. =
SLOPES =SLOPES =
Standard
Local
Operating
Procedures for
Endangered
Species
Concept of Programmatic PermitsConcept of Programmatic Permits
• Streamline permitting and ESA consultation process for projects that are:Relatively Minor in impactsRepetitive in usageImpacts are Predictable
• Up front permit• Statewide authorization for 5-years• Only for species regulated by NMFS
(anadromous salmonid species)
Permit IncentivesPermit Incentives
• Design constraints are known up front during project development
• Nominal risk – Permit terms & conditions are known
• Notification process is quick• Cost and time savings• Monitoring & reporting expectations are
know upfront (budget & schedule)• ESA “take” is permitted & legal• Statewide applications & coverage• 1-stop shop
Questions at This Point?Questions at This Point?
Restoration
Boulder Placement Piling Removal
Fish Passage Restoration
Set-Back (Dikes, Berms, Levees)
Spawning Gravel Restoration
Streambank Restoration
Large Wood Restoration
Water Control Structure Removal
Habitat Restoration
SLOPES IV - RESTORATION SLOPES IV - RESTORATION MODULEMODULE
Permit Issued February 22, 2008Permit Issued February 22, 2008
SLOPES IV –TRANSPORTATION SLOPES IV –TRANSPORTATION MODULEMODULE
Transportation Module
Major Hazard
Response
Streambank& Channel
Stabilization
MaintenanceRehabilitationReplacement
UtilityLine
StreamCrossing
To be complete
June ‘08
Design Criteria of ActionsDesign Criteria of Actions
1. Major Hazards
2. Streambank & Channel Stabilization
3. Maintenance, Rehabilitation and Replacement
4. Utility Line Stream Crossing
Types of Actions AuthorizedTypes of Actions Authorized
1. Major Hazard Responses– Immediate repairs of roads, culverts,
bridges, or utility lines when major hazards are declared by manger of transportation infrastructure
– Must notify Corps. & NMFS as soon as possible
2. Streambank & Channel Stabilization2. Streambank & Channel Stabilization
• These actions include installation & maintenance of:– Scour protection necessary to prevent scour
or down cutting of culverts, road foundations, or bridge supports using: Log or roughened rock toe of slopes Partially spanning porous weirs Woody plantings & herbaceous cover Soil reinforcements, coir logs Bank reshaping and slope grading Floodplain roughness Engineered log jams
3. Maintenance, Rehabilitation & 3. Maintenance, Rehabilitation & Replacement Replacement
• These actions include maint., rehab. & replacement necessary to ensure roads, culverts, and bridges remain safe & reliable:– Geotechnical surveys-drilling– Excavation, grading & filling necessary to
maintain, rehab. or replace existing roads, culverts & bridges
– Construct & maintain stormwater facilities
4. Utility Line Stream Crossings4. Utility Line Stream Crossings
• Design in the following priority:– Aerial lines– Directional drilling, boring, jacking– Trenching “in the dry”
Trenching must be backfilled below OHW w/ native materials & capped with clean river gravel
Large wood displaced must be returned to original location
Processing of New ActionsProcessing of New Actions
• Species presence: Corps. will confirm is actions are within range of ESA salmon
• Corps. & NMFS will review each application [email protected]
• Electronic notification and project tracking system
• 30-day approval process by NMFS & Corps.
• Site access• Project completion report w/in
60 days “post-construction”• Work completed during in-water
work window(s)• In-water work must be isolated• Stormwater management plan
– Must meet stormwater pollution reduction & flow control requirements
– Any new impervious surface or create a new stormwater discharge
Components/Conditions of Components/Conditions of PermitPermit
Conditions of Permit cont…Conditions of Permit cont…
• Fish passage must be provided • Capture & release of fish (fishery
biologist)• Water diversions (pumps) must be
screened• Erosion & pollution control plans must
be developed and implemented
• Vehicle staging and use: – Equipment storage, fueling, staging – 150 ft
from stream– Daily inspections for fluid leaks– Steam cleaning prior to work below OHW
• Site restoration activities– Native material(s) stockpile for re-use (large
wood, vegetation, topsoil, channel material, etc.)
• No treated wood use below OHW– Except when coated with waterproof seal or
barrier
Conditions of Permit cont…Conditions of Permit cont…
Site Restoration Action Plan Site Restoration Action Plan ComponentsComponents• Any action that results in significant
disturbance to riparian vegetation, soils, streambanks, or stream channel must:– Develop a plan to clean up site and restore
those features “post-construction” – Soil stability – Native vegetation (replanting plan)
noxious species are prohibited– Streambanks are stable & well vegetated– Electronic submittal of plan
Compensatory Mitigation Action Plan Compensatory Mitigation Action Plan ComponentsComponents
• Actions that require a compensatory mitigation plan include:– Stormwater management facility that requires
new or enlarged structure w/in riparian zone or has insufficient capacity to infiltrate and retain stormwater volumes
– Riprap revetments extending above streambank toe, beyond previous footprint, or does not include vegetation & large wood
– Bridge rehab. or replacements that do not span functional floodplain or cause net increase in fill w/in functional floodplain
Exclusions of SLOPES IVExclusions of SLOPES IV
• Baffled culverts or fishways (roughened channels)• Culverts exceeding 6% grade• Tidegate maintenance or replacements• Stream barbs, non-porous partially or full spanning weirs• Instream flow control structures• Significant channel realignment• Construction of new roads w/in riparian zones• Construction of new bridge where a previous structure
did not previously exist• Construction of new or larger gas, water, or sewer line to
support new or expanded service area(s)• Noxious vegetative species
Who Do You Contact With Who Do You Contact With Questions?Questions?
• ODOT Headquarters Staff• ODOT Region Technical Center Staff
(Biologists or Region Environmental Coordinators)
• Environmental Consultants• NMFS or Corps.
Or you can attend ODOT’s Training June 3 & 4, ‘08
ODOT’s BA Qualification ODOT’s BA Qualification TrainingTraining• June 3 & 4, 2008 in Salem• 2-Day Training & Test• Must Be Qualified to Write or Review BA’s for
ODOT Under Contract• Must Maintain Qualification and Renew Every
3-Years
To Register: Lorrie Schaefer at 503-986-3840By E-mail: [email protected]