STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS Srl No Material /components/ As per SOTR/QA Activity Qty. as per P.O. Characteristic/ Type Check Quantum of Check Reference Documents Acceptance Criteria Format of Record Action by QAE Remarks 1 1.00 DRAWINGS/DOCUMENTS/TYPE TESTS 1.01 Drawings & Documents GA drawings and detailed bill of material(DBOM) 100% PO & SOTR/ TNC Minutes PO & SOTR/ TNC Minutes List of approved binding drawings CHP For R Binding Drawing & Binding Data, duly approved by Design authority, Professional & Inspection Authority (or by Command for MO orders) to be verified. 1.02 Type test / ETT / EMI/EMC reports Availability & verification 100% PO & SOTR / TNC Minutes/ JSS 55555 PO & SOTR / TNC Minutes JSS 55555 Type Test / ETT/EMI / EMC reports CHP For R If not type tested, Equipment to be Type Tested as per Sl. 4.0.0 2.00 SECTION I - RAW MATERIAL INSPECTION 2.01 (a) Pump Casing, (Casting) (i) Pouring with integral test bar 100% SOTR, Approved Drawings and relevant Standards SOTR, Approved Drawings and relevant Standards IR R If casting is without integral test bar, pouring to be witnessed by QAO (ii) Material Identification & Stamping 100% IR W (iii) Heat Treatment 100% HT reports R (iv) Physical Mechanical & Chemical properties 01 sample/ heat / lot LTC R Test to be done at NABL Lab (v) RT (Applicable as per Drg./ spec.) Critical Regions NDE Report CHP For R Shooting sketches to be provided. Testing to be done by ISNT/ ASNT level II or III qualified technician.
Transcript
Page 1: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

1

1.00 DRAWINGS/DOCUMENTS/TYPE TESTS1.01 Drawings & Documents GA drawings and detailed

bill of material(DBOM)100% PO & SOTR/

TNC MinutesPO & SOTR/TNC Minutes

List ofapprovedbindingdrawings

CHPForR

Binding Drawing &Binding Data, dulyapproved byDesign authority,Professional &Inspection Authority (orby Command for MOorders) to be verified.

1.02 Type test / ETT /EMI/EMC reports

Availability & verification 100% PO & SOTR /TNCMinutes/JSS 55555

PO & SOTR /TNC MinutesJSS 55555

TypeTest /ETT/EMI/ EMCreports

CHPForR

If not type tested,Equipment to beType Tested as perSl. 4.0.0

2.00 SECTION I - RAW MATERIAL INSPECTION2.01(a)

Pump Casing,(Casting)

(i) Pouring with integraltest bar

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR RIf casting is without

integral test bar,pouring to bewitnessed by QAO

(ii) Material Identification &Stamping

100% IR W

(iii) Heat Treatment 100% HT reports R(iv) PhysicalMechanical &Chemical properties

01sample/heat / lot

LTC R Test to be done atNABL Lab

(v) RT (Applicable as perDrg./ spec.)

CriticalRegions

NDE Report CHPForR

Shooting sketches tobe provided. Testing tobe done by ISNT/ASNT level II or IIIqualified technician.

Page 2: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

2

2.01(b)

Pump casing(Extrusion)

(i) Material Identification &Stamping 100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W(ii) Physical,Mechanical &Chemical properties

01sample/heat / lot

LTC RTest to be done atNABL Lab

2.02 Shaft(Forging)

(i) Material Identification &Stamping 100% IR W(ii) Heat Treatment HT reports R(iii) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC RTest to be done atNABL Lab

(iv) Micro & Macroexamination LTC R

2.03 Impeller,(Casting)

(i) Pouring with integraltest bar

100% IR R If casting is withoutintegral test bar,pouring to bewitnessed by QAO

(ii) Material Identification &Stamping

100%IR W

(iii) Heat Treatment 100% HT Report R

(iv) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC RTest to be done atNABL Lab

(v) RT (Applicable as perDrg./ spcn)

CriticalRegions

NDE Report CHPForR

Shooting sketches tobe provided. Testing tobe done by ISNT/ASNT level II or IIIqualified technician.

Page 3: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

3

2.04 Coupling(Machined)

(i) Material Identification &Stamping

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

(ii) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC R Test to be done atNABL Lab

2.05 Stuffing Box/CasingCover(Casting)

(i) Pouring with integraltest bar for casting

100% IR R If casting is withoutintegral test bar,pouring to bewitnessed by QAO

(ii) Material Identification &Stamping

100% IR W

(iii) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC R Test to be done atNABL Lab

(iv) RT (Applicable as perDrg./ spec.)

CriticalRegions

NDE Report CHPForR

Shooting sketches tobe provided. Testing tobe done by ISNT/ASNT level II or IIIqualified technician.

2.06 Lower & UpperBearing housing/ BearingCover (Casting)

(i) Pouring with integraltest bar

100% IR R If casting is withoutintegral test bar,pouring to bewitnessed by QAO

(ii) Material Identification &Stamping

100% IR W

(iii) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC R Test to be done atNABL Lab

Page 4: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

4

(iv) RT (Applicable as perDrg./ spec.)

CriticalRegions

SOTR,ApprovedDrawingsand RelevantStandards

SOTR,ApprovedDrawingsand RelevantStandards

NDE Report CHPForR

Shooting sketches tobe provided. Testing tobe done by ISNT/ASNT level II or IIIqualified technician

2.07 Wearing RingWearing Plate(Casting)

(i) Pouring with integraltest bar

100% IR R If casting is withoutintegral test bar,pouring to bewitnessed by QAO

(ii) Material Identification &Stamping

100% IR W

(iii) Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC R Test to be done atNABL Lab

(iv) RT (Applicable as perDrg./ spec.)

CriticalRegions

NDE Report CHPForR

Shooting sketches tobe provided. Testing tobe done by ISNT/ASNT level II or IIIqualified technician.

2.08 Gland Plate, Cover Plate,Seal Housing Material Identification &

Stamping100% IR W

Test to be done atNABL Lab

2.09 Impeller Nut

2.10 Impeller Key ,CouplingKey

Physical,Mechanical,Chemical properties

01sample/heat / lot

LTC R2.11 Companion Flange-

Suction2.12 Companion Flange-

Delivery

Page 5: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

5

BOUGHT OUT ITEMS2.13 SV Mounts (i) Prod. Identification 100%

SOTR,ApprovedDrawingsand SQAP

SOTR,ApprovedDrawingsand SQAP

IR W

(ii) SQAP Compliance 100% IR as perSQAP

R

(iii) Dispatch clearance -- I-note/ Form4/ DispatchCertificate(asapplicable)

R

2.14 Motor (i) Prod. Identification 100% IR W

(ii) SQAP Compliance 100% IR as perSQAP

R

(iii) Dispatch clearance -- I-note/ Form4/ DispatchCertificate(asapplicable)

R

2.15 Starter Panel (i) Prod. Identification 100% IR W

(ii) SQAP Compliance 100% IR as perSQAP

R

(iii) Dispatch clearance -- I-note/ Form4/ DispatchCertificate(asapplicable)

R

Page 6: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

6

2.16 Diffuser, Strainer Product identification 100% SOTR/Approveddrawings/Supplier'scatalogue

SOTR/Approveddrawings/Supplier'scatalogue

STC/LTC W

2.17 Flexible Hose Visual and DimensionalExamination

IR R

COTS ITEMS

2.17 Gasket

(i) Product identification

(ii) Visual andDimensional Examination

100%

Approveddrawing/SOTR/Supplier'scatalogue/OEM Spec

Approveddrawing/SOTR/Supplier'scatalogue/OEM Spec

(i) STC/CC

(ii) IR

W

R

2.18 Mechanical Seal2.19 Bearings2.20 O Rings2.21 Compound Gauge,

Pressure gauge2.22 Gauge Piping2.23 Valves

2.24 Bellows

2.25 Hardware Items-Studs, Nut, bolts,Screws, washers,Circlips, lantern, Rivet,Keys Sand Guard, CapChain, Plug Assy, NamePlate, Sleeve, flange,Neck Ring, Sealing Ring

Page 7: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

7

3.00 SECTION II - IN PROCESS INSPECTION3.01 Pump Casing,

(Casting or(Extrusion)

(i) Visual and DimensionalExamination

100%

SOTR,ApprovedDrawing

ApprovedDrawing

IR R

(ii) Surface Defects,MPT /DPT

100% Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician.

(iii) Hydraulic PressureTest (1.5 times of workingpressure)

100% No leakage IR CHPforW

3.02 Shaft(Forging)

(i) Visual and DimensionalExamination

100% ApprovedDrawing

IR R

(ii) Surface Defects,UT/MPT/DPT

100% Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician.

(iii) Static & Dynamicbalancing

100% IR CHPforW

3.03 Impeller,(Casting)

(i) Visual and DimensionalExamination

100% ApprovedDrawing

IR R

(ii) Surface DefectsMPT /DPT

100% Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician.

(iii) Static & Dynamicbalancing

100% IR CHPfor W

Page 8: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

8

3.04 Impeller Nut

Visual and DimensionalExamination

100%

SOTR,ApprovedDrawing

SOTR,ApprovedDrawing

IR R3.05 Impeller Key, CouplingKey

3.06 Companion Flange –suction

3.07 Companion Flange –Delivery

3.08 Stuffing Box/CasingCover

(i) Visual andDimensional Examination

100% ApprovedDrawing

IR R

(ii) Surface DefectsMPT /DPT

100% Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician.

(iii) Hydraulic PressureTest

100% No leakage IR R

3.09 Bearing housing/Cover-Lower & Upper

Visual and DimensionalExamination

100% ApprovedDrawing

IR R .

Surface DefectsMPT /DPT

Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician

3.10 Gland Plate, Cover Plate,Seal Housing

Visual and DimensionalExamination

100% ApprovedDrawing

IR R

3.11 Wearing Plate/WearingRing

(i) Visual andDimensional Examination

100% ApprovedDrawing

IR R

(ii) Surface DefectsMPT /DPT

100% Approveddrawing andrelevantstandard

NDEReport

CHPforW

Testing to be done byISNT/ ASNT level II orIII qualified technician.

Page 9: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

9

4.00 SECTION III : PRE-REQUISITE- FINAL INSPECTION

TYPE TESTING OF PUMP ( To be carried out on one unit /prototype)

4.01 Pump & Motor Assy Free rotation of Pump &Motor

One Unit

Rotate freely Free Rotation IR W

4.02 Overall DimensionalInspection

ApprovedDrawings/Mfg Drawing

ApprovedDrawings/Mfg Drawing

IR R

4.03 Over Speed test(20% above specifiedspeed)

PO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spec402

PO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spec402

IRCHPforW

4.04 Start /Stop test IR W4.05 Cooling Test IR W4.06 Endurance Test

(100 Hrs)Performance test withintegral Motor and controlpanel

Flow(Q) v/s Head(H)

IR CHPforW

Readings to berecorded every 02 hrs.

Flow(Q) v/sEfficiency(Effn)Flow(Q) v/s Power(P)Motor TemperatureBearing TemperatureWinding Resistance (Cold& Hot)Insulation ResistanceVibration LevelAir Borne NoiseIndication/ Alarm/ShutDown test

Page 10: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

10

4.07 Strip Open Test Wearing Parts One UnitPO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spec402

PO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spcn402

IR W

4.08 Post-Trial testFor 1 hour

Flow(Q) v/s Head(H)One Unit IR W

Flow(Q) v/s Eff(n)

Flow(Q) v/s Power(P)

Noise Level

Vibration test

4.09 Environmental Shock &Vibrations

Shock & VibrationsAnalysis

One Unit SOTR/NSS-II/ BR 3021/MIL-Std-167

SOTR/NSS-II/ BR 3021/MIL-Std-167

NSTLReport

CHPforR

4.10 Structure Borne Noise Structure Borne Noiseemitted by Unit

One Unit SOTR /TNCMinutes /MIL-STD-740-2

SOTR /TNCMinutes /MIL-STD-740-2 LTC CHP

forR

Test to be carried outby NABL approved Lab/Agencies. In case ofnon -availability ofNABL accredited lab,third party / Agencyselected for conductingABN & SBN tests needsto be approved by NHQ

4.11 Tilt test for 8 Hrs Head(H) v/s Flow (Q) v/sPower(P)

One Unit SOTR /TNCMinutes/App. TestProcedure

SOTR /TNCMinutes/App. TestProcedure

IR CHPforW

Page 11: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

11

5.00 SECTION IV : FINAL INSPECTON

5.01 Pump & Motor Assy Free rotation of Pump &Motor

100% Rotate freely Free Rotation IR W

5.02 Performance test withIntegral motor andControl PanelDuration- 8 hours/set

Flow(Q) v/s Head(H)

100% byfirm20% byQAE PO, SOTR ,

TNCMinutes/ApprovedDrawing,DME Spec402

PO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spec402

IR CHPforW

Compliance certificateto be submitted by thefirm to the InspectingOfficer for 100%quantity

Flow(Q) v/sEfficiency(Effn)Flow(Q) v/s Power(P)Motor temperatureBearing TemperatureInsulation resistanceWinding Resistance

5.03 Strip Open test Wearing Parts 100%

IR W5.04 Post-Trial testFor 1 hour

Suction head, DischargeHead, Output, RPM

100%

Noise and Vibration test

5.05 Overall DimensionalInspection

100%ApprovedDrawings/Mfg Drawingand SOTR

ApprovedDrawingsSOTR

IR W

5.06 Weight Weight recording 100% Weightcertificate

W

5.07 Tally Plate Check 100% IR R

5.08 Lifting arrangement 100% IR R

Page 12: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

12

6.0 SECTION V : PRE REQUISITE ISSUE OF FORM -4

6.01 OBS Items as perPurchase Order (i) Product identification

100%

PO,SOTR,ApprovedDrawings/PIL / OEMSpecification

PO &ApprovedDrawings/PIL

IR R

(ii) VI/DI OEM TC,CC , IR R

6.02 Submission of As BuiltDrawings

Verification 100% ApprovedDrawings,Concessions& Deviations

Approveddrawings &Concurrencefrom drawingapprovalauthority

As builtdrawings

CHPforW

6.03 Submission of approveddocuments for stamping

sets Verification and stamping 100% PO,SOTR,ApprovedDrawings

PO,SOTR,ApprovedDrawings

Documentation

CHPforW

6.04 Liquidation ofobservation during FATs,if any

Defect rectification 100% ApprovedDrawing,SOTR & FATdocument

ApprovedDrawing,SOTR , FATdocument &necessaryapproval

IR CHPforW

6.05 Painting Visual Inspection & DFT 100% ApprovedDrawing,SOTR, PaintPlan

ApprovedDrawing/SOTR/ PO

IR W

Page 13: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/ TypeCheck

Quantumof Check

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

Actionby

QAE

Remarks

13

6.06 Preservation & Packing Visual Inspection 100% ApprovedDrawing,SOTR, OEMPreservationPlan

ApprovedDrawing,ApprovedPreservationPlan

IR W

6.07 Submission of Form -4(I&T Certificate) Correctness 100% SOTR,PO SOTR,PO Form-4 P

Important Notes:-

(a) Each type of Equipment & accessories to be supplied shall conform to specification acceptable to the TYPE APPROVAL authority.(b) Motor to be procured only from Naval approved vendors.(c) EMI/EMC and ETT tests to be done at NABL approved Lab.(d) Material Testing to be done at NABL approved Lab.(e) All NDT to be performed by ASNT/ISNT Level II or Level III qualified person.(f) Imported items to be accepted on the basis of review of Import documents viz. (a) Bill of entry (b) Bill of Lading (c) Country of Origin

(d) Shipping Bill/Air way Bill (e) OEM Test Reports (f) Compliance certificate (g) Guarantee certificate(g) In case the items are of 'Bought Out ' nature, the inspections of the store are to be carried out on the basis of STC/OEM TC/ CC/QAP

as applicable based on criticality.(h) The COTS/ 'Bought out' items in the QAP are indicative only. The firm is required to categorically define the 'Bought out'/COTS items

specific to their products in the drawings. Items will be categorized as bought out or COTs in the QAP on the basis of approveddrawings. Further, only finished products will be accepted as COTs and no raw material for manufacturing will be acceptable as a COTSitem.

(j) The SQAP does not apply to items not in the scope of supply of the firm.(k) The column 'Quantity as per P.O' has been left blank which has to be filled by the firm as per P.O while submitting Draft QAP for

approval.(l) WPS / WPQ certificates to be submitted by the firm for all welding related work.(m)Assy more than 40 Kgs weight should be provided with lifting arrangement.

Page 14: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

1

1.00 DRAWING/ DOCUMENTS/ TYPE TEST1.01 Drawings & Documents GA Drawing

and detailed billof material(DBOM)

100% PO & SOTR/TNC Minutes

PO & SOTR/TNC Minutes

List ofapprovedbindingdrawings

CHPForR

Binding Drawing &Binding Data, dulyapproved by Designauthority, Professional &Inspection Authority (orby Command for MOorders) to be verified.

1.02 Type test / ETT/EMI/EMC reports

Availability &verification

100% PO & SOTR/TNC Minutes/JSS 55555

PO & SOTR /TNC MinutesJSS 55555

Type test/ETT/EMI/EMCreports

CHPForR

If not type tested,Equipment to beType Tested as perSl. 4.0.0

2.00 SECTION I : RAW MATERIAL INSPECTION

2.01(a)

Pump Casing(Casting)

(i) Pouring withintegral test bar 100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR RIf casting is without

integral test bar, pouringto be witnessed byQAO

(ii) MaterialIdentification&Stamping

100% IR W

(iii) HeatTreatment

100% HTreports

R

(iv) PhysicalMechanical &Chemicalproperties

1sampleper heat /lot

LTC RTest to be done atNABL Lab

(v) RT(Applicable asper Drg/spcn)

CriticalRegions NDE

Report

CHPforR

Shooting sketches to beprovided. Testing to bedone by approvedASNT/ISNT level II or IIIqualified technician.

Page 15: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

2

2.01(b)

Pump casing(sheet plate fabrication)

MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1 Sample/lot/heat LTC R

Test to be done atNABL Lab

2.02 Insert/Liner(casting)

(i) Pouring withintegral test bar

100%IR R

If casting is withoutintegral test bar, pouringto be witnessed byQAO

(ii) MaterialIdentification &Stamping

100%IR W

(iii) HeatTreatment

100% HTReports

R

(iv) PhysicalMechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done atNABL Lab

(iv) RT(Applicable asper Drg/spcn)

CriticalRegions

NDEReport

CHPforR

Shooting sketches to beprovided. Testing to bedone by approvedASNT/ISNT level II or IIIqualified technician

Page 16: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

3

2.03 Stator(for single screw pump)

MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1sample/heat / lot

LTC R Test to be done atNABL Lab

2.04 Rotor(for single screw pump)

MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleheat / lot

LTC R Test to be done atNABL Lab

2.05 Drive Shaft(for single screw pump)

MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done atNABL Lab

2.06 Screw Shaft(Power Screw)

MaterialIdentification &Stamping

100% IR W

PhysicalMechanicalChemical &properties

1sample/heat / lot

LTC R Test to be done atNABL Lab

Page 17: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

4

2.07 Screw Shaft(Idler Screw)

MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1sample/heat / lot

LTC R Test to be done atNABL Lab

2.08 PS balancing Bush(Casting)

MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sample/heat /r lot

LTC R Test to be done atNABL Lab

2.09 IS Balancing Bush(Casting)

MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done atNABL Lab

2.10 Seal Housing MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sample/heat / lot

LTC R Test to be done atNABL Lab

Page 18: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

5

2.11 Coupling Pump Half MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1sample /rheat / lot

LTC R Test to be done atNABL Lab

2.12 Coupling Motor Half MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleheat / lot

LTC R Test to be done atNABL Lab

2.13 Suction flange MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sample/heat / lot

LTC R Test to be done atNABL Lab

2.14 Discharge Flange MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done atNABL Lab

Page 19: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

6

2.15 Bearing Housing MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1sample/heat / lot

LTC R Test to be done atNABL Lab

2.16 Cover MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sample /heat /lot

LTC R Test to be done atNABL Lab

2.17 Gear Box MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sample/heat /lot

LTC R Test to be done atNABL Lab

2.18 Relief Valve Assembly MaterialIdentification &Stamping

100% IR W

PhysicalMechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done atNABL Lab

Page 20: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

7

2.19 Motor stool MaterialIdentification &Stamping

100%

SOTR,ApprovedDrawings andrelevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

PhysicalMechanical &Chemicalproperties

1sample /heat / lot

LTC R Test to be done atNABL Lab

BOUGHT OUT ITEMS

2.20 SV Mounts Productidentification

100%

SOTR,ApprovedDrawings andSQAP

SOTR,ApprovedDrawingsand SQAP

IR W

SQAPCompliance

IR as perSQAP

R

Dispatchclearance

I-note/Form4Dispatchcertificate( asapplicable)

2.21 Motor Productidentification

100% IR W

SQAPCompliance

IR as perSQAP

R

Dispatchclearance

I-note/Form4Dispatchcertificate( asapplicable)

Page 21: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

8

2.22 Starter Panel Productidentification

100% SOTR,ApprovedDrawings andSQAP

SOTR,ApprovedDrawingsand SQAP

IR W

SQAPCompliance

IR as perSQAP

R

Dispatchclearance

I-note/Form4Dispatchcertificate( asapplicable

2.23 Diffuser, strainerProductidentification

100% SOTR/Approveddrawings/Supplier'scatalogue

SOTR/Approveddrawings/Supplier'scatalogue

STC/LTC W

Visual &DimensionalCheck

IR R

2.24 Flexible HosesProductidentification

100% SOTR/Approveddrawings/Supplier'scatalogue

SOTR/Approveddrawings/Supplier'scatalogue

STC/LTC W

Visual &DimensionalCheck

IR R

Page 22: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

9

COTS ITEMS

2.25 Bearings

(i) Productidentification

(ii) Visual &DimensionalCheck

100%

Approveddrawing/SOTR/Catalogue/OEM spec

Approveddrawing/SOTR/Catalogue/OEM spec

(i) STC/CC

(ii) IR

W

R

2.26 Mechanical seal

2.27 Valves

2.28 Bellows

2.29 Compound gauges andPressure gauges

2.30 Gauge Piping

2.31 O Rings and Gasket

2.32 Hardware Items-fastener

2.33 Studs, Nut, bolts,Screws, washers,Circlips, Rivet, KeysSand Guard, Plug Assy,Name Plate, Sleeve,flange, Neck Ring,Sealing Ring

Page 23: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

10

3.00 SECTION II : IN PROCESS INSPECTION

3.01 Pump Casing Visual andDimensionalExamination

100%

SOTR/ApprovedDrawing

ApprovedDrawings

IR R

Surface Defect,MPT/DPT

100% ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

HydraulicPressure test(1.5 times ofworkingpressure)

100% No Leakage IR CHPforW

DPT of weldjoint

100% ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.02 Insert Visual &Dimensional

100% ApprovedDrawings

IR R

Surface Defect,MPT/DPT

100% ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.03 Motor stool Visual &Dimensional

100% ApprovedDrawings

IR R

Surface Defect,MPT/DPT

100% ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Page 24: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

11

3.04 Stator Visual &Dimensional

100%

SOTR/ApprovedDrawing

ApprovedDrawings

IR R

Surface Defect,MPT/DPT

100% ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.05 Rotor Visual &Dimensional

100% ApprovedDrawings

IR R

Surface Defect,MPT/DPT

100%ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Balancing 100% IR CHPForW

3.06 Drive Shaft Visual &Dimensional

100% ApprovedDrawings

IR R Dimensional check aftercase hardening

Case DepthHardness

100%ApprovedDrawings &RelevantStandard

IR CHPforR

Test to be done atNABL Lab

Surface Defect,MPT/DPT

100% NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Balancing 100% IR CHPForW

Page 25: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

12

3.07 Idler Screw Visual &Dimensional

100%

SOTR/ApprovedDrawings &RelevantStandard

ApprovedDrawings

IR R Dimensional check aftercase hardening

Case DepthHardness

100%ApprovedDrawings &RelevantStandard

IR CHPforR

Test to be done atNABL Lab

Surface Defect,MPT/DPT

100% NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Balancing 100% IR CHPforW

3.08 Power Screw Visual &Dimensional

100% ApprovedDrawings

IR R Dimensional check aftercase hardening

Case DepthHardness

100%ApprovedDrawings &RelevantStandard

IR CHPforR

Test to be done atNABL Lab

Surface Defect,MPT/DPT

100% NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Balancing 100% IR CHPforW

3.09 Balancing Bush Visual &Dimensional

100%SOTR/ApprovedDrawings &RelevantStandard

ApprovedDrawings IR R

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.10 Seal Housing

3.11 Coupling Pump Half Surface Defect,MPT/DPT

ApprovedDrawings &RelevantStandard

NDEReport

CHPforW3.12 Coupling Motor Half

3.13 Suction Flange

Page 26: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

13

3.14 Discharge Flange Visual &Dimensional

100% SOTR/ApprovedDrawings &RelevantStandard

ApprovedDrawings

IR R

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.15 Liner/Insert

3.16 Bearing Housing Surface Defect,MPT/DPT

ApprovedDrawings &RelevantStandard

NDEReport

CHPforW

3.17 Cover3.18 Gear Box

3.19 Relief Valve Assy Visual &Dimensional

100%

SOTR/ApprovedDrawings &Relevantstandard

ApprovedDrawings &Relevantstandard

IR

R

Relief valvebody Hydraulicpressure test/Leak test

100%

CHPforWSet pressure

test for reliefvalve assembly@ 1.1Xoperatingpressure

100%

3.20 Flexible Hoses HydraulicPressure Test

100% ApprovedDrawings/Supplier'scatalogue

2 X Operatingpressure

IR W

3.21 Sub Assy consisting ofPower Screw/RotorPump Half coupling,Pump Shaft Key,Shaft Sleeve,Coupling Bolt,Coupling washer

Balancing 100%SOTR/ApprovedDrawings &Relevantstandard

ApprovedDrawings &Relevantstandard

IR CHPforW

Page 27: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

14

4.00 SECTION III : PRE-REQUISITE- FINAL INSPECTIONTYPE TESTING OF PUMP ( To be carried out on one unit /prototype)

4.01 Pump & Motor Assy Free rotation ofPump & Motor

One Unit

Rotate freely Free RotationIR W

4.02 Overall DimensionalInspection

ApprovedDrawings/ MfgDrawing

ApprovedDrawings/Mfg Drawing

IR R

4.03 Over Speed test(20% above specifiedspeed)

PO, SOTR ,TNC Minutes/ApprovedDrawing, DMESpec 402

PO, SOTR ,TNC Minutes/ApprovedDrawing,DME Spcn402

IR CHPforW4.04 Start /Stop test

4.05 Cooling Test4.06 Endurance Test

(100 Hrs)Performance test withintegral Motor andcontrol panel

Flow(Q) v/sHead(H)

IR CHPforW

Readings to berecorded by every 02hrs.

Flow(Q) v/sEfficiency(Effn)Flow(Q) v/sPower(P)Motor TempBearing Temp

WindingResistance(Cold & Hot)InsulationResistanceVibration LevelAir Borne NoiseIndication/Alarm/ShutDown test

Page 28: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

15

4.07 Strip Open Test Wearing Parts

One Unit

PO, SOTR ,TNC Minutes/ApprovedDrawing, DMESpec 402

PO, SOTR ,TNC Minutes/ApprovedDrawing,DME Spec402

IR W

4.08 Post-Trial testFor 1 hour

Flow(Q) v/sHead(H) IR WFlow(Q) v/sEff(n)Flow(Q) v/sPower(P)Noise LevelVibration test

4.09 Environmental Shock &Vibrations

Shock &VibrationsAnalysis

One Unit SOTR/NSS-II/BR 3021 /MIL-Std-167

SOTR/NSS-II/BR 3021/MIL-Std-167

NSTLReport

CHPforR

4.10 Structure Borne Noise Structure BorneNoise emittedby Unit

One Unit SOTR /TNCMinutes /MIL-STD-740-2

SOTR /TNCMinutes /MIL-STD-740-2

LTC CHPforR

Test to be carried out byNABL approved Lab/Agencies. In case ofnon -availability ofNABL accredited lab,third party / Agencyselected for conductingABN & SBN tests needsto be approved by NHQ

4.11 Tilt test for 8 Hrs Head(H) v/sFlow (Q) v/sPower(P)

One Unit SOTR /TNCMinutes/App. TestProcedure

SOTR /TNCMinutes/App. TestProcedure

IR CHPforW

Page 29: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

16

5.00 SECTION IV : FINAL INSPECTON

5.01 Pump & Motor Assy Free rotation ofPump & Motor

100% Rotate freely Free Rotation IR W

5.02 Performance test withIntegral motor andControl PanelDuration- 8 hours/set

Flow(Q) v/sHead(H)

100% byfirm20% byQAE

PO, SOTR ,TNC Minutes/ApprovedDrawing, DMESpec 402

PO, SOTR ,TNC Minutes/ApprovedDrawing,DME Spec402

IR CHPforW

Compliance certificateto be submitted by thefirm to the InspectingOfficer for 100%

Flow(Q) v/sEfficiency(Effn)

Flow(Q) v/sPower(P)

MotortemperatureBearingTemperatureInsulationresistanceWindingResistance

5.03 Strip Open test Wearing Parts 100%

IR W5.04 Post-Trial testFor 1 hour

Suction head,DischargeHead, Output,RPM

100%

Noise andVibration test

Page 30: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

17

5.05 Overall DimensionalInspection

100% ApprovedDrawings/ MfgDrawing andSOTR

ApprovedDrawingsSOTR

IR W

5.06 Weight Weightrecording

100% Weightcertificate

W

5.07 Tally Plate Check 100% IR R

5.08 Lifting arrangement 100% IR R

6.0 SECTION V : PRE REQUISITE ISSUE OF FORM -4

6.01 OBS Items as perPurchase Order (i) Product

identification

100% PO,SOTR,ApprovedDrawings/ PIL /OEMSpecification

PO &ApprovedDrawings/PIL

IR R

(ii) VI/DI OEM TC,CC , IR R

6.02 Submission of as BuiltDrawings

Verification 100% ApprovedDrawings,Concessions &Deviations

Approveddrawings &Concurrencefrom drawingapprovalauthority

As builtdrawings

CHPforR

6.03 Submission of approveddocuments for stamping

sets Verification andstamping

100% PO,SOTR,ApprovedDrawings

PO,SOTR,ApprovedDrawings

Documentation

CHPforR

6.04 Liquidation ofobservation during FATs,if any

Defectrectification

100% ApprovedDrawing,SOTR & FATdocument

ApprovedDrawing,SOTR & FATdocument,necessaryapprovals

IR CHPforR

Page 31: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SCREW PUMP

SrlNo

Material /components/ Asper SOTR/QA Activity

QTYAs PerPO

Characteristic/Type Of Check

Quantum ofCheck

ReferenceDocuments

AcceptanceCriteria

Format ofRecord

ActionbyQAE

Remarks

18

6.05 Painting VisualInspection &DFT

100% ApprovedDrawing,SOTR, PaintPlan

ApprovedDrawing/SOTR/ PO

IR W

6.06 Preservation & Packing VisualInspection

100% ApprovedDrawing,SOTR, OEMPreservationPlan

ApprovedDrawing,ApprovedPreservationPlan

IR W

6.07 Submission of Form -4(I&T Certificate) Correctness 100% SOTR,PO SOTR,PO Form-4 P

Important Notes:-

(a) Each type of Equipment & accessories to be supplied shall conform to specification acceptable to the TYPE APPROVALauthority.

(b) Motor to be procured only from Naval approved vendors.(c) EMI/EMC and ETT tests to be done at NABL approved Lab.(d) Material Testing to be done at NABL approved Lab.(e) All NDT to be performed by ASNT/ISNT Level II or Level III qualified person.(f) Imported items to be accepted on the basis of review of Import documents viz. (a) Bill of entry (b) Bill of Lading (c) Country

of Origin (d) Shipping Bill/Air way Bill (e) OEM Test Reports (f) Compliance certificate (g) Guarantee certificate(g) In case the items are of 'Bought Out ' nature, the inspections of the store are to be carried out on the basis of STC/OEM TC/

CC/QAP as applicable based on criticality.(h) The COTS/ 'Bought out' items in the QAP are indicative only. The firm is required to categorically define the 'Bought

out'/COTS items specific to their products in the drawings. Items will be categorized as bought out or COTs in the QAP on thebasis of approved drawings. Further, only finished products will be accepted as COTs and no raw material for manufacturingwill be acceptable as a COTS item.

(j) The SQAP does not apply to items not in the scope of supply of the firm.(k) The column 'Quantity as per P.O' has been left blank which has to be filled by the firm as per P.O while submitting Draft QAP

for approval.(l) WPS / WPQ certificates to be submitted by the firm for all welding related work.(m)Assy more than 40 Kgs weight should be provided with lifting arrangement.

Page 32: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

1

1.00 DRAWINGS/DOCUMENTS/TYPE TESTS

1.01 Drawings & Documents GA drawings anddetailed bill ofmaterial(DBOM)

100% PO & SOTR/TNC Minutes

PO &SOTR/TNCMinutes

List ofapprovedbindingdrawings

CHPforR

Binding & BindingData, Duly approvedBy Design authority,Professional& Inspection.Authority(orby Commandfor MO orders)be verified

1.02 Type test / ETT /EMI/EMC reports

Availability &verification

100% PO & SOTR/TNC Minutes/JSS 55555

PO & SOTR/ TNCMinutes/JSS 55555

Type test/ETT/EMI/EMCreports

CHPforR

If not type tested earlier,Equipment to be typetested as per Sl 4.0.0

2.00 RAW MATERIAL INSPECTION2.01 Pump Casing,

(Upper & Lower)(i) Pouring withintegral test bar

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR R If casting is withoutintegral test bar, pouringto be witnessed by QAO

(ii) Materialidentification &Stamping

100% IR W

(iii) HeatTreatment

100% HT reports R

(iv) Physical,Mechanical &Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

(v) RT (Applicableas per Drg/Spcn)

Criticalregions

NDEReport

CHPforR

Shooting sketches to beprovided. Testing to bedone by approved ASNT/ISNT level II or IIIqualified technician

Page 33: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

2

2.02 Impeller(casting)

(i) Pouring withintegral test barfor casting

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR R If casting is withoutintegral test bar, pouringto be witnessed by QAO

(ii) Materialidentification &Stamping

100% IR W

(iii) HeatTreatment

100% HT Report R

(iv) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at GovtApproved/NABL Lab

(v) RT (Applicableas per Drg/Spcn)

Criticalregions

NDEReport

CHPforR

Shooting sketches to beprovided Testing to bedone by approvedASNT/ISNT level II or IIIqualified technician

2.03 Lower Bearing Bracket&Upper Bearing Bracket

(i) Pouring withintegral test barfor casting

100% IR R If casting is withoutintegral test bar, pouringto be witnessed by QAO

(ii) Materialidentification &Stamping

100% IR W

(iii) HeatTreatment

100% HT report R

(iv) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at GovtApproved/NABL Lab

Page 34: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

3

(v) RT (Applicableas per Drg/Spcn)

Criticalregions

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

NDEReport

CHPforR

Shooting sketches to beprovided Testing to bedone by approvedASNT/ISNT level II or IIIqualified technician

2.04 Wear Ring/Wear Plate (i) Materialidentification &Stamping

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.05 Bearing Cover (i) Materialidentification &Stamping

100% IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.06 Bar stock for RotorShaft

(i) Materialidentification &Stamping

100% IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

Page 35: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

4

2.07 Zinc Anode (i) Materialidentification &Stamping

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.08 Die cast Rotor (i) Materialidentification &Stamping

100% IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.09 Cable Gland (i) Materialidentification &Stamping

100% IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.10 Discharge outlet (i) Materialidentification &Stamping

100% IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

Page 36: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

5

2.11 Stator (i) Materialidentification &Stamping

100%

SOTR,ApprovedDrawingsand relevantStandards

SOTR,ApprovedDrawingsand relevantStandards

IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.12 Stator Casing (i) Materialidentification &Stamping

100%IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.13 Stator laminated pack (i) Materialidentification &Stamping

100%IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

2.14 Holding Plate forMechanical seal

(i) Materialidentification &Stamping

100%IR W

(ii) Physical,Mechanical,Chemicalproperties

1sampleper heat/per lot

LTC R Test to be done at NABLLab

Page 37: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

6

BOUGHT OUT ITEMS

2.15 Starter/Control Panel (i) Productidentification

100%SOTR,ApprovedDrawingsand SQAP

SOTR,ApprovedDrawingsand SQAP

IR W

(ii) SQAPCompliance

IR as perSQAP

R

(iii) Dispatchclearance

I-Note/Form4Dispatchcertificate(as applicable )

R

2.16 Diffuser, strainer (i) Productidentification 100%

SOTR,Supplier'scatalogue

SOTR,Supplier'scatalogue

STC/TC W

(ii) Visual &DimensionalCheck

IR R

2.17 Cable (i) Productidentification 100%

STC/TC W

(ii) Electrical &MechanicalProperties

STC/TC R

(iii) Visual &DimensionalCheck

IR R

2.18 Copper Wire Electrical &MechanicalProperties

100% SOTR,Supplier'scatalogue

SOTR,Supplier'scatalogue

STC/TCR

Page 38: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

7

COTS ITEMS2.19 Bearings

(i) Productidentification

(ii) Visual &Dimensionalexamination

100%

Approveddrawing/SOTR/Catalogue/OEM Spec

Approveddrawing/SOTR/Catalogue/OEM Spec

(i) STC/CC

(ii) IR

W

R

2.20 Mechanical Seal2.21 Valves2.22 Compound gauge

Pressure Gauge2.23 Gauge Piping2.24 'O' Rings & Gaskets2.25 Oil Seals2.26 Handle/Lifting Hook

2.27 Cable grommet

2.28 Spacer for Glands

2.29 Inst Coupling2.30 Hardware Items-

fastenersStuds, Nut, bolts,Screws, washers,Circlips, Rivet, Keys,Sand Guard, PlugAssy, Name Plate,Sleeve, flange, NeckRing, Sealing Ring, CapChain, Cable Clamps,Cable Grip

(i) Productidentification

(ii) Visual &Dimensionalexamination

100% Approveddrawing/SOTR/Catalogue/OEM Spec

Approveddrawing/SOTR/Catalogue/OEM Spec

(i) STC/CC

(ii) IR

W

R

2.30 Oil Test Certificate 100% Catalogue/OEM Spec

Catalogue/OEM Spec

CC R

Page 39: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

8

3.00 SECTION II - IN PROCESS INSPECTION3.01 Pump Casing,

(Upper & Lower)(i) Visual &DimensionalExamination

100%SOTR/Approveddrawing

Approveddrawing

IR R

(ii) Surface defectMPT/ DPT

Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

(iii) HydraulicPressure test(1.5times of theworking pressure)

NoLeakage

IR CHPforW

3.02 Impeller (i) Visual &DimensionalExamination

100%

Approveddrawing

IR R

(ii) Surface defectMPT/ DPT

Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

(iii) Static &DynamicBalancing

IR CHPforW

3.03 Lower Bearing BracketUpper Bearing Bracket

(i) Visual &DimensionalExamination

100% Approveddrawing

IR R

(ii) Surface defectMPT/DPT

100% Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Page 40: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

9

3.04 Diffuser, Strainer Visual &DimensionalExamination

100%

SOTR/Approveddrawing

Approveddrawing

IR R

3.05 Seal Housing (i) Visual &DimensionalExamination

100% Approveddrawing

IR R

(ii) Surface defectMPT/DPT

100% Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.06 Wear Ring/Wear Plate (i) Visual &DimensionalExamination 100%

Approveddrawing

IR R

(ii) Surface defectMPT/DPT

Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.07 Bearing Cover (i) Visual &DimensionalExamination

Approveddrawing

IR R

(ii) Surface defectMPT/DPT

Approveddrawing &Relevantstandard

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

Page 41: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

10

3.08 Rotor Shaft (i) Visual &DimensionalExamination

100%SOTR/Approveddrawing

Approveddrawing &Relevantstandard

IR R

(ii) Surfaceroughness

LTC R Test to be done at NABLLab

(iii) Surface defectMPT/DPT

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

(iv) UT

(v) Static andDynamicBalancing

IR CHPforW

(vi) Hardness LTC R Test to be done at NABLLab

3.09 Zinc Anode Visual &DimensionalExamination

Approveddrawing &Relevantstandard

IR R

3.10 Cable Gland Visual &DimensionalExamination

IR R

3.11 Discharge outlet Visual &DimensionalExamination

IR R

3.12 Stator Laminated Pack Visual &Dimensionalexamination

IR R

Page 42: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

11

3.13 Die Cast Rotor (i) Visual &Dimensionalexamination

100%

SOTR/Approveddrawing

IR R

(ii) Surface defectMPT/DPT

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.14 Stator Casing (i) Visual &DimensionalExamination

100%Approveddrawing &

IR R

(ii) Surface defectMPT/DPT

NDEReport

CHPforW

Testing to be done byapproved ASNT/ISNTlevel II or III qualifiedtechnician

3.15 Casing (AssembledPump)

(i) HydrostaticPressure [email protected] times ofworking pressure

100%No Leakage IR

CHPforW

(ii) Pneumaticpressure test

IR

3.16 Rotor Complete (i) Visual &DimensionalExamination

100% Approveddrawing &Relevantstandard

IR CHPforW

(ii) Run Out(iii) DynamicResidualunbalancing/DynamicBalancing(iv) Calculation ofair gap

Page 43: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

12

3.17 Stator Complete (i) Shaping

100% SOTR/Approveddrawing

Approveddrawing &Relevantstandard

IR CHPforW

(ii) Insulationresistance(iii) Line resistance(iv) HV Test IR(v) Surge test IR(vi)Varnish coating IR(vii)Epoxy coating IR

3.18 Integral Motor (i) All applicabletests as per EED-Q-071 R4(ii) IR before &after HV test

IR CHPforR

4.00 SECTION III : PRE-REQUISITE- FINAL INSPECTION

TYPE TESTING OF PUMP ( To be carried out on one unit /prototype)

4.01 Pump & Motor Assy Free rotation ofPump & Motor One Unit

Rotate freely Free Rotation IR W

4.02 Overall DimensionalInspection

ApprovedDrawings/Mfg Drawing

ApprovedDrawings/Mfg Drawing

IR R

4.03 Over Speed test(20% above specifiedspeed)

PO, SOTR ,TNCMinutes/ApprovedDrawing,

PO, SOTR ,TNC Minutes/ApprovedDrawing,DME Spec

IR CHPforW4.04 Start /Stop test

4.05 Cooling Test

Page 44: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

13

DME Spec402

402

4.06 Endurance Test(25 Hrs)Performance test withintegral Motor andcontrol panel

Flow(Q) v/sHead(H)

One Unit PO, SOTR ,TNCMinutes/ApprovedDrawing,DME Spec402

PO, SOTR ,TNC Minutes/ApprovedDrawing,DME Spec402

IR CHPforW

Readings to be recordedby every 02 hrs.

Flow(Q) v/sEfficiency(Effn)Flow(Q) v/sPower(P)Heat run/ TempriseBearing TempWindingResistance (Cold& Hot)InsulationResistanceHigh Voltage TestIndication/Alarm/Shut Downtest

4.07 Strip Open Test Wearing Parts

One Unit

IR W4.08 Post-Trial test

For 1 hourFlow(Q) v/sHead(H)Flow(Q) v/s Eff(n)Flow(Q) v/sPower(P)

4.09 Environmental Shock &Vibrations

Shock &VibrationsAnalysis

One Unit SOTR/NSS-II/ BR 3021/MIL-Std-167

SOTR/NSS-II/BR 3021/MIL-Std-167

NSTLReport

CHPforR

Page 45: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

14

5.00 SECTION IV : FINAL INSPECTON5.01 Pump & Motor Assy Free rotation of

Pump & Motor100% Rotate freely Free

RotationIR W

5.02 Performance test withIntegral motor andControl PanelDuration- 4 hours/set

Flow(Q) v/sHead(H)

100% PO, SOTR ,ApprovedDrawing &DME Spec 402

PO, SOTR,Approved drgand DMESpec 402

IR CHPforW

Compliance certificateto be submitted by thefirm to the InspectingOfficer for 100%

Flow(Q) v/sEfficiency(Effn)Flow(Q) v/sPower(P)Heat runTemperature riseBearingTemperatureInsulationresistanceWindingResistanceHigh Voltage Test

5.03 Strip Open test Wearing Parts 100%

IR W5.04 Post-Trial test

For 1 hourSuction head,Discharge Head,Output, RPM

100%

5.05 Overall DimensionalInspection

Dimensional Check 100%ApprovedDrawings/SOTR

ApprovedDrawings/SOTR

IR W

5.06 Weight Weight recording 100% Weightcertificate

W

5.07 Tally Plate Check 100% IR R

5.08 Lifting arrangement 100% IR R

Page 46: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

15

6.0 SECTION V : PRE REQUISITE ISSUE OF FORM -46.01 OBS Items as per

Purchase Order (i) Productidentification

100% PO,SOTR,ApprovedDrawings/ PIL /OEMSpecification

PO &ApprovedDrawings/PIL

IR R

(ii) VI/DI OEM TC,CC , IR R

6.02 Submission of as BuiltDrawings

Verification 100% ApprovedDrawings,Concessions &Deviations

Approveddrawings &Concurrencefrom drawingapprovalauthority

As builtdrawings

CHPforR

6.03 Submission of approveddocuments for stamping

sets Verification andstamping

100% PO,SOTR,ApprovedDrawings

PO,SOTR,ApprovedDrawings

Documentation

CHPforR

6.04 Liquidation ofobservation duringFATs, if any

Defectrectification

100% ApprovedDrawing,SOTR & FATdocument

ApprovedDrawing,SOTR & FATdocument

IR CHPforR

6.05 Painting VisualInspection &DFT

100% ApprovedDrawing,SOTR, PaintPlan

ApprovedDrawing/SOTR/ PO

IR W

6.06 Preservation & Packing VisualInspection

100% ApprovedDrawing,SOTR, OEMPreservationPlan

ApprovedDrawing,ApprovedPreservationPlan

IR W

6.07 Submission of Form -4(I&T Certificate) Correctness 100% SOTR,PO SOTR,PO Form-4 P

Page 47: STANDARD QUALITY ASSURANCE PLAN FOR CENTRIFUGAL · PDF filestandard quality assurance plan for centrifugal pumps srl no ... nabl lab (v) rt ... standard quality assurance plan for

STANDARD QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMPS

SrlNo

Material /components/As per SOTR/QAActivity

Qty.asperP.O.

Characteristic/Type Check

Quantum ofCheck

ReferenceDocuments

Acceptance Criteria

Format ofRecord

Actionby

QAE

Remarks

16

Important Notes:-

(a) Each type of Equipment & accessories to be supplied shall conform to specification acceptable to the TYPE APPROVALauthority.

(b) Motor to be procured only from Naval approved vendors.(c) EMI/EMC and ETT tests to be done at NABL approved Lab.(d) Material Testing to be done at NABL approved Lab.(e) All NDT to be performed by ASNT/ISNT Level II or Level III qualified person.(f) Imported items to be accepted on the basis of review of Import documents viz. (a) Bill of entry (b) Bill of Lading (c) Country

of Origin (d) Shipping Bill/Air way Bill (e) OEM Test Reports (f) Compliance certificate (g) Guarantee certificate(g) In case the items are of 'Bought Out ' nature, the inspections of the store are to be carried out on the basis of STC/OEM TC/

CC/QAP as applicable based on criticality.(h) The COTS/ 'Bought out' items in the QAP are indicative only. The firm is required to categorically define the 'Bought

out'/COTS items specific to their products in the drawings. Items will be categorized as bought out or COTs in the QAP on thebasis of approved drawings. Further, only finished products will be accepted as COTs and no raw material for manufacturingwill be acceptable as a COTS item.

(j) The SQAP does not apply to items not in the scope of supply of the firm.(k) The column 'Quantity as per P.O' has been left blank which has to be filled by the firm as per P.O while submitting Draft QAP

for approval.(l) WPS / WPQ certificates to be submitted by the firm for all welding related work.(m)Assy more than 40 Kgs weight should be provided with lifting arrangement.(n) Motor of Submersible Pump is not independent Motor. Stator & Rotor of the motor be purchased from approved/authorized

vendors which in turn will be integral part of the Pump set housed in the single pump casing. Due to design peculiarity andnature of the pump set the applicable tests will be according to SOTR/approved drawing and shall be checked at Motormanufacturers/firm's premises. The pump set with integrated motor shall be complying IP68 & EED(Q) -071-R4


Recommended