+ All Categories
Home > Documents > Standards and guidelines for PV GreenCard in South Africa · BSW-Solar 1 Standards and Guidelines...

Standards and guidelines for PV GreenCard in South Africa · BSW-Solar 1 Standards and Guidelines...

Date post: 31-Mar-2018
Category:
Upload: phamngoc
View: 218 times
Download: 0 times
Share this document with a friend
26
BSW-Solar Standards and Guidelines for PV in South Africa 1 Standards and guidelines for PV GreenCard in South Africa Dipl.-Ing. Udo Siegfriedt [email protected]
Transcript

BSW-Solar Standards and Guidelines for PV in South Africa1

Standards and guidelines for PV

GreenCard in South Africa

Dipl.-Ing. Udo Siegfriedt

[email protected]

BSW-Solar Standards and Guidelines for PV in South Africa2

This presentation will give an overview of International and South African

standards and guidelines for PV installations. The PV GreenCard as a

measure to ensure a high quality installations aims cover standards and best

practices for the following areas

Components

AC Installation (especially Grid Codes)

DC Installation (cable, DC switches, induction loop, fuses)

Lightning Protection

Fire Safety

Rooftop Installation

Safety at work

Commissioning, Operation & Maintenance

The presentation should be seen as a guideline for the PV GreenCard.

Especially for rooftop installations there are questions of regulations covering

other technical areas. This is open for further discussion.

The goal should be for the PV GreenCard to deal with all pertinent topics.

Introduction

BSW-Solar Standards and Guidelines for PV in South Africa3

Quality assurance steps along the value chain of PV systems

Along the value chain the installer must consider all applicable standards

De-

Commis-

sioning

Upcoming:- Recycling- removal

BSW-Solar Standards and Guidelines for PV in South Africa4

Standards and other technical directives

National standards and guidelines

International standards and guidelines

Directives of grid operators

Regional codes and standards (building regulations)

Manuals and certificates by the manufacturer

South Africa did already take a big step forward with

implementing good standards and guidlines

For South Africa some international standards apply, some

national standards are developed based on international

standards

BSW-Solar Standards and Guidelines for PV in South Africa5

Standard/Guideline Content Important for GreenCardElectricity Regulation Act 2006.pdf Licensing of generation and distribution of energy ??

Electricity Regulation Ammendment Act 2007.pdf also but for municipcalities ??

Environment Conservation Act 73 of 1989.pdf how to handle with the environment

G83-2 Engineering

_Recommendation_Aug2012.pdf Guideline for generators up to 16A per phase ??

IEC 60068-2-1 (preview).pdf Cold test Implemented in other standards

IEC 60068-2-2 (preview).pdf Dry heat test Implemented in other standards

IEC 60068-2-30 (preview).pdf Damp heat, cycling Implemented in other standards

IEC 60255-1 (preview).pdf

Requirements for measurements on relays and

safety devices Implemented in other standards

IEC 60255-151 (preview).pdf Requeirements under/over current protection

IEC 60255-21-1 (preview).pdf mechanical test for relays Implemented in other standards

IEC 60255-26 (preview).pdf EMC Should be covered e.g. with an inverter certificate

IEC 60364-7-712 (preview).pdf Installation of PV

most important, includes for example if a RCD shall

be mounted on the AC side and that a DC-isolator is

required

IEC 60529 (preview).pdf IP degree of protection

to name the IP of inverter and other relevant

components should be included in the passport

IEC 61000-4-1 Overview of series (preview).pdf EMC measurements compliance necessary

IEC 61727 (preview).pdf PV systems grid interface compliance necessary

IEC 62109-1 (preview).pdf Safety of power converters general requirements compliance necessary

IEC 62109-2 (preview).pdf particular requirements for inverters compliance necessary

IEC 62116 (preview).pdf test procedure anti islanding device Implemented in other standards

IEEE 1547.pdf

Interconnecting distributed resources with electric

power systems compliance necessary

National Building Regulations - R 2378 of 1990.pdf see next

national building regulations and building standards

act (2008).pdf Part T Fire protection

Another standard or guideline for detailes measures

necessary

National Regulator for Compulsory Specifications

Act No5 of 2008.pdf ??

Standards and other technical directives

BSW-Solar Standards and Guidelines for PV in South Africa6

Standard/Guideline Content Important for GreenCard

NEMA National Environmental Management Act No

107 or 1998.pdf ??

NRS 057 Electricity Metering.pdf compliance necessary

NRS048 part 2 Quality of Supply - Voltage

characteristics etc.pdf compliance necessary

NRS048 part 3 Quality of Supply -Procedures for

monitoring and reporting.pdf compliance necessary

NRS048 part 4 Quality of Supply - Application

requirements for utilities.pdf compliance necessary

NRS048-7 Edition 1 WG DRAFT.doc

NRS-097-2-1.pdf

NRS-097-2-3-final-2014.pdf

Maximum individual generation limit in a shared LV

(400 V/230 V) feeder

Occupational Health and Safety 1993

Ammended.pdf

Another standard or guideline for detailes measures

necessary

RSA Distribution Metering Code Ver 6.pdf

To ensure compliance with minimum requirements

for tariff metering and energy trading metering

installations

RSA Distribution Network Code Ver 6.pdf

Operational Responsibilities of Embedded

Generators and Other Customers

APPENDIX B: Embedded Generator Connection

Application Form

SAGC Network Version 7_March 2008.pdf Grid code

SANS 1019-2001.pdf

Standard voltages, currents and insulation levels for

electricity supply

SANS 211 (relevant but not actual standard).pdf EMC

components like inverter must have a certificate,

the whole installation must comply, but a individual

measurement is not done in most cases.

SANS10142-1(Amdt7) LV wiring of premises.pdf´ Same as next, older version? see next

SANS10142-1Amdt8 Wiring of Premises LV.pdf Part 1: Low-voltage installations. compliance necessary

Part 2: Medium-voltage installations above 1 kV

a.c. not exceeding 22 kV a.c. and up to and

including 3 000 kW installed capacity

SANS60947-2 IEC60947-2 (preview).pdf Circuit breakers

Standards and other technical directives

BSW-Solar Standards and Guidelines for PV in South Africa7

Standard/Guideline Content Important for GreenCard

South African Grid Code Requirements for

Renewable Power Plants - Version 2 8.pdf (i) Category A1: 0 - 13.8 kVA

Should be covered e.g. with an inverter certificate,

some of the content is comparable to VDE AR N

4105

This sub-category includes RPPs of Category A with

rated power in the range of 0 to 13.8 kVA.

(ii) Category A2: 13.8 kVA – 100 kVA

This sub-category includes RPPs of Category A with

rated power in the range greater than 13.8 kVA but

less than 100 kVA.

(iii) Category A3: 100 kVA – 1 MVA

This sub-category includes RPPs of Category A with

rated power in the range 100 kVA but less than 1

MVA.

This category also includes RPPs of Category A1

and A2 with a rated power less than 100kVA that are

directly connected to a MV-LV transformer.

Note: RPPs with a rated power greater than 4.6 kVA

must be balanced three-phase.

Appendix 2: No special requirements for PV,

Appendix 8: Documentation

Standard for Interconnection of Embedded

Generation (Eskom doc).pdf Medium voltage, high voltage…, not for low voltage

Shall the greencard also cover a medium voltage

installation?

VDE-AR-N_4105 (contents).pdf compliance necessary

Standards and other technical directives

BSW-Solar Standards and Guidelines for PV in South Africa8

KfW Toolbox: Standards for PV systems

Inverter

BSW-Solar Standards and Guidelines for PV in South Africa9

KfW Toolbox: Standards for PV-systems

BSW-Solar Standards and Guidelines for PV in South Africa10

KfW Toolbox: Standards for PV-systems

BSW-Solar Standards and Guidelines for PV in South Africa11

Most relevant German grid connection standards for a later

assessment of a South African selection

Standards and guidelines:

DIN EN 61727: PV systems – Characteristics of the grid operator interface

DIN VDE 0126-1: Automatic isolation unit between a private power generator and

the public grid (incl. anti islanding)

VDEW-“Guideline for connecting and parallel operating of a private power generator

to the public grid

TAB 2007 Technical requirements by the grid companies for connecting to the

public grid

Grid connection point (German Renewable Energy Law EEG)

Technical and economically most suitable connecting point

Power generator < 30 kW: existing grid connection point = most suitable

Larger generator: : Assignation / in consultation with the grid company

In case of dispute: - EEG-Arbitration Office: www.clearingstelle-eeg.de

BSW-Solar Standards and Guidelines for PV in South Africa12

Requirements EEG 2014 Part 2

FNN (Committee on the elaboration of VDE guidelines)- guideline VDE-

AR-N 4105 for connecting and operating of private power generators at

the low voltage grid (VDE: German Electrical Engineering Association)

BDEW guideline „Erzeugungsanlagen am Mittelspannungsnetz” (10 to

35 kV) – for connecting an operating of private power generators at the

medium voltage grid 06/2008

„European Network of Transmission System Operators for Electricity“

(entsoe) “ENTSO-E Draft Requirements for Grid Connection Applicable

to all Generators”. Not valid yet. Regulations close to VDE-AR-N 4105

and BDEW guidelines

Technical requirements for connecting to the public low voltage and

medium voltage grid of the BDEW (BDEW: German Utilities Association)

Requirements for PV grid integration as implemented in Germany

BSW-Solar Standards and Guidelines for PV in South Africa13

Criteria for connection:

Max unbalanced load: 4,6 kVA

Power > 13,8 kVA :

use of three phase inverters or

single phase inverter using a communication

to avoid unbalanced load behavior

Large three phase systems can be enlarged

on one phase up to 4,6 kVA without adding a

communication

Increase in voltage at the feed in point:

max. 3% (until 2011: 2%)

Limit values for flicker, odd and even

harmonics

=> Declaration of conformity

of the inverter manufacturer

German electricity grid - rules of application (VDE AR 4105)

BSW-Solar Standards and Guidelines for PV in South Africa14

Grid stability

Feed-in management

Renewable Energy Law

(EEG)

Grid stability control

(reactive power) VDE 4105

Dynamic grid support

(fault ride through)

BDEW Guideline

Inverter

BSW-Solar Standards and Guidelines for PV in South Africa15

Generator power Necessary measures

≤ 3,68 kVA

Active

pow

er

reduction if fr

equency >

50,2

Hz

and s

hut dow

nif fre

quency <

47,5

Hz

• Reactive power cos φ = +/- 0,95 according EN 50438

• Remote feed in reduction / shut down or feed in reduction to max. active power of 70%

≤ 13,8 kVA

max 4

,6 k

VA

unbala

nced load

• Reactive power according given characteristic with cos φ = +/- 0,95

• Central or inverter integrated grid protection

• Remote feed in reduction / shut down or feed in reduction to

max. active power of 70%

≤ 30 kVA • Reactive power according given characteristic with cos φ = +/- 0,9

• Central or inverter integrated grid protection

• 3 phase inverter or 1 phase inverter and communication

• Remote feed in reduction / shut down or feed in reduction to

max. active power of 70%

≤ 100 kVA • Reactive power according given characteristic with cos φ = +/- 0,9

• Central grid protection, anti islanding protection integrated in inverter possible

• 3 phase inverter or 1 phase inverter and communication

• Remote feed in reduction

> 100 kVA • Reactive power according given characteristic with cos φ = +/- 0,9

• Central grid protection, anti islanding protection integrated in inverter possible

• 3 phase inverter or 1 phase inverter and communication

• Remote feed in reduction in several steps (mostly done with centralized telecontrol

signal 100%, 60%, 30%, 0%) and transmission of actual feed in power to the grid

company

Requirements to the grid connection of

PV-systems according §6 EEG and VDE 4105

Bold: same generator power as in <SA Grid Code Requirements for Renewable Power Plants Version 2.8>

BSW-Solar Standards and Guidelines for PV in South Africa16

Components : Inverter

The installation and therefore the

inverter must fulfil the grid codes of

South Africa

Conformity to grid codes must be

certified by an accredited institute.

The PV GreenCard will require the

compliance to the SA Grid codes.

The certificates and declarations have to

be added to the documentation

Special requirements must be

implemented in the GreenCard

(see example next slide)

BSW-Solar Standards and Guidelines for PV in South Africa17

Special requirements for shared LV feeder NRS-097-2-3-final-2014

BSW-Solar Standards and Guidelines for PV in South Africa18

Arc protecting / safe DC installation

Earth fault and short circuit

safe installation (cable

laying avoiding sharp

edges, tight cable radius,…)

according IEC 60364-4

Protection class II

Fused strings (positive and

negative pole, DC-fuse)

Measurements during

commissioning to ensure

correct installation

Lightning and overvoltage

protection (if appropriate)

• Quality components

• Proper planning

• Good craftsmanship!

• Sufficient O+M

Inverter

DC main cable

Isolators

String fuses

Generator junction box

Isolators

( String diodes )

String fuses

Source: Shell solar

BSW-Solar Standards and Guidelines for PV in South Africa19

Earth- and short circuit proof – protection class II

UV- and weatherproof (temperature range approx. -40°C to 120°C).

Exceptionally robust, but flexible

Flame retardant, with little toxicity in case of fire, halogen-free

Dimensioning for voltage and current

Low cable loss < 1 %

Type code PV-1-F

If required: ammonia resistant

If required: water proof, suitable for laying directly in the ground

Question: Does the significantly higher UV irradiation in SA influence the selection?

Are additional measures required (e.g. use of UV resistant conduit for exposed

cables)?

DC Installation: Requirements for solar cable

BSW-Solar Standards and Guidelines for PV in South Africa20

Excerpt solar cable datasheet (example)

BSW-Solar Standards and Guidelines for PV in South Africa21

PV GreenCard and Cable

The GreenCard shall address the requirements and necessary measures, e.g. if

the cable are to be laid directly in the ground

Most common requirements and the resulting measures should be answered in

check boxes

The certificates and declarations have to be added to the documentation

The installer shall also declare, that the whole installation is earth- and short

circuit proof by avoiding sharp edges, tight bending radiuses etc.

BSW-Solar Standards and Guidelines for PV in South Africa22

Mounting of solar-modules on roofs as per VDI 6012 Sheet 1.4

The Installer has to design and is responsible for the following parts of the mechanical

structure:

Mounting of modules

The installation of the mounting structure on the building

Structural integrity of the building (static load, wind etc.)

Support is given by:

User directives (e.g. VDI guidelines)

Software (mounting system manufacturer)

Installation manual (module manufacturer, mounting system manufacturer)

Structural engineer

BSW-Solar Standards and Guidelines for PV in South Africa23

So

urc

e: M

an

nh

eim

er A

G

Tilted roof with tiles

Consider roofing standards or guidelines to ensure that a roof remains impermeable

against water after a PV system was installed.

In the GreenCard the installer can only sign off an installation if all appropriate

standards and guidelines were adhered to.

BSW-Solar Standards and Guidelines for PV in South Africa24

Load calculations according to European standard series EN 1991 (Eurocode)

Eurocode 1 Part 1: Actions on structures, General actions

Part 1-1: Densities, static weight, imposed loads for buildings

Part 1-3: Snow loads

Part 1-4: Wind actions

Parts 1-2, 1-5, 1-6, 1-7 contain actions like fire, thermal action and others

National annexes for country specifics like wind and snow maps

For South Africa SANS 10160-3:2010 applies

The GreenCard will require information on the mounting situation and all

assumptions using check boxes. Example: Building height in steps (see next

slide)

The results of a structural analysis should be part of the documentation where

applicable

Structural analysis

Wind zones for other regions: http://www.sander-partner.ch; http://www.anemos.de

BSW-Solar Standards and Guidelines for PV in South Africa25

Windloads due to DIN EN 1991-1-4

Wind: Load influence on inclined roofs

Windzone Speed pressure q in KN/m² dependent of height

of building

landlocked country

landlocked country

landlocked country

landlocked country

Islands North Sea

Islands Baltic Sea

Islands Baltic Sea

Islands Baltic Sea

BSW-Solar Standards and Guidelines for PV in South Africa26

PV GreenCard approach: Challenge is …

Include as much technical content (standards and

guidelines) as necessary and as few as possible

Keep it substantiated, but also simple and workable!

Conclusion


Recommended