+ All Categories
Home > Documents > STATE OF CONNECTICUT Core-CT Project

STATE OF CONNECTICUT Core-CT Project

Date post: 10-Jan-2016
Category:
Upload: candie
View: 39 times
Download: 3 times
Share this document with a friend
Description:
STATE OF CONNECTICUT Core-CT Project. Financials User Group Meeting Accounts Payable/Purchasing December 2003. Agenda. Introduction/Production Support Elaine Pelletier Workflow Nayda Flores Purchasing Catalog Management Joann Bellamo Large Contracts PO Dispatch PO Set Up Options - PowerPoint PPT Presentation
Popular Tags:
63
1 STATE OF CONNECTICUT Core-CT Project Financials User Group Meeting Financials User Group Meeting Accounts Payable/Purchasing Accounts Payable/Purchasing December 2003 December 2003
Transcript
Page 1: STATE OF CONNECTICUT Core-CT Project

1

STATE OF CONNECTICUTCore-CT Project

Financials User Group MeetingFinancials User Group MeetingAccounts Payable/PurchasingAccounts Payable/Purchasing

December 2003December 2003

Page 2: STATE OF CONNECTICUT Core-CT Project

2

• Introduction/Production Support Elaine Pelletier

• Workflow Nayda Flores

• Purchasing– Catalog Management Joann Bellamo– Large Contracts– PO Dispatch– PO Set Up Options

• BREAK• Accounts Payable

– Payment Cancellation Holly Osburn– Voucher Matching & Match Exceptions Cynthia Babbitt– Voucher Tips Mark Aronowitz– Making Funds Available Deb Carta

AgendaAgenda

Page 3: STATE OF CONNECTICUT Core-CT Project

3

Production SupportProduction Support

• Keep Core-CT Up and Running• Provide training to End-Users • Monitor the system for problems – both system and

user errors• Implement delayed functionality of Phase 1 modules• Coordinate and disseminate business process decisions

Page 4: STATE OF CONNECTICUT Core-CT Project

4

Whole Support TeamWhole Support Team

Core-CT Production Support Team

DOIT Help DeskCentral Process Owners

OSC – Accounting ServicesOSC – Accounts Payable

DAS & DOIT – Procurement ServicesOTT - Treasurer

Page 5: STATE OF CONNECTICUT Core-CT Project

5

Production Support TeamProduction Support Team

Elaine PelletierElaine Pelletier

Jeanne SkellettJeanne Skellett

Holly OsburnHolly Osburn

Development Development

Configuration & SecurityConfiguration & Security

Business SupportBusiness Support

Level 2 Help DeskLevel 2 Help Desk

Page 6: STATE OF CONNECTICUT Core-CT Project

6

Production SupportProduction Support TeamTeam

Page 7: STATE OF CONNECTICUT Core-CT Project

7

•FinancialsWorklist Procedures•Requisition Workflow•PO Workflow

WorkflowWorkflow

Page 8: STATE OF CONNECTICUT Core-CT Project

8

Fin Worklist NavigationFin Worklist Navigation

Page 9: STATE OF CONNECTICUT Core-CT Project

9

Fin Worklist ProceduresFin Worklist Procedures

Page 10: STATE OF CONNECTICUT Core-CT Project

10

Fin Worklist ProceduresFin Worklist Procedures

Page 11: STATE OF CONNECTICUT Core-CT Project

11

Training Update

Order delivered by vendor and received in Core-CT:Status: “Received”Both Goods and Services are received in Core-CT.

Return to Vendor:Optional – If items delivered by the vendor do not meet State expectations, the items can be returned to the vendor.

Invoice Processed by Accounts Payable:Vouchers created and invoices posted for payment.

Payment Issued to the Vendor:The vouchers are “Matched”, the Pay Cycle Runs and payments are issued to the vendor.Status: “Complete”

Requisition:Requisition Created in eProcurementStatus: “Open”

Requisition Submitted for Approval:Status: “Pending” Result: “Approved”Amount: ChartField:Amt 1 (All Requisitions)Budget Approver

Amt 2 (>$2,500)Purchasing Amt 3 (>$10,000)Approver

Amt 4 (>$1,000,000)

Requisition Sourced Into a PO: AutoSelect ProcessPO Staging TablePO Calculations ProcessPO Create ProcessBatch Frequency: 4x daily.Status: “PO(s) Created”

PO Approval:Purchase Orders that were created from Requisitions do not require approval as a PO.

PO Dispatched to the Vendor:Status: “PO(s) Dispatched”Batch Frequency: 4x daily.

Requisition Budget Checked: Validates sufficient funds are available for the proposed purchase by coding string. If sufficient funds exist, a pre-encumbrance is created. Batch Frequency: 4x daily. Budget Status: “Valid”

Req. to Check

Page 12: STATE OF CONNECTICUT Core-CT Project

12

Requisition WorkflowRequisition Workflow

Requisition Amount

Approver 1

Requisition Amount

Approver 2

Requisition Amount

Approver 3

Requisition Amount

Approver 4

Requisition Budget

Approver

Requisition Purchasing Approver

-All transactions

-Approve up to $2,500

- All transactions exceeding $2,500 Approve to $10,000

-All transactions exceeding $10K

-Approve to $1mm

-All transactions exceeding $1M

-Approve over $1mm

- All transactions regardless of amount

- Validates chartfield information

- All transactions regardless of amount

- Validates purchase information (General Buyer) Name prints on PO

Purchase Order Sent to Vendor

- Automated batch processing creates PO and sends to vendor

Additional Approval can be inserted at any time during the Approval process.

RequesterCreates

RequisitionOnline

Page 13: STATE OF CONNECTICUT Core-CT Project

13

Reviewing Status of RequisitionsReviewing Status of Requisitions

Page 14: STATE OF CONNECTICUT Core-CT Project

14

Reviewing Status of ApprovalReviewing Status of Approval

Page 15: STATE OF CONNECTICUT Core-CT Project

15

Training UpdatePO Life Cycle

Agenda Topic goes hereOnline (Manual) PO:Purchase Order Created in the Purchasing ModuleStatus: “Open”

PO Submitted for Approval:Initial Status: “Pending Approval” Resulting Status: “Approved”Amount: ChartField:Amt 1 (All POs) PO Budget ApproverAmt 2 (>$10,000)

PO Budget Checked: Validates sufficient funds are available for the proposed purchase by coding string. If sufficient funds exist, an encumbrance is created for the PO.Batch Frequency: 4x daily.Budget Status: “Valid”

PO Dispatched to the Vendor:PO delivered to the vendor by fax, email, EDX, phone, or print method.Status: “Dispatched”Batch Frequency: 4x daily.

Order delivered by vendor and received in Core-CT:Both Goods and Services are received and keyed into Core-CT.Resulting Status: “Received”

Return to Vendor:Optional – If items delivered by the vendor do not meet State expectations, the items can be returned to the vendor.

Invoice Processed by AP and Payment Issued to the Vendor:The vouchers are created, approved and “Matched”. Additionally, the Pay Cycle Runs and payments are issued to the vendor.

PO Closed and Reconciled:Closing a PO sets the status of the PO to “Complete” and signals that the PO is completely processed. Reconciling a PO releases any unused encumbrances associated with the PO.Status: “Complete”

Online PO Life Cycle

Page 16: STATE OF CONNECTICUT Core-CT Project

16

16

PO WorkflowPO Workflow

Buyer Creates

PO Online

- All transactions - All transactions exceeding $10K

- All transactions regardless of amount

-Validates chartfield information

-Name prints on PO

-Manual PO Emergency or immediate need

-PO created from RFQ

-PO created from contract (POS, PSA, Right Of Way, Construction, RL, MOU, Grant)

PO AmountApprover 1

PO BudgetApprover

PO AmountApprover 2

Page 17: STATE OF CONNECTICUT Core-CT Project

17

PO TroubleshootingPO Troubleshooting

Page 18: STATE OF CONNECTICUT Core-CT Project

18

PO TroubleshootingPO Troubleshooting

Page 19: STATE OF CONNECTICUT Core-CT Project

19

PO TroubleshootingPO Troubleshooting

Page 20: STATE OF CONNECTICUT Core-CT Project

20

PO TroubleshootingPO Troubleshooting

Page 21: STATE OF CONNECTICUT Core-CT Project

21

Common Workflow IssuesCommon Workflow Issues

1. Why don’t I have items on my Worklist?

2. I have items stuck on my Worklist…

3. I have duplicate items on my Worklist…

4. Why aren’t requisitions appearing on myWorklist?

Page 22: STATE OF CONNECTICUT Core-CT Project

22

WorkflowWorkflow

Page 23: STATE OF CONNECTICUT Core-CT Project

23

• Catalog Management– Patch loaded 12/10– File update process started 12/12– File update completed by 1/1– Listing of files loaded

PurchasingPurchasing

Page 24: STATE OF CONNECTICUT Core-CT Project

24

PurchasingPurchasing

Page 25: STATE OF CONNECTICUT Core-CT Project

25

PurchasingPurchasing

• eProcurement – Advanced Search

– By Vendor– By Description– By Manufacturer– By Manufacturer Item ID– By Item ID

Page 26: STATE OF CONNECTICUT Core-CT Project

26

Catalog SearchCatalog Search

Page 27: STATE OF CONNECTICUT Core-CT Project

27

Advanced SearchAdvanced Search

Page 28: STATE OF CONNECTICUT Core-CT Project

28

Search ResultsSearch Results

Page 29: STATE OF CONNECTICUT Core-CT Project

29

PurchasingPurchasing

• Large Contracts– Tolerances– PO Change Orders

• PO Dispatch

Page 30: STATE OF CONNECTICUT Core-CT Project

30

• PO Set Up Options– From a Requisition– Online PO– Amount Only vs. Quantity– Receiving Required

PurchasingPurchasing

Page 31: STATE OF CONNECTICUT Core-CT Project

31

Requisition vs. Online PORequisition vs. Online PO

Defaults Requisition Online PO

Searching the ItemCatalog

ePro utilizing the Advanced Search functionality

Does not utilize the Advanced Search functionality

Amount Only Checkbox Is not a selectable option in ePro

Is a selectable option located on the Line Details Page

Receiving “Receiving is Required”

Defaults from the Item and can not be changed

User decides to check the receiving checkbox or not

Page 32: STATE OF CONNECTICUT Core-CT Project

32

PO Set Up OptionsPO Set Up Options

Distributeby Type*

Requisition Online PO

Amount Only You CANNOT create anAmount Only Requisition

UtilitiesPurchase of Services (POSs)Personal Service Agreements (PSAs)

Quantity CommoditiesFood OrdersOffice Supplies

Items Stocked in Warehouses

CommoditiesFixed cost monthly services – Rent, Snow Plowing, Lawn Service

Fixed cost monthly goods

*You CANNOT mix Amt Only and Quantity on a PO

Page 33: STATE OF CONNECTICUT Core-CT Project

33

TroubleshootingTroubleshooting

• Document Cross Reference–PO to REQ–REQ to PO–PO Activity Summary–Document Status–Receiving Required Query

•Other Troubleshooting Aids

Page 34: STATE OF CONNECTICUT Core-CT Project

34

TroubleshootingTroubleshooting

Page 35: STATE OF CONNECTICUT Core-CT Project

35

TroubleshootingTroubleshooting

Page 36: STATE OF CONNECTICUT Core-CT Project

36

TroubleshootingTroubleshooting

Page 37: STATE OF CONNECTICUT Core-CT Project

37

TroubleshootingTroubleshooting

Page 38: STATE OF CONNECTICUT Core-CT Project

38

TroubleshootingTroubleshooting

Page 39: STATE OF CONNECTICUT Core-CT Project

39

TroubleshootingTroubleshooting

Page 40: STATE OF CONNECTICUT Core-CT Project

40

TroubleshootingTroubleshooting

Page 41: STATE OF CONNECTICUT Core-CT Project

41

PurchasingPurchasing

Page 42: STATE OF CONNECTICUT Core-CT Project

42

EPM User Groups

EPM User Groups are about to begin

• One User Group meeting on a monthly basis

− First Meeting: January 12, 2004 from 9 am to 12 pm at DOIT 1002 A & B

• Attendees

- Submitted by agency sponsor; 1 – 2 per agency per meeting is requested

- Communication forthcoming to Agency Sponsors requesting agency attendees

• Meeting Content

- Presentations on topics of interest (EPM enhancements and fundamentals)

- Q & A / Issues

• EPM User Group rollout will be announced at the Financials User Group’s Purchasing / Accounts Payable (Group 1) meeting on December 15, 2003

• EPM User Group update will be provided at the Financial User Group’s General Ledger / Accounts Receivable (Group 2) meeting in January 2004

Page 43: STATE OF CONNECTICUT Core-CT Project

43

Payment CancellationsPayment CancellationsPayment

StatusAction Required Reissue Payment?

-Payment Not Yet Issued to Vendor

-Call Linda Carney (OSC)702-3396

-Complete FormCO-790, Send to OSC/APD withproper backup

-If NO, and payment is non-PO, process is complete

-If NO, and payment is PO-related, prepare Reversal Voucher

-If YES, and payment is PO-related with a wrong $amt and/or a wrong vendor, prepare Reversal Voucher after OSC contacts you that pmt cancellation is processed. Then prepare new Regular Voucher for the correct $amt and/or the correct vendor

-If YES, and payment is non-PO with a wrong $amt and/or a wrong vendor, prepare new Regular Voucher for the correct $amt and/or the correct vendor

Page 44: STATE OF CONNECTICUT Core-CT Project

44

Payment CancellationsPayment CancellationsPayment

StatusAction Required Reissue Payment?

-Payment Already Issued to Vendor But Not Cashed and Returned to Agency

-Call Linda Carney (OSC) 702-3396 for procedures

-Complete FormCO-790, Send to OSC/APD with proper backup

-If NO, and payment is non-PO, process is complete

-If NO, and payment is PO-related, prepare Reversal Voucher

-If YES, and payment is PO-related but for a wrong $amt and/or the wrong vendor, prepare a Reversal Voucher after OSC contacts you that pmt cancellation is complete. Then prepare new Regular Voucher for the correct $amt and/or the correct vendor

-If YES, and payment is non-PO but for a wrong $amt and/or the wrong vendor, prepare a Regular Voucher for the correct $amt and/or the correct vendor

Page 45: STATE OF CONNECTICUT Core-CT Project

45

Payment CancellationsPayment CancellationsPayment

StatusAction Required Reissue Payment?

-GIRO Payment to Another State Agency – Deposit Not Yet Processed

-Call Bob Gnocchi (OTT) 702-3108to remove deposit

-Call Linda Carney (OSC) 702-3396 tocancel payment

-If NO, and payment is non-PO, process is complete

-If NO, and payment is PO-related, prepare Reversal Voucher

-If YES, and payment is PO-related but for a wrong $amt and/or the wrong vendor, prepare a Reversal Voucher after OSC contacts you that pmt cancellation is complete. Then prepare new Regular Voucher for the correct $amt and/or the correct vendor

-If YES, and payment is non-PO but for a wrong $amt and/or the wrong vendor, prepare a Regular Voucher for the correct $amt and/or the correct vendor

Page 46: STATE OF CONNECTICUT Core-CT Project

46

Payment CancellationsPayment Cancellations

Void Payment Stop Payment Action Required

Payment is not yet Issued

Payment is issued but not yet returned to

Agency (in jeopardy of being cashed)

Complete form CO-860 and send to

Joanne Vallo, (OTT). 860-702-3115.

Page 47: STATE OF CONNECTICUT Core-CT Project

47

Create Voucher Match

Process

Resolve Match Exceptions

Approve Voucher

Budget Check

Process

Resolve Budget

Exceptions

PostVouch

er

Generate/Post Payment

STARTEND

Voucher Life Cycle ReviewVoucher Life Cycle Review

Page 48: STATE OF CONNECTICUT Core-CT Project

48

Match Exceptions•Unmatched receivers exist•Exceeded PO Tolerances•Amount Vs. Quantity•Consequences of overriding Match Exceptions

MatchingMatching

Page 49: STATE OF CONNECTICUT Core-CT Project

49

Reviewing MatchingReviewing Matching

Page 50: STATE OF CONNECTICUT Core-CT Project

50

Understanding Match RulesUnderstanding Match Rules

Page 51: STATE OF CONNECTICUT Core-CT Project

51

Voucher Tips - Can I delete this voucher?

Page 52: STATE OF CONNECTICUT Core-CT Project

52

Voucher Tips - Can I delete this voucher?

Page 53: STATE OF CONNECTICUT Core-CT Project

53

Voucher Tips - Can I delete this voucher?

Page 54: STATE OF CONNECTICUT Core-CT Project

54

Voucher Tips - Where is my payment?

Page 55: STATE OF CONNECTICUT Core-CT Project

55

Voucher Tips - Where is my payment?

Page 56: STATE OF CONNECTICUT Core-CT Project

56

Voucher Tips - Duplicate Invoice Checking

Page 57: STATE OF CONNECTICUT Core-CT Project

57

Duplicate Invoice CheckingDuplicate Invoice CheckingVoucher Tips - Duplicate Invoice Checking

Page 58: STATE OF CONNECTICUT Core-CT Project

58

Voucher Tips - Duplicate Invoice CheckingMedical Services9/10/03 Jennings Dr Marks10/15/03 Dental Health Care8/10 Haslam Kaplan Cox1603122 Dr Baker7/1/03 Medicaid 06020

Real Estate Transactions

7/10/03 Closing for Smith Main St Avon

Rent

7/1/03 to 7/31/03 Rent 159 High St Waterbury7/1/03 to 7/31/03 Rent 999 Asylum St Hartford7/1/03 to 7/31/03 Taxes 25 Sigourney St Hartford

Professional Services

PSA 3621 final paymentAnnual audit 200311/30/03 Design for CCSU

Child/Foster Care

7/1/03 to 7/15/03 shelter

Catering Service

7/2/ and 8/6 catering services

Board Member Reimbursements

7/7 and 7/8 board fees

Per Diem Reimbursements

5/4 5/5 5/11 5/12Construction

Project 576396 number 5025

Postage

First class presort account 03212Permit fee account 0470440

Transportation

Shoreline East 7/03Transportation 10/23-11/8/03

GIRO

123456

Utilities

Account 54321 7/03Account 65432 7/03

Page 59: STATE OF CONNECTICUT Core-CT Project

59

Voucher Tips - Knowing your Voucher Dates

Page 60: STATE OF CONNECTICUT Core-CT Project

60

Duplicate Invoice CheckingDuplicate Invoice CheckingVoucher Tips - Knowing your Voucher Dates

Page 61: STATE OF CONNECTICUT Core-CT Project

61

•Process Deposits and Interagency Payments•Manage Match Exceptions•Manage Requisitions•Manage Purchase Orders

Making Funds AvailableMaking Funds Available

“Show me the

money!”

Page 62: STATE OF CONNECTICUT Core-CT Project

62

Accounts PayableAccounts Payable

Page 63: STATE OF CONNECTICUT Core-CT Project

63

Thank You for your participation today. We look forward to continuing our work together to makeCore-CT a Success!

• Look for this presentation and meeting Q & A’son the Core-CT Website (http://www.core-ct.state.ct.us/)

• Overflow Meeting - January 5, 2004101 E. River Drive, Room 1002 A&B - AP/PO/Overflow

• AR/GL/Reporting Meeting - January 26, 2004101 E. River Drive, Room 1002 A&B - AR/GL/ Reporting

ClosingClosing


Recommended