STATE OF ILLINOIS
ILLINOIS COMMERCE COMMISSION
Northern Illinois Gas Company )
d/b/a Nicor Gas Company )
)
Petition Pursuant to Rider QIP ) Docket No. 19-0294
of schedule of Rates for Gas Service )
to initiate a Proceeding to Determine )
the Accuracy and Prudence of )
Qualifying Infrastructure Investment )
PUBLIC VERSION
DIRECT TESTIMONY OF
SEBASTIAN COPPOLA
ON BEHALF OF
THE PEOPLE OF THE STATE OF ILLINOIS
AG Exhibit 1.0
December 13, 2019
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
2
TABLE OF CONTENTS
I. Introduction ..............................................................................................................................5
II. Summary Conclusions and Recommendations .....................................................................9
III. Infrastructure Cost Incurred ... ...........................................................................................11
IV. Nicor Gas Attestation of Prudency ... ..................................................................................13
V. Assessment of the 2018 Rider QIP Reconciliation .... .........................................................14
VI. Projects with Large Cost Variances ....................................................................................16
A. Copper Services Replacement ..........................................................................................19
B. Norridge Cast Iron Main Replacement ...........................................................................22
C. Franklin Park Main Replacement ...................................................................................23
D. Glenview Main Replacement ...........................................................................................25
E. Oak Lawn Main Replacement .........................................................................................26
F. Princeton Main Replacement ...........................................................................................28
G. Landscaping and Paving Carryover Costs .....................................................................29
H. Carpentersville Main Replacement .................................................................................30
I. Norridge Cast Iron Services Replacement .......................................................................31
J. Ancona Storage Field Gathering Lines ............................................................................33
K. Horizon Station Odorizer Replacement .........................................................................36
L. Summary ............................................................................................................................37
VII. Project Change Order .........................................................................................................38
A. Railway ROE Approval Issues.........................................................................................39
B. Other Change Order Issues ..............................................................................................44
VIII. Acceptance of Higher Cost Bids ........................................................................................54
A. Aux Sable Pipeline Replacement .....................................................................................55
B. Paving Restoration Zone 2 ...............................................................................................58
C. Paving Restoration Zone 3 ...............................................................................................60
D. Paving Restoration Zone 6 ...............................................................................................62
E. Summary ............................................................................................................................64
IX. Project Not Bid Out ...............................................................................................................65
X. Lack of Contractor Audits ....................................................................................................69
XI. Exclusion of Gas Storage Infrastructure Costs ..................................................................71
XII. Other Observations ..............................................................................................................72
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
3
EXHIBIT LIST
AG Ex. 1.1 Sebastian Coppola Regulatory Experience and Qualifications 1
AG Ex. 1.2 Nicor Gas Responses to DR AG 3.01, AG 5.01, AG 1.07(Docket 18-1775) 2
AG Ex. 1.3 CONF Nicor Gas Response to DR AG 5.16 with Exhibit 1 CONF 3
AG Ex. 1.4 Nicor Gas Responses to DR MEM 1.03 (Ex. 1), AG 4.10 (Ex. 3), AG 5.15 4
AG Ex. 1.5 Copper Services QIP Cost and Surcharge Adjustment 5
AG Ex. 1.6 Nicor Gas Responses to DR AG 4.25, AG 5.28 6
AG Ex. 1.7 Hudson Compressor Capital Additions Disallowance 7
AG Ex. 1.8 Franklin Park Main QIP Cost and Surcharge Adjustment 8
AG Ex. 1.9 Glenview Main QIP Cost and Surcharge Adjustment 9
AG Ex. 1.10 Oak Lawn Main QIP Cost and Surcharge Adjustment 10
AG Ex. 1.11 Princeton Main QIP Cost and Surcharge Adjustment 11
AG Ex. 1.12 Carryover Restoration Main QIP Cost and Surcharge Adjustment 12
AG Ex. 1.13 Carpentersville Main QIP Cost and Surcharge Adjustment 13
AG Ex. 1.14 Norridge Cast Iron Services QIP Cost and Surcharge Adjustment 14
AG Ex. 1.15 Ancona C & D Gathering Lines QIP Cost and Surcharge Adjustment 15
AG Ex. 1.16 Horizon Station Odorizer Replacement QIP Cost and Surcharge Adjustment 16
AG Ex. 1.17 Nicor Gas Response to DR AG 3.11 17
AG Ex. 1.18 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 178-182 18
AG Ex. 1.19 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 183-188 19
AG Ex. 1.20 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 218-218 20
AG Ex. 1.21 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 252-253 21
AG Ex. 1.22 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1B, pages 35-40 22
AG Ex. 1.23 CONF Nicor Gas Response to DR AG 5.04 23
AG Ex. 1.24 Railway ROW Change Orders QIP Cost and Surcharge Adjustment 24
AG Ex. 1.25 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 57-58 25
AG Ex. 1.26 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1A, pages 302-303 26
AG Ex. 1.27 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1B, pages 67-68 27
AG Ex. 1.28 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1C, page 159 28
AG Ex. 1.29 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1C, page 303 29
AG Ex. 1.30 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1C, pages 188-189 30
AG Ex. 1.31 CONF Nicor Gas Response to DR AG 3.11 Exhibit 1D, page 31
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
4
AG Ex. 1.32 Other Change Orders QIP Cost and Surcharge Adjustment 32
AG Ex. 1.33 CONF Nicor Gas Responses to DR AG 4.20 (Ex. 3 CONF and Ex. 4 CONF) 33
AG Ex. 1.34 CONF Nicor Gas Responses to DR AG 5.23 CONF (Ex. 1 CONF) 34
AG Ex. 1.35 CONF Nicor Gas Resp. DR MEM 1.02 (Ex. 13 App. B, p.4), AG 4.22, AG 5.25 35
AG Ex. 1.36 CONF Nicor Gas Resp. DR MEM 1.02 (Ex. 13 App. B, p.5), AG 4.23, AG 5.26 36
AG Ex. 1.37 CONF Nicor Gas Resp. DR MEM 1.02 (Ex. 13 App. B, p.8), AG 4.24, AG 5.27 37
AG Ex. 1.38 Bids Accepted Over Lower Bids QIP Cost and Surcharge Adjustment 38
AG Ex. 1.39 Nicor Gas Response to DR AG 5.06 39
AG Ex. 1.40 Nicor Gas Response to Data Request AG 23.25 from Docket No. 18-1775 40
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
5
I. INTRODUCTION 41
Q. PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. 42
A. My name is Sebastian Coppola. My business address is 5928 Southgate Rd., Rochester, 43
Michigan 48306. 44
Q. BY WHOM ARE YOU EMPLOYED AND IN WHAT CAPACITY? 45
A. I am President of Corporate Analytics, Inc., a business consulting firm specializing in 46
financial and strategic business issues in the fields of energy and utility regulation. 47
Q. PLEASE SUMMARIZE YOUR PROFESSIONAL QUALIFICATIONS. 48
A. I have more than forty years of experience in public utility and related energy work, both 49
as a consultant and utility company executive. I have been an independent consultant for 50
more than 15 years. Before that, I spent three years as Senior Vice President and Chief 51
Financial Officer of SEMCO Energy, Inc. with responsibility for all financial operations, 52
corporate development and strategic planning for the company’s Michigan and Alaska 53
regulated gas utility operations and non-regulated businesses. During the period at 54
SEMCO Energy, I also had responsibility for certain storage and pipeline operations as 55
President and COO of SEMCO Energy Ventures, Inc. Prior to SEMCO, I was Senior 56
Vice President of Finance for MCN Energy Group, Inc., the parent company of Michigan 57
Consolidated Gas Company. 58
During my 24-year career at MCN and MichCon, I held various analytical, accounting, 59
managerial and executive positions, including Manager of Gas Accounting with 60
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
6
responsibility for maintaining the accounting records and preparing financial reports for 61
gas purchases and gas production. Over the years, I also held the positions of Treasurer, 62
Director of Investor Relations, Director of Accounting Services, Manager of Corporate 63
Finance, and Manager of Customer Billing. Additionally, I have been responsible for and 64
have managed several new pipeline and construction projects, as well as the 65
implementation of information technology projects. 66
I have testified in several regulatory proceedings before various regulatory commissions. 67
I have prepared and/or filed testimony in general rate case proceedings, revenue 68
decoupling reconciliations, gas conservation programs, gas cost and power supply cost 69
recovery reconciliation mechanisms, and pipeline and meter infrastructure replacement 70
cases. 71
In recent years, I have filed testimony in several infrastructure replacement cases on 72
behalf of the Illinois Attorney General and the Citizens Utility Board before the Illinois 73
Commerce Commission (“the Commission” or “ICC”) pertaining to Peoples Gas and 74
Coke’s accelerate main replacement program and Rider QIP reconciliations. I also 75
submitted testimony in the last Nicor Gas rate case, ICC Docket 18-1775. 76
AG Exhibit 1.1 describes my regulated-energy qualifications in more detail and a list of 77
cases in which I have testified in different jurisdictions. 78
Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY IN THIS CASE? 79
A. On November 9, 2018, Northern Illinois Gas Company, d/b/a Nicor Gas Company, 80
(“Nicor Gas, or “Company”) filed a petition under Docket No. 19-0294 before the Illinois 81
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
7
Commerce Commission (“the Commission” or “ICC”) to initiate an annual reconciliation 82
proceeding, pursuant to Rider QIP of its Schedule of Rates for Gas Service (“Rider QIP”), 83
in order to determine the accuracy and the prudence of the qualifying infrastructure plant 84
investments for the calendar year 2018. 85
I have been asked by the Office of the Attorney General, on behalf of the People of the 86
State of Illinois (“AG”), to provide an independent analysis of the prudency and 87
reasonableness of the qualifying infrastructure costs incurred in 2018, and present related 88
recommendations for adjustments to costs, the Rider QIP Tariff, and management 89
practices. 90
Q. WHAT TOPICS ARE YOU ADDRESSING IN YOUR TESTIMONY? 91
A. My review is mainly limited to the larger QIP capital expenditures incurred by Nicor Gas 92
during 2018, and the processes and practices applied by the Company in planning and 93
completing the construction of various projects. 94
Specifically, I will address the following topics in this case: 95
1. Company witness Patrick Whiteside’s attestation about the reasonableness and 96
prudency of the 2018 QIP costs; 97
2. Cost disallowances related to certain projects with significant cost overruns, or 98
inadequate evidence to support the actual expenditures; 99
3. Cost disallowances related to imprudent approval of contractor change orders; 100
4. Acceptance of higher project bids above the lowest acceptable bid; 101
5. Poor project bidding practices; 102
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
8
6. Lack of contractor audits of billed costs and lack of transparency on contractors’ 103
work performance; and 104
7. Inclusion of non-qualified infrastructure plant projects within the Rider QIP 105
Tariff. 106
The absence of a discussion of other matters in my testimony should not be taken as an 107
indication that I agree with those aspects of Nicor Gas’s QIP filing. My testimony is, 108
instead, a consequence of focusing on priority issues within the resources available to me. 109
Other AG witnesses may identify other proposed disallowances that may be additive to the 110
recommendations made in this testimony. 111
Q. DO YOU HAVE ANY EXHIBITS SUPPORTING YOUR TESTIMONY? 112
A. Yes. I am sponsoring AG Exhibits 1.1 through 1.40. 113
Q. WHAT INFORMATION HAVE YOU RELIED UPON IN FORMULATING YOUR 114
RECOMMENDATIONS? 115
A. I have relied on Nicor Gas’s testimony, exhibits, and data request responses provided in 116
this docket. I have also relied on pertinent information from the Company’s last general 117
rate case in Docket No. 18-1775 and other select information from Nicor’s prior Rider 118
QIP reconciliation case filings. 119
In addition, I have read, and I am familiar with, the Rider QIP tariff filed by the Company 120
with the Commission, and Section 9-220.3 of the Public Utilities Act that authorized the 121
Commission to establish the Rider QIP tariff surcharge, including the transcript1 of the 122
1 Available at: https://www.icc.illinois.gov/downloads/public/edocket/366197.pdf (approved by ICC
January 7, 2014).
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
9
deliberations of the Illinois House of Representatives in passing legislation in May 2013 123
authorizing the establishment of the Rider QIP. 124
II. SUMMARY CONCLUSIONS AND RECOMMENDATIONS 125
Q. PLEASE SUMMARIZE YOUR CONCLUSIONS AND RECOMMENDATIONS. 126
A. Nicor Gas incurred several capital expenditures in 2018 which were not reasonable or 127
prudently incurred. The information provided by the Company also showed that project 128
management and cost control processes were deficient in various areas. 129
Therefore, I recommend that the Commission disallow the following capital expenditures 130
included in the calculation of the 2018 Rider QIP surcharge and direct the Company to 131
adjust future surcharges accordingly: 132
1. Remove $27.5 million of capital expenditures related to excessive costs 133
incurred over planned amounts for 11 major projects. As a result, the 134
Commission should order the Company to refund $1.8 million of Rider 135
QIP surcharges to customers. 136
2. Remove $8.0 million of capital expenditures for cost change orders 137
pertaining to imprudent decision by the Company. As a result, the 138
Commission should order the Company to refund approximately $353.000 139
of Rider QIP surcharges to customers. 140
3. Remove $5.2 million of capital expenditures pertaining to higher project 141
cost bids approved over lower acceptable bids received from contractors. 142
As a result, the Commission should order the Company to refund 143
approximately $271,000 of Rider QIP surcharges to customers. 144
In total, I recommend that the Commission disallow $40.7 million of 2018 capital 145
expenditures and reduce the Rider QIP surcharge by $2.5 million in this reconciliation 146
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
10
through the O Factor adjustment. In addition, I recommend that the Commission instruct 147
the Company to remove the disallowed capital expenditures from the calculation of future 148
Rider QIP surcharges and from the Company’s rate base when filing changes to its 149
distribution base rates in the next general rate case. 150
By removing the disallowed capital expenditures from rate base for imprudence, consumers 151
will not be required to pay the principal amount of capital expenditures, which in this case 152
is approximately $40.7 million. In addition, the Company forfeits the return on the 153
disallowed capital expenditures over the depreciable life of those capital additions. 154
Furthermore, the Commission should: 155
a. Direct the Company that in future Rider QIP reconciliations it will identify all 156
capital projects that were competitively bid, the bids considered and selected, 157
and if capital projects of at least $250,000 in value were not competitively bid 158
individually, or combined with other projects, explain and justify why not. 159
b. Direct the Company to perform annual audits of the amounts billed by any 160
contractor who bills the Company at least $5 million for work performed 161
during the annual QIP program. The absence of such audits in future Rider 162
QIP reconciliations should be considered a failure to attest as to the 163
reasonableness and prudency of the costs included in the QIP program. 164
c. Direct the Company to exclude gas storage related plant additions and 165
retirements from future Rider QIP plans and reconciliations. My conclusion is 166
that storage-related capital expenditures were never intended to be included in 167
the Rider QIP program and the Company has expanded the definition of 168
Qualifying Infrastructure Plant beyond its actual and intended purpose. 169
d. Direct the Company that in future Rider QIP reconciliation filings include 170
testimony and other exhibits to provide through explanations of (1) the major 171
projects completed during the Rider QIP reconciliation year; (2) any 172
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
11
significant variance of 10% or greater in the cost of the major projects 173
completed during the year in comparison to the plan filed with the 174
Commission; (3) QIP projects that had been planned for the year, but were 175
later deferred and not completed, as well as new projects added that were not 176
initially planned; (4) the number and amount of change orders affecting 177
capital expenditures for QIP projects and an explanation of the more 178
significant cost change orders exceeding $250,000; (5) how the Company 179
prioritized the projects for public safety and reliability; and (6) other useful 180
information that justify undertaking the QIP projects completed during the 181
reconciliation year. 182
The remainder of my testimony provides further details and support to these summary 183
conclusions and recommendations. 184
III. INFRASTRUCTURE COSTS INCURRED 185
Q. PLEASE BRIEFLY SUMMARIZE THE 2018 QIP RIDER RECONCILIATION 186
FILING MADE BY NICOR GAS. 187
A. Nicor Gas filed the testimony and exhibits of Matthew Kim and Patrick Whiteside to 188
provide an accounting of the infrastructure capital costs incurred in 2018 and explanations 189
of how in their opinion they conform to the Rider QIP statute and rate tariff. The Company 190
also filed affidavits and attestations required under the Rider QIP rate tariff. 191
According to the filing, in 2018 the Company incurred capital spending costs of 192
approximately $350.4 million net of retirements, disposal costs and deferred taxes, as 193
shown in Nicor Gas Ex. 1.1. The amount of gross plant additions, including cost of 194
removal and salvage value, for the 2018 Rider QIP was $372.9 million. Table 1 below 195
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
12
shows the capital expenditures and net recoverable investments requested by the Company 196
for 2018 by account and plant category. 197
198
Capital spending to replace Gas Distribution steel pipelines and copper/steel services with 199
new steel and plastic pipelines is the largest component at $211.3 million. Replacement of 200
Gas Transmission pipelines and related equipment is the second largest component of 201
spending in 2018 at $112.7 million. The third component of capital spending included by 202
Nicor Gas in the Rider QIP is for Gas Storage facilities in the amount of $49 million. Later 203
in my testimony, I will discuss the propriety of including capital expenditures for storage 204
facilities within the Rider QIP. 205
($000) Plant Net Plant
Additions 1 Retirements Other 2 Investment
352.00 - Storage Wells 532$ -$ (18)$ 514$
353.00 - Storage Lines (Gathering Lines) 37,924 (2,837) 323 35,410
354.00 - Storage Compressor Station Equipment (Compressors) 4,131 (10,092) 9,028 3,067
355.00 - Storage Measuring & Regulating Equipment 730 (8) (26) 696
356.00 - Storage Gas Conditioning 5,668 (730) 365 5,303
Total Storage 48,985$ (13,667)$ 9,672$ 44,990$
365.20 - Transmission Right of Way 31$ (405)$ 313$ (61)$
366.00 - Transmission Structure & Improvements - (245) 200 (45)
367.10 - Transmission Main - Steel 96,641 (3,085) (1,026) 92,530
369.00 - Transmission Stations - Reg. & Meas. Equip. 15,998 (2,811) 1,468 14,655
Total Transmission 112,670$ (6,546)$ 955$ 107,079$
374.00 - Distribution Right of Way 29$ -$ (1)$ 28$
376.10 - Distribution Main - Steel 50,154 (4,057) 847 46,944
376.20 - Distribution Main - Plastic 95,007 (1,176) (1,270) 92,561
376.30 - Distribution Main - Cast Iron 211 (215) 155 151
378.00 - Distribution Measuring & Reg. Equip. - Vaults 1,861 (131) 39 1,769
380.00 - Services 58,605 (6,639) 181 52,147
381.00 - Meters 1,449 (1,090) 947 1,306
382.00 - Meter Installations 1,495 (146) (113) 1,236
383.00 - Regulator Installations 2,466 (9) (235) 2,222
Total Distribution 211,277$ (13,463)$ 550$ 198,364$
Grand Total 372,932$ (33,676)$ 11,177$ 350,433$
Net QIP Investments - 13 month average Used for Surcharge Calculation 145,986$ 1 Includes cost of retirement and salvage value. 2 Includes depreciation, deferred taxes and other items.
Table 1 - Nicor Gas - 2018 Rider QIP Investments
Plant Account & Category
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
13
Based on the net 2018 Rider QIP plant investments of $350.4 million, the average cost base 206
on which the Company could earn a return was approximately $146 million, as shown on 207
page 9 of Nicor Gas Ex. 1.1, and also on line 1, column A, of page 1 of Nicor Gas Ex. 1.6. 208
The return on this cost base is $17.3 million as reported by the Company.2 209
AG witness Mary Selvaggio presents the impact of my adjustments to the 2018 recoverable 210
QIP costs in AG Ex. 2.1, along with other adjustments she has identified. 211
IV. NICOR GAS ATTESTATION OF PRUDENCY 212
Q. PLEASE PROVIDE YOUR ASSESSMENT OF THE ATTESTATION BY 213
COMPANY WITNESS WHITESIDE THAT THE RIDER QIP CAPITAL 214
EXPENDITURES WERE PRUDENTLY INCURRED. 215
A. On page 1 of his direct testimony. Mr. Whiteside states that he is responsible for the 216
Company’s top line growth and for the customer development teams focused on improving 217
gas utilization and streamlining customer additions to the Nicor Gas system. Additionally, 218
he stated that he is responsible for leading the Company’s planning and execution of 219
investment in qualifying infrastructure plant, workforce development, strategic capital asset 220
portfolio design, strategic operational projects and the energy efficiency program.3 221
On page 2 of his direct testimony, he “conclude[s] that the costs of the Rider QIP 222
infrastructure investments for the 2018 reconciliation period were prudently incurred.” 223
2 Nicor Gas Ex. 1.6, page 1.
3 Nicor Gas Ex. 2.0, page 1.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
14
In the subsequent pages of his seven pages of direct testimony, Mr. Whiteside provides a 224
summary of the categories of qualifying plant additions allowed under the Rider QIP tariff, 225
plus a summary of the number of units installed or replaced, and a summary statement on 226
the prioritization approach taken to select projects for the Rider QIP program. The rest of 227
his testimony addresses the number of jobs attributable to the Rider QIP program. 228
Nowhere in his testimony does Mr. Whiteside explain what direct involvement he has with 229
the Rider QIP program or on what basis he can attest that the costs incurred in 2018 were 230
reasonable and prudently incurred. In fact, in response to a data request, the Company 231
shows that Mr. Whiteside is not a member of the Project Management Group responsible to 232
manage and direct the execution of the QIP projects. 233
His involvement with the QIP program appears to be so significantly removed from the 234
operation of the program that it renders his attestation of the prudency and reasonableness 235
of the costs incurred in 2018 meaningless. Therefore, I recommend that the Commission 236
disregard the attestation by Mr. Whiteside that all the QIP costs incurred by the Company 237
were reasonable or prudently incurred. Instead, based on my testimony, the Commission 238
should find that certain costs were not prudently incurred and should be removed from the 239
recoverable base on which the Rider QIP surcharges during 2018 were calculated. 240
V. ASSESSMENT OF THE 2018 RIDER QIP RECONCILIATION 241
Q. PLEASE PROVIDE YOUR OVERALL ASSESSMENT OF THE PRUDENCY AND 242
REASONABLENESS OF THE COSTS INCLUDED IN THE 2018 RIDER QIP 243
RECONCILIATION. 244
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
15
A. In 2018, the Company continued to significantly ramp up its QIP capital expenditures, 245
taking advantage of the cost recovery mechanism permitted by the enactment of the Rider 246
QIP beginning in 2014. As stated earlier, the Company spent approximately $372.9 million 247
on QIP projects in 2018. In comparison, in 2017 it spent $327.2 million. Although the 248
capital spending increased in 2018, the number of miles of pipe replaced decreased. In 249
2017, the Company replaced 84 miles of vintage plastic, vintage steel and bare steel 250
pipelines. In 2018, the number of miles of pipe replaced declined to 70 miles.4 251
Similarly, Nicor Gas replaced 15,847 service lines in 2018, which was a lower number than 252
the 16,346 services replaced in 2017.5 Therefore, with regard to gas distribution projects, 253
the increase in capital spending from 2017 to 2018 does not track with the number of miles 254
of mains and services replaced. 255
It is also concerning that the Company had planned to replace 106 miles of vintage plastic, 256
vintage steel, and bare steel pipe in 2018. However, it actually replaced only 70 miles, or 257
66% of the planned miles, while still increasing 2018 capital expenditures over the prior 258
year. AG Exhibit 1.2 includes the Company’s responses to data request AG 1.07 (Docket 259
No. 18-1775), AG 3.01 and AG 5.01 showing this information. 260
In my review of the Company’s capital expenditures on various QIP projects, I have 261
identified several issues with the level of capital spending, cost change order requests, poor 262
bidding acceptance practices, and other problems with the Company’s actions and practices. 263
4 In Nicor Gas Ex. 2.2 in Docket Nos. 19-0294 and 18-0621, the Company reports 161.2 miles of vintage
and bare steel main replaced/installed in 2018 and 139.3 miles in 2017. Although the number of miles
installed can differ somewhat from the miles retired, it is not clear why these quantities differ significantly
from the Company’s response to data requests AG 1.07 (Docket No. 18-1775) and AG 5.01 included in AG
Ex. 1.2. 5 Nicor Gas Ex. 2.2 in Docket Nos. 19-0294 and 18-0621.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
16
These occurrences warrant several cost disallowances from the amount of capital 264
expenditures and related costs that the Company seeks to recover in this reconciliation case. 265
In the following pages of my testimony, I describe the most egregious cases and identify 266
recommended cost disallowances and adjustments to the Rider QIP surcharge billings. 267
Table 2 below identifies my summary assessment of the capital expenditures that should be 268
disallowed for 2018 and the related adjustments to the surcharge billings. 269
270
In total, I have identified approximately $40.7 million of capital expenditure disallowances 271
in the reconciliation of the 2018 Rider QIP. Approximately $27.5 million relate to large 272
cost variances between planned costs and actual costs for 11 construction projects. An 273
additional $8 million of disallowed capital expenditures pertains to change orders where 274
imprudent decisions were made by the Company. The other $5.2 million of capital 275
disallowances pertain to projects where the Company accepted higher cost bids than the 276
lower acceptable bid from contractors. 277
Capital Surcharge
Expenditures Revenue
Large Cost Variance Projects 27,489,988$ 1,836,372$
Project Change Orders 7,995,208 353,090
Bid Amounts Over Lowest Bid 5,219,618 270,707
Total Disallowance 40,704,814$ 2,460,169$
1 Source: AG Witness Coppola Testimony and Exhibits.
Table 2
2018 Nicor Gas Rider QIP Disallowances 1
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
17
The proposed disallowances for each of these categories are explained in the following 278
pages of my testimony. 279
VI. PROJECTS WITH LARGE COST VARIANCES 280
Q. PLEASE EXPLAIN YOUR FINDINGS FROM REVIEWING MAJOR PROJECTS 281
WITH LARGE COST VARIANCES. 282
A. In discovery, the Company was asked to provide a reconciliation of the projects and costs 283
proposed in the 2018 QIP plan update, filed with the Commission under Section J of the 284
Rider 32 QIP tariff, against the actual costs incurred for the projects completed in 2018. 285
The Company also was asked to provide a comparison of actual costs incurred and units 286
installed in 2018 versus prior years for major project categories. 287
In response to several data requests, the Company provided a report of 189 major projects 288
with planned costs, actual costs, cost variances, units planned and installed, and 289
explanations for cost variances. AG Exhibit 1.3 CONF includes a copy of the report 290
provided in response to data request AG 5.16 along with the confidential exhibit. 291
The 189 major projects planned for 2018 had a total projected cost of $338.9 million. 292
During the year, the Company decided to defer 28 projects to future years. The capital cost 293
of these projects totals $32.7 million. Thus, the remaining 161 projects completed in 2018 294
had a total projected cost of $306.2 million. In comparison, the Company incurred actual 295
capital expenditures of $359.5 million for the remaining 161 projects. Therefore, actual 296
costs for the 161 projects exceeded the projected cost by $53.3 million, an overall variance 297
of 17% over the projected cost. 298
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
18
Q. DID YOU IDENTIFY LARGE VARIANCES BETWEEN PLANNED AND ACTUAL 299
EXPENDITURES IN CERTAIN PROJECTS THAT RAISE CONCERNS ABOUT 300
THE REASONABLENESS AND PRUDENCY OF THE COST INCURRED FOR 301
THOSE PROJECTS? 302
A. Yes. Of the 161 projects completed in 2018, 134 had variances of 10% or greater. Of the 303
134 projects with variances of 10% or greater, 78 had positive variances (actual costs above 304
planned costs) with 39 of them having variances of greater than 50% above the planned cost 305
amount. The remaining 56 projects of the 134 projects with variances of 10% or greater had 306
negative variances of varying degrees with some exceeding 50%. AG Exhibit 1.3 CONF 307
provides the full list of projects and related cost variances. 308
The explanations provided by the Company for the larger variances are generally attributed 309
to project estimates not being final when the QIP plan was developed. The Company also 310
attributes the increase in costs to higher installation and restoration costs, permit delays, 311
difficult ground conditions, prior year carryover costs, etc. The large variances raise 312
concerns about the adequacy of the Company’s project planning practices, the accuracy of 313
forecasted costs provided to the Commission, and the adequacy of project management cost 314
controls. 315
Based on my review of the information provided by the Company, I have identified 11 316
projects where the explanations and justifications are inadequate or not credible, and a 317
disallowance of a portion of the project actual capital expenditures is warranted. The total 318
capital expenditures disallowance amount for the 11 projects is $27.5 million. The Rider 319
QIP surcharge adjustment refundable to customer from the capital expenditures 320
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
19
disallowance is $1.8 million. I will discuss each of the disallowances in my testimony 321
below. 322
A. Copper Services 323
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 324
EXPENDITURES FOR COPPER SERVICES. 325
A. In response to data request AG 4.10, the Company provided the actual cost incurred to 326
complete replacement of 4,630 copper services during 2018 at $23,015,860, or $4,971 per 327
service line. In the plan filed with the Commission, the Company had projected that it 328
would replace 5,500 services in 2018 at a cost of $20,139,000, or cost per unit of $3,662. 329
The Company spent approximately $2.9 million more to replace 870 fewer services at a 330
higher unit cost. 331
The information provided by the Company in response to Staff data request MEM 1.03 332
(Exhibit 1) shows that the unit cost to replace copper service in 2017 was $3,557 and in 333
2016 it was $2,182. In discovery, the Company was asked to explain the cost increase 334
experienced in 2018 over prior years. In response to data request AG 4.10(b), the Company 335
stated that the cost increase was due to completion of more copper service replacements by 336
outside contractor crews than by Company crews. 337
Asked to explain why copper service line replacement costs by contractor crews is more 338
costly than using Company employees, the Company stated that contractor crew sizes are 339
larger than Company crews. The Company also provided service line installation cost data 340
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
20
that shows Company crews are able to complete an average service line installation for 341
$3,026, while the contractor charges $7,246, or 2.4 times more. 342
The Company was also asked to explain why it did not hire and use more employees to 343
perform service line replacement given the large cost difference. In response, the Company 344
stated that it had limited internal resources to replace copper services, and in an effort to 345
replace copper service by the end of 2019 additional outside resources were required. 346
Instead of hiring additional full-time employees for work that was not sustainable, the 347
Company decided to utilize resources. Although on the surface these reasons appear 348
plausible, they are not credible when reviewing the Company’s practices in prior years. 349
In 2018, Company employees replaced 54% of the total copper services replaced that year. 350
In 2017, they replaced 71% of all copper service replaced that year. The percentage 351
replaced by Company employees reached 88% in 2016. While in 2015, only 59% of the 352
copper services were replaced by Company employees. Therefore, the Company had 353
staffed for and dedicated more Company crews to complete copper service line 354
replacements in 2016 and 2017, and could have kept those internal crews into 2018 to 355
complete more copper service replacements at a much lower cost. 356
AG Exhibit 1.4 and 1.6 include the information provided by the Company in response to 357
several data requests discussed above. 358
Q. DID THE COMPANY BID OUT THE SPECIFIC SERVICE LINE REPLACEMENT 359
PROJECTS TO MULTIPLE CONTRACTORS TO ENSURE THE WORK WAS 360
COMPLETED AT THE LOWEST COMPETITIVE COST? 361
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
21
A. No. It does not appear that the Company competitively bid out the specific projects either 362
as a total group or by sub-groups in specific areas to multiple contractors in order to 363
determine that the work would be completed at the lowest cost within the applicable 364
standards. In response to a data request, the Company stated that it performs service line 365
replacement under blanket contracts which are not bid out annually.6 The lack of 366
competitive bids likely was a contributing factor to the excessive cost billed by the 367
contractors above the cost per service line incurred through installations by Company 368
employees. Later in my testimony, I will discuss in more detail my concerns with the 369
Company’s contractor work bidding practices. 370
Q. DID YOU CALCULATE THE INCREMENTAL AVOIDABLE COST OF USING 371
MORE COMPANY CREWS INSTEAD OF CONTRACTOR CREWS TO 372
COMPLETE THE COPPER SERVICE LINE REPLACEMENTS IN 2018? 373
A. Yes. I have determined that if the Company had maintained the same average mix of 374
service line replacement with Company crews as it did in 2017 and 2016, it could have 375
reduced capital expenditures in 2018 by approximately $9.7 million. 376
I determined this amount by taking the average cost to replace copper services in 2017 and 377
2016 of $2,870 per service line7 and multiplied it by the 4,630 services completed in 2018 in 378
order to calculate a total cost of $13.3 million. The difference between the $13.3 million 379
and the actual cost of $23.0 million incurred by the Company in 2018 is $9.7 million. This 380
6 Nicor Gas response to DR AG 5.06 included in AG Ex. 1.39 7 In response to data request Staff MEM 1.03 Exhibit 1, the Company reported that it installed 7,232 copper
services at a cost of $25,727,021, or $3,557 per service. It also reported that in 2016 it installed 10,032
copper services at a cost of 21,894,501, or $2,182 per service. The average cost for the two years is $2,870
per copper service installed. AG Exhibit 1.4 includes this information.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
22
incremental cost is not reasonable and was not prudently incurred. Therefore, I recommend 381
that the Commission remove $9.7 million from the 2018 QIP capital investments. 382
Assuming the capital expenditures were incurred evenly throughout 2018, the adjustment to 383
the QIP surcharge is $718,301, as calculated in AG Exhibit 1.5 using the Company financial 384
model shown in Nicor Gas Ex. 1.1. 385
B. Norridge-Chicago #119620 Cast Iron Main Replacement 386
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 387
EXPENDITURES FOR THE NORRIDGE-CHICAGO CAST IRON MAIN 388
REPLACEMENT. 389
A. In data request AG 4.25, the Company was asked to explain why it spent $6.7 million to 390
retire and replace 1.4 miles of cast iron main in 2018 at a cost of $4.8 million per mile, when 391
in 2017 and 2016 it spent $968,000 and $809,000 per mile, respectively. In its initial 392
response, the Company stated that the main drivers for the cost increase per mile were 393
carryover costs for landscape and paving from the prior year with no associated miles of 394
pipe replaced in 2018. In addition, the Company stated that the last 1.4 miles of cast iron 395
main replaced in the Norridge-Chicago area involved road openings and tight city 396
coordination, which increased the average cost per mile. 397
In a follow up data request, the Company was asked to explain in more detail the amount of 398
carryover costs, the categories of costs where the higher costs were incurred and specifically 399
why. In response to data request AG 5.28, the Company stated that carryover costs were 400
$1.6 million of the $6.7 million, leaving still $5.1 million of costs in 2018 for 1.4 miles of 401
main. The Company also explained that the Norridge-Chicago main replacement required 402
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
23
$1.5 million in incremental landscaping and paving costs due to City of Chicago permit 403
requirements. After adjusting for this incremental cost, the remaining amount is $3.6 404
million. AG Exhibit 1.6 includes the Company response to data requests AG 4.25 and AG 405
5.28. 406
If we use the cost per mile of cast iron main replaced in 2017 of $968,000 and multiply it by 407
the 1.4 miles replaced in 2018, the expected cost is approximately $1.4 million. Comparing 408
this amount to the $3.6 million of remaining costs from the actual amount spent in 2018 409
leaves $2.2 million of costs incurred in 2018 that the Company has not justified. 410
It is also noteworthy to point out that in the QIP plan filed with the Commission, the 411
Company has projected that it would incur $4.9 million in 2018 to complete this project, 412
including carryover costs. Actual costs exceeded this amount by more than $1.8 million. 413
This is a further indication that the $2.2 million of incremental costs incurred in 2018 for 414
this project are not reasonable, and do not appear to have been prudently incurred. 415
Therefore, I recommend that the Commission remove $2.2 million from the 2018 Rider QIP 416
capital expenditures. Assuming the capital expenditures were incurred evenly throughout 417
2018, the adjustment to the QIP surcharge is $115,331, as calculated in AG Exhibit 1.7 418
using the Company financial model. 419
C. Franklin Park #119662 Main Replacement 420
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 421
EXPENDITURES FOR THE FRANKLIN PARK MAIN REPLACEMENT 422
PROJECT. 423
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
24
A. On line 34 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 424
reported that it planned to retire and replace 8,287 feet of steel main at a cumulative cost of 425
[BEGIN CONFIDENTIAL] 426
427
428
429
. [END CONFIDENTIAL] 430
Although the installation of additional feet of pipe explains part of the increase in cost, it 431
does not explain the entire increase. Using the planned cost of [BEGIN CONFIDENTIAL] 432
433
. [END CONFIDENTIAL] This leaves $684,739 of higher actual costs due to 434
other reasons. In Exhibit 1 CONF to DR AG 5.16, the Company explained that the 435
additional increase in costs was due to higher restoration costs due to permit delays which 436
required the Company to temporarily backfill and restore areas, and later return to redo 437
some of this work.8 438
Having timely permits is a basic task of scheduling work so that work can be completed in 439
the most cost-efficient manner. It is the responsibility of the Company to ensure it has the 440
necessary work permits to complete the work timely and without the need to redo the same 441
work and incur additional costs. Customers should not pay for imprudently incurred costs. 442
Therefore, I recommend that the Commission remove the $684,739 of higher costs incurred 443
by the Company for this project from the total 2018 QIP capital expenditures. Assuming 444
8 See line 34 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
25
that this incremental cost was incurred evenly throughout the year, the applicable reduction 445
in billed Rider QIP surcharge is $35,888, as calculated in AG Exhibit 1.8 using the 446
Company financial model. 447
D. Glenview #120043 Main Replacement 448
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 449
EXPENDITURES FOR THE GLENVIEW MAIN REPLACEMENT PROJECT. 450
A. On line 36 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 451
reported that it planned to retire and replace 9,462 feet of steel main at a cost of [BEGIN 452
CONFIDENTIAL] 453
454
455
. 456
[END CONFIDENTIAL] 457
The only explanation provided by the Company was that the main installation and 458
restoration costs were higher than the QIP plan.9 This explanation is inadequate and 459
provides no evidence to justify the significant increase in actual cost over the planned 460
amount. Using the planned cost per mile of [BEGIN CONFIDENTIAL] 461
. [END CONFIDENTIAL] The 462
remaining amount of $1,456,186 is unsupported and unjustified. I recommend that the 463
Commission remove this amount from the total 2018 QIP capital expenditures. Assuming 464
9 See line 36 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
26
that this incremental cost was incurred evenly throughout the year, the applicable reduction 465
in billed Rider QIP surcharge is $76,332, as calculated in AG Exhibit 1.9 using the 466
Company financial model. 467
E. Oak Lawn #120058 Main Replacement 468
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 469
EXPENDITURES FOR THE OAK LAWN MAIN REPLACEMENT PROJECT. 470
A. On line 58 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 471
reported that it planned to retire and replace 25,675 feet of steel main at a cost of [BEGIN 472
CONFIDENTIAL] 473
474
475
476
[END CONFIDENTIAL] 477
Although the installation of additional feet of pipe explains part of the increase in cost, it 478
does not explain the entire increase. Using the planned cost of [BEGIN CONFIDENTIAL] 479
480
[END CONFIDENTIAL] This leaves $1,514,406 of higher actual costs due to 481
other reasons. In Exhibit 1 CONF to DR AG 5.16, the Company explained that facilities of 482
other utilities encountered in the right of way increased the difficulty of the pipe installation 483
and increased costs.10 484
10 See line 58 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
27
Performing appropriate due diligence upfront about the conditions of the project, including 485
other utilities’ facilities in the common right-of-way, is a basic step at the time the project is 486
designed and before it is let out for construction work to begin. Also, providing all pertinent 487
information in the request for cost bids allows the contractors to provide accurate cost 488
proposals so the Company can properly select the lowest cost bid that meets all other 489
applicable requirements. This avoids subsequent project cost change orders that increase 490
the cost of the project without an appropriate competitive bidding process. 491
From the information provided by the Company, it appears that it did not do sufficient 492
research and due diligence work up-front to establish the true cost of the project. 493
Information about the location of facilities installed by other utilities in the common right-494
of-way should have been readily available to the Company at the time the project was 495
designed by working collaboratively with the city and other utilities. The failure to 496
determine the existence of those facilities and any additional difficulties that would be 497
encountered in the installation of the main rises to the level of imprudence on the part of the 498
Company. The lack of proper planning for the project should not be rewarded by allowing 499
the Company to recover the large incremental costs incurred for this project. 500
Therefore, I recommend that the Commission remove the $1,514,406 of higher costs 501
incurred by the Company for this project from the total 2018 QIP capital expenditures. 502
Assuming that this incremental cost was incurred evenly throughout the year, the applicable 503
reduction in billed Rider QIP surcharge is $79,392, as calculated in AG Exhibit 1.10 using 504
the Company financial model. 505
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
28
F. Princeton #128621 Main Replacement 506
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 507
EXPENDITURES FOR THE PRINCETON MAIN REPLACEMENT PROJECT. 508
A. On line 70 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 509
reported that it planned to retire and replace 11,903 feet of steel main for a cost of [BEGIN 510
CONFIDENTIAL] 511
512
0 513
514
[END CONFIDENTIAL] 515
The only explanation that the Company provided to justify this cost increase was that the 516
main installation and retirement costs were higher than the QIP plan.11 This explanation is 517
inadequate and provides no evidence to justify the significant increase in actual cost over the 518
planned amount. Given that the 10,289 feet of new pipe actually installed was lower than 519
the 11,903 feet planned, the entire amount of cost variance of $637,393 between the actual 520
and planned amounts is unsupported and unjustified. 521
I recommend that the Commission remove this amount from the total 2018 QIP capital 522
expenditures. Assuming that this incremental cost of $637,393 was incurred evenly 523
throughout the year, the applicable reduction in billed Rider QIP surcharge is $33,401, as 524
calculated in AG Exhibit 1.11 using the Company financial model. 525
11 See line 70 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
29
G. Landscaping and Paving Carryover Costs 526
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 527
EXPENDITURES FOR CARRYOVER LANDSCAPING AND PAVING COSTS 528
PERTAINING TO PRIOR YEAR MAIN REPLACEMENT PROJECTS. 529
A. On line 112 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 530
reported that it planned to incur [BEGIN CONFIDENTIAL] [END 531
CONFIDENTIAL] during 2018 for landscaping, paving and retirement costs pertaining to 532
various projects completed or undertaken in the prior year. The Company also reported that 533
the actual carryover costs incurred during 2018 were [BEGIN CONFIDENTIAL] 534
[END 535
CONFIDENTIAL] 536
The only explanation that the Company provided was that carryover costs for restoration 537
and retirement were higher than the QIP plan.12 This explanation states the obvious and is 538
inadequate. It provides no evidence to justify the significant increase in actual costs over 539
the planned amount. I recommend that the Commission remove the unexplained and 540
unjustified cost variance of $3,016,258 from the total 2018 QIP capital expenditures. 541
Assuming that this incremental cost was incurred evenly throughout the year, the applicable 542
reduction in billed Rider QIP surcharge is $158,125, as calculated in AG Exhibit 1.12 using 543
the Company financial model. 544
12 See line 112 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
30
H. Carpentersville #128737 Main Replacement 545
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 546
EXPENDITURES FOR THE CARPENTERSVILLE MAIN REPLACEMENT 547
PROJECT. 548
A. On line 119 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 549
reported that it planned to retire and replace 2,810 feet of main at a cost of [BEGIN 550
CONFIDENTIAL] 551
552
r 553
554
[END CONFIDENTIAL] 555
The only explanation that the Company provided was that the main installation and 556
retirement costs were higher than the QIP plan.13 This explanation states the obvious and is 557
inadequate. It provides no evidence to justify the significant increase in actual costs over 558
the planned amount. Although the installation of additional feet of pipe explains part of the 559
increase in cost, it does not explain the entire increase. Using the planned cost of [BEGIN 560
CONFIDENTIAL] 561
. [END CONFIDENTIAL] This leaves $859,889 of actual costs 562
due to other reasons, which the Company has not identified, explained, or justified. 563
13 See line 119 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
31
Therefore, I recommend that the Commission remove this amount from the total 2018 QIP 564
capital expenditures. Assuming that this incremental cost was incurred evenly throughout 565
the year, the applicable reduction in billed Rider QIP surcharge is $45,081, as calculated in 566
AG Exhibit 1.13 using the Company financial model. 567
I. Norridge Cast Iron Services Replacement 568
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 569
EXPENDITURES FOR THE NORRIDGE CAST IRON SERVICES 570
REPLACEMENT PROJECT. 571
A. On line 123 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 572
reported that it planned to retire and replace 285 cast iron services at a cost of [BEGIN 573
CONFIDENTIAL] 574
575
576
. 577
[END CONFIDENTIAL] 578
The first explanation for the higher cost provided by the Company was that 150 of the 579
services were located under pavement which increased the replacement unit cost for those 580
services.14 In a subsequent response to a follow up data request, the Company explained 581
that when replacing the cast iron services in the City of Chicago – Norridge area all long 582
14 See the response to data request AG 4.10(b), second bulleted item, included in AG Ex. 1.4.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
32
side services had to be open cut as part of the permit requirements. Outside the City of 583
Chicago, the Company replaces service lines by directional boring, not open cut.15 584
Performing appropriate due diligence upfront about the conditions of the project, including 585
determining the site conditions of services being located under pavement, as well as the 586
permit requirements of the City of Chicago about replacement of service lines by open cut, 587
are basic steps that should be taken and understood at the time the project is designed and 588
before it is let out for construction work to begin. 589
Additionally, providing all pertinent information in the request for cost bids allows the 590
contractors to provide accurate cost proposals from which the Company can select the 591
lowest cost bid that meets all other applicable requirements. This avoids subsequent project 592
cost change orders that increase the cost of the project without an appropriate competitive 593
bidding process. 594
From the information provided by the Company, it appears that it did not do sufficient 595
research and due diligence work up-front to establish the basic requirements and true cost of 596
the project. Information about the placement of the services below pavement can be 597
readily determined by performing a site visit to the project before or during the design 598
phase. The Company knows the location of its services because it must mark those 599
locations under the JULIE system before customers and other contractors undertake 600
construction work near those service lines. Also, with a portion of its service area in the 601
15 See the response to data request AG 5.15(g) included in AG Ex. 1.4.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
33
City of Chicago, the Company knows, or should know, what the permitting requirements are 602
for replacing service lines in the city. 603
The failure to determine the existence of those requirements and difficulties during the 604
design phase of the project rises to the level of imprudence on the part of the Company. The 605
lack of proper planning for the project should not be rewarded by allowing the Company to 606
recover the large incremental costs incurred for this project. 607
Given that the 252 services actually installed were lower than the 285 services planned, the 608
entire amount of cost variance of $453,376 between the actual and planned amount should 609
be removed as unreasonable and imprudently incurred. I recommend that the Commission 610
remove this amount from the total 2018 QIP capital expenditures. Assuming that this 611
incremental cost was incurred evenly throughout the year, the applicable reduction in billed 612
Rider QIP surcharge is $33,569, as calculated in AG Exhibit 1.14 using the Company 613
financial model. 614
J. Ancona Storage Field Gathering Lines (“SFGL”) Replacement 615
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 616
EXPENDITURES FOR THE ANCONA LINE D AND C STORAGE FIELD 617
GATHERING LINES REPLACEMENT PROJECTS. 618
A. On lines 147 and 148 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the 619
Company reported that in 2018 it planned to replace 475 feet of the Ancona “D” line 620
gathering system at a cost of [BEGIN CONFIDENTIAL] 621
622
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
34
623
624
625
. [END 626
CONFIDENTIAL] 627
In its initial explanation the Company stated that the higher cost was attributed to 628
unforeseen site conditions that required more pipe to be installed than had been planned.16 629
In a subsequent response to a follow up data request, the Company explained that the 630
original design and construction plan was to open cut the two 16” gathering lines crossing 631
the Moon Creek. As the projects moved into the construction phase, the Company 632
determined that it would not be possible to properly and safely control the volume of water 633
present in the Moon Creek. Instead, the Company decided to utilize directional drilling to 634
cross the creek with new lines. According to the Company, due to the close proximity of 635
the Moon Creek to IL Route 17, the contour of the land, and the deflection of the pipe, the 636
directional drilling required more pipe than planned with the original open cut approach.17 637
Q. WHAT IS YOUR ASSESSMENT OF THE PROJECT PLANNING WORK AND 638
THE RESULTING INCREASE IN PROJECT COSTS. 639
A. There are at least four main issues that arise from the Company’s explanations about the 640
reason for the tripling in the actual costs to $9.3 million for these two projects from the 641
planned amount of $3.2 million. First, it is difficult to understand why the Company would 642
16 See the response to data request AG 4.10(b), page 2, fifth bulleted item from the top of the page, included
in AG Ex. 1.4. 17 See the response to data request AG 5.15(h) included in AG Ex. 1.4.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
35
plan to open cut a trench across a creek with a significant running water stream. Diverting 643
the water stream, in order to cut a trench to remove the old pipe and then install new pipe 644
over a period of multiple weeks is not an easy task. Additionally, when cutting an open 645
trench, there is the risk of environmental damage to the creek bed and contamination of the 646
water stream. From my experience working at two gas utilities and reviewing dozens of 647
construction projects proposed by other utilities in several rate cases, utilities perform such 648
crossings usually through directional drilling under the creek or river bed to avoid the 649
problems described above. 650
Second, installation of a 16” pipeline through directional drilling under a river bed can be a 651
lower cost option than cutting an open trench given the challenges and risks discussed 652
above. The Company has often stated this lower cost preference for directional drilling with 653
other pipeline projects. It is difficult to understand why replacing the pipelines through an 654
open cut trench would have been the preferred option with this project. 655
Third, it is also difficult to understand why directional drilling would require between four 656
and five times more pipe than the open trench approach. Unless the Company was making 657
some wide loops of nearly a half mile past the original pipeline crossing area, the increase in 658
the number of feet of pipe from 475 to 2,031 for the D Line and from 528 to 2,609 feet for 659
the C line seems exceptionally high and likely unnecessary. 660
Fourth, this is another case where a simple site inspection and critical assessment of the two 661
projects up-front should have led to the reasonable conclusion that crossing the creek and 662
replacing the existing pipelines through an open cut trench would not be a workable option. 663
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
36
In conclusion, it seems clear that the Company did not plan the project in a reasonable and 664
prudent manner. The result was a tripling of the cost of the project for an incremental 665
amount of $6,101,804. The lack of proper planning should not be rewarded by allowing the 666
Company to recover the large incremental costs incurred for the two projects. 667
Therefore, I recommend that the Commission remove the $6,101,804 from the total 2018 668
QIP capital expenditures. Assuming that this incremental cost was incurred evenly 669
throughout the year, the applicable reduction in billed Rider QIP surcharge is $488,979, as 670
calculated in AG Exhibit 1.15 using the Company financial model. 671
K. Horizon Station 125 Odorizer Replacement 672
Q. PLEASE EXPLAIN YOUR FINDINGS AND DISALLOWANCE OF CAPITAL 673
EXPENDITURES FOR THE HORIZON STATION ODORIZER REPLACEMENT 674
PROJECT. 675
A. On line 169 of Exhibit 1 CONF to data request AG 5.16 (AG Ex. 1.3 CONF), the Company 676
reported that it planned to replace the odorizer equipment at the Horizon station at a cost of 677
[BEGIN CONFIDENTIAL] 678
[END CONFIDENTIAL] 679
which is an increase of $865,937 or 156.2% over the planned amount. 680
The only explanation that the Company provided was that the construction costs were 681
higher than the QIP plan.18 This explanation states the obvious and is inadequate. It 682
18 See line 169 of Exhibit 1 CONF to the response to data request AG 5.16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
37
provides no evidence to justify the significant increase in actual costs over the planned 683
amount. This leaves the $865,937 cost variance unexplained and unjustified. 684
Therefore, I recommend that the Commission remove this amount from the total 2018 QIP 685
capital expenditures. Assuming that this incremental cost was incurred evenly throughout 686
the year, the applicable reduction in billed Rider QIP surcharge is $51,973, as calculated in 687
AG Exhibit 1.16 using the Company financial model. 688
L. Summary 689
Q. PLEASE SUMMARIZE THE QIP CAPITAL EXPENDITURES AND RIDER QIP 690
SURCHARGE REVENUE ADJUSTMENTS THAT YOU RECOMMEND. 691
A. The following table summarizes the capital expenditure amounts that I recommend the 692
Commission should remove from the 2018 QIP capital expenditures for the Projects with 693
Large Variances, and the related surcharge revenue that should be refunded to customers for 694
the 2018 Rider QIP reconciliation. 695
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
38
696
In total for this group of projects, I recommend that the Commission remove $27.5 million 697
of capital expenditures from the amount proposed by the Company, and order the Company 698
to refund $1.8 million of excess Rider QIP surcharges billed to customers. 699
VII. PROJECT CHANGE ORDERS 700
Q. PLEASE DESCRIBE WHAT ISSUES YOU DISCOVERED IN YOUR REVIEW OF 701
THE PROJECT COST CHANGE ORDER DOCUMENTS PROVIDED BY NICOR 702
GAS. 703
Capital Surcharge
Expenditures Revenue
Copper Services Replacement 9,700,000$ 718,301$
Norridge Main Replacement Project 2,200,000 115,331
Franklin Park Main Replacement 684,739 35,888
Glenview Main Replacement 1,456,186 76,332
Oak Lawn Main Replacement 1,514,406 79,392
Princeton Main Replacement 637,393 33,401
Landscaping and Paving Carryover Costs 3,016,258 158,125
Carpentersville Main Replacement 859,889 45,081
Norridge Services Replacement 453,376$ 33,569$
Ancona Storage Field Gathering Lines Replacement 6,101,804$ 488,979$
Horizon Station Odorizer Replacement 865,937$ 51,973$
Total Disallowance 27,489,988$ 1,836,372$
1 Source: AG exhibits.
Table 3
2018 Large Cost Variance Projects - Disallowances 1
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
39
A. In response to data request AG 3.11, the Company provided several documents pertaining 704
to approximately 60 change orders entered into between Nicor Gas and its construction 705
contractors for QIP projects completed during 2018.19 In my review of the change orders 706
provided by the Company, I discovered 12 situations where the change order was the result 707
of an imprudent action or decision by Nicor Gas which unnecessarily increased the 708
construction cost of the project. The total incremental construction cost from these 12 709
change orders is $7,995,208. These costs were imprudently incurred and should be 710
removed from the QIP capital expenditures included by the Company in this reconciliation 711
case. 712
Five of the change orders pertain to Railway Right-of-Way (“ROW”) approval issues. The 713
remaining seven change orders are for other specific projects. 714
A. Railway ROW Approval Issues 715
Q. PLEASE DESCRIBE THE RAILWAY ROW ISSUES THAT YOU DISCOVERED 716
IN YOUR REVIEW OF THE CHANGE ORDERS. 717
A. In my review, I discovered five change orders where contractors encountered difficulties in 718
completing the project as initially agreed with Nicor Gas. The difficulties arose from the 719
contractor’s inability to complete the work in a railway ROW. In each of these cases, the 720
contractors requested a project cost increase allowance through a change order, which the 721
Company approved. The total incremental cost of the five change orders included in 2018 722
QIP capital expenditures is $5,556,274. I will describe each of them separately. 723
19 AG Ex. 1.17.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
40
1. Aux Sable Phase 6 – Project 143642, Change Order 17, Dated 4/12/18: 724
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 725
of [BEGIN CONFIDENTIAL] 726
727
728
729
[END CONFIDENTIAL]. The 730
full text of the change order and cost is included in AG Ex. 1.18 CONF. The Company 731
approved the change order on April 17, 2018. According to the Company’s response to 732
data request AG 5.04, the actual incremental cost due to the change order included in 2018 733
QIP capital expenditures was $1,639,278.20 734
2. Aux Sable Phase 6 – Project 143642, Change Order 18, Dated 4/12/18: 735
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 736
of [BEGIN CONFIDENTIAL] 737
738
739
740
[END CONFIDENTIAL]. The 741
full text of the change order and cost is included in AG Ex. 1.19 CONF. The Company 742
approved the change order on April 17, 2018. The actual incremental cost due to the 743
change order included in 2018 QIP capital expenditures was $1,906,471.21 744
20 AG Ex. 1.23 21 AG Ex. 1.23.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
41
3. Aux Sable Phase 6 – Project 143642, Change Order 21, Dated 4/21/18: 745
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 746
of [BEGIN CONFIDENTIAL] 747
748
[END 749
CONFIDENTIAL]. The full text of the change order and cost is included in AG Ex. 1.20 750
CONF. The Company approved the change order on June 12, 2018. The actual 751
incremental cost due to the change order included in 2018 QIP capital expenditures was 752
$265,114.22 753
4. Aux Sable Phase 6 – Project 143642, Change Order 24, Dated 6/25/18: 754
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 755
of [BEGIN CONFIDENTIAL] 756
757
758
759
e 760
[END CONFIDENTIAL] The full text of the change order and cost is 761
included in AG Ex. 1.21 CONF. The Company approved the change order on June 25, 762
2018. The actual incremental cost due to the change order included in 2018 QIP capital 763
expenditures was $137,196.23 764
22 Id. 23 Id.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
42
5. Aux Sable Phase 7 – Project 143645, Change Order 19, Dated 4/12/18: 765
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 766
of [BEGIN CONFIDENTIAL] 767
768
769
770
[END 771
CONFIDENTIAL] The full text of the change order and cost is included in AG Ex. 1.22 772
CONF. The Company approved the change order on April 17, 2018. The actual 773
incremental cost included in 2018 QIP capital expenditures was $1,608,215.24 774
Q. WHAT IS YOUR ASSESSMENT OF THE FIVE CHANGE ORDERS DESCRIBED 775
ABOVE? 776
A. It appears that the Company ran into difficulties in obtaining permission from CN to cross 777
the railway and to work in the railway ROW as early as September 2017. The Company 778
knew since September 2017 following the CN train derailment that CN had notified Nicor 779
Gas to cease any work in the railroad ROW. AG Ex. 1.40 includes the Company’s response 780
to data request AG-23.25 from Docket No. 18-1775 detailing the sequence of events leading 781
to the cease and desist request by CN. 782
24 Id.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
43
Nevertheless, the Company proceeded to schedule the contractor to perform work in an area 783
for which it had no permission to do work, resulting in the contractor incurring additional 784
costs which the Company now wants to recover in this rate case. 785
The change orders indicate that the Company released work to its construction contractors 786
before Nicor Gas had obtained permits or permission to do work in the railway ROW. 787
Such a practice is unusual, and can be risky and very costly, as demonstrated by the cost 788
change orders. The Company should not have released the contractors to begin work on 789
the projects before obtaining the necessary permits or permission for the contractors to 790
work in the railway ROW. 791
By proceeding with the projects without the necessary permits or permission, Nicor Gas 792
incurred cost increases through change orders for a total amount exceeding $5.5 million. 793
This happened on multiple occasions in the construction of the Aux Sable pipeline 794
replacement project during 2018. The number of occurrences clearly shows a pattern of 795
imprudent decisions and actions by Nicor Gas. The incremental costs of $5,556,274 796
incurred for the five change orders are not reasonable and should not be included in the 797
2018 QIP capital expenditures. 798
Q. WHAT IS YOUR RECOMMENDATION? 799
A. I recommend that the Commission disallow the $5,556,274 pertaining to the five change 800
orders for the railway ROW problems from the calculation of the Rider QIP surcharge in 801
this reconciliation case. Based on the information provided by the Company in response to 802
data request AG 5.04(j) (AG Ex. 1.23) and the months when the incremental costs were 803
incurred, I have calculated a Rider QIP surcharge adjustment of $256,949. The calculation 804
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
44
of the surcharge adjustment was determined using the Company’s financial model and is 805
shown in AG Ex. 1.24. 806
B. Other Change Order Issues 807
Q. PLEASE DESCRIBE WHAT OTHER ISSUES YOU DISCOVERED DURING 808
YOUR REVIEW OF THE CHANGE ORDERS PROVIDED BY NICOR GAS. 809
A. During my review, I discovered 7 additional change orders where the Company incurred 810
excessive cost overruns in certain projects or approved change orders for incremental costs 811
caused by its own imprudent action or lack of action. 812
The total incremental cost of the 7 change orders is $2,438,934 I will describe each of the 813
cost change orders separately. 814
1. Aux Sable Phase 6 – Project 143642, Change Order 11, Dated 5/10/18: 815
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 816
of [BEGIN CONFIDENTIAL] 817
818
819
820
821
822
823
824
[END CONFIDENTIAL] 825
AG Ex. 1.25 CONF includes the full text of the change order and the related cost. From 826
the information shown in the change order, it appears that the Company did not deliver 827
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
45
sufficient pipe of the appropriate wall thickness. This failure caused the contractor to incur 828
additional costs for which it requested reimbursement under the change order. 829
Nicor Gas is responsible for providing the contractor with the correct materials at the 830
scheduled time. With this project, it seems clear that the Company failed to deliver the 831
correct material. The result of the imprudent action or inaction on the part of Nicor Gas 832
was an additional cost of [BEGIN CONFIDENTIAL] [END CONFIDENTIAL] 833
to complete the project. Customers should not pay for the Company’s errors in completing 834
a project within the specified design and cost parameters. The additional cost is 835
unreasonable, and the Commission should disallow it from the 2018 QIP capital 836
expenditures in this reconciliation case. 837
2. Aux Sable Phase 6 – Project 143642, Change Order 041, Dated 9/14/18: 838
In this change order, the contractor, Precision Pipeline, requested a cost increase allowance 839
of [BEGIN CONFIDENTIAL] 840
841
842
843
844
845
[END CONFIDENTIAL] 846
AG Ex. 1.26 CONF includes the full text of the change order and the related cost. In 847
response to data request AG 5.04(b), the Company explained that a PCR is a steady state 848
decoupler which allows AC electric current a path to the ground while retaining DC 849
electric current needed on the pipeline. This device is typically utilized on pipelines 850
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
46
installed within a high voltage transmission electric corridor. The PCR protects the 851
pipelines against corrosive AC current and ensures the long-term integrity of the pipe. 852
In the data request, the Company was asked to explain why the PCRs needed to be 853
relocated, and why they were not initially located in the appropriate area to avoid the 854
additional cost of relocation. In its response, the Company stated that typically when a 855
transmission pipeline is not located in farm fields it places the PCRs on two-foot pedestals. 856
With this project, the Company placed the PCRs on 6-foot pedestals to make them more 857
visible but did not consider the fact that they would be interfering with the equipment used 858
by the farmer to farm the land above the pipeline. 859
Apparently, a site visit by the engineering designing the project failed to discover this basic 860
problem. After the Company completed construction of the pipeline and placed the PCR 861
pedestals in the farming area, the farmer knocked over one or more of the pedestals and 862
complained about their location. The result was that the Company now had to relocate the 863
PCR to a different location away from the farming area. DR AG 5.04(b) included in AG 864
Ex. 1.23 provides more details on the sequence of events. 865
Given the Company’s experience in building transmission lines through farming areas, it is 866
difficult to understand why this problem was not anticipated and avoided. The fact that 867
Nicor Gas initially placed the PCRs on taller pedestals indicates that the Company was 868
concerned with visibility of the PCRs and potential interference with farming activities. 869
However, it still decided to proceed with locating the PCRs in the path of farming 870
activities. This was an imprudent decision. Customers should not pay for the unnecessary 871
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
47
incremental cost of relocating the PCR to a location where they should have been placed 872
initially. 873
The additional cost of [BEGIN CONFIDENTIAL] [END CONFIDENTIAL] is 874
unreasonable and the Commission should disallow it from the 2018 QIP capital 875
expenditures in this reconciliation case.25 876
3. Aux Sable Phase 7A – Project 143645, Change Order 041A, Dated 10/16/18: 877
This change order addresses the same problem as item 2 above for a different phase of the 878
Aux Sable pipeline. The contractor, Precision Pipeline, requested a cost increase 879
allowance of [BEGIN CONFIDENTIAL] 880
881
882
883
884
885
886
[END CONFIDENTIAL] 887
AG Ex. 1.27 CONF includes the full text of the change order and the related cost. In data 888
request AG 5.04(c), the Company was asked to explain why this problem reoccurred for a 889
later phase of the Aux Sable pipeline replacement project. In its response, the Company 890
stated that Phases 6 and 7A were built concurrently and the PCRs were located in the 891
farming area before the decision was made to relocate them away from the farming area.26 892
25 AG Ex. 1.23. In its response to DR AG 5.04(j), the Company reported the higher amount of $203,927 being
charged to 2018 QIP construction costs than the $169,355 shown in the change order. 26 AG Ex. 1.23, DR AG 5.04(c).
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
48
The same issues arise with this cost change order as with the Phase 6 change order and the 893
imprudent decision to locate the PCR in the farming area necessitating a relocation and 894
higher construction costs. Customers should not pay for the incremental cost of relocating 895
the PCR to a location where they should have been placed initially. 896
The additional cost of [BEGIN CONFIDENTIAL] [END CONFIDENTIAL] is 897
unreasonable and the Commission should disallow it from the 2018 QIP capital 898
expenditures in this reconciliation case.27 899
4. Oak Brook Station 256 – Project 116006, Change Order COR 008, Dated 10/4/18: 900
In this change order, the contractor, NPL, requested a cost increase allowance of [BEGIN 901
CONFIDENTIAL] 902
903
904
905
906
907
908
909
910
911
912
. 913
914
[END CONFIDENTIAL] 915
AG Ex. 1.28 CONF includes the full text of the change order and the related cost. From 916
the information shown in the change order, it appears that the Company did not deliver the 917
correct valves and at the scheduled time to allow the contractor to install the valves as 918
27 In its response to DR AG 5.04(j), the company reported the higher amount of $144,274 being charged to 2018
QIP construction costs than the $124,194 shown in the change order.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
49
planned and according to the design specs. Because of Nicor Gas’s errors, the contractor 919
had to incur extra time and equipment costs to complete the construction work, for which 920
the Company reimbursed the contractor. 921
Nicor Gas has the responsibility to provide the contractor with the correct materials at the 922
scheduled time. With this project, it seems clear that the Company failed to meet that 923
responsibility. Nicor Gas’s imprudent action or inaction resulted in the project completion 924
costing an additional [BEGIN CONFIDENTIAL] . [END CONFIDENTIAL] The 925
additional cost is unreasonable, and the Commission should disallow it from the 2018 QIP 926
capital expenditures in this reconciliation case. 927
5. Oak Brook Station 256 – Project 116006, Change Order COR 015, Dated 11/5/18: 928
In this change order, the contractor, NPL, requested a cost increase allowance of [BEGIN 929
CONFIDENTIAL] 930
931
932
933
934
935
936
937
[END CONFIDENTIAL] 938
AG Ex. 1.29 CONF includes the full text of the change order and the related cost. From 939
the information shown in the change order, it appears that there are three reasons for the 940
higher cost allowance being requested. First, the change order indicates a desire to 941
complete the job by the end of October and the need to work on Sunday and adding crews 942
to meet the deadline. Second, the change order references the fact that the contractor had 943
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
50
to mobilize and demobilize its crews multiple times due to work scheduling issues, which 944
usually increase costs. Third, it appears that the contractor did not have full access to the 945
gate station, and as a result the project was delayed and likely incurred higher costs. 946
All three reasons for the cost overruns were within the control of Nicor Gas. Not giving 947
the contractor the necessary access to the gate station and forcing the contractor to mobilize 948
and demobilize its crews several times are inexcusable reasons. The resulting higher cost 949
to complete the gate station is the outcome of imprudent actions or decisions on the part of 950
Nicor Gas. The additional cost of [BEGIN CONFIDENTIAL] [END 951
CONFIDENTIAL] is unreasonable and the Commission should disallow it from the 2018 952
QIP capital expenditures in this reconciliation case. 953
6. Oak Brook Station 256 – Project 116006, Change Order 11, Dated 10/11/18: 954
In this change order, the contractor, NPL, requested a cost increase allowance of [BEGIN 955
CONFIDENTIAL] 956
957
958
959
960
961
[END 962
CONFIDENTIAL] 963
AG Ex. 1.30 CONF includes the full text of the change order and the related cost. In 964
response to data request AG 5.04(d), the company elaborated further on the reason for the 965
delay stating that the back feed into the system supplied by the station was interrupted. 966
This interruption required a delay in completing the station work until the back feed was 967
restored. Although the delay in completing the station work seems plausible, it is 968
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
51
perplexing why the Company did not redirect the contractor crews to a different project and 969
still continued to incur costs on this project after it became clear that the project needed to 970
be delayed. 971
Additionally, it is not clear why the contractor was waiting on delivery of the 30” valves 972
and flaring of gas when supposedly work on the project could not proceed. The 973
inconsistencies in the contractor’s statements with the Company’s explanation, and the 974
inaction on the part of the Company to avoid the incurrence of additional costs once it 975
became clear the project needed to be delayed rise to the level of imprudent actions or 976
inactions. Customers should not pay for the Company’s imprudent decisions. The 977
additional cost is unreasonable, and the Commission should disallow the [BEGIN 978
CONFIDENTIAL] [END CONFIDENTIAL] from the 2018 QIP capital 979
expenditures in this reconciliation case. 980
7. Madison Street Main Replacement – Project 155084, Change Order Date N/A: 981
The Company provided an incomplete change order document that shows the incremental 982
cost of [BEGIN CONFIDENTIAL] [END CONFIDENTIAL] to complete the 983
Madison Street, Elmhurst, main replacement. AG Ex. 1.31 includes the information 984
provided by the Company about the incremental costs. Nicor included [BEGIN 985
CONFIDENTIAL] [END CONFIDENTIAL] for this change order in the 2018 986
QIP costs.28 987
28 Nicor Gas response to data request AG 5.04(j).
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
52
Although it could not provide a completed standard charge order document, in response to 988
data request AG 5.04(f) the Company stated that it could not complete replacement of the 989
entire main in 2017, and completion of the second half of the project was extended into 990
2018. The Company also stated that the extension of the project into 2018 increased costs 991
due to additional fittings, taps, paving and other materials needed to temporarily return a 992
portion of the previous main back into service and complete the rest of the project in 2018. 993
The Company also incurred additional costs for using contracted inspection services 994
instead of internal resources, and from additional permit requirements imposed by the City 995
of Elmhurst, which the Company had not included in its initial project cost estimate. 996
These additional inspection and permit costs totaled [BEGIN CONFIDENTIAL] 997
[END CONFIDENTIAL]. AG Ex. 1.23 includes the response to DR AG 5.04(f). 998
Q. WHAT IS YOUR ASSESSMENT OF THIS PROJECT COST INCREASE? 999
A. This project is beset by multiple problems. First, it appears that either a scheduling 1000
problem or field construction problem delayed completion of the project in 2017, therefore 1001
requiring a duplication of effort and materials to return part of the old main into service 1002
again temporarily before the start of the winter season of 2017-2018. The remainder of the 1003
project was then restarted and completed in 2018, which resulted in significantly higher 1004
costs. 1005
Second, it appears that the Company encountered water and sewer lines at locations which 1006
it did not expect. The Company stated that it relied on information provided by the City of 1007
Elmhurst. Although additional fittings and materials were needed to work around the 1008
water and sewer lines, it is not known how significant this additional cost was. 1009
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
53
Third, the Company stated that, as part of the work permit requirements, the City of 1010
Elmhurst required paving of the entire street, daily street sweeping and digital sign boards 1011
around the project, which increased the cost of the project. It is unknown why the 1012
Company did not anticipate these costs in its original cost estimate given that such 1013
information would be easily determined by consulting the city’s permit department during 1014
the project design and cost estimating phase. 1015
Fourth, the Company decided to use contracted inspection services to inspect the pipeline 1016
construction work instead of its own employees. This increased the cost of the project, but 1017
the Company did not state why this change and additional cost were necessary. 1018
In conclusion, this series of events seems to emanate from poor planning and execution of 1019
the project. The incremental costs do not appear to be prudently incurred. Therefore, it is 1020
not reasonable to burden customers with incremental costs that the Company could have 1021
avoided or significantly minimized through better planning and execution of the project. I 1022
recommend that the Commission disallow [BEGIN CONFIDENTIAL] [END 1023
CONFIDENTIAL] from the 2018 QIP capital expenditures in this reconciliation case.29 1024
Q. WHAT IS TOTAL DISALLOWANCE FOR THE 7 CHANGE ORDERS YOU 1025
HAVE DISCUSSED ABOVE? 1026
A. The total capital expenditures disallowance for the other seven change orders is 1027
$2,438,934. Based on the information provided by the Company in response to data 1028
request AG 5.04(j) (AG Ex. 1.23) and the months when the incremental costs were 1029
29 In its response to DR AG 5.04(j), the Company reported the lower amount of $1,280,000 being charged
to 2018 QIP construction costs rather than the $1,610,000 shown in the change order.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
54
incurred, I have calculated a Rider QIP surcharge adjustment of $96,141. The calculation 1030
of the surcharge adjustment was determined using the Company’s financial model and is 1031
shown in AG Ex. 1.32. 1032
Q. WHAT ARE YOUR OVERALL CONCLUSION AND RECOMMENDATION 1033
WITH REGARD TO THE 12 CHANGE ORDERS YOU HAVE DISCUSSED 1034
ABOVE? 1035
A. As discussed in detail above, the Company made several imprudent decisions in the 1036
planning and execution of the 2018 Rider QIP capital projects that resulted in higher 1037
construction costs. My review of the hundreds of documents pertaining to the 60 change 1038
orders provided by the Company determined that 12 projects had cost increases which 1039
were not prudently incurred. The total amount of capital expenditures pertaining to those 1040
12 change orders is $7,995,208. Customers should not pay for those costs. 1041
Therefore, I recommend the Commission remove the $7,995,208 from the 2018 QIP 1042
capital expenditures and order the Company to refund to customers the related surcharge 1043
revenue of $353,090 billed during 2018. 1044
VIII. ACCEPTANCE OF HIGHER COST BIDS 1045
Q. PLEASE DESCRIBE WHAT ISSUES YOU DISCOVERED IN YOUR REVIEW OF 1046
CONTRACTOR BIDS FOR QIP PROJECTS. 1047
A. In response to data request AG 4.20, the Company provided documents showing the 1048
evaluation results of project bids received from contractors bidding on major projects 1049
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
55
completed in 2018.30 In my review of the bid evaluation documents, I discovered four 1050
situations where the Company accepted higher cost bids without adequate evidence that the 1051
decision was justified by the available information. The acceptance of the higher cost bids 1052
increased the construction cost of the projects by $5,219,618. These costs were 1053
imprudently incurred and should be removed from the 2018 QIP capital expenditures in 1054
this reconciliation case. 1055
I will discuss each of the four situations separately below. 1056
A. Aux Sable Pipeline Replacement (Phases 6 & 7) 1057
Q. PLEASE DESCRIBE THE BID EVALUATION RESULTS FOR PHASES 6 AND 7 1058
OF THE AUX SABLE PIPELINE REPLACEMENT PROJECT. 1059
A. Based on the information that the Company provided in Exhibit 4 CONF to the response to 1060
data request AG 4.20, the Company received four acceptable bids from contractors for 1061
construction of Phase 6 and 7 of the Aux Sable Pipeline.31 The bid evaluation documents 1062
provided by the Company shows the lump sum cost bids ranged from [BEGIN 1063
CONFIDENTIAL] 1064
[END 1065
CONFIDENTIAL] 1066
The Company uses a scorecard approach to evaluate bids that in addition to price considers 1067
construction capability of the contractor, strength of the proposal, safety record, supplier 1068
30 AG Ex. 1.33 CONF.
31 According to Nicor Gas, a fifth contractor bid did not advance to the second stage of bid evaluation.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
56
diversity and acceptance of contract terms. The comparative scorecard shows that 1069
[BEGIN CONFIDENTIAL] 1070
1071
1072
. 1073
1074
1075
1076
y 1077
1078
1079
1080
1081
1082
1083
1084
1085
[END CONFIDENTIAL] AG Ex. 1.33 CONF includes DR AG 1086
4.20 and Exhibit 4 CONF showing the scorecard and related information. 1087
The Company tried to explain these inconsistencies in its response to data request AG 1088
5.23(e) by stating that [BEGIN CONFIDENTIAL] 1089
32 Nicor Gas response to DR AG 4.21(b).
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
57
1090
1091
1092
1093
1094
1095
[END 1096
CONFIDENTIAL] AG Ex. 1.34 CONF includes the response to DR AG 5.23(e) CONF. 1097
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1098
A. Nicor Gas did not perform a fair and reasonable evaluation of the construction bids it 1099
received [BEGIN CONFIDENTIAL] 1100
1101
1102
1103
1104
1105
1106
. [END 1107
CONFIDENTIAL] I recommend that the Commission disallow this higher cost from the 1108
2018 QIP capital expenditures proposed for recovery by the Company. 1109
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
58
B. Paving Restoration Zone 2 (Crestwood and Glenwood) 1110
Q. PLEASE DESCRIBE THE BID EVALUATION RESULTS FOR PAVING 1111
RESTORATION WORK IN ZONE 2. 1112
A. In response to Staff data request MEM 1.02 and attached Exhibit 13 Appendix B CONF, 1113
page 4, the Company provided the results of its request for proposal (“RFP”) for paving 1114
restoration work in Zone 2 in the Crestwood and Glenwood area. The RFP was for a 1115
multi-year contract spanning from 2017 to 2021. The Company received three cost bids. 1116
[BEGIN CONFIDENTIAL] 1117
1118
1119
[END 1120
CONFIDENTIAL] AG Ex. 1.35 CONF includes the response to data request MEM 1.02, 1121
the bids received, and the bid evaluation scorecard. 1122
In data request AG 4.22 CONF, the Company was asked to explain why [BEGIN 1123
CONFIDENTIAL] 1124
1125
1126
1127
1128
1129
. 1130
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
59
1131
1132
1133
1134
1135
[END CONFIDENTIAL] In the 1136
response, the Company stated that there were differences between estimated and actual 1137
work performed. No further details were provided as to what specifically changed and 1138
why. AG Ex. 1.35 CONF includes the responses to DR AG 4.22 CONF and AG 5.25 1139
CONF. 1140
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1141
A. Once more, Nicor Gas did not perform a fair and reasonable evaluation of the cost bids it 1142
received. [BEGIN CONFIDENTIAL] 1143
1144
1145
1146
1147
1148
1149
33
.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
60
1150
1151
[END 1152
CONFIDENTIAL] 1153
C. Paving Restoration Zone 3 (Bloomington, Etc.) 1154
Q. PLEASE DESCRIBE THE BID EVALUATION RESULTS FOR PAVING 1155
RESTORATION WORK IN ZONE 3. 1156
A. In response to Staff data request MEM 1.02 and attached Exhibit 13 Appendix B CONF, 1157
page 5, the Company provided the results of its request for proposal (“RFP”) for paving 1158
restoration work in Zone 3 in the Bloomington, Kankakee, Ottawa and Paxton area. The 1159
RFP was for a multi-year contract spanning from 2017 to 2021. [BEGIN 1160
CONFIDENTIAL] 1161
1162
1163
1164
1165
1166
1167
. [END CONFIDENTIAL] AG Ex. 1.36 CONF includes the bid 1168
evaluation document, the responses to DR AG 4.23 CONF and AG 5.26 conf. 1169
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
61
The contract was awarded to [BEGIN CONFIDENTIAL] 1170
1171
1172
1173
[END CONFIDENTIAL] In the response, 1174
the Company stated that there were differences between estimated and actual work 1175
performed. No further details were provided as to what specifically changed and why. 1176
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1177
A. From the conflicting information provided in the responses to the data requests and the 1178
information shown in the bid evaluation document, it is impossible to determine what 1179
actually occurred [BEGIN CONFIDENTIAL] 1180
1181
1182
1183
1184
1185
1186
1187
1188
1189
34
.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
62
1190
1191
1192
1193
1194
1195
1196
1197
[END CONFIDENTIAL] 1198
D. Paving Restoration Zone 6 (Crystal Lake, Etc.) 1199
Q. PLEASE DESCRIBE THE BID EVALUATION RESULTS FOR PAVING 1200
RESTORATION WORK IN ZONE 6. 1201
A. In response to Staff data request MEM 1.02 and attached Exhibit 13 Appendix B CONF, 1202
page 8, the Company provided the results of its request for proposal (“RFP”) for paving 1203
restoration work in Zone 6 in the Crystal Lake, Elgin, Ingleside and Schaumburg area. 1204
The RFP was for a multi-year contract spanning from 2017 to 2021. The Company 1205
received four cost bids. [BEGIN CONFIDENTIAL] 1206
1207
1208
[END 1209
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
63
CONFIDENTIAL] AG Ex. 1.37 CONF includes the response to data request MEM 1.02, 1210
the bids received, and the bid evaluation scorecard. 1211
In data request AG 4.24 CONF, the Company was asked to explain why [BEGIN 1212
CONFIDENTIAL] 1213
1214
1215
1216
1217
1218
1219
1220
1221
1222
1223
[END CONFIDENTIAL] AG 1224
Ex. 1.37 CONF includes the responses to DR AG 4.24 CONF and AG 5.27 CONF. 1225
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1226
A. The discussion above shows how Nicor Gas [BEGIN CONFIDENTIAL] 1227
1228
1229
1230
1231
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
64
1232
1233
1234
1235
1236
1237
[END CONFIDENTIAL] 1238
E. Summary 1239
Q. PLEASE SUMMARIZE THE QIP CAPITAL EXPENDITURES AND RIDER QIP 1240
SURCHARGE REVENUE ADJUSTMENTS THAT YOU RECOMMEND FOR BIDS 1241
ACCEPTED OVER LOWER BIDS. 1242
A. From the analysis shown above, it is evident that the Company does not have a consistent 1243
and transparent process of selecting construction bids. The Company’s current approach 1244
has resulted in higher construction costs which the Company seeks to recover through the 1245
Rider QIP and ultimately in base rates. The Commission should instruct the Company to 1246
be better disciplined, and revamp its bid evaluation and acceptance procedures in order to 1247
avoid incurring higher construction costs. 1248
In total for the above four bid contracts, I recommend the Commission should remove 1249
$5,219,618 from the QIP capital expenditures, and $270,707 of related surcharge revenue 1250
from the 2018 Rider QIP reconciliation. 1251
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
65
IX. PROJECTS NOT BID OUT 1252
Q. PLEASE DISCUSS THE 2018 CAPITAL EXPENDITURES FOR QIP PROJECTS 1253
THAT WERE AND WERE NOT BID OUT TO MULTIPLE CONTRACTORS. 1254
A. In response to data request AG 4.20 and the attached Exhibit 1, the Company provided 1255
information showing that of the 725 projects completed in 2018 at a total cost of $354.1 1256
million, only 6 projects were bid out, representing a total cost of $109.7 million. The 1257
remaining projects at a cost of $244.5 million representing 69% of the total capital 1258
expenditures incurred during 2018 were not bid out and were completed under blanket 1259
contracts or the alliance agreement that the Company has with Northern Pipeline Company 1260
(“NPL”). Of the $244.5 million work not bid out, $143.7 million represents 66 projects 1261
with a cost of $1 million or greater, including a project for $23 million to replace copper 1262
services under a blanket contract.35 1263
Q. WHAT WORK WAS DONE UNDER BLANKET AGREEMENTS, AND AT WHAT 1264
COST? 1265
In 2018, NPL billed the Company $85.8 million for a variety of projects under its alliance 1266
blanket contract which was last bid out 13 years ago in 2005. Other blanket contracts with 1267
major contractors, such as KS Energy, were last bid out in 2014. Blanket contracts with 1268
smaller contracts for paving and restoration work were last bid out in 2017 for a five-year 1269
period, as discussed earlier in my testimony. AG Ex.1.39 includes DR AG 5.06 which 1270
provides additional details. 1271
35 AG Ex. 1.33.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
66
Q. DID THE COMPANY ATTEMPT TO EXPLAIN ITS FAILURE TO BID OUT 1272
MORE THAN SIX 2018 PROJECTS? 1273
A. In response to data request AG 3.11, the Company attempts to justify its practice of not 1274
bidding out more projects by stating that historically it has developed three primary 1275
methodologies to drive competitive labor pricing and deliver superior quality and safety. 1276
According to the Company, the first approach is to competitively bid unique and distinct 1277
projects with a defined scope and completion date. This approach supposedly covers the 6 1278
projects identified earlier that the Company bid out for work completed in 2018. 1279
The second approach is to use blanket contracts for repetitive work with competitive 1280
contractor markets and lower risk profiles. According to the Company this work is 1281
competitively bid under 3 to 5-year contract terms to allow for a consistent work product. 1282
The Company defines competitive markets as the presence of multiple suppliers who can 1283
perform this type of work. It also defines low risk profiles as work that is not specialized 1284
and not requiring unique technical skills. 1285
The third approach is for repetitive work with higher risk profiles and certain barriers to 1286
entry which the Company has decided to address by developing alliances with contractors, 1287
such as NPL. The Company defines high risk profile work as work requiring intimate 1288
knowledge of the specific natural gas system and the Company processes. It also defines 1289
barrier to entry as specialized work requiring a steep learning curve for any new supplier to 1290
match the quality and productivity of the previous supplier. AG Ex.1.17 includes DR AG 1291
3.11(c), and AG Ex. 1.39 includes DR AG 5.06, which provide additional details. 1292
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
67
The second and third approaches supposedly justify not bidding out 99% of the projects 1293
and 69% of all the capital expenditures billed by contractors for 2018 QIP program work. 1294
Q. WHAT IS YOUR ASSESSMENT OF THE COMPANY’S PROJECT BIDDING 1295
PRACTICES? 1296
A. Not competitively bidding hundreds of millions of dollars of construction work should not 1297
be an acceptable practice, irrespective of the explanations and approaches articulated by 1298
the Company, or any modest amount of savings that the alliance with NPL may have 1299
generated. 1300
Repetitive work such as relocating meters, replacing service lines and distribution mains is 1301
not work that should be restricted to only one or two contractors under multi-year blanket 1302
contracts. There are dozens of utility contractors that perform this type of work nationally 1303
and regionally in the U.S. Nicor Gas’s gas distribution system is not unique among 1304
utilities in the U.S. The best work practices used by NPL, KS Energy and other major 1305
contractors used by Nicor Gas under blanket contracts are rather common among other 1306
contractors. Therefore, the justification that the work completed under blanket contracts is 1307
somehow highly specialized with a steep learning curve for any new contractors is a red 1308
herring and unsupported speculation. 1309
Although it may be not practical to bid out every work project, larger projects of at least $1 1310
million in value or larger, whether repetitive or not, should be bid out routinely. Even 1311
smaller projects down to a value of $100,000 could be bundled in a bid package and issued 1312
to several contractors for requests for proposal. Only through a competitive bidding 1313
process can there be assurance that the Company is not overpaying for work completed by 1314
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
68
contractors. Unfortunately, as we have seen with the high contractor costs incurred to 1315
replace copper services in section VI of my testimony, there is clear evidence that the 1316
Company may be paying more for contractor work than it should. 1317
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1318
A. As discussed above, the Company bid out only a small fraction of the QIP work completed 1319
in 2018. The Company’s justification for not bidding out a much larger portion of this 1320
work is not credible. There is also evidence that work completed under blanket contracts, 1321
such as service line replacements, is much more costly than work completed by Company 1322
employees. This is a clear indication that work completed under blanket contracts, which 1323
have not bid out in years, may no longer be competitively priced. 1324
Furthermore, and equally troubling, the Company has granted construction work to 1325
contractors when those contractors’ bids were significantly higher than the lowest bidder, 1326
and the lowest bidder was equally, if not more, qualified than the selected contractor. 1327
I recommend that the Commission require that in future Rider QIP reconciliations, the 1328
Company identify all capital projects that were competitively bid, the bids considered and 1329
selected, and if capital projects of at least $250,000 in value were not competitively bid 1330
individually or combined with other projects, explain and justify why not. The 1331
exceptionally large capital expenditures incurred under the Rider QIP program require that 1332
the Company enter in competitively bid construction contracts to ensure that capital 1333
additions are prudent and reasonable. 1334
1335
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
69
X. LACK OF CONTRACTOR AUDITS 1336
Q. PLEASE DISCUSS WHETHER THE COMPANY ROUTINELY PERFORMS 1337
AUDITS OF CONTRACTOR INVOICED COSTS AND CONDUCTS 1338
CONTRACTOR PERFORMANCE REVIEWS. 1339
A. In data request AG 4.20, the Company was asked to provide copies of operational audits 1340
performed for amounts billed by contractors for costs included in the 2018 QIP program. 1341
The Company was also asked to provide copies of scorecards or performance reviews of 1342
work performed by contractors during 2018. In a subsequent data request AG 5.23, the 1343
Company was asked to provide the amount of performance incentives paid for superior 1344
performance or penalties assessed for underperformance by its contractors. 1345
In response to those data requests, the Company stated that it did not perform any specific 1346
audits of costs invoiced by contractors in 2018 and pointed to general internal controls and 1347
compliance procedures for assurances.36 1348
With regard to contractor performance reviews, the Company provided 15 performance 1349
reports on some of its contractors. Some of the performance reports show performance 1350
levels where incentive payments should have been made and others show under-1351
performance where penalties should have been assessed under the contracts. However, in 1352
response to DR AG 5.23(c), the Company stated that no performance incentive payments 1353
or penalties were included in the 2018 QIP program costs. This is somewhat surprising. 1354
No explanation was provided as to why. 1355
36 DR AG 5.23(a) included in AG Ex. 1.34 CONF.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
70
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1356
A. The fact that the Company did not perform audits of the costs invoiced by major 1357
contractors during 2018 is concerning. The experience gained from other gas utilities in 1358
Illinois with a Rider QIP program has shown that audits performed of contractor invoices 1359
has uncovered millions of dollars of improper cost billings. 1360
For example, through audit of contractor billings, one utility discovered that certain 1361
contractors had overbilled for work performed on projects completed in 2014 and 2015. 1362
The audits found billing discrepancies and internal control failures relating to 13 1363
contractors. Some of the audit findings showed excessive mark-ups on subcontracted 1364
services, unsupported third-party charges, billings for more expensive open trenching work 1365
instead of actual directional drilling work performed, and unverified billing rates against 1366
approved contract rates. The audits recommended changes in the utility internal invoice 1367
review and approval procedures and other internal control processes. 37 1368
I recommend that the Commission direct the Company to perform annual audits of the 1369
amounts billed by any contractor who bills the Company at least $5 million for work 1370
performed during the annual QIP program. The absence of such audits in future Rider QIP 1371
reconciliations would be considered a failure to attest as to the reasonableness and 1372
prudency of the costs included in the QIP program. The audit should be performed by 1373
third party auditors who are independent of the Company and of the contractors. 1374
37 ICC Docket No. 15-0209 AG-CUB Ex 1.0 at 10 and Docket No. 16-0197 AG-CUB Ex. 1.0 at 16.
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
71
Furthermore, the Company should be more transparent about the performance of its major 1375
contractors by reporting in the testimony filed with the annual Rider QIP reconciliation any 1376
under performance by its major construction contractors and the total incentive payments 1377
made and penalties assessed to all its contractors. 1378
XI. EXCLUSION OF GAS STORAGE INFRASTRUCTURE COSTS 1379
Q. PLEASE DISCUSS WHY GAS STORAGE INFRASTRUCTURE COSTS SHOULD 1380
NOT BE INCLUDED IN THE RIDER QIP PROGRAM. 1381
A. In this reconciliation and other recent Rider QIP reconciliations, the Company has 1382
included the cost of reworking gas wells, replacing storage gas lines that move gas from 1383
compressor stations to the storage wells, replacing or upgrading compressors and 1384
compressor stations, replacing and upgrading storage measuring and regulating 1385
equipment, and gas storage heaters and other gas conditioning equipment. For 2018, these 1386
capital expenditures were approximately $49 million. 1387
Although I am not a lawyer and I am not rendering a legal opinion, a literal reading of the 1388
statute that authorized the Rider QIP does not refer to gas storage infrastructure as being 1389
“qualifying infrastructure plant.” The reference to qualifying infrastructure plant seems 1390
limited to distribution and high-pressure transmission plant. It appears that the Company 1391
has expanded this definition to include gas storage plant. 1392
When comparing the text of the Rider 32 Qualified Infrastructure Plant in Nicor Gas’s 1393
tariff to the text of the Rider QIP tariff of Peoples Gas Light and Coke Company (“PGL”) 1394
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
72
there are some telling differences. For example, Nicor Gas has included a definition of 1395
High-Pressure Transmission Pipelines which includes facilities for compression, 1396
conditioning, and storage field and gathering system appurtenances. The PGL QIP does 1397
not have a definition for High-Pressure Transmission Pipelines at all, much less the 1398
inclusion of storage-related facilities. It appears that PGL uses the more literal definition 1399
of high-pressure transmission pipelines included in Sec. 9-220.3(5) of the Public Utility 1400
Act. Although PGL has also storage facilities, it does not include any capital expenditures 1401
for those facilities in its Rider QIP program cost reconciliation. 1402
Q. WHAT ARE YOUR CONCLUSION AND RECOMMENDATION? 1403
A. My conclusion is that storage-related capital expenditures were never intended to be 1404
included in the Rider QIP program and the Company has expanded the definition of 1405
Qualifying Infrastructure Plant beyond its intended purpose. 1406
Therefore, I recommend that the Commission direct the Company to exclude gas storage 1407
related plant additions and retirements from future Rider QIP plans and reconciliations. 1408
XII. OTHER OBSERVATIONS 1409
Q. DO YOU HAVE ANY OTHER OBSERVATIONS YOU WANT TO MAKE WITH 1410
REGARD TO THE COMPANY’S 2018 RIDER QIP RECONCILIATION FILING? 1411
A. From reviewing Nicor Gas Ex. 1.0 and 2.0, it is readily apparent that the Company 1412
provided no useful information about the infrastructure replacement or upgrade projects 1413
completed during 2018. The testimony and exhibits of Mr. Kim and Mr. Whiteside do not 1414
identify any specific 2018 projects as qualifying infrastructure plant under each of the 1415
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
73
major qualifying plant categories as described in the statute, or address whether the 1416
projects were selected and prioritized to improve public safety and reliability. The 1417
testimony is devoid of any explanation of major variances in the cost of the major projects 1418
completed in comparison to the plan filed with the Commission. The testimony also lacks 1419
any explanation about projects that had been planned, were later deferred and not 1420
completed in 2018. Neither Mr. Kim nor Mr. Whiteside address the number and amount 1421
of change orders affecting capital expenditures for 2018, or explain any of the major cost 1422
change orders. 1423
It would be reasonable to expect Company management to describe the major projects 1424
completed during the reconciliation year and justify major cost increases, as well as other 1425
major project changes from the plan filed with the Commission, and explain why the 1426
Company decided to pursue new projects and defer other previously planned projects. 1427
Unfortunately, the QIP reconciliation filing gives the appearance of a perfunctory filing to 1428
simply reconcile the Rider QIP revenue billed to the revenue recoverable. 1429
I recommend that the Commission direct the Company that in future Rider QIP 1430
reconciliation filings include testimony and other exhibits to provide thorough 1431
explanations of (1) the major projects completed during the Rider QIP reconciliation year; 1432
(2) any significant variance of 10% or greater in the cost of the major projects completed 1433
during the year in comparison to the plan filed with the Commission; (3) QIP projects that 1434
had been planned for the year, but were later deferred and not completed, as well as new 1435
projects added that were not initially planned; (4) the number and amount of change 1436
orders affecting capital expenditures for QIP projects and an explanation of the more 1437
ICC Docket No. 19-0294
Direct Testimony of Sebastian Coppola
AG Exhibit 1.0 PUBLIC
74
significant cost change orders exceeding $250,000; (5) how the Company prioritized the 1438
projects for public safety and reliability; and (6) other useful information that justify 1439
undertaking the QIP projects completed during the reconciliation year. 1440
Q. DOES THIS CONCLUDE YOUR DIRECT TESTIMONY? 1441
A. Yes. However, I reserve the right to amend, revise or supplement my testimony to 1442
incorporate new information that may subsequently become available. 1443