+ All Categories
Home > Documents > STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing...

STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing...

Date post: 16-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
7
·• I STATEMENT OF WORK TECHNICAL AND ENFORCEMENT OVERSIGHT SALEM ACRES RI/FS Salem, Massachusetts Introduction The purpose of this work assignment is to conduct a Technical and Enforcement OVersight for the Salem Acres \'laste Site located in Salem, Massachusetts. The Remedial Investigation/ Feasibility Study (Rl/FS) to be conducted will be performed by PRP Contractor, The Maguire Group, Inc. The work plan for Salem Acres was prepared for EPA by GCA Corporation of Bedford, MA. This work plan is divided into four phases, Phases 1 through 3 describe the work to be completed under the RI, and Phase 4 describes the work to be completed under the FS. The Remedial Investigation and Feasibility Study is being conducted under an EPA Administrative Order by Consent with the South Essex Sewerage District (SESD). On April 10, 1987, EPA initiated an Emergency Removal Action to stabilize the two sludge pit areas which are leaching out into the Strongwater and Swampscott Road Brook Wetlands. Damage to wetlands is apparent. · Task 1 - Technical Review of the RI/FS Work Plan The purpose of this task is to perform a review of the PRP's RI/FS work plan (GCA/EPA approved work plan). The work plan shall be approved and modified to reflect the SARA/CERCLA Amendments and any changes to the NCP. Subtask 1.1 - Review existing documents pertinent to RI/FS l-lork Plan The objective of this task is to become familiar with material pertinent to the RI/FS work plan. Site Inspection Reports conducted by State, County, or Federal Government should be reviewed. NUS FIT Report, Hazardous Ranking System Report, Disposal History at Site and any other reports deemed essential. Subtask 1.2 - Review Phase I: Project Operations Plan (POP) Before any onsite Remedial Investigation work begins at Salem Acres, a variety of RI support activities must be addressed. The Salem Acres Project Operations Plan (POP) will be written to identify site-specific policy and procedural guidelines that will be implemented throughout the RI/FS. The POP will be written a series of specific plans that will incorporate individual remedial activities proposed to take place onsite or in the surrounding areas. Specifically, the Salem Acres POP will include plans for: 0 and Analysis
Transcript
Page 1: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

·• I

STATEMENT OF WORK TECHNICAL AND ENFORCEMENT OVERSIGHT

SALEM ACRES RI/FS Salem, Massachusetts

Introduction

The purpose of this work assignment is to conduct a Technical and Enforcement OVersight for the Salem Acres \'laste Site located in Salem, Massachusetts. The Remedial Investigation/ Feasibility Study (Rl/FS) to be conducted will be performed by PRP Contractor, The Maguire Group, Inc. The work plan for Salem Acres was prepared for EPA by GCA Corporation of Bedford, MA. This work plan is divided into four phases, Phases 1 through 3 describe the work to be completed under the RI, and Phase 4 describes the work to be completed under the FS. The Remedial Investigation and Feasibility Study is being conducted under an EPA Administrative Order by Consent with the South Essex Sewerage District (SESD). On April 10, 1987, EPA initiated an Emergency Removal Action to stabilize the two sludge pit areas which are leaching out into the Strongwater and Swampscott Road Brook Wetlands. Damage to wetlands is apparent. ·

Task 1 - Technical Review of the RI/FS Work Plan

The purpose of this task is to perform a review of the PRP's RI/FS work plan (GCA/EPA approved work plan). The work plan shall be approved and modified to reflect the SARA/CERCLA Amendments and any changes to the NCP.

Subtask 1.1 - Review existing documents pertinent to RI/FS l-lork Plan

The objective of this task is to become familiar with material pertinent to the RI/FS work plan. Site Inspection Reports conducted by State, County, or Federal Government should be reviewed. NUS FIT Report, Hazardous Ranking System Report, Disposal History at Site and any other reports deemed essential.

Subtask 1.2 - Review Phase I: Project Operations Plan (POP)

Before any onsite Remedial Investigation work begins at Salem Acres, a variety of RI support activities must be addressed. The Salem Acres Project Operations Plan (POP) will be written to identify site-specific policy and procedural guidelines that will be implemented throughout the RI/FS. The POP will be written ~s a series of specific plans that will incorporate individual remedial activities proposed to take place onsite or in the surrounding areas. Specifically, the Salem Acres POP will include plans for:

0 Sa~~ling and Analysis

Page 2: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

I, - .2 ­

• Quality Assurance/Quality Control

• Site Health, and Safety

• Topographic Mapping

• Data Management

Subtask 1.3 - Review groundwater aspect of the RI/FS

The groundwater section is a very important aspect of the POP and is identified as a separate subtask. The purpose of this task is to provide a review of the PRP's Remedial Investigation/Feasibilty Study (RI/FS)· activities with respect to groundwater at the site. The review activities will include the review of the PRP's draft and final WOrk Plan, Full Field OVersight of RI activities, and review of the RI report. Comments on the work plan and the RI report will be summarized in letter reports and discussed at technical review meetings with EPA staff as designated by Remedial Project Manager.

Subtask 1.3.1 - Review existing geological/hydrogeological information of the Salem Acres Site

An attempt must be made to identify and review any existing information pertaining to geology or hydrogeology of the Salem Acres Site. Reports by NUS/FIT could supply pertinent information.

Subtask 1.3.Z - Review of PRP's RI Work Plan with emphasis on well design

The RI work plan will be reviewed with special emphasis on the well placement and design. Attendance at informational meetings to clarify the work plan elements is anticipated. Work plan comments will be summarized in a letter report and additional meetings to discuss the RI work plan comments are anticipated.

Subtask 1.4 - Review Phase II: Wetlands Assessment Plan

This task will deal with determining harm to the surrounding wetland areas. Since it is believed that the wetlands are receptors of groundwater and surface water contamination, an in depth study to assess this damage will be made. An assessment of the wetland ecosystem is anticipated; this will include a determination of stress to the benthos macroinvertebrate community. A review of the wetlands plan will be summarized in a written report and discussed at technical review meetings as scheduled by RPM.

Page 3: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

. . ­:.~· · ~~·.· · ·~~:-: - · - '7 ...-:-..·. . -: · · ::::­

-; . -3­

Subtask 1.5 - Review Phase III: Data Summary and Analysis

The data summary and analysis phase is composed of 1) siteconceptualization 2) the endangerment assessment and 3) the Remedial Investigation Report. A review of each reportwill be summarized in a written report and discussed attechnical review meetings as scheduled by RPM.

Subtask 1.5 - Review Endangerment Assessment (EA)

The endangerment Assessment is a very important aspect of the Data Summary and Analysis phase and is describedseparately. The endangerment assessment will consider and focus on those compounds found on-site that pose the greatestthreat to human health, welfare or the environment due to their toxicological properties, and concentrations of on­site compounds the E-A will also consider the fate of the compounds. A review of the endangerment assessment will beoutlined in a written report and discussed at technicalreview meetings.

Subtask 1.5 - Review Remedial Investigative Report

The overall purpose of the report is to present a compre­The report'J hensive site characterization of Salem Acres.

will review and analyze in detail the data for each specificmedium investigated. It will include all figures, maps, data tables etc. as outlined in the individual tasks. The RI report will identify and discuss the concentrations ofcontaminants in specific ~edia, migration pathways, and sensitive environmental and/or human receptors. The specif­ic format to be used in the development of the RI reportwill be based on the RI report format found in •Guidance on Remedial Investigations Under CERCLA• and subject to u.s.EPA Region I modifications. The data collected during the RI will be summarized in a report incorporating the results of the tasks specified in the Work Plan. The OversightContractor will conduct an in depth review of RI Report and identify any data gaps or inconsistencies and provide a written report for discussion with EPA technical review tea~. · The Contractor and RPM will meet with PRP Contractor to correct any deficiencies.

Subtask 1.6 - Review Phase IV Feasibility Study

The underlying purpose for the development of a Feasibility Study for Salem Acres is tofulfill the requirements stipulat­ed in the National Oil and Hazardous Substance ContingencyPlan (NCP; 50 FR 47912, 20 November 1985: 40 CFR 300) as may be further amended. More specifically, the FS willutilize the site characterization data obtained during the remedial investigation and the risk characterization obtainert

Page 4: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

0

-4:..

in the EA to develop and evaluate alternative •remedial actions• appropriate for the Salem Acres site as required by CERCLA Section 121. This alternative evaluation process will result in the identification of the most cost-effective alternative that is technologically feasible and reliable and which effectively mitigates or minimized the release of hazardous substances . to, and provides adequate protectionof, present and future public health, welfare or the environment and meets the requirements of CERCLA Section 121. Several subtasks and analyses comprise the Feasibility Study.

• Refinement of Site - Specific Remedial Response Objectives

• Refinement of Remedial Technologies

• Treatability studies (Remedial Investigation)

• Development of Remedial alternatives (Remedial Investigation)

• Initial Screening of Remedial Alternatives (Remedial - ­Investigation)

• Detailed Analysis of Limited Number of Remedial Alternatives

• Conceptual Design

Draft and Final Report .

The PRP's feasability study report, based on the remedial investigations, will be reviewed and comments will be summarired in a written report. Attendance and formal presentations at technical and legal review meetings will be provided as required by RPM.

Task 2 - Oversight Activities

2.1 Review existing documents pertinent to RI/RS Work Plan

Technical OVersight is required for this task to assure identification of all Federal and State ARAR's and compliance with EPA Policy Guidance. Treatability Studies must consider all available technologies.

Subtask 2.2 - Technical Oversight for Review of Project Operations Plan

Technical Oversight is required under this task. The contractor will be responsible for overseeing all aspects of media sampling. This includes QA/OC protocol, and chai~­of-custody. The contractor will also be responsible for

Page 5: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

....;

-s­

reviewing environmental sampling collected by the TAT team during Removal Action in Spring, 1987. This data will be reviewed for data validation, and OA/OC. This data will assist the PRP's contractor to develop sampling and analysis plan for the RI in order to complete the soil/sludge invest­igation for the DA-1 and DA-2. Modification to existing work plan will be neccessary to account for fieldwork completed in conjunction with EPA Removal Action.

A workplan for field oversight of the responsible party including split sampling and health and safety plan will be prepared. Emergency response activities occurred at Salem Acres in Spring 1987 and are continuing. Therefore, it will be required that the contractor participate during any oversight removal of soil, sludges, and contaminated surface water that may be removed or stabilized during RI activities. The Removal Action must be integrated with the Remedial Investigation and Feasibility Study.

-.....

Subtask 2.3 - Technical OVersight of the Groundwater RI/FS ':o:

Full time field monitoring of the RI activities, including well construction, equipment installation, and data collec­tion phases, will be performed. Pertinent field observations, will •Je documented in a letter report to RPM. Surface and sub-surface water, soil and sediment sampling will be collected and split with the PRP and sent to the CLP for analysis. Pertinent field observations will be documented in brief status letters and provided in a timely manner to the RPM and discussed as appropriate. oversight contractor will maintain detailed logs of all field activities and assure proper air monitoring is being conducted by PRP Contractor. Wind direction and odor releases must be strictly monitored.

Subtask 2.4 - Technical OVersight of Wetlands Assessment .fl!!l Technical oversight will be required, the Contractor will oversee the mapping of the wetlands area.

Subtask 2.5 - Technical oversight for Data Summary and Analysis Quality Objectives

No field oversight is required under this task. The Contactor will be responsible for reviewing any conceptualized model. Strict observance of EPA Data Oualit~ Objectives Guidance (10-86) must be adhered to and is the responsibility of the Oversight Contractor.

Page 6: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

I. I

~ II

.·:- -- . ::-- ­

I -6­

Task 3 - General Management

The Contractor will be responsible for reviewing monthly

progress and preparing financial reports for oversight.

costs, attending technical and legal review meetings, and

review and provide written analysis of all PRP technical

reports.

The Contractor will be responsible for assembling and

preparin~ draft ROD package including Public Review and

Comment. EPA will establish a Record of Decision (ROD)

Team early within the RI process and will review all sub­

missions (reports/deliverables) of the PRP Contractor

(The Maguire Group, Inc.). The Contractor will attend all

such technical review meetings and be responsible for

filling any data gaps on EPA technical or legal review

concerns in close coordination with Site RPM and provide

enforcement support of EPA PRP Consent Order.

Modifications to the EPA approved RI/FS workplan may become

necessary due to admendments or modifications to the NCP or

Federal and State ARARS. The Contractor and RPM will

closely coordinate and implement any necessary changes or

modifications of the RI/FS workplan and requirements of the~

PRP (SESD) under the terms of the EPA Administrative Order

of Consent with the PRP South Essex Sewerage District

(SESD). Contractor will provide any additional technical

support or oversight on any EPA enforcement action underIt will be

the EPA Administrative Order of Consent.neccessary for Oversight Coordinator to identify any

modifications or clarifications on initial review of the RI tasks which are presently

current RI/FS wo~k plan.bein; conducted as part of the EPA removal action must be

modified and incorporated into the the RI and FS (Sludge/

Soil Investigation, Treatability Studies, Wetland Assessment,

Groundwater Investigation, Topographic Mapping, Geologic

Investigation)

The Oversight Contractor must be guided by EPA Directive

9355,0-19 Interim Guidance on Superfund Selection of Remedy

(Dec.24, 1986) and SARA/CERCLA Section 121 - Cleanup

Standards.

If negotiations with PRP are neccessary, oversight Contractor

may be required to participate. All disputes arising under

terms of PRP Consent Order will require contractor

participation.

The Oversight Contractor will design, develop, establish

and keep current the Site Administrative Record. It will

be neccessary for the Contractor and the RPM to identify

all previous documents for this site.-whic.h should be

contained in the Administrative Record.

The Contractor will review the PRP Contractor's •project'~

• J

Schedule• and develop a tracking system to identify current

Page 7: STATEMENT OF WORK · Remedial Project Manager. Subtask 1.3.1 - Review existing geological/hydrogeological . information of the Salem Acres Site . An attempt must be made to identify

-7­

status and projected completion of all RI/FS Tasks, Sub­Tasks, reports due/received, comment returned, complied with, and compliance with Schedule of Deliverable• and any other events neccessary for tracking.

Community Relations Plan

Oversight Contractor will review, update and appropriately modify Community Relations Plan developed for the site by NUS - December, 1985. OVersight Contractor will be responsible for the conduct of the Community Relations Plan in close coordination with the RPM and EPA Community Relations staff.


Recommended