Statement showing the allotment of plots for the construction of Liquid Storage Tank Farm at Kandla Port Trsust

Plot No.

Name of Plot Allottee Allotment letter Issued on

Present Status

3 : M/s Aegis Logistics 17/04/2015 Construction not started yet.

4 : M/s Aegis Logistics 26/10/2015 Construction not started yet.

5 : M/s Aegis Logistics 26/10/2015 Construction not started yet.

7 : M/s Shreeji Liquid Storage Pvt. Ltd.

9/11/2015 Lease Deed has not been executed yet

10 : M/s Friends Logistics 16/04/2015 Construction started.

Remaining plots are under tendering / allotment process. Further, the copy of six monthly compliance reports of stipulated

conditions mentioned in CRZ Recommendation submitted by successful plot allottee are place as under with this compliance report.

Plot No. Name of Plot Allottee Annexure 3 M/s Aegis Logistics A 4 M/s Aegis Logistics A 5 M/s Aegis Logistics A 7 M/s Shreeji Liquid Storage Pvt. Ltd. Lease Deed has not

been executed yet 10 M/s Friends Logistics B

Name of Work: Development of plots for construction of liquid storage tank farms at

Kandla, District Kachchh . CRZ Recommendations: Letter No. ENV-10-2008-366-E March9, 2009 of Director

(Environment), Forest & Environment Department, GoG.

Sr. No. Conditions in CRZ Recommendation Letter Compliances

Specific Conditions

1

The project proponents shall strictly adhere to the provisions of the CRZ notification of 1991 and its amendments issued by the Ministry of Environment and Forest, GOI, from time to time.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

2

The project proponents shall obtain all necessary permissions from different Government Departments / agencies shall be obtained by the KPT before commencing the expansion activities.

Point Noted. NOC already granted by GPCB, GOG vide letter No. PC/NOC/CCA-Kutch – 78(2)/ GPCB ID 17832/14401 Dated : 13th, July, 2009. Further, GPCB vide letter no GPCB/CCA-Kutch- 1285/GPCB ID 46364/ dated 28/8/2016 had extended the validity period of NOC up to 5/08/2020.

3

The project proponent shall not handle any hazardous cargo or any classified chemicals at the site in question and this permission is valid only for the petroleum products and edible oils having no hazardous characteristics and as permissible in the CRZ notification, 1991, and its amendments issued from time to time.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

4 No ground water shall be tapped to meet the water requirements during the construction and /or operation phases.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

5 The Kandla Port Trust shall undertaken roof –top water harvesting in areas wherever it is feasible.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

6

The project proponents shall contribute towards the cost of any common study that may be carried out for the KPT region for environmental protection and management issues.

Point Noted and will be complied by Successful plot allottee.

7

The Kandla Port Trust shall duly incorporate the above-mentioned activities and update its Diaster Management Plan at the earliest and submit a copy to this Department.

Point Noted KPT already having updated Disaster Management Plan prepared by M/s Telos Consultancey, Mumbai.

8 The project proponents shall implement all the suggestion/ recommendations given by the NIOT in their Rapid EIA report.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

9

The project proponents shall strictly comply with all the conditions stipulated by the Gujarat Pollution Control Board in its Consent to Establish (NOC) and the CCA.

Point Noted and will be complied by Successful plot allottee.

10

The project proponents shall bear the cost of the external agency that may be appointed by this Department for supervision / monitoring of proposed activities and the environmental impacts of the proposed activities.

Point Noted and will be complied by Successful plot allottee.

11

The project proponents shall take up mangrove plantation in an area of 50 ha. As well as green belt development activities in consultation with the Gujarat Institute of Desert Ecology/Forest Department.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

12 Any other condition that may be stipulated by this Department from time to time for environmental protection / management purpose.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

General Conditions

1

The construction camps shall be located outside the CRZ area and the construction labour shall be provided with the necessary amenities, including sanitation, water supply and fuel and it shall be ensured that the environmental conditions are not deteriorated by the construction labours.

Point Noted. However, Adequate measures shall be taken by Successful plot allottee.

2

The KPT shall have to contribute financially for talking up the socio-economic upliftment activities in this region in construction with the Forest and Environment Department and the District Collector / District Development Officer.

CSR Work is already attending by KPT. Copy of CSR activities for the year 2014 – 2015 placed at Annexure I. However, Adequate Measures shall be taken by successful plot allottee.

3

A separate budget shall be earmarked for environmental management and socioeconomic activities and details there of shall be furnished to this Department as well as the MoEF, GOI. The details with respect to the expenditure from this budget head shall also be furnished.

A separate account for environmental protection has been maintained by Kandla Port Trust. Kandla Port has kept Rs.50.00 Lakhs in B.E. 2015 – 2016 and RBE Rs. 1.90 Crore for the year 2016 – 2017 under the scheme of “General Environment Management Programme” and approximate expenditure incurred till date is Rs.30.5 Lakhs. However, Adequate Measures shall be taken by successful plot allottee.

4

A separate environmental management cell with qualified personnel shall be created for environmental monitoring and management during construction and operational phases of the project.

KPT already having EMC constituted vide office order EG/WK/4660(EMC)/2010/270 dated 12/01/2011. Further, Kandla Port has also strengthening the Environmental cell by appointing two Environmental Experts and one Legal Person from M/s Precitech Laboratories Pvt. Ltd. They

are permanently stationed at Kandla Port. However, Adequate Measures shall be taken by successful plot allottee.

5

An Environmental reports indicating the changes, if any, with respect to the baseline environmental quality in the coastal and marine environment shall be submitted every year by the KPT to this Department as well as to the MoEF, GOI.

Point Noted. However, Adequate Measures shall be taken by successful plot allottee.

6

A six monthly reports on compliance of the conditions mentioned in this letter shall have to be furnished by the KPT on regular basis to this department/MoEF, GOI.

Point Noted and will be complied by successful plot allottee.

7

Any other condition that may be stipulated by this department from time to time for environmental protection/management purpose shall also have to be complied with by the KPT.

Point Noted and will be complied by successful plot allottee.

Following projects for up-grading/creating certain facilities under CSR activities have been identified with the total expenditure of Rs 236.22 lakhs for the year 2014 – 2015.

Sr. No

Details of Activities /Projects

1 Construction of Community Hall-cum school at Maheshwari Nagar, Gandhidham

2 Renovation of “Muktidham” at Kandla 3 Sunderpuri-1 valmiki community hall at Gandhidham. 4 Sunderpuri-2 valmiki community hall at Gandhidham 5 Ganeshnagar Community Hall at Gandhidham 6 Jagjivan Maheshwari community hall at Gandhidham. 7 Various works of Road of Sapanagar at Gandhidham 8 Construction of compound wall in the Dam of Jogninar village

Following CSR activities have been carried out at Tuna, Vandi, Rampar, etc.

9 Providing 3 Dustbins for solid waste collection at Mithi Rohar 10 Providing 400 mt Water supply line with size of 4” along with awada for

domestic animals at Khari Rohar 11 Tree Plantation along with road from Gaushala to Muslim Samaj along

with Parab for providing fresh water to village people at Kidana & Bharapar.

12 Providing Dustbins for solid waste collection and Tree plantation at Tuna.

13 Construction of overhead water Tank with capacity of 50,000 L for providing fresh water to village people at Wandi.

14 Providing 600 mt water supply line with size of 3” at Rampar 15 Providing 800 mt water supply line with size of 3” at Sanghad. 16 Providing 400 mt water supply line with size of 3” at Mathak. 17 Providing 3 Dustbins for solid waste collection at Shinay. 18 Providing Dustbins for solid waste collection and Tree plantation at

Antarjal. 19 Providing 3 Dustbins for solid waste collection at Galpadar.

Annexure - A

Annexure - B


Recommended