+ All Categories
Home > Documents > Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS...

Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS...

Date post: 25-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
21
[email protected] Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office, KEPCO Korea SUMMARY KEPCO is pushing variety efforts to lead green technologies and increase energy efficiency through smart grid. Superconductor technologies are at the center of them. KEPCO is focusing on high temperature superconducting (HTS) cables that enable high-capacity transmission and superconducting fault current limiters (SFCL) that control fault current effectively when faults occur. KEPCO is planning to verify that AC 22.9kV, 50MV, 500m HTS cable and 22.9 630A SFCL in Icheon substation by 2011. Also DC 80kV HTS cable and AC 154kV HTS cable are expected to demonstrate until 2014. In this paper, background of these projects, information and effects will be described. KEYWORDS High Temperature Superconducting Cable (HTS Cable); Fault Current Limiter; HVDC.”. Oct.26-28, 2011, Thailand PL-18 CIGRE-AORC 2011 www.cigre-aorc.com
Transcript
Page 1: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

[email protected]

Status and Future Direction of HTS Power Application in KEPCO

K. W. Jeong, B. S. Moon, S. K. Park

Grid Planning Office, KEPCO Korea

SUMMARY KEPCO is pushing variety efforts to lead green technologies and increase energy efficiency through smart grid. Superconductor technologies are at the center of them. KEPCO is focusing on high temperature superconducting (HTS) cables that enable high-capacity transmission and superconducting fault current limiters (SFCL) that control fault current effectively when faults occur. KEPCO is planning to verify that AC 22.9kV, 50MV, 500m HTS cable and 22.9 630A SFCL in Icheon substation by 2011. Also DC 80kV HTS cable and AC 154kV HTS cable are expected to demonstrate until 2014. In this paper, background of these projects, information and effects will be described. KEYWORDS High Temperature Superconducting Cable (HTS Cable); Fault Current Limiter; HVDC.”.

Oct.26-28, 2011, Thailand PL-18 CIGRE-AORC 2011 www.cigre-aorc.com

Page 2: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

2

1. Introduction

Environmental problems such as sustained rise in oil prices, fossil fuel depletion and global warming

have emerged as a big issue to the power industry [1]. Thus, Korea Electric Power Corporation

(KEPCO) is looking for new solutions about green growth policy and slowdown in profitability due to

the reduction of domestic demand. As a solution, KEPCO declared new management vision that

“Global Top 5 Utility for Green Energy". And low-carbon generation technologies, high-efficiency

power transmission technologies and new demand creation were selected as a strategic project. In this

category, including superconducting technology, HVDC, 8 technologies were chosen as green growth

power technologies [2].

Superconducting technology makes power facilities economic operation possible. Costly civil

construction cost, difficulty using road for electric pipelines construction, NIMBY phenomenon, need

to replace the aging old cable and increase of fault current due to growing load have been an issue in

KEPCO. Superconducting technology is emerging as a solution for those issues. Superconducting

technology enables the miniaturization of the equipment and operates with high efficiency, reduce

carbon emissions, save on the high construction cost. And also it is an eco-tech that solves the NIMBY

phenomenon. KEPCO is developing these superconducting technologies with DAPAS project, GENI

project, test of transmission class superconducting devices and Gochang power test center. In this

paper, the current status, plans for the future and expectations of superconductor technologies will be

described.

2. DAPAS project

DAPAS is an abbreviation of Development of Advance Power system by Applied

Superconductivity technologies Program. And it aimed to develop HTS power equipments

using superconducting wires from 2001 to 2011. One of result of DAPAS project is

developing world-class HTS wire manufacturing technology. HTS wires can be manufactured

with less than half price and twice faster than before. Also the world top class low-voltage

level high-capacity HTS cable was developed. It is 22.9kV 50MVA and it can send electrical

energy 15 times more than conventional cable. Core technology of 22.9kV 150MVA high-

capacity HTS cable to replace the conventional 154kV cable and design, manufacturing

technology of 154kV 1GVA HTS cable that has same capacity of 345kV or higher

conventional cable are also developed. The world top class 22.9kV 3kA SFCL was developed

and core components of 154kV 4kA SFCL have been developed which can apply to 154kV

power system. In addition, core components of 5MW superconductor motor were developed.

It is one-third volume and weight of conventional motor with 2% higher efficient.

3. GENI project

GENI is an abbreviation of Green superconducting Electric power Network at Icheon

substation. This project is installing 22.9kV HTS cable and SFCL in 154kV Icheon substation

to develop commercialized model of HTS equipment and operating techniques.

The HTS cable is connected to the secondary side of the main transformer in service. The

cable system operates at the distribution class voltage of 22.9 kV and the rated current is 1250

A. The cable is composed of three phase in a cryostat, a joint box, and two terminations. The

whole length of between terminations including a joint-box is approximately 500m. The

cooling system for the cable uses sub-cooled liquid nitrogen (LN2) as a coolant [3].

Page 3: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

3

Fig. 1. Layout of HTS cable and SFCL in 154kV Icheon S/S

SFCL is connected to the 22.9kV Jangpyung D/L. It operates at 22.9 kV and the rated

current is 630A at around 76K. SFCL is hybrid type using superconductor and fast switch.

Now 100m HTS cable with transmission class voltage of 154kV and the capacity of 1GVA

is testing in Gochang power test center and it is expected to demonstrate in KEPCO power

system until 2014.

4. Study on transmission class HTS application

Study on transmission class HTS application is based on GENI project and it is to expand

transmission class HTS application to KEPCO power system. KEPCO is aiming to

commercialize transmission class HTS cables and SFCL. Development, production,

installation, operation of DC 80 kV HTS cable and AC 154 kV HTS cable will be performed.

Developing AC 154kV HTS cable is completed and it is on testing at Gochang Power Test

Center. And also it will demonstrate at Guem-ahk C/S in Jeju Island by 2014. In case of DC

80kV HTS cable, core technology of cable will be developed in a year from July 2011.

Installation and demonstration will be progressed in Hanlim HVDC test bed by 2013. Tres

Amigas Super Station project will carry forward with DC 80kV HTS cable.

Fig. 2. Layout of Hanlim HVDC test bed

Page 4: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

4

5. Introduction of Gochang Power Test Center

Gochang Power Test Center is portal test site of KEPCO in power technologies. New

technologies in the fields of electric power and research and development outputs have been

conducting experiments for the demonstration. HTS cable systems laboratory and various

latest test equipments are available in test yard for underground cable which was complete in

June of 2010.

Fig. 3. Test yard for underground cable(left) and 154kV, 1GVA, 30m HTS cable system(right)

Main facilities of test yard are 100m length of 22.9kV, 50MVA HTS cable system, HTS

application testing laboratory, HTS cooling system room and various equipment. Now 154kV

1GVA HTS cable is on testing.

6. Tres Amigas Super Station Project

Fig. 4. Tres Amigas Super Station Concept

Tres Amigas Super Station (TASS) project is connecting three different power systems in

USA using HVDC inverters, energy storage, and HTS cables. These connections will be made

profits through electric power exchange, renewable energy connection and so on. On

February 2010 a consortium for TASS project has formed with LS cable. According to the

consortium, KEPCO is charge in engineering part such as HTS cable testing. And LS Cable

takes charge of manufacturing and installation part. American Superconductor (AMSC),

which has been delegated the superconducting cables technical evaluation from Tres Amigas

Page 5: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

5

LLC, was signed awards with KEPCO as a qualified superconducting cable provider. This

project is currently under negotiation.

7. Plans and expectations

KEPCO will secure the world's leading technology with the world first DC 80kV HTS cable

by 2013 and AC 154kV HTS cable. At the field of SFCL, after finishing the demonstration

the 22.9kV hybrid fault current limiter in Icheon S/S, the world top technology will be

secured with 154kV, 4kA SFCL. Final aim is developing 345kV SFCL. The world top

technology of HTS application will make short-range metro-centric grid environmentally

friendly, high efficiency of power transmission and better power quality. Also, when entering

overseas HTS project, we can provide HTS applications and engineering technology as a

package with manufacturers.

8. Conclusion

KEPCO has been preceding many projects to develop HTS technology. Starting with

DAPAS project, superconducting wires, cable, fault current limiter, motor and more products

have been developed. Through GENI project, HTS cables and SFCL are installed and

operated in Icheon substation. To develop transmission class of HTS cable, AC 154kV and

DC 80kV HTS cables are plan to design and manufacturing. And 154kV 1 GVA HTS cable is

on testing in Gochang Power Test Center. These cables will be demonstrated in Jeju Island.

This continued R&D will enable KEPCO secure the world’s leading HTS application

technology. KEPCO is expecting that HTS application technology will make KEPCO

advance the leading overseas markets for new revenue-generating, set the HTS technology

standard to take the technology leadership, contribute to green growth by building Eco-

friendly grid with high power quality, and reduce power costs.

BIBLIOGRAPHY [1] Lee, S. Y., "HTS application demonstration project and commercialization", in Efficiency Speed

Environment, No. 17, pp. 28-29 (2010)

[2] Won, Y. J., "8 Green Technologies of KEPCO and Superconductor", in Efficiency Speed

Environment, No. 16, pp. 20-21 (2010)

[3] Sohn, S. H., Lim, J. H., Yang, B. M., Lee, S. K., Jang, H. M., Kim, Y. H., Yang, H. S., Kim, D.

L., Kim, H. R., Won, Y. J., Hwang, S. D., “Design and Development of 500 m Long HTS Cable

System in the KEPCO Power Grid,” in Physica C superconductivity, Vol. 470, Issue 20, pp.

1567-1571 (2010).

Short Bio-data of Main Author

Kyuwon Jeong. He Received the B. S., M. S., and Ph. D. degrees in electrical

Engineering from SungKyunKwan University, Seoul, Korea, in 1993, 1995 and

2001, respectively. He is currently a Senior Manager in a Grid Planning Office at

Korea Electric Power Company (KEPCO) Seoul, Korea, His interests include High

Temperature Superconductor (HTS) facilities development and application & East-

Asian grid inter-connection.

Page 6: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

K. W. Jeong, B. S. Moon, S. K. Park

Grid Planning Office, KEPCO

Korea

Page 7: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

2

Contents

Page 8: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

3

1. Introduction

Why Superconductor ? Solution for environmental problems

Maldives’ cabinet underwater meeting(‘09.10)

Page 9: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

4

Decrease energy dependence and enhance energy self-sufficiency

Support adaptation to climate change impacts

Develop green technologies as future growth engines

Greening of industry

Develop cutting-edge industries

Set up policy infrastructure for green growth

Green city and green transport

Green revolution in lifestyle

Reduce carbon emissions

Country Enhance global cooperation on green growth

10 policy directions

1. Introduction

Korean Government’s Policy of Green growth

1

2

3

4

5

6

7

8

9

10

Field of KEPCO’s main role

Page 10: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

5

1. Introduction

KEPCO’s solutions for Environmental problems. Global Top 5 Energy &

Engineering Company

8 Green Technologies IGCC

CCS

Nuclear Power Generation

Smart grid

Superconductor

HVDC

Electric Vehicle

Electrical Energy House

Page 11: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

6

HTS Technology in KEPCO

Large Capacity & Low loss + Eco-friendly

HTS applications

Page 12: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

7

2. DAPAS Project

DAPAS : Development of Advanced Power System by Applied Superconductivity technologies

Develop HTS Power equipments using superconductor wires(KEPCO, KERI, LS cable, SeoNam etc.)

Project period : 2004 ~ 2011

HTS

Cable

FCL

2G

Wire

- The World top class manufacturing technology- manufactured with half price less and twice faster

- 22.9kV 50MVA, send electrical energy 15 times more than conventional cable. - Core technology of 22.9kV 150MVA, 154kV 1GVA HTS cable are developed

Motor

- The world top class 22.9kV 3kA SFCL was developed.- Also core components of 154kV 4kA SFCL were developed.

- Core components of 5MW superconductor motor were developed.- One-third volume and weight of conventional motor with 2% higher efficient

Page 13: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

8

3. GENI Project

GENI : Green Superconducting Electric Power Network at Icheon S/S

Installing 22.9kV HTS cable and SFCL in Icheon substation to develop commercialized model of HTS equipment and operating techniques. (KEPCO, LS cable, KERI etc.)

Project period : 2008 ~ present & Planning 2nd stage

HTS

Cable

SFCL

- 22.9 kV, 50MVA, 1250 A, 500m @ 2nd side of #5M.Tr.- 3 phase in a cryostat, a joint box, and two terminations. - Sub cooled liquid nitrogen (LN2)

- 22.9kV 630A, SFCL @ Jangpyung D/L.- hybrid type : superconductor + fast switch.

Page 14: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

9

Layout of HTS cable and SFCL in Icheon S/S

Page 15: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

10

4. Transmission class HTS applications

New project of HTS application in KEPCO grid.Development, production, installation, HTS cables and SFCL(KEPCO,

KEPRI, LS Cable etc.)

Project period : 2011.7 ~ 2016.6

Total budget : \75.4 bil ($68 mil)

Tres Amigas Super Station project will carry forward with DC 80kV HTS cable

HTS

Cable

SFCL

- DC 80kV HTS cable, 500m(2013)- AC 154kV HTS cable, 1km(2014)- Guem-ahk C/S in Jeju Island

- AC 154kV 4000A

Page 16: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

11

Direction for new project

+

Expanding Base

Collaboration (Industry-Academy-R&D)

Domestic (wire, cooling systems)

Longer cable (Cooling system development)

Required Technologies

EconomicReliabilities

Downsizing (Cryogenic Insulation development)

Page 17: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

12

Layout of Hanlim test bed

HanlimC/C

Hanlim

154kV West Jeju- Hanlim T/L

154kVACHTS(~1km,2014)

#2HVDC(2011)

(250kV,400MW)

DC OverHead(ACCC/TW) (±80kV,~5km,2011)

Anduk

W. Jeju

MainlandNewTownin Jeju

154kV Hanlim-Anduk T/LDCHTS(~0.5km,2013)

GumAk C/S(80kV,60MW)

154kV West Jeju –Anduk T/L

: AC: DC: HTS

Page 18: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

13

5. Gochang Power Test Center

Portal test site of KEPCO in power technologies

Test yard for Underground Cable(2010) : HTS cable systems laboratory, various test equipments

Test Yard for Underground Cable 154kV, 1GVA, 30m HTS cable system

Page 19: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

14

6. Tres Amigas Super Station Project

Tres Amigas Super Station(TASS) Connecting 3 different power system

Using HVDC inverters, energy storage, and HTS cables

KEPCO, LS cable formed a consortium(2010) KEPCO : Engineering

LS Cable : manufacturing and installation

TASS project is under negotiation

Page 20: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

15

7. Plans and expectations

Short-range metro-centric grid environmentally friendly, high efficiency of power transmission better power quality.

Entering overseas HTS project Package of HTS applications and engineering technology

with manufacturers

’09 ’10 ’11 ’12 ’13 ’14 ’15 future

HTSApplications

22.9kV HTSC154kV HTSC

345kV SFCL154kV SFCL22.9kV SFCL

DC 80kV HTSC

Longer HTSC(above 3km)

Page 21: Status and Future Direction of HTS Power Application in KEPCO · Status and Future Direction of HTS Power Application in KEPCO K. W. Jeong, B. S. Moon, S. K. Park Grid Planning Office,

16

8. Conclusion

Since KEPCO had selected ‘8 Green Technologies’, HTS applications are

developed through many projects.

In DAPAS project, superconducting wires, HTS cable, SFCL, motor and more

products have been developed.

Through GENI project, 22.9kV HTS cables and SFCL are installed and operated

in Icheon substation.

To develop transmission class of HTS cable, AC 154kV and DC 80kV HTS cables

are plan to design and manufacturing. These cables will be demonstrated in Jeju

Island by 2014. And 154kV 1 GVA HTS cable is on testing in Gochang Power

Test Center.

HTS application technology will make KEPCO advance the leading overseas

markets for new revenue-generating, set the HTS technology standard to take

the technology leadership, contribute to green growth by building Eco-friendly

grid with high power quality, and reduce power costs.


Recommended