Status and Plans of the CMS Experiment
Darin AcostaUniversity of FloridaOn behalf of the CMS Collaboration
Dijet recorded 12/6/09, ET~25 GeV
17 December 2009
D.Acosta - Miami 2009 2
Outline Start-up of the LHC State of the CMS experiment Recent results from the LHC start-up Prospects for early physics measurements
17 December 2009
D.Acosta - Miami 2009 3
2009/10 LHC Beam commissioning strategy
Global machine checkout
Essential 450 GeV commissioning
System/beam commissioning
Machine protection commissioning 2
3.5 TeV beam & first collisions
450 GeV collisions
Ramp commissioning to 1.2 TeV
Full machine protection qualification
Pilot physics
System/beam commissioning
Machine protection commissioning 1
Energy Safe Very Safe
450 1 e12 1 e11
1 TeV 2.5 e11 2.5 e10
3.5 TeV 3.0 e10 probe
Experiments’ magnets at 450 GeV
Trial ramps
Xmas
2010
17 December 2009
D.Acosta - Miami 2009 4
The LHC Start-Up in 2009 Injection Tests Oct.23-25 & Nov.7-9 Nov.20, 18:00, Start of 2009 beam circulation
First beam 1 circulation by 20:40 RF captured beam 1 for several
minutes by 21:50, 4 hours after start! Beam 2 captured by 0:10
Nov.23, First collisions at 900 GeV 13:30, both beams in, evidence for collisions
at ATLAS (P1), LHCb, and ALICE 19:00, Second attempt for CMS (P5), tuning,
collisions seen! About 30min. Dec.6, First physics fills
5:00, collisions, 4 proton bunches/beam, ~4 hours Dec.8, Acceleration
21:44: both beams ramped to 1.18 TeV each Dec.11, Higher proton intensities (7E10)
Starting to accumulate luminosity at 900 GeV Dec.14, Collisions at 2.36 TeV !
4:00: about 2 hours of highest energy pp collisions 21:00: still higher intensity 900 GeV collisions (16 bunches, 1.8E11)
17 December 2009
D.Acosta - Miami 2009 5
Start of the LHC Physics Program !
23-Nov-09
Spring-2010
First collisions on Nov.23 at 900 GeV
~0.1 Hz collisions L ~ few 1024 cm-2s-1
In the last week, collisions at 900 and 2236 GeV
~10Hz collisions L ~ few 1026 cm-2s-1
Ultimately, the LHC program should take us to:
14 TeV 109 Hz collisions L ~ 1034 cm-2s-1
14-Dec-09
= 1
/L
2011
17 December 2009
D.Acosta - Miami 2009 6
The Compact Muon Solenoid (CMS)
(4T) 210 m2 of silicon sensors: 9.6M (Str) & 66M (Pix) channels
PbWO4 crystals (76K)
Scintillator/brass
Iron / Quartz fiber fwd calorimeter, 3<||<5;
+ Castor, 5<||<6.55
+ Zero Degree Calorimeter
Cathode Strip Chambers, Drift Tubes, Resistive Plates
+ Trigger and data acquisition systems: 50 kHz into High Level Trigger (100 kHz max), record O(100) Hz
2 planes of silicon modules for ECAL
17 December 2009
D.Acosta - Miami 2009 7
CMS Detector SubsystemsBarrel pixelsBarrel pixels
Silicon Silicon strip modulesstrip modules
Crystal calorimeter, Crystal calorimeter, 1/2 of one endcap1/2 of one endcap
Hadron Hadron calorimeter calorimeter (1/2 barrel)(1/2 barrel)
Magnet Magnet
Endcap muon Endcap muon system (1/8 disks)system (1/8 disks)
Barrel muon Barrel muon system (1/5 wheels)system (1/5 wheels)
17 December 2009
D.Acosta - Miami 2009 8
CMS in Closed Configuration
17 December 2009
D.Acosta - Miami 2009 9
CMS Global Commissioning Program
During 2007 and 2008, commissioned progressively larger fractions of the systems for global data-taking
Integration of detector components and data acquisition system Synchronization of detector signals with cosmic rays Calibration and alignment with cosmic rays
Restarted in 2009 during last shutdown
17 December 2009
D.Acosta - Miami 2009 10
First LHC Beams, 2008HCAL energy ECAL energy
particle debris
Beam onto collimators (splash events)
Halo muons from circulating beams
But program cut shortdue to the major fault in one LHC sector
17 December 2009
D.Acosta - Miami 2009 11
The Cosmic Runs At Four Tesla CRAFT08:
23 days from Oct.13 – Nov.11, 2008 270M cosmic triggers with B=3.8T
Followed by shutdown, then: CRAFT09:
40 days from July 23 – Sept.1, 2009 320M cosmic triggers with B=3.8T
Commission the experimentwith magnet at operating field
Operate the experiment for an extended period (month)
Collect ~300M cosmics for detector studies
17 December 2009
D.Acosta - Miami 2009 12
Detector Performance Publications 23 CMS detector performance papers (500 pages!)
submitted to the Journal of Instrumentation based on data from CRAFT08 and 2008 beams
Available on ArXiv: http://arxiv.org/find/all/1/au:+CMS/0/1/0/all/0/1?skip=0&query_id=9f85c0e5eae277b4
To appear in a single volume of JINST Coverage:
Performance of all major detector systems, including trigger
Precision mapping of magnetic field in the steel return yoke Performance of track and muon reconstruction algorithms Alignment and calibration
17 December 2009
D.Acosta - Miami 2009 13
CRAFT Results in Thumbnails
17 December 2009
D.Acosta - Miami 2009 14
Alignment of the Silicon Strip and Pixel Trackers
Distributions of the means ofthe residuals, barrel components
Much improved from the survey accuracy of O(100m)
Close to ideal alignment even before collisions
Barrel Pixel: 2.6 m
Tracker outer barrel: 2.6 m
Tracker inner barrel: 2.5 m
17 December 2009
D.Acosta - Miami 2009 15
Tracking Performance Efficiency and resolution measurements
Tag a muon in the muon detectors and study the inner tracker (or vice versa)
Split a cosmic track into 2 “legs” and compare them Silicon tracking efficiency
99.5% for muons passing completely through the detector and close to the beamline
Muon momentum resolution 1% for pT=10 GeV, increasing to 8% for pT~500 GeV
(should improve to 5% when detectors are perfectly aligned)
17 December 2009
D.Acosta - Miami 2009 16
’08-’09 Shutdown – CMS Activities After the cosmics run (Nov ‘08), detector was opened for
maintenance & repair activities, installation of preshower subdetector & CASTOR forward calorimeter.
Work progressed according to the schedule laid down in Nov. 2008.
Major Accomplishments: Removal, repair, and re-insertion of the forward pixel system Installation and commissioning of the preshower detector Completion of maintenance & (some) repairs of all sub-systems Completion of the revision of the tracker cooling plant Understanding of magnetic field in the return iron-yoke Overpressure protection (new item) Re-commissioning of CMS New TOSCA B Field Map – agreement of data & MC now better
than 2% Large Monte Carlo production & analysis exercise at 10 & 7 TeV
17 December 2009
D.Acosta - Miami 2009 17
Sub
dete
ctor
Operational Fractions
Detector and Data-Taking Status for CRAFT09
TID TEC
1 control ring
1 cooling loop
Strips: 98.1%Pixels: 98.5%Strip Tracker Status Map:
Average CRAFT09 data-taking efficiency: 71%Without service disruptions: > 80%
2009 LHC Operations
17 December 2009
D.Acosta - Miami 2009 19
Beam “Splash” (~109 protons onto upstream collimator)
Beam 2
Nov.7-9, 2009 injectiontests
ECAL energy deposits in red, HCAL energy deposits in blue (light blue for HF and HO)
RPC muon hits are in yellow, and CSC muon hits are in magenta.
Silicon strips and pixels off for safety
17 December 2009
D.Acosta - Miami 2009 20
ECAL vs. HCAL Observed Energy O(1000) splash events in a wide
range of beam intensity Good linear correlation between
ECAL and HCAL measured energies Response in EndCap+ is lower than EndCap-
due to particle losses from material in CMS
Barrel
EndCap+
EndCap-
O(1M) muons per event 1000’s of TeV/event!
17 December 2009
D.Acosta - Miami 2009 21
Synchronization with Splash Events, HCAL
HCAL Barrel: RMS= 1.9 ns
HCAL Endcap: RMS= 2.3 ns
Splash09 - Before Splash09: After
HCAL Barrel: RMS= 1.2 ns
HCAL Endcap: RMS= 1.4 ns
Similar timing improvements were achieved in ECAL Endcap and Preshower
Corrections checked with new splash events
17 December 2009
D.Acosta - Miami 2009 22
ECAL Occupancy CMS 2009 Preliminary
ECAL Endcap - ECAL Endcap +
ECAL BarrelECAL Barrel
Average energy per crystal in ECAL
White regions are masked channels
0.9% of total one quarter may
be recovered. Use coarse trigger
data to recover allbut 0.15%
Energy modulations are combination of energy flow traversing CMS & geometry effects.
For the hadron calorimeter, no dead channels
=0
=1.5
= -1.5
=1.5
= 3
beam
bott
om
17 December 2009
D.Acosta - Miami 2009 23
Collisions ! Dec.6, Early Sunday morning
First “physics” fill of the LHC with 450 GeV beams colliding for several hours
(Very first collisions were provided Nov.23 with partial tracking) All CMS detectors powered, including pixel and strip
trackers, magnet on
17 December 2009
D.Acosta - Miami 2009 24
Muons Much lower rate than cosmic rays at this luminosity
17 December 2009
D.Acosta - Miami 2009 25
Dimuon Candidate at 2.36 TeV
17 December 2009
D.Acosta - Miami 2009 26
Rediscover mesons: 0
Mass uncorrected for effects of the readout threshold of ECAL that had to be lowered, and material effects
Data will be used to intercalibrate the ECAL crystals, precision expected is O(1%)
Data Simulation
17 December 2009
D.Acosta - Miami 2009 27
Rediscover mesons:
Data Simulation
Mass and width compatible with MC yield scale as expected:
N() / N(0) = 0.020 ± 0.003 DATA N() / N(0) = 0.021 ± 0.003 MC
17 December 2009
D.Acosta - Miami 2009 28
Rediscover mesons and baryons: K0, K0s
Ks
0.4975 GeV 1.115 GeV
Tracking reconstruction software working These events tagged by separated vertex (V0)
Magnetic field calibrated (mapped to precision <0.1%)
17 December 2009
D.Acosta - Miami 2009 29
K0s Candidate at 2.36 TeV
17 December 2009
D.Acosta - Miami 2009 30
Rediscover the Standard Model: Jets
CMS Experiment at the LHC, CERNDate Recorded: 2009-12-06 07:18 GMTRun/Event: 123596 / 6732761 Candidate Dijet Collision Event
Anti-KT algorithm with cone size R=0.7
Jet 1 Jet 2
Corrected pT (GeV) 24 26
0.3 2.0
2.5 -0.7
CMS Preliminary
17 December 2009
D.Acosta - Miami 2009 31
Multi-jet Candidate at 2.36 TeV
17 December 2009
D.Acosta - Miami 2009 32
(To come) Rediscover the Standard Model: QCD
Soft: Charged hadron measurements at 900 GeV up to 10 TeV
Pseudo-rapidity distribution expectedwith only 5K events
Also underlying event properties 10 TeV
Hard: Inclusive jet cross section measurements Example for 10pb-1 at 10 TeV
with kT algoirthm
17 December 2009
D.Acosta - Miami 2009 33
(To come) Rediscover the Standard Model: EWK
To be followed by measurements of, for example, the rapidity distribution and PT(Z) -- understanding of PDFs and pQCD at LHC
Isolated muon with PT>25 and ||<2 Two isolated electrons with ET>20 and ||<2.5
Systematic uncertainty: 2.4% 10% (lumi)
10 TeV 10pb-1
17 December 2009
D.Acosta - Miami 2009 34
Discover! New Z’ gauge boson Feasibility study
Luminosity required for 5 discovery as a function of Z’ mass in dimuon decay channel (very similar for dielectron) for two models and for several machine collision energies
Need 100 pb-1 at 10 TeV for discovery of mass > 1 TeV
17 December 2009
D.Acosta - Miami 2009 35
Discover! SUSY Opposite sign dileptons
Dilepton edges in MSSM:
PTl >16; 3 jets ET>100, 50, 50; MET>100
Feasibility study of LM0: m0=200, m1/2=160, A0=-400, µ>0,
tan=10 = 150 pb 52.7 GeV endpoint
200pb-1 of 10 TeV data, fit shape: Mll,max = 51.31.5(stat) 0.9(syst)
Opposite sign, ee, Opposite sign, e +
0 02 1 0 0
2 1
p
p
g~
b~
b
b
01~
02~
~
q~
17 December 2009
D.Acosta - Miami 2009 36
Future Plans LHC stopped 2009 operations yesterday, Dec-16 A short shutdown follows for XMAS and to complete
commissioning of the LHC quench protection system in January
CMS will use the short shutdown for maintenance Replacement of cooling circuit connections on endcaps
We resume operations in Feb-2010 with operations at a 3.5 TeV beam energy
Deemed safe with remaining anomalous resistance in some splices between magnets
Possible step-up to 4 to 5 TeV beam energy after ~3 months, requiring one month to reestablish physics, and running another 4-5 months
Heavy ion collider run for 1 month at end
17 December 2009
D.Acosta - Miami 2009 37
Conclusions After a long road of design, construction, and commissioning the
CMS experiment and the LHC are here! All detector systems are operational Excellent synchronization, alignment and calibration precision
achieved using cosmic rays and initial beam data Achieved high operational data-taking efficiency Recorded data from cosmic muons, “beam splashes”,
and collisions at 900 and 2360 GeV (& many known resonances seen!)
CMS is ready for physics !
Backup
17 December 2009
D.Acosta - Miami 2009 39
The Large Hadron Collider (LHC) 27 km ring 7 TeV maximum
beam energy 3.5 TeV for start
of 2010 0.45 TeV @ injection
1232 superconducting 8.4T dipole magnets @ T=1.9ºK
4 experiments ATLAS, CMS ALICE, LHCb
First launched Sept.10, 2008
17 December 2009
D.Acosta - Miami 2009 40
CRAFT09 Data Acquisition
Efficient running with 80 kHz input rate
All systems in, including Preshower detector
> 4700 applications running on 672 PCs
for High Level Trigger
Huge muon trigger rate, DAQ still ok
17 December 2009
D.Acosta - Miami 2009 41
Muon dE/dX Measured in Calorimeters ECAL: Measurement of the
absolute energy loss in PbWO4 as a function of measured muon momentum, compared to calculation
collision
radi
ativ
e
HCAL: Measurement of the energy loss in the barrel hadron calorimeter as a function of measured muon momentum, compared to Monte Carlo
17 December 2009
D.Acosta - Miami 2009 4242
Silicon Strip Tracker: Signal / Noise
Deconvolution mode is the APV readout mode planned for LHC operation (narrow pulse shaping to minimize pile-up from out-of-time collisions)
Implemented for second half of CRAFT09
The ratio S/N (Peak/Deconvolution) is ~ 1.7 as expected (x1.5 noise and x0.9 signal) and sufficiently high for efficient hit identification
QuickTime™ et undécompresseur
sont requis pour visionner cette image.
APV Pulse shape
Peak mode
Deconvolution mode
Change of cosmic trigger typeS
igna
l to
nois
e ra
tio
CMS preliminary
Signal/Noise