Date post: | 20-Dec-2015 |
Category: |
Documents |
View: | 213 times |
Download: | 0 times |
04/18/23 University of Sheffield 2
Target Controller Hardware
Single key to ‘Enable’ system
• Hardware for Stage 1 upgrade is now complete
– May need to add extra wires if additional outputs are required – but already have 3 spare BNC’s on back panel
04/18/23 University of Sheffield 3
Target Controller Firmware
• Core control firmware is complete & functionalCore control firmware is complete & functional
• Remaining work primarily involves integration of control logic & USB interface
– Have demonstrated rudimentary Target operations under computer control (park/hold & start/stop actuation)
– Need to expose full functionality to USB interface for integration with EPICS
• Also require an interlock to prevent Target Frame from lowering if Target not in hold position (& to raise Frame in the event of any serious error condition)
– Logic exists in FPGA, but need to route Frame inhibit signal from MLCR to Target Frame Controller (can use existing spare cable) & build small relay switch interface
– Daresbury need to update Frame Controller PLC wiring/logic – planned for January
04/18/23 University of Sheffield 4
Target Controller Software
• Software also nearing completion
– Hardware driver framework in place
• User interface has been defined
– Have implemented all EPICS server / client functionality
• Tested using ‘virtual’ Target Controller Device
• Remaining work: implement low-level hardware driver ‘plug-in’
– Being developed in parallel with firmware/USB interface integration task
04/18/23 University of Sheffield 5
ISIS BPS
• ISIS requires a MICE Target BPS signal
– All other targets in ISIS produce them – MICE cannot be an exception
• Normally require a BPS to be generated from 2 signals using 2 different technologies
• Valid signals must be ‘hardwired’ – cannot be produced in firmware/software
– Cannot use Target controller FPGA
• Need robust methods of checking whether Target has dropped
• Will require some level of redesign of Target hardware
– Addition of limit switches?
– Additional optical readout channel?
– Have not yet commenced work on this – it will not be trivial
• Craig will set up a meeting early next year between Paul S & Mark Arnold, where implementation options will be investigated
04/18/23 University of Sheffield 6
Schedule• Plan to have Stage 1 upgrade complete & installed by end of January
• However, Paul S has very recently been signed off work with a back problem
• Currently not possible to estimate when he will be fit to return
• This will cause an unknown delay to the project
– Cannot predict whether installation before end of shutdown will now be possible
04/18/23 University of Sheffield 7
Summary
• Good progress with hardware, firmware & software
– Remaining work primarily involves integration of firmware & software
• Need to implement a BPS signal – requires some Target redesign
– Details to be worked out early next year
• Were on schedule to complete Stage 1 upgrade by end of January
– Health issues mean this may not be possible (should know more by mid-January)