Steam-Air-Injection:
In-Situ-Remediation of a CHC Contamination
below a historical BuildingOliver Trötschler, Hans-Peter Koschitzky
Universität Stuttgart, VEGAS
Pfaffenwaldring 61
D-70550 Stuttgart (Germany)
http://www.vegasinfo.de
A contaminant source of chlorinated hydrocarbons (CHC, mainly PCE) under an
old historical building caused by a former dry-cleaner in the unsaturated and
saturated zone leads to a long persistant contaminant plume.
The groundwater level is in the range of 3 - 3.5 m b.g.s..
SituationSituation
1.5 m: replenishments
2.5 m: sandy soil with fine silt
layers (kf < 1 x 10-5 m/s)
4 m: fine silty sand
(kf ~ 5 x 10-5 m/s)
7 m: fine and medium sand
(kf ~ 0.8 - 3 x 10-4 m/s)
8 m: medium sand with gravel
(kf ~ 0.5 - 2 x 10-3 m/s)
10 m: gravel
(kf ~ 3 - 8 x 10-3 m/s)
Numerical SimulationNumerical Simulation
Steps of the pilot injection:
(1) One week groundwater and soil-vapour extraction to achieve constant
conditions; PCE extraction: 70 kg
(2) One week Air-Sparging: injection of approx. 20 m³/h air through the
injection well; PCE extraction: 33 kg
(3) Four weeks injection of a steam-air mixture (105 - 110°C), decreasing
rates from 200 to 120 kg/h; PCE extraction: 200 kg
(4) Six weeks cooling phase: starting with one week of air sparging
accompanied by soil-vapour and groundwater extraction;
PCE extraction: 135 kg.
Total extraction of more than 440 kg PCE confirmed the
efficiency of the steam air injection at the location
Contact:
Hans-Peter Koschitzky, Oliver Trötschler
Principle of Remediation Technology and local situationPrinciple of Remediation Technology and local situation
Full Scale Remediation DesignFull Scale Remediation Design
vertical expansion of the
contamination approx. 6 - 7 m b.g.s.
unsaturatted zone: concentrations of
PCE in the soil samples up to 3800
mg/kg soil (1 - 2.5 m b.g.s)
saturated zone (3-4 m b.g.s.), concen-
trations up to 850 mg/kg, as well as 70
mg/kg (4-5 m), and 6 mg/kg (5-6 m)
CHC concentration up to 40 - 60 mg/l
of CHC in the groundwater indicate
residual NAPL in the near field of the
sampling location (source zone). ResultsResults
-800
-700
-600
-500
-400
-300
-200
-100
-400 -300 -200 -100 0 100
-300-200
-1000
XY
Z
temperature100
95
90
85
80
7570
65
60
55
50
45
4035
30
25
20
15
10
I6BR38
E8EK2
24 h
-800
-700
-600
-500
-400
-300
-200
-100
-400 -300 -200 -100 0 100
-300-200
-1000
XY
Z
temperature
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
I6BR38
E8EK2
168 h
-800
-700
-600
-500
-400
-300
-200
-100
-400 -300 -200 -100 0 100
-300-200
-1000
XY
Z
temperature
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
I6BR38
E8EK2
552 h
-800
-700
-600
-500
-400
-300
-200
-100
-400 -300 -200 -100 0 100
-300-200
-1000
XY
Z
temperature
100
95
90
85
80
75
70
65
60
5550
45
40
35
30
25
20
15
10
I6BR38
E8EK2
48 h
2 d
21 d7 d
1 d
Partners and AcknowledgementPartners and Acknowledgement
Pilot - TestPilot - Test
t = 6 h t = 12 h
t = 24 h t = 36 h
36 h)
-10
-9
-8
-7
-6
-5
-4
-3
273 283 293 303 313 323 333 343 353 363 373 383
T [K]
z [
m]
uG
OK
TC 7 (0,1 m) TC 1 (0,5 m) TC 3 (2,05 m) TC 5 (2,9 m)
TC 7 mess TC 1 mess TC 3 mess TC 5 mess
36 h)
-10
-9
-8
-7
-6
-5
-4
-3
273 283 293 303 313 323 333 343 353 363 373 383
T [K]
z [
m]
uG
OK
TC 7 (0,1 m) TC 2 (0,9 m) TC 4 (1,55 m) TC 6 (4,25 m)
TC 7 mess TC 2 mess TC 4 mess TC 6 mess
0,9
1,55
4,33
0,5
2,0
5
3,0
1
0 1 m 2 m 3 m 4 m 5 m
1,27
2,9
1
4,24
0,1
1
7,0
8
Source zone
A mixture of steam-air is injected into the contaminated zones to evaporate
organic contaminants by active convective heating of the soil to steam-air temp-
erature. The contaminants are carried by the amount of hot air towards the soil-
vapour extraction wells. The extracted soil-vapour is treated conventionally on-
site.
TSVE can be applied for organic contaminants with boiling points lower than
180°C and aquifers of medium permeability, e.g. sands and silty sands.
In case of a DNAPL contamination the risk of a downward migration due to the
accumulation of the organic phase in front of the steam front has to be prevented.
Therefore, steam-air injection is advised. The injected air functions as an inert gas
to transport the evaporated organic phase to prevent accumulation, the steam
serves as the energy-transfer medium.
On behalf of the environmental agency of the city of
Karlsruhe, a pilot remediation test was carried out using one
injection well for the steam-air mixture with parallel soil-
vapour and groundwater extraction.
The pilot was accompanied by the numerical simulation of the
steam propagation. The goal was to determine the range of
the steam propagation in the saturated zone, as well as to
verify the site-specific applicability and efficiency of the
remediation technology in order to design the full scale
application.
steam extension radius > 3 m within some days (200 kg/h steam-air)
steam zone extension maintained with an injection of 120 kg/h - 140 kg/h to
heat up highly contaminated silt layer by conduction (steam override),
fast heat propagation during the first two days in the medium permeable
sand layers below 5 m (temperatures between 80 and 100°C),
after approximately 20 days, the subsurface between 2 - 7 m bgs. was
effectively heated (> 90°C) with 3 m radius, most of the pollutants were
evaporized and extracted (> 99,5 % mass removal due to soil sampling)
The accompanying numerical simulation for the determination „of the thermal
radius“ as a basis for the design of the full scale remediation (distance of injection
wells, determination of the mass flows) requires a detailed investigation of the
subsurface (vertical distribution of kf-values). The anisotropy of the layered aquifer
plays a significant role in steam propagation.
The pilot application was funded by the environmental agency of Karlsruhe.
The consultant dplan, Karlsruhe was responsible project director and
controller.
Based on the results of the pilot the full scale remediation was designed, the time
frame (less than 1 year) and the costs (515 k€, ~ 300 € p. m³ soil) were estimated.
Declined and horizontal drilling is required to install injection and extraction wells
due to local situation (historical building).
On-Site Treatment Installation
Historical building “source zone”
Scheme of TSVE (Thermally Enhanced Soil Vapour Extraction) in Karlsruhe
Top view of test field
Sketch of test field
I6: steam injection well
E8: SVE wells
EK2, Br38: SVE and GW wells
T1 – T8: in-situ
temperature
measurement
Numerical simulation of steam
propagation (S. Ochs, IWS, Universität Stuttgart)
Comparison of temperature distribution: simulation and field
measurements (S. Ochs, IWS, Universität Stuttgart)
The numerical simulation
almost matches perfectly
the field data for an
anisotropy (kh/kv) of 3.
For distances larger than
3 m the simulation
underestimates the
steam propagation. This
may be addressed to
inhomogeneities of the
subsurface or a lower
permeable soil compared
to the simulation.
Steam propagation in the target zone
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
0 2 4 6 8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56
58
60
62
64
66
68
70
72
74
76
78
80
82
84
time[d]
co
nc
en
tra
tio
n P
CE
(g
/m³)
SV
E
0
50
100
150
200
250
300
350
400
450
500
27
.06
.05 1
2:0
0
29
.06
.05 1
2:0
0
01
.07
.05 1
2:0
0
03
.07
.05 1
2:0
0
05
.07
.05 1
2:0
0
07
.07
.05 1
2:0
0
09
.07
.05 1
2:0
0
11
.07
.05 1
2:0
0
13
.07
.05 1
2:0
0
15
.07
.05 1
2:0
0
17
.07
.05 1
2:0
0
19
.07
.05 1
2:0
0
21
.07
.05 1
2:0
0
23
.07
.05 1
2:0
0
25
.07
.05 1
2:0
0
27
.07
.05 1
2:0
0
29
.07
.05 1
2:0
0
31
.07
.05 1
2:0
0
02
.08
.05 1
2:0
0
04
.08
.05 1
2:0
0
06
.08
.05 1
2:0
0
08
.08
.05 1
2:0
0
10
.08
.05 1
2:0
0
12
.08
.05 1
2:0
0
14
.08
.05 1
2:0
0
16
.08
.05 1
2:0
0
18
.08
.05 1
2:0
0
20
.08
.05 1
2:0
0
22
.08
.05 1
2:0
0
24
.08
.05 1
2:0
0
26
.08
.05 1
2:0
0
28
.08
.05 1
2:0
0
30
.08
.05 1
2:0
0
01
.09
.05 1
2:0
0
03
.09
.05 1
2:0
0
05
.09
.05 1
2:0
0
07
.09
.05 1
2:0
0
09
.09
.05 1
2:0
0
11
.09
.05 1
2:0
0
13
.09
.05 1
2:0
0
15
.09
.05 1
2:0
0
17
.09
.05 1
2:0
0
19
.09
.05 1
2:0
0
su
m P
CE
[k
g]
PCE (g/m³)
Summe LCKW (g/m³), dplan
Summenkurve PCE (kg)
Summenkurve LCKW (kg), dplan
Air
Sparging
steam-air injection (17 kg/h air)
180 k
g/h
cooling phase120 kg/h steam
100
kg/h
steam
air
(25 kg/h)
Air
SpargingSVE
Mass balance based on SVE
123
4 (GW-Infiltration)
wells:
SI: Injection well: declined drilling, 2", 8 m bgs.
E: Extraction well: vertical drilling, 4", 5 m bgs.
EK: combined well (SVE + GW) vertical drilling, 4",
10 m bgs.
horizontal well SVE-Hor, 2.8 - 3 m bgs.
temperature measurement lances:
Pt100 by vertical and declined drilling:
appr. 72 pcs.
PT-SVE in wells annulus:
appr. 50 pcs.
0 1 m 2 m 3 m 4 m 5 m
The site is to be divided into
4 areas to be remediated
stepwise by the injection of
350 kg/h steam-air.
Groundwater is extracted
with 2 m³/h and after treat-
ment infiltrated upstream
the source zone.
In total 300 m³/h of soil
vapour are to be extracted.
designed full scale
remediation