Date post: | 03-Jun-2018 |
Category: |
Documents |
Upload: | tanja-djordjevic |
View: | 215 times |
Download: | 0 times |
of 198
8/12/2019 SteelStockholder_3
1/198
FACULTY OF ENGINEERING AND PHYSICAL SCIENCES
Final Report
Feasibil i ty of a
Steel Stockholding Warehouse
Group 3
(2010-2011)
Panayiota Christodoulaki
6037992
Tom Olorenshaw
6003228
Gi D i C ll P
8/12/2019 SteelStockholder_3
2/198
8/12/2019 SteelStockholder_3
3/198
Steel Stockholder Group 3
Executive Summary
As stated in the project brief, the steel stockholder is required to transport steel to potential clients
by both road and the Birmingham canal system. The location of the steel stockholders was chosen
to be Grazebrook Industrial Park, Brierley Hill, West Midlands. The location having been selected
due to the excellent transport facilities to both the local road networks and Birmingham canal
system. After initial site investigations and borehole logs, the ground conditions in the area were
found to be of sufficient strength to support the required services and infrastructure.
When operating at full production capacity, the factory is required to process orders of up to
120,000 tonnes a year. Based on 240 working days a year, the daily production rate required is
approximately 500 tonnes to produce the full production capacity of the warehouse. Of this 500
tonnes per day, only 5% will be transported along the canal system. With this daily output, two
multi-strand processing lines are required. The chosen machine was decided by the Kepner-
Tregoe method and was based on features including self weight, processing speed and cost. The
chosen multi-strand processing machine came out as the JV3X1850 produced by JV-WEI
Machine Equipment Manufacture Co, LTD. The full production capacity of the warehouse is not
reached until year 6, as such it is unnecessary to install both multi-strand processing machines in
year 1. As a way of making economic savings, the second multi-strand processing machine will
8/12/2019 SteelStockholder_3
4/198
Steel Stockholder Group 3
The quay design uses galvanised steel sheet piling to retain the soil and surcharge of 10kN/m2in
accordance with the British waterways. Sheet piling methods have been selected due to the ease
of construction, cost and effectiveness. The quay has sufficient room to allow 1 working narrow
boat to operate. The total depth of the sheet piles is 4.46m which includes a factor of safety of 2.0.
The quay and foundation system have been designed to function as a single unit.
A portal frame warehouse structure was selected for the steel stockholders due to cost, ease of
construction and opportunity for future expansion of the warehouse. To allow for the greatest
efficiency of floor space and in keeping with crane movements, 3 separate portal frame structures
have been designed. The internal layout of the warehouse was essential to producing an efficient
and safe working area. The warehouse incorporates separate areas for loading and unloading of
materials to avoid unnecessary conflicts. Logistically, the unloading and loading areas of the
warehouse are at opposite ends so that the production process flows from one section of the
warehouse to the other without cross over. Steel coils are unloaded and loaded onto the storage
rack by an automated crane. A separate crane then moves the required steel coil onto the multi-
strand processing line for it to be processed. Once processed, the finished product is packaged and
lifted by crane into the dispatch area ready to be loaded onto either the barge or LGV.
In addition to the internal layout, the external layout is also of critical importance to the
f ti lit f th t l t kh ld A t ll d t i i ti d th
8/12/2019 SteelStockholder_3
5/198
Steel Stockholder Group 3
Table of Contents
Acknowledgements .......................................................................................................................... i
Executive Summary ...................................................................................................................... ii
Table of Contents ........................................................................................................................... iv
List of Figures ................................................................................................................................ xi
List of Tables ................................................................................................................................... 1
1. Introduction .............................................................................................................................. 2
2. Location of the Steel Stockholders ......................................................................................... 2
2.1 Location Choice and Reasoning ................................................................................... 2
2.1.1 Location ......................................................................................................... 2
2.1.2 British Geological Survey .............................................................................. 4
2.2 Regulations and Permissions ........................................................................................ 5
2.2.1 Planning Permissions ..................................................................................... 5
2.2.2 Planning Requirements and Building Regulations ......................................... 6
3. Transportation ......................................................................................................................... 6
8/12/2019 SteelStockholder_3
6/198
Steel Stockholder Group 3
5.3 Steel Stockholder Customers ...................................................................................... 19
5.3.1 Narrow boat Customers ................................................................................ 19
5.3.2 General Customers ....................................................................................... 20
6. Warehouse Internal Layout .................................................................................................. 22
7. Crane Options / Selection ...................................................................................................... 23
8. Foundation Design ................................................................................................................. 25
8.1 Foundation Selection .................................................................................................. 25
8.2 Ground Profile ............................................................................................................ 27
8.3 Bearing Capacity ......................................................................................................... 27
8.4 Maximum Loading ..................................................................................................... 28
8.5 Sample Calculations ................................................................................................... 29
8.5.1 Piles .............................................................................................................. 298.5.2 Raft Foundation ............................................................................................ 30
8.5.2.1 Design of Flat Slab. ..................................................................... 31
9. Quay ........................................................................................................................................ 34
9.1 Bank Failure and Flood Defences ............................................................................... 34
9 1 1 L i l ti 34
8/12/2019 SteelStockholder_3
7/198
Steel Stockholder Group 3
9.4 Selection of Quay Structure ........................................................................................ 44
9.5 Design of Sheet Pile Retaining wall ........................................................................... 45
9.5.1 Design Drawing ........................................................................................... 45
9.5.2 Design Assumptions ..................................................................................... 46
9.5.3 Soil Parameters and Groundwater Conditions ............................................. 46
9.5.4 Earth Pressure Calculations .......................................................................... 46
9.5.5 Pressure Distribution Diagram ..................................................................... 48
9.5.6 Determine Depth of Penetration, D............................................................ 48
10. Warehouse Design .................................................................................................................. 50
10.1 Warehouse Structure Selection ................................................................................... 50
10.1.1 Simply Spanned Frame ................................................................................ 50
10.1.2 Cantilever Frame .......................................................................................... 51
10.1.3 Portal Frame ................................................................................................. 52
10.1.4 Space Frame ................................................................................................. 53
10.2 Chosen Warehouse StructurePortal Frame ............................................................. 54
10.2.1 Construction of Portal Frames ..................................................................... 54
10.2.2 Cladding ....................................................................................................... 55
10 2 3
P li d Sh ti R il 55
8/12/2019 SteelStockholder_3
8/198
Steel Stockholder Group 3
10.5.3 Description of LoadingLoading calculations ........................................... 63
10.5.3.1 Self-weights (G) ........................................................................... 63
10.5.3.2 Wind load (W) ............................................................................. 63
10.5.3.3 Snow load (S)............................................................................... 69
10.5.3.4 Live load (Q) ................................................................................ 70
10.5.3.5 Crane operation dynamic load (C) ............................................... 70
10.5.3.6 Roofs dead load due to cladding (R).......................................... 74
10.5.3.7 Lateral loading due to cladding (L) ............................................. 74
10.5.4 Load combinations ....................................................................................... 74
10.5.5 Design of Members ...................................................................................... 75
10.5.5.1 Portal rafter design ....................................................................... 75
10.5.5.2 Column Design ............................................................................ 79
10.5.5.3 Connection Design ....................................................................... 80
10.5.5.4 Bill of Quantities .......................................................................... 83
10.5.6 Storage Racks ............................................................................................... 84
10.5.7 Discussion of analysis .................................................................................. 84
11. External Warehouse Layout ................................................................................................. 85
11.1 Traffic Management ................................................................................................... 86
8/12/2019 SteelStockholder_3
9/198
Steel Stockholder Group 3
14.1 Quality Control ......................................................................................................... 103
14.1.1 Infrared Cameras ........................................................................................ 103
14.1.2 Light Emitting Diodes (LEDs) And Light Dependent Resistors (LDRs) .. 104
14.1.3 Human Factor ............................................................................................. 105
14.1.4 Chosen System ........................................................................................... 105
14.2 LGV live location ..................................................................................................... 106
14.2.1 Chosen System ........................................................................................... 107
14.2.1.1 Transmitting the Data ................................................................ 107
14.3 Safety System ........................................................................................................... 108
14.3.1 RFID ........................................................................................................... 108
14.3.2 Safety Laser Scanners ................................................................................ 109
14.3.3 Chosen System ........................................................................................... 111
14.4 Security system ......................................................................................................... 112
14.4.1 Current Access Technology ....................................................................... 112
14.4.2 Security Code ............................................................................................. 112
14.4.3 RFID ........................................................................................................... 112
14.4.4 CCTV ......................................................................................................... 113
14.5 Traffic Light System ................................................................................................. 116
14 5 1 P Fl 116
8/12/2019 SteelStockholder_3
10/198
Steel Stockholder Group 3
17. Automated System Program ............................................................................................... 124
17.1 Order Processing ....................................................................................................... 12417.2 Simulation Run Time ................................................................................................ 124
17.3 Random Order ........................................................................................................... 125
17.3.1 Random Number Generation ..................................................................... 126
17.3.2 Defining The Order Length ........................................................................ 126
17.3.3 Defining The Order Width and Thickness ................................................. 127
17.3.4 Defining The Number of Parts per Order ................................................... 128
17.3.5 Defining the Order Grade ........................................................................... 128
17.4 Order Processing ....................................................................................................... 129
17.4.1 Order Function ........................................................................................... 129
17.4.2 Searching for Stock .................................................................................... 129
17.4.3 Crane Time Calculations ............................................................................ 13117.4.4 Saving the Crane Times for Analysis ......................................................... 132
17.4.5 Updating Stock Levels ............................................................................... 132
17.4.6 Replenishing Stock..................................................................................... 133
17.4.7 Calculating The Production Output per Day .............................................. 133
17.4.8 Calculating Processing Times for Each Machine....................................... 135
8/12/2019 SteelStockholder_3
11/198
Steel Stockholder Group 3
21.1 Aim ........................................................................................................................... 144
21.2 CAPEX (Capital Expenditure) .................................................................................. 144
21.3 Risk ........................................................................................................................... 145
21.4 Rate of Return ........................................................................................................... 145
21.5 Funding ..................................................................................................................... 147
21.6 Financial Modelling .................................................................................................. 150
21.7 Revenues.................................................................................................................. 150
21.8 Profitability ............................................................................................................... 151
21.9 Net Present Value ..................................................................................................... 151
21.10Return on Investment and Gearing ........................................................................... 152
21.11Sensitivity Analysis .................................................................................................. 153
21.11.1Likely Sales Model .................................................................................... 155
21.11.2Pessimistic Sales Model ............................................................................. 155
21.11.3Optimistic Sales Model .............................................................................. 155
21.12Conclusion ................................................................................................................ 156
22. Conclusion ............................................................................................................................ 156
23. Citations .................................................................................................................................... I
24 A di A VI
8/12/2019 SteelStockholder_3
12/198
Steel Stockholder Group 3
List of Figures
Figure 2.1-1: Satellite map of suggested area. Source: Google maps .............................................. 3
Figure 2.1-2: OS map showing road, rail and canal networks in local vicinity. Source: Digimap
Roam ................................................................................................................................................ 3
Figure 2.1-3: OS map of suggested location. Source: Digimap Roam ............................................. 4
Figure 2.1-4: Birmingham Canal system. Source: Birmingham Metropolitan B C ......................... 4
Figure 2.1-5: British geological map of proposed location. Source: British Geological Survey ..... 4
Figure 2.1-6: Location of borehole logs. Source: British Geological Survey .................................. 4
Figure 2.2-1- Planning Permissions (Dudley Metropolitan Borough Council, 2008) ...................... 5
Figure 3.1-1: Barge route ................................................................................................................. 7
Figure 3.1-2: Graph of Transport Time vs Number of LGV's.......................................................... 8
Figure 3.1-3: Cost Analysis of Haulier Service ................................................................................ 9
http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641629http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc2826416208/12/2019 SteelStockholder_3
13/198
Steel Stockholder Group 3
Figure 9.1-1: Source: Agriculture committee, 1997 ....................................................................... 35
Figure 9.2-1: Existing location showing section of the canal ......................................................... 38
Figure 9.2-2: Initial plan of Quay ................................................................................................... 39
Figure 9.3-1: Example of Installed Steel sheet piles ...................................................................... 42
Figure 9.3-2: Example of a Gabion Structure................................................................................. 43
Figure 9.3-3: Examples Rip Rap Revetment .................................................................................. 44
Figure 9.5-1Design of quay wall .................................................................................................... 45
Figure 9.5-2: Simplified design scenario ........................................................................................ 45
Figure 9.5-3 .................................................................................................................................... 48
Figure 9.5-4: Plan of Quay ............................................................................................................. 50
Figure 10.1-1: The typical portal frame layout is shown ............................................................... 53
Figure 10.2-1: C Purlin ................................................................................................................... 56
Figure 10.2-2: Z Purlin ................................................................................................................... 56
Figure 10.3-1: Single skin membrane ............................................................................................ 58
http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641646http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641646http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641657http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc2826416468/12/2019 SteelStockholder_3
14/198
Steel Stockholder Group 3
Figure 10.5.5-12: Free Bending moment Diagram for Loading ..................................................... 77
Figure 10.5.5-13: Reactions of Loading - Angle Calculation ........................................................ 77
Figure 10.5.5-14: Reactant Bending Moment Diagram ................................................................. 77
Figure 10.5.5-15: Final Collapse Mechanism ................................................................................ 78
Figure 10.5.5-16: Connection details and Software Analysis Results Printout .............................. 81
Figure 10.5.6-17: Storage Racks .................................................................................................... 84
Figure 11.1-1 - Quay Crossing ....................................................................................................... 86
Figure 11.1-2 - Weigh-Bridge ........................................................................................................ 88
Figure 11.1-3 - Traffic Management .............................................................................................. 89
Figure 11.2-1Challenger-1 ......................................................................................................... 90
Figure 11.3-1 - Drainage and Light Map ........................................................................................ 90
Figure 14.1-1 Thermovision A320 Infrared Camera .................................................................... 103
Figure 14.1-2 Surface Defect Captured By Infrared Camera ....................................................... 104
Figure 14.1-3 LED Array ............................................................................................................. 104
http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641677http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641677http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641685http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc2826416778/12/2019 SteelStockholder_3
15/198
Steel Stockholder Group 3
Figure 14.4-3 Security and Safety System Diagram .................................................................... 115
Figure 14.5-1: Traffic Lights and RFID Readers Location. ......................................................... 119
Figure 14.5-2: Traffic Light Concept System Diagram ............................................................... 120
Figure 17.2-1: Runtime selection window ................................................................................... 125
Figure 17.3-1- Random Integer Generator ................................................................................... 126
Figure 17.3-2-Generating Order Length ....................................................................................... 126
Figure 17.3-3 - Random Thickness selection ............................................................................... 127
Figure 17.3-4 - Parts per Order Generator .................................................................................... 128
Figure 17.3-5 - Order Grade Selection ......................................................................................... 128
Figure 17.4-1 - Code for Created Order ....................................................................................... 129
Figure 17.4-2 - Function Used to Locate Coils ............................................................................ 130
Figure 17.5.1-1: Summary data output ......................................................................................... 137
Figure 19.3-1: Re-use and recycling of steel used in construction(Corus, 2008) ..................... 142
Figure 21.4-1:Sales Volume Vs Time......................................................................................... 146
http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641703http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641703http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc2826417038/12/2019 SteelStockholder_3
16/198
Steel Stockholder Group 3
List of Tables
Table 1: Transport Times ............................................................................................................... 11
Table 2: Cranes' Specifications ...................................................................................................... 24
Table 3: Cranes' Beams Selection .................................................................................................. 25
Table 4: Hazard risk assessment ..................................................................................................... 39
Table 5: Soil Parameter Assumptions ............................................................................................ 46
Table 6: Trial Depth ....................................................................................................................... 49
Table 7: Roughness factor values ................................................................................................... 65
Table 8: Mean wind speed values .................................................................................................. 66
Table 9: Wind turbulence vaqlues .................................................................................................. 66
Table 10: Peak velocity pressure values ......................................................................................... 67
Table 11: Wind pressure on surfaces .............................................................................................. 67
Table 12: Snow distribution on roof members ............................................................................... 70
8/12/2019 SteelStockholder_3
17/198
Steel Stockholder Group 3
1.Introduction
Steel has been used within the Engineering industry since the beginning of the 17th century in
many wide spread applications. As one of the most common and versatile materials used, steel
has both structural and non-structural applications. Structural applications include the
construction of ships, bridges and buildings whereas non-structural applications of steel include
packaging, appliances and use in the automotive industry. The composition and material
properties of the steel determine its application within the industry and the way in which it is
processed.
Whatever the use of the steel, manufacturers use third party steel stockholders to source the steel
in the required form with the intention of minimizing costs and sourcing the steel just in time.
The third party steel stockholder must be able to process multiple orders and fulfill the
requirements of the customer.
2.Location of the Steel Stockholders
There are several requirements that need to be considered when positioning the steel stockholder.
8/12/2019 SteelStockholder_3
18/198
Steel Stockholder Group 3
Figure 2.1-1: Satelli te map of suggested area. Source: Google maps
As yet, there has been no construction on the site, however there is an existing road to the site.
The site is located adjacent to the Birmingham No.2 Canal and so deliveries can be made via the
canal to a wide range of locations. The location has excellent road links as it is sandwiched
between the M5 Jct.2 and the A4036. An existing train line runs close by and services the
industrial estate, as shown in Figure 2.1-1.
The location is Hulbert Drive,
Grazebrook Industrial Park,
Brierley Hill,
West Midlands
8/12/2019 SteelStockholder_3
19/198
Steel Stockholder Group 3
From Figure 2.1.1-4, it can be seen that the site is
located near to a nature reserve and footpaths.
However initial estimations of warehouse size mean
that it will not encroach on this area.
2.1.2 British Geological Survey
F igur e 2.1-4: B irmingham Canal system. Source:
Birmi ngham Metropolitan B C
Figure 2.1-3: OS map of suggested
location. Source: Digimap Roam
8/12/2019 SteelStockholder_3
20/198
Steel Stockholder Group 3
Borehole logs taken in the area have been sourced from the British Geological Survey and are
shown in Figure 2.1.2-2.
The Borehole Logs obtained are;
SO98NW337, SO98NW1777, SO98NW1780, SO98NW1782, SO98NW1784, SO98NW1786,
SO98NW1783, SO98NW1778, SO98NW1871 and SO98NW1323.
The main consensus of the borehole logs is that the land along the canal has a layer of made
ground of approximately 1.5m, below this is approximately 1.2m of firm to silty stony clay andthen highly weathered light brown sandstone to a depth of 7m. This layer has thin coal layers
running through it. Below this is grey mudstone. To the east of the canal this mudstone gives way
to sandstone.
The borehole logs give no indication of the strength of these layers however this will be
investigated further prior to a foundation design.
2.2 Regulations and Permissions
2.2.1 Planning Permissions
8/12/2019 SteelStockholder_3
21/198
Steel Stockholder Group 3
Stockholder on this site would likely have the backing of the Council (Dudley Metropolitan
Borough Council, 2008)
There are many different factors which the council will have to consider prior to approving
planning permission. These factors will be both negative and positive regarding the impact on the
community, these are as follows: (Barclay, 2009)
A justification on the requirement of the proposed development. The impact on the local economy.
The impact on the surrounding area and businesses within the area. The accessibility of the site for local residents using either public or private
transport. The sustainability of the development, in relation to minimising the carbon dioxide
emissions during and after the construction of the development.(Barclay, 2009)
Currently there are many manufacturing and construction industries located in the local area and
within Grazebrook Industrial Park in particular. Another concern to the council is that of theexternal appearance, this will be in keeping with the current plants located within the industrial
park. Another aspect which will help win planning permission is that of the jobs created for the
local community. Considering this, it is possible to generate a strong case for obtaining planning
permission from the council.
2.2.2 Planning Requirements and Building Regulations
8/12/2019 SteelStockholder_3
22/198
Steel Stockholder Group 3
approximately 500 tonnes of steel each day. The incoming amount of steel coils would be of a
similar magnitude, therefore it is important to plan and investigate the logistics of such a large
scale operation in as much detail as possible.
The logistics can be split into two sections, one for transportation to the warehouse and one for
transportation to customers from the warehouse.
3.1 Transporting Pre-Processed Steel to the Warehouse
3.1.1 Barge route
Following on from the inception report it is clear that
transport by barge is not a viable option. The lead
times between ordering a coil and having it on site is
too great. More detailed calculations show that each
narrow boat can carry a maximum of 15 tonnes per
journey (3.2.3 Barge calculations). These narrow
boats have to be used between point 3 and 4 of the
journey (Figure 3.1.1-1) due to imposed size
restrictions (ABNB, 2010). Table 1 in the inception
8/12/2019 SteelStockholder_3
23/198
Steel Stockholder Group 3
F igur e 3.1-2: Graph of Transport Time vs Number of LGV' s
The graph shows the time it would take a varying number of LGVs to transport 500 tonnes of
steel from Port Talbot to Birmingham. Although the output production of the warehouse is 500
tonnes per day, it is likely that the replenished steel coils would total slightly less; however, as
mentioned previously the profit margins are very small in the steel processing industry so it is
8/12/2019 SteelStockholder_3
24/198
Steel Stockholder Group 3
Figure 3.1-3: Cost Analysis of Haul ier Servi ce
The intersection points shown on Figure 3.1-3 indicates the point where the cost of paying the
haulier company will coincide with the cost of buying and running the fleet of LGVs. Therefore,
it can be concluded that after 45 days (for the 15/tonne estimate) of hiring a haulier company the
steel plant will be spending money that it could have saved if a purchased fleet of LGVs were in
8/12/2019 SteelStockholder_3
25/198
Steel Stockholder Group 3
deliveries are made otherwise financial penalties will be incurred. Other customers are assumed to
be within 40 miles of the warehouse.
3.2.1 LGVs
The customers located away from the canal side will have to use LGVs for distribution. Seeing
as a fleet of LGVs will have been purchased for transporting pre-processed steel, it would be
most cost effective to expand this fleet of vehicles instead of contracting a haulier for post-
processed distribution. A similar analysis can be carried out to determine how many trucks would
be needed (Appendix A 24.2).
Transport Time vs Daily Costs (Swindon)
4.00
6.00
8.00
10.00
12.00
14.00
16.00
TransportTime
200.00
300.00
400.00
500.00
600.00
Transport Time Cost per Day
8/12/2019 SteelStockholder_3
26/198
Steel Stockholder Group 3
Combining data from both pieces of analysis (Table 1) it can be seen the optimum amount of
LGVs to handle both local and deliveries to Swindon would be 3; it is the optimum point whi ch
balances cost and lead time.
Transport Time vs Daily Costs (Local)
0.00
5.00
10.00
15.00
20.00
25.00
1 2 3 4 5
Number of LGVs
Tr
ansportTime
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
800.00
900.00
1,000.00
Transport Time Cost Per day
F igur e 3.2-2: Tr ansport Time vs Dail y Costs (Local)
8/12/2019 SteelStockholder_3
27/198
Steel Stockholder Group 3
Due to the narrow canals, the 18m long narrow boats would not be able to make a 180 degree
turn. Therefore it would need to navigate all the way around the ring to return to the warehouse
located in Dudley. The Stourport ring is 75 miles long; as discussed in the inception report the
speeds of narrow boats range between 3.511mph. Therefore each journey would take between
21.46.8 hours, giving an average time of 14.1 hours. However, time would need to be added for
navigating the 105 locks on the canal and loading/unloading times. The final time of transport
comes to 36.6 hours (Figure 3.2.2-1).
Narrow BoatSpeed (mph)
Numberof locks
Distance Totravel
(miles)
Time toNavigate
Locks (Hours)
Time toNavigate
Canal
(Hours)
Total
Time
Fi gure 3.2-3: Barge route
8/12/2019 SteelStockholder_3
28/198
Steel Stockholder Group 3
dsteel= 7850 kg/m3
dwater= 1000 kg/m3
dwaterx Vdraught = dsteelx Vsteel
Vsteel= (dwaterx Vdraught )/ dsteel
Vsteel= (1000 x 17.28)/ 7850
Vsteel= 2.2 m3
Hence, the buoyancy will be the weight of the steel that can be loaded on boat, so:
Buoyancy = Wsteel= Vsteelx dsteel= 2.2 x 7850
So, Wsteel= 17.27 tons
This need to be reduced to account for uncertainties, and safety and as such 15 tones has been
assumed. It is still a draft calculation of the load capacity of the narrow boat, however in such a
case, for one boat trip per day, and knowing that the daily production is about 500 tons, the
product to be transported by narrow boats will be only about 3% of the daily production.
8/12/2019 SteelStockholder_3
29/198
Steel Stockholder Group 3
4.2 Coil Processing
There are numerous different processes which a steel stockholder carries out during its operations.
These include De-coiling, Slitting, Re-coiling, Blanking and Packaging. All of these different
terms should be explained in order to understand the running of an efficient processing plant.
De-coiling is unwinding a roll of steel coil and creating a flat, level surface for future processes to
be carried out. The sheet is rolled off the parent coil and passed through a levelling head. This
levelling head is a group of carefully positioned rollers situated both above and below the steel
which apply a set pressure. (Servosteel-1, 2010)
Once the steel has been correctly de-coiled it then
needs to be passed through a slitting machine.
Slitting is the action of cutting a parent coil into one
or a number of narrower widths using rotary slitting
knives (Servosteel-2, 2010). The slitting process
works by driving the steel coil through a slitting head,
this head consists of two circular knifes which are set
in position by carefully placed spacers. The process canF igure 4.2-1: Slitt ing Process(Advantage
Fabri cated Metals-1, 2009)
8/12/2019 SteelStockholder_3
30/198
Steel Stockholder Group 3
F igur e 4.2-2: Slitti ng Process - (Red Bud, Unknown)
Blanking is the process of removing a section of metal from a primary metal sheet. The sheet is
removed by a procedure known as punching, which removes a section to create the metal sheet
(blank). This method forces a metal punch through a die which then shears the section away from
the remaining metal sheet. The process is shown in Figure 4.2-2.This process of blanking has
numerous drawbacks which need to be considered: the creation of residual cracks and hardening
along the blanked edges. (Advantage Fabricated Metals-2, 2009).
There are many different machines which are capable of carrying out these processes individually
Fi gure 4.2-3: Bl anking Process(AdvantageFabri cated Metals-2, 2009).
8/12/2019 SteelStockholder_3
31/198
Steel Stockholder Group 3
When considering machinery it is important to select the specifications required prior to viewing
the machinery. The following specifications are important:
Maximum coil weight must be 27T, this will allow for larger coils to be purchased from
Port Talbot and hence stock fewer coils.
Fast slitting and blanking speeds, which can be accurately calculated when the machinery
is in use by the stockholder.
To be able to deal with a wide range of widths making it is possible to cut full width coils
and the excess coils.
Can cope with a wide range of coil thicknesses, as the thickness of the coil is dependent
on its purpose.
Joint slitting and blanking line, therefore less staff and machinery is required to transport
the product between machines.
From research it has been found that there are at least 12 different companies which manufacture
slitting and cut-to-length machines, these include Jet Edge, Reliant, Millutensil, Imal Group, Il
Kwang, Arku, Serconsult and Soenen. (Direct Industry, 2010).
4.3 Ranking of machines
8/12/2019 SteelStockholder_3
32/198
Steel Stockholder Group 3
For the two machines that pass the must criteria, tables of wants will be produced:
Objectives
Ref. MUSTS ESCL-2X1850 Go/No Go
A Load capacity greater than 27 tones 20 No Go
B Coil width up to 1850 mm 1850 Go
C Coil thickness up to 3 mm 0.35-2mm No Go
Evaluation of multi strand processing line: ESCL -2X1850
"JINAN EAGLE CNC MACHINE CO.,LTD"
Alternative
Objectives
Ref. MUSTS ESCL-3X1850 Go/No Go
A Load capacity greater than 27 tones 30 Go
B Coil width up to 1850 mm 1850 Go
C Coil thickness up to 3 mm 0.5-3mm Go
Evaluation of multi strand processing line: ESCL -3X1850
"JINAN EAGLE CNC MACHINE CO.,LTD"
Alternative
No. E/T Information Rating
1 E/T 6 4 50m/min 9 54 36
2 E/T 5 5 40m/min 9 45 45
3 T 6 35x10.5x2.5 8 48
4 E 9 500.000 8 72
5 E 7 2 months 7 49
6 T 6 0.3mm 8 48
7 T 8 85 tonnes 8 64Self weight of machine
JVWEI MACHINE EQUIPMENT MANUFACTURE CO, LTD
Price (Excluding Works)
Delivery period
Cut to length precision
Ranking Weighted score
Slitting speed
Blanking speed
Dimensions
WANTS
8/12/2019 SteelStockholder_3
33/198
Steel Stockholder Group 3
5.Steel Customer Orders
5.1 Target Market
When considering a steel stockholder it would be impossible to stock all of the variations of coil:
width, thickness, grades and coatings. Therefore it is imperative to establish a target market to
reduce the amount of variation with regards to stock. There are various different uses for steel coil
including, automotive, construction, packaging and electrical products. The UK uses steel coil forall of these purposes and these will be considered.
There are many businesses which the steel stockholder will supply including washing machines,
oil drums, construction industry and aerosol canisters. However the main target is the automotive
industry for numerous UK manufacturers.
Currently the automotive manufacturing process employs 570,000 people over 70,000 companiesin the United Kingdom and turns over 14 Billion annually. The NAIGT report states that if the
automotive manufacturing industry moves abroad over 333,000 jobs could be at risk. (Business
and Enterprise Committee, 2009).
The following major companies manufacture cars in Britain however they are not necessarily
owned by the UK: Mini Honda Toyota Nissan Aston Martin Rolls Royce Jaguar MG Motors
8/12/2019 SteelStockholder_3
34/198
Steel Stockholder Group 3
Mass (M) 27,000KgWidth 1.6m
Thickness 0.0012mDensity () 7860 kg/m3
Steel Volume (V): 1.6m x 0.0012m x L = 0.00192.L
M = x V
27,000 = 7860 x 0.00192.L
L = 27000 / 15.0912
L = 1789.12m
This needs to be reduced to 1700m to allow for the self-weight of the inner core of the coil. This
same procedure has been followed to calculate the maximum length of steel that can be placed
onto a coil.
5.2.2 Steel Coil Specifications
There are some restrictions for the chosen machine (JV3X1850, JvWei Machine Equipment
manufacture co, Ltd) in terms of loading and dimensions of steel coils. These restrictions are the
following:
Steel coil weight not to exceed 30 tons
8/12/2019 SteelStockholder_3
35/198
Steel Stockholder Group 3
The following blanks are required to fit the 4 sides of a washing machine assuming the Base and
Top is to be covered separately by the manufacturer. All blanks are to be 0.8mm thick and of
grade DC 01. (Atlas Steels Australia, 2001)
Blank (Sides) = 900x600 - Required 4
A theoretical value of 300 washing machines has been placed daily. This would take a total time
of 14 mins to be processed by the machine as it will use 195m worth of the selected coil and a
total weight of 4T.
Each 1.8m section of coil creates 4 blanks, which are packaged together; these will then be
shipped in packs of 50s. These packages have an assumed air void value, creating a maximum
package size of 0.32x0.9x0.6m, and 6 of these will be required.
Coil to be ordered: 27T, 1200mm wide by 0.8mm thick, Grade DC 01.
Another assumed customer is that of a large electrical product manufacture. This company isbased further around on the canal route. This company requires a regular daily supply of the same
coil to keep up with their daily production rate of the generic electrical product.
Blanks required: 500 x 1200mm long, 800mm wide, 1.4mm thickness,
This equates to 0.672 m3of steel weighing 5.28 tonnes. It is possible for the processing machine
8/12/2019 SteelStockholder_3
36/198
Steel Stockholder Group 3
The Panel sections are shown below:
The steel is always 1.3 m in width and the
thickness of the steel covers is 0.5mm both
front and back. The manufactures of these
steel insulation panels will require steel
blanks to be delivered to them on a daily
basis, to meet there manufacturing
requirements. Assuming the client requires
steel blanks to always be cut to a standard to
1.3m, and the length is changeable.
(Steadmans. (2010).)
The steel stockholder will also deal with many other orders on an as required system; these
include oil drums, aerosol canisters and general blanks for the manufacturing trade. Thedimensions, grades and specifications for these orders will arrive as per its exact requirement and
will not be known until the order is made. These orders cannot be assumed in advance and will
not be regular. This is the main section of the market which allows for the steel stockholder to
expand.
Some theoretical regular customers will be Toyota(Burton Rd Derby DE65 UK) and
AS35 panel dimensions
Cover 1m
Standard lengths 1.8 12m (others onrequest)
Thickness 40, 60, 80, 100mm
Standard cutbacks 25 250mm (also availablewithout cutbacks)
8/12/2019 SteelStockholder_3
37/198
Steel Stockholder Group 3
27T, 1600mm wide by 1.3mm thick, Grade DC 04. (Processing time for 1 coil is 40 min)
HONDA:
27T, 1200mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 45 min)
27T, 1400mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 45 min)
27T, 1600mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 40 min)
6.Warehouse Internal Layout
Now that the potential market has been decided along with the number of multi-strand processing
machines required it is possible to decide both the internal and external layout element.
Numerous key aspects had to be considered when deciding on the optimum and most efficient
internal layout. The LGVs are rear loaded and unloaded and as such dedicated bays will be
required, the number of these bays is dependent on the time taken for the cranes to process the
steel.
A simplified block diagram below shows the possible process of transporting the steel from
delivery to dispatch. In the flowchart, the grey arrows symbolize a crane or mechanical system.
8/12/2019 SteelStockholder_3
38/198
Steel Stockholder Group 3
The steel will arrive by LGV and its content is then off-loaded by Crane 1,which then loads the
coils into the pigeon hole storage system. This storage system will then be accessed from the
other side of the storage system by Crane 2. Crane 2 then loads multiple coils on the carousel
system at the start of the processing line. Excess coil are then to be removed from the line after
the slitting stage and then stored on the peg system with the assistance of Crane 2.Coils can then
be passed into the blanking lines to suit the customers requirements. The finished product is then
packaged by machinery and a work force. A forklift will then place the steel blanks in the steel
blank storage area. Crane 3is then used to move the blanks from the blank storage area to the
narrow boats. Both the forklift truck and Crane 3can be used to load the steel onto the dispatch
LGVs. There is also a small office facility located to the North-East of the warehouse.
All 3 cranes will be used as per required, and will not interact with one another minimizing
problems. Both of the multi-strand processing lines are situated in parallel, and also consist of a
multiple unit carousel.
7.Crane Options / Selection
There are several types of cranes that can be used for lifting steel coils within a steel stockholding
warehouse. The type of the crane that will be used in the warehouse depends on its layout as well
as on the storage racking system used There are also two major categories of cranes; overhead
8/12/2019 SteelStockholder_3
39/198
Steel Stockholder Group 3
F igur e 7-2: Crane's Adaptation to Main Structure
There are several companies that sell automated overhead bridge cranes. The one that meets the
standards of the warehouse is DEMAG CRANES, which has a UK supplier company called AG
CRANES. The specifications of the cranes that will be used are listed on the table below and on
the detail drawings in the Appendix A, section 24.10.
ZKKE double-girder overhead travelling crane
ZKKE 9.00m ZKKE 20.00m ZKKE 28.00m
8/12/2019 SteelStockholder_3
40/198
Steel Stockholder Group 3
Fi gure 7-3: M aximum M oment Calculation for Crane Beams
The table below shows the maximum moments on the crane beams in each building section as
well as the selected sections.
BuildingMaximum
momentSelected Moment
8/12/2019 SteelStockholder_3
41/198
Steel Stockholder Group 3
improvement methods such as vibro-compaction techniques could be used to treat the ground
prior to construction in order to increase the strength.
A raft foundation of uniform thickness is one option that could be used for this foundation. It
would need to be designed for the highest loading. This could be uneconomical for areas of low
loading, however, it allows stability. Also, where there is a junction of areas of high loading and
low loading a large shear force would occur that could lead to failure. Alternatively, the raft could
be thickened locally to the higher loading areas by using ground beams or deepening the depth,
this could still lead to tilting however, as the load is still outside of the central axis.
Piling considerably reduces settlement of structures and hence, can be used in conjunction with a
raft to form the foundation. They can be located and designed to transfer all of the loading from
the various loading zones of the structure to the grey mudstone at 7m below ground level. A raft
cast over the top of these piles would then form the floor slab for the warehouse. The raft can then
be uniform across the entire cross-section of the foundation area. Extra thickness can be includedlocally where the piles and columns meet to prevent punching failure.
Pits must be included as part of the foundation at the correct location for the multi-strand
processing lines. By merging piles and a raft, the raft can be thinner at the location of these pits
without causing any considerable issues, so long as there is no pile placed directly below. If a pile
were to be placed below the pit locations punching failure could occur
8/12/2019 SteelStockholder_3
42/198
Steel Stockholder Group 3
8.2 Ground Profile
This profile has been acquired from boreholes taken by the
British Geological Society. The Borehole Logs obtained are;
SO98NW337, SO98NW1777, SO98NW1780, SO98NW1782,
SO98NW1784, SO98NW1786, SO98NW1783, SO98NW1778,
SO98NW1871 and SO98NW1323.
l kh ld
8/12/2019 SteelStockholder_3
43/198
Steel Stockholder Group 3
8.4 Maximum Loading
Zone Loading Loading Value Reference
1Delivery Area 6 x Delivery HGVs
Structure/crane
Factory, workshopand similar buildings
44x6 t
3025 kN
5 kN/m2
UK Parliamentbriefing papers
Structural design
BS 6399-1: 1996.Table 1
2Storage Pegs Partially used coils x10
Structure/crane
Factory, workshop
and similar buildings
10 x 27 t
2622 kN
5 kN/m2
Previous research
Structural design
BS 6399-1: 1996.Table 1
3Storage Racks Racking structure
60 x full coils
Structure/crane
Factory, workshop
and similar buildings
450 kN
60 x 27 t
3025 kN
5 kN/m2
Structural design
Previous research
Structural design
BS 6399-1: 1996.
Table 1
4Processing Area 2 x MultistrandMachines
12 X Full coils
Packaging area. 2 xcoil, packagingmaterials
Structure/crane
2 x 85 t
12 x 27 t
2 x 27 t, 5 kN/m2
2636 kN
5 kN/m2
www.servoday.com
Previous research
Structural design
BS 6399-1: 1996.Table 1
St l St kh ld G 3
8/12/2019 SteelStockholder_3
44/198
Steel Stockholder Group 3
8.5 Sample Calculations
8.5.1 Piles
There will be a pile located underneath each column and they will be designed to take most of the
loading from both the floor area and the columns, however, where there is a negative spare pile
capacity this excess loading will be supported by the raft foundation.There will be 38 piles in
total plus test piles, each will be 7m in depth and have a diameter of 0.5m. For ease of
construction each pile will be of the same diameter, this will reduce the need for more than onerig attachment and hence save both time and cost. The design of the pile will relate to the worst
case loading. This sample calculation is for a pile in zone 1. (Refer to Zone Map in 24.3 and
Section24.4.1 for full pile design calculations.)
Assumptions
There are drained conditions (long term stability of clays)
The piles will be CFA bored reinforced concrete.
Drained Shaft Friction, fs= K v' tan '
Where K = Coefficient of lateral earth pressure, 0.7 (CFA piles in silts)
v' =vertical effective stress around the pile after installation = dry unit weight x Depth
St l St kh ld G 3
8/12/2019 SteelStockholder_3
45/198
Steel Stockholder Group 3
The piles will be acting as a group and so will influence each other. The efficiency of the group,
, must be calculated to find the capacity of the group.
= 1-[Tan-1
B/s] [m(n-1)+n(m-1)/90mn]
Where B = Width of pile group
s = Centre to centre spacing of piles
m = Number of rows in the pile group
n = Number of columns in the pile group
Capacity of the group, Qgroup, = N Qsingle
Where N = Number of piles in the group
Qsingle= Bearing capacity of a single pile
Single Pile capacity (kN) 2496.55
Number of piles 14 Centre to centre spacing (s), (m) 9 0.95
Total Width of block (m) 9.55 Number of rows (m) 2
Total Length of block (m) 54 Number of columns (n) 7 Degrees Qgroup (kN) 33275.75
tan^-1 (B/s) 0.06 6.34Total Load(kN) 5603.05
m(n-1) 12
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
46/198
Steel Stockholder Group 3
8.5.2.1 Design of F lat Slab.
The largest moment is located in Zone 7 (Blank storage area), where the excess force is 59.7
kN/m2. This is supported between piles distanced at 20.5m and 12.72m.
Characteristic Material strength fck= 25 N/mm2, fyk= 500 n/mm
2
Assume a slab depth of 500mm.
Cover = 45mm, as Exposure XC-1 for buried slab in Non-aggressive soil (cyclic wet and dry).
ly= 20.5m, lx= 12.72m, therefore ly/lx= 1.61
This creates a bending-moment coefficients which are interpolated to:
asx= 0.108, asx = 0.040 EN 1992:1:Table 8
Self weight of the slab = d. fck= 500x25x10-3
= 12.5 kN/m2
Ultimate Load = 1.35gk+ 1.5qk
= 1.35x12.5 + 1.5x59.7 = 106.425 kN/m2
Bending Short Span
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
47/198
Steel Stockholder Group 3
= 0.04 x 106.425 x 12.722 = 688.78 kN.m
Lever Arm calculations, same as short span minus the bar diameter:
Area of steel reinforcement required:
As =
=
= 3,443 mm
2/m
Therefore 3 x 40mm bars at 300mm spacings with a
As=3770 mm2/m
Punching Shear
The steel columns are to be supported by 500mmx500mm
plates, VED= 3025 kN
(i) Check maximum permissible force at face ofloaded area
Maximum Shear resistance: VRd,max= *( )+
= *( )+
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
48/198
Steel Stockholder Group 3
Therefore punching shear reinforcement is required.
(iii) Check outer perimeter at which reinforcement is not required
uout,ef=
This occurs at a distance of xd from the face of the loaded area such that
9010 = 2000 + 2 x 215 xX
X = 5.18 (>3.0)
(iv) Provision of ReinforcementThus shear reinforcement should be provided within the zone extending from a distance
not greater than 0.5d and less than (5.18-1.5)d = 3.68d from the loaded face.
3 Perimeters of steel will be adequate located at 0.4d, 1.15d and 1.9d.
(Sr) = 0.75d = 341.25mm, (S
t) = 1.5d = 682.5mm
The Minimum link leg area is therefore:
= 123mm2
Hence satisfied by 16mm bar (201mm2)
The area of steel required/perimeter is thus:
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
49/198
Steel Stockholder Group 3
9.Quay
9.1 Bank Failure and Flood Defences
Flooding of canals can be triggered by rising sea level, storms and urbanisation. The full effects of
climate change, on flooding are as yet unknown. Flooding can lead to erosion and deposition of
an area. The extent of which depends on the composition of the land (soft rock, hard rock etc).
The average annual value of damage from flooding and coastal erosion in England and Wales is
estimated at 2.1 billion (Agriculture committee, 1997).
9.1.1 Legislation
The 1953 East Coast Floods, triggered by a storm surge, lead to coastal defences along the entire
coast being breached or overtopped. In total 300 lives were lost and the damage to property assets
and infrastructure was estimated to be in the region of 5 million. These catastrophes lead to the
formation of a committee to establish the causes and possibility of a reoccurrence. One outcome
of this committee prompted changes in inland and costal flood protection legislation and
encouraged a substantial building programme that underpins the existing network of hard
engineered defences on flood plains and along the coast.
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
50/198
Steel Stockholder Group 3
To reduce the risk to people and the developed and natural environment from flooding and
coastal erosion by encouraging the provision of technically, environmentally and economically
sound and sustainable defence measures (Agriculture committee, 1997)
Further to this aim, the use of adequate and cost-effective flood warning systems should be
encouraged. (Agriculture committee, 1997)
9.1.2 Organisational Responsibilities Structure for Flood and Coastal Defence
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
51/198
p
The right to impound or divert the flow of water by placing obstructions in the
watercourse
Rights of fishery and
Rights of navigation.
An owner of waterside land may take responsible action to prevent flood water reaching their land
so long as the watercourse is not diverted from its normal channel or the course that it takes
during flood. It follows from this that a riparian owner may construct flood defences to protect
their land even if it leads to an increased water flow over neighbouring land during times of flood.
However, the implementation of defences can lead to an increased risk of flooding to
neighbouring or opposing land. If this is the case then the riparian owner should employ the
principle of good neighbourliness and work with nearby landowners whom could be affected to
ensure the best flood defence option is chosen. (Howarth, 2002)
9.1.4 Planning
The town and country planning act (1990) is central to the implementation of flood defences. It
states that an environmental impact assessment is required for projects that are likely to have a
significant impact on the environment. Planning permission will be required and as a part of this,
consent for flood defences must be obtained
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
52/198
p
9.1.6 Bank Failure
Bank failure is due to the river bank eroding over time from either natural or manmade causes. In
reality, a combination of both is the underlying problem. All river banks will erode in some form
or another with the rate of erosion dependant on the exposure conditions. This includes the
geographical location, velocity of the river, river bank material and the surrounding infrastructure.
Natural erosion of a river bed can occur locally or as a regional problem. If river conditions where
to change upstream, then this will affect the river downstream. For example, melting ice caps will
cause a greater flow of water and hence a change in velocity. This will therefore affect the river
downstream.
A natural example of erosion to a river bank is that on the apex of a bend (where the river changes
direction and is no longer flowing in a straight line). The flow of a river is faster on the outside of
the river where it has a further distance to travel. The increase in river flow velocity places greater
force on the side of the bank, which in turn causes the river to pick up greater sedimentation and
suspended particles. The inside of the bank will flow much slower as it has less of a distance to
travel. A reduction in speed causes the river to drop the sedimentation in which it is carrying.
Therefore, this side of the bank will begin to build up.
Although erosion to river beds is a natural occurrence this process can be sped up due to
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
53/198
be reduced to a minimum. As detailed above, bank protection is essential in reducing the effects
of erosion and so when designing the flood defences it is important to minimise the bank damaged
caused due to installing the flood defences.
In designing the flood defences it is important to consider the geographical location and take into
effect any changes that the engineering works may have on the river bank, both locally and
regionally. Engineering works which are taking place are likely to affect the river in the following
ways; a change in velocity of the river, three dimensional flow fields (deflection of flow by a
bridge pier) and an increase in turbulence. All of which will affect the river locally and regionally
downstream.
9.1.8 Sustainable Flood Defences
The Agriculture Committee (1997) have concluded that the use of hard engineered approaches to
flood prevention are less sustainable than soft engineering solutions and that the implementation
of soft engineered defences may, in the future, justify the removal of existing hard engineered
solutions. However, there are still cases where hard engineered solutions are more appropriate.
9.2 Quay Design
The quay will be located on the existing canal side and will be designed to BS 6349-2:2010
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
54/198
Clause 4.1.1 states that planning and a risk assessment should be completed prior to starting the
design.Figure 9.2-2 is a plan of the proposed quay. However, the dimensions are as yet unknown.
Fi gure 9.2-2: I nitial plan of Quay
9.2.1 Risk Assessment: Clause 4.1.1
Table 4 details the possible hazards that would affect the loading on the quay wall.
Hazard Action
Vessel hitting/crashing into quay wall Dynamic horizontal loading on quay wall
Waves caused by wake/storm Dynamic horizontal loading of quay wall
Cargo dropped from crane Dynamic vertical loading behind quay wall
Crane falling over Dynamic vertical loading behind quay wall
Cargo stored on quay side Static vertical loading behind quay wall
Changing water level in the canal Hydrostatic loading on quay wall
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
55/198
Any maintenance required to the narrow boat or quay will be completed on weekends. The
warehouse will not be in operation during these times and so there will be no lapse in delivery
capacity via the canals.
To be adequately functional the berth must be able to accommodate the necessary vessels and
cargo handling operations (clause 4.1.3). The warehouse will be producing on average 9.28
tonnes of steel that will need to be transported by narrow boat each day. As each narrow boat can
only transport 15 tonnes of steel safely in each load, one narrow boat will need to be loaded each
day. This means that only one berth will be needed in order to cope with the warehouses
expected capacity. By having one berth the maintenance availability of the quay will be limited to
weekends only. If major maintenance or repair is required that will have duration of greater than
one weekend then deliveries will need to be taken by LGV for that short time.
To comply with clause 4.1.4, the quay must be located so that it is accessible for emergency
services. There must be escape routes provided from hazardous areas such as the path of the crane
and the quay wall itself and there must be safe and easy access to the loading areas. There must be
the correct provision of fire fighting and lifesaving equipment.
9.2.4 Berth Geometry: Clause 4.1.6
An average narrow boat is approximately 20m long and has a width of 2 1m The berth length
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
56/198
structures consist of a suspended deck supported on piles. They can be flexible, on vertical piles
only or more rigid with struts to take shear. Flexible structures are not preferred for loading
platforms and so the quay should be a solid structure. The existing level of the canal and ground
level must be investigated in order to derive design levels for the chosen structure.
Local construction materials should be considered to reduce haulage distances and times. This
could influence the choice of structure. The fill material placed behind the quay should be
granular and free draining to ensure maximum natural consolidation is achieved in the submerged
zone. Above the water level, fill should be compacted using conventional means. This will
increase the lateral pressures on the wall and/or anchorage. To provide adequate drainage, flap
valves should be fixed just above the low water level to allow maintenance and should be
connected to drains behind the wall. These drains should be a granular material between the quay
wall and the fill. Scour protection should be provided in the form of a rubble apron in front of the
berthing positions to protect against any scour caused by the propellers of the vessels. The upper
surfaces of the coping and working area should be allowed for rainfall and spray to drain. Suitable
cross fall towards the structure will allow this and is typically of a gradient between 1:60 and
1:100.
The method of construction must also be carefully considered. Prefabricated sections will reduce
the construction times The structure could be constructed from the land side or from the water If
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
57/198
Electrical power
Sewerage
Mooring devices (mooring rings or posts)
Life saving equipment
Loading crane and equipment
Lighting (area and navigation)
Safety railings
Access stairways Cathodic protection (impressed current transformers)
Vessel approach aids
The fire fighting systems should be designed and placed in accordance with the emergency
response philosophy of the structure. Water hydrants for this purpose need to be provided at
convenient locations as well as fuel hydrants. Both will be served by buried pipelines to either a
mains system or storage tank. An electrical outlet may be required at each berth.
9.3 Types of Quay Structure
Current methods for protecting against flooding and river bank protection are detailed below:
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
58/198
Cantilevered- Soil provides the stability for the wall and requires minimal space for installation.
In situations where a high retaining wall is required, excessive bending forces can result. In this
situation, it is therefore essential that anchored sheet piles are used.
Anchored- For walls of greater height, anchored sheet piles may be more advantageous.
Anchored piles require greater space for installation. If the length of the sheet pile exceeds 4.5 m,
without a safety factor applied, anchored sheet pile design should be used.
When piling works are carried out on canals, the British Waterways board uses galvanised steel.
Steel piles would permit the barge to dock flush with the quay, allowing for easy loading and
unloading. The installation of steel piles would also have little effect on the flow of the river in
comparison to other engineering solutions. Therefore, the use of steel piles would have a smaller
effect on the banks of the river downstream.
9.3.2 Gabion Structures:
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
59/198
9.3.3 Rip-Rap Revetment
Rip-Rap revetment can be used in many applications. Rip-Rap aims to build up the slope of the
river bank to protect against erosion as shown in the above diagrams. For use with the quaydesign, however, rip- rap would not be the best suited. This is because rip rap slopes up the bank
of the river to form a defence, so would not suit the vertical bank of the canal. This would mean
the barge would not be able to dock flush with the side of the bank, therefore making the loading
and unloading of the barge unfeasible. This form of defence is more suited to natural erosion and
does not provide a hard engineering solution to the problem As with gabions rip rap would
F igure 9.3-3: Examples Rip Rap Revetment
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
60/198
tidal changes, therefore, steel piles could potentially prove to be cheaper as no dewatering is
required.
9.5 Design of Sheet Pile Retaining wall
Sheet piles are subjected to varying pressures and loadings. Loadings which are applied to sheet
piles can include; Ice thrust (Ice forming in soil causing a volume expansion), wave forces, barge
impact and the pull associated with mooring barges. Steel sheet piles are subjected to passive and
active pressures on either side due to pressures exerted by the surrounding earth. Steel sheet pilesare also subjected to out of balance water pressures. The pressure subjected is maximum at low
and high tide.
Sheet piles can fail in the following ways:
1. Failure of the sheet piles in bending
2. Overall instability
3. The soil under passive conditions on excavated side of sheet pile wall.
In designing for a sheet pile retaining wall, the following outlines the method that should be
followed:
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
61/198
9.5.2 Design Assumptions
Soil conditions are assumed based on similar ground conditions but subject to change
after a full site investigation carried out.
Design relies on in-situ soil conditions.
Soil conditions are similar to those found in nearby boreholes. Based on these boreholes,the sheet piles will be driven and sit in stiff clay.
Soil parameters are approximations of averages for that soil type
Factor of safety of F = 2.0
Ties for sheet piling wall are to be placed at 2.0m intervals (if required)
Length of pile required will be calculated based on a 1m section
9.5.3 Soil Parameters and Groundwater Conditions
In designing the quay wall, certain soil parameters and assumptions need to be allowed for. As a
full site investigation has not been completed, this allows design calculations to be based on
similar examples and hence increasing reliability.
Soil parameter assumptions:
Table 5: Soil Parameter Assumpti ons
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
62/198
v = 10 kN/m (Surcharge)
u = 0
'v= 10 - 0 = 10 kN/m
'h = 0.368* 10 = 3.68 kN/m
At Level b: Active Side
v = 10 + (1.0 * 20.0) = 30 kN/m
u = 0
'v = 30 - 0 = 30 kN/m
'h = 0.368* 30 = 11.0 kN/m
At Level c: Active Side
v = 10 + (2.2 * 20.0) = 54 kN/m
u = 0
'v = 54 - 0 = 54 kN/m
'h = 0.368* 54 = 19.9 kN/m
At Level c: Passive Side
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
63/198
9.5.5 Pressure Distribution Diagram
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
64/198
Table 6: Tr ial Depth
D' (m)
Resultant
(kN/m)
2 -296.9
1 23.3
1.5 -94.3
1.2 -14.4
1.1 5.94
1.15 -3.85
1.12 2.111.13 0.152
Applying a factor of safety of 2.0:
Depth of penetration = 2.0 * 1.13
= 2.26m
Therefore,
Total Steel pile length = 2.26 + 1.2 + 1.0
= 4.46m
As discussed in Section 9.3.1, the length of the sheet pile does not exceed 4.5m without the safety
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
65/198
Fi gure 9.5-4: Plan of Quay
10. Warehouse Design
10.1 Warehouse Structure Selection
The type of structure used for warehouse design can vary significantly depending on the intended
use and the loading subjected. Warehouses consist of three main types; purpose made units,
standard units and advanced units. In the case of the steel stockholders, the warehouse will be a
privately owned warehouse and effectively combine automated plant and a distribution centre.
Steel coils will arrive on site, processed and then distributed just in time to the customer.Taking
this into account, the type of structure used for the warehouse needs to be carefully considered to
suit the final application. Areas to consider are; loadings applied, cost, on site space restrictions
and time for fabrication and erection. The likelihood is that the design will have to be purpose
Steel Stockholder Group 3
8/12/2019 SteelStockholder_3
66/198
provide additional strength and allow for yet greater span lengths to be achieved. Simply spanned
roof structures are generally flat roof construction, which affects the strength to weight ratio
compared to other types of structure. This is unless intermediate columns are used to furtherincrease the length of the span. Using the truss roof design compared to the simple I beam span
allows for increased restraint against lateral torsional bucking due to the inherent strength of truss
designs.
Bending moments of a uniformly distributed simply spanned structure are assumed maximum in
the centre of the span. The footings require concrete pad foundations to allow for the concentratedloads subjected to the span ends. Columns transfer the loads from the roof to the foundations.
Advantages
Simple design, manufacture and erection
No non useable floor space for span lengths up to 20m
Disadvantages
Limited span lengths of 20m (Unless additional columns are used)
Truss design is not economic
Steel Stockholder Group 3