+ All Categories
Home > Documents > SteelStockholder_3

SteelStockholder_3

Date post: 03-Jun-2018
Category:
Upload: tanja-djordjevic
View: 215 times
Download: 0 times
Share this document with a friend

of 198

Transcript
  • 8/12/2019 SteelStockholder_3

    1/198

    FACULTY OF ENGINEERING AND PHYSICAL SCIENCES

    Final Report

    Feasibil i ty of a

    Steel Stockholding Warehouse

    Group 3

    (2010-2011)

    Panayiota Christodoulaki

    6037992

    Tom Olorenshaw

    6003228

    Gi D i C ll P

  • 8/12/2019 SteelStockholder_3

    2/198

  • 8/12/2019 SteelStockholder_3

    3/198

    Steel Stockholder Group 3

    Executive Summary

    As stated in the project brief, the steel stockholder is required to transport steel to potential clients

    by both road and the Birmingham canal system. The location of the steel stockholders was chosen

    to be Grazebrook Industrial Park, Brierley Hill, West Midlands. The location having been selected

    due to the excellent transport facilities to both the local road networks and Birmingham canal

    system. After initial site investigations and borehole logs, the ground conditions in the area were

    found to be of sufficient strength to support the required services and infrastructure.

    When operating at full production capacity, the factory is required to process orders of up to

    120,000 tonnes a year. Based on 240 working days a year, the daily production rate required is

    approximately 500 tonnes to produce the full production capacity of the warehouse. Of this 500

    tonnes per day, only 5% will be transported along the canal system. With this daily output, two

    multi-strand processing lines are required. The chosen machine was decided by the Kepner-

    Tregoe method and was based on features including self weight, processing speed and cost. The

    chosen multi-strand processing machine came out as the JV3X1850 produced by JV-WEI

    Machine Equipment Manufacture Co, LTD. The full production capacity of the warehouse is not

    reached until year 6, as such it is unnecessary to install both multi-strand processing machines in

    year 1. As a way of making economic savings, the second multi-strand processing machine will

  • 8/12/2019 SteelStockholder_3

    4/198

    Steel Stockholder Group 3

    The quay design uses galvanised steel sheet piling to retain the soil and surcharge of 10kN/m2in

    accordance with the British waterways. Sheet piling methods have been selected due to the ease

    of construction, cost and effectiveness. The quay has sufficient room to allow 1 working narrow

    boat to operate. The total depth of the sheet piles is 4.46m which includes a factor of safety of 2.0.

    The quay and foundation system have been designed to function as a single unit.

    A portal frame warehouse structure was selected for the steel stockholders due to cost, ease of

    construction and opportunity for future expansion of the warehouse. To allow for the greatest

    efficiency of floor space and in keeping with crane movements, 3 separate portal frame structures

    have been designed. The internal layout of the warehouse was essential to producing an efficient

    and safe working area. The warehouse incorporates separate areas for loading and unloading of

    materials to avoid unnecessary conflicts. Logistically, the unloading and loading areas of the

    warehouse are at opposite ends so that the production process flows from one section of the

    warehouse to the other without cross over. Steel coils are unloaded and loaded onto the storage

    rack by an automated crane. A separate crane then moves the required steel coil onto the multi-

    strand processing line for it to be processed. Once processed, the finished product is packaged and

    lifted by crane into the dispatch area ready to be loaded onto either the barge or LGV.

    In addition to the internal layout, the external layout is also of critical importance to the

    f ti lit f th t l t kh ld A t ll d t i i ti d th

  • 8/12/2019 SteelStockholder_3

    5/198

    Steel Stockholder Group 3

    Table of Contents

    Acknowledgements .......................................................................................................................... i

    Executive Summary ...................................................................................................................... ii

    Table of Contents ........................................................................................................................... iv

    List of Figures ................................................................................................................................ xi

    List of Tables ................................................................................................................................... 1

    1. Introduction .............................................................................................................................. 2

    2. Location of the Steel Stockholders ......................................................................................... 2

    2.1 Location Choice and Reasoning ................................................................................... 2

    2.1.1 Location ......................................................................................................... 2

    2.1.2 British Geological Survey .............................................................................. 4

    2.2 Regulations and Permissions ........................................................................................ 5

    2.2.1 Planning Permissions ..................................................................................... 5

    2.2.2 Planning Requirements and Building Regulations ......................................... 6

    3. Transportation ......................................................................................................................... 6

  • 8/12/2019 SteelStockholder_3

    6/198

    Steel Stockholder Group 3

    5.3 Steel Stockholder Customers ...................................................................................... 19

    5.3.1 Narrow boat Customers ................................................................................ 19

    5.3.2 General Customers ....................................................................................... 20

    6. Warehouse Internal Layout .................................................................................................. 22

    7. Crane Options / Selection ...................................................................................................... 23

    8. Foundation Design ................................................................................................................. 25

    8.1 Foundation Selection .................................................................................................. 25

    8.2 Ground Profile ............................................................................................................ 27

    8.3 Bearing Capacity ......................................................................................................... 27

    8.4 Maximum Loading ..................................................................................................... 28

    8.5 Sample Calculations ................................................................................................... 29

    8.5.1 Piles .............................................................................................................. 298.5.2 Raft Foundation ............................................................................................ 30

    8.5.2.1 Design of Flat Slab. ..................................................................... 31

    9. Quay ........................................................................................................................................ 34

    9.1 Bank Failure and Flood Defences ............................................................................... 34

    9 1 1 L i l ti 34

  • 8/12/2019 SteelStockholder_3

    7/198

    Steel Stockholder Group 3

    9.4 Selection of Quay Structure ........................................................................................ 44

    9.5 Design of Sheet Pile Retaining wall ........................................................................... 45

    9.5.1 Design Drawing ........................................................................................... 45

    9.5.2 Design Assumptions ..................................................................................... 46

    9.5.3 Soil Parameters and Groundwater Conditions ............................................. 46

    9.5.4 Earth Pressure Calculations .......................................................................... 46

    9.5.5 Pressure Distribution Diagram ..................................................................... 48

    9.5.6 Determine Depth of Penetration, D............................................................ 48

    10. Warehouse Design .................................................................................................................. 50

    10.1 Warehouse Structure Selection ................................................................................... 50

    10.1.1 Simply Spanned Frame ................................................................................ 50

    10.1.2 Cantilever Frame .......................................................................................... 51

    10.1.3 Portal Frame ................................................................................................. 52

    10.1.4 Space Frame ................................................................................................. 53

    10.2 Chosen Warehouse StructurePortal Frame ............................................................. 54

    10.2.1 Construction of Portal Frames ..................................................................... 54

    10.2.2 Cladding ....................................................................................................... 55

    10 2 3

    P li d Sh ti R il 55

  • 8/12/2019 SteelStockholder_3

    8/198

    Steel Stockholder Group 3

    10.5.3 Description of LoadingLoading calculations ........................................... 63

    10.5.3.1 Self-weights (G) ........................................................................... 63

    10.5.3.2 Wind load (W) ............................................................................. 63

    10.5.3.3 Snow load (S)............................................................................... 69

    10.5.3.4 Live load (Q) ................................................................................ 70

    10.5.3.5 Crane operation dynamic load (C) ............................................... 70

    10.5.3.6 Roofs dead load due to cladding (R).......................................... 74

    10.5.3.7 Lateral loading due to cladding (L) ............................................. 74

    10.5.4 Load combinations ....................................................................................... 74

    10.5.5 Design of Members ...................................................................................... 75

    10.5.5.1 Portal rafter design ....................................................................... 75

    10.5.5.2 Column Design ............................................................................ 79

    10.5.5.3 Connection Design ....................................................................... 80

    10.5.5.4 Bill of Quantities .......................................................................... 83

    10.5.6 Storage Racks ............................................................................................... 84

    10.5.7 Discussion of analysis .................................................................................. 84

    11. External Warehouse Layout ................................................................................................. 85

    11.1 Traffic Management ................................................................................................... 86

  • 8/12/2019 SteelStockholder_3

    9/198

    Steel Stockholder Group 3

    14.1 Quality Control ......................................................................................................... 103

    14.1.1 Infrared Cameras ........................................................................................ 103

    14.1.2 Light Emitting Diodes (LEDs) And Light Dependent Resistors (LDRs) .. 104

    14.1.3 Human Factor ............................................................................................. 105

    14.1.4 Chosen System ........................................................................................... 105

    14.2 LGV live location ..................................................................................................... 106

    14.2.1 Chosen System ........................................................................................... 107

    14.2.1.1 Transmitting the Data ................................................................ 107

    14.3 Safety System ........................................................................................................... 108

    14.3.1 RFID ........................................................................................................... 108

    14.3.2 Safety Laser Scanners ................................................................................ 109

    14.3.3 Chosen System ........................................................................................... 111

    14.4 Security system ......................................................................................................... 112

    14.4.1 Current Access Technology ....................................................................... 112

    14.4.2 Security Code ............................................................................................. 112

    14.4.3 RFID ........................................................................................................... 112

    14.4.4 CCTV ......................................................................................................... 113

    14.5 Traffic Light System ................................................................................................. 116

    14 5 1 P Fl 116

  • 8/12/2019 SteelStockholder_3

    10/198

    Steel Stockholder Group 3

    17. Automated System Program ............................................................................................... 124

    17.1 Order Processing ....................................................................................................... 12417.2 Simulation Run Time ................................................................................................ 124

    17.3 Random Order ........................................................................................................... 125

    17.3.1 Random Number Generation ..................................................................... 126

    17.3.2 Defining The Order Length ........................................................................ 126

    17.3.3 Defining The Order Width and Thickness ................................................. 127

    17.3.4 Defining The Number of Parts per Order ................................................... 128

    17.3.5 Defining the Order Grade ........................................................................... 128

    17.4 Order Processing ....................................................................................................... 129

    17.4.1 Order Function ........................................................................................... 129

    17.4.2 Searching for Stock .................................................................................... 129

    17.4.3 Crane Time Calculations ............................................................................ 13117.4.4 Saving the Crane Times for Analysis ......................................................... 132

    17.4.5 Updating Stock Levels ............................................................................... 132

    17.4.6 Replenishing Stock..................................................................................... 133

    17.4.7 Calculating The Production Output per Day .............................................. 133

    17.4.8 Calculating Processing Times for Each Machine....................................... 135

  • 8/12/2019 SteelStockholder_3

    11/198

    Steel Stockholder Group 3

    21.1 Aim ........................................................................................................................... 144

    21.2 CAPEX (Capital Expenditure) .................................................................................. 144

    21.3 Risk ........................................................................................................................... 145

    21.4 Rate of Return ........................................................................................................... 145

    21.5 Funding ..................................................................................................................... 147

    21.6 Financial Modelling .................................................................................................. 150

    21.7 Revenues.................................................................................................................. 150

    21.8 Profitability ............................................................................................................... 151

    21.9 Net Present Value ..................................................................................................... 151

    21.10Return on Investment and Gearing ........................................................................... 152

    21.11Sensitivity Analysis .................................................................................................. 153

    21.11.1Likely Sales Model .................................................................................... 155

    21.11.2Pessimistic Sales Model ............................................................................. 155

    21.11.3Optimistic Sales Model .............................................................................. 155

    21.12Conclusion ................................................................................................................ 156

    22. Conclusion ............................................................................................................................ 156

    23. Citations .................................................................................................................................... I

    24 A di A VI

  • 8/12/2019 SteelStockholder_3

    12/198

    Steel Stockholder Group 3

    List of Figures

    Figure 2.1-1: Satellite map of suggested area. Source: Google maps .............................................. 3

    Figure 2.1-2: OS map showing road, rail and canal networks in local vicinity. Source: Digimap

    Roam ................................................................................................................................................ 3

    Figure 2.1-3: OS map of suggested location. Source: Digimap Roam ............................................. 4

    Figure 2.1-4: Birmingham Canal system. Source: Birmingham Metropolitan B C ......................... 4

    Figure 2.1-5: British geological map of proposed location. Source: British Geological Survey ..... 4

    Figure 2.1-6: Location of borehole logs. Source: British Geological Survey .................................. 4

    Figure 2.2-1- Planning Permissions (Dudley Metropolitan Borough Council, 2008) ...................... 5

    Figure 3.1-1: Barge route ................................................................................................................. 7

    Figure 3.1-2: Graph of Transport Time vs Number of LGV's.......................................................... 8

    Figure 3.1-3: Cost Analysis of Haulier Service ................................................................................ 9

    http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641629http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641626http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641624http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641623http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641622http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641621http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641620
  • 8/12/2019 SteelStockholder_3

    13/198

    Steel Stockholder Group 3

    Figure 9.1-1: Source: Agriculture committee, 1997 ....................................................................... 35

    Figure 9.2-1: Existing location showing section of the canal ......................................................... 38

    Figure 9.2-2: Initial plan of Quay ................................................................................................... 39

    Figure 9.3-1: Example of Installed Steel sheet piles ...................................................................... 42

    Figure 9.3-2: Example of a Gabion Structure................................................................................. 43

    Figure 9.3-3: Examples Rip Rap Revetment .................................................................................. 44

    Figure 9.5-1Design of quay wall .................................................................................................... 45

    Figure 9.5-2: Simplified design scenario ........................................................................................ 45

    Figure 9.5-3 .................................................................................................................................... 48

    Figure 9.5-4: Plan of Quay ............................................................................................................. 50

    Figure 10.1-1: The typical portal frame layout is shown ............................................................... 53

    Figure 10.2-1: C Purlin ................................................................................................................... 56

    Figure 10.2-2: Z Purlin ................................................................................................................... 56

    Figure 10.3-1: Single skin membrane ............................................................................................ 58

    http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641646http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641646http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641657http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641656http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641655http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641654http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641653http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641650http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641649http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641648http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641646
  • 8/12/2019 SteelStockholder_3

    14/198

    Steel Stockholder Group 3

    Figure 10.5.5-12: Free Bending moment Diagram for Loading ..................................................... 77

    Figure 10.5.5-13: Reactions of Loading - Angle Calculation ........................................................ 77

    Figure 10.5.5-14: Reactant Bending Moment Diagram ................................................................. 77

    Figure 10.5.5-15: Final Collapse Mechanism ................................................................................ 78

    Figure 10.5.5-16: Connection details and Software Analysis Results Printout .............................. 81

    Figure 10.5.6-17: Storage Racks .................................................................................................... 84

    Figure 11.1-1 - Quay Crossing ....................................................................................................... 86

    Figure 11.1-2 - Weigh-Bridge ........................................................................................................ 88

    Figure 11.1-3 - Traffic Management .............................................................................................. 89

    Figure 11.2-1Challenger-1 ......................................................................................................... 90

    Figure 11.3-1 - Drainage and Light Map ........................................................................................ 90

    Figure 14.1-1 Thermovision A320 Infrared Camera .................................................................... 103

    Figure 14.1-2 Surface Defect Captured By Infrared Camera ....................................................... 104

    Figure 14.1-3 LED Array ............................................................................................................. 104

    http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641677http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641677http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641685http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641681http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641680http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641678http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641677
  • 8/12/2019 SteelStockholder_3

    15/198

    Steel Stockholder Group 3

    Figure 14.4-3 Security and Safety System Diagram .................................................................... 115

    Figure 14.5-1: Traffic Lights and RFID Readers Location. ......................................................... 119

    Figure 14.5-2: Traffic Light Concept System Diagram ............................................................... 120

    Figure 17.2-1: Runtime selection window ................................................................................... 125

    Figure 17.3-1- Random Integer Generator ................................................................................... 126

    Figure 17.3-2-Generating Order Length ....................................................................................... 126

    Figure 17.3-3 - Random Thickness selection ............................................................................... 127

    Figure 17.3-4 - Parts per Order Generator .................................................................................... 128

    Figure 17.3-5 - Order Grade Selection ......................................................................................... 128

    Figure 17.4-1 - Code for Created Order ....................................................................................... 129

    Figure 17.4-2 - Function Used to Locate Coils ............................................................................ 130

    Figure 17.5.1-1: Summary data output ......................................................................................... 137

    Figure 19.3-1: Re-use and recycling of steel used in construction(Corus, 2008) ..................... 142

    Figure 21.4-1:Sales Volume Vs Time......................................................................................... 146

    http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641703http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641703http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641710http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641709http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641708http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641707http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641706http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641705http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641704http://c/Users/giorgos/Documents/My%20Dropbox/MDDP/Compiling%20Report/Final%20Report%20.docx%23_Toc282641703
  • 8/12/2019 SteelStockholder_3

    16/198

    Steel Stockholder Group 3

    List of Tables

    Table 1: Transport Times ............................................................................................................... 11

    Table 2: Cranes' Specifications ...................................................................................................... 24

    Table 3: Cranes' Beams Selection .................................................................................................. 25

    Table 4: Hazard risk assessment ..................................................................................................... 39

    Table 5: Soil Parameter Assumptions ............................................................................................ 46

    Table 6: Trial Depth ....................................................................................................................... 49

    Table 7: Roughness factor values ................................................................................................... 65

    Table 8: Mean wind speed values .................................................................................................. 66

    Table 9: Wind turbulence vaqlues .................................................................................................. 66

    Table 10: Peak velocity pressure values ......................................................................................... 67

    Table 11: Wind pressure on surfaces .............................................................................................. 67

    Table 12: Snow distribution on roof members ............................................................................... 70

  • 8/12/2019 SteelStockholder_3

    17/198

    Steel Stockholder Group 3

    1.Introduction

    Steel has been used within the Engineering industry since the beginning of the 17th century in

    many wide spread applications. As one of the most common and versatile materials used, steel

    has both structural and non-structural applications. Structural applications include the

    construction of ships, bridges and buildings whereas non-structural applications of steel include

    packaging, appliances and use in the automotive industry. The composition and material

    properties of the steel determine its application within the industry and the way in which it is

    processed.

    Whatever the use of the steel, manufacturers use third party steel stockholders to source the steel

    in the required form with the intention of minimizing costs and sourcing the steel just in time.

    The third party steel stockholder must be able to process multiple orders and fulfill the

    requirements of the customer.

    2.Location of the Steel Stockholders

    There are several requirements that need to be considered when positioning the steel stockholder.

  • 8/12/2019 SteelStockholder_3

    18/198

    Steel Stockholder Group 3

    Figure 2.1-1: Satelli te map of suggested area. Source: Google maps

    As yet, there has been no construction on the site, however there is an existing road to the site.

    The site is located adjacent to the Birmingham No.2 Canal and so deliveries can be made via the

    canal to a wide range of locations. The location has excellent road links as it is sandwiched

    between the M5 Jct.2 and the A4036. An existing train line runs close by and services the

    industrial estate, as shown in Figure 2.1-1.

    The location is Hulbert Drive,

    Grazebrook Industrial Park,

    Brierley Hill,

    West Midlands

  • 8/12/2019 SteelStockholder_3

    19/198

    Steel Stockholder Group 3

    From Figure 2.1.1-4, it can be seen that the site is

    located near to a nature reserve and footpaths.

    However initial estimations of warehouse size mean

    that it will not encroach on this area.

    2.1.2 British Geological Survey

    F igur e 2.1-4: B irmingham Canal system. Source:

    Birmi ngham Metropolitan B C

    Figure 2.1-3: OS map of suggested

    location. Source: Digimap Roam

  • 8/12/2019 SteelStockholder_3

    20/198

    Steel Stockholder Group 3

    Borehole logs taken in the area have been sourced from the British Geological Survey and are

    shown in Figure 2.1.2-2.

    The Borehole Logs obtained are;

    SO98NW337, SO98NW1777, SO98NW1780, SO98NW1782, SO98NW1784, SO98NW1786,

    SO98NW1783, SO98NW1778, SO98NW1871 and SO98NW1323.

    The main consensus of the borehole logs is that the land along the canal has a layer of made

    ground of approximately 1.5m, below this is approximately 1.2m of firm to silty stony clay andthen highly weathered light brown sandstone to a depth of 7m. This layer has thin coal layers

    running through it. Below this is grey mudstone. To the east of the canal this mudstone gives way

    to sandstone.

    The borehole logs give no indication of the strength of these layers however this will be

    investigated further prior to a foundation design.

    2.2 Regulations and Permissions

    2.2.1 Planning Permissions

  • 8/12/2019 SteelStockholder_3

    21/198

    Steel Stockholder Group 3

    Stockholder on this site would likely have the backing of the Council (Dudley Metropolitan

    Borough Council, 2008)

    There are many different factors which the council will have to consider prior to approving

    planning permission. These factors will be both negative and positive regarding the impact on the

    community, these are as follows: (Barclay, 2009)

    A justification on the requirement of the proposed development. The impact on the local economy.

    The impact on the surrounding area and businesses within the area. The accessibility of the site for local residents using either public or private

    transport. The sustainability of the development, in relation to minimising the carbon dioxide

    emissions during and after the construction of the development.(Barclay, 2009)

    Currently there are many manufacturing and construction industries located in the local area and

    within Grazebrook Industrial Park in particular. Another concern to the council is that of theexternal appearance, this will be in keeping with the current plants located within the industrial

    park. Another aspect which will help win planning permission is that of the jobs created for the

    local community. Considering this, it is possible to generate a strong case for obtaining planning

    permission from the council.

    2.2.2 Planning Requirements and Building Regulations

  • 8/12/2019 SteelStockholder_3

    22/198

    Steel Stockholder Group 3

    approximately 500 tonnes of steel each day. The incoming amount of steel coils would be of a

    similar magnitude, therefore it is important to plan and investigate the logistics of such a large

    scale operation in as much detail as possible.

    The logistics can be split into two sections, one for transportation to the warehouse and one for

    transportation to customers from the warehouse.

    3.1 Transporting Pre-Processed Steel to the Warehouse

    3.1.1 Barge route

    Following on from the inception report it is clear that

    transport by barge is not a viable option. The lead

    times between ordering a coil and having it on site is

    too great. More detailed calculations show that each

    narrow boat can carry a maximum of 15 tonnes per

    journey (3.2.3 Barge calculations). These narrow

    boats have to be used between point 3 and 4 of the

    journey (Figure 3.1.1-1) due to imposed size

    restrictions (ABNB, 2010). Table 1 in the inception

  • 8/12/2019 SteelStockholder_3

    23/198

    Steel Stockholder Group 3

    F igur e 3.1-2: Graph of Transport Time vs Number of LGV' s

    The graph shows the time it would take a varying number of LGVs to transport 500 tonnes of

    steel from Port Talbot to Birmingham. Although the output production of the warehouse is 500

    tonnes per day, it is likely that the replenished steel coils would total slightly less; however, as

    mentioned previously the profit margins are very small in the steel processing industry so it is

  • 8/12/2019 SteelStockholder_3

    24/198

    Steel Stockholder Group 3

    Figure 3.1-3: Cost Analysis of Haul ier Servi ce

    The intersection points shown on Figure 3.1-3 indicates the point where the cost of paying the

    haulier company will coincide with the cost of buying and running the fleet of LGVs. Therefore,

    it can be concluded that after 45 days (for the 15/tonne estimate) of hiring a haulier company the

    steel plant will be spending money that it could have saved if a purchased fleet of LGVs were in

  • 8/12/2019 SteelStockholder_3

    25/198

    Steel Stockholder Group 3

    deliveries are made otherwise financial penalties will be incurred. Other customers are assumed to

    be within 40 miles of the warehouse.

    3.2.1 LGVs

    The customers located away from the canal side will have to use LGVs for distribution. Seeing

    as a fleet of LGVs will have been purchased for transporting pre-processed steel, it would be

    most cost effective to expand this fleet of vehicles instead of contracting a haulier for post-

    processed distribution. A similar analysis can be carried out to determine how many trucks would

    be needed (Appendix A 24.2).

    Transport Time vs Daily Costs (Swindon)

    4.00

    6.00

    8.00

    10.00

    12.00

    14.00

    16.00

    TransportTime

    200.00

    300.00

    400.00

    500.00

    600.00

    Transport Time Cost per Day

  • 8/12/2019 SteelStockholder_3

    26/198

    Steel Stockholder Group 3

    Combining data from both pieces of analysis (Table 1) it can be seen the optimum amount of

    LGVs to handle both local and deliveries to Swindon would be 3; it is the optimum point whi ch

    balances cost and lead time.

    Transport Time vs Daily Costs (Local)

    0.00

    5.00

    10.00

    15.00

    20.00

    25.00

    1 2 3 4 5

    Number of LGVs

    Tr

    ansportTime

    0.00

    100.00

    200.00

    300.00

    400.00

    500.00

    600.00

    700.00

    800.00

    900.00

    1,000.00

    Transport Time Cost Per day

    F igur e 3.2-2: Tr ansport Time vs Dail y Costs (Local)

  • 8/12/2019 SteelStockholder_3

    27/198

    Steel Stockholder Group 3

    Due to the narrow canals, the 18m long narrow boats would not be able to make a 180 degree

    turn. Therefore it would need to navigate all the way around the ring to return to the warehouse

    located in Dudley. The Stourport ring is 75 miles long; as discussed in the inception report the

    speeds of narrow boats range between 3.511mph. Therefore each journey would take between

    21.46.8 hours, giving an average time of 14.1 hours. However, time would need to be added for

    navigating the 105 locks on the canal and loading/unloading times. The final time of transport

    comes to 36.6 hours (Figure 3.2.2-1).

    Narrow BoatSpeed (mph)

    Numberof locks

    Distance Totravel

    (miles)

    Time toNavigate

    Locks (Hours)

    Time toNavigate

    Canal

    (Hours)

    Total

    Time

    Fi gure 3.2-3: Barge route

  • 8/12/2019 SteelStockholder_3

    28/198

    Steel Stockholder Group 3

    dsteel= 7850 kg/m3

    dwater= 1000 kg/m3

    dwaterx Vdraught = dsteelx Vsteel

    Vsteel= (dwaterx Vdraught )/ dsteel

    Vsteel= (1000 x 17.28)/ 7850

    Vsteel= 2.2 m3

    Hence, the buoyancy will be the weight of the steel that can be loaded on boat, so:

    Buoyancy = Wsteel= Vsteelx dsteel= 2.2 x 7850

    So, Wsteel= 17.27 tons

    This need to be reduced to account for uncertainties, and safety and as such 15 tones has been

    assumed. It is still a draft calculation of the load capacity of the narrow boat, however in such a

    case, for one boat trip per day, and knowing that the daily production is about 500 tons, the

    product to be transported by narrow boats will be only about 3% of the daily production.

  • 8/12/2019 SteelStockholder_3

    29/198

    Steel Stockholder Group 3

    4.2 Coil Processing

    There are numerous different processes which a steel stockholder carries out during its operations.

    These include De-coiling, Slitting, Re-coiling, Blanking and Packaging. All of these different

    terms should be explained in order to understand the running of an efficient processing plant.

    De-coiling is unwinding a roll of steel coil and creating a flat, level surface for future processes to

    be carried out. The sheet is rolled off the parent coil and passed through a levelling head. This

    levelling head is a group of carefully positioned rollers situated both above and below the steel

    which apply a set pressure. (Servosteel-1, 2010)

    Once the steel has been correctly de-coiled it then

    needs to be passed through a slitting machine.

    Slitting is the action of cutting a parent coil into one

    or a number of narrower widths using rotary slitting

    knives (Servosteel-2, 2010). The slitting process

    works by driving the steel coil through a slitting head,

    this head consists of two circular knifes which are set

    in position by carefully placed spacers. The process canF igure 4.2-1: Slitt ing Process(Advantage

    Fabri cated Metals-1, 2009)

  • 8/12/2019 SteelStockholder_3

    30/198

    Steel Stockholder Group 3

    F igur e 4.2-2: Slitti ng Process - (Red Bud, Unknown)

    Blanking is the process of removing a section of metal from a primary metal sheet. The sheet is

    removed by a procedure known as punching, which removes a section to create the metal sheet

    (blank). This method forces a metal punch through a die which then shears the section away from

    the remaining metal sheet. The process is shown in Figure 4.2-2.This process of blanking has

    numerous drawbacks which need to be considered: the creation of residual cracks and hardening

    along the blanked edges. (Advantage Fabricated Metals-2, 2009).

    There are many different machines which are capable of carrying out these processes individually

    Fi gure 4.2-3: Bl anking Process(AdvantageFabri cated Metals-2, 2009).

  • 8/12/2019 SteelStockholder_3

    31/198

    Steel Stockholder Group 3

    When considering machinery it is important to select the specifications required prior to viewing

    the machinery. The following specifications are important:

    Maximum coil weight must be 27T, this will allow for larger coils to be purchased from

    Port Talbot and hence stock fewer coils.

    Fast slitting and blanking speeds, which can be accurately calculated when the machinery

    is in use by the stockholder.

    To be able to deal with a wide range of widths making it is possible to cut full width coils

    and the excess coils.

    Can cope with a wide range of coil thicknesses, as the thickness of the coil is dependent

    on its purpose.

    Joint slitting and blanking line, therefore less staff and machinery is required to transport

    the product between machines.

    From research it has been found that there are at least 12 different companies which manufacture

    slitting and cut-to-length machines, these include Jet Edge, Reliant, Millutensil, Imal Group, Il

    Kwang, Arku, Serconsult and Soenen. (Direct Industry, 2010).

    4.3 Ranking of machines

  • 8/12/2019 SteelStockholder_3

    32/198

    Steel Stockholder Group 3

    For the two machines that pass the must criteria, tables of wants will be produced:

    Objectives

    Ref. MUSTS ESCL-2X1850 Go/No Go

    A Load capacity greater than 27 tones 20 No Go

    B Coil width up to 1850 mm 1850 Go

    C Coil thickness up to 3 mm 0.35-2mm No Go

    Evaluation of multi strand processing line: ESCL -2X1850

    "JINAN EAGLE CNC MACHINE CO.,LTD"

    Alternative

    Objectives

    Ref. MUSTS ESCL-3X1850 Go/No Go

    A Load capacity greater than 27 tones 30 Go

    B Coil width up to 1850 mm 1850 Go

    C Coil thickness up to 3 mm 0.5-3mm Go

    Evaluation of multi strand processing line: ESCL -3X1850

    "JINAN EAGLE CNC MACHINE CO.,LTD"

    Alternative

    No. E/T Information Rating

    1 E/T 6 4 50m/min 9 54 36

    2 E/T 5 5 40m/min 9 45 45

    3 T 6 35x10.5x2.5 8 48

    4 E 9 500.000 8 72

    5 E 7 2 months 7 49

    6 T 6 0.3mm 8 48

    7 T 8 85 tonnes 8 64Self weight of machine

    JVWEI MACHINE EQUIPMENT MANUFACTURE CO, LTD

    Price (Excluding Works)

    Delivery period

    Cut to length precision

    Ranking Weighted score

    Slitting speed

    Blanking speed

    Dimensions

    WANTS

  • 8/12/2019 SteelStockholder_3

    33/198

    Steel Stockholder Group 3

    5.Steel Customer Orders

    5.1 Target Market

    When considering a steel stockholder it would be impossible to stock all of the variations of coil:

    width, thickness, grades and coatings. Therefore it is imperative to establish a target market to

    reduce the amount of variation with regards to stock. There are various different uses for steel coil

    including, automotive, construction, packaging and electrical products. The UK uses steel coil forall of these purposes and these will be considered.

    There are many businesses which the steel stockholder will supply including washing machines,

    oil drums, construction industry and aerosol canisters. However the main target is the automotive

    industry for numerous UK manufacturers.

    Currently the automotive manufacturing process employs 570,000 people over 70,000 companiesin the United Kingdom and turns over 14 Billion annually. The NAIGT report states that if the

    automotive manufacturing industry moves abroad over 333,000 jobs could be at risk. (Business

    and Enterprise Committee, 2009).

    The following major companies manufacture cars in Britain however they are not necessarily

    owned by the UK: Mini Honda Toyota Nissan Aston Martin Rolls Royce Jaguar MG Motors

  • 8/12/2019 SteelStockholder_3

    34/198

    Steel Stockholder Group 3

    Mass (M) 27,000KgWidth 1.6m

    Thickness 0.0012mDensity () 7860 kg/m3

    Steel Volume (V): 1.6m x 0.0012m x L = 0.00192.L

    M = x V

    27,000 = 7860 x 0.00192.L

    L = 27000 / 15.0912

    L = 1789.12m

    This needs to be reduced to 1700m to allow for the self-weight of the inner core of the coil. This

    same procedure has been followed to calculate the maximum length of steel that can be placed

    onto a coil.

    5.2.2 Steel Coil Specifications

    There are some restrictions for the chosen machine (JV3X1850, JvWei Machine Equipment

    manufacture co, Ltd) in terms of loading and dimensions of steel coils. These restrictions are the

    following:

    Steel coil weight not to exceed 30 tons

  • 8/12/2019 SteelStockholder_3

    35/198

    Steel Stockholder Group 3

    The following blanks are required to fit the 4 sides of a washing machine assuming the Base and

    Top is to be covered separately by the manufacturer. All blanks are to be 0.8mm thick and of

    grade DC 01. (Atlas Steels Australia, 2001)

    Blank (Sides) = 900x600 - Required 4

    A theoretical value of 300 washing machines has been placed daily. This would take a total time

    of 14 mins to be processed by the machine as it will use 195m worth of the selected coil and a

    total weight of 4T.

    Each 1.8m section of coil creates 4 blanks, which are packaged together; these will then be

    shipped in packs of 50s. These packages have an assumed air void value, creating a maximum

    package size of 0.32x0.9x0.6m, and 6 of these will be required.

    Coil to be ordered: 27T, 1200mm wide by 0.8mm thick, Grade DC 01.

    Another assumed customer is that of a large electrical product manufacture. This company isbased further around on the canal route. This company requires a regular daily supply of the same

    coil to keep up with their daily production rate of the generic electrical product.

    Blanks required: 500 x 1200mm long, 800mm wide, 1.4mm thickness,

    This equates to 0.672 m3of steel weighing 5.28 tonnes. It is possible for the processing machine

  • 8/12/2019 SteelStockholder_3

    36/198

    Steel Stockholder Group 3

    The Panel sections are shown below:

    The steel is always 1.3 m in width and the

    thickness of the steel covers is 0.5mm both

    front and back. The manufactures of these

    steel insulation panels will require steel

    blanks to be delivered to them on a daily

    basis, to meet there manufacturing

    requirements. Assuming the client requires

    steel blanks to always be cut to a standard to

    1.3m, and the length is changeable.

    (Steadmans. (2010).)

    The steel stockholder will also deal with many other orders on an as required system; these

    include oil drums, aerosol canisters and general blanks for the manufacturing trade. Thedimensions, grades and specifications for these orders will arrive as per its exact requirement and

    will not be known until the order is made. These orders cannot be assumed in advance and will

    not be regular. This is the main section of the market which allows for the steel stockholder to

    expand.

    Some theoretical regular customers will be Toyota(Burton Rd Derby DE65 UK) and

    AS35 panel dimensions

    Cover 1m

    Standard lengths 1.8 12m (others onrequest)

    Thickness 40, 60, 80, 100mm

    Standard cutbacks 25 250mm (also availablewithout cutbacks)

  • 8/12/2019 SteelStockholder_3

    37/198

    Steel Stockholder Group 3

    27T, 1600mm wide by 1.3mm thick, Grade DC 04. (Processing time for 1 coil is 40 min)

    HONDA:

    27T, 1200mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 45 min)

    27T, 1400mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 45 min)

    27T, 1600mm wide by 1.4mm thick, Grade DC 03. (Processing time for 1 coil is 40 min)

    6.Warehouse Internal Layout

    Now that the potential market has been decided along with the number of multi-strand processing

    machines required it is possible to decide both the internal and external layout element.

    Numerous key aspects had to be considered when deciding on the optimum and most efficient

    internal layout. The LGVs are rear loaded and unloaded and as such dedicated bays will be

    required, the number of these bays is dependent on the time taken for the cranes to process the

    steel.

    A simplified block diagram below shows the possible process of transporting the steel from

    delivery to dispatch. In the flowchart, the grey arrows symbolize a crane or mechanical system.

  • 8/12/2019 SteelStockholder_3

    38/198

    Steel Stockholder Group 3

    The steel will arrive by LGV and its content is then off-loaded by Crane 1,which then loads the

    coils into the pigeon hole storage system. This storage system will then be accessed from the

    other side of the storage system by Crane 2. Crane 2 then loads multiple coils on the carousel

    system at the start of the processing line. Excess coil are then to be removed from the line after

    the slitting stage and then stored on the peg system with the assistance of Crane 2.Coils can then

    be passed into the blanking lines to suit the customers requirements. The finished product is then

    packaged by machinery and a work force. A forklift will then place the steel blanks in the steel

    blank storage area. Crane 3is then used to move the blanks from the blank storage area to the

    narrow boats. Both the forklift truck and Crane 3can be used to load the steel onto the dispatch

    LGVs. There is also a small office facility located to the North-East of the warehouse.

    All 3 cranes will be used as per required, and will not interact with one another minimizing

    problems. Both of the multi-strand processing lines are situated in parallel, and also consist of a

    multiple unit carousel.

    7.Crane Options / Selection

    There are several types of cranes that can be used for lifting steel coils within a steel stockholding

    warehouse. The type of the crane that will be used in the warehouse depends on its layout as well

    as on the storage racking system used There are also two major categories of cranes; overhead

  • 8/12/2019 SteelStockholder_3

    39/198

    Steel Stockholder Group 3

    F igur e 7-2: Crane's Adaptation to Main Structure

    There are several companies that sell automated overhead bridge cranes. The one that meets the

    standards of the warehouse is DEMAG CRANES, which has a UK supplier company called AG

    CRANES. The specifications of the cranes that will be used are listed on the table below and on

    the detail drawings in the Appendix A, section 24.10.

    ZKKE double-girder overhead travelling crane

    ZKKE 9.00m ZKKE 20.00m ZKKE 28.00m

  • 8/12/2019 SteelStockholder_3

    40/198

    Steel Stockholder Group 3

    Fi gure 7-3: M aximum M oment Calculation for Crane Beams

    The table below shows the maximum moments on the crane beams in each building section as

    well as the selected sections.

    BuildingMaximum

    momentSelected Moment

  • 8/12/2019 SteelStockholder_3

    41/198

    Steel Stockholder Group 3

    improvement methods such as vibro-compaction techniques could be used to treat the ground

    prior to construction in order to increase the strength.

    A raft foundation of uniform thickness is one option that could be used for this foundation. It

    would need to be designed for the highest loading. This could be uneconomical for areas of low

    loading, however, it allows stability. Also, where there is a junction of areas of high loading and

    low loading a large shear force would occur that could lead to failure. Alternatively, the raft could

    be thickened locally to the higher loading areas by using ground beams or deepening the depth,

    this could still lead to tilting however, as the load is still outside of the central axis.

    Piling considerably reduces settlement of structures and hence, can be used in conjunction with a

    raft to form the foundation. They can be located and designed to transfer all of the loading from

    the various loading zones of the structure to the grey mudstone at 7m below ground level. A raft

    cast over the top of these piles would then form the floor slab for the warehouse. The raft can then

    be uniform across the entire cross-section of the foundation area. Extra thickness can be includedlocally where the piles and columns meet to prevent punching failure.

    Pits must be included as part of the foundation at the correct location for the multi-strand

    processing lines. By merging piles and a raft, the raft can be thinner at the location of these pits

    without causing any considerable issues, so long as there is no pile placed directly below. If a pile

    were to be placed below the pit locations punching failure could occur

  • 8/12/2019 SteelStockholder_3

    42/198

    Steel Stockholder Group 3

    8.2 Ground Profile

    This profile has been acquired from boreholes taken by the

    British Geological Society. The Borehole Logs obtained are;

    SO98NW337, SO98NW1777, SO98NW1780, SO98NW1782,

    SO98NW1784, SO98NW1786, SO98NW1783, SO98NW1778,

    SO98NW1871 and SO98NW1323.

    l kh ld

  • 8/12/2019 SteelStockholder_3

    43/198

    Steel Stockholder Group 3

    8.4 Maximum Loading

    Zone Loading Loading Value Reference

    1Delivery Area 6 x Delivery HGVs

    Structure/crane

    Factory, workshopand similar buildings

    44x6 t

    3025 kN

    5 kN/m2

    UK Parliamentbriefing papers

    Structural design

    BS 6399-1: 1996.Table 1

    2Storage Pegs Partially used coils x10

    Structure/crane

    Factory, workshop

    and similar buildings

    10 x 27 t

    2622 kN

    5 kN/m2

    Previous research

    Structural design

    BS 6399-1: 1996.Table 1

    3Storage Racks Racking structure

    60 x full coils

    Structure/crane

    Factory, workshop

    and similar buildings

    450 kN

    60 x 27 t

    3025 kN

    5 kN/m2

    Structural design

    Previous research

    Structural design

    BS 6399-1: 1996.

    Table 1

    4Processing Area 2 x MultistrandMachines

    12 X Full coils

    Packaging area. 2 xcoil, packagingmaterials

    Structure/crane

    2 x 85 t

    12 x 27 t

    2 x 27 t, 5 kN/m2

    2636 kN

    5 kN/m2

    www.servoday.com

    Previous research

    Structural design

    BS 6399-1: 1996.Table 1

    St l St kh ld G 3

  • 8/12/2019 SteelStockholder_3

    44/198

    Steel Stockholder Group 3

    8.5 Sample Calculations

    8.5.1 Piles

    There will be a pile located underneath each column and they will be designed to take most of the

    loading from both the floor area and the columns, however, where there is a negative spare pile

    capacity this excess loading will be supported by the raft foundation.There will be 38 piles in

    total plus test piles, each will be 7m in depth and have a diameter of 0.5m. For ease of

    construction each pile will be of the same diameter, this will reduce the need for more than onerig attachment and hence save both time and cost. The design of the pile will relate to the worst

    case loading. This sample calculation is for a pile in zone 1. (Refer to Zone Map in 24.3 and

    Section24.4.1 for full pile design calculations.)

    Assumptions

    There are drained conditions (long term stability of clays)

    The piles will be CFA bored reinforced concrete.

    Drained Shaft Friction, fs= K v' tan '

    Where K = Coefficient of lateral earth pressure, 0.7 (CFA piles in silts)

    v' =vertical effective stress around the pile after installation = dry unit weight x Depth

    St l St kh ld G 3

  • 8/12/2019 SteelStockholder_3

    45/198

    Steel Stockholder Group 3

    The piles will be acting as a group and so will influence each other. The efficiency of the group,

    , must be calculated to find the capacity of the group.

    = 1-[Tan-1

    B/s] [m(n-1)+n(m-1)/90mn]

    Where B = Width of pile group

    s = Centre to centre spacing of piles

    m = Number of rows in the pile group

    n = Number of columns in the pile group

    Capacity of the group, Qgroup, = N Qsingle

    Where N = Number of piles in the group

    Qsingle= Bearing capacity of a single pile

    Single Pile capacity (kN) 2496.55

    Number of piles 14 Centre to centre spacing (s), (m) 9 0.95

    Total Width of block (m) 9.55 Number of rows (m) 2

    Total Length of block (m) 54 Number of columns (n) 7 Degrees Qgroup (kN) 33275.75

    tan^-1 (B/s) 0.06 6.34Total Load(kN) 5603.05

    m(n-1) 12

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    46/198

    Steel Stockholder Group 3

    8.5.2.1 Design of F lat Slab.

    The largest moment is located in Zone 7 (Blank storage area), where the excess force is 59.7

    kN/m2. This is supported between piles distanced at 20.5m and 12.72m.

    Characteristic Material strength fck= 25 N/mm2, fyk= 500 n/mm

    2

    Assume a slab depth of 500mm.

    Cover = 45mm, as Exposure XC-1 for buried slab in Non-aggressive soil (cyclic wet and dry).

    ly= 20.5m, lx= 12.72m, therefore ly/lx= 1.61

    This creates a bending-moment coefficients which are interpolated to:

    asx= 0.108, asx = 0.040 EN 1992:1:Table 8

    Self weight of the slab = d. fck= 500x25x10-3

    = 12.5 kN/m2

    Ultimate Load = 1.35gk+ 1.5qk

    = 1.35x12.5 + 1.5x59.7 = 106.425 kN/m2

    Bending Short Span

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    47/198

    Steel Stockholder Group 3

    = 0.04 x 106.425 x 12.722 = 688.78 kN.m

    Lever Arm calculations, same as short span minus the bar diameter:

    Area of steel reinforcement required:

    As =

    =

    = 3,443 mm

    2/m

    Therefore 3 x 40mm bars at 300mm spacings with a

    As=3770 mm2/m

    Punching Shear

    The steel columns are to be supported by 500mmx500mm

    plates, VED= 3025 kN

    (i) Check maximum permissible force at face ofloaded area

    Maximum Shear resistance: VRd,max= *( )+

    = *( )+

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    48/198

    Steel Stockholder Group 3

    Therefore punching shear reinforcement is required.

    (iii) Check outer perimeter at which reinforcement is not required

    uout,ef=

    This occurs at a distance of xd from the face of the loaded area such that

    9010 = 2000 + 2 x 215 xX

    X = 5.18 (>3.0)

    (iv) Provision of ReinforcementThus shear reinforcement should be provided within the zone extending from a distance

    not greater than 0.5d and less than (5.18-1.5)d = 3.68d from the loaded face.

    3 Perimeters of steel will be adequate located at 0.4d, 1.15d and 1.9d.

    (Sr) = 0.75d = 341.25mm, (S

    t) = 1.5d = 682.5mm

    The Minimum link leg area is therefore:

    = 123mm2

    Hence satisfied by 16mm bar (201mm2)

    The area of steel required/perimeter is thus:

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    49/198

    Steel Stockholder Group 3

    9.Quay

    9.1 Bank Failure and Flood Defences

    Flooding of canals can be triggered by rising sea level, storms and urbanisation. The full effects of

    climate change, on flooding are as yet unknown. Flooding can lead to erosion and deposition of

    an area. The extent of which depends on the composition of the land (soft rock, hard rock etc).

    The average annual value of damage from flooding and coastal erosion in England and Wales is

    estimated at 2.1 billion (Agriculture committee, 1997).

    9.1.1 Legislation

    The 1953 East Coast Floods, triggered by a storm surge, lead to coastal defences along the entire

    coast being breached or overtopped. In total 300 lives were lost and the damage to property assets

    and infrastructure was estimated to be in the region of 5 million. These catastrophes lead to the

    formation of a committee to establish the causes and possibility of a reoccurrence. One outcome

    of this committee prompted changes in inland and costal flood protection legislation and

    encouraged a substantial building programme that underpins the existing network of hard

    engineered defences on flood plains and along the coast.

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    50/198

    Steel Stockholder Group 3

    To reduce the risk to people and the developed and natural environment from flooding and

    coastal erosion by encouraging the provision of technically, environmentally and economically

    sound and sustainable defence measures (Agriculture committee, 1997)

    Further to this aim, the use of adequate and cost-effective flood warning systems should be

    encouraged. (Agriculture committee, 1997)

    9.1.2 Organisational Responsibilities Structure for Flood and Coastal Defence

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    51/198

    p

    The right to impound or divert the flow of water by placing obstructions in the

    watercourse

    Rights of fishery and

    Rights of navigation.

    An owner of waterside land may take responsible action to prevent flood water reaching their land

    so long as the watercourse is not diverted from its normal channel or the course that it takes

    during flood. It follows from this that a riparian owner may construct flood defences to protect

    their land even if it leads to an increased water flow over neighbouring land during times of flood.

    However, the implementation of defences can lead to an increased risk of flooding to

    neighbouring or opposing land. If this is the case then the riparian owner should employ the

    principle of good neighbourliness and work with nearby landowners whom could be affected to

    ensure the best flood defence option is chosen. (Howarth, 2002)

    9.1.4 Planning

    The town and country planning act (1990) is central to the implementation of flood defences. It

    states that an environmental impact assessment is required for projects that are likely to have a

    significant impact on the environment. Planning permission will be required and as a part of this,

    consent for flood defences must be obtained

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    52/198

    p

    9.1.6 Bank Failure

    Bank failure is due to the river bank eroding over time from either natural or manmade causes. In

    reality, a combination of both is the underlying problem. All river banks will erode in some form

    or another with the rate of erosion dependant on the exposure conditions. This includes the

    geographical location, velocity of the river, river bank material and the surrounding infrastructure.

    Natural erosion of a river bed can occur locally or as a regional problem. If river conditions where

    to change upstream, then this will affect the river downstream. For example, melting ice caps will

    cause a greater flow of water and hence a change in velocity. This will therefore affect the river

    downstream.

    A natural example of erosion to a river bank is that on the apex of a bend (where the river changes

    direction and is no longer flowing in a straight line). The flow of a river is faster on the outside of

    the river where it has a further distance to travel. The increase in river flow velocity places greater

    force on the side of the bank, which in turn causes the river to pick up greater sedimentation and

    suspended particles. The inside of the bank will flow much slower as it has less of a distance to

    travel. A reduction in speed causes the river to drop the sedimentation in which it is carrying.

    Therefore, this side of the bank will begin to build up.

    Although erosion to river beds is a natural occurrence this process can be sped up due to

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    53/198

    be reduced to a minimum. As detailed above, bank protection is essential in reducing the effects

    of erosion and so when designing the flood defences it is important to minimise the bank damaged

    caused due to installing the flood defences.

    In designing the flood defences it is important to consider the geographical location and take into

    effect any changes that the engineering works may have on the river bank, both locally and

    regionally. Engineering works which are taking place are likely to affect the river in the following

    ways; a change in velocity of the river, three dimensional flow fields (deflection of flow by a

    bridge pier) and an increase in turbulence. All of which will affect the river locally and regionally

    downstream.

    9.1.8 Sustainable Flood Defences

    The Agriculture Committee (1997) have concluded that the use of hard engineered approaches to

    flood prevention are less sustainable than soft engineering solutions and that the implementation

    of soft engineered defences may, in the future, justify the removal of existing hard engineered

    solutions. However, there are still cases where hard engineered solutions are more appropriate.

    9.2 Quay Design

    The quay will be located on the existing canal side and will be designed to BS 6349-2:2010

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    54/198

    Clause 4.1.1 states that planning and a risk assessment should be completed prior to starting the

    design.Figure 9.2-2 is a plan of the proposed quay. However, the dimensions are as yet unknown.

    Fi gure 9.2-2: I nitial plan of Quay

    9.2.1 Risk Assessment: Clause 4.1.1

    Table 4 details the possible hazards that would affect the loading on the quay wall.

    Hazard Action

    Vessel hitting/crashing into quay wall Dynamic horizontal loading on quay wall

    Waves caused by wake/storm Dynamic horizontal loading of quay wall

    Cargo dropped from crane Dynamic vertical loading behind quay wall

    Crane falling over Dynamic vertical loading behind quay wall

    Cargo stored on quay side Static vertical loading behind quay wall

    Changing water level in the canal Hydrostatic loading on quay wall

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    55/198

    Any maintenance required to the narrow boat or quay will be completed on weekends. The

    warehouse will not be in operation during these times and so there will be no lapse in delivery

    capacity via the canals.

    To be adequately functional the berth must be able to accommodate the necessary vessels and

    cargo handling operations (clause 4.1.3). The warehouse will be producing on average 9.28

    tonnes of steel that will need to be transported by narrow boat each day. As each narrow boat can

    only transport 15 tonnes of steel safely in each load, one narrow boat will need to be loaded each

    day. This means that only one berth will be needed in order to cope with the warehouses

    expected capacity. By having one berth the maintenance availability of the quay will be limited to

    weekends only. If major maintenance or repair is required that will have duration of greater than

    one weekend then deliveries will need to be taken by LGV for that short time.

    To comply with clause 4.1.4, the quay must be located so that it is accessible for emergency

    services. There must be escape routes provided from hazardous areas such as the path of the crane

    and the quay wall itself and there must be safe and easy access to the loading areas. There must be

    the correct provision of fire fighting and lifesaving equipment.

    9.2.4 Berth Geometry: Clause 4.1.6

    An average narrow boat is approximately 20m long and has a width of 2 1m The berth length

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    56/198

    structures consist of a suspended deck supported on piles. They can be flexible, on vertical piles

    only or more rigid with struts to take shear. Flexible structures are not preferred for loading

    platforms and so the quay should be a solid structure. The existing level of the canal and ground

    level must be investigated in order to derive design levels for the chosen structure.

    Local construction materials should be considered to reduce haulage distances and times. This

    could influence the choice of structure. The fill material placed behind the quay should be

    granular and free draining to ensure maximum natural consolidation is achieved in the submerged

    zone. Above the water level, fill should be compacted using conventional means. This will

    increase the lateral pressures on the wall and/or anchorage. To provide adequate drainage, flap

    valves should be fixed just above the low water level to allow maintenance and should be

    connected to drains behind the wall. These drains should be a granular material between the quay

    wall and the fill. Scour protection should be provided in the form of a rubble apron in front of the

    berthing positions to protect against any scour caused by the propellers of the vessels. The upper

    surfaces of the coping and working area should be allowed for rainfall and spray to drain. Suitable

    cross fall towards the structure will allow this and is typically of a gradient between 1:60 and

    1:100.

    The method of construction must also be carefully considered. Prefabricated sections will reduce

    the construction times The structure could be constructed from the land side or from the water If

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    57/198

    Electrical power

    Sewerage

    Mooring devices (mooring rings or posts)

    Life saving equipment

    Loading crane and equipment

    Lighting (area and navigation)

    Safety railings

    Access stairways Cathodic protection (impressed current transformers)

    Vessel approach aids

    The fire fighting systems should be designed and placed in accordance with the emergency

    response philosophy of the structure. Water hydrants for this purpose need to be provided at

    convenient locations as well as fuel hydrants. Both will be served by buried pipelines to either a

    mains system or storage tank. An electrical outlet may be required at each berth.

    9.3 Types of Quay Structure

    Current methods for protecting against flooding and river bank protection are detailed below:

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    58/198

    Cantilevered- Soil provides the stability for the wall and requires minimal space for installation.

    In situations where a high retaining wall is required, excessive bending forces can result. In this

    situation, it is therefore essential that anchored sheet piles are used.

    Anchored- For walls of greater height, anchored sheet piles may be more advantageous.

    Anchored piles require greater space for installation. If the length of the sheet pile exceeds 4.5 m,

    without a safety factor applied, anchored sheet pile design should be used.

    When piling works are carried out on canals, the British Waterways board uses galvanised steel.

    Steel piles would permit the barge to dock flush with the quay, allowing for easy loading and

    unloading. The installation of steel piles would also have little effect on the flow of the river in

    comparison to other engineering solutions. Therefore, the use of steel piles would have a smaller

    effect on the banks of the river downstream.

    9.3.2 Gabion Structures:

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    59/198

    9.3.3 Rip-Rap Revetment

    Rip-Rap revetment can be used in many applications. Rip-Rap aims to build up the slope of the

    river bank to protect against erosion as shown in the above diagrams. For use with the quaydesign, however, rip- rap would not be the best suited. This is because rip rap slopes up the bank

    of the river to form a defence, so would not suit the vertical bank of the canal. This would mean

    the barge would not be able to dock flush with the side of the bank, therefore making the loading

    and unloading of the barge unfeasible. This form of defence is more suited to natural erosion and

    does not provide a hard engineering solution to the problem As with gabions rip rap would

    F igure 9.3-3: Examples Rip Rap Revetment

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    60/198

    tidal changes, therefore, steel piles could potentially prove to be cheaper as no dewatering is

    required.

    9.5 Design of Sheet Pile Retaining wall

    Sheet piles are subjected to varying pressures and loadings. Loadings which are applied to sheet

    piles can include; Ice thrust (Ice forming in soil causing a volume expansion), wave forces, barge

    impact and the pull associated with mooring barges. Steel sheet piles are subjected to passive and

    active pressures on either side due to pressures exerted by the surrounding earth. Steel sheet pilesare also subjected to out of balance water pressures. The pressure subjected is maximum at low

    and high tide.

    Sheet piles can fail in the following ways:

    1. Failure of the sheet piles in bending

    2. Overall instability

    3. The soil under passive conditions on excavated side of sheet pile wall.

    In designing for a sheet pile retaining wall, the following outlines the method that should be

    followed:

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    61/198

    9.5.2 Design Assumptions

    Soil conditions are assumed based on similar ground conditions but subject to change

    after a full site investigation carried out.

    Design relies on in-situ soil conditions.

    Soil conditions are similar to those found in nearby boreholes. Based on these boreholes,the sheet piles will be driven and sit in stiff clay.

    Soil parameters are approximations of averages for that soil type

    Factor of safety of F = 2.0

    Ties for sheet piling wall are to be placed at 2.0m intervals (if required)

    Length of pile required will be calculated based on a 1m section

    9.5.3 Soil Parameters and Groundwater Conditions

    In designing the quay wall, certain soil parameters and assumptions need to be allowed for. As a

    full site investigation has not been completed, this allows design calculations to be based on

    similar examples and hence increasing reliability.

    Soil parameter assumptions:

    Table 5: Soil Parameter Assumpti ons

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    62/198

    v = 10 kN/m (Surcharge)

    u = 0

    'v= 10 - 0 = 10 kN/m

    'h = 0.368* 10 = 3.68 kN/m

    At Level b: Active Side

    v = 10 + (1.0 * 20.0) = 30 kN/m

    u = 0

    'v = 30 - 0 = 30 kN/m

    'h = 0.368* 30 = 11.0 kN/m

    At Level c: Active Side

    v = 10 + (2.2 * 20.0) = 54 kN/m

    u = 0

    'v = 54 - 0 = 54 kN/m

    'h = 0.368* 54 = 19.9 kN/m

    At Level c: Passive Side

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    63/198

    9.5.5 Pressure Distribution Diagram

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    64/198

    Table 6: Tr ial Depth

    D' (m)

    Resultant

    (kN/m)

    2 -296.9

    1 23.3

    1.5 -94.3

    1.2 -14.4

    1.1 5.94

    1.15 -3.85

    1.12 2.111.13 0.152

    Applying a factor of safety of 2.0:

    Depth of penetration = 2.0 * 1.13

    = 2.26m

    Therefore,

    Total Steel pile length = 2.26 + 1.2 + 1.0

    = 4.46m

    As discussed in Section 9.3.1, the length of the sheet pile does not exceed 4.5m without the safety

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    65/198

    Fi gure 9.5-4: Plan of Quay

    10. Warehouse Design

    10.1 Warehouse Structure Selection

    The type of structure used for warehouse design can vary significantly depending on the intended

    use and the loading subjected. Warehouses consist of three main types; purpose made units,

    standard units and advanced units. In the case of the steel stockholders, the warehouse will be a

    privately owned warehouse and effectively combine automated plant and a distribution centre.

    Steel coils will arrive on site, processed and then distributed just in time to the customer.Taking

    this into account, the type of structure used for the warehouse needs to be carefully considered to

    suit the final application. Areas to consider are; loadings applied, cost, on site space restrictions

    and time for fabrication and erection. The likelihood is that the design will have to be purpose

    Steel Stockholder Group 3

  • 8/12/2019 SteelStockholder_3

    66/198

    provide additional strength and allow for yet greater span lengths to be achieved. Simply spanned

    roof structures are generally flat roof construction, which affects the strength to weight ratio

    compared to other types of structure. This is unless intermediate columns are used to furtherincrease the length of the span. Using the truss roof design compared to the simple I beam span

    allows for increased restraint against lateral torsional bucking due to the inherent strength of truss

    designs.

    Bending moments of a uniformly distributed simply spanned structure are assumed maximum in

    the centre of the span. The footings require concrete pad foundations to allow for the concentratedloads subjected to the span ends. Columns transfer the loads from the roof to the foundations.

    Advantages

    Simple design, manufacture and erection

    No non useable floor space for span lengths up to 20m

    Disadvantages

    Limited span lengths of 20m (Unless additional columns are used)

    Truss design is not economic

    Steel Stockholder Group 3