Stephen Milton
Undulator System Update [email protected]
20 April, 2006
LCLS Undulator System Update
S. Milton, ANL
FAC, April 20th, 2006
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Outline
SafetySlideESH Work Authorization form
1st ArticlesInitial MeasurementsMu-metal shieldsGo forward plan
SUTQuick StatusLong range plan
Vacuum SystemSingle path recommendationFocus on solving all issuesFull length prototype in June
RF BPM ProgressMechanicalBrazingTesting
Beam Finder Wire ProgressOTR S1Beam Loss Monitoring System
Delayed due to engineering availability
SLAC MeasurementsMMF (SLAC)Assembly Planning
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Integrated Safety Management
Damaged Translation SlideMany CausesRoot Issue
Did not fully follow all ISM processes
Corrective ActionsRetraining in ISM basicsAdditional engineering and administrative controls put in place
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Work Authorization Checklist
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
1st Articles (See White’s Talk)
One each received from the two vendors
Initial Measurements and Tuning
x/y trajectories well under the 2 micron limit
RMS phase error well under the 10 deg. limit
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Undulator Production
Mu-metal ShieldsWill be implemented to buck Earth’s fieldCurrently working out the tuning procedure and overall effectiveness
Go AheadWill be given shortly to the vendors pending overall acceptance
Production PlansExpect 10 to 15 complete by end of fiscal year
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Single Undulator Test (See Pile’s Talk)
Phase IComplete assembly with either production or mock up in magnet measurement labFull fit up expected plan by the end of April
Phase IIComplete assembly with all production componentsTunnel mockup includedWill remain at ANL for refinement, trouble shooting, and value engineering
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Vacuum System (See Walter’s Talk)Single Path Pursued
Our project management oversight group was adamant about not pursuing an alternate time.
Considered too costlyMake what we have work
Current focusSolve all issues
PrototypeFull length prototype expected late June early July completion
ScheduleStill considered an undulator system critical path item
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
RF BPM
First Prototype CompletedBench Measurements
No surprises
Installation for Beam TestPlanned to install in ITS by end of month
3 BPM TestPlanned installation mid to late summer
ScheduleStill considered an undulator system critical path item
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Beam Finder Wire (See Walter’s Talk)
Excellent Progress
Testing of positioningExcellent results
5 micron repeatability
Expect PrototypeMid Summer
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
OTR S1Location
Near beam dump after analyzing magnet at 135 MeV point in linac
PerformanceSimilar to what ANL was designing for the undulator
PlanBuild what we had designed for phase I and test in operation
Improve design performance if warranted in the future
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Beam Loss Monitoring System
Basic concept establishedDetails, however, are notSchedule
Not yet on critical path, but we clearly are falling behind on the plan
PlanGet an appropriate engineer and physicist on this
This has proven difficult to maintain
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
SLAC Work
Measurement Bench (See Wolf’s talk)ANL bench on loan for development of overall production measurement and tuning planPrototype undulator at SLAC
Magnet Measurement Facility (See Wolf and Pope’s Talks)
Building construction completedEquipment to move in in the coming weeksThis will be a busy place
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Assembly Planning (See Pope’s Talk)
SLAC working closely with ANLThe SUT will be used heavily in refining overall assembly sequence
Component deliverySchedule and assemble being refined to match planned component arrivals
This is already forcing us to optimize our effort planning to improve the arrival timing
Stephen Milton
Undulator System Update [email protected]
20 April, 2006
Summary
Things are getting excitingProduction undulators are starting to arrive and be measured
There is still much to be doneThere are a few kinks we need to work out
Eg. The beam loss monitor workWe must keep our eye on some key items
BPMsVacuum Chambers
But we still believe we will meet all our critical milestones while not compromising performance