Date post: | 19-Jan-2016 |
Category: |
Documents |
Upload: | harry-thomas |
View: | 215 times |
Download: | 0 times |
STEREO SWG May 2005 1
PLASTIC Status Report to the STEREO SWG
2 May 2005 Hamburg Planetarium
UNH: A.B. Galvin (PI), E. Moebius (Lead CoI), L. Kistler, M. Popecki, J. Quinn, M. Lee, C. Farrugia, S. Turco IM
UBern: L. Blush (Lead CoI), P. Bochsler, P. Wurz
U Kiel: R. F. Wimmer-Schweingruber (Lead CoI)
MPE: B. Klecker (Lead CoI)
NASA/GSFC: B. Thompson (Lead CoI)
STEREO A
STEREO A
STEREO B
STEREO B
STEREO SWG May 2005 2
Previous Status SummaryAt the time of the previous SWG (December 2004)
FM1 had completed:Full IntegrationUNH ion gun tests for functionality/performanceIPERVibration
FM1 was midway through performance testing and calibration at the U. Bern. Issue with TOF resolution and minor coding and table changes identified.
FM2 had finished:Entrance System integration, TOF chamber integration
FM2 was midway through reassembly and functional testing (after board coatings) of power supplies and digital electronics
IDPU s/w 2.6 development and testing was ongoing at UNH/UCB
STEREO SWG May 2005 3
Previously Reported IssueNASA requested change of venue for TV/TB tests:Testing was being planned at UBern facility for late January 2005
- To save about 2-3 weeks on the FM1 delivery schedule- To provide additional personnel support (to inhibit US costs and collateral schedule erosion to FM2)- To get early notice of any low temperature issues- UBern was providing TV MGSE support, radioactive sources
Resolution:Testing to take place at GSFC facilities
- Associated schedule erosion to FM1 accepted by Project- UNH fabricated new TV MGSE (facility specific)- FM1 refurbished for “noise reduction” prior to TV- Project shall provide 3 people to supplement PLASTIC personnel support in the TV/TB round-the-clock 3 week test schedule- Project will provide radioactive sources
STEREO SWG May 2005 4
Current Status
STEREO SWG May 2005 5
FM1 Calibration at Bern Dec04-Jan05• Deflection test - tipping instrument to known elevation angles
and sweeping the deflectors on the Main and S channels with at selected energies
• ESA E/Q and Angle response (“fish”) scans at selected energies and species
• MCP efficiency for selected MCP bias, species, energies, PAC
• Energy (SSD) data for selected E/Q and species• Test of ESA and DEFL sweeping in Main Channel• Test of ESA and DEFL sweeping in Proton Channel• Extended operation at -20 kV PAC• Test of Main/Proton Chn switching by Digital Electronics
(w/o IDPU) during sweeping• Limited azimuthal scans• Test of tables (SWEEP, RA, Classification)• Test of ACTEL coding• Quadrant 0 (Solar Wind Sector) fully covered. Quadrant 1,
2, 3 selectively covered• Rate linearity tests• Limited UV test in MEFISTO • Not accomplished: planned IDPU s/w testing with real
beams (S/W NR)
STEREO SWG May 2005 6
Results from FM1 Calibration
0
500
1000
1500
2000
2500
3000
0 10 20 30 40 50 60 70
RA Azimuth (ch, 0:63)
Cou
nts
40.8237.9835.1432.329.4626.2723.7820.5917.0414.210.657.816.031.77-4.26-9.59-13.85-18.11-20.6-25.92-33.38-38.7-46.16-53.97-62.13-68.53
Deg from Ctr SWS
0
5
10
15
20
25
30
35
40
45
50
-45 -35 -25 -15 -5 5 15 25 35 45
Beam Azimuth (deg)
Avera
ge R
A P
osi
tion (
ch)
FM1-041215-1726
0
5
10
15
20
25
30
35
-25 -20 -15 -10 -5 0 5 10 15 20 25
Instrument Elevation (UBe Beta, deg)
Ph
ysic
al D
efl
ecti
on
Ch
. Main Ch Avg Peak
Fitted Values
Main Channel Deflection
0
5
10
15
20
25
30
-20 -15 -10 -5 0 5 10 15
Instrument Elevation Angle (Beta, deg)
Ph
ysic
al D
eflecti
on
Peak c
h
S-Ch Avg Peak
S-ch Fit for -10 to +10 deg
S-Channel Deflection
Solar Wind Sector Flow Angle Measurement:
STEREO L1 requirement:Proton solar wind bulk flow angle determination to within +/- 10o
Polar Angle by electrostatic deflection: -10o to +15o FOV tested Main Chan 1.5o /step Proton Chan 1.3o /step
Azimuthal Angle by Resistive Anode: Full SWS 45o FOV tested 0.5o peak angle determination for FOV +/-(2o-15o). Peak determination better than a couple degrees inside FOV +/- 2o requires PHA.
STEREO SWG May 2005 7
Results from FM1 Calibration
200
210
220
230
240
250
260
270
280
290
300
0 200 400 600 800 1000
Input Rate (kHz)
TO
F Pe
ak
Channel (c
h)
30
32
34
36
38
40
42
44
46
48
50
TO
F Pe
ak
FWH
M (
ch)
Solar Wind Sector intensity measurement:
STEREO L1 requirement:
Proton solar wind density to +/-10 [30]%
High Rate Limits and Linearity:
Required: 625 kHz for a single rate
Measured: PHA data obtained at rates up to 840 kHz.
Resistive anode rate counter exhibits monotonic increase up to 840 kHz.
1
10
100
1000
10000
100000
1000000
0 200 400 600 800 1000
Beam Rate (kHz)
RA
_Tri
g &
Fit
(H
z)
1
10
100
1000
10000
100000
SF
0,
SF
R0
, S
SD
_SW
(H
z)
SFR0 RA_Trig Fit to RA_trig SF0 SSD_SW
STEREO SWG May 2005 8
Results from FM1 CalibrationSolar Wind Sector intensity
measurement:
STEREO L1 requirement:
Proton solar wind density to +/-10 [30]%
Measurement of Efficiency as a function of azimuthal angle
Main Channel Solar Wind Sector Response for Integrated instrument 2keV He+ PAC: 20 kV at -14 deg azim.
STEREO SWG May 2005 9
Results from FM1 Calibration
Channel Electrode Ana.Con. FWHMS-Channel SCO-L 3.19 10.40% 3.23 10.40% 3.25 10.64%
SCI-U 3.59 13.80% 3.68 13.20% 3.64 10.76%ESA 8.35 6.10% 8.46 6.34% 8.47 6.26%
MC ESA 8.26 6.10% 8.24 6.12% 8.26 6.48%WAP ESA 8.32 6.70% 8.25 6.77% 8.29 7.30%
FM1 FM2
-1000
0
1000
2000
3000
4000
5000
6000
7000
180 200 220 240 260 280
beta = -6
beta = -5
beta = -4
beta = -3
beta = -2
beta = -1
beta = 0
beta = 1
beta = 2
beta = 3
beta = 4
Solar Wind Sector E/Q measurement:
STEREO L1 requirement:
Proton solar wind speed to +/-10 [30] %, temperature +/-10 [30]%
Measurement of response over incident E/Q and incident angles
Measured from 300 eV/e to 60,000 eV/e
0
200
400
600
800
1000
1200
6480 6980 7480
60 keV He+ ESA V
Rate
(H
z,
60
keV
)
0
100
200
300
400
500
600
700
2160 2260 2360 2460 2560
20 keV He+ ESA V
Rate
(H
z,
20
keV
)
SF0: 60keV He+
SF0: 20 keV He+
STEREO SWG May 2005 10
Results from FM1 CalibrationSolar Wind Sector Species
measurement:
STEREO L1 requirement:
Species resolution for protons, alphas and selected major charge groups
Requires good E/Q, good Time-of-flight and reasonable E resolution
Species Measured at Bern facility:
H+, He+, He2+, O+, O2+, Ar+, Ar2+, Ar3+, Ar4+, Ar5+, Ar6+
Solid State Detector Energy: Measured 30-420 keV ions (Higher ion energies were not obtainable given E/Q limit and available charge states of beam)Results were nominal
Time-of-Flight:Measured from 10 – 250 nsTime of Flight determination nominal, but resolution was not acceptable. Proton efficiency also suffered.
Further testing at UNH determined that TOF inputs were picking up the 200 kHz syncing of the power supplies (nX50khz EMC Plan requirement). Shielding, filtering, and thresholds have been added to FM1 and FM2.
STEREO SWG May 2005 11
Improvement in TOF Resolution after Noise Reduction
• Noise reduction efforts improved time of flight resolution
• Lower noise allows lower threshold – improved proton efficiency
• Quadrant 0 spectra shown (solar wind sector)
• Data from UNH ion gun – ambient air beam
0
10
20
30
40
50
60
70
80
0 200 400 600 800 1000 1200
Time of Flight (ch)
Co
un
ts
Post-noise refurbishment: Q0, 50keV
Pre-noise refurbishment: Q0, 65 keV
PLA-FM1-050411-1630 post-refurb.PLA-FM1-041121-1444 pre-refurb
|Proton peak
|Water Group
0
5
10
15
20
25
30
2400 2500 2600 2700 2800 2900 3000 3100 3200 3300
MCP V
H+
TO
F F
WH
M (
gaus
sian
) Q
0
0
5
10
15
20
25
30
2400 2500 2600 2700 2800 2900 3000 3100 3200 3300
H+
TO
F F
WH
M (
gaus
sian
)
Q2,
3
Q0
Q2
Q3
15kV PAC, 35 keV air, TAC thresh Rs in external boxes
t ~3ns FWHM in SSD sectiont ~ 2ns FWHM in non-SSD section
STEREO SWG May 2005 12
Then and Now Species Determination
0
500
1000
1500
2000
2500
3000
0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2Mass/charge (amu/e)
Fre
quency
0
50
100
150
200
250
300
60 keV H+ Pre-refurb
35 keV H+ Post-refurb.
0
50
100
150
200
250
300
350
400
450
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8 3
Mass (amu)
Qty
0
10
20
30
40
50
60
70
80
90
100
0.0
0
0.2
0
0.4
0
0.6
0
0.8
0
1.0
0
1.2
0
1.4
0
1.6
0
1.8
0
2.0
0
2.2
0
2.4
0
2.6
0
2.8
0
3.0
0
60 keV H+ Pre-Refurb.
35 keV H+ (air) Post-Refurb.
L1 Species Requirement now met.
STEREO SWG May 2005 13
FM1 Current Status-- All issues identified from performance testing corrected
(noise reduction, actel code changes for science product)-- Passed vibration-- More than 500 hours of trouble free testing in vacuum at operational voltages
STEREO SWG May 2005 14
FM1 Current Status-- All issues identified from performance testing corrected
(noise reduction, actel code changes for science product)-- Passed vibration-- More than 500 hours of trouble free testing in vacuum at operational voltages
Almost made it out the door in late March …
Flight board re-inspection in March 2005 raised QA issues regarding component placement on “SSD C” board. Board is part of the solid state detector electronics. Component placement on original flight boards was primarily motivated by crosstalk and LED response issues.
New boards “SSD C-3” and “SSD-4” built to replace “SSD C-1” (FM1) and “SSD C-2” (FM2) respectively. Components mounted differently. NASA inspectors very helpful. Additional board and flight parts purchased for SSD-4. Three week minimum turn around per board.
STEREO SWG May 2005 15
Replacement Board StatusReplacement board SSD C-3 integrated into FM1 almost two weeks ago.
New C-3 board does not respond properly in the integrated instrument.
Trouble shooting is continuing this week. Requires major disassembly and reassembly activities.
Access to board requires removal of entrance system, power supplies, and electronics box. Retest requires re-assembly.
This process has been done several times in past week. Concern about mechanical fatigue. Designing and fabricating new testing jig to allow more “lifelike” testing outside of instrument.
SSD Electronics
STEREO SWG May 2005 16
Other StatusFM2 has been fully assembled and gone through initial functional testing. -- performance looks good
-- noise reduction looks good-- no sensor problems identified, except for LVC voltage
regulation behavior at low (near zero) temperatures-- LVC returned to UCB for troubleshooting-- FM2 waiting in queue behind FM1 for SSD C board exchange
Project has put into place major resources to assist in the PLASTIC portion of the IMPACT/PLASTIC IDPU. Flight s/w build 2.7 is in “beta testing”. Build 2.8 may be ready to start beta testing later this week. Build 2.8 could potentially be validated by end of May. Build 3.0 (science) may be ready and partially validated by end of June. Can proceed with electrical integration of PLASTIC on the spacecraft with a validated build 2.8.
All testing with IDPU flight s/w thus far is with PLASTIC EM electronics. There may not be an opportunity to fully validate science product section of s/w with actual FM beam calibrations.