Date post: | 21-Oct-2014 |
Category: |
Business |
View: | 12,872 times |
Download: | 0 times |
Program Startup Workshop--A Program Transition Assist--
Jess Stewart
Defense Acquisition University (DAU) Fort Belvoir, Virginia
February 24-25, 2009
Program Startup Workshop (PSW): “WHY”
• Many DoD programs struggled or have failed due to Lack of :– Common vision & plan for success– Understanding of performance measurement
baseline including program risks
• Importance of working together to start new programs underestimated
DOD & Industry: Finding a Better Approach TogetherDOD & Industry: Finding a Better Approach Together
Background• NDIA/DUSD (A&T) Program for 2008 Emphasis
• The Workshop is intended to better start new or programs in transition and:– Held soon (3-6 weeks) after contract award – Jointly conducted with government and contractor
teams
It’s the Culture
What We Have Found• Preparing for a Workshop after Contract
Award is Very Difficult– Neither the Government or Contractor are
Typically Well Prepared to Align Processes and Teams
– Need RFP to Contain Requirement for Workshop
– Government Must Model Behaviors Prior to Source Selection & Communicate Expectations
A New Contract is a Cultural Change!
The “What” of a New Program Startup Workshop
Workshop ObjectivesProgram• Produce key program startup products
• Improved Roadmap to Integrated Baseline Review (IBR)
• Integrated Product Team (IPT) Tasks, Charters and Sustainment Process
People• Build an environment of trust, collaboration,
teamwork and communication• Align Teams
Planning Timeline: Earlier is Better!
Model PostEvent
Event + 4-6 WksEvent + 2 WksEvent + 1 Wk
Contract Award
Workshop planning scheduledFacilitator confirmed
Pre-Workshop planning meetingReview/tailor workshop modulesEstablish administrative responsibilities
RFP
DFAR Clause
Conduct workshop(move earlier if DFAR Clause used
• Program Managers • Deputy PMs• PCO/Contracting Head• Chief Financial Mgrs• EVM/IBR Leads• Chief Engineers• Chief Logisticians• Significant IPT Leads• DCMA PI /ACO/EV• PMs of Major Subs Sponsor/User Rep Facilitation Team
• Program Oversight• Training• Integrated Baseline Review• Grading Program Managers• Baseline audit• Negotiation of Contract Changes• Post Award Orientation or
Conference (unless integrated by government into workshop)
Not just for New Starts!
• Alignment of Gov’t & Industry • Clarifications & Emphasis:
- Transparency - Communications Plans- Key Contract Requirements- Baseline Management
- - Mgt. Reserve / Incentives- IMP/IMS - Change Management- Data/Workflow Management
• IBR Execution Plan• PMR Process Including Metrics• Risk Management• IPT Charters, Responsibilities, etc• Other Topics Selected By PMs
Early Alignment & Mutual Commitment To Program Success
What NPSW IS What NPSW Isn’t Participants
Observations!
Some Observations• Noted!
– I didn’t plan for a workshop– This looks like work– If I wanted a workshop I would have done one– Why would I invite OSD in—to help? (I’m already helped)– You don’t work for me– The contractor didn’t bid it– Corporate—we never let them in the door– My people are too busy doing work (and we know what
we are doing) or I’m too busy ; or– Every Program Should Have One
But Here is the Rest of The Story!
Rest of the Story• Change of Program phase (All Milestones/Nunn-
McCurdy) Planning often Immature– Workshop helps model government and contractor team
interaction for new phase (best to do early)• Workshop focuses on team management—how & what
the teams do– Sets clearer expectations on team roles– Team roles, responsibilities and reporting often not clearly
defined– EVM use and pre IBR planning not Fleshed Out
Transition Challenge
Rest of the Story (Cont.)• Independent third party facilitization an asset for
PMs—less program or contractor spin
• Corporate Participation focuses Contractor Program Managers Objectives
• PMs Understanding of Each Other Often Superficial
• Workshop is Basic Program Management– Helps to Prepare Team
What Should You Consider for
Your Workshop?
Thoughts for Best Results
• Program Managers Must be on Message– Have Agenda/Strategic Objectives
• Model Processes to Implement Strategy– Teams need Processes and Leadership
• Transition Assist Visits Useful– Internal Alignment Prior to Contract Award– Peer and/or Non-Advocate Reviews
Leadership Meets Management
Workshop Mechanics• Pre RFP planning and training best approach
– Include Clause in RFP for Workshop
• Pre-meeting between Govt. and Contractor PMs to tailor Workshop agenda – Potentially multi-meeting expanded post award conference
and workshop– Principals required to set tone for workshop
• Facilitator role agreed to by PMs and Facilitator Team Lead
• Facilitators work with IPT leads in reviewing presentations----Coaching
Pre-Workshop Planning
• PMs “One on One” for Personal Alignment
• Both Program Managers Participation in Workshop Planning is Key
• Program/Project Leadership and Facilitators Review Workshop Detailed Objectives; i.e. Weekly metrics/EVM data
• Tailor workshop agenda
1415-1430 BreakGovt./Cont.Executives
1415-1430 Introductions
0915-0930 Break
1500-1630PM Review
– Path to IBR– Action Items– Team Challenges
1200-1500IPT Status
– Charter Update– Responsibility– Accountability– Problem
Resolution– Risk Register– IBR Planning– IMP/IMS Issues– Comms Plan– Near Term
Deliveries– GFE Review
1130-1200Working Lunch
0745-1130IPT Working Sessions
0730-0745Recap
Event
PMs
Facilitator(Moderator)
IPT Leads(Co-Brief)
Facilitator(Moderator)
IPT Leads
PMs/DAU
Briefer
1730-2030Dinner & Social
1430-1730IPT Working Sessions
1345-1415Comm./Collaborative WorkflowProblem/Conflict Resolution
1245-1345Risk & Opportunity Mgmt / IMP/IMS
1200-1245Program Metrics/Best Practices
1130-1200Working Lunch
0930-1130Contract Baseline, Incentives, & Change Mgmt
0830-0915Program Startup (IBR) Overview
0745-0830User Viewpoint/Reporting Reqts
0730-0745Recap
Event
IPT Leads
DAUCont./Gov.
DAUCont./Gov.
DAUContractorGovernment
DAUCont./Gov.
DAUCont./Gov.
Users
PMs/DAU
Briefer
PMs1515-1630PM Values & Vision
DAU1430-1515Program Strengths/ Barriers to Success
DAU1400-1415 Workshop Overview
BrieferEvent
Detailed schedule for a 2.5 day workshopDetailed schedule for a 2.5 day workshop
Notional Post MS B Workshop ModuleModule Title: Workshop Products Captured:
Module 1: Workshop Orientation Program Vision, Values, Mission, GoalsList of Program Success Factors and Potential Problem Areas (Force Field Analysis)
Module 2: Program Startup Plan to Integrated Baseline Review (IBR)
Validated IBR Roadmap (Startup Plan)IMS/IMP/Critical Path AnalysisList of Action Items and POCs(Potential Side meeting on processes)
Module 3: Contract Baseline Change/Scope ManagementSubcontractor Management
Common Contract Framework UnderstandingIncentives/CPAR Application Contract Point of Contacts ListList of Issues That Need Clarification/Resolution
Module 4: Govt. and Industry Key Practices Practices Applicable to Program – Govt. & Contractor
Module 5: Integrated Product Team (IPT) Structuring & Chartering
IPT Charters, Integrated Master Sched., IPT ResponsibilitiesTeam inputs to IBR Preparation, CDRLs, Communications Plan & Risk/Opportunity Management
Module 6: Communications Planning/Collaborative Workflow
Communications Content and SchedulingCollaborative Work ProcessesProblem/Conflict Resolution
Post MS B Workshop Modules (Cont.)
Module Title: Workshop Products Captured:
Module 7: Risk and Opportunity Management
Documented Risk and Opportunity Mgt. ProcessActions for Joint Risk Process
Module 8: Program Metrics Program Metrics-PoPS/Ps/Industry Best Practice Metrics/Detailed Program Metrics
Module 9: PMs’ Wrap-up PMs and Team Commitment to Work Together to Achieve Program GoalsAgreed Actions Item List
Examples
Joint Tactical Radio Airborne, Maritime, Fixed (JTRS AMF)Key Benefits
1. Unlike Contract “Kick-Off” Meeting, Teams had Objective Tasks Assigned Prior that Focused on IBR and Beyond Success– Lesson Learned from Program’s with Successful IBR, but Subsequent Struggles
2. Getting the Team Together Early with Focused Tasks Resulted in – Opening / Re-Opening Lines of Communications– Exposing Blind-Spots Early– Closure Oriented Actions
3. Realigned the Government and LM Team from a Restrictive Pre-Milestone B Dual Competition Environment to a Collaborative IPT Operating Model – Joint Development of IPT Charter to be Applied to all IPTs
4. Established the Need for Future Meetings to Continue Success to CDR and Beyond– Partnership and Collaboration is not a One-Time Event
Additional JTRS (AMF) Observations• Perfect Timing
– Strong Team Building and Perspective Exchange– Both Sides Noted Excellent Setting of Tone– No Negative Energy
• Successful Blending of DAU and LM Corporate Wisdom – Leveraged Lessons from Past/Present Programs – Positioned for Continuity for Follow-Up Engagement(s)
• Excellent Information Sharing on New/Updated Customer Organization – Lexicon & Roles/Responsibility Exchange Supports Integration
• Bottom Line - Successful– Lowered Risk to IBR– Key Sync Points Made (e.g. LM PM added to Government CCB)– No Major Issues Identified
• Confidence Builder through Sharing of Existing Processes/Procedures and Plans• Adjustments and Forward Actions will make us Stronger
– Joint Program Processes – Requirements (DOORS), Risk/Opportunity, Metrics
“ One Program Team” Better Enabled to Execute IBR & Beyond ““ One Program TeamOne Program Team”” Better Enabled to Execute IBR & Beyond Better Enabled to Execute IBR & Beyond
C-5 RERP Program Start-Up Workshop (PSW) Summary
8 Sep 2008
24
Bottom-Line Up Front• PSW was worth the work—forum for joint discussion
of relevant and time-sensitive issues– Lessons learned applied: conducted extensive pre-work– Aggressive agenda, but all topics addressed– Key focus on LRIP IBR planning and tracking to plan– DAU and LM Corporate facilitation team kept the team on
track
• 54 Action Items assigned– No show-stoppers, but some substantial topics – Part of normal business flow
• Will be worked by IPTs • Will be statused in RERP team meetings
25
Purpose of C 5 RERP PSW
• Lay groundwork for successful LRIP IBR
• Focus on LRIP/Production and associated cultural changes with a fixed price environment
• Engage all stakeholders to:– Reinforce effective communications – Ensure clarity of expectations– Identify specific actions for a clear way ahead
—A Program Transition Assist!
- Practical Program Alignment Tool-
-Driving Cultural Change-
Questions?
The “New” Program Startup Workshop
Additional Slides
Workshop “Mechanics”
• Facilitators present workshop process early in workshop– Get a feeling from the participants on success factors/program
barriers• PMs/Corporate/PEOs provide facilitators their areas of
concern for emphasis• Mapping of IPTs before workshop is expected• Workshop briefings are initially given from the perspective of
the government’s and contractor’s team leads– DAU or other presentation provided on request
• Recommend PMs brief PEO/corporate VP on workshop action items
Workshop Feedback“Our evolved agenda, which allowed the User and Resource Sponsor to express their viewpoints, was CRITICAL for contractor awareness and understanding of the warfighter “big picture.”
“We did deliver products: face-to-face meetings to establish “running rules”, the way ahead, program issues, and formulation of joint team charters.”
“The key accomplishment was to have Government and Contractor team lead counterparts sit down with one another in a relaxed forum to discuss broad-based and team-focused challenges.”
“Some people questioned why DAU was involved, thought Contractor/Government could have done it on their own. I disagree, DAU was the forcing function, we would not have done this on ourown.”
Example Program Startup Workshop--Typical Modules for Tailoring
PM’s Wrap-up
8am
9am
10am
11am
12pm
1pm
2pm
3pm
4pm
5pm
6 pm
Day 1 Day 2 Day 3 Day 4 Day 5
9Plan for Post Program
Start-up ReviewAffirm Schedule,
immediate priorities, &Parking lot
8Program Metrics
2AProgram Contract
Baseline
No Host Social Event
Lunch
1Program Startup
WorkshopOrientation
Lunch
5(cont.)IPT Structuring& Chartering
Lunch
15 min wrap-up/next day
15 min morning kick-off
2BContract Change
Mgt. & Subcontractor Mgt.
7Program Risk
and Opportunity
6Communications
Planning& Collaborative
Workflow
15 min wrap-up/next day
15 min morning kick-off
15 min wrap-up/next day
15 min morning kick-off
IPT Report-out
15 min morning kick-off
IPT Structuring& Chartering
4Key Practices
IPT TimeNo Host Evening
Event
Working Lunch
3Roadmap to IBR
5IPT Chartering
Workshop Tailorablefrom 2.5 to
4.5 days
Workshop FlowWorkshop Introduction (Challenges & Vision)
-Executives, PMs, Sponsors and/or Users/Facilitator
Topic Introduction-DAU/Corporate Facilitator—Areas for Module Discussion-Govt. and Contractor Present their Baseline
Process/Progress for Module
IPT Chartering Session-IPTs Work Through Each Module-IPT Cont./Govt. Co-Leads brief Joint Charter, Issues &
Actions
PMs Establish Workshop Action Items
Prime Program Team 15 - 25Subcontractors 2 - 6Govt. Program Team 10 - 15Resource Sponsor 1 - 3DCMA 1 - 2DAU & Corporate 4 - 6Total 33 - 57
Workshop Participants –More Attendees are Program Socialization!
Key Leadership Team Members