Stormwater Program Workshop Public Works Department May 1 st , 2019 Focus on the Customer Focus on the Environment Focus on the Future 1
Transcript
  • Stormwater Program

    Workshop Public Works Department

    May 1st , 2019

    Focus on the Customer

    Focus on the Environment

    Focus on the Future

    1

  • • Overview

    • Sustainability Plan

    • Funding

    Stormwater Program Workshop

    2

  • Overview

    3

  • A Sustainable Stormwater System

    Vision

    Cultivate a sustainable and financially responsible stormwater

    management system.

    • Asset preservation and minimize risk of flood damage.

    • Look for opportunities to include green infrastructure in projects.

    • Seek out, evaluate, and implement innovative methods to improve water

    quality, storm event management, and customer service.

    4

  • One Water Approach

    • Sustainable management of life’s most essential resource

    • All water is valuable • Rivers, lakes, reservoirs, aquifers

    • Watershed Planning • Include regional partners to

    respond to the natural flows of watersheds and the natural ecosystem.

    5

  • Watersheds

    • Hillsborough County has 17 watersheds

    • Cover 1354 Sq Miles

    • Polk County and Pasco County contribute

    122 Sq Miles drainage area to

    Hillsborough River

    • Polk County contributes 159 Sq Miles

    drainage area to Alafia River Watershed

    • Little Manatee River Watershed covers

    76 Sq Miles Manatee County area

    • SWFWMD Interjurisdictional Regulatory

    Agency

    6

  • • Pipes – 1,313 Miles

    • Ditches – 1,345 Miles

    • Drainage Structures – 41,545

    • Ponds – 2,099

    • Pump Stations - 36

    Stormwater System Assets

    Pump Station Rehab

    Lucy Dell Pond Enhancements

    7

  • FY 18 Revenue and Expenditures

    Capital

    Program,

    $22.6M, 52%

    Maintenance /

    Operations,

    $16M, 37%

    Engineering /

    Investigation,

    $4.8M, 11%

    Unincorporated

    General Fund,

    $20M, 46%

    Grants, $1.5 M,

    3%

    Assessment,

    $21.9M, 50%

    REVENUE EXPENDITURES $43.4 Million $43.4 Million

    Stormwater

    Current Assessments

    • Single Family Home: $42.00

    • Apartment / Condominium / Townhouse / Mobile Home: $21.00 per dwelling

    • Agricultural: $42.00

    • Commercial / Industrial: $.035 per 1.5 square feet of impervious area

    8

    https://Agricultural:$42.00https://SingleFamilyHome:$42.00

  • Clean

    Annual Improvements

    Maintenance

    • 50.2 miles of pipe

    • 1,228 drainage structures Plan • 80 miles of ditch

    • 15k cubic yards of sediment

    Capital

    • 5 Watershed Studies Updated

    • 12 Watershed Studies Underway

    Repair • 1.7 miles of pipe

    • 435 drainage structures Design • 58 Flood Protection Projects

    Mow • 3,320 acres Construct • 14 Flood Protection Projects

    • 131 Pipe Replacement Projects

    Keeping Drainage Working

    9

  • Focus on the Environment

    10

    Compliance

    Inspection

    Analysis

    Action

    Met 100% inspection requirements.

    Over 9,680 assets and 500 miles ditch/pipe

    inspected.

    Monitored 512 sites on 80 waterbodies.

    Studied 43 waterbodies for health of system.

    Water quality projects/initiatives,

    nutrient source tracking, tree planting, street

    sweeping, rain gardens, pollution prevention.

    Compliance with Federal National Pollutant

    Discharge Elimination System (NPDES) and

    state environmental protection agencies.

  • - -

    Focus on the Environment

    Collaboration • Tampa Bay Estuary Program

    • Nitrogen Management Consortium

    • Adopt A Pond

    • Keep Tampa Bay Beautiful

    Innovation • One Water Initiative

    • Green Infrastructure

    • Conservation

    • Aquifer Recharge

    11

  • Sustainability Plan

    12

  • FY 2018 Stormwater Work Requests

    13

    • Demand for maintenance and

    flooding reduction

    • Increased maintenance

    • Pre-regulatory development

    • Aging infrastructure failures

  • --

    Maintenance Service Levels

    Asset Maintenance Activity Existing Service Level

    Pond Systems

    Pump Stations

    Major Outfalls

    Drainage Structures

    Pipes

    Ditches

    Street Sweeping

    • Prevent erosion & maintain healthy vegetation

    • Debris and sediment removal

    • Inspection and repair: electrical and mechanical

    systems

    • Inspect for condition and obstructions

    • Clean, repair, and replace pipe/structures

    • Inspect for clogs and damage

    • Jet clean and vacuum or repair

    • Maintain flow

    • Clean, repair, and replace pipes

    • Trash and debris removal

    • Clean, mow, and spray to maintain flow

    • Arterial roadways approx. 663 lane miles per month

    • Demand sweeping citizen requests

    • Local roadways approx. 4500 lane miles per year

    Sustainable Service Level

    10 Year Cycle

    60 Day Cycle

    Biannual Cycle

    50 Year Cycle

    Quarterly Cycle

    50 Year Cycle

    10 20 Year Cycle

    17 Year Cycle

    25 100 Year Cycle

    25 Year Cycle

    15 Year Cycle

    Quarterly Cycle

    20 Year Cycle

    Annual Cycle

    14

  • Asset Management Typical Life Span Average Asset Age

    Pump Stations

    • Pumps & Equipment 15 years

    • Wet Well 75 years

    Metal Pipes – 40 years

    Concrete Pipes and Structures – 75 years

    16 years

    19 years

    New Asset

    Maintain

    Inspect

    Repair

    Replace

    39 years

    29 years

    Asset

    Life Cycle

    15

  • -

    Asset Preservation Service Levels

    Asset Activity

    Pump Stations

    Pipes

    Flood Projects

    • Pump Station life cycle replacement

    • Pipe life cycle replacement

    • Neighborhood, Intermediate, Regional

    Flood Protection Projects

    Water Quality

    Hazard Mitigation

    • Regulatory Compliance

    • Environmental protection and

    restoration

    • Reduce community flood risk costs and

    impacts

    Existing Service Level Sustainable Service Level

    30 Year Replacement

    10 year backlog reduction

    60 year life cycle replacement

    5 year Critical backlog reduction

    Neighborhood, Intermediate & Regional Projects

    Enhanced water quality projects

    County funded flood area mitigation projects

    30 Year Replacement

    Unfunded backlog

    90 100 year life cycle replacement

    Unfunded backlog

    Neighborhood Projects

    NPDES Compliance

    Limited to Grant Availability

    16

  • Sustainable Funding Proposal

    Operation & Maintenance

    Asset Preservation

    Flood Protection, Water Quality & Hazards Mitigation

    Total

    Existing Funding Increased Funding Total Outcomes

    $20.8M

    $15.1M

    $7.5M

    $43.4M

    $32.7M

    $28.8M

    $20.2M

    $81.7M

    $11.9M

    $13.7M

    $12.7M

    $38.3M

    • Improve customer satisfaction

    • Preserve and restore drainage flow

    • Improved water quality

    • Regulatory compliance

    • Replace failing assets to eliminate backlog

    • Safety and property protection

    • Reduces annual repair costs

    • Develop and refine flood protection projects for future

    funding opportunities

    • Regional and Intermediate project design and

    construction

    • Regulatory compliance

    • Environmental protection and restoration

    • Reduce community flood risk costs and impacts

    17

  • Assessment Options

    18

  • -

    -

    Program Revenue

    • Original Stormwater Assessment Ordinance adopted in 1989

    • Currently funds capital and water quality

    • Historically supplemented by the General Fund, Community Investment Tax (CIT), and Grants

    • Current rate method:

    • Residential one size fits all

    • Commercial cost per square foot impervious

    After

    Pipe Replacement Pipe Rehab

    Before

    19

  • • Updated Rate Method

    • Full Program Cost Recovery

    • Sustainable Level of Service (maintenance & capital)

    Assessment Options

    20

  • Rate Methods

    Impervious Area ≈ 1,415 ft²

    • Current Rate Method : Based on assumed 1,800 ft² average impervious area on residential lot (Est. 1990).

    • Updated Rate Method : Based on actual 4,267 ft² average impervious area on residential lot and tiered sizes.

    Small Medium Large

    Impervious Area ≈ 3,200 ft² Impervious Area ≈ 5,120 ft²

    21

  • Method Revenue Source Comparison UPDATED METHOD

    (ACTUAL AVERAGE 4,267 FT²)

    CURRENT METHOD

    (ASSUMED AVERAGE 1,800 FT²)

    Residential,

    386,505,000 SF,

    45%

    Commercial,

    475,569,951 SF,

    55%

    CURRENT METHOD REVENUE

    Residential,

    918,186,416 SF,

    66%

    Commercial,

    475,569,951 SF,

    34%

    UPDATED METHOD REVENUE

    Residential,

    $12,841,584

    54%

    Commercial,

    $11,096,694 ,

    46%

    Residential,

    $17,172,776,

    73%

    Commercial,

    $6,226,435,

    27%

    ,

    22

  • Full Program Cost Recovery

    CURRENT FUNDING SOURCES PROPOSED FUNDING SOURCES Stormwater

    $43.4 Million $43.4 Million Assessment,

    $21.9M, 50%

    3%

    Grants, $1.5M,

    Grants,

    $1.5M, 3%

    Unincorporated

    General Fund,

    $20M, 46%

    Stormwater

    Assessment,

    $41.9M, 96%

    23

  • Residential Assessment Options

    Existing Number of Updated Revenue Method Households Method Neutral Rate

    $31.43 per year

    $57.15 per year

    $87.44 per year

    -$10.57

    +$15.15

    +$45.44

    32,697

    153,402

    27,845

    $42 per year

    Small

    Medium

    Large

    Rate Equity

    24

  • Residential Assessment Options

    Existing Number of Updated Full Cost Full Cost Method Households Method Recovery Recovery Rate

    +$25.55

    +$46.44

    +$71.06

    $56.98 per year

    $103.59 per year

    $158.50 per year

    -$10.57

    +$15.15

    +$45.44

    32,697

    153,402

    27,845

    $42 per year

    Small

    Medium

    Large

    Reduce General Fund

    Expense Rate Equity

    25

  • Residential Assessment Options

    Existing Number of Updated Full Cost Additional Rate

    Method Households Method Recovery Maintenance

    +$25.55

    +$46.44

    +$71.06

    +$15.31

    +$27.83

    +$42.58

    $72.29 per year

    $131.42 per year

    $201.08 per year

    -$10.57

    +$15.15

    +$45.44

    32,697

    153,402

    27,845

    $42 per year

    Small

    Medium

    Large

    Increased Level of Service

    Reduce General Fund

    Expense Rate Equity

    26

  • Residential Assessment Options

    Existing Number of Updated Full Cost Additional Additional Sustainable Method Households Method Recovery Maintenance Capital Rate

    Present Future

    +$34.00

    +$61.81

    +$94.57

    +$15.31

    +$27.83

    +$42.58

    +$25.55

    +$46.44

    +$71.06

    -$10.57

    +$15.15

    +$45.44

    32,697

    153,402

    27,845

    $42 per year

    Small

    Medium

    Large

    $106.28 per year

    $193.23 per year

    $295.66 per year

    Increased Level of Service

    Reduce General Fund

    Expense Rate Equity

    Life Cycle High Risk Pipes

    27

  • Commercial Assessment Options

    Actual Existing Updated Revenue Impervious Method Method Neutral Rate

    Area (ft²)

    $107.15 per year

    $200.91 per year

    $267.88 per year

    Rate Equity

    $186.87 per year

    $350.00 per year

    $466.67 per year

    8,000

    15,000

    20,000

    -$79.72

    -149.09

    -$198.79

    28

  • Commercial Assessment Options

    Actual Existing Updated Full Cost Full Cost Impervious Method Recovery Rate Method Recovery Area (ft²)

    +$87.07

    +$163.26

    +$217.68

    $194.22 per year

    $364.17 per year

    $485.56 per year

    Reduce General Fund

    Expense Rate Equity

    $186.87 per year

    $350.00 per year

    $466.67 per year

    8,000

    15,000

    20,000

    -$79.72

    -149.09

    -$198.79

    29

  • Commercial Assessment Options

    Actual Existing Updated Full Cost Additional Impervious Rate Method Method Recovery Maintenance Area (ft²)

    +$52.88

    +$97.41

    +$130.81

    +$87.07

    +$163.26

    +$217.68

    $247.10 per year

    $461.58 per year

    $616.37 per year

    Increased Level of Service

    Reduce General Fund

    Expense Rate Equity

    $186.87 per year

    $350.00 per year

    $466.67 per year

    8,000

    15,000

    20,000

    -$79.72

    -149.09

    -$198.79

    30

  • Commercial Assessment Options

    Actual Existing Updated Full Cost Additional Additional Sustainable Impervious Method Method Recovery Maintenance Capital Rate

    Present Future Area (ft²)

    $186.87 per year

    8,000 -$79.72 +$87.07 +$52.88 +$117.44 $364.54 per year

    +$216.34

    +$290.52

    +$97.41

    +$130.81

    +$163.26

    +$217.68

    $677.92 per year

    $906.89 per year

    Increased Level of Service

    Reduce General Fund

    Expense Rate Equity Life Cycle

    High Risk Pipes

    $350.00 per year

    $466.67 per year

    15,000

    20,000

    -149.09

    -$198.79

    31

  • Stormwater Assessment

    • Original Stormwater Assessment Ordinance adopted in 1989.

    • Notification processing, rate hearing in August.

    32

  • Residential Rate Comparison

    Annual Residential Assessment - Medium Size Home

    $300 $280

    $250 $230

    $200 Sustainable Rate : $193.23

    $175

    $187

    $160 $160 $163 $163 $165

    $150 $139 $143

    $118 $120 $125

    $100 $82 $91 $91 $95

    $72

    $50 $42 $47 $53

    $58 $60

    $-

    1) Currently Effective Rates as of 10/1/2018;

    2) Rates may not reflect Full Cost Recovery

    33

  • Recommendations

    34

    • Incorporate tiered residential method

    • Full cost recovery

    • Increased level of service in maintenance

    • Sustainable capital funding

  • 7/8

    8/7 10/16/19

    5/1

    Program Timeline

    Public Hearing Public Hearing Rates Effective

    Request

    2019

    10/1

    2020

    8/7 6/19

    7/8

    This image cannot currently be displayed.

    OCT NOV DEC JULY AUG SEPT APRIL MAY JUNE

    5/1

    JAN FEB MAR

    Workshop Mailers & Ad

    35

    OverviewSustainabilityPlanAssessmentOptionsRecommendations


Recommended