Date post: | 17-Dec-2015 |
Category: |
Documents |
Upload: | violet-norris |
View: | 224 times |
Download: | 1 times |
Strategic Capacity PlanningDefined
• Capacity: the ability to hold, receive, store, or produce.
• Strategic capacity planning is an approach for determining the overall capacity level of capital intensive resources, including facilities, equipment, and overall labor force size.
The Experience Curve
Total accumulated production of units
Cost orpriceper unit
As plants produce more products, they gain experience in the best production methods and reduce their costs per unit.
Capacity Focus• The concept of the focused factory holds
that production facilities work best when they focus on a fairly limited set of production objectives.
• Plants Within Plants (PWP) (from Skinner)– Extend focus concept to operating level
Example of a Decision Tree Problem
A glass factory specializing in crystal is experiencing a substantial backlog, and the firm's management is considering three courses of action:
A) Arrange for subcontracting,B) Construct new facilities.C) Do nothing (no change)
The correct choice depends largely upon demand, which may be low, medium, or high. By consensus, management estimates the respective demand probabilities as .10, .50, and .40.
Example of a Decision Tree Problem: The Payoff Table
Probability 0.1 0.5 0.4Low sales Medium sales High sales
Subcontract 10 50 90Build new -120 25 200No change 20 40 60
The management also estimates the profits when choosing from the three alternatives (A, B, and C) under the differing probable levels of demand. These costs, in thousands of dollars are presented in the table below:
Example of a Decision Tree Problem: Step 1. We start by drawing the three decisions
Subcontract
Build New
No Change
Example of Decision Tree Problem: Step 2. Add our possible states of nature, probabilities, and payoffs
Subcontract
Build New
No Change
High demand (.4)
Medium demand (.5)
Low demand (.1)
$90k$50k
$10k
High demand (.4)
Medium demand (.5)
Low demand (.1)
$200k$25k
-$120k
High demand (.4)
Medium demand (.5)
Low demand (.1)
$60k$40k
$20k
Example of Decision Tree Problem: Step 3. Determine the expected value of each decision
High demand (.4)
Medium demand (.5)
Low demand (.1)
Subcontract
$90k$50k
$10k
EVA=.4(90)+.5(50)+.1(10)=$62k
$62k
Example of Decision Tree Problem: Step 4. Make decision
High demand (.4)
Medium demand (.5)
Low demand (.1)
High demand (.4)
Medium demand (.5)
Low demand (.1)
A
B
CHigh demand (.4)
Medium demand (.5)
Low demand (.1)
$90k$50k
$10k
$200k$25k
-$120k
$60k$40k
$20k
$62k
$80.5k
$46k
Alternative B generates the greatest expected profit, so our choice is B or to construct a new facility.
Capacity Utilization & Service Quality
• Best operating point is near 70% of capacity - balances efficiency and reserve
• From 70% to 100% of service capacity, what do you think happens to service quality? - customers are serviced, but service quality often declines
Components of Demand• Average demand for a period of time
• Trend
• Seasonal element
• Cyclical elements
• Random variation
• Autocorrelation
Delphi Methodl. Choose the experts to participate. There should be
a variety of knowledgeable people in different areas.
2. Through a questionnaire (or E-mail), obtain forecasts (and any premises or qualifications for the forecasts) from all participants.
3. Summarize the results and redistribute them to the participants along with appropriate new questions.
4. Summarize again, refining forecasts and conditions, and again develop new questions.
5. Repeat Step 4 if necessary. Distribute the final results to all participants.
2 Period Moving Average( Weekly Video Rentals)
650
660
670
680
690
700
710
720
3 4 5 6 7 8 9 10 11 12 13
Week
Vid
eo
Ren
tals
Forecast
Actual
Which Forecast Would You Prefer?
4 Period Moving Average(Weekly Video Rentals)
650
660
670
680
690
700
710
720
5 6 7 8 9 10 11 12 13
Week
Vid
eo
Ren
tals
Forecast
Actual
Which Forecast Would You Prefer?Exponential Smoothing (Weekly Video Rentals)
a = .1
620
630
640
650
660
670
680
690
700
710
720
2 3 4 5 6 7 8 9 10 11 12 13
Week
Vid
eo R
enta
ls
Forecast
Actual
Exponential Smoothing (Weekly Video Rentals)a = .6
620
630
640
650
660
670
680
690
700
710
720
2 3 4 5 6 7 8 9 10 11 12 13
Week
Vid
eo R
enta
ls
Forecast
Actual
In Class Example
3 Period Moving Average
July 110
August 115
September 105
October 110
November 125
December 110
January
(110 +115 + 105)/3 = 110
(115 + 105 + 110)/3 =110
(105 + 110 + 125)/3 = 113.333
(110 + 125 + 110)/3 = 115
In Class Example
Exponential Smoothing, a = .4 Ft = aAt-1 + (1- a)Ft-1
July 110
August 115
September 105
October 110
November 125
December 110
January
110
.4(110) + (1-.4)110 = 110
.4(115) + (1-.4)110 = 112
.4(105) + (1-.4)112 = 109.2
.4(110) + (1-.4)109.2 = 109.52
.4(125) + (1-.4)109.52 = 115.71
.4(110) + (1-.4)115.71 = 113.43
In Class 2 a = .4
At Ft
Forecast Error RSFE
Absolute Deviation MAD TS
July 110 110.0
August 115 110.0
September 105 112.0
October 110 109.2
November 125 109.5
December 110 115.7
January 113.4
a = .4
At Ft Forecast Error
July 110 110.0
August 115 110.0 115-110 = 5.0
September 105 112.0 105 – 112 = -7.0
October 110 109.2 110-109.2 = 0.8
November 125 109.5 125 – 109.5 = 15.5
December 110 115.7 110-115.7 = -5.7
January 113.4
a = .4
At Ft
Forecast Error RSFE
July 110 110.0
August 115 110.0 5.0 5.0
September 105 112.0 -7.0 5 – 7 = -2.0
October 110 109.2 0.8 -2+.8 = -1.2
November 125 109.5 15.5 -1.2 + 15.5 = 14.3
December 110 115.7 -5.7 14.3 – 5.7 = 8.6
January 113.4
a = .4
At Ft
Forecast Error RSFE
Absolute Deviation
July 110 110.0
August 115 110.0 5.0 5.0 5.0
September 105 112.0 -7.0 -2.0 7.0
October 110 109.2 0.8 -1.2 0.8
November 125 109.5 15.5 14.3 15.5
December 110 115.7 -5.7 8.6 5.7
January 113.4
a = .4
At Ft
Forecast Error RSFE
Absolute Deviation MAD
July 110 110.0
August 115 110.0 5.0 5.0 5.0 5/1 = 5.0
September 105 112.0 -7.0 -2.0 7.0 (5+ 7)/2 = 6.0
October 110 109.2 0.8 -1.2 0.8 (5+7+.8)/3 = 4.3
November 125 109.5 15.5 14.3 15.5 (5+7+.8+15.5)/4 = 7.1
December 110 115.7 -5.7 8.6 5.7 (5+7+.8+15.5+5.7)/5 = 6.8
January 113.4
a = .4
At Ft
Forecast Error RSFE
Absolute Deviation MAD TS
July 110 110.0
August 115 110.0 5.0 5.0 5.0 5.0 5/5 = 1.00
September 105 112.0 -7.0 -2.0 7.0 6.0 -2/6 = -0.33
October 110 109.2 0.8 -1.2 0.8 4.3 -1.2/4.3 = -0.28
November 125 109.5 15.5 14.3 15.5 7.1 14.3/7.1 = 2.02
December 110 115.7 -5.7 8.6 5.7 6.8 8.6/6.8 = 1.26
January 113.4
Master Production Scheduling
Material Requirements Planning
Order SchedulingWeekly Workforce &Customer Scheduling
Daily Workforce &Customer Scheduling
Process Planning
Strategic Capacity Planning
Sales and Operations (Aggregate) Planning
Long-range
Intermediate-range
Short-range
Manufacturing Services
Sales Plan Aggregate Operations Plan
Forecasting and Demand
Mgmt.
Aggregate Planning
• Goal: Specify the optimal combination of– production rate (units completed per unit of time)– workforce level (number of workers)– inventory on hand (inventory carried from
previous period)
• Product group or broad category - family (Aggregation)
• Intermediate-range planning period: 6-18 months
Key Strategies for Meeting Demand
• Chase - Match production to customer order rate by hiring and laying off employees
• Level - Stable workforce with constant output, inventory and backlogs absorb fluctuations in demand
• Some combination of the two - Stable workforce, variable hours - vary output through overtime or flexible schedules