STRATIX/PRICE for Sawing
Option to improve pricing flexibility
STRATIX/PRICE for Sawing
• Used to automatically compute Time, Cost, and Charge for Sawing
• Integrated with Quote/Order Entry Application
Features of STRATIX/Process
• Material Process Group• Multiple Times and Costs provided (Set-up, Run, etc.)• Ability to view & modify fixed & variable Time, Cost,
& Charge components within Quote/Order Entry application• Re-price, Re-cost, and Compute Functions
• Processing Instructions• Customer Processing Discounts• Minimum Profit Percentage• Outside Processing• Zero Charge• Series Processing
Sawing Process Entry
Total Cost = Set-up Cost + R unCost + Fixed Cost + Tooling Cost
Charge = Total Cost (1 - Pft % )
Discount %(from Cust. Profile)
Profit %(from Charge table)
R em arks(from Charge table)
Total Tim e = Set-up Tim e + R unTim e + Handling Tim e
Set Up Tim e(from Charge table)
R un Tim e(Manually entered)
Outside ProcessingI nform ation
Set Up Cost(from Charge table)
R un Cost = R un Tim e *R un Cost R ate
(from Charge table)
Fixed Cost(from Charge table)
Tooling Cost(Entered m anually)
Sawing Pricing
• Used to calculate Sawing Time, Cost, and Charge• For each Material Process Group, Sawing Tables can
be based on Cross Section Area &/or Wall Thickness (Tubes).
• Multiple Sawing Rate Entry Types • Cost and Charge, Cost and Profit, Charge and Profit • Percentage of Metal Charge
• Multiple Weight and Cut Brackets • Apply First Bracket• Minimum Cost Amount and Minimum Charge Amount• Series Processing (based on Pieces, Measure, Length,
and/or Time)
Rate Entry Types
• Cost and Charge
• Cost and Profit• Charge and Profit
• Percentage of Metal Charge
Num ber of Cuts
Cost Charge
1 11-9996-102-5
2.00 4.50 1.50 2.50 1.00 1.25 0.25 0.30
Cost Charge Cost Charge Cost Charge
55.56% 40.00% 20.00% 16.67%
Processing Profi t = (1 - Cost/ Charge) * 100 %
User
STR ATI X
Sawing Computations
• Time = Set-up Time + Run Time + Handling Time• Where Run Time = [(Cross Section Area * Sawing Time
Rate) * Number of Cuts]
• Cost = Set-up Cost + Run Cost + Fixed Cost + Tooling Cost• Where Run Cost is determined based on Rate Entry Type.
• Cost & Profit or Cost and Charge: Cost is given.• Charge & Profit: Cost = Charge (1 – Profit %)• Percentage: Cost = Minimum Cost Amount
• Charge is determined based on Rate Entry Type.• Cost & Profit: Charge = Cost / (1 – Profit %)• Cost & Charge or Charge & Profit: Charge is given.• Percentage: Charge = Metal Charge * Percentage
Sawing Computation Example
Saw ing enterprise param eterProcessing Chargeenterprise param eter
Set-up Tim e = 10m inSet-up Cost = $3 LOTFixed Cost = $2 LOT
Order Entry
Carbon Angles, 36, 22145 Pieces
Cost = $1.00/ CUTProfit = 60%
M aterial P rocess Group = Carbon 36Cross Section Area Range = 0-1
N um Size 1 Range = 0-999
Burning Process EntryW indow
5 CutsHandling Tim e = 0Tooling Cost = 0
N um ber o f Cuts Range = 0-5W eight Bracket - 0-99999LBS
Saw ing Tim e R ate = 20sec/ SI N
Product
0.9383
Carbon Angles, 36, 2214
R un Tim e = (Cross Section Area* Saw ing Tim e R ate) * Num ber of Cuts = (0 .9383SI N* 20sec/ SI N ) * 5 Cuts = 1m in34sec
T otal T im e = Set-up T im e + Run T im e + H andling T im e= 10m in + 1m in34sec + 0 = 11m in34sec
R un Cost = $1.00/ Cut * 5Cuts = $5.00
T otal Cost = Set-up Cost + Run Cost + F ixed Cost + T oo ling Cost= $3LO T + $5.00 + $2LO T + 0 = $10.00
Charge = Cost / (1 - Profi t % ) = $1.00 / (1 - 0 .60) = $2.50/ CutCharge = $2.50/ Cut * 5 Cuts = $12.50
N O T E : Cost and Charge U M can be Length-based, W eight-based, o r P ieces.
Apply First Bracket
• Used to account for higher costs associated with first set of cuts
• Number of Cuts = 8• Apply First Bracket set to “No”
• Cost = $1.00/CUT, Charge = $1.50/CUT
• Apply First Bracket set to “Yes”• Cost = (1CUT*$3.00/CUT + 7CUTS*$1.00/CUT) / 8 CUTS = $1.25/CUT • Charge = (1CUT*$3.50/CUT + 7CUTS*$1.50/CUT) / 8 CUTS =
$1.75/CUT
Num ber of Cuts
Cost Charge
1 11-9996-102-5
3.00 3.50 2.00 2.50 1.00 1.50 0.25 0.75
Cost Charge Cost Charge Cost Charge
0-999999
W eight
Minimum Charge & Minimum Cost Amounts
• Example of use of Minimum Charge Amount
Com puted R un Charge Am ount= Saw ing Charge * I tem
Quantity = $2.00/ PCS * 5 PCS= $10.00
Saw ing Charge =$2.00/ PCS
Minim umCharge
Am ount =$15.00
Com putedR un ChargeAm ount =
$10.00
Saw ing Charge =Minim um Charge Am ount /
I tem Quantity =$15.00/ 5PCS = $3.00/ PCS
Series Processing
• Ordered Length > Length Limit• Ordered Measure > Measure Limit• Estimated Processing Time > Time Limit• With Auto Job Creation, used to assign PWG.