PIPE STRESS ANALYSIS- CONCEPTSSatyashish Sahu
Month YearMonth Year
Date of last change Reference/Name of Presentation/SN 2
PIPE STRESS ANALYSIS -CONCEPTS
! Analytical procedure to evaluate the stress state at
various points in a piping system.
! Also known as flexibility analysis since it also helps
ascertain the required flexibility in the piping system
! Helps determine displacements and forces / moments on
the hangers, supports, restraints, guides, stops and
anchors in the piping system
- STRESS ANALYSIS -- STRESS ANALYSIS -
What is piping stress analysis
Date of last change Reference/Name of Presentation/SN 3
PIPE STRESS ANALYSIS -CONCEPTS
! Stress in pipes! Stress categories! Failure of pipes! Thermal behavior of pipes! Stress limits! Stress in piping components! External load categories! Piping supports! Spring hangers! Constant effort hangers! Friction! Piping codes! ASME B 31.1 - Power piping code! Linear and non linear supports! Effect of supports on stress
- STRESS ANALYSIS -- STRESS ANALYSIS -
Contents
Date of last change Reference/Name of Presentation/SN 4
Stress in pipes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Fig-1 Biaxial stress state in a pipe
l = PDO/4t + BM/ZWhere BM = (Mx2+My2)1/2
h = PDO/2t = TM/JWhere TM= Mz
Date of last change Reference/Name of Presentation/SN 5
Stress in pipes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Fig-2 Mohrs circle of the biaxial stress state
Date of last change Reference/Name of Presentation/SN 6
Stress in pipes
! Figure-1 shows the stresses in pipes. The various stresses includedin stress evaluation are: Pressure Hoop stress Pressure longitudinal stress Bending & torsional stress due to weight of pipe, contents and insulation Bending & torsional stress due to any point loads, wind loads,
earthquake loads, hammer loads Bending & torsional stress due to restriction of thermal expansion
! It is always assumed (in fact due care is taken to ensure) that plantpiping will consist of at least two perpendicular segments betweenanchors. The Axial stresses due to thermal effects and also due toany other external loading in such a case will be negligible and arehence neglected in stress calculations. So also is buckling neglected.
- STRESS ANALYSIS -- STRESS ANALYSIS -
Stress in pipes
Date of last change Reference/Name of Presentation/SN 7
Stress categories
! Primary stress (membrane and bending) This is the stress due to external loading of the pipe like weight,
point load, wind, earthquake If this exceeds the allowable stress it will cause failure of the pipe
through continuous yielding
! Secondary stress This stress is not caused by any external loading but by such
physical tendencies as thermal expansion This stress is self-limiting in nature. It relieves itself upon yielding.
It is due to this fundamental difference in behavior betweenprimary and secondary stress that these two stress categoriesare treated very differently. These stresses are never added upand have different allowable values
- STRESS ANALYSIS -- STRESS ANALYSIS -
Classification of stress
Date of last change Reference/Name of Presentation/SN 8
Stress categories
! Peak stress Peak stresses are cyclical stresses which cause fatigue failure in
pipes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Classification of stress
Date of last change Reference/Name of Presentation/SN 9
Failure of pipes
! Plastic deformation leading to bursting - This happens whenever themagnitude of the primary membrane stress exceeds the yieldstrength.
! Plastic instability or incremental collapse - This occurs when thesecondary stress range exceeds twice the yield stress as explainedunder title stress range.
! Fatigue - Low cycle fatigue occurs in piping systems due to cyclicloads (like thermal load cycles, vibrations, etc).This occurs when thecumulative usage factor exceeds 1.0.
! Creep - Creep or elastic instability or elastic follow-up is a timedependent failure phenomenon that occurs in high temperaturepiping - typically above 750 deg F (400 deg C). Creep failure wouldeventually occur if the primary stress in the pipe is above the creepstrength of the material.
- STRESS ANALYSIS -- STRESS ANALYSIS -
Failure mechanism
Date of last change Reference/Name of Presentation/SN 10
Thermal behavior of pipes
! When a pipe is heated up, stresses are caused if the free thermalmovement of the pipe is restricted. Upon reaching the yield point, thepipe starts yielding and the stresses as well as the thermal loads onthe restraints get relieved. This is called thermal shakedown. Whenthe pipe is cooled, it comes back to its original position and now thestresses and restraint loads reappear but with opposite signs.
The range between the hot stress and the cold stress is called thestress range.
- STRESS ANALYSIS -- STRESS ANALYSIS -
Thermal shakedown / Stress range
Date of last change Reference/Name of Presentation/SN 11
Thermal behavior of pipes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Fig-3 Stress range
Total stress range ST = Shy + Scy
where:Shy = Hot yield strengthScy = cold yield strength
If deformation exceeds case-IIas in case III, there will beplastic instability in subsequentcycles leading eventually toincremental collapse.
Date of last change Reference/Name of Presentation/SN 12
Stress Limits
- STRESS ANALYSIS -- STRESS ANALYSIS -
FIG-4 Limit stress-combined tension and bending. (ASME, Criteria. )! Fig shows two curves - one the
limit stress or the failure curveand the other the design limitcurve.
! A conservative design limit of0.66Sy for primary membrane(tensile) and 1.0Sy for combinedbending and membrane stress isused.
Date of last change Reference/Name of Presentation/SN 13
Stress Limits
- STRESS ANALYSIS -- STRESS ANALYSIS -
Stress limits for Time dependent deterioration - Fatigue and Creep
! Low cycle Fatigue (load cycles lower than 105)
Stress reduction factor f for the allowable stress range for different
cumulative cycles are available in the piping codes. Ensuring that the
piping is not stressed beyond these levels guarantees that the pipe would
not fail in fatigue for the postulated number of operating cycles.
! Creep
The allowable stress values for various material listed in the piping codes
take into account the creep strength in the high temperature range (above
400 deg C). Limiting the primary stress in the pipe below the allowable
stress value as listed in the piping code would ensure that the creep rate
is no more than 1% per 100,000 hours.
Date of last change Reference/Name of Presentation/SN 14
Stress Limits
- STRESS ANALYSIS -- STRESS ANALYSIS -
FIG-5 Stress categories and limits of stress intensity(Source:ASME Section VIII Div-2, Appendix-4)
Date of last change Reference/Name of Presentation/SN 15
Stress Limits
- STRESS ANALYSIS -- STRESS ANALYSIS -
FIG-5 Stress categories and limits of stress intensity (Contd)(Source:ASME Section VIII Div-2, Appendix-4)
Date of last change Reference/Name of Presentation/SN 16
Stress in piping components
- STRESS ANALYSIS -- STRESS ANALYSIS -
Stress intensification factors - SIF! Elbows, branch connections and reducers will have a higher level of
stress when compared to a straight pipe for the same amount ofbending moment.
! The factor by which the stress in the pipe component exceeds that ofthe straight pipe is called SIF (stress intensification factor).
! SIF of a component depends upon its geometry and is calculatedusing empirical formulae available in piping codes.
! For special components like Y-piece where no empirical relations areavailable, SIF will have to be determined through a analyticalprocedure like FEM.
Date of last change Reference/Name of Presentation/SN 17
Stress in piping components
- STRESS ANALYSIS -- STRESS ANALYSIS -
Relation between Elbow geometry and SIF! Elbow / bend radius - Has inverse relation to SIF! Elbow diameter - Has direct relation to SIF! Elbow thickness - Has inverse relation to SIF
Relation between Branch geometry and SIF
! Header diameter - Has direct relation to header & branch SIFs! Header thickness - Has inverse relation to header & branch SIFs! Branch diameter - Has direct relation to branch SIF. Has no bearing
on header SIF! Branch thickness - Has direct relation to branch SIF. Has no bearing
on header SIF
Date of last change Reference/Name of Presentation/SN 18
Stress in piping components
- STRESS ANALYSIS -- STRESS ANALYSIS -
Relation between Branch type and SIF
! The various branch types are listed with their SIF in theincreasing order Welding Tee
Integrally reinforced fitting as per MSS SP 97
Reinforced fabricated Tee
Unreinforced fabricated Tee
I
n
c
r
e
a
s
i
n
g
S
I
F
Date of last change Reference/Name of Presentation/SN 19
External load categories
- STRESS ANALYSIS -- STRESS ANALYSIS -
Types of external loading on pipes! Sustained loading
These loads will act on the pipe throughout its operating tenureand include
Dead loads like weight of pipe, insulation and inlinecomponents
Live loads like weight of contents in the pipe
! Occasional loading These loads act on the pipe only for certain duration or during
abnormal operating conditions and include wind Dynamic loads like earthquake, hammer, safety valve thrust
Date of last change Reference/Name of Presentation/SN 20
Piping supports
- STRESS ANALYSIS -- STRESS ANALYSIS -
Types of pipe supports! Rigid support - An inflexible restraint used primarily to carry the
sustained pipe loading. They cannot be used where there is upwardpipe movement. Rigid hanger Sliding base support
! Variable effort (spring) support - A flexible spring used to carry thesustained pipe loading while allowing for upward / downward pipemovement. The supporting effort varies as the pipe moves up ordown.
! Constant effort support - Used to carry the sustained pipe loadingwhile allowing for upward / downward pipe movement. Thesupporting effort remains constant throughout the upward /downward travel of the pipe.
Date of last change Reference/Name of Presentation/SN 21
Piping supports
- STRESS ANALYSIS -- STRESS ANALYSIS -
Types of pipe supports (cont)! Thermal Restraint - This is usually a rigid element used to alter /
control the thermal growth of the piping system so as to bring theterminal point forces / moments and thermal stresses under limit. Axial restraint : Movement prevented in pipe axial direction Transverse / Lateral restraint : Movement prevented in pipe transverse
direction! Guides - Guides are similar to bi-directional restraints but with the
primary purpose of guiding the pipe smoothly into the pipe axial orlateral direction. Transverse / Lateral guide : Pipe movement guided into the transverse
direction Axial guide : Pipe movement guided into the pipe axial direction
! Anchors - Anchors arrest all the six degrees of freedom of the pipe.Anchors are sometimes inserted to completely separate twoconnected pipes to enable the analyst to analyse the pipesindependently.
Date of last change Reference/Name of Presentation/SN 22
Spring Hangers
- STRESS ANALYSIS -- STRESS ANALYSIS -
Spring Hanger selection procedureFor spring hanger selection the following steps are required! Calculation of weight balance load
The load that would act on the spring hanger if it were completely rigidand the piping system was in static equilibrium under sustained loadingcondition
! Calculation of vertical free thermal movement The thermal growth of the pipe under the influence of temperature I.e the
vertical pipe length x the coeff of thermal expansion
! Selection of appropriate spring constant An appropriate spring constant from a supplier catalogue based upon the
weight balance load and vertical thermal movement such that the loadvariation between the cold and hot positions is within 25%.
Date of last change Reference/Name of Presentation/SN 23
Spring Hangers
- STRESS ANALYSIS -- STRESS ANALYSIS -
Hot setting / Cold setting of springsThere are two ways of setting the springs - Hot setting and Cold setting
! Hot setting - The spring is set such that it carries the weight balance
load in the hot position of the pipe
! Cold setting - The spring is set such that it carries the weight balance
load in the cold position of the pipe.
The behavior of the piping system will vary under hot and cold setting
because the spring carries different loads under the two settings.
Fig-4 shows how exactly these two types of spring setting affect the
load carried by the spring.
Date of last change Reference/Name of Presentation/SN 24
Spring Hangers
- STRESS ANALYSIS -- STRESS ANALYSIS -
Fig-6 Hot / Cold setting
S
p
r
i
n
g
c
a
g
e
m
o
v
e
m
e
n
t
0%
100%
Cold pos of pipe
Hot pos of pipe
Load
W
e
i
g
h
t
b
a
l
a
n
c
e
l
o
a
d
Coldsetting
Hotsetting
Date of last change Reference/Name of Presentation/SN 25
Spring Hangers
- STRESS ANALYSIS -- STRESS ANALYSIS -
Spring hanger terminologies! Cold load - The load carried by the spring when the pipe is in cold
position
! Hot load - The load carried by the spring when the pipe is in hotposition
! Installation load - The load the spring would carry when the pipe is atits installation position I.e zero vertical displacement. The installationload would be equal to the cold load provided the vertical pipedisplacement in the cold condition is zero. But this may not be thecase always.
The spring is pre-compressed to the installation load, locked andthen erected on the pipe.
Date of last change Reference/Name of Presentation/SN 26
Constant effort Hangers
- STRESS ANALYSIS -- STRESS ANALYSIS -
Constant effort hangers! When pipe vertical movement is high (above 50 mm), it is usually not
possible to select variable effort hangers with load variation within25%. In such a situation, constant effort hangers are used.
! Constant effort hangers as the name suggests apply a constant efforton the pipe throughout the complete range of the pipe verticalmovement.
! The effect of the constant effort hanger is similar to that of supportingthe pipe with a chain-pulley-block system
Date of last change Reference/Name of Presentation/SN 27
Friction
- STRESS ANALYSIS -- STRESS ANALYSIS -
Frictional effects of pipe supports! Friction at sliding surfaces of supports especially in hot pipes
generate significant forces which affect the pipe stresses as well as
the loads on anchors and restraints.
! It is advisable to avoid sliding supports / restraints in hot critical
piping systems - like Main steam, Cold and Hot reheat piping
systems - and use instead the angulating types.
! If sliding supports / restraints are used for critical applications, then
the sliding surfaces should be of rust free materials like stainless
steel / teflon and the appropriate friction coefficient must be included
in the analysis.
Date of last change Reference/Name of Presentation/SN 28
Piping codes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Importance of piping codes in stress analysis! Piping codes are industry specific. They outline the stress evaluation
criteria and also the design requirements specific to the industry overwhich they have their jurisdiction.
! The piping code lies at the heart of any stress analysis. A pipingsystem necessarily has to be qualified as per the stress criteriaestablished in the particular piping code.
! The stress evaluation criteria - while largely based on thefundamentals discussed earlier - differ from code to code, thedifferent criteria necessitated by the specific operating conditionsand requirements of the industry to which the particular code catersto. The difference in the criteria are in some cases also attributed tothe historical circumstances / different committees that haveestablished the codes.
Date of last change Reference/Name of Presentation/SN 29
Piping codes
- STRESS ANALYSIS -- STRESS ANALYSIS -
Important ASME piping codes! Power piping ASME B 31.1! Process piping ASME B 31.3! Pipeline transportation systems for
liquid hydrocarbons and other liquids ASME B 31.4! Refrigeration piping and heat transfer
components ASME B 31.5! Gas transmission and distribution piping
systems ASME B 31.8! Nuclear piping ASME section III
The ASME B 31.1 power piping code forms the basis for pipingdesign and stress analysis of all piping except Boiler internalpiping at ALSTOM.
Date of last change Reference/Name of Presentation/SN 30
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Allowable stress! The allowable stress for various ASTM piping materials at various
temperatures are listed in Appendix-A of the code.! The allowable stresses are actually reproduced from the ASME
Boiler & pressure vessel code, section II
Basis for allowable stress in ASME section II part DMin of: R/4, 1.1/4 x Rt, 0.67 E, 0.67 Et, 0.67 Sr, 0.8 Sr min and 1.0 S
R = Specified minimum tensile strength at room temperature.Rt = Specified minimum tensile strength at the temperature.E = Yield point (0.2% proof stress at room temp)Et = Yield point (0.2% proof stress at the temp)Sr = Average stress at the temp to cause rupture at the end of 100,000 hr.Sr min = Minimum stress at the temp to cause rupture at the end of 100,000 hr.S = Average stress at the temp to produce an elongation of 1% (creep) in 100,000 hr.
Date of last change Reference/Name of Presentation/SN 31
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Other important data! The thermal expansion data for the various materials are listed in
Table B-1 of Appendix-B of the code.
! The modulus of elasticity data for the ferrous materials are listed in
table C-1 of Appendix-C of the code.
! The formulae for the SIF and flexibility factors for various pipe
components are listed in Table D-1 of Appendix-D of the code.
Date of last change Reference/Name of Presentation/SN 32
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Comments on allowable stress values of Appendix-A! The values listed include weld joint efficiency factors where
applicable. Weld joint efficiencies affect only the hoop direction andnot the longitudinal pipe direction. Since in stress analysis, we areinterested in the longitudinal stresses only, the allowable stress forstress calculation must be obtained by dividing the values fromappendix-A by the appropriate weld efficiency factor.
! The actual stress may exceed the allowable for occasional shortperiods by the following factors: 15% for events duration < 8 hrs at any one time and 800 hrs/year 20% for events duration < 1 hrs at any one time and 80 hrs/year
The allowables may be exceeded due to external occasional loads ordue to pressure-temperature excursions (which would bring down theallowables).
Date of last change Reference/Name of Presentation/SN 33
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Comments on allowable stress values of Appendix-A! The allowable stress in shear can be taken as 80% of the allowables
listed in appendix-A.
! The allowable stress in bearing can be taken as 160% of the
allowables listed in appendix-A.
! The stress in pipe during hydrotest can be considered as high as
90% of yield stress.
Date of last change Reference/Name of Presentation/SN 34
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Code qualification equations! Stress due to sustained loads (Clause 104.8.1 of B31.1)
SL = (PDO/4Tn) + (0.75iMA/Z) < 1.0ShWhere MA = resultant moment loading on cross section due to all sustained loads
The above relation can be easily derived by considering the stressstate of fig-1 and applying the Maximum shear stress theory.
From maximum shear stress theory, failure would occur when the max shear stress is > half of allowable stress in tension.Max shear stress can be calculated from mohr's circle (fig-2) as follows:2max = 2 x radius of mohr's circle = {(h-l)2 + 42}1/2
= {(PDO/4t + BM/Z)2 + 4 (TM/J)2}1/2
= {(PDO/4t)2 + (M/Z)2 + 2 . PDO/4t . BM/Z}1/2 Where M = (Mx2+My2+Mz2)1/2
= PDO/4t + M/Z ( by substituting BM with M; this makes the calculated max slightly conservative)
To avoid failure, PDO/4t + M/Z < Sh
Incorporating fitting SIF into the above eqn gives the 31.1 code eqn for sustained stressesPDO/4t + 0.75iMA/Z < Sh
Date of last change Reference/Name of Presentation/SN 35
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Code qualification equations (cont)! Stress due to occasional loads (Clause 104.8.2 of B31.1)
(PDO/4Tn) + (0.75iMA/Z) + (0.75iMB/Z) < k.ShWhere MB = resultant moment loading on cross section due to all occasional loads
k = stress exceeding factor (1.15 or 1.20 depending on occasional load duration)
! Thermal expansion stress range (Clause 104.8.3 of B31.1) SE = iMC / Z < SA + f (Sh-SL)
Where MC = range of resultant moments on cross section due to thermal expansion SA = Allowable stress range
= f (1.25 Sc + 0.25 Sh) Sc = basic material allowable stress (appendix-A) at cold temperature Sh = basic material allowable stress (appendix-A) at hot temperature
f = stress range reduction factor for cyclic loading (= 1 for general power plant applications)
Date of last change Reference/Name of Presentation/SN 36
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Code qualification equations (cont)! Understanding allowable stress range
From figure-3, Total stress rangeST = Shy + Scy
= 1.5 Sh + 1.5 Sc
Taking only 83.3% so as to have margin,ST = 1.25 Sh + 1.25 Sc
Thus for thermal expansion, the allowable stress range SA = 0.25 Sh + 1.25 Sc (deducting 1.Sh for sustained loading)
Incorporating the fatigue factor gives the 31.1 code equationSA = f .(0.25 Sh + 1.25 Sc)
Date of last change Reference/Name of Presentation/SN 37
ASME B 31.1 - Power pipingcode
- STRESS ANALYSIS -- STRESS ANALYSIS -
Important code considerations! Modulus of elasticity - The code stipulates that the stress must be
evaluated considering the cold modulus of elasticity. However, forces
and moments on anchors and restraints can be evaluated
considering the hot modulus.
! Corrosion allowance and mill tolerance - The stress analysis
including evaluation of restraint loads is to be done on the nominal
pipe thickness. Corrosion allowance and mill tolerance are not
considered.
Date of last change Reference/Name of Presentation/SN 38
Linear and non linear supports
- STRESS ANALYSIS -- STRESS ANALYSIS -
What are Linear and non linear supports! Linear Supports
These supports do not change their stiffness over the complete range of
pipe displacement in the direction of their application. All bi-directional
restraints without gap and friction and spring hangers fall in this category
! Non linear supports
These supports change their stiffness when the pipe moves from cold to
hot position. All restraints with gap and friction and single directional
restraints fall in this category.
Date of last change Reference/Name of Presentation/SN 39
Effect of supports on stress
- STRESS ANALYSIS -- STRESS ANALYSIS -
Pipe supports & stress! When a pipe lifts up in hot condition, the
change in stress from cold to hot position
can be considered as secondary stress
only if the displacement is minor.
! In case of significant displacements, the
stress assumes both - primary and
secondary stress characteristics and
hence must be checked against the
primary & secondary stress allowables
simultaneously.
Coldposition
U
p
w
a
r
d
p
i
p
e
m
o
v
e
m
e
n
t Hotposition
Date of last change Reference/Name of Presentation/SN 40
Effect of supports on stress
- STRESS ANALYSIS -- STRESS ANALYSIS -
Spring hangers & stress! Similarly in case of spring hangers, when
pipe moves from cold to hot position, the
stress level in the pipe changes due to
change in the supporting effort of the
spring. The change in the stress level
has primary characteristics and hence
should be limited to 25% to ensure a safe
design.
Hotposition
Coldposition
www.alstom.com