+ All Categories
Home > Documents > Study of Social and Economic Impacts of Construction of ...

Study of Social and Economic Impacts of Construction of ...

Date post: 01-Jan-2017
Category:
Upload: vuongdan
View: 245 times
Download: 9 times
Share this document with a friend
249
INTERNATIONAL SYMPOSIUM ON Bali, Indonesia, June 1 ST – 6 TH , 2014 Study of Social and Economic Impacts of Construction of SIAHBISHEH Dam Using Rapid Matrix Method Roohollah Mohammadvali Samani Site Manager, Dam, Water & Wastewater Division, KAYSON Co., Iran. [email protected] Kazem Heidarpour Chenar HSE Supervisor, KAYSON Co., Iran. Fatemeh Iravaniniay Tehrani Advisor to Managing Director, KAYSON Co., Iran. ABSTRACT: Considering to the growing needs of society for more water and energy resources, Nowadays construction of dams and hydroelectric power plants appear as an applicable solutions for the problem. Hence many countries have turned to the construction and use of these resources. Such that from 1950 the number of large dams with a height of over 15 meters in 5700 has reached more than 41,000. Dam construction along with the benefits and valuable impacts has disastrous effects on the environment and surrounding community and that’s why having provided grounds for so many criticism. Industrial processes in the world to protect the environment and its associated parameters are in more attention and development by the day. In dam construction industry, this monumental task of screening is responsibility of professionals of this scope that are work In order to more correspond and coordinates between this industry and environmental factors. On the other hand, due to the growth and development of science in various fields, deployment of new and modern ways seems necessary and useful to achieve different and useful results. One of these methods is the analysis of the effects that reported by EIA. In order to fulfill these tasks and to reduce the social and economic consequences and improvements in the construction and operation of dams and case study of SIAHBISHEH pumped storage dams in Iran, extensive research has been conducted by the present authors. This paper with considering the current situation, proceed to assess the social and economic impacts of the project on the rapid matrix in EIA and have to offer the results were analyzed to improve the situation and solutions, strategies and experiences in this area. Keywords: Dam, Environment, Rapid Matrix, EIA. 1. INTRODUCTION The efficient economic aspects of dam construction and the amount of the electricity produced are the matters to be considered in the studies of prefabricated constructions; this is while the dam construction is of great environmental importance in the way that it will affect both the region and the community of it. These cases are of direct and indirect socio- economic effects that are to be taken into consideration at the proposal level to prevent their negative effects. I - 1
Transcript
Page 1: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Study of Social and Economic Impacts of Construction of

SIAHBISHEH Dam Using Rapid Matrix Method

Roohollah Mohammadvali Samani Site Manager, Dam, Water & Wastewater Division, KAYSON Co., Iran.

[email protected]

Kazem Heidarpour Chenar HSE Supervisor, KAYSON Co., Iran.

Fatemeh Iravaniniay Tehrani

Advisor to Managing Director, KAYSON Co., Iran.

ABSTRACT: Considering to the growing needs of society for more water and energy resources, Nowadays construction of dams and hydroelectric power plants appear as an applicable solutions for the problem. Hence many countries have turned to the construction and use of these resources. Such that from 1950 the number of large dams with a height of over 15 meters in 5700 has reached more than 41,000. Dam construction along with the benefits and valuable impacts has disastrous effects on the environment and surrounding community and that’s why having provided grounds for so many criticism. Industrial processes in the world to protect the environment and its associated parameters are in more attention and development by the day. In dam construction industry, this monumental task of screening is responsibility of professionals of this scope that are work In order to more correspond and coordinates between this industry and environmental factors. On the other hand, due to the growth and development of science in various fields, deployment of new and modern ways seems necessary and useful to achieve different and useful results. One of these methods is the analysis of the effects that reported by EIA. In order to fulfill these tasks and to reduce the social and economic consequences and improvements in the construction and operation of dams and case study of SIAHBISHEH pumped storage dams in Iran, extensive research has been conducted by the present authors. This paper with considering the current situation, proceed to assess the social and economic impacts of the project on the rapid matrix in EIA and have to offer the results were analyzed to improve the situation and solutions, strategies and experiences in this area. Keywords: Dam, Environment, Rapid Matrix, EIA. 1. INTRODUCTION The efficient economic aspects of dam construction and the amount of the electricity produced are the matters to be considered in the studies of prefabricated constructions; this is while the dam construction is of great environmental importance in the way that it will affect both the region and the community of it. These cases are of direct and indirect socio-economic effects that are to be taken into consideration at the proposal level to prevent their negative effects.

I - 1

Page 2: Study of Social and Economic Impacts of Construction of ...

In almost all the pre-studies of dam construction the ultimate focus has always been on the environmental factors; the socio-economic factors were considered to be of less importance, and the typical number of the predictions were far from the reality; this makes the control and the reduction of the damage on the socio-economic aspects’ preparations less efficient. Of some the effects of the dam construction on the social aspects and their possible side effects we can count: the reduction in the size of the farms, the increase of the salt in the lower parts, the reduction in the nutritional elements of the soil, etc. Side effects like the reduced productivity of the farms, the land-use change, moving of the local nomads, population change, and change of occupation and income, which can, in their turns, accelerate the change in the environmental and economic situations. So the considerations of the socio-economic conditions could reduce the environmental risks, which presuppose more attentions to this matter. 2. METHODOLOGY After the general and the local studies of the needed data such as the population data used in this study from the Statistical Center of Iran, other data apropos the prediction of the events and the population effects with a case study on the Iran’s dam constructions, such as Karkhe and Alborz dams and their effects on the immediate covered society and the use of the experts’ opinions, were collected and Siah Bishe’s socio-economic population susceptibility of construction of a dam was predicted. Then suggestions were made by the experts for the executors for the future preparations and the rapid matrix was used for the comparisons among the dam construction activities. 3. THE INTRODUCTION AND THE FEATURES OF THE EIA The assessment of the environmental effects is a way of identification and measuring the environmental aftermath of the construction and the utilization of the construction projects that can have bad effects on the environment of the project’s base in global terms. Therefore, before implementing a project, we should do an assessment of the side effects to make sure that it does not have bad effects on the environmental factors and to propose corrective measures and the projects is to be implemented as long as it does not have negative side effects. In Iran, according to the proceedings of the Iran’s Grand Council of the Environmental Care in 23/12/1997, the executors of the construction projects such as dam construction with the height of more than 15 meters are bound to find the feasibility and locating studies along with the assessment of the environmental factors. There are a number of different methods to assess the environmental effects of the plan, methods such as the use of the check-list, matrix, explanatory index, and the addition and the analysis of the system which are used in predicting the environmental effects of the construction and the in the implementation of the projects. The most common method used in these cases is the matrix; the method of the rapid matrix is used in this study to assess the socio-economic effects of the construction of Siah Bishe’s dams, which are under construction, to propose some corrective measures after the passage of a long time after their primary assessments. In this method the assessment criteria are divided into two groups: 1. The groups which are of prime importance and have great impact on scoring (A).

I - 2

Page 3: Study of Social and Economic Impacts of Construction of ...

2. The groups whose locations are of great importance but are of less impact compared to the first group (B). As it is shown in Table 1, the scores of the first group which consists of two sub-groups: A1 and A2 are multiplied and scores of second group consisting of three sub-groups of B1, B2, and B3 are added, the sum of the first group is multiplied by the sum of the second one and the environmental score of the ES which is achieved from the equation 1 and is shown compared in the range of the scores of the Table 2; and in the analysis part the best possible method with the least amount of damage to the environment and society is chosen.

1 2 1 2 3 (1)

Table 1. Classification of Assessment Factors in Rapid Matrix Method

Effects Sum ( B3)

Effects Reversibility

(B2)

Effects Sustainability

(B1)

Effects Amounts

(A2)

Effects Importance

(A1)

Factors

Row

1 Without Change

1 Without Change

1 Without Change

3 Very Positive

Change

4 National/

International Importance

1

2 Non-

Cumulative

2 Reversible

2 Temporary

2 Considerable

Improvement in the Situation

3 Local/ National

Importance 2

3 Cumulative

3 Irreversible

3 Permanent

1 Improvement in

Situation

2 Important for Local Areas

3

- - - 0

Without Change

1 Important for

Local 4

- - - 1-

Negative Change

0 Without

Importance 5

- - -

2- Considerable

Negative Change

- 6

- - -

3- Severe

Negative Change

- 7

I - 3

Page 4: Study of Social and Economic Impacts of Construction of ...

Table 2. Classification of Environmental Scores

Description Group Skirt Environmental Scores )ES(

Very Positive Effect E+ 108<ES<72

Considerable Positive Effect D+ 71<ES<36

Average Positive Effect C+ 35<ES<19

Little Positive Effect B+ 18<ES<10

Negligible Positive Effect A+ 9<ES<1

Without Effect N 0

Negligible Negative Effect A- 1-<ES<9-

Little Negative Effect B- 10-<ES18-

Average Negative Effect C- 19-<ES<35-

Considerable Negative Effect

D- 36-<ES<71-

Very Negative Effect E- 72-<ES<108-

4. THE INTRODUCTION OF THE CASE STUDY OF THE PUMPED-STORAGE DAMS PROJECT OF SIAH BISHE Siah Bishe’s dam and PSH (Pumped-storage hydroelectricity) project is located 150 kms on the north of Tehran, Iran in the central Alborz. This project consists of two rock-fill dams with CFRD that is to initiate a 1040MW power station. The pumped-storage system used in this project among the higher and lower dams make the generation and the compensation of the power in the peak times at night and the adjustment of the peak-time load for pumping operations at different times during the day possible. This project is adjacent to one of the busiest entertaining mountain roads of Iran and there are a lot of small villages around it that provide the socio-economic connections of these two population centers. 5. THE SOCIO-ECONOMIC SITUATIONS OF THE PROJECT’S LOCATION The higher dam is located on Chaloos River and the lower one at the confluence of Chaloos and Garmroodbar and is in the heart of Hirkani Forrest. Daryabak, Siah Bishe’s villages, Verkloo, Harijan, and Vali Abad which are some the environs of Marzan Abad, are some of the villages close to the dam’s location. The climatic condition of the region is cold and damp with the average temperature of 7 to 9 °C which is a popular mountainous countryside. There are many seasonal moving in these villages and some of these villagers move to the adjacent towns and come back again at the end of the spring. The dominant occupation of the people is traditional animal husbandry and keeping the local road inns. Women are generally in charge of the house and sporadically produce handicrafts. Vali Abad village has an elementary school to which many students from adjacent villages come to study. There are no health centers in the local villages and the people seek medical

I - 4

Page 5: Study of Social and Economic Impacts of Construction of ...

help from Marzan Abad’s health center. According to the data collected form Statistical Center of Iran 69.7% of the villagers and 77.9% of Marzan Abad’s inhabitants are literate and the human sex ratio of the males to females is 86%. 6. THE DESCRIPTION OF THE CONNECTION BETWEEN EIA AND SIAH BISHE’S DAM’S BASE Given the fact that it has been a long time since the primary assessments and the implementation of the proposal and the changed conditions of the region, it was necessary to have a second assessment of problems analysis, the environmental aftermath, and socio-economic effects of the project under construction to think of some corrective measures in the face of the possible issues. Therefore, by consulting specialized experts, studying the other dams constructed in Iran, and the conditional changes from the start of the project, we assessed the socio-economic effects of the dam construction both during and after its implementation. 7. THE ANALYSIS OF THE SOCIO-ECONOMIC EFFECTS OF THE DAM CONSTRUCTION BY THE RAPID MATRIX Given the fact that Siah Bishe is a seasonal tourist attraction and is located in Tehran-Shomal’s road, it is considered to be a recreational area and the entertainment is up to some measures part of it. Nevertheless the education opportunities have not been improved and the students have to travel to the adjacent towns to study at the boarding schools. With the start of Siah Bishe’s dams’ construction, some temporary clinics will start giving health service to the locals, and the transferring of the patients to the adjacent towns will be stopped. Most of the local pieces of land belong to the Natural Resources Organization and only a few numbers of them are in private ownership. Given the nature of the region and the locals’ jobs, animal husbandry, the construction of the dam will cover some of the land that is at the back of the dam in water and the region will enjoy less pastures. With the start of the construction process the price of the locals’ land will increase that will encourage them to sell their land to non-locals. In addition to employing many of the locals in the construction process, many others will inhabit and find jobs in the region, making the region a temporary cultural melting pot, and at same time prevents the locals to move from one place to another to find jobs and will increase their earning income. These criteria are shown in Table 3 to assess the social-economic effects of Siah Bishe’s dams’ construction at the present time of the project’s implementation. With the current state of the affairs in the predicted location and the implementation plan, after the construction, the region turns into an unofficial recreation area for both the people who inhabit in the neighborhood and the visitors passing by; and given the fact that the proper facilities are not provided for the people some shortcomings in facilities and needed resources will emerge which will result in a collective environmental crisis that will gradually makes the number of the visitors less and less. At the end of the project the local young workers will have to leave the place and move to somewhere else in search of jobs, this will change the sex ratio of the region, land will be sold and villas will have been built by that time, and women will stop producing handicrafts, and the locals’ income will decrease accordingly. After the end of the project, the workers’ clinic will shut down and

I - 5

Page 6: Study of Social and Economic Impacts of Construction of ...

the locals have to take long ways to Marzan Abad to seek medical help. According to all these, the criteria for the socio-economic assessments under analysis are shown in Table 4.

Table 3. Rapid Matrix for Assessment of Socio- Economic Effects of SIAHBISHE Dam at Implementation Stage

Immediately after the prediction of the likely socio-economic situations after the construction of the dam, and other constructed dams inside the country, some measures were taken to reduce the negative side effects of the construction and at the same time improving the corrective procedures, these considerations made the assessment of the EIA like the ones in Table 5. It was ruled out that the region is to be a tourist attraction site with the help of the Environment Protection Organization of Iran and the local people are going to be used in the corrective procedures. Not only will this direct the region’s tourism, but also it will make the locals stay in the region possible and stop their moving from one place to another. It will also keep the region’s climate stable and will keep the supervision of the land-use more in control. Moreover, a clinic is going to be built to improve the health conditions in the area and give people social services. In the end, as far as the traditional ways of comparing the range of the socio-economic scores are concerned, in three different stages of implementation, the post-construction stage, and the post corrective-procedures stage, the bar charts of the different stages were drawn and compared, and the result is shown in Table 1.

Factors Description

B3 B2 B1 A2 A1 ES Skirt Social-Economic Factors

2 3 3 1 1 8 A+ Fun and Entertainment

2 3 3 0 1 0 N Schools Situation

1 2 2 2 2 20 C+ Situation of Medical Centers

3 3 3 -3 2 -54 D- Land Use Change

2 2 2 2 3 36 D+ Changing Role of Local People

1 1 1 0 1 0 N Changing Women’s Roll

3 3 3 -2 1 -18 B- Local Land Worth

1 1 2 -1 1 -4 A- Change in Minority Groups

3 3 3 0 2 0 N Changing in the Living Location of

Residents

1 1 1 1 3 9 A+ Change in Sex Ratio

1 2 2 1 2 10 B+ Change in Ratio of Society Activist’s

Age

2 2 2 2 2 24 C+ Change in the Natives Income

3 3 3 1 2 18 B+ Change in Tourism

I - 6

Page 7: Study of Social and Economic Impacts of Construction of ...

Table 4. Rapid Matrix for Assessment of Socio- Economic Effects of SIAHBISHE Dam at Post Construction Stage without Corrective Procedure

Table 5. . Rapid Matrix for Assessment of Socio- Economic Effects of SIAHBISHE Dam at Post

Corrective- Procedure Stage

Description Factors

Social-Economic Factors Fun and Entertainment

Skirt ES A1 A2 B1 B2 B3

Schools Situation C- -28 2 -2 2 2 3

Social-Economic Factors N 0 1 0 3 3 2

Situation of Medical Centers C- -20 2 -2 2 2 1

Land Use Change D- -54 3 -2 3 3 3

Changing Role of Local People D- -54 3 -2 3 3 3

Changing Women’s Roll A- -7 1 -1 3 2 2

Local Land Worth D- -36 2 -2 3 3 3

Change in Minority Groups N 0 1 0 2 1 1

Changing in the Living Location of Residents C- -32 2 -2 3 2 3

Change in Sex Ratio B- -9 3 -1 1 1 1

Change in Ratio of Society Activist’s Age B- -10 2 -1 2 2 1

Change in the Natives Income C- -12 2 -1 2 2 2

Change in Tourism C+ 24 3 1 3 2 3

Description Factors

Social-Economic Factors Fun and Entertainment

Skirt ES A1 A2 B1 B2 B3

Schools Situation B+ 14 2 1 3 2 2

Social-Economic Factors N 0 1 0 2 2 1

Situation of Medical Centers B+ 18 1 2 3 3 3

Land Use Change N 0 3 0 3 3 3

Changing Role of Local People C- -21 3 -1 3 2 2

Changing Women’s Roll A+ 7 1 1 3 2 2

Local Land Worth D- -36 2 -2 3 3 3

Change in Minority Groups N 0 1 0 2 1 1

Changing in the Living Location of Residents N 0 2 0 3 2 3

Change in Sex Ratio N 0 3 0 1 1 1

Change in Ratio of Society Activist’s Age N 0 2 0 2 2 2

Change in the Natives Income B+ 12 2 1 2 2 2

Change in Tourism C+ 24 3 1 3 2 3

I - 7

Page 8: Study of Social and Economic Impacts of Construction of ...

Figure 1. Scores Comparison of Different Stages of Implementation, Post Construction and Post

Corrective- Procedure As it is seen in Chart and Table 6 the condition at the implementation stage was in its height and that it was worsen by the end of the project; and after applying the corrective measures it has been improved. Given the difficulties of the interpretation of the number of the scores of the comparison chart in Table, a simplified quantative method of showing the conditions differences was used; in this study, the coefficients of each of the ranges and their algebraic additions were used to have the least range of the difference in the output data. Therefore, in this study the score ranges were given coefficients and the number of the existing ranges in each of conditions is multiplied by their own coefficient and at the end all the conditions’ numbers are added up and the quantative sum of each effect is calculated as the calculation method is shown in Formula 2. The reducing scoring method of the effects was considered in the way that the N range’s coefficient was zero and other ranges of the A, B, C, D, and E were 1,2,3,4, and 5 respectively. The positive and the negative coefficients were added up at the end.

QuantityofSituation ∑Xi n (2)

0

2

4

6

8

10

12

E- D- C- B- A- N A+ B+ C+ D+ E+

Sco

re N

umbe

r

Score Range

1)Implementation Stage 2) Post Construction Stage 3) Post Corrective-Procedures Stage

I - 8

Page 9: Study of Social and Economic Impacts of Construction of ...

Table 6. Comparison of Socio- Economic Score of SIAHBISHE Dam

8. CONCLUSION According to the results derived from Tables 3, 4, and 5, we observed that by the start of a dam construction project many of the socio-economic factors of the region have had positive growth and make the whole region’s condition better, some of the betterments are seen in the raised amount of salary earned by the locals and the growth of the tourism industry and job opportunities in the region which are closely counter-related to the corrective measures to be taken after the project’s completion in the way that will directly affect or reduce the positive effects. At the same time, the land’ indices that relates to their value and the use had negative growth which will be aggravated in case of improper supervision and will result in land-use change. Given the fact that the Iran’s Natural Resources Organization is the owner of the big shares of the land, it can have more supervision over the region and the land by employing the local people and will prevent the land-use change and property speculation. As it was pointed out earlier, the project is located in the crowded road of Tehran-Shomal and regarding the high number of road accidents in Iran and the area’s need for a health center, the construction of a round-the-clock medical center according to Table 3 will contribute greatly to the medical indices of the area, will save the time, accelerates the process of medical diagnosis, and will save the precious time of saving people’s lives in emergencies, all of which would be impossible if the center is not built by the end of the project, creating numerous problems in the area according to Table 4. Therefore, proper arrangements of building a medical center in the region were settled with the Ministry of Health and Medical Education, and a permanent medical center was built in the region. Due to the scattering of the villages and the low number of their population, building schools for each of them is not possible, making this index intact. Given the distance between the workers’ hostel and their houses it might create negative temporary social issues which will be over when the project is finished. According to the results derived from Table 6, if the corrective measures are carried out properly and completely, the socio-economic condition of the area will see a drastic improvement. Study, investigation, and accuracy in different areas of dam construction projects to deal with their negative effects which is the source of much criticism about such projects is for construction experts, and as it was observed we can make considerable progress by employing different and various forms of new science and technologies available in the world today to improve and contribute to the industry.

Kind of Effect Situation

E- D- C- B- A- N A+ B+ C+ D+ E+ Sum of

Quantative Effects

Implementation Stage

0 1 0 1 1 3 2 2 2 1 0 9+

Post Construction Stage

0 3 4 2 1 2 0 0 1 0 0 27-

Post Corrective- Procedure Stage

0 1 1 0 0 6 1 3 1 0 0 4+

I - 9

Page 10: Study of Social and Economic Impacts of Construction of ...

REFERENCES Ana, Silvia Arevalo. And El Salvador, C.A. (2003): Rapid environmental assessment tool for the

extended Berlin geothermal field project, International geothermal conference, session 12: pp. 81-87, Reykjavik, Iceland.

Duvail, S., Hamerlynck, O. (2003): Mitigation of negative ecological and socio-economic impacts of the Diama dam on the Senegal River Delta wetland (Mauritania) using a model based decision support system, Hydrology and earth system sciences, Vol. 7: pp.133-146, Centre for Ecology and Hydrology, Crowmarsh Gifford, Wallingford, UK.

Ghannad, Z., Modarres, L. (2011): Constructions methods in Siah bishe CFRD, Sixth international conference on dam engineering, C.Pina, E.Portela, J.Gomes, Lisbon, Portugal.

Kawabena, K.Y., Enoch, B. Asare., Philip, Gyau, Boakye. And Makoto, Nishigaki. (2005): Rapid impact assessment matrix (RIAM) – an analytical tool in the prioritization of water resources management problems in Ghana, Journal of the faculty of environmental science and technology,Vol.10: NO.1, pp.75-81, Okayama University, Japan.

Larry Lestritz, F., Karen, C.MK. (1981): Socioeconomic effects of large-scale resource development projects in Rural areas, Department of agriculture economics north Dakota agricultural experiment station north Dakota state university Fargo,US.

Leistritz, F.L., Maki, K.C., (1981): Socio-economic effects of large-scale resource development projects in rural areas: the case of McLean County, North Dakota.Department of Agricultural Economics, North Dakota State University, Fargo, N.Dak.

N. Lohani, B., Warren Evans, J., R. Everitt, R., Ludwig, H., A. Carpenter, R., Liang Tu, S. (1997): Environmental impact assessment for developing countries in Asia, Asian Development Bank.

Morris, P., Therivel, R. (2001): Methods of environmental impact assessment, by Spon Press, London.

Wathern, P. (1988): Environmental impact assessment theory and practice, by The academic division of Unwin Hyman, London, England.

I - 10

Page 11: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

The Evolving History of Lake Biwa Weir

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj

Masahisa Nakamura

Research Center for Sustainability and Environment, Shiga University, Japan Scientific Committee, International Lake Environment Committee Foundation, Japan

Katsuki Matsuno River Basin Policy Bureau, Shiga Prefectural Government, Japan

Keywords: Lake Biwa, Water Resources, Flood Control, Upstream-Downstream Conflict,

Ecosystem Concerns

1. AN OVERVIEW OF THE WEIR HISTORY

Lake Biwa water flows down through part of Kyoto Prefecture over the distance of some

twenty kilometers, reaching the jurisdictional boundary of Osaka Prefecture and then all

the way down to the Osaka Bay some seventy kilometers away from the lake. The

topological and hydrological features are such that the riparian land of Lake Biwa is

naturally flood prone. The Lake Biwa region residents always wanted the flood water to be

quickly released downstream to save the riparian lands from inundation, while the

downstream Osaka region residents always wanted the flood water to be kept within the

lake to save the highly populated downstream. This contentious relationship has persisted

ABSTRACT The management history of Japan’s Lake Biwa - Yodo River basin may be characterized by the

conflicting interests between upstream Shiga Prefecture and downstream Kyoto-Osaka-Hyogo

Prefectures, with the central government playing a role to mediate as well as to dictate the

situation. Over the course of basin history, it was the Lake Biwa communities that had to suffer

from the occasional severe flooding, allowing those downstream to be spared of the flooding risk.

The catastrophic and historic flooding in 1896 led to the construction of a flood control weir in

1905, bringing about a significant reduction in risk. The weir was replaced with a new structure in

1961. Development of lake water resource has also been a central issue of Biwa-Yodo basin

management, as exemplified by the inauguration in 1972 of the Lake Biwa Comprehensive

Development Project (LBCDP). Completed in 1997, the Project included water resources

development, enhanced flood control measures and economic development and environmental

conservation for Shiga Prefecture. Together with the construction of an around-the-lake levy

system, Lake Biwa was effectively turned into a huge reservoir. Over the past decades following the

completion of LBCDP, there has been emergence of an array of new issues, with gradually

changing upstream-downstream relationship. This article is meant to introduce the Lake Biwa

Weir implication depicted in Chapter 6, “Evolving History of Lake Biwa and Yodo River Basin

Management”, in the book entitled “Lake Biwa: Interactions between Nature and People, cited in

REFERENCE.

I - 11

Page 12: Study of Social and Economic Impacts of Construction of ...

over the period of more than a century, having led to the need for a flow control weir that

have undergone three phase transformations, the first being its construction in 1905 (the

Nango Weir), the second being its replacement with a new one (the Setagawa Weir or Seta

River Weir), and the third being its renovation with construction anew of an accompanying

bypass structure for more precise flow control.

2. FLOOD CONTROL

2.1. Constraining Topography of Lake Biwa

There are some 120 or so inflowing rivers to Lake Biwa originating from the surrounding

mountains. These short and steep rivers discharge the collected precipitation from the

mountainous terrains almost instantaneously into Lake Biwa. At times of severe rains, the

lake would swell to the extent that the inflowing river water would be prevented from

entering the lake, causing flooding along the shore as well as along and upstream of those

feeder rivers. The above phenomenon is also exasperated by the hydro-topography of Seta

River, the only outflowing river from the lake. The flow of water used to be impeded by a

constriction point caused by the natural protrusion a few kilometers downstream of the

river mouth. During the record-breaking flood of September 1896, for example, the lake

water level rose up to 3.76 m above the normal level, causing unprecedented flooding

around the lake, inundating most of the towns and villages around the lake and along the

inflowing water courses.

2.2. Upstream–Downstream Conflicts over Dredging of Seta River

Since the mid-19th Century, there have been a number of proposed attempts to dredge the

Seta River to increase the discharge volume of the lake water, particularly for dealing with

the above-mentioned natural topographic feature impeding the river flow. These proposed

attempts by the upstream local leaders always met severe opposition by the leaders of the

downstream Osaka, the political power house of the region at the time. The simple

dredging along the shallow and constricting stretch of the Seta River would mean sending

flood waters to the downstream, potentially jeopardizing the human lives and valuable

properties, rather than keeping the damage within the upstream farmland and villages. In

other words, the downstream region wanted the flood water to be kept upstream as long as

possible, allowing its gradual release over a prolonged time, rather than to be released all at

once. It was only after the above record flooding in 1896 that the central government

agreed to undertake a major channelization work, together with installation of a flow

control weir.

3. RELATIONSHIP BETWEEN SETA RIVER DREDGING AND THE WEIR

3.1. Synchronizing the Weir Operation for Upstream and Downstream Needs

The dredging of the Seta River and operation of the weir are inextricably linked. The weir

controls the Lake Biwa water level in such a way that, under predicted heavy rains, the lake level may be reduced to lower than the normal level and, in turn, the dredged river

bottom at the lake outlet would allow flooding water stored in the lake to be quickly

released when the downstream flooding risk has been sufficiently reduced. Dredging alone,

however, would pose the problem of causing the lake water level to decrease too much at

times when there is little rain. The weir prevents this from happening by holding back the

water and allowing the lake to function as a reservoir for downstream water uses. The

I - 12

Page 13: Study of Social and Economic Impacts of Construction of ...

dredged channel, in turn, allows passage of the amount of water required by the

downstream, as regulated by the weir.

Under conditions of heavy rains, the peak discharge from Lake Biwa can be controlled,

whereas the peak flow of the Yodo River below the weir cannot be controlled. This results

in a „time lag‟ between the impacts of heavy rains on Lake Biwa versus the downstream

Yodo River because of the topographic and hydraulic characteristics of the Yodo River

catchment area. This lag is actually beneficial for managing the Yodo River flooding.

When there is heavy rain, the Lake Biwa discharge may be restricted or completely shut

off. Once the downstream flow starts to subside, the weir operation may be synchronized

to allow discharge of lake water, thereby allowing the lake water level to slowly decrease.

Applying this principle, the weir may be operated in such a way that dredging would not

increase the risk of downstream flooding. When it rains, the rise in water level can be kept

within certain bounds, such that the duration of peak water level may be promptly reduced.

3.2. Conflicts over Fully Closing the Seta River Weir

Before the Seta River Weir was installed, people living downstream strongly opposed

dredging of the outflow channel, arguing that Lake Biwa was a self-regulating natural lake.

They believed that increasing the flow capacity would upset the lake‟s natural equilibrium.

Once the weir was installed, however, it became possible to carry out large-scale dredging

of the Seta River. The increase in the discharge capacity of the Seta River allowed

lowering of the Lake Biwa water level at times of floods, therefore, reducing the flooding

damages around the lake. However, the weir would have to be kept fully closed to prevent

lake water passing down to the Yodo River at times when it is already on the verge of

flooding with waters coming from the Katsura River and Kizu River watersheds. Thus,

what is beneficial for upstream, i.e., opening the weir at times of flooding, is not likely to

be beneficial for downstream residents, being the fundamental cause for the upstream–

downstream conflict.

4. WATER RESOURCES AND REGIONAL DEVELOPMENT NEEDS

4.1. A Brief History of Water Resources Development

Water resources development in the Lake Biwa and Yodo River basin may be told in three

major episodic tales. The first pertains to Osaka whose water resources come directly from

the downstream Yodo River. As the main use of water in the region historically was for

irrigation, there were a large number of irrigation barrages and intake structures scattered

around the mainstream and its tributaries of the Yodo River portion of the basin. Between

1896 and 1905, the first large-scale water resources development project was implemented

here, synchronically with the various flood control measures for Lake Biwa to be described

in 4.4. The main project components included widening of the channel and consolidation

of many of these barrages and intakes. As a consequence, Osaka benefited greatly from the

resultant increase in water intake capacity. The second pertains to Kyoto. The Metropolitan

Kyoto area does not lie along the Yodo River, and therefore the improvement of the Yodo River infrastructures does not necessarily benefit Kyoto. The Kyoto Governor at the time

foresaw the need for Kyoto to be supplied water directly from Lake Biwa through a canal.

After five years of construction work since 1885, directed by a young legendary engineer

Sakuro Tanabe, the canal was completed in 1890, sparing this water-constrained city from

a serious economic decline. The third and the latest pertain to Osaka, Kyoto and the Lake

Biwa region. It took shape when Osaka and the entire downstream Yodo River region

I - 13

Page 14: Study of Social and Economic Impacts of Construction of ...

began to regain its industrial strength in the early-1950s after the World War II

devastations. By the early 1960s, the existing water rights from the Yodo River flow had

already been exhausted, and Osaka was eyeing the use of abundant Lake Biwa water. This

thirst of Osaka, no longer being fully satisfied with the previous infrastructure

improvements mentioned above, culminated to the Lake Biwa Comprehensive

Development Project (LBCDP).

Figure 1: A Bird‟s View of the Lake Biwa - Yodo River Basin

4.2. Lake Biwa Comprehensive Development Project (LBCDP)

As industrialization and urbanization got accelerated in the post-war period, Osaka began

to demand that more lake water should be released from Lake Biwa, particularly during the

drought periods. The Nango Weir which had been constructed more for flood control

purposes than for water resource development. It was in 1961 that the new Seta River Weir

was constructed at a short distance downstream, both for flood control and water resource

development. More than a decade of heated political exchange took place among the

downstream local governments (mainly Osaka Prefecture and Osaka City), the National

Government, and the Shiga Prefectural Government with regard to the potential gains and

losses of this action, in terms of accrued benefits, financial burdens, and environmental

implications of transforming Lake Biwa into a sort of man-made reservoir. Increasing the

amount of flow through the Seta River channel meant the need for enlargement of the weir

capacity, as well as for dredging of the constricting channel. However, reconstruction of

the weir to provide a greater water volume in the lake, in preparation for extreme droughts,

also meant an increased probability for flooding damage around the lakeshore lands.

Combined with the need to protect the downstream Yodo River from still imminent

flooding, the ultimate solution was to construct a levy around the lake to impound more

water within the lake in anticipation of possible droughts, and in preparation for protecting

both the downstream Yodo River and Lake Biwa coastal areas from flooding. This agreed

I - 14

Page 15: Study of Social and Economic Impacts of Construction of ...

scheme of Lake Biwa water resource development is called the Lake Biwa Comprehensive

Development Project (hereafter referred to as LBCDP).

4.3. Policy Framework of LBCDP

Having turned out to be a 25-year plan (1972-1997), rather than the originally anticipated

10-year plan (1992-1981), LBCDP has expended 1.9 trillion JPY. The broader goal of the

project was developing and managing Lake Biwa in order to contribute to the sound

development of the Kinki Region (the entire Lake Biwa - Yodo River basin and the

surrounding prefectures) and to the well-being of everyone who relies on the lake.

Specifically, the objective of the LBCDP was to make proper and effective use of Lake

Biwa‟s resources, while conserving the lake and its surroundings, improving the quality of

polluted lake water, and protecting the natural environment. The policies of the project

were guided by three main concerns, i.e., management of Lake Biwa water quantity to

further reduce flooding around the lake; development of the water resources for

downstream users, as well as for Shiga Prefecture; and improvement of Lake Biwa water

quality and conservation of the natural environment. Practical targets included

development of water resources for the downstream use amounting to a maximum 40 m3/s

at times of droughts, construction of flood control embankment around the lake, and

dredging of the Seta River, together with installation of pumping stations to drain the

inundated fields. The local development projects, including road construction, sewerage

installation, establishment of nature conservation parks, solid waste disposal facilities,

water quality monitoring stations, and irrigation return flow pollution treatment facilities,

were to be implemented by Shiga Prefecture and the Water Resource Development

Corporation, with financial support coming from the national as well as the downstream

prefectural and municipal governments, apart from the due payment to be made by the

Shiga Prefecture itself.

4.4. Implementation Schemes of LBCDP

4.4.1. Planned Management of Lake Biwa Water Level

The purpose of the LBCDP was to fulfill the water supply needs of the downstream

Keihanshin (the general designation of the greater metropolitan region encompassing

Kyoto, Osaka and Kobe Cities and their Suburbs) area, based on the arrangement to release

the Lake Biwa water down through the Seta River Weir (at a maximum of 40 m3/s during

extreme droughts), as well as coping with the floods of a scale that may occur once in a

hundred years. Consequently, the maximum draw down level of lake water was set at

B.S.L. (the Biwako Basic Surface Water Level) -1.5 m. In addition, a special arrangement

was made for the Shiga Prefectural residents that any damages incurred due to the water

level decline between B.S.L. -1.5 m and -2.0 m would be compensated by the national

government and downstream local governments. The agreed process is that the

contingency plan would be implemented for the domestic, industrial, and agricultural

waterworks to continue to function when the lake water level declines toward -2 m, and

that the compensatory payments would be made for wells that may run dry. Other

provisions include compensation to the fisheries to offset income losses related to reduced fish catches. On matters pertaining to the maximum water level, the planned high water

level is set at B.S.L. +1.4 m to cope with the once-in-a-hundred-year floods, in conjunction

with other countermeasures carried out around the lake. The Lake Biwa Flood Protection

Plan was drawn up after considering the flood protection and water supply needs of the

Yodo River system as a whole.

I - 15

Page 16: Study of Social and Economic Impacts of Construction of ...

4.4.2. Seta River Dredging and Shoreline Flood Management Measures

The Seta River, the only outflow channel from Lake Biwa, was excavated during LBCDP

to increase the lake water discharge rate. The increased discharge allows for lowering of

the lake level in anticipation of increased rainy season water inflows. This „pre-lowering‟

of the water level also would allow the lake to accommodate once-in-a-hundred-year

floods, with the lake level reaching its high water mark of B.S.L. +1.4 m. Further, the

increased discharge capacity of the lake will enable the prompt reduction of its water level,

which would lessen the potential flooding damages around the lake peripheries. Prevention

of overflow from the lake and removal of inundating water, were also major goals in the

LBCDP. Consequently, the construction of the round-the-lake levees and the river channel

improvements were key elements. To allow for 1.2 m headroom over the B.S.L. +1.4 m

planned high water level, the levy embankment was constructed up to the height of B.S.L.

+2.6 m around the lake. Channel improvement of inflowing rivers also was carried out, and

pumping stations were installed to remove water that might spill over from flooded rivers

to cause lowland inundation around the lake that was blocked by the levy structure.

4.4.3. Formulation of Weir Operating Principles

Even after the weir was installed, regulations for its operation were still undecided because

of continuing opposing upstream and downstream interests. As LBCDP neared completion

in 1992, the downstream governments were finally able to execute their acquired right to

draw up to 40 m3/s of water from the Yodo River during times of severe droughts. The

Seta River Weir has been managed and operated based on these regulations since April 1,

1992. Under these regulations, the planned peak water level is set at B.S.L. of +1.4 m.

Seasonally, during the potential flood periods, the level is reduced to B.S.L. –20 cm or –30

cm (between 16 June and 15 October), while at other times, when there is a low risk of

flooding, the water level may be allowed to reach B.S.L. +30 cm (between 16 October and

15 June the next year). Accordingly, water discharges through the weir are finely

controlled so not to exceed the regulated values. During times of downstream water

shortages, the weir would be finely controlled. If the Lake Biwa water level decreases to

below B.S.L. –1.5 m, however, the Minister of Land, Infrastructure, Transport and

Tourism decides the weir operation policy, after consulting with the Governor of Shiga and

the other concerned prefectures.

4.4.4. Development of the Yodo River Basin Management Plans

The Rivers Act of 1896 was revised in 1964 to promote the integrated management of both

flood control and water supply in the entire drainage systems. Based on the revised Act,

the first Yodo River Improvement Master Plan was developed in 1965, covering the entire

Yodo River and Lake Biwa. In 1971, recognizing the need for security for the increased

population and the expanded industrial areas in the Yodo River basin, the goal of

preventing the flood damages was set at once-in-two-hundred-year flooding. The 1964

Rivers Act was revised in 1997 for the environmental aspect of river management to be

brought forth as an important consideration as flood control and water resources

management. In conformity to this revised Act, the Fundamental Yodo River Management

Policy was formulated in August 2007, and the Yodo River Improvement Plan (YRIP) was

developed in 2009 through an elaborate and quite controversial participatory process

spanning several years. Nonetheless, the spirit of the Policy was agreed to be: “rather than

sacrificing one area of a region to protect another, the intention is to improve security from

flooding in the entire river system; and “after the downstream flood control infrastructure

development has been completed and as long as there would be no threat of flooding

downstream, the weir would not be completely closed.”

I - 16

Page 17: Study of Social and Economic Impacts of Construction of ...

Box 1: Outline of Lake Biwa Comprehensive Conservation Plan (ML21 Plan)

a) Targeted Geographic Coverage

The jurisdictional area of the Shiga Prefectural Government, taking cognizance of

the implications to the downstream Yodo River region;

b) Planning Horizons

The specified period is from April 1999 through March 2020, in two phases; the

first was from 1999 to 2010, and the second is from 2010 to 2020;

c) Measures of Achievement

Improvements in overall quality of Lake Biwa water, in water infiltration and

retention capacities of watershed soils, and in the natural environment and

landscape ecology;

d) Compatibility with Other Plans

To be consistent with plans formulated by the existing national and local plans:

e) Implementation Emphasis

Promotion of citizen engagement and networking at sub-basin levels across the

watershed, and of information dissemination and research promotion;

f) Financial Provision

Mainly through the existing prefectural government sector agency budgets:

5. RESTORATION OF ECOSYSTEM INTEGRITY AND WATER QUALITY

5.1. Lake Biwa Comprehensive Conservation Plan (LBCCP)

While the downstream governments acknowledged the LBCDP accomplishments, their

gained benefits were more of an expectancy nature, i.e., more water during times of severe

droughts (which may happen once in ten years), and reduced loss of property and human

lives from major flood incidents that may happen once every few hundred years. On the

other hand, the benefits gained from the LBCDP for the Shiga government and its residents

were more direct and explicit. They saw ports and harbors renovated, levees and

embankments constructed around the lake that also now serve as a major artery road

around the lake, paddy lands extensively improved with large-scale pumping facilities for

irrigation with lake water, and even basic urban infrastructure provided for industrial

developments. The Shiga population has increased by nearly three quarters of a million

over the period of LBCDP implementation, and its per capita income, which was

previously ranked as one of the lowest among the forty seven prefectures, increased to be

among the top incomes, thanks largely to the transformation of the Shiga economy from

being primarily agricultural in nature to being primarily industrial, due in part to migration

of population and industries from the downstream Osaka region to the Lake Biwa

watershed.

This dramatic change in the profile of Lake Biwa watershed, now very urbanized and

industrialized, also meant that the paddy-wetlands along the lakeshore, which used to

provide prolific fish habitats, have been lost. During the same period, quite extensive land

conversions also have taken place, e.g., from paddy land to housing and industrial estates,

forest land to industrial estates, etc. Thus, despite the introduction of significant structural

and non-structural environmental control measures, the water quality and ecosystem

integrity of the lake and its watershed began to deteriorate. While the point source

pollution load has been significantly reduced as a result of the sewerage coverage

I - 17

Page 18: Study of Social and Economic Impacts of Construction of ...

Figure 2: Shoreline Landscape Alteration and Its

Ecological Impact

implemented during this period, the restoration of the natural self-purification capacity lost

through transformed land uses remained as a major challenge at the time of LBCDP

completion.

Consequently, toward the terminal years of the LBCDP, the Shiga government decided to

pursue a new post-LBCDP project focusing on ecosystem restoration. In March 1997, the

Shiga Prefecture compiled the results of the deliberations of a national council established

for this purpose, and prepared a plan called the Lake Biwa Comprehensive Conservation

Plan (LBCCP), dubbed “Mother Lake 21 (ML21).” The plan emphasizes that the ultimate

solution to the problems facing Lake Biwa lies in restoration of the natural and ecosystem

capacities of the coastal zone and watershed, while also pursuing the revival of an

environmental culture to allow such re-transformation to occur. The Plan is being financed

basically under sectoral budgets, with some preferential subsidy based on their merit

within already-existing sectoral plans and programs. Specific elements of the ML21 plan

are elaborated in Box 1.

5.2. Appraisal of First 10 Years of LBCCP (1998-2010)

In March 2010, with the first phase

of LBCCP having reached its

terminal year, and the second phase

about to be launched, the LBCCP

scientific advisory committee issued

a review report of the first phase,

with recommendations for the second

phase. The report‟s appraisal was that

the Plan has generally played a

significant role as a long term vision

for Lake Biwa, with the first phase

attaining some significant

achievements in lowering the

concentration of total phosphorus

(TP), although the rate of reduction

in the total nitrogen (TN)

concentration was not as impressive

as that for TP. The chemical oxygen

demand (COD) has actually

gradually increased during the period,

being, a puzzling phenomenon whose

implications are not yet clearly

understood scientifically. In terms of

the inflowing pollution load, the point-source contribution has been significantly reduced,

although the nonpoint contribution remained much the same as ten years earlier.

In regard to improved water infiltration and retention capacities of the watershed soils, the results are not so significant. Among others, the report points out, more profoundly, the

need for the Japanese forest industry to gain competitive strength over inexpensive

imported forest products so that an institutionalized system of forest maintenance would be

established both for providing for economic viability and for healthy forest land. Further,

the report points out that the 1st period target was not very clear for the on-the-ground

implementation of plans and programs, particularly with regard to "land acquisition for

I - 18

Page 19: Study of Social and Economic Impacts of Construction of ...

Figure 3: Transformation from Conflict to Cooperation

ecosystem restoration." But most of all, the report pointed out that there are issues and

problems that did not exist before the LBCCP that are now posing serious threats to the

natural environment and landscape ecology of Lake Biwa, including the loss of habitat for

indigenous species of fish, and the prolific growth of macrophytes in the South basin of

Lake Biwa, particularly in relation to the changed operational procedure of the Seta River

Weir, all indicating that the future of the LBCCP is directly linked to the Yodo River

System improvement policy.

6. THE CHALLENGES AHEAD

The topographical,

climatological, hydrological

settings of the Biwa-Yodo basin

have fostered the peculiar

human geography of the region,

with its resulting unique

demographic, socioeconomic,

and political interactions.

Historically, the pressures put on

to Lake Biwa and its watershed

from the downstream water

users has been enormous

because of the latter‟s political,

economic, and industrial power.

The restrictions on the discharge

of Lake Biwa flood water, both

geophysically and geopolitically, had been causing an insurmountable stress on the

relationship between the upstream and the downstream communities, until a series of

physical interventions was introduced in the first half of the twentieth century, including

construction of a flood control weir at the outlet of Lake Biwa. With additional

interventions to expand the role of the weir to accommodate water resources development

through LBCDP, the strained relationship between the upstream and downstream entities

seemed to have been ameliorated, at least superficially. The Biwa-Yodo system is today

providing water, flood, and drought mitigation, as well as environmental and livelihood

amenities to the population of over 18 million living in Shiga and the Keihanshin area,

totaling some 1,200 km2 .The Biwa-Yodo basin is also characterized by the historic timing

of key policy interventions. Whether they were construction of monumental water control

facilities, development and implementation of instrumental plans and programs, and/or

emergence of controversial and conflicts, their timing seem to have helped shape lake

basin governance since they relate to the region‟s social and economic profile.

LBCDP has brought about a dramatic change in the management profile of water resources

and flood control, accompanied by the emergence of new economic geography within the

Biwa-Yodo basin, and in the entire downstream region. Thereafter, people and industries

began to migrate from the densely packed downstream region to the more spacious

upstream region around Lake Biwa. The underlying intricacy of this fundamental linkage

dynamics resurfaced as a dictating factor in the evolving process of policy development for

the post-LBCDP water and environmental management, in relation to implementation of

LBCCP.

I - 19

Page 20: Study of Social and Economic Impacts of Construction of ...

The overriding issue in the former is whether or not it will be possible for LBCCP to play a

catalytic role in accelerating the lake‟s ecosystem integrity when the national government

and the downstream governments and people consider that they have already fulfilled what

they were obliged to do for the lake over the past decades. On the other hand, the

overriding issue for the latter is if, and how, the Shiga Prefecture together with the

downstream governments may be able to develop a regional institutional framework for

resolving the contentious issues imbedded in the YRIP. Among the emerging frameworks

is a regionally autonomous governance structure for the Biwa-Yodo basin, with the

national government probably playing a much less prominent role in having “the last say,”

as having historically been the case since the late 19th

Century.

ACKNOWLEDGEMENT The authors wish to acknowledge the coauthors of Chapter 6, “Evolving History of Lake Biwa and

Yodo River Basin Management” in the book titled “Lake Biwa: Interactions between Nature and

People, as cited in the REFERENCE Section below. This article is meant to present an overview of

the Chapter, particularly in regard to the evolving history of Lake Biwa Weir. We would like to

acknowledge in particular that the information on flood control mainly prepared by one of the

coauthors of that Chapter, Mr. Y. Moriyasu. Part of that information was presented here in a

summary form.

REFERENCES

Matsuno, K. (2011): Aiming at Integrated Basin Management in the Lake Biwa-Yodo River

Basin, 14th

World Lake Conference, Austin, Texas USA.

Nakamura, M. (1995): Lake Biwa: Have sustainable development objectives been me?t,

Lakes & Reservoirs: Research and Management, 1:1. pp. 3-29, Blackwell Publishing

Asia Pty Ltd. Australia.

Nakamura, M. (2002): Lake Biwa Watershed Transformation and the Changed Water

Environments, Verh. Internat. Verein. Limnol, 28: pp. 1-15. Stuttgart, Germany.

Nakamura, M., Ogino, Y., Akiyama, M. and Moriyasu Y. (2012): Evolving History of Lake

Biwa and Yodo River Basin Management in “Lake Biwa: Interactions between

Nature and People” by Hiroya Kawanabe et al. (eds.), Springer Dordrecht

Heiderberg New York London.

I - 20

Page 21: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Environmentally friendly water-powered DTH drilling in dam applications - The history of Down-The-Hole-Drilling and

use of water-powered hammers [Blank line 11 pt]

Dr. Donald A. Bruce President, Geosystems, L.P., P.O. Box 237, Venetia, PA 15367, U.S.A., [email protected]

[Blank line 10 pt]

Rudy Lyon Research and Development Manager, Center Rock Inc., 1 W. 4th Street, Salem, VA 24153, U.S.A.

[Blank line 10 pt]

Stefan Swartling / M. Sc. Michael Beas Managing Director / Dam Application Responsible respectively,

LKAB Wassara AB, Rosenlundsgatan 52 SE-118 63 Stockholm, Sweden

[Blank line 10 pt]

[Blank line 10 pt]

[Blank line 10 pt]

[Blank line 10 pt]

ABSTRACT Down-the-hole drilling has been a feature of dam anchoring and rock mass grouting in the U.S. for

many decades. Until quite recently, this rotary percussive drilling method was synonymous with

the use of compressed air. Within the last decade, however, increasing use has been made of

water-activated, down-the-hole hammers. These provide many significant advantages, especially

for rock fissure grouting where the use of water flush is now regarded as standard, and the use of

compressed air is not advisable. This paper provides a brief history of the development of down-

the-hole hammers in U.S. practice, and describes the numerous steps which have been followed to

make contemporary hammers especially efficient and cost effective. The paper also describes the

operating principles of water-powered hammers, and reviews the numerous, significant advantages

these tools have brought to the dam remediation community. [Blank line 10 pt]

Keywords: water power drilling environment safety [Blank line 10 pt]

[Blank line 10 pt]

1. HISTORICAL PERSPECTIVE ON PERCUSSIVE DRILLING METHODS [Blank line 10 pt]

Air-flushed drilling with top hammers began in the mining industry in Sweden in 1873,

while down-the-hole (DTH) drills, again with air flush (and activation) became operational

in 1950. During that same interval, Simon Ingersoll had patented the first steam-powered,

top hammer rock drill to provide higher productivity in blast hole drilling. It is well known

that water, as an activating, flushing and cooling medium, has many significant advantages

over the use of air. However, it was not until 1973 that top hammer systems (either air or

hydraulically activated) for larger rigs were adapted to the use of water flush, typically via

“under the head” swivels. [Blank line 10 pt]

The concept of a water-powered, down-the-hole hammer (WDTH) had been explored prior

to G. Drill acquiring the original patent from Atlas Copco in 1988. LKAB, a huge

underground mining company, owned by the Swedish Government and providing about

90% of the European Union’s iron ore, purchased G. Drill in 1991 and encouraged the

I - 21

Page 22: Study of Social and Economic Impacts of Construction of ...

commercial development of the WDTH for mining-related operations. The first full-scale

WDTH production works were carried out for LKAB in 1995, since when over 25 million

lineal meters of drilling have been recorded in both underground and surface applications. [Blank line 10 pt]

In 2001, G-Drill was renamed Wassara, which today still holds the worldwide patents for

WDTH technology. Regarding North American usage, the first significant application was

by Advanced Construction Techniques (ACT) Ltd. during the test grouting program

conducted for the U.S. Army Corps of Engineers at McCook Reservoir, Chicago, in 2002.

Since then, WDTH has become the tool of choice for specialty drilling and grouting

contractors on rock grouting projects for dams and other major structures throughout the

U.S. [Blank line 10 pt]

Other DTH variants have been developed over the last 15 years or so, and are based on air

activation and flush. These are described in Weaver and Bruce (2007) and include: [Blank line 10 pt]

• Reverse circulation (air flush)

• Dual-fluid system (using air as the activator but permitting water flush also) [Blank line 10 pt]

However, the purpose of this paper is to focus on WDTH technology for dam-related

projects, and to contrast it, wherever appropriate, with corresponding direct air flush,

conventional DTH systems. [Blank line 10 pt]

[Blank line 10 pt]

2. GENERAL BACKGROUND TO AIR-POWERED, DOWN-THE-HOLE

HAMMER DRILLING (DTH) [Blank line 10 pt]

For production hole drilling, there are fundamentally three basic methods, as illustrated in

Figure 1: rotary; rotary percussive top drive; and rotary percussive down-the-hole

hammering (DTH). An elderly but still useful application chart was produced by

McGregor (1967) and is reproduced in Figure 2. As noted above, in the 1960’s both top

hole percussion and DTH drilling were synonymous with the use of air flush. It is now

generally recognized and widely accepted in rock fissure grouting circles that water flush

is far preferable, since compressed air tends to force rock cuttings into fissures, so greatly

reducing the ability of the formation to accept grout. [Blank line 10 pt]

[Blank line 10 pt]

Figure 1. Schematic showing basic rock drilling principles. [Blank line 10 pt]

Rotary

Top-Ham

mer

Down-The-Hole

I - 22

Page 23: Study of Social and Economic Impacts of Construction of ...

[Blank line 10 pt]

Figure 2. Basic drilling method selection guide for rock using non-coring methods

(Littlejohn and Bruce, 1977. Adapted from McGregor, 1967). [Blank line 10 pt]

Of course there have been many significant developments and modifications in the

intervening period, but the basic guidelines remain the same: [Blank line 10 pt]

• Rotary drilling is economic in all hole sizes in soft-medium rocks. This method requires

high bit load (“crowd”) and high rotary torque. This was the standard method of drilling

grout holes for dams in the U.S. since earliest times (i.e., the 1890’s) as only rotary drilling

could permit water flush to be used.

• Rotary percussive (top drive) is economic in materials of all types, up to about 5-inch

diameter. It has low crowd and torque requirements and typically modest flush pressure

and flow demands (both for air and water).

• Rotary percussive (down-the-hole hammer) drilling is typically preferred in medium-hard

materials for holes over 4-inch diameter and over 40 feet deep. High pressure, high volume

flushing media are required, whereas low feed and torque requirements are relatively low. [Blank line 10 pt]

DTH drilling has many advantages over top hammer drilling for larger, deeper holes in

medium-hard formations: [Blank line 10 pt]

• There is minimal power loss as the hole is deepened and so penetration rates do not

markedly decline with depth provided that back pressure does not rise significantly in the

borehole.

• The low crowd pressures, coupled with the relatively large diameter rods which are used,

combine to promote much straighter holes.

• The lower rotational speed reduces vibrations to the drill head and rig. [Blank line 10 pt]

In relation to pure rotary drilling, DTH drilling is faster, due to the more focused and

intensified stresses imposed on the rock, and does not require sophisticated drilling mud

preparation, handling and cleaning systems. Air-powered equipment has the obvious yet

distinct advantage of exhausting energy-depleted air directly into the atmosphere, where

the difference between rock and air density makes separation direct and simple. [Blank line 10 pt]

For the conventional, air-powered DTH (as shown in Figure 3), there are three basic

considerations: [Blank line 10 pt]

1. Compression of the air to operate the DTH by generating impact energy.

2. Energy transmissions from the piston to the rock.

I - 23

Page 24: Study of Social and Economic Impacts of Construction of ...

3. Removal of cuttings from the hole by the exhausted air. [Blank line 10 pt]

[Blank line 10 pt]

Figure 3. Components of a typical air-powered Down-the-Hole Hammer

(Courtesy of Center Rock, Inc.). [Blank line 10 pt]

Each of these considerations has, in turn, many controlling factors and nuances: suffice it

to say that the contemporary hammers continue to undergo progressive development as

consequences of close field monitoring and highly sophisticated computer modelling at the

design stage. A particularly critical factor — for all types of the DTH’s — relates to the

cycling of the piston. The objective is to consume the activating medium with the highest

level of efficiency. Bearing in mind that the drill penetration rate is proportional to the

power applied, it will therefore be dictated by the energy imparted to the piston times the

frequency of the blows. Hence, it follows that a prime goal is to maximize the area of the

piston and the effective air pressure, and to minimize leakage or bypass. The interested

reader is referred to Lyon and Soppe (2012) for detailed considerations [Blank line 10 pt]

[Blank line 10 pt]

3. GENERAL BACKGROUND TO WATER-POWERED, DOWN-THE-HOLE

HAMMER DRILLING (WDTH) [Blank line 10 pt]

WDTH’s are used in hard, stable rock drilling, and with casing systems for overburden

drilling. Compared to conventional air driven down-the-hole hammers or top hammers,

these WDTH’s provide many advantages, including low energy consumption, reduced

environmental impact, minimal hole deviation, deeper drilling, high output power and

minimal impact on the surrounding ground. [Blank line 10 pt]

A WDTH has only two moving parts, the piston and the valve. This simplicity contributes

to its high degrees of reliability and performance, especially noteworthy in more difficult

drilling conditions. Water at up to 180 bar delivery pressure is used to activate the impact

mechanism of the hammer at high frequency and with high power. When the water leaves

the hammer, it has a low pressure and very low flush velocity (100-500 ft/min) which is

still adequate to bring the cuttings to the surface and to clean the borehole. Further, the

hydrostatic column created above the hammer helps to keep the hole stable and prevents

collapse, while in strata with high water tables it prevents ground water being sucked into

I - 24

Page 25: Study of Social and Economic Impacts of Construction of ...

the hole, as would be the case with air flush, giving rise to hole stability problems and

potentially environmental implications. [Blank line 10 pt]

[Blank line 10 pt]

4. WDTH EQUIPMENT DETAILS [Blank line 10 pt]

Table 1 shows the range of hammer and bit sizes, while the overall system organization is

shown in Figure 4. With respect to the individual components, the following points are

especially relevant: [Blank line 10 pt]

Table 1. Range of hammers, bits and operating parameters (courtesy of LKAB Wassara). [Blank line 10 pt]

[Blank line 10 pt]

[Blank line 10 pt]

Figure 4. WDTH system components (courtesy of LKAB Wassara). [Blank line 10 pt]

• Drill Bits: These are of premium quality, incorporating an impact surface and flushing

channels, specifically designed to enhance productivity and improve wear resistance.

• Check Valve: This is used to ensure that the hammer function is not disturbed by particles

entering the hammer through the drill bit when the hammer is shut off when, for example,

changing drill rods. This feature is particularly useful when drilling deep holes or when

drilling through fine grained sediments. The check valve has also a fully closed / fully open

function which can be activated.

• Drill Rods: These are thick-walled, friction welded tubes with O-ring sealed tube threads, to

minimize water loss at these locations. If leakage should occur, the pump delivery rate is

I - 25

Page 26: Study of Social and Economic Impacts of Construction of ...

increased slightly to maintain the target hammer operating pressure. It may be noted that the

use of water, and sealed-connection rods greatly reduces the safety risk arising from spraying

of debris, which often occurs when drilling with air, and standard thread rods. The typical

combinations for hard rock drilling are as follows: [Blank line 10 pt]

HAMMER

ROD

DIAMETER

(mm)

ROD

THREAD

(inches)

W50 48 API NC13

W80 76 API 2⅜

W100 89 API 2⅜

W120 102 API 3½

W150 114 API 3½

[Blank line 10 pt]

Table 2. Hammer and drill rod set-ups. [Blank line 10 pt]

These rods are manufactured in standard lengths of 3.3; 4.6; 6.6; and 10.0 feet. Casing

diameters of 4½ to 8½ inches can be accommodated. [Blank line 10 pt]

• Swivels: Two different designs are available to permit drilling rigs to operate WDTH, and

are built to be maintenance free. They have a roller bearing-free design, with water

lubricated sliding bearings and seals. Swivels can be mounted either on top of the rotary

head, or under the head (and so directly above the uppermost rod).

• Water Pump Units: Dedicated units are used for each of the different hammer sizes. The

pump features include a water inlet buffer tank if drilling with an irregular water supply, a

dampening system for the pressure return pulses generated by the hammer, and a control

system that optimizes the drilling operation as well as the fuel consumption. The operation

of the pump is highly automated, so reducing labor requirements and maintenance. It is

standard to have diesel power, but electric drive pumps are often used in urban

environments, and soundproofing is also a common option.

• Water Supply and Consumption: Water should be fresh, and contain particles of no larger

than 50 μm. The WDTH pumps contain an inlet water filter to further prevent

malfunctions of the hammer. Salt water can be used, but special maintenance details need

to be implemented, such as flushing the system with fresh water before stand-down

periods. Recirculation of the flushing water is not recommended as this can cause

accelerated wear of the internal components of the hammers. Water consumption is

modest: for example, when drilling a 4½ -inch hole with the W100 hammer at full power,

the requirement is 55 to 90 gpm (at service limit). This is equivalent to an hourly

consumption in the range of 9.2 to 16.2 cubic yards at 60% drilling activity.

• Flushing Water Treatment: The activating water is not contaminated since no lubricants are

used in the hammer. Thus, if the ground itself is not contaminated, the flush return cannot

be contaminated and so requires no special measures during the collection and disposal

processes. [Blank line 10 pt]

[Blank line 10 pt]

5. SUMMARY OF ADVANTAGES OF WDTH [Blank line 10 pt]

5. 1. Cost Effectiveness

The hammer is always in contact with the bit, and so impact energy does not diminish with

depth, when increasing water heads are encountered. Drilling depths of around 1,500 feet

can be readily achieved. For WDTH drilling, the hammer, and the high pressure pump, are

much more energy efficient than an equivalent air-powered DTH system, resulting in

I - 26

Page 27: Study of Social and Economic Impacts of Construction of ...

significantly lower fuel consumption. For illustration, a typical air compressor has an

efficiency of 7-10%, compared to a plunger pump’s efficiency of about 90%. Typical

values for average fuel consumption when drilling with the W120 hammer and a 5⅛-inch

bit are: [Blank line 10 pt]

• Idling, 1.1 to 1.3 gallons/hour (gph)

• Medium power (including when casing), 4 to 5.3 gph

• Maximum power, 6.6 to 7.9 gph. [Blank line 10 pt]

These are measured values, based on 60% drilling time. A study by Lindholm (2011)

confirmed that fuel consumptions for air DTH (i.e., for the compressor) average around 0.8

g per meter drilled, a figure 3 to 4 times higher than for WDTH. [Blank line 10 pt]

5. 2. Clean Water for Powering the Hammer is Environmentally Harmless

The use of clean, oil-free water for powering and lubricating the hammer means that

neither the borehole nor the flushing water carrying the cuttings is contaminated by oil.

Lubricating oil consumptions for standard size air-powered DTH’s vary from about 0.05 to

0.4 gph, depending on hammer diameter. Likewise, there is no dust or oil mist which can

cause air pollution, or which needs to be captured. [Blank line 10 pt]

5. 3. Drilling System Advantages [Blank line 10 pt]

• There is reduced component wear since the velocity of the flushing water is

relatively low, resulting in low rates of wear on the surface of the hammer and drill

rods. It is not unusual for the service life of the W100 hammer body to be up to

30,000 l. ft. even in very abrasive conditions, while the limitation on rod usage is

typically thread wear at over 100,000 lft. Hammers are serviced every 5,000-

10,000 l.ft. of drilling, depending on water quality. Lindholm (2011) recorded air

hammer and rod longevities of 11,000 lft. and 2,300 lft., respectively

• Less harm is caused to the ground since the flushing water exits the hammer under

low pressure and, given the fact that the rate of flow is moderate, the up-hole

velocity is correspondingly low. Further, the hydrostatic pressure created by the

flushing water helps stabilize the hole wall and therefore promotes straightness in

soft formations or overburden by reducing “overbreak.” Likewise, such low up-

hole velocities permit the use of tight tolerance hammer and rod stabilizing devices

further enhancing straightness, and deviations in the range of up to 1 degree can be

anticipated, and values less than 0.2 degree can be achieved. This “gentle” drilling

mechanism supply reflects the fact that water is an incompressible medium, unlike

compressed air – the volume of which expands as pressure reduces (such as occurs

when air flush passes out of the hammer and begins to move up the drill hole

annulus). [Blank line 10 pt]

[Blank line 10 pt]

6. SUMMARY OF DISADVANTAGES OF WDTH [Blank line 10 pt]

Water consumptions are not insubstantial and so WDTH may not be a potential tool in

very arid areas, especially since recirculation of flush water is not advisable. Also, it is fair

to say that the components (however, rods and pumps especially) are higher priced than

conventional air-powered DTH. However, in this regard, WDTH will still prove attractive

when its advantages, in terms of productivity, depth, environmental impact and so on, are

weighed.

I - 27

Page 28: Study of Social and Economic Impacts of Construction of ...

[Blank line 10 pt]

[Blank line 10 pt]

7. WDTH APPLICATIONS [Blank line 10 pt]

7. 1 Routine construction drilling for grout curtains

WDTH is routinely used for drilling production holes for grout curtains throughout the

world. The fast, straight, environmentally favorable nature of the drilling is particularly

appreciated in this application where water flush is essential for the high efficiency of the

subsequent grouting operations. Significant examples in North America from 2002

onwards include McCook Reservoir and Thornton Reservoir, Chicago, IL; Wolf Creek

Dam, KY (where both 4-inch and 8-inch holes were drilled for grout holes, and for guided

pilot holes, respectively); Niagara, ON, Clearwater Dam, MO; Center Hill Dam, TN

(Bruce, 2012), Logan Martin Dam, AL, and Mormon Island Dam, CA (Bruce 2012).

WDTH’s have also been used on dams throughout Europe, Asia and Central America.

Other applications include drilling for anchors and micro piles, typically in the range of 3 -

6½ inches in diameter. [Blank line 10 pt]

As noted in Section 1 (above), the first U.S. application was at the McCook Reservoir,

where a test program was conducted partly to determine the optimal drilling method. Two

parallel rows of inclined grout holes were drilled, each row containing 128 holes to depths

over 400 feet. One row was drilled with conventional rotary methods, the other with a

Wassara W80 hammer, 3.75-inch diameter bit, and 3-inch diameter drill rods. In the

Silurian Dolomites and limestones of the site, the test results showed the WDTH to be over

100% more productive then the rotary system, while the average deviation at maximum

depth was restricted to just over 1%. As a result, the WDTH was specified by the U.S.

Army Corps of Engineers for the following 874,000 lft. of production drilling for the grout

curtain. [Blank line 10 pt]

7. 2 Drilling in sensitive areas

Urban areas are usually “sensitive” in the sense that they have limited capacity to absorb

movements and/or changes in groundwater level due to drilling operations. This equally

applies to dam drilling applications. Furthermore, the injection of air or oil into the ground

is typically prohibited. Due to the incompressible nature of the water flush, and its low up-

hole velocity, over-pressurization risks are minimized unlike the case with compressed air.

WDTH’s are also very quiet, do not create dust, and do not use lubricants. [Blank line 10 pt]

7. 3 Overburden drilling:

WDTH’s can be used with a variety of overburden drilling systems, most notable and

recently the Rotolock system of Center Rock Inc. (Bruce, 2012a). The water helps to

lubricate the system, promoting a smoother drilling operation even through complex and

variable conditions, from soft clays and sands to boulders and old timber piles. WDTH’s

are particularly efficient for deeper holes in areas of high water tables and, as noted above,

cannot cause over-pressurization of the formation, as compressed air can do. The

environmental advantages (e.g., no oil, dust, reduced noise) are as described for the

previous applications. Casing systems of diameter 4½ to 8½ inches are standard. When

drilling with overburden systems or in soft rocks, the hammer pressure is reduced to about

50% of that for harder rock drilling. [Blank line 10 pt]

I - 28

Page 29: Study of Social and Economic Impacts of Construction of ...

7. 4 Geothermal Drilling

This typically involves the drilling of deep holes which have to be very straight to avoid

intersection. This plays to the WDTH’s strengths, especially in urban areas where space

for installing replacement holes may be at a premium. The environmental and operational

advantages listed for previous applications remain in play. On a recent project in Malmö,

Sweden, 75 holes each 900 feet long were drilled through saturated soil and rock

formations. The maximum allowance for return water to the sedimentation system was

about 250 cyds per day, which was satisfied by WDTH drilling. A previous test with air

DTH drilling had produced about 130 cyds per hour which had to be contained. [Blank line 10 pt]

7. 5 Jet grouting

When jet grouting in difficult bouldery conditions, it is a common requirement to have to

predrill the hole to permit the jet grouting rods and monitor to be subsequently placed.

This newer development in WDTH technology permits single pass jet grouting whereby

the jetting can be conducted through the specially adapted hammer, and the sealed-

connection drill rods. Precutting of the formation during drilling with water or air can still

be accomplished, leading to enhanced column diameter with this otherwise conventional,

one-fluid jet grouting system. The standard hammer is the W100 JG hammer, equipped

with a 6-inch diameter bit. This requires 52-93 gpm of water at 170 bars. A maximum

grout delivery pressure of 500 bars can be accommodated. The hammer activation, and the

jet grouting operation, are each controlled independently by different pumps. [Blank line 10 pt]

7. 6 Marine and reservoir drilling operations

The main advantages of WDTH’s in this applications are: [Blank line 10 pt]

• Penetration rate does not decrease with depth as is the case with air-powered hammers.

• No oil is introduced into the water.

• Minimal risk of over-pressurizing the formation. [Blank line 10 pt]

7. 7 Exploratory drilling

WDTH is being increasingly used to lower exploration costs by providing relatively fast

methods to penetrate to the “pay zone” which is to be cored or otherwise logged or tested.

Such non-cored horizons will typically comprise overburden, fills, moraine/till, and rock

above the ore body. This WDTH drilling can be conducted for both surface and

underground excavation, in conjunction with standard core rigs (which also use water

flush). Experience shows that the average WDTH penetration rate is up to 5 times that of

core drilling. The extreme straightness of the WDTH holes is also a considerable

advantage of this application. Figure 5 shows the details of the exploratory drill system

setup, designed to accommodate N-size (3-inch) coring afterwards. [Blank line 10 pt]

It is specifically recommended that: [Blank line 10 pt]

• To avoid the risk of wear being caused by the vibrations from the hammer, “weight rods”

be incorporated in the standard drill string.

• The WDTH should operate at around 70 bars during casing installation, and up to 180 bars

during rock drilling.

• PCD (Poly-Crystalline Diamond Composite) bits limit wear on the bit perimeter promoting

hole verticality and optimizing bit life. However, traditional TC (tungsten carbide) bits

can be used if the formation is favorable (i.e., non-abrasive). [Blank line 10 pt]

I - 29

Page 30: Study of Social and Economic Impacts of Construction of ...

[Blank line 10 pt]

Figure 5. WDTH system for Exploration (courtesy LKAB Wassara). [Blank line 10 pt]

7. 8 Mining

The particular demands of the deep mining industry (especially fast penetration, hole

straightness, reduced rate of bit wear, and enhanced safety and environmental

considerations) initially drove the development in Sweden of WDTH’s. In the words of

the Wassara promotional brochure, “In short, it (i.e., WDTH) enables mining companies to

scale up, improve safety, lower their energy consumption and minimize the impact on the

environment.” The fundamental driving principle was that pressurized water can provide a

high frequency and high energy per blow and, when exhausted through the hammer, still

had sufficient up-hole velocity to flush and clean the hole. In support of these claims,

Wassara claims: [Blank line 10 pt]

• Deviations < 1% as opposed to 10-20% with top hammers.

• Energy consumptions are about 20% that of an air compressor and 33% that of a top

hammer.

• Uphole velocity of 100-500 ft./min. as opposed to air at over 7,000 ft./min.

• Frequency of blows (3,600 bpm) higher than air DTH (2,000-2,700 bpm). [Blank line 10 pt]

[Blank line 10 pt]

8. FINAL REMARKS [Blank line 10 pt]

WDTH’s are a proven method for safe and efficient drilling in all — and especially

sensitive — formations and applications. The use of water as a power transmitter to the

hammer has fundamentally changed DTH drilling principles and, being incompressible,

I - 30

Page 31: Study of Social and Economic Impacts of Construction of ...

ensures minimal power loss to great depths under the ambient water table. WDTH drilling

is applied from both surface and underground locations and already has a rich history of

usage in dams in North America. Its other main advantages over conventional air-powered

DTH’s include superior productivity, straighter holes, protection to the environment

(subsurface and atmosphere), and much reduced energy requirements. [Blank line 10 pt]

WDTH’s are a proven method for safe and efficient drilling in all — and especially

sensitive — formations and applications. The use of water as a power transmitter to the [Blank line 10 pt]

[Blank line 10 pt]

9. REFERENCE PROJECTS [Blank line 10 pt]

Some projects of reference where the water-powered drilling technology has been

successfully used will be presented more in details at the ICOLD 2014 Bali Symposium: [Blank line 10 pt]

• The McCook Reservoir in USA (rehab) (2006-2009)

• The Wolf Creek Dam in USA (rehab) (2007-2011)

• The Angostura Dam in Chile (new dam) (2012) [Blank line 10 pt]

[Blank line 10 pt]

REFERENCES [Blank line 9 pt]

Bruce, D.A. (2012): Specialty Construction Techniques for Dam and Levee Remediation,

Spon Press an imprint of Taylor and Francis, 304 pp.

Bruce, D.A. (2012a): The Evolution of Small Hole Drilling Methods for Geotechnical

Construction Techniques, ADSC EXPO, ADSC: The International Association of

Foundation Drilling, March 14-17, San Antonio, TX, 18 pp.

Lindholm, J.A. (2011): Cost Calculation and Market Analysis of Geothermal Drilling

Methods, MSC Thesis, Luleå University of Technology, Sweden, January, 75 pp.

Littlejohn, G.S. and D.A. Bruce. (1977): Rock Anchors - State of the Art., Foundation

Publications, Essex, England, 50 p. (Previously published in Ground Engineering in

5 parts, 1975-1976.).

Lyon, R. and Soppe, R. (2012): Drill Tooling: Down Hole Hammers, Presentation at the

ADSC Drill Operator School, September 11, Greensboro, NC.

McGregor, K. (1967): The Drilling of Rock, C.R. Books Ltd., London

Weaver, K.D. and D.A. Bruce (2007): Dam Foundation Grouting, Revised and Expanded

Edition, American Society of Civil Engineers, ASCE Press, New York, 504 p.

I - 31

Page 32: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Development of Cruising RCD Construction Method hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj

2(14pt)

Y. YAMAGUCHI, T. FUJISAWA & Y.YOSHIDA Japan Dam Engineering Center, Taito, Tokyo, Japan

[email protected]

T. SASAKI Large-scale Hydraulic Structure Division, National Institute for Land and Infrastructure Management,

Ministry of Land, Infrastructure, Transport and Tourism, Tsukuba, Ibaraki, Japan

ABSTRACT: The RCD construction method is a rationalized construction method for concrete dams which was

originally developed in Japan in 1970’s. The RCD construction method has been applied to about

50 concrete gravity dams in Japan, and has achieved reduction of the construction period, the

labor cost, the environmental issue, and the hazard in safety for the constructor. However, under

the current social and economic conditions, it is necessary to develop technologies to achieve

further rationalization in order to cut costs.

The conventional RCD construction method has two major problems to be solved for the further

rationalization, such as alternate placement of RCD and external concretes and setting of cross-

forms along transverse joints at the stopping of RCD concrete placement in a lift. The “cruising

RCD construction method” has been newly developed to solve these problems.

In this paper, we will introduce an outline of this technology including application cases based on

“Engineering Manual for Cruising RCD Construction Method Technology” published by the

Japan Dam Engineering Center.

Keywords: Cruising RCD Construction Method, Concrete Dams, Rationalization

1. INTRODUCTION

The RCD construction method, which is a rational construction method for concrete dams

developed originally in Japan in the 1970’s, is a roller compacted concrete construction

method which preceded the RCC method. In Japan, about 50 dams have been constructed

by the RCD method, contributing to the shortening of construction periods, reduction of

labor costs, resolution of environmental problems, and ensuring safety during construction.

But as a result of social and economic conditions which have appeared in Japan in recent

years, there is a demand for the development of technologies to further speed up and lower

the cost of dam construction, so technologies that permit faster and more efficient

execution of the conventional RCD method have been developed.

But the conventional RCD method still has two major problems to be resolved for the

further rationalization. One is an alternate placement of RCD concrete and external

I - 32

Page 33: Study of Social and Economic Impacts of Construction of ...

concrete in order to fully integrate the two types of concrete, and the other is the need to

install cross-forms at placing ends of RCD concrete while aligning them with the

transverse joint locations. To resolve these problems, the “Cruising RCD Construction

Method” was developed as a new construction method. This method can speed up

execution of construction by placing the RCD concrete prior to placing the external

concrete and by stopping placing of RCD concrete without using cross-forms.

The cruising RCD construction method was established through a technology development

study that began in 2006 at the Kasegawa Dam (Kyushu Regional Development Bureau,

Ministry of Land, Infrastructure, Transport and Tourism (MLIT), dam height, H=97m, dam

body volume, V=941,000m3), where it was applied to the upper part of the dam body,

confirming its effectiveness. And beginning in 2010, at the Yunishigawa Dam (Kanto

Regional Development Bureau, MLIT, H=119m, V=1,060,000m3), technology was studied

and developed to permit continuous placing of an entire lift in order to further rationalize

the cruising RCD construction method, confirming that this new technology further speeds

up and improves the workability and safety of construction.

Based on these successes, the Japan Dam Engineering Center (JDEC), which has led the

development of the cruising RCD construction method and the first application of it,

published the “Engineering Manual for Cruising RCD Construction Method” in June

2010 [JDEC, 2010] and a revised edition in February 2012 [JDEC, 2012]. Since the

publication of the revised edition, the application of the cruising RCD method has

expanded as it has, for example, been applied to construct the Tsugaru Dam (Tohoku

Regional Development Bureau, MLIT, H=97.2m, V=717,000m3) and the Gokayama Dam

(Fukuoka Prefectural Government, H=102.5m, V=935,000m3).

This paper outlines this construction method and introduces the basic technologies which

achieved this construction method and, based on actual applications, demonstrates its

effectiveness.

2. CHRACTRISTCS OF THE CRUSING RCD CONSTRUCTION METHOD

The cruising RCD construction method has the three execution characteristics shown

below which distinguish it from the conventional RCD construction method (see Fig. 1).

Figure 1. Concept of cruising RCD construction method

I - 33

Page 34: Study of Social and Economic Impacts of Construction of ...

[1] Advance placing of the RCD concrete

When applying the conventional RCD method, placing is performed while ensuring mutual

integration of the external concrete and RCD concrete by complying with placing time

regulations, so external concrete and RCD concrete are repeatedly placed alternately. This

is a major factor causing a decline of the placing efficiency.

When applying the cruising RCD method on the other hand, prior placing of the RCD

concrete permits the external concrete and RCD concrete to be executed separately and

independently. This means it is not necessary to alternately place external concrete and

RCD concrete, maintaining high placing speed that takes full advantage of the equipment

capacity beginning immediately after the start of placing, and at the same time, improving

placing efficiency.

Photo 1 is a view of the cruising RCD method being executed by prior placing of the RCD

concrete.

Photo 1. View of cruising RCD construction method

[2] Later independent placing of external concrete

The external concrete is placed independently of the RCD concrete after it has been placed,

in small block units enclosed by upstream- or downstream-surface form, RCD concrete

and transverse joints (see Photo 2). And the placing joints between the external concrete

and RCD concrete do not, in practice, require placing time restrictions. For the above

reasons, the execution plan is extremely unrestricted, improving the efficiency of placing,

and at the same time sharply improving the safety of the execution.

[3] Omitting the cross-forms at placing ends of RCD concrete

When using the cruising RCD construction method, instead of using the placing method

performed by installing cross-forms at the transverse joint locations and placing slump

concrete at the edges of these forms, which is done using the conventional RCD method, a

placing stop execution method at any optional location is executed by generally forming an

end slope with gradient of 1:0.8 at the RCD concrete placing. This eliminates the need to

temporarily stop placing RCD concrete by installing cross-forms, and the complexity of

the execution accompanying the installation of cross-forms.

I - 34

Page 35: Study of Social and Economic Impacts of Construction of ...

The RCD concrete, whose placing was stopped at an optional location, is jointed to the

RCD concrete by carefully applying mortar to its placing joint surface.

Photo 2. View of Placing of External Concrete using the Cruising RCD Construction Method

3. BASIC TECHNOLOGIES FOR CRUSING RCD CONSTRUCTION METHOD

[1] Technology for advance placing of RCD (internal) concrete

End slope compaction technology

With the cruising RCD construction method, the RCD concrete is placed prior to the

external concrete, so that end slopes are formed at the outside edges of the RCD concrete.

These end slopes are formed with a slope gradient of 1:0.8, and compacted firmly by a

specialized machine so that its density is equal to that of the general part of RCD concrete

(see Photo 3).

Photo 3. Compacting end slope of RCD concrete

[2] Technology for independent and later placing of external concrete

Confirming integration of RCD concrete and external concrete

With the conventional RCD method, after advance placing of the external concrete, RCD

concrete is subsequently placed within 4 hours, and they are integrated by concrete

vibrators.

I - 35

Page 36: Study of Social and Economic Impacts of Construction of ...

In contrast, when executing the cruising RCD method, the external concrete is placed later

in small blocks enclosed by its end slopes, upstream- or downstream-form and transverse

joint panels with the end slopes of the previously placed RCD concrete already compacted

to firmly integrate the two kinds of concrete (see Photo 2).

[3] Technology for placing stop of RCD concrete without using cross-forms

Confirming integration with placing joints of RCD concrete by end slope compaction

With the cruising RCD construction method that does not use cross-forms, in some cases,

two blocks of RCD concrete are jointed with each other, but generally end slope formed at

a gradient of 1:0.8 (see Photo 4). When jointing RCD concrete placing at the end slope, the

careful application of mortar to the end surface of RCD concrete formed at a gradient of

1:0.8, is required.

Photo 4. Stopping placing with 1:08 end-slope in cruising RCD construction method

[4] Technology for continuous execution

Horizontal placing joint surface treatment technology for external concrete and RCD

concrete

To apply the cruising RCD construction method, it is necessary to start horizontal placing

joint surface treatment as soon as RCD concrete placement is finished, and at the same

time, improve treatment speed to keep pace with the rise of placing speed.

Because bleeding of the external concrete occurs after it is compacted, it is necessary to

perform placing joint surface treatment by a method that can effectively remove laitance.

When doing this while applying the cruising RCD construction method, it is necessary to

have a technology that permits good reliability and workability with curing time shorter

than that of past placing surface treatment and reliable treatment of the narrow spaces at

form edges and transverse joints. In past cases, treatment was done by pressurized water.

But bleeding of RCD concrete does not occur, so placing joint surface treatment is done by

a method that can reliably removing the concrete sludge leakage formed on the surface by

roller compaction done using a vibrating roller. It has been confirmed that before setting, it

is possible to perform appropriate placing joint surface treatment using the so-called “soft

treatment”, which is removal using water washing with an appropriate pressure (see Photo

5).

I - 36

Page 37: Study of Social and Economic Impacts of Construction of ...

Photo 5. Soft treatment for RCD concrete placing joint surface

Next, regarding the placing joint surface of the RCD concrete end compacted slope, unlike

horizontal placing joint surface compacted with a vibrating roller, this slope need not be

treated by water washing that is done on horizontal placing joint surfaces to prevent the

occurrence of concrete sludge leakage.

4. EFFECTS BY THE CRUSING RCD CONSTRUCTION METHOD

4.1 Faster placing speed

So the placing speed improvement effectiveness is analyzed based on the past application

of the cruising RCD construction method at the Yunishigawa Dam. At the Yunishigawa

Dam, the cruising RCD construction method was applied to build approximately

180,000m3 from EL.621m to EL.640m, and of this part, from EL.621m to EL.631m

(Range [2] in Fig. 2) was placed at 3 days per lift, and from EL.631m to EL.640m (Range

[3] in Fig. 2) was placed continuously at a rate faster than 3 days per lift.

Figure 2. Execution locations and categorization of construction method at Yunishigawa Dam

At the construction of the Yunishigawa Dam, the placing equipment with higher capacity

than that for previous RCD construction cases was prepared. Therefore, even conventional

RCD construction method achieved a high average placing speed of 142.7m3/h. But, the

average placing speed by the cruising RCD construction method executed at 3 days per lift

was 153.8m3/h, and was improved by about 7% over the average placing speed by the

conventional RCD construction method. In addition, by the application of the cruising

[1] Conventional RCD construction method

(placing in 3 blocks per lift)

[2] Cruising RCD construction method (placing at

3 days per lift)

[3] Cruising RCD construction method

(continuous placing faster than 3 days per lift)

I - 37

Page 38: Study of Social and Economic Impacts of Construction of ...

RCD construction method executed continuously faster than 3 days per lift, the average

placing speed was 155.7m3/h, and was improved by about 9% above the average placing

speed of the conventional RCD construction method.

In addition to increasing placing speed, the cruising RCD construction method shortens

interval periods. When using the conventional RCD construction method, when placing is

done with 1 lift divided into 3 sections, the period from completion of one section to the

start of placing of the next section is, based on past works, an interval of between 2 and 3

hours needed to move the materials and machinery, and three of these intervals occur for

each lift. At Yunishigawa Dam, there were 3 interval periods per lift, taking an average

total of about 6 hours.

But when using the cruising RCD construction method to perform continuous placing at a

rate faster than 3 days per lift, the execution was continuous without any division of the

lifts and placing continued as the machinery was moved, so no intervals were needed while

placing each lift. Only one interval was needed: that when the placing advanced to the next

lift. The interval period per lift was an average of 2.2 hours at the Yunishigawa Dam. This

means that the work period could be shortened by about 4 hours for each lift.

4.2 Raising speed improvement and work period shortening effect

Figure 3 shows monthly average raising speed of the RCD part of the Yunishigawa Dam

compared with those at other dams.

Figure 3. Relationship of RCD part height with RCD part average raising completion speed

This figure shows that the monthly average raising speed of the RCD part of the

Yunishigawa Dam constructed by the conventional RCD construction method was

6.0m/month due to the higher capacity of placing equipment, and was higher than that of

previous large-scale dams of 3.4m/month. Besides, when using the cruising RCD

construction method at the Yunishigawa Dam, the execution efficiency was improved

I - 38

Page 39: Study of Social and Economic Impacts of Construction of ...

largely, and construction monthly average raising speed of the RCD part of the

Yunishigawa Dam increased to 9.0m/month.

4.3 Improving workability

(1) Improving workability when temporarily stopping and resuming placing

[1] Improving workability in response to rainfall

Using the cruising RCD construction method, even when rainfall is predicted, it is possible

to stop placing RCD concrete at an end slope of 1:0.8 at an optional place at a location

which avoids the surrounding of transverse joints, permitting placing to continue until the

just before rain begins and leaving time needed for placing stop treatment. And after the

rain has fallen, execution can begin by applying mortar to the end slope, permitting quick

resumption of concrete placing. For this reason, it is possible to make on-site decisions to

temporarily stop and restart placing in hour units, permitting the minimization of stopping

placing work during a period when no rain will fall.

When using the conventional RCD method on the other hand, it is necessary to stop

placing by installing a transverse joint in response to a prediction of rainfall, so it is

impossible to continue placing until immediately before the rain starts, and even after the

rain has stopped, it takes time to revise the lane demarcation plan, so it is difficult to

quickly restart placing.

[2] Improving workability the day before a holiday

When executing work the day before a holiday, it is necessary that the placing plan should

also consider extending the work period in response to unpredictable events. In this case,

when using the cruising RCD construction method, it is possible to continue placing almost

up to the predicted time of completion, by considering the placing stop work time.

When using the conventional RCD construction method, the quantity executed tends to

shrink for the similar reason mentioned in [1].

[3] Response when execution is only possible for a short period

There are days during placing of the body of a dam when the number of hours placing can

be executed is shortened because of various circumstances. Using the conventional RCD

construction method, even when it is necessary to suspend placing on a specific day, for

the same reason cited in [1] and [2] above, using the cruising RCD construction method, it

is possible to place according to the time, so it is possible effectively use times when

placing is possible.

(2) Improving freedom of placing external concrete

When using the cruising RCD construction method, the external concrete is independently

placed in small block units enclosed by the RCD concrete which was placed earlier,

upstream- or downstream-surface form, and transverse joint panels installed at transverse

joints (see Photo 2).

I - 39

Page 40: Study of Social and Economic Impacts of Construction of ...

(3) Improving freedom of lane dividing for concrete placing

When using the conventional RCD construction method, there is a placing time restriction

stipulating less than 4 hours between placing adjoining slump concrete and RCD concrete.

In contrast, using the cruising RCD construction method, there are no placing time

restrictions between different kinds of concrete, so it is possible to relatively reduce the

quantity of slump concrete, which is executed slowly, boosting the overall execution speed.

(4) Improving workability of placing concrete in contact with rock foundation

Using the cruising RCD construction method, slump concrete including that in contact

with rock foundation is independently placed after other concrete, so after prior placing of

the RCD concrete, there are no restrictions on placing time period.

4.4 Improving execution safety

The work of placing RCD concrete and slump concrete is done by two teams: an RCD

concrete placing team and a slump concrete placing team.

Using the conventional RCD construction method, because RCD concrete and slump

concrete are executed at adjoining places, there are time periods when the two teams are

working at the same place. This means the ensuring safety of workers from the other

team’s heavy execution machinery is an important challenge.

In contrast, using the cruising RCD construction method, the RCD concrete and the slump

concrete placing locations are completely separated, eliminating working at the same place

as another team, greatly improving execution safety.

5. CONCLUSIONS AND FUTURE PLANS

Japan has developed the cruising RCD construction method, as a concrete dam

construction method that can speed up execution by placing RCD concrete prior to the

external concrete and at the same time, stopping placing of the RCD concrete without

using cross-forms. This construction method is a technology established by verifying its

applicability while executing it at actual dams, that is, the Kasegawa Dam (Kyushu

Regional Development Bureau, MLIT) and the Yunishigawa Dam (Kanto Regional

Development Bureau, MLIT), and it has already been summarized in the “Engineering

Manual for Cruising RCD Construction Method” (published in June 2010 and revised in

February 2012) [JDEC, 2010 & JDEC, 2012]. Its application is expanding, as it is now

adopted as the dam body construction method for two new dams.

This paper outlines this construction method and introduces the basic technologies which

achieved this construction method and, based on actual applications, demonstrates its

effectiveness.

In the future, we must introduce new innovations to further rationalize the construction

method. Examples of challenges that must now be faced include improving workability of

end slopes, further speeding up placing and placing completion by continuous execution of

two lifts as an advance of the 1 lift continuous execution method, and applying the cruising

I - 40

Page 41: Study of Social and Economic Impacts of Construction of ...

RCD construction method from river beds through upper elevations, including the lifts

installed to build a structure.

REFERENCES

Japan Dam Engineering Center (2010): Engineering Manual for Cruising RCD

Construction Method, (in Japanese), Japan Dam Engineering Center, Tokyo, Japan

Japan Dam Engineering Center (2012): Revised Engineering Manual for Cruising RCD

Construction Method, (in Japanese), Japan Dam Engineering Center, Tokyo, Japan

I - 41

Page 42: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Public participation, Human Security and

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj Public Safety around Dams in Sweden:

A case study of the regulated Ume and Lule Rivers

Dr. M-B Öhman

Technoscience, Centre for Gender Research, Uppsala University

[email protected]

M. Palo Technoscience, Centre for Gender Research, Uppsala University, Sweden

Dr. E-L Thunqvist Centre for Health and Buildings, Royal Institute of Technology, Stockholm, Sweden

ABSTRACT: This paper presents findings of an empirical study of the current situation with geographical focus

on two rivers in the north of Sweden, the indigenous territory Sápmi.The major focus in Sweden

within “dam safety” is on the prevention of dam failure, and emergency preparedness. The issue of

“public safety around dams” is left aside to the detriment of “human security”. While a major dam

failure may cause the death of hundreds up to thousands of people, the current rate of human

deaths caused by dam failure the last 40 years is one person. The number of fatalities that may be

referred to as “public safety around dams” on the Lule River only amounts to 1-2 persons per

year. The risks and dangers involved also cause stress, anxiety, and difficulties on an everyday

basis for residents along the regulated rivers and water courses. From a study of literature,

available statistics, interviews and newspaper reports we discuss the accidents and incidents over

the last decade (2002-12), how these may be defined as “public safety around dams”, the void of

work to prevent such accidents and how the surrounding societal contexts play in, such as the lack

of availability to fast and efficient emergency rescue services to be able to save lives.

Finally, we also discuss the current void of public participation and make recommendations to

enhance public participation and thereby possibilities to an enhanced public safety around dams in

Sweden. The research is funded by Swedish research councils VR and FORMAS.

Keywords: Public Safety, Sweden, Sápmi, Human Security

1. PUBLIC PARTICIPATION, HUMAN SECURITY AND PUBLIC SAFETY

1.1.Summary of findings

This paper presents part of the findings of an empirical study of the current situation in

regard to Public Safety around dams in Sweden. The geographical focus is on the Ume and

Lule Rivers, in the northern part of Sweden.

The empirical study is mainly qualitative with interviews, participatory observations and

literature studies. The studies have been made as part of three different research projects,

from June 2008 and is still ongoing. In terms of resources, we have due to limited funding,

I - 42

Page 43: Study of Social and Economic Impacts of Construction of ...

not been able to do the study to the extent that we would have wished for. Also the limited

understanding of “public safety around dams” where the majority of actors involved

(police, local authorities, rescues services, regional authorities, power companies/dam

owners) do not address the issue in any coordinated way, means that much of the time has

had to be spent at finding out if at all work is being done in this sector.

We have come to the conclusion that in Sweden the issue of ”Public Safety around dams

and reservoirs” is currently more or less a non-issue. As an example, the latest state inquiry

(SOU 2012) does not discuss public safety around dams at all. The same goes for several

earlier studies (Idenfors et al 2012). For instance drowning accidents which take place on

hydropower reservoirs are not necessarily categorized as dam safety – public safety around

dam issues. Furthermore a number of other, apart from drowning, accidents and incidents

caused by the regulation of the rivers, are not considered as part of the dam safety

discourse (Idenfors et al. 2012).

We find that despite a quite strong legislation (SFS 2003:778) that holds the dam owner

responsible for the safety of the public, as well has holding the local authorities responsible

for making sure that the dam owners fulfill their responsibilities, public safety around dams

is to a large extent neglected. We argue that this an important problem that needs to be

resolved, in particular as the number of deaths on regulated rivers is relatively high and

because the worry, anxiety and distress that the public is subject to due to the dangers on

and around the regulated rivers. We argue that the concept of “human security” (UNDP

1994) should be used to discuss and resolve the situation.

The problems are located on several levels, ranging from responsibilities of the dam

owners and local/regional authorities as well as support to the public for them to be able to

avoid the dangers. We have amongst other identified a void of statistics as grounds for

analyzing accidents and incidents; lack of information on and support for legal instruments

to enter court processes to determine legal liabilities related to actual accidents and

incidents; lack of information to the public to avoid getting hurt; lack of fast access to

rescue services and also lack of local action plans to reduce the number of incidents and

accidents.

Finally, in regard to being able to advance the situation, we have identified a void of public

participation. So far little to no work is taking place from the local authorities or dam

owners to involve the public in addressing the issues around Public Safety around dams.

(Idenfors et al 2012, Palo 2013) We argue that involving the public is an important task as

people reside, live, work and have their leisure time along the regulated rivers. In short, the

people were there before the regulation took place, and the rivers became industrialised

(Jakobsson 1996; Öhman 2007; Össbo 2013) - regulated, and thus dangerous industrial

areas and this needs to be addressed in regard to the issue of “Public Safety around dams”. ]

2. REGULATED RIVERS AND THE PUBLIC IN SWEDEN [Blank line 10 pt]

2.1. Hydropower regulation, production and location of dams in Sweden [Blank line 10 pt]

There are about 10 000 dams in Sweden. Of these there are approximately 2000

hydropower plants and dams. Out of these 190 dams are so called large dams, according to

the international definition, with dam walls measuring at least 15 meters from foundation

to crest. Hydropower stands for approximately 50% of the entire power production within

Sweden. The majority of the hydropower dams were constructed between 1950s and the

1970s. (SOU 2012:46; RiR 2007:9)

I - 43

Page 44: Study of Social and Economic Impacts of Construction of ...

The majority of the large dams and regulated water courses are located in the northern part

of Sweden, known as “Norrland” and also “Sápmi” – the traditional core area of the

indigenous people Sámi, which is also reindeer grazing lands. Sweden has about 9,5

million inhabitants. Norrland - Sápmi has about 1,1 million residents (SCB Befolkning

2014).There are a great number of tourists coming in to these areas throughout the whole

year. For instance Norrbotten, the northern most county, topped the statistics with of a

quarter of a million foreign guest nights during July 2013 (SCB Gästnätter 2014). How

these tourists interact or not with regulated rivers is difficult to estimate as there is

currently no such specific statistics available.

By all these regulated rivers – and thus regulation reservoirs or just downstream of

hydropower plants, as well as dry beds due to regulation, there are homes, industries and

infrastructure close by. Many people reside, work, or visit as tourists during all seasons of

the year. Reindeer herders have to cross the regulated rivers to take care of their reindeer.

Other locals do leisure or professional fishing, sports, bathe, sun bathe, drive snow mobile

in winter or go out by boat in summer. We have not been able to estimate the number of

people who are on the regulated reservoirs at each given moment, as there is no such

statistics available. However, the number is likely to be high, as the regulated rivers were

and are as important for transports and all other activities as they were before regulation

took place.

2.2 Human security

The concept of human security was popularized through the United Nations Development

Programme’s 1994, Human Development Report (UNDP, 1994). Traditional security

policies are designed to promote demands ascribed to the state, and other interests are most

often considered subordinated to those. We therefore depart from the human security

concept which focuses on people and the protection of individuals. The original meanings

of security : “security—from the Latin securitas—refers to tranquility and freedom from

care, or what Cicero termed the absence of anxiety upon which the fulfilled life depends”

(Liotta and Owen 2006) . Security is relevant to feelings of safety and stability, routines, or

rather, security of expectations, whereby we can count on certain things for our future, that

which we most value, upon which we can build capacity (Hoogensen 2005, Wibben 2010)

2.2. The Lule River – Julevädno – and the Ume River - Ubmejeiednuo

The geographical focus of the empirical study is on the Ume and Lule Rivers, in the two

northern most counties, Västerbotten and Norrbotten.

The Lule river – in Sámi language “Julevädno” - measures 461 kilometers from mountain

regulated source lakes to the coast and is dammed with 15 hydropower plants. The Lule

River produces around 10 per cent of the totality of electricity produced within Sweden –

or 13-16 TWh per year. In 2012, 16, 4 Twh was produced, which corresponds to ten per

cent of the totality of power production and 21 per cent of the hydropower produced (78,0

TWh) within the Swedish borders (Svensk energi 2013). All dams and power plants on

the Lule River are owned and run by the Swedish state owned power company Vattenfall.

Regulations started in 1910, and peaked during the 1950s-1970s.

There are around 100 000 inhabitants residing in the municipalities located along the Lule

river from the mountain to the coasts. The majority of these (around 75 000 inhabitants) do

not reside permanently near the reservoirs, but downstream of the last of the 15

dams/hydropower plants (Boden) in the municipality of Luleå. However, many of the

inhabitants of Luleå travel up towards the mountain areas for both work and leasure.

I - 44

Page 45: Study of Social and Economic Impacts of Construction of ...

Furthermore, this is a river with the majority of reindeer herding enterprises in Sweden.

Along the Lule river there are 224 registered reindeer herding companies, and a maximum

of 40 800 reindeer in the winter herd (Sametinget 2014).

The Ume river – Ubmejeiednuo in Sámi language - measures 470 kilometers from

mountain regulated source lakes to the delta at the coast and is dammed with 21

dams/hydropower plants. During 2012 the Ume river produced 9,4 TWh, or 8,3 per cent of

the totality of hydropower production and five per cent of the totality of power

production,162,0 TWh (Idenfors et al. 2012; Svensk Energi 2013). In the whole of the

Ume river valley there is approximately 150 000 inhabitants within six municipalities

(SCB 2010). Furthermore there are 53 reindeer herding companies, within three “sameby”

and a maximum allowed of 24 300 reindeer (Sametinget 2014).

The dams/hydropower plants along the Ume River are owned by four different companies;

the Swedish state owned Vattenfall, the Norwegian state owned Statkraft, the private

owned companies Eon and Vattenregleringsföretagen, jointly owned by the different

power producers in the rivers ( Länsstyrelsen Västerbotten, 2011).

3. TYPE OF ACCIDENTS AND INCIDENTS – LACK OF STATISTICS BLANK LINE

3.1. Identifying a void of official statistics on accidents related to public safety BLANK LINE

Within our empirical study a lot of effort has been devoted to find if there is official

statistics available to easily identify accidents and incidents which can be considered as

“public safety around dams” related. The result of the investigation shows that there is

currently no such data available and there is currently no ongoing effort to collect such

data.The power companies do not keep such records, nor do the local rescue services

(Idenfors et al 2012; Palo 2013).

There is a national database available on drowning accidents – fatalities. But within this

database lake is equated to regulated reservoir (MSB 2014). Thus one has to identify the

accident by geographical location and then find out if the location is on a reservoir or on an

unregulated river/water course. Furthermore, to be able to establish whether it was an

accident caused by the regulation – for instance more release of water causing the ice to

crack up faster in combination with increasing temperature (Öberg 2009) – there is much

more information needed than what is currently available.

For other information regarding the circumstances to be able to identify to what extent the

power company could have prevented the accident, information is needed from the local

rescue services or the police. When asking for such information from the different local

rescue services, it turned out that at some cases we could get good help while in other cases

we did not receive help within the time limit of the empirical study (Idenfors 2013; Palo

2013).

To the question if it possible to receive statistics regarding accidents on or nearby a

reservoir the answers were from local rescue services by the Lule River:

Jokkmokk municipality: ”I can not provide you with such statistics, it might be better if

you contact Vattenfall regarding this issue” (Ström 2013).

Boden municipality rescue services responded: ”Our system unfortunately has deficiencies

in its search functions. Therefore it takes very much working time to go through the data

base which I do not have the time for at this point”(Lindvall, 2013). The Gällivare municipality rescue manager stated that he had no information whether there

is any specific statistic available on accident near to dams. He also stated that he had no

I - 45

Page 46: Study of Social and Economic Impacts of Construction of ...

information regarding what statistical system that is used in Gällivare for such reporting

(Sonesson 2013).

We also contacted the police authorities of the Norrbotten County, to get more information

on the accidents on the Lule River. We were provided a number of accident reports from

2004 until 2012. However, the details in these reports were not exact enough to be able to

define whether the regulation was the cause of the accident or not (Palo 2013).

As many accidents in winter are related to snow mobile transportations – for work or

leisure – we contacted the Non-Governmental organization (NGO) SNOFED, the Swedish

Snowmobiles owner national association, where one part of the tasks is work with

information to avoid accidents. The response regarding statistics on accidents on regulated

water courses was: “the exact geographical position is not information that we receive, or

we have difficulties to verify. […]When and if we get exact position data we cannot enter

this into our data base other than as place or lake names. We invest the time we have

possibility to in this registration, and more deeper analysis would request more staff

resources than what we have today. Also we do not have the possibility to access details

today. It is only a small part of our and my work time that is dedicated to this task”

(Persson 2013)

For the Ume River, the situation is equal to that of the Lule River. Information on

accidents and incidents are difficult to access and there is no specific data base available

for “public safety around dams” accidents and incidents at any official level. Nor are there

any records kept by power companies/dam owners (Idenfors 2013; Palo 2013).

3.2. Types of accidents and incidents

Within the research project, despite not being able to receive official relevant statistics, the

interviews and requests for information have provided a certain, although not full,

understanding of the situation. We have interviewed both rescue services and also people

living and working along the rivers.

According to the local rescue services the number of fatalities that may be referred to as

“public safety around dams” on the Lule River only amounts to 1-2 persons per year.

(Lundström 2010; Nilsson 2013). On the Ume River and regulated river courses adjacent

to the Ume River the number of drowning or incidents – with injuries or no injuries -

amounted to ten during the period of 2002 to 2013 (Backman 2013; Asp 2013).

Secondly, there are other types of accidents that fall out of the category of drowning. For

instance, the danger in winter time is to fall into holes in the ice. One may not drown, but if

one does not get help within a short period of time, one is likely to die out of hypothermia

within very short time, depending on location and actual air temperature. This is in

particular a problem for reindeer herders who work a lot on their own and thus can be

subject to accidents without anyone being informed.

One of our informants speaks of such an accident, by a regulated water course adjacent to

the Lule River. The accident occurred around 2005-2006:

“A man froze to death here. They went into the water with their snow mobiles. I don’t

know how wet he got, but he never made it to the cabin. His friend made it to the cabin and

survived.” (Pittsa, 2011).

I - 46

Page 47: Study of Social and Economic Impacts of Construction of ...

The informant continues stating regarding the ice situation in the area that ”it is very bad

ice here. The whole of this stretch is really bad ice, the whole of this stretch is river course.

[…] it might be considered a ‘snow mobile accident’ but I am not so sure the accident

would have happened if it was not regulated. The stream would not be the way it is

[without the regulation] (Pittsa, 2011).

Participatory observations – field studies and interviews provides a number of other types

of accidents, incidents and also risks that can be categorized as “public safety around

dams”. Below are some examples of accidents, incidents and risks identified through

interviews and participatory observations –field studies:

- Cracks in the ice that can cause snow mobile accidents, broken limbs for both humans and

animals, and also become traps for children and animals (:

One woman having a residence by the Suorva reservoir – Lule River - tells how she

managed to save her two year old daughter from slipping into such a crack at the last

second ( Harnesk 2009). Öhman herself when walking on the ice-track at Suorva reservoir

happened to step into a crack covered with snow and fell. (Öhman 2009). Accidents of this

type was reported also by the security co-ordinator of Storuman Municipality – Ume River

(Sundqvist 2013).

- The regulated reservoirs becomes large inland seas, in the mountain areas. As people need

to travel on these lakes, to and from their residences, they need big boats which become

difficult to handle at the eroded shores, especially when one is alone and especially for

older people. (Öhman 2008, 2009, 2010).

- In the mountain areas, storms can come very suddenly, and as the shores are heavily

eroded at the Suorva reservoir, it can become impossible to land the boat and get into

safety (Harnesk 2009).

- Erosion caused by the regulation causes holes in the bottom. An older woman told how she

stepped into such a hole when getting out of her boat and thereby getting injured

(Nordqvist 2009).

- The four regulations of the Suorva reservoir has forced people to move up on the hillsides

at Änonjalme and Vaisaluokta. Combined with the regulation amplitude makes it difficult

to access the houses from the boats, or snow mobiles in winter when the snow is not good

enough to get close to the houses. It is especially difficult for older people and people with

disabilities and when carrying baggage. Also for tourists there are reports of problems

when the elevators do not function properly. (Öhman 2008, 2009; Palo 2013).

Figure 1: The hole in the ice created by water release from the Ritsem power station, Suorva

reservoir, Lule River. Two men died as they went through the ice near this hole, May 2008.

I - 47

Page 48: Study of Social and Economic Impacts of Construction of ...

4. ACTORS, RESPONSIBILITIES AND VOID OF PUBLIC PARTICIPATION

4.1 Strong legislation but weak enforcement of laws blank

The dam owners along Ume and Lule Rivers do work with certain preventive measures,

although it is to a quite small extent. For instance, the state power company Vattenfall

provides for the maintenance of ice roads at two locations on the Lule River, at Ritsem –

Änonjalme, and at Saltoluokta (Palo 2013). However Vattenfall does leave the most of the

responsibility with the individuals, which are more or less considered to be out on the ice

or the waters of the reservoirs at their own risk (Palo 2013). Also the ice roads are closed

by the end of April – beginning of May each year, which is the time when the reindeer

herders come with the reindeer, and the local Sámi residents starts coming into the area for

the summer residence (Öhman 2008,2009,2010).

The work with “public safety around dams” is not defined at all in most of the

municipalities which we have contacted. It seems overall as a concept that is not discussed

or analyzed at all. However, during the interviews that were made by telephone many of

the informants started thinking around the concept, and agreed that it is an important issue

that is far too neglected. A response was that there is certainly room for more work in this

regard (Idenfors 2013; Palo 2013). In regard to the existing legislation the informants at the

rescue services of the municipalities claim that the legislation regarding public safety is

potentially very strong. However, several of them stated that the legislation is not enforced

to the extent which it potentially could be and that there seems to be a void of actually

prosecuting dam owners when accidents and incidents regarding public safety around dams

occur (Idenfors 2013; Palo 2013).

Also, the responsibilities of the municipalities to work with prevention against such

accidents is according to the interviews not something that is spent time or efforts on by

the municipalities along the Ume River (Tapani 2013;Wiklund 2013; Jonsson 2013) and to

a very little extent along the Lule River (Nilsson 2013).

According the “law on protection against accidents” (2003:778) the responsibilities are

quite clear. According to this law the dam owners are responsible to both warn and either

keep or finance emergency preparedness including staff, property as well as other

measures to hinder or limit damages and accidents. Furthermore, the dam owner is

responsible to analyze all serious risks for accidents that may be a threat to person’s life or

health (SFS 2003:778 §2:4). Apart from the dam owner, also the local authorities – the

municipality – is responsible to work with accident prevention, as well as through advice,

information and by other means ensure that dam owners to comply to their responsibilities

according to the law LSO (2003:778 §3:2). The municipality is furthermore required to

have an action plan of preventive actions, within which the organization of such acitivies

should be defined. This action plan is to be renewed for each electoral period, that is every

four years (2003:778 §3:3). Also the state has according to this law certain responsibilities.

In the mountain areas the state should delegate to specific rescue services to assist and

rescue those that have had an accident (or a disease) and who needs a rapid medical care or

other assistance (2003:778 §4:1). blank

4.2 Lack of available rescue services as cause of unnecessary fatalities blank

Despite that the legislation is very far stretching regarding what has to be done to prevent

accidents and actually places are large responsibility with the dam owner, as well as with

I - 48

Page 49: Study of Social and Economic Impacts of Construction of ...

the local and state authorities, our study indicates that this legislation is currently far from

enforced. For instance, one problem is the time for rescue services to be able to assist.

Interviews with the rescue service in Jokkmokk, where the number of fatal accidents –

drowning – on the regulated rivers amounts to 1-2 per years, indicates that although that

the rescue services can be ready to assist anyone in danger within five minutes – the

distances are long and there is a need of helicopters. The local rescue services however,

does not have access to any rescue helicopter, which is the responsibility of the mountain

rescue service (Lundström 2010).

For instance, despite the legislation, the State power company Vattenfall does not finance

any helicopters stationed by the Suorva reservoir to support rescue operations. There are no

other available resources by the reservoir that can be operated by people who are

witnessing an accident. One accident on the Suorva reservoir in 2008 where two men went

down a hole in the ice on the snow mobile had several witnesses, not far away from the

accident location. (See Fig 1), But due to the condition of the ice, no one could reach them

in time to save their lives. The ambulance helicopter, stationed by the closest helicopter in

Gällivare, which arrived on site after 32 minutes, was not equipped for life saving

operations. The helicopter staff could not even take care of the bodies of the men

themselves, but had to be assisted by some people on site (Pittsa 2011). This may be

compared to another occasion, in Porjus, 2009, when three men went into a hole in the ice.

Due the private helicopter station in Porjus, where there were people available two of the

men could be rescued (Pittsa 2011). Thus the access to fast rescue is obviously the

difference between death and survival in these situations.

So far in our study, we have not been able to follow up if in any of the fatal accidents there

has been any legal consequences for the dam owners or the local authorites/rescue services.

4.3 Void of public participation in the understanding of public safety around dams

The interviews made within the study indicates that first of all there is a lack of discussion

of what “public safety around dams” should be defined as, and secondly that there is

currently little or no work to change this situation. The majority of the informants

responded that issues of dam safety – in particular the issue of “emergency preparedness”

is discussed to a large extent within a specific setting named “River groups” (Älvgrupper)

involving different local and regional authorities as well as the dam owners (Idenfors et al

2012). One informant stated that sometimes issues of what can be defined as “public safety

around dams” is discussed, but to a very limited extent (Tapani 2013).

These River Groups seems to be a potential way for highlighting the issues of public safety

around dams, although at this moment they do not involve professional groups such as

reindeer herders or professional fishermen/women (Tapani 2013).

Within our empirical study we have found that there is a wide knowledge and

understanding among communities as well as individuals that could be made use of to

enhance the safety for the public around the existing dams, but that this knowledge and

understanding is today not considered of importance. Another explanation may be that the

issue of public safety around dams has not been invested in, and thus the need for

understanding the problems, risks, and worries of the public, has not been dealt with. Some

of the explanation may reside within that the hydropower exploitation era, the

overwhelming focus was on power production, and that all other uses of the river and

water courses were more or less completely neglected (Jakobsson 1996; Öhman 2007;

Össbo 2013). BLANK

I - 49

Page 50: Study of Social and Economic Impacts of Construction of ...

5. CONCLUSION AND RECOMMENDATIONS

Our study clearly indicates a large need to direct focus towards Public Safety around dams

in Sweden. There are a great number of accidents, incidents and also perceived risks and

threats in regard to the regulated rivers. The current lack of attention to the issue means a

continued distress and anxiety for the local inhabitants along the rivers, as well as visiting

tourists. Thus an obvious recommendation based on the findings is to immediately invest

into further studies and actual work to enhance public safety around dams, involving the

public from all parts of society, taking into account the different age groups, gender,

ethnicities, language, disabilities, professional groups and the indigenous Sámi and other

local inhabitants cultural and traditional relationships to the rivers.

ACKNOWLEDGEMENTS

The research was/is funded by the research projects “Situated perspectives on hydropower

exploitation in Sápmi: Swedish technological expansion in the 20th century and its impacts

on indigenous peoples” (Swedish Resaerch Council, VR, 2009-2010); “DAMMED:

Security, Risk and Resilience around the Dams in Sub Arctica (Swedish Research Council,

VR, 2010-12) and “Rivers, resistance, resilience: sustainable futures in Sápmi and other

indigenous peoples’ territories” (FORMAS, 2013-16) All research projects are led by Dr.

Öhman.

REFERENCES [Blank line 9 pt]

Interviews and email exchanges:

Asp, M. (2013), MSB- Swedish Civil Contingencies Authorities, Email June 10.

Backman, G. (2013) Emergency preparedness coordinator (Beredskapssamordnare)

Storuman Municipality (Ume River), Telephone interview, June 2013.

Harnesk, V. (2009), Resident of the Suorva reservoir, Personal interview, April 2009.

Jonsson, G. (2013), Fire inspector, Lycksele Municipality. Email May 27.

Lindvall, T. (2013), Security coordinator, Boden Municipality, Email March 21.

Lundström, G. (2010), Security coordinator, Jokkmokk Municipality, Personal Interview,

Oct., 2010.

Nilsson, B. (2013), Security manager (Räddningschef), Jokkmokk and Boden

Municipalities, March 2013.

Nordqvist, S. (2009), Resident of Maksjonjalme. Personal Interview.

Persson, P. (2013), SNOFED, Email March 27.

Pittsa, B-E (2011), reindeer herder and consultant for Vattenfall ice tracks at Suorva dam.

Personal Interview, April 2011.

Sonesson, K. 2013) Rescue services manager (Räddningschef), Gällivare Municipality,

telephone interview 07-05-2013.

Ström, N. (2013) Security coordinator, Jokkmokk Municipality, Email March 19.

Sundqvist, L-E. (2013), Security co-ordinator. Storuman Municipality, June 2013.

Tapani, L. (2013), Fire brigade manager, Umeå Municipality. Email May 31.

Wiklund, E.( 2013) Emergency preparedness coordinator, Vännäs Muni., Email June 3.

Öberg, B. (2009), Resident of Björkudden and responsible for maintenance of ice track.

Personal Interview.

I - 50

Page 51: Study of Social and Economic Impacts of Construction of ...

Field studies - participatory observations- notes from empirical study

Idenfors, A. (2013) Unpublished notes from empirical study on public safety around dams,

Ume River. May to June 2013.

Palo, M. (2013) Unpublished notes from empirical study on public safety around dams, the

Lule River, March to August, 2013)

Öhman, M-B (2008; 2009;2010) The Suorva reservoir – notes from field studies and

participatory observations.

Literature:

Hoogensen, G. (2005) Gender, Identity, and Human Security: the case of women

terrorists. Canadian Foreign Policy. 12(1):119-140.

Idenfors, A.; Sandström, C; Öhman, M-B; Hanberger, A; Thunqvist, E-L, (2012) När det

brister: En studie av dammsäkerhet och säkerhetsarbete mot översvämningar längs

Skellefte och Umeälven, Umeå universitet, Umeå

Jakobsson, E. (1996) Industrialisering av älvar: studier kring svensk vattenkraftutbyggnad

1900-1918. Doctoral Dissertation. Göteborg Universitet, Göteborg.

Länsstyrelsen Västerbotten (2011). Risk- och sårbarhetsanalys för Västerbottens län 2011, Länsstyrelsen Västerbotten, Livsmiljöenheten, Umeå

Liotta, P. H. and Taylor Owen (2006). "Sense and Symbolism: Europe Takes on Human

Security." Parameters Autumn 2006: 87.

MSB (2014), IDA MSB:s statistik och analysverktyg - Döda till följd av skador 1972-2012,

Dödsorsaksregistret (DOR) (Swedish Civil Contingencies Authorities statistic &

analysis tool.) [http://ida.msb.se/ida2#page=a0145] acc. March 10, 2014.

Riksrevisionen (2007). Säkerheten vid vattenkraftdammar, Riksrevisionen RiR 2007:9,

Riksdagstryckeriet, Stockholm

Sametinget (2014) Rennäringens markanvändning , Sametinget, Giron/Kiruna.

http://sametinget.se/8382 acc. 09-03-2014

SCB Folkmängd (2014) Folkmängd i riket, län och kommuner efter kön och ålder 31

december 2013 (Population statistics in Sweden, per Dec 2013) http://www.scb.se/

(acc. 03-10-2014)

SCB Gästnätter (2014), (Statistics guest nights data base) Gästnätter för samtliga hotell,

stugbyar, vandrarhem, campingar, förmedlade privata stugor och lägenheter efter

region. Prel. statistik. 2008M01 - 2014M01 [www.scb.se] (acc. 03-10-2014)

SCB (2010). Folkmängd i riket, län och kommuner 31 december 2010 och

befolkningsförändringar 2010. [www.scb.se]

SFS 2003:778 Lag om skydd mot olyckor (Law about protection against accidents)

http://www.notisum.se/rnp/sls/lag/20030778.htm , acc. 20140309)

SOU 2012:46. Utredningen om översyn av de statliga insatserna för dammsäkerhet.

Dammsäkerhet - Tydliga regler och effektiv tillsyn: betänkande. Fritze, Stockholm

Svensk Energi (2013) Elåret 2012, Svensk Energi – Swedenergy – AB, Stockholm

United Nations Development Programme (UNDP) (1994). Human Development Report,

UNDP, New York

Wibben, A (2010), Feminist Security Studies: A Narrative Approach, Routledge: New

York

Öhman, M-B. (2007) Taming Exotic Beauties: Swedish Hydropower Constructions in

Tanzania in the era of Development Assistance, 1960s-90s. Diss. KTH: Stockholm.

Össbo, Å. (2013) Nya vatten, dunkla speglingar: Industriell kolonialism genom svensk

vattenkraftutbyggnad i renskötselområdet 1910-1968. Diss. Umeå Univ.:Umeå

I - 51

Page 52: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Roadmap of pre-investment process for a hydropower project.

.hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj Case study Tarnita-Lapustesti pump-storage hydropower plant.

2(14pt)

Ph. D. Eng. Irinel Daniela Iacob Hidroelectrica SA,Bucharest, Romania

[email protected]

ABSTRACT Building a high power hydro plant with accumulation through pumping is an old interest of the

specialists within the romanian national energy system.

The location of the project is Somesul Cald River, Cluj County. Hydropower parameters are:

maximum installed capacity 1000 MW; hydro-mechanic equipment motor-generator reversible

units (no. of units: 4 pieces x 250 MW); pumping cycle: weekly; quantity of energy generated in

generator mode: 1,625 GWh/year; quantity of energy generated in pumping mode: 2,132

GWh/year; transformation coefficient: 0.76.Investment cost on 1.01.2009 is 1,029 million euro

(VAT exclusive).

This material aims to present the roadmap of national interest project Tarnita-Lapustesti PSHPP

(pump-storage hydropower plant), pre-investment process :

• strategic environmental assessment (SEA) procedure;

• environmental impact assessment (EIA) procedure;

• public consultations held ,public acceptance of the project;

• land acquisition and resettlement;

• historical monuments assessment procedure .

Keywords: pump-storage hydropower plant

I. A BRIEF HISTORY OF THE PROJECT

Building a large pumped storage hydropower plant became a need ever since the year

1975.

More localtions on the territory of our country have been inspected during the period of

1975 – 1985, and about 17 locations were considered fit for building a pumped storage

power plant.

During the period of 1985 – 1988 the option became clear and the hydrographic basin of

the Somesul Cald River was chosen, as the existent Tarnita Reservoir could accomplish the

role of a lower reservoir. Such a location is most valuable since it is placed close to an

important consumption center – Cluj Napoca industrial area.

I - 52

Page 53: Study of Social and Economic Impacts of Construction of ...

Figure 1. The hydrographic basin of the Somes River.

Throughout the period that followed, various study reports evaluating the conditions of

carrying out the Tarnita-Lapustesti PSHPP have been drawn up. Such study reports were

written by some prestigious design and consultancy institutions such as: the Institute of

Hydroelectric Studies and Designs (ISPH), the Institute of Energy Studies and Research

(ISCE), Electric Power Development Co. (E.P.D.C.) from Japan, following to a grant

awarded by the Japenese government, the IPA/Verbund/Poyry Consultant within the

SEEREM program of the World Bank in 2005 – financed by IBRD.

As soon as the study reports were done, two equipping scenarios were primarily outlined:

the scenario with the plant equipped with four reversible hydro-aggregates, with the

turbine – pump having each the capacity of 250 MW, and the scenario with the plant

erquipped with three reversible hydro-aggregates having each 330 MW.

These study reports were written considering the power equipment offers from behalf of

some famous companies such as: Ansaldo GIE from Italy, Toshiba – Japan, Alsthom –

Neyopic from France, Hitachi and Mitsubishi from Japan, etc., a good estimation of cost

and efficiency was therefore provided.

All the study reports highlighted the strategic importance of commissioning the Tarnita-

Lapustesti PSHPP for the National Energy System (SEN) to run under safe conditions for:

Re-commissioning the SEN (black out);

Providing the frequency-power regulation;

Providing the rapid tertiary reserve;

Providing the short-run breakdown reserve;

Providing reactive power, running in compensatory mode with respecting the

quality standards of electric energy;

Providing the optimal conditions for developing the wind and nuclear power

generation sectors;

I - 53

Page 54: Study of Social and Economic Impacts of Construction of ...

Enhancing the running mode of the large units in Cernavoda NPP and of the

fossil and co-generation condensation thermal power plants (the power

generation on the condensation tail is thus avoided) by transferring electric

energy from idle to peak;

Improving SEN’s participation in the sole energy market, and increasing the

SEN’s global safety, and making possible the SEN’s running in higher technical

and cost-effective conditions;

Inter-connection exchange within UCTE;

Cutting off the utilization of the pretious fossil fuel resources,

besides the strengths we detailed above, we also add the fact that the project will use clean

and renewable energy resources.

II. TARNITA-LAPUSTESTI PROJECT GENERAL DATA

II. 1. Construction characteristics

The principal construction parts of the Tarnita-Lapustesti PSHPP are:

The Upper Reservoir (Lapustesti Storage) has a volume of 10 mil. cubic meters, is located

on Lapustesti plateau at an elevation of 1070.00 m.a.s.l., and will be erected by digging

and dyking, having in mind the principle that the volume of digs should be equal to the

volume of fills from the dykes.

The Lower Reservoir (Tarnita Storage) is an existent objective, has an efficient volume of

15 mil.cubic meters, is located on the Somesul Cald River at the thalweg elevation of

441.00 m.a.s.l., is accomplished by the Tarnita Dam (double arch reinforced concrete),

and has a normal top water level of 521.50 m.a.s.l. and a minimum operation level of

514.00 m.a.s.l.

Figure 2. Tarnita dam

The cavern, which shelters the electro-mechanic equipment, is an underground building

placed in the left slope of the Tarnita Storage, in the area of Somesul Cald – Valea

Farcasului. The cavern is made by the machine hall cavern and the transformers cavern and

I - 54

Page 55: Study of Social and Economic Impacts of Construction of ...

has some access tunnels and connection tunnels between them, suction galleries, gates

inspection shafts, cable tunnel, and operational personnel’s access.

The inter-basin diversions, which are the hydraulic transportation works between the upper

reservoir and the undergound plant, and the underground plant and the lower reservoir, are

made of the following galleries :

- The high pressure gallery, an underground construction, inclined to 45°

between the upper reservoir and the underground plant. Length L = 1096 m;

Diameter Ø = 6.00 m.

- Two low pressure galleries, underground constructions, almost horizontal,

for discharging the turbined water and sucking the water pumped between

the plant building and the lower reservoir. Dimensions: Length: 2 wires x

1,325. Diameter Ø = 6.20 m.

Electro-mechanic equipment is made of reversible units (pump and turbine mode, with a

capacity of 4 x 250 MW) and its related installations of control, automation, and

connection to the National Energy System (SEN).

Figure 2. Tarnita-Lapustesti PSHPP Development Scheme.

This location benefits from some natural conditions that are favourable to such a

development. The lower reservoir is the existent Tarnita storage lake itself, meanwhile

there is a plateau on the Laupstesti hill placed on the left slope at the elevation of 1070

m.a.s.l., which allows the erection of the upper reservoir. The level difference is 560 m and

the Hmax/Hmin ratio is of maximum 1/1. It is a weekly regulation storage with a volume of

about 10 mil.cubic meters and an inslalled capacity of about 1,000 MW. The diversion has

a H/L = ¼ ratio and is quite short. A vital criterion in choosing the development location

I - 55

Page 56: Study of Social and Economic Impacts of Construction of ...

was that it could be executed technically and that it provided the necessary of materials for

executing the dykes from the site excavations. The sources of construction materials were

detailed in the geological reports, for which some digging works and lab tests were made.

The geological conditions, both of the plateau and for the underground works, are good

and are certified by the results of the land survey reports.

II.2. Execution technology

In order to execute the development project, some execution technologies of great

potential were investigated:

The Upper Reservoir (Polder type, V = 10 mil.cubic meters) is executed on the Lapustesti

plateau by building dykes of an average height of 35 m and of a length of about 2,600 m.

In order to execute it, the excavated material from the polder’s cuvette is used, so that the

quantity required for filling should be supplied from the excavations. The excavation

volume is 6.64 mil.cubic meters, and the volume of dykes fills is 5.16 mil.cubic meters.

The upper reservoir is tightened all over the area with a two-layered 16 cm thick asphalte

concrete blanket. The works will be developed on three sectors, with 8 work locations,

using excavators of very big capacity.

The main diversion works taken into account are: the high pressure gallery (the diameter of

which is 6 m and serves the 4 units), the low pressure galleries (one to 2 units, so 2

wires), suction galleries (to every unit), surge tanks (one to 2 suctions in the downstream,

so one to one wire), lower and upper intakes, and valve chambers to both intakes that will

be executed in wet shaft. The high pressure gallery, with L = 1,096 m, will be built with a

15-60 mm thick tunnel lining, which is variable according to the water column height. The

low pressure galleries, with L = 2 x 1,325 m, of which diameters are 6.20 m, will be built

with multiple reinforced concrete linings of up to 60 cm thikness. The high pressure

gallery with a 6.00 m diameter and a 1.096 m length will be executed at a 45 slope, with a

drilling machine, at a full section and in an ascendant tunnel face, with no intermediary

adits.

The underground plant is made of 2 caverns, the machine hall cavern and the transformers

cavern and more galleries: the main adit, the secondary access tunnel, the cable tunnel, and

ventilation gallery, as well as the connection galleries between the 2 caverns in order that

people should have access or for technological flows.

All the underground works are developed in the rock from the area: quartz-mica schists –

detailed in the geological report and given in procentage according to their various types of

toughness. The machine hall cavern with a length of 115 m and width of 25 m will be

executed starting with the arch with development drifts and then in the longwall mining,

the arch having been concreted on the lifts placed on the cradles. The structural work is

made of reinforced concrete and holds the equipment and the 2 travelling cranes, each of

200/ 50 t, for mounting the equipment. The transformers cavern is 115 m long and 19 m

wide and will be executed in the same manner as the machine hall cavern will be executed.

The electric wire connection tunnels between the generators and transformers will be

shored and then concreted. The adit between the caverns and also all over its length will be

initially shored in steel supports for underground excavation and then concreted. The

connection tunnel from the end opposite to the mounting platform will be executed the

same way. The cable tunnel will be developed with a horizontal canal reach of about 600m

I - 56

Page 57: Study of Social and Economic Impacts of Construction of ...

from the outside and the canal reach inclined to 1:1.5 from the inside. It will be concreted

and departmentalized.

II.3. Functional and technological data

The Tarnita-Lapustesti PSHPP will have high maneuverability and consequently it will be

capable to timely respond to load variations. The operational period in the turbine mode

depends on the peak load period during daytime. The operational period in the pump mode

depends on the off-peak period during non-business days. Depending on the operational

periods (pump-turbine mode) the volume of the upper reservoir was established (10 mil.

m3). The discharge of the hydro-aggregate is different in the turbine mode as compared to

the discharge in the pump mode. To prevent hydraulic hammering in the pump mode due

to some failures, which could occur at nuclear or thermal energy generators, the turbine-

pump hydro-aggregate must be capable to adjust the absorbed load.

Figure 3. Synoptic profile of the Tarnita-Lapustesti PSHPP

While running in pump mode, both at start and at shut down, there is a frequency variation

in the national energy system, namely: at soon as the pumping starts, the frequency

decreases under 50 Hz (for a unit of 250 MW it decreases to 4.92 Hz). As soon as the

pumping stops, the frequency increases over 50 Hz in the national energy system (for the

same unit of 250 MW it increases to 50.08 MW). The scope of this frequency of variations

is tightly connected to the power of the aggregate adopted for the PSHPP, but also to the

feedback of the national energy system when the PSHPP starts to run in the pump mode.

From this point of view and according to the capacity of the thermal or nuclear units,

capacities as higher as possible would be highly recommended for the turbine-pump hydro-

aggregates installed in the PSHPP. But, the higher the capacity installed in these

aggregates is, the higher the frequency variations in SEN produced at shut down or at start

of the pump mode are.

I - 57

Page 58: Study of Social and Economic Impacts of Construction of ...

For the actual capacity of SEN and in the light of the years 2015 – 2020, focusing on

developing the nuclear, thermal (by refurbishment), and wind power capacities, the

scenario of equipping the Tarnita-Lapustesti PSHPP with 4 tubine-pump hydro-aggregates

of 250 MW each was therefore adopted (4 x 250 = 1,000 MW).

III. COMMUNICATION WITH THE LOCAL COMMUNITY

According to the law, the public is to be consulted for the environmental permit for the

construction. Up to this date, there aren’t significant negative opinions or opposition of the

public regarding the project. Feasibility studies show that the project of Tarnita-Lapustesti

PSHPP does not impact the protected natural areas of community interest. Tarniţa – Lăpuşteşti PSHPP is located in rural Mărişelu , Capusu Great Râşca , Gilău ,

Dângăul Great Big Hill , Lăpuşteşti , Warm Somes Cluj County .

For the the communication with the local community, Hidroelectrica hired a consultant.

The consultant proposed action plan in consultation with representatives of the local

community.

There were numerous contacts with local media and local NGOs . After identify key NGOs

active in the Cluj Country and held preliminary identification of areas of activity and

interest for each such organization. Afther that, consultant prepared joint meetings and

presentations of the project. Hidroelectrica, held several meetings with NGOs local

representatives. Mr. Dorin Chiorean , project manager from Hidroelectrica participated in

meeting to provide some details on project promotion by authorities.

NGO representatives reactions can be classified into two main areas :

- Such a massive and spectacular project will significantly impact the landscape and

environment in the construction. Even if the impact of plant construction and higher

accumulation can be considered limited to the construction area at the colony;

- Such a project could create 5,000 temporary jobs would have a social impact . NGOs

active in the area would like to have more information about structure professions

workforce will be employed by the project ( many employees with university high or

medium , many employees in various specialties , etc. ) , considering that this such persons

during the 5-7-8 years will influence economic and social development of the region.

Immediate conclusion is that a study social impact would be absolutely necessary.

Regarding relations with the local community, we can mention frequent contacts with

Mayors of Mărişelu , Capusu Great Râşca , Gilău , Dângăul Great Big Hill , Lăpuşteşti ,

Warm Somes Cluj County. It was noted a total openness of local authorities to support

project implementation. They understood that the project would bring significant benefits

for local infrastructure development, job creation and development of tourism in the area.

Meanwhile for the project permitting were held with the participation of community

members locale and representatives Hidroelectrica. In these meetings were made detailed

presentations of the project and were given answers on the implications of the project.

I - 58

Page 59: Study of Social and Economic Impacts of Construction of ...

Figure 4. Meanwhile the project permitting process under way

In the ongoing campaign to promote the Tarnita project among the local community in the

20th

September was organized a visit to the leading journalists on the Lapustesti plateau

.This meeting was attended by project Mr. Dorin Chiorean. The most important local

publications have participated. On this occasion, journalists traveled route the plateau

Tarnita-Lapustesti, being informed of the details of hydropower construction and its

implementation status. It has also been made a visit to the hydroelectric Mariselu for a

concrete view of a construction of this kind. In addition, there where organized public

debates The Hall of Rasca.

Figure 5. Visit to the plateau Tarnita-Lapustesti

At long last, sustained media campaign and open permanent dialogue with representatives

of local communities gave the expected result. The project was approved by local

community members, they have given their consent for the project.

I - 59

Page 60: Study of Social and Economic Impacts of Construction of ...

CONCLUSIONS

From the point of view of the national energy sector development, the accomplishment of

the Tarnita-Lapustesti PSHPP is a must and opportune. In the light of the years 2015 –

2020 when the following are forecasted: developing the nuclear, thermal (by

refurbishment), and wind power capacities, the Tarnita-Lapustesti PSHPP responds to the

concrete need of the National Energy System of existing a generation capacity that could

store efficiently the energy produced for which there is no immediate consumption and

contributes to increasing the quality of the power supplied by participating to the

frequency-power regulation and to providing the rapid tertiary reserve.

According to the law, the public is to be consulted for the environmental permit for the

construction. Feasibility studies show that the project of Tarnita-Lapustesti PSHPP does

not impact the protected natural areas of community interest.

After a sustained campaign of public information, community members understood the

importance of the project to the national energy system and the benefits of developing such

a project for the local community. The project has approved the local community.

It can be concluded that the key to success of the roadmap of preinvestment process for

Tarnita-Lapustesti PSHPP was the open and sustained communication between the

beneficiary Hidroelectrica and the local community.

REFERENCES

Irinel Daniela Iacob: ”Effectively Sourcing Funding Solutions for Developing and

Managing Renewable Power Generation Projects”, The annual European Power

Generation Strategy Summit 2010, Prague, 2010;

Irinel Daniela Iacob and Dragos Zachia Zlatea: The Tarnita-Lapustesti PSHPP,

European Club Symposium Saring experience for safe and sustainable water storage, 10-12

April 2013, Venice, Italy.

Oprea Traian, Razvan Cojoc and Irinel Daniela Iacob: “Tarnita-Lapustesti PSHPP, the

first pumped storage plant in Romania”, The 10th

Regional Energy Forum - FOREN,

Neptun-Olimp, 2010 ;

I - 60

Page 61: Study of Social and Economic Impacts of Construction of ...

SincepetroAs anrole ihydropositipositithermin thethe namoureserCompengin Keyw 1. GE Atmoconsuatmoconsufiguraveraetc inheat fromstratenaturpoweimpoenerg1.0 t

Evaluatio

e 1961, witholeum, globaln engineerinin slowing dopower statiive and negaive effects, (1

mal power ste reservoir aegative effec

unt of electrirvoir createdparing the neering is far

words: dam,

ENERAL I

osphere is aumption of

osphere is umed 1.32 bres reached age annual n the atmosisland effec

m year 2000egy: to devral gas-geneer constantlortant targetgy-consumiton for eve

on on the

Dadu R

h the increasl temperatur

ng measure tdown the gloion in Chinaative effect of1) hydropowtation; (2) Rearea, enhanccts, (1) the scicity, petroled by dam wabove indicr more super

CO2 release,

INSTRUCT

a necessity f coal, petroexperiencinbillion tons2.167 billiogrowth of 1sphere, abnct in metrop

0, the Chinavelop hydroperated powly. At the sat of nationaling index isery 10,000

INTERNA

Bali, In

Effect of

LinzhanRiver Hydropow

sing global re has been rto harness hobal warminga with a therf dams to the

wer station caeservoirs forcing the capacale of dams

eum and conwill inundat

ces of CO2rior to their n

, reservoir, a

TIONS

for the survoleum and ong unpreces of coal andon tons and10.15 percennormal weatpolitans dura Governmepower and er rationallame time, enl economic s planed to r

yuan of G

ATIONAL

ndonesia, Ju

f Dam En

g Gao, Fuhwer Developmen

130904040

ABSTRACpopulation

rising continuhydropower, g process. Irmal power e atmospherean reduce thermed by damacity of plans is usually l

nstruction mate plants wrelease, the

negative effec

atmospheric

vival of manother fossildented desd 224 milliod 325 milliont. Due to tther appearring summeent began twind powey, and to onergy-savindevelopmenreduce fromGDP. In Ju

SYMPOS

une 1ST – 6TH

gineering

hai Yao & Bnt Co., Ltd. [email protected]

CT: and consumually at an adams are pl

In this paperstation of t

e ecosystem e release of

ms can impronts above thelarge and itsaterial, indir

whose rottinge positive efcts to the atm

temperature

nkind. How fuels, the

struction. Aon tons of pon tons respthe significared in manyer time, acidto implemeer vigorousloptimize theng and wastnt by China

m 1.22 ton ouly’s G-8 s

SIUM ON

H , 2014

g to Atmo

Bin Duan engdu Sichuan,

mption of fosverage speedlaying more r, by comparthe same insare analyzedCO2 by 648g

ove the meteoe water levels constructiorectly emitting will also ffects of po

mospheric ec

e

wever, with tecological

According tpetroleum inpectively in ant increasey places of d rain in thnt a new ely, nuclear e proportionte-reducing a governmenof standard csummit hel

ospheric E

, China

ssil fuel as d of 0.2oC peand more i

ring the Dagstalled capacd thoroughlyg/kWh compaorological cl to absorb C

on will consung some CO2

release somower-generatcosystem.

the large amenvironmento statisticsn year 2000

year 2005 e of CO2, SO

China, suche South. Thenergy devepower activn of coal-gwork is listnt, and by 2coal in yearld in Japan

Ecosystem

coal and er decade. important gangshan city, both y. For the ared with onditions CO2 . For ume large

2; (2) the me CO2. ting dam

mount of nt of the s, China , and the with the

O2, NO2, ch as the herefore, elopment vely and enerated ted as an 2010, the r 2005 to n, China

m

I - 61

Page 62: Study of Social and Economic Impacts of Construction of ...

Government support the decision to reduce the release of greenhouse gases by 50 percent of the present level by 2050. During the past 10 years, dam construction, as a necessity for hydropower development, has been questioned. One argument is that hydropower plants transmit clean electricity, so the dam itself is an environment-friendly facility, while the opposite view that dam construction occupies a large number of farmland and woodlands and consumes a large amount of building material, its reservoir filling inundates a large number of woodland and farmland and destroys the local ecosystem. Obviously, for the dams to be constructed in China, it’s necessary to use scientific attitude to evaluate theirs advantages and disadvantages to the atmospheric ecosystem thoroughly, thus to reach a consensus and to create a good external environment for construction. 2. ADVANTAGES AND DISADVANTAGES OF DAM CONSTRUCTION TO THE ATMOSPHERIC ECOSYSTEM 2.1. The ecological benefits of dammed water resources to atmosphere The dams have three main functions: (1) Flood control and disaster reduction. (2) Breed aquatics and tourism. (3) Hydropower generation. The first two have not direct relationship to atmospheric ecosystem. Upon the completion of a dam, a hydropower station with a capacity of a kWh can reduce the release of CO2 by 0.648a kg and SO2 by 0.0044a kg annually. The figure is based on unit coal consumption of 0.35 kg / kWh and CO2 release of 0.648 kg / kWh in thermal power plants provided by China government. 2.2. Dam construction consumes a large amount of building materials and energy and releases CO2 indirectly Construction of dam and its affiliated power plant involve excavation and filling of earth and stone, production of sand and aggregate, concrete casting, electrical and mechanical equipment installation and so on. With the continuous progress of dam construction technology, a dam construction can be finished within 10 years from planning to completion. If the construction consumes energy of bi for the i year (i<10) and the transportation of cement and steel and other bulk goods consumes energy of ci, then the total energy consumption during construction of the dam is Σ (bi + ci). This part of energy consumption is equivalent to 0.648 Σ (bi + ci) (kg). of CO2 release to the air, based on the release index of thermal power plants. 2.3.The plants in the reservoir area cannot absorb CO2 after filling For the fast-growing forests in mild region, their absorption capacity of CO2 is 270 t/km2 annually. When they are destroyed, the decay of plant residues accumulatively releases CO2 of 500 t/km2. If the total area for the construction of a dam and its reservoir is S square kilometers, then the ability of CO2 absorption will reduce by 270 S (t), and the decay of underwater plant residues will add another 500 S (t) accumulatively. 2.4 .Comprehensive analysis of dam construction to the atmospheric ecosystem

I - 62

Page 63: Study of Social and Economic Impacts of Construction of ...

3

From above analysis, dam construction has both advantages and disadvantages to atmospheric ecosystem. If the life of the dam is n years, and the total amount of CO2 released from both dam construction and the plant decay under its reservoir is averaged by n year, then index of dam to the reduction of CO2 release would be F = [0.648 Σ (bi + ci) +5 ×105S] / n +27 ×104S -0.648a, where the unit of F is kg, i ≤ 10, n ≤ 200. If F <0, then index of dam to the reduction of CO2 release is good. 3. CASE HISTORY 3.1 Impacts of Dagangshan hydropower station, Dadu River to atmosphere Dagangshan Hydropower Station is composed of a 210 m-high concrete arch dam and an underground powerhouse with an installed capacity of 2600 MW. Upon completion, the power station bears a multi-year average power-generating capacity of 11.4 billion kWh. Major indices of the project include excavation of earth and stone 12.77 million m3, concrete casting of 4.57 million m3, mechanical and electrical equipment installation of 24,000 ton. It takes about nine years from 2006 to 2014 to finish the dam. The multi-year average temperature is 15.40 C and the rainfall is 642 mm in the dam area, and the total area of the reservoir-inundated woodland is 13.56 km2.The impacts of the dam to atmospheric ecosystem are analyzed as follow.

fig1. Dagangshan dam

(1)The annual 11.4 billion kWh of hydropower saves 3.99 million tons of standard coal, reducing 7.39 million tons of CO2 release each year based on release index of thermal power plants. (2)Within the nine years of construction, the yearly average power of all kinds of construction equipment is 3000, 4000, 4500, 4500, 6000, 7000, 7000, 8000, 9000 and 6000 kW respectively. Supposing the average usage of the construction equipment is 6000 hours, the total consumption of electricity during the construction is 354 million kWh, which is equivalent to CO2 release of 228,700 tons in thermal power plants. (3)Within the nine years of construction, the yearly average power for transport equipmenta is 2000, 2500, 3000, 3500, 4000, 5000, 5000, 5500 and 5000 kw respectively, the energy used for transportation of bulk materials is 175 million kWh, which is equivalent to release 113,400 tons of CO2 in thermal power plants.

I - 63

Page 64: Study of Social and Economic Impacts of Construction of ...

4

(4)After the 13.56 km2 of woodland is inundated or decomposed in the damsite and in the reservoir area, the total CO2 release will be 6780 tons. (5)After the 13.56 km2 of woodland is inundated or decomposed in the damsite and in the reservoir area, 3661 tons of CO2 absorption by local environment will be reduced.

fig2. Dagangshan reservoir area

If Dagangshan arch dam can stands for 200 years (a conservative figure), then index of dam to the reduction of CO2 release is 0.174 +0.3661-739 = -7.3846 million tons. That is, when various factors are considered, the dam can reduce the release of CO2 by 7.3846 million tons to the atmosphere annually, compared with an equivalent thermal power plant. If compared with a thermal power plant of capacity of 11.4 billion kWh, its total amount of engineering is equivalent to concrete casting of 300,000 m3, its plant electricity usage is 7%, construction period is three years and the plant can be used for30 years, then the equivalent CO2 release will amount to 203,000 tons for its material transport and construction, and to 7.9 million tons annually during operation period, 29.7 times as that by the construction and reservoir filling of Dagangshan Hydropower Station. 3.2 The environmental benefits of Ertan Dam, Yalong River The China Ertan concrete arch dam is 242 m high with an installed capacity of 3300 MW and a multi-year average generating capacity of 17 billion kWh. Its reservoir extends for 145 km long with an area of 102 km2. The dam construction commenced in 1989 and ended in 1998. After the completion of the dam, climate in the reservoir area changes drastically. Its winter temperature increases by around 20C, while its summer temperature drops almost 20C than before. Before dam construction, the multi-year average rainfall in the dam site area is 700 mm and it seldom rains during the dry season. After dam construction, the average rainfall in the reservoir area increases by 50 mm and it often has flurry in the dry season. According to statistics, 90 percent of electricity consumption of Panzhihua City, 46 km away from the Ertan Dam, is from the clean energy supplied by Ertan power station, which greatly improves the city’s the atmospheric environment with the reduction of coal consumption. In May 2006, the Ertan dam won the national environment-friendly project prize awarded by China Government.

I - 64

Page 65: Study of Social and Economic Impacts of Construction of ...

5

fig3. the ertan dam

4. CONCLUSION (1)The dams with power generation function can do more advantage than harm to the atmosphere ecosystem.Dagangshan hydropower station in China can reduce the CO2 emission by 7384.6 million tons each year.On the other hand, the rotting plants below the reservoir water level can release some CO2 during the building time and operating time,and it will release 1.74 million tons every year. Though the reservoir would inundate woodland, reducing the absorption of CO2 by 3.66 thousand tons each year, the negative effect is far less than the positive effect. (2)Reservoirs formed by the dams can improve the local climate conditions.After the adjustment of the reservoir,the temperature and the water vapour content will be more suitable for the survival of animals and plants . REFERENCES "China's energy Yearbook" (2007) China Plans Press, Beijing, China ZHENG Shou-ren: China's water resources utilization and environmental protection issues.

"Water Science and Technology forefront of the new century" (2005) Tianjin University Press, Tianjin, China

I - 65

Page 66: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1

ST – 6

TH , 2014

ENVIRONMENTAL MANAGEMENT DURING CONSTRUCTION

IN COMPLIANCE WITH MEXICAN REGULATIONS

M.A. Gomez-Balandra Instituto Mexicano de Tecnología del agua

[email protected]

C. Lecanda Terán, A. Hollands Torres and R.D. Llerandi Juárez Comisión Federal de Electricidad Subgerencia de Anteproyectos

ABSTRACT: Due to the advance in environmental regulations, impacts related to land use and forest loss, noise,

atmospheric emissions, solid and hazardous wastes, as well as water use and discharges during

construction are being managing and enforcing through auditing and certification. The Federal

Commission of Electricity and contractors are accomplishing several environmental standards

which are becoming best and common practices through the planning, bidding, construction and

operation phases. As a part of the environmental impact assessment procedure, projects' activities

and works are described and analyzed twofold spatially and temporary. For each project it is

important to establish the direct impacted zone, and its area of influence or Environmental

Regional System, where natural processes are going to be modified. In the first area the project

needs to solve the compatibility with the policies of land use, either it allows some uses or reserves

land for conservation. For forested area, even with arid or semi-arid vegetation, the project need

to submit an additional study denominated Technical Justificatory Study as a kind of dasonomic

inventory to go into a process of forest compensation through the National Forestry Commission.

In addition, each project is required estimate and gets authorizations to deal with urban solid and

hazardous wastes. In the case of construction or excavation wastes, they are considered of special

management since are produced in large volumes and need disposal mechanisms. In this paper the

experiences gained by the environmental management and certification of La Yesca dam are

described and discussion is focused on the procedures efficiency. Overcoming the associated

impacts to this environmental management will help to focus and to develop approaches to deal

with impacts in the environmental regional system such as ecosystems fragmentation,

environmental flows, biodiversity stress and regional cumulative impacts.

Keywords: environment, land, wastes, discharges, emissions, certification.

1. INTRODUCTION

As in many developing countries, Mexico has issued a large number of criteria and

standards to regulate the activities and economic development. Some are specific for each

sector for example energy, tourism, etc. while most are of general application to

environmental protection, pollution control and compensation for loss of natural areas.

In Mexico several institutions have been responsible for the environmental management

and protection since the beginning of the 70 decade to date. During this period of time a

I - 66

Page 67: Study of Social and Economic Impacts of Construction of ...

comprehensive environmental legislation and regulations have been issued at federal and

state level, so the hydroelectric projects should be subject to the procedures and

regulations.

Due to the nature of hydroelectric projects, especially large dams are subject to the

environmental impact assessment procedure in the early stages of planning. However,

these undergo when technical and economic studies are in advanced. Thus it is difficult to

change the site but some can be done for the generation scheme. Currently for site

selection a strategic is being tested to match lesser environmental impact with greater

energy generation.

From this point, detailed information is required for the project and its area of influence to

evaluate their impacts and make decisions. Specific environmental studies are

commissioned to different institutions and universities and their results integrated in the

Environmental Impact Statement (EIS).

At the same time, it is compulsory to follow a land use change procedure, and integrate

detailed information on the forest to be impacted and the mitigation measures taken by the

project, mainly during construction phase in a justificatory technical report (ETJ).

The Ministry of Environment carries out a consultation process with institutions and

interested parties if a public audience is requested. Thus stated mitigation in the EIS,

petitions and recommendations under the environmental compliance are integrated in a

final resolution issued for the project.

This resolution outlines conditions under which the project was authorized and the

proponent must meet an Environmental Management Program (EMP), to present

semiannual reports to the Ministry of Environment. Besides carrying out negotiations with

other federal, state and municipal institutions as the land use change, the solid waste

management and wastewater discharges, among others.

During the tender process these requirements are established as clauses of contracts for

contractors to implement them under the local supervision of the Federal Commission of

Electricity (CFE). This paper describes the main aspects and procedures of environmental

management projects in their planning and construction stages. Recommendations to

improve its efficiency are included, as well as to incorporate more holistic approaches to

solve complex issues such as environmental flows, ecosystems fragmentation, biodiversity

stress and regional cumulative impacts.

2. ENVIRONMENTAL MANAGEMENT AND PROJECT STAGES

It is important to recognize that at the different stages of each hydroelectric project

development, the environmental management that need to be accomplished, for example

during planning at feasibility stage there are regulations from geological exploration and

until the resolution of the environmental impact procedure. Figure 1 point out the general

environmental management at each stage of hydro projects development in Mexico.

I - 67

Page 68: Study of Social and Economic Impacts of Construction of ...

Figure 1. Environmental Management for Hydro Projects in Mexico (modified from Gómez-

Balandra et al, 2006).

The organizational structure within the CFE for environmental management of a project

like La Yesca included the technical and operative areas shown in Figure 2. This scheme

must be read from bottom to top. Then compete to CFE’s Initial Projects Sub-management

determine the project technical, economic and socio-environmental feasibility, as well as

obtain the resolution granted by the Ministry of Environment. Specifically for La Yesca

this was carried out by at the North Pacific Initial Projects Centre with support of central

headquarters (Hydropower Projects Coordination).

On the other hand, the Environmental and Archeological Heritage Department and The

Environmental Protection Management help to review and submit EIS’s at the Ministry of

Environment. Finally, the Financed Investment Project management alongside the

Hydropower Projects Coordination is in charge of the bidding process.

I - 68

Page 69: Study of Social and Economic Impacts of Construction of ...

Figure 2. CFE organizational structure for environmental management

Once the bid succeeded and was formalized, a local Social-Environmental Residence is

established, under the General Residence for Construction (Figure 3). Its main objectives

are to conditions of approval compliance, implement the EMP and monitoring mitigation

measures. The Social-Environmental Residence in La Yesca had five areas to: 1) address

mapping and databases, 2) environmental, 3) social and liaison with agencies, 4) property

rights acquisition and 5) social and infrastructure compensation. At this residence 78 field

and office employees were assigned.

I - 69

Page 70: Study of Social and Economic Impacts of Construction of ...

Figure 3. Structure of the Social and Environmental Residence.

3. MAIN ENVIRONMENTAL REGULATIONS FOR HYDROPOWER PROJECTS

A hydropower project is regulated in accordance to its activities during the site preparation,

construction and operation. Thus since the geological exploration there is a standard to

regulated how the site must be leave it (Official Mexican Standard NOM-120-

SEMARNAT-2011), for the environmental protection specifications for direct mining

exploration activities in agriculture, livestock or abandoned areas with dry and temperate

climates with desert scrub vegetation, tropical deciduous forest, coniferous forest or oak.

The main standards to be met at present by any hydropower project are listed in table 1.

These must be declared in chapter III of EIS indicating which are the project activities and

strategies for its compliance.

Table 1. Main standards for hydropower projects

Official Mexican Standard Environmental Protection

NOM-001-SEMARNAT-1996 Wastewater discharges to water bodies

NOM-004-SEMARNAT-2002 Sludge and bio-sludge disposal

NOM-041-SEMARNAT-2006 Vehicular emissions (oil)

NOM-043-SEMARNAT-1993 Solid particles from fix sources

NOM-045-SEMARNAT-2006 Vehicular emissions (diesel)

NOM-080-SEMARNAT-1994 Noise by mobile sources

NOM-081-SEMARNAT-1994 Noise by fix sources

NOM-052-SEMARNAT-2005 Hazardous wastes

NOM-059-SEMARNAT-2010 Native and protected species

NOM-017-STPS-2008 Personal equipment

NOM-031-STPS-2011, Security and health at work

In addition the project must be in accordance with compulsory and guiding instruments for

conservation, in the first category: Ecological and Territorial Ordinance Program (POET)

I - 70

Page 71: Study of Social and Economic Impacts of Construction of ...

and its environmental management units; Management plans of Natural Protected Areas

(ANP), Ramsar sites, etc. Examples for the second category are: Priority Terrestrial and

Hydrological Areas, Sites of importance for birds, among others.

During the EIS integration is necessary to review the scope of laws and its regulations

(including updates) such as the general or federal laws for:

Ecological Equilibrium and Environmental Protection,

Sustainable forestry development

Prevention and Integrated Management of Wastes

National Waters

Archeological zones and Monuments

4. GEOGRAPHICAL SCOPING

An Environmental Regional System (SAR according to its name in Spanish) is required for

each hydropower project which is the area that comprises the impacted surface by the

works, activities, and project operation. In those areas a land use change permit is needed.

Apart from the directly impacted area it is necessary to include the area of influence,

mainly downstream, in the reservoir catchment limits and some areas to be occupied

temporarily. In the SAR the natural processes and structures modified by the projects must

be analyzed such as hydrological changes, biological corridors and vegetal communities.

For La Yesca located in the Santiago River Basin Northwest Mexico in a cascade scheme,

its Environmental Regional System reached the 1,000 m elevation in the plateau, as the

limit in the contour around the reservoir. The SAR was 65,000 ha, initiating upstream of

Rio Santiago from Santa Rosa Hydro and ending 5 km downstream at the terminal part of

the El Cajon reservoir (Figure 4). In this area, 3,492 ha belong to the reservoir, plus 200 ha

for project activities at the dam site. Both comprise the impacted area, where a Technical

Justificatory Study as a kind of dasonomic inventory was carried out to estimate the forest

and environmental services (mainly carbon capture and groundwater recharge) to be

compensated through the National Forestry Commission. The main structure and content is

as listed:

I. Uses that are intended to give to the acquired or expropriated land;

II. Location and area of the property or set of properties, and delimitation of the

portion you intend to remove forest lands, through geo-referenced maps;

III. Description of the physical and biological elements of the hydrological-forest basin

where the project site is located;

IV. Description of project site conditions including the purpose for which it is intended,

climate, soil types, average slope, landform, hydrography and vegetation and fauna

types;

V. Estimation of volume by species of forest raw materials resulting from the change

in land use;

VI. Time and manner of implementation of land use change;

VII. Vegetation to be respected or established to protect fragile lands;

VIII. Prevention and mitigation measures of impacts on forest resources, wildlife,

applicable during different developmental stages of land use change;

IX. Environmental services under jeopardy by the proposed change of land use;

I - 71

Page 72: Study of Social and Economic Impacts of Construction of ...

X. Technical, economic and social justification to motivate the exceptional

authorization of land use change;

XI. Inscription data in the register of the person who made the study and, if applicable,

responsible for directing the implementation;

XII. Application of the criteria established in land’s ecological regulation programs in

different categories;

XIII. Economic Estimation of biological resources to be protected in the area subject to

land use change;

XIV. Cost estimation of restoration activities due the change of land use, and

XV. Where appropriate, other requirements specified by the applicable provisions.

For La Yesca project, in the corresponding Regional Environmental System 65,000 ha, the

expected impacts were analyzed including changes in surface hydrology, groundwater,

topography, demography, environmental and social aspects with data integrated into the

EIS.

At present more databases and geographic tools are available to set the Environmental

Regional System under criteria (figure 5) such as:

Limits of basin, sub-basin and micro-basins

Landforms

Limits of vegetal or forest communities

Zoning criteria in management instrument such as POET and ANP plans and others

Biological corridors

Figure 4. La Yesca Hydro ERS Figure 5. Pescado Hydro ERS

5. FUNCTIONAL HOLISTIC APPROACH

The large dams’ impacts cannot be analyzed out of their natural context including the

position in the basin, since the ecosystems fragmentation is an important issue to preserve

environmental flows, sediment transport and hydro-geomorphology. Wildlife and aquatic

biodiversity depend on these natural processes and have been impacted by regional

cumulative impacts, including dams. (Bratrich et al, 2004; Richer et al, 2010; Kibler et al,

I - 72

Page 73: Study of Social and Economic Impacts of Construction of ...

2013). Some provisions are being taken by CFE to incorporate these criteria for site

selection at early planning stages.

In addition, environmental flow strategies are being included in the hydropower operation

to resemble natural variability even though a loss in generation, because of a technical

regulation to promote that was issued in September 2012. An adaptive approach to make

the project profitable and preserve aquatic ecosystem is discussed for new projects and its

implementation will be a real challenge for CFE or any other electricity public or private

company (Arthington et al, 2006).

Our Environmental Federal Law issued in 1988 with its several amendments (last during

this year) considered initially topics such as ecosystem functionality and little by little has

been introducing more complex topics such as ecological integrity, load capacity and

ecosystem services to be evaluated by project proponents with so few available official

data and accepted methods. Nevertheless, some consultants and academic institutions have

some advances in these topics and they have included at least frameworks for its analysis.

In Mexico, many impacts of large dams are classified as significant due to the definition

as: alteration in ecosystems, its natural resources or health that create obstacles for the man

and other life forms development and in the continuity of natural processes. Because of iIts

recognition as residual or cumulative impacts is also important to promote specific

assessments and mitigation among the most important are: (Brismar, 2004; Bratrich et al,

2004; Kibler et al, 2013 )

Reservoir surface area as quantity of riparian and terrestrial habitat inundated,

including habitat losses for wildlife.

River channel inundated or dewatered with impacts on aquatic habitat in the

reservoir and downstream

Riparian and terrestrial diversity loss

Catchment and basin-scale connectivity, impounded free streams of different order

and cascade systems

Hydrologic and sediment regimes due to flow modification and the barrier effect of

dam and impacts downstream

Residence time change and water quality in the reservoir and downstream

Potential growth of invasive species in the reservoir

6. CONCLUSIONS

Due to advances in environmental management required by the Ministry of Environment

and the Environmental Attorney to deal with air emissions, wastewater discharges, solid

and hazardous wastes, noise and other issues during planning and construction stages,

associated impacts can be overcome and manage properly.

For that reason the stress of Mexican legislation to submit an EIS for its review and

authorization is on differentiate ordinary or controlled impacts (by standards) from those

significant which are affecting functional features of ecosystems and provoking cumulative

effects.

Focus on developing strategies and data generation is needed for more complex

environmental processes, for example not only on environmental flows but hydro-regime

I - 73

Page 74: Study of Social and Economic Impacts of Construction of ...

and sedimentary - habitat processes, biological structures and relationships between cycles

of dry seasons and floods, etc.

These kinds of issues need more comprehensive assessments, rather than just the

information to be included in an EIS and for that reason encouraging the participation of

institutions and universities is an urgent need, as well as promoting sectoral programs to

produce data and measurements.

It is also important to demonstrate the dams’ positive and negative externalities and work

in improving the social inclusion from the assessment to the decision making, under an

informed and participatory process.

7. ACKNOWLEDGEMENT

We would like to thank José Antonio Dehesa Ortega and The Residence of Environmental

and Social issues for their contribution to describe part of their work in this paper.

8. REFERENCES

Arthington Angela H., Stuart E. Bunn, N. LeRoy Poff, and Robert J. Naiman 2006. The

challenge of providing environmental flow rules to sustain river ecosystems.

Ecological Applications 16:1311–1318.

Bratrich, C., B. Truffer, K. Jorde, J. Markard, W. Meier, A. Peter, M. Schneider, and M.

Wehrli (2004), Green hydropower: A new assessment procedure for river

management, River Res. Appl., 20, 865–882.

Brismar A. 2004. Attention to impact pathways in EISs of large dam projects

Environmental Impact Assessment Review Volume 24, 59–87.

Gómez-Balandra M. A., P. Saldaña F., C. Lecanda T. and E. Gutiérrez L. 2006. Advances

in integrative approaches for dams’ viability in Mexico in: Dams and Reservoirs,

Societies and Environment in the 21st Century. Bera et al. editors. Proceedings of the

Intrnational Symposium on Dams in the Societies of the 21st Century. ICOLD-

SPANCOLD. Barcelona, Spain. Taylor & Francis. Volume 2 1187-1193.

Kibler Kelly M. and Desiree D. Tullos. 2013 Cumulative biophysical impact of small and

large hydropower development in Nu River, China. WATER RESOURCES

RESEARCH, VOL. 49, 1–15, doi:10.1002/wrcr.20243,

Ley General de Desarrollo Forestal Sustentable, 2003. Artículo 117, ley publicada en el

Diario Oficial de la Federación el 25 de febrero de 2003, última reforma publicada:

DOF 07-06-2013. Congreso de la Unión, México D.F.

Ley General del Equilibrio Ecológico y la Protección al Ambiente. 1988, ley publicada en

el Diario Oficial de la Federación el 28 de enero de 1988, última reforma publicada

DOF 16-01-2014. Congreso de la Unión, México D.F.

Poff, N. L., J. D. Olden, D. M. Merritt, and D. M. Peppin (2007), Homogenization of

regional river dynamics by dams and global biodiversity implications. Proc. Natl.

Acad. Sci. USA, 104, 5732–5737.

Reglamento de La Ley General de Desarrollo Forestal Sustentable, 2005. Artículo 121,

reglamento publicado en el Diario Oficial de la Federación el 21 de febrero de 2005,

última reforma publicada: DOF 24-02-2014. Congreso de la Unión, México D.F.

I - 74

Page 75: Study of Social and Economic Impacts of Construction of ...

Richter, B.D.; Postel, S.; Revenga, C.; Scudder, T.; Lehner, B.; Churchill, A. and Chow,

M. 2010. Lost in development’s shadow: The downstream human consequences of

dams.Water Alternatives 3(2): 14-42.

Vörösmarty C. J., P. B. McIntyre, M. O. Gessner, D. Dudgeon, A.

Prusevich, P. Green, S. Glidden, S. E. Bunn, C. A. Sullivan, C.

Reidy Liermann & P. M. Davies Affiliations Global threats to human water

security and river biodiversity Nature 467, 555–561.

Winter T. A. 1988 Conceptual Framework for Assessing Cumulative Impacts on the

Hydrology of Nontidal Wetlands. Environmental Management Vol. 12, No. 5: 605-

620

.

I - 75

Page 76: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

GREENHOUSE METHANE GAS EMISSION FROM RESERVOIRS IN

JAVA, INDONESIA.

By:

Simon S.Brahmana

Water Resources Research Center,Bandung, Indonesia

[email protected].

Tontowi

Water Resources Research Center,Bandung, Indonesia

[email protected]

Sukmawati

Water Resources Research Center,Bandung, Indonesia

[email protected]

Yani Sumarriani

Water Resources Research Center,Bandung, Indonesia

[email protected].

ABSTRACT

Global warming may cause climate change followed by a negative impact, namely: increased

rainfall, increased frequency of disease, rising sea levels , declining biodiversity. Global

warming is mainly caused by increasing levels of greenhouse gases ( GHG ) , namely CO2 ,

CH4 , N2O , HFCs , SF6 , PFCs in the atmosphere . Reservoir waters are considered by

some researchers as a very potential source of methane (CH4). In connection with this,

research was done on the emission of methane gas in the reservoirs in Java. The study of

methane emissions in these reservoirs was done by direct field measurement by means of

Fluxmeter. The results showed that the amount of methane gas emissions from 14 reservoirs

in Java ranged from 0.094 to 4.461 g/m2/day with an average of 1,705 g/m2/day. Reservoir

water quality, especially organic content , depth and season have a great affect on methane

emissions. Reservoirs in Indonesia cover approximate an area of 98 269 ha, thus, the

amount of methane gas emissions is estimated to be around 1,675 tonnes/day. Based on these

result, is indicated that the contribution of methane gas from reservoirs in Indonesia is very

little when compared to the source of the swamps, rice paddies, livestock and garbage.

Methane emissions from wetlands, rice paddies , livestock and garbage in Indonesia is

respectively 529,590 tons/day 17,986 tons/day, 1,477 tons/day and 6,673 tonnes/day.

Key words: reservoirs, global warming, potential, emission, methane gas

I - 76

Page 77: Study of Social and Economic Impacts of Construction of ...

1.BACKGROUND

Since year 1990, one of main issues for environmentalist is global warming. Global

warming has been widely reported to cause adverse effects, such as the occurrence of

extreme climate change on earth, degraded ecosystems, sea levels resulting in island nations

such as Indonesia will have a huge influence.

Global warming is happening on this planet is mainly caused by increasing levels of

greenhouse gases (GHGs) in the atmosphere. The Kyoto Protocol classified the six types of

greenhouse gases , namely carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), and

industrial gases containing fluorine hydrofluorocarbons (HFCs), perfluorocarbons ( PFCs)

and sulfur hexafluoride (SF6).

In an agricultural and tropical countries like Indonesia, the issue of global warming

associated with GHG emissions, many focused on methane gas. This is because methane can

occur naturally in wetlands such as swamps, reservoirs and paddy farming is widely available

in Indonesia. Other GHGs such as N2O, HFCs, PFCs and SF6 are generally produced by

industrial processes. Methane gas needs serious attention because it has a value of Global

Warming Potential ( GWP ) 21, meaning that each molecule of methane has the potential to

heat up the earth 21 times greater than CO2 molecules. Besides causing a greater warming

effect, methane gas also can not be absorbed by the chlorophyll of plants so that more setabil

in the atmosphere than CO2. Given the things mentioned above, this study is limited to

investigational GHG methane alone.

Sources of natural gas such as methane can be emitted from wetlands and geothermal areas.

Moreover, it can also come from human activities such as animal husbandry, agriculture

mining and fuel consumption ( US- EPA, 2010). Globally, livestock are the largest source of

methane gas that comes from human activities (US-EPA, 2011b)

Lately, there is the assumption that the reservoirs and dams in tropical countries is a source of

methane is quite large and is the cause of global warming potential. This assumption is still

controversial and generated much debate. Some researchers claim that the reservoirs and

dams are a source of methane gas which is quite large and potentially cause global warming .

However, some other researchers disagree and consider that statement was a mistake and just

based on assumptions that are not necessarily were correct. (MED India net working for

Health, 2007, PM Fearnside 2007, and International Rivers Press Release, 2007). In fact,

research on methane emissions in the reservoir is still rarely carried out, including in

Indonesia. .

To determine the amount of methane gas emissions from reservoirs in Indonesia, the

measurement had been carried out in the reservoir, particular in Java Island. The study

conducted in April 2012 until in October 2012. Location of the study methane gas emissions

from reservoirs in P.Jawa is showed in Figure 1.

I - 77

Page 78: Study of Social and Economic Impacts of Construction of ...

Figure 1 . Area measurements of methane in reservoirs in Java

2. METHODOLOGY

Measurements of methane emissions from reservoirs was carried out direct on reservoirs

using the equipment Fluxmeter from West System. Fluxmeter equipment consists of a

floating lid that is connected by an infrared spectrophotometer, This equipment can measure

the levels of methane gas directly in the field. This equipment is also equipped with GPS,

(Global Positioning System), thermometers, pressure gauges, as well as special programs for

calculating methane emissions are being measured.

3.1 The amount of methane gas emissions from reservoirs in Java.

1. Measurements of methane emissions was conducted on 14 reservoirs in Java Island,

namely 3 reservoirs in West Java Province (Saguling, Cirata and Jatiluhur reservoir ); 6

reservoirs in Central Java namely: Cacaban reservoirs, Mrica, Kedungombo Wadaslintang

and Gajahmungkur reservoir and 5 reservoirs in East Java Province namely: Sengguruh,

Karangkates, Lahor, Selorejo and Wlingi reservoir. The location number of measurements

on each reservoirs is different amount, depend on the area of reservoir and its morphology.

Result of measurements showed that, emission of methane gas can be detected in each

reservoir more than 70 % of total amount locations except in the Wadaslintang reservoir. In

Wadaslintang reservoir, from the number of locations as much as 8 locations, methane

emissions were detected only 2 locations, or about 25 percent. In the Mrica reservoir,

Saguling, Sengguruh, and Wlingi, methane emissions can be detected up to 90 % of the total

measured location. The results of measurements of methane emissions from 14 reservoirs in

Java island is varied between 0 to 18.691 g/m2/day. The largest emission of methane gas

found in reservoirs Selorejo, in the province of East Java, namely 18, 691 g/m2/day ; while

the average emissions of methane gas in the 14 reservoir varied from 0.094 to 4.461

g/m2/day with average average 1.705 g/m

2/day. The total amount of methane gas emissions

to 14 reservoirs was measured as 333.3 tons/day ( Table 1, and Figure 1 ) .

I - 78

Page 79: Study of Social and Economic Impacts of Construction of ...

Table 1 : Emissions of methane gas reservoirs in Java

No Name of

reservoirs

Locations amount measurement

Locations amount (CH4) detected

Emission Min (CH4*)

Emission Max (CH4*)

Emission average (CH4*)

Reservoirs area (Ha) **)

Emission total (Ton/day)

1 Saguling 12 11 0 8.174 57,60

2 Cirata 15 10 0 2.262 38,39

3 Jatiluhur 19 8 0 5.70 31,96

4 Cacaban 7 4 0 5.715 10,45

5 Sempor 6 5 0 8.717 5,77

6 Mrica 12 12 0.67 2.023 12,47

7 Wadaslintang 8 2 0 0.637 1,24

8 Kedungombo 6 4 0 2.902 43,24

9 Gajahmungkur 18 15 0 9.163 84,27

10 Sengguruh 10 9 0 9.582 8,88

11 Lahor 14 10 0 12.107 6,51

12 Karangkates 13 7 0 1.237 5,71

13 Wlingi 9 8 0 13.386 16,95

14 Selorejo 10 6 0 18.691 15,86

Emission Average - - - - 1.705 - -

Emission total 333,3

* ) . Unit g/m 2/day

** ) Source : Research Institute for Water Resources , Large Dams in Indonesia in 1995 .

I - 79

Page 80: Study of Social and Economic Impacts of Construction of ...

Figure 1: Emissions of methane gas reservoirs in Java inland (Tons/day)

To determine the variation of methane emissions in the reservoir during 24 hours, had been

measured every two hours in Saguling reservoir. Results of these measurements showed in

table 2. At location 1, the value of the methane emissions varied from 0.1675 g/m2/day to

4.711 g/m2/day with an average of 1.5457 g/m

2/day. At location 2, the values methane

emissions varied from 0.005 g/m2/day to 2.1491 g/m

2/day. Statistical analysis at level of

(p <0.05) was obtained results there is no significant difference between the emission of

methane gas during the day and night.

Table 2.Variation of emission methane gas during 24hour in Saguling reservoir.

Location1 Location 2

No Time Emission CH4 Time Emission CH4

1 7.oo 0.023 7.oo 2.1491

2 9.oo 2.6134 9.oo 0.0233

3 11.oo 1.108 11.oo 1.1315

4 13.oo 0.3669 13.oo 0.7738

5 15.oo 2.1672 15.oo 0.5715

6 17.oo 0.1675 17.oo 1.097

7 19.oo 1.082 19.oo 0.005

8 21.oo 2.972 21.oo 0.264

9 23.oo 2.763 23.oo -

10 1.oo 4.711 1.oo 0.225

12 3.oo 2.432 3.oo 0.794

13 5.oo 2.284 5.oo 1.017

Unit: g/m2/day

0

10

20

30

40

50

60

70

80

90

Emis

sion

CH

4 to

n/da

y

Name of reservoir

I - 80

Page 81: Study of Social and Economic Impacts of Construction of ...

3.2 Discussion of Methane Emissions from the reservoir

Based on the results of measurements, methane emissions per unit area is very fluctuating.

The fluctuation are depend on time, location, temperature, water flow. The fluctuation of

methane emissions in the reservoir is different from one location the other locations. For

example in Saguling reservoir, fluctuations between locations of the other locations ranged

from 0.00 to 8.174 g/m2/day. The fluctuations in methane emissions also occur between

reservoirs each other reservoirs. For example, the average emissions of methane gas in the

reservoir at 0,094 g/m2/day Wadaslintang, whereas in Wlingi of 6.154 g/m

2/day. (Table 2).

Wawan Herawan et.al, (2011), shown that concentration of methane gas is largest in

Saguling reservoir than Cirata reservoir. and Jatiluhur reservoir. The concentration of

methane gas in Saguling reservoir varied from 0.9 to 1.9 mg/L, in Cirata reservoir varied

from 0.9 to 1.6 mg/L and in Jatiluhur reservoir varied from 1,2 - 1,4 mg/L. Measurement of

methane gas used by Gas Chromatography. Measurement of the methane gas is not direct

in the field. Brahmana et .al, (2011) shown that emission methane gas at Saguling varied

0,272 to 71,47 mg/m2/hour, with average 13,446 mg/m

2/hour (5 locations ); at Cirata varied

from 0,080 to 10,658 mg/m2/hour , with average 2,664 mg/m2/hour (4 locations ) and at

Jatiluhur reservoir varied 0,097 to 0,474 mg/m2/hour with average 0,274 (5 locations).

Wawan Herawan et.al, (2011) Brahmana et .al, (2011) were analysed the methane gas is

not direct in the field but in laboratory and used gas Chromatogrhy Shimadzu A8. Saguling

,Cirata and Jatiluhur reservoirs located in catchment area of the Citarum river. The Saguling

reservoir located in upstream, followed by Cirata reservoir, and Jatiluhur reservoir. The

Saguling reservoir more polluted than Cirata and Jatiluhur reservoir.

The methane emissions from reservoirs fluctuate greatly also occurs in reservoirs the others

countries. The results of the study of methane emissions in Nielisz Reservoir in Southeast

Poland showed that methane emissions fluctuated between 0.256 to 6.138 g/m2/day (

Gruca - Rokosz, R at.al, 2012 ). Research in Reservoir Funil, San Antonio and Tres Maria

in Brazil also showed fluctuating values each between 0.005 - 0.159 g/m2/day ; 0,00 to

0,634 g/m2/day and 0.000 to 0.007g/m

2/day (Emma,2012).

Conditions at the bottom of the reservoir is very influential on the emission of methane

on the surface of the reservoir, due to the formation of methane gas occurs at the bottom of

the reservoir. If the reservoir is widely available on the basis of crop residues and plants or

contain lots of organic matter and an aerobic, then the bottom of the reservoir occurs

significant methane emissions. The reservoir contains a lot of organic matter, (concentration

of BOD, and COD very high), will produces lot of methane gas. If concentration of BOD,

COD are high in the water and the concentration of the dissolved oxygen are low, and

condition anaerobic situation triggers the decomposition of organic materials will produce

methane gas.

Reservoir water quality also affects the emission of methane gas. The reservoir which contains a lot

of organic matter , both derived from domestic sewage, industrial wastes or other wastes will cause

oxygen levels in the water is reduced or even depleted. This situation triggers the decomposition of

organic materials that produce methane gas. Water flow that occurs in the water reservoir can cause

methane gas to move from one location to another to follow the direction of the current. Therefore, if

in a location at the base of the formation of methane gas reservoirs, not necessarily at the surface

location of the large emissions. With respect to emissions of methane on the surface of the reservoir

fluctuates widely from one location to another, then to determine the amount of methane gas

emissions at the surface of the reservoir is required observations at many locations and represent a

I - 81

Page 82: Study of Social and Economic Impacts of Construction of ...

reservoir of water quality conditions and reservoir morphology. The more locations the better

repeatability of measurements and data obtained.

3.3 . Comparison of methane emissions from reservoirs with emissions from other sources Based on the research that has been done in P. Java to examine 14 of different reservoir

conditions are obtained values of methane emissions from the reservoir per unit breadth ranged from

0.094 to 4.461 g/m2/day with an average 1,705 g/m2/day. Based on the data area of reservoir

obtained , in Indonesia namely 98 269 ha (Ministry of Ocean and Fisheries , 2011), thus the amount

of methane gas emissions from reservoirs in Indonesia is estimated at about 1,675 tons /day .

Emissions of methane gas , generated by the dam in addition can also be generated by other sources

eg landfills (landfill) garbage, swamps and paddy cultivation process and ranch activities .

a.Emissions from Landfill.

Landfill waste is a potential source of methane gas . In developed countries even utilized landfill

waste to generate energy. The production of methane gas at landfill waste is also influenced by

several factors including: waste composition, levels of available oxygen, moisture, acidity,

nutrient availability, size and density of litter (Purwanto, 2009).

Measurement of methane gas emission from garbage in the field has been conducted in Indonesia. .

Based on the number of Indonesian population reached 218.8 million, and estimated each person

generates garbage of 0.61 kg/person per day (Purwanto , 2009), the waste generated reaches 133 468

000 kg/day or approximately 133 468 tonnes /day . Based on estimates each ton of waste can produce

50 kg of methane (Sudarman , 2010) so that methane gas emissions in Indonesia can reach 6,673

tons/day.

b. Emissions from the Swamp and Peat Soil

The swamp/peat soil is one of main a sources methane gas. In the swamp area and peat

soil there are many organic materials , such as grass or plants from rotting. Furthermore,

these organic materials with the help of microorganisms methanogens and certain conditions

(especially the lack of oxygen) will decompose produces methane gas. The study gas

methane emission in swamp area in Indonesia is still rare. Instead a special study of

carbon dioxide emission in peat soil has been done. Loss of carbon dioxide (C2O) gas for

10 years in the peat soil 69.9 ton/ha/year. (Miswar 2013). Research the amount of methane

emissions from swamp conducted in Canada shows a very fluctuating emission values

between 0.39 to 197.81 mmol/m2/day (Pelletier, et al, 2007) or 0.00624 to 3.16496 g/m2/

day. Assuming the average value is the average value of the minimum and the maximum

value of the average emissions of methane gas in the swamp is at 1.5856 g/m2/day. Based on

extensive swamps in Indonesia reached 33.4 million hectares (Simatupang, P and

A.Adimiharja, 2004), it can be estimated magnitude of methane emissions from marsh

reached 529 590 tonnes/day.

c. Emissions from Paddy field

Paddy field is a source of methane emissions. Release of methane from paddy crop can

occur through three processes, namely through aerenchime vessels of rice plants, through a

process of diffusion in air bubbles and dissolving in water through irrigation. The amount of

methane emissions from rice cultivation process is very diverse, among others, depend on

I - 82

Page 83: Study of Social and Economic Impacts of Construction of ...

how the management of the land. Research conducted by Prihasto and friends give methane

emissions from rice cultivation process in Indonesia amounted to 169.9 kg /ha/cropping

season (Prihasto et. al, 2008). If the year consisted of 3 seasons, the methane emissions from

paddy field is estimated at 0.1396 g/m2/hari. Based on statistical data, extensive rice crops

in Indonesia reached approximately 12.88 million hectares, the estimates of methane

emissions from rice fields to reach 17, 986 tonnes/day.

d. Emission from Livestock

Farm business is a source of methane is also considered potential. In America's farm business

is the largest source of methane emissions third ( US- EPA, 2011b ). At the farm business ,

methane emissions to the atmosphere can occur in two ways. The first way is called "enteric

fermentation" that occurs in the stomach of ruminant animals such as cattle, sheep and goats.

At the time of these animals did digestive methane gas formed in considerable amounts . The

second way is through the feces of these animals. The animal waste contains a lot of organic

ingredients. If the organic matter decomposes in the anaerobic atmosphere, it will produce

methane gas. Based on the research that has been conducted emissions of methane gas from

one cow in developing countries is estimated at 95.9 g/head/day (Veerasamy, S., et al., 2011).

From the data released by the Central Bureau of Statistics and Ministry of Agriculture

recorded the number of cows and buffaloes around 15.4 million head, thus the methane

emissions from the livestock sector is estimated at about 1,477 tons/day. This value does not

include that derived from horses, pigs, goats, sheep, ducks, chickens, ducks, geese and other

species. Based on the data and the calculation above shows that although the reservoir as a

source of methane gas, but in general the amount is relatively small compared with other

sources such as swamps, rice, garbage, livestock and industry (Figure3.)

e.Emissions from Industrial waste.

Industrial waste that contains organic substances such as food and beverage industry also

produces methane gas. The numbers are big enough, but in this paper not yet metioned.

I - 83

Page 84: Study of Social and Economic Impacts of Construction of ...

Figure 3 : Comparison of methane emissions from a variety of sources ( in tons/day )

From the figure 3 above show that the greatest emissions generated by the swamp. This

value is the result of calculations based on the assumption that the data of methane emissions

per unit area were taken from the results of studies elsewhere. In addition to the value of

emissions per unit area which is still based on the assumption, the amount of methane

emissions is also due to the enormous swamp in Indonesia . Instead most small emissions

generated from the farm. Compared with the situation in the livestock business overseas in

Indonesia remain undeveloped so that emissions of methane produced is relatively small.

Methane emissions from reservoirs in Indonesia is estimated at 1,675 tons per day . This

value is below the value of methane emissions from wetlands, rice plants and garbage.

4.CONCLUSIONS

a. The methane emissions from reservoirs is different from one reservoir to anothers

reservoirs and one location to others locations in same reservoir.

b. Value of methane emissions in reservoirs in Java ranged from 0.094 to 4.461 g/m2/day

c. with an average 1,705 g/m2/day

d. Based on the data, area of reservoirs in Indonesia around 98,269 hectares the amount

of methane gas emissions from reservoirs in Indonesia is estimated at about 1,675

tons/day .

e. When compared to other sources such as swamps, rice or the value of the waste sector

is very small.

f. In an effort to reduce methane emissions from reservoirs can be done in several ways,

among others :

g. Reservoir will be impounded, must be clean up his plants and others materials. It is

important to be reduced emission methane gas.

h. For long- stagnant reservoirs, if on the edge of the reservoir there is a lot of wild plants

or other plants at low tide when the water level needs to be cleaned, thereby reducing

the decomposition process of organic matter in the reservoir when the water level

rises.

i. The quality of river water into the reservoir needs to be maintained so as not to contain

many pollutants, especially organic pollutants as organic pollutants in water reservoirs

will ultimately lead to increased emissions of methane gas.

j. Other efforts to reduce methane emissions is to look for microbes that consume

methane and oxidize.

REFERENCES

1. Brahmana et.al 2011. Emisi Gas Rumah Kaca (metana) di Perairan Waduk . Prosiding Kolokium

Puslibang Sumber Daya Air ,Bandung Maret 2011.

2. Emma Hällqvist, (2012), Methane emissions from three tropical hydroelectrical

reservoirs, Committee of Tropical Ecology, Uppsala University, Sweden

3. Gruca-Rokosz, R., , E.Czerwieniec, J.A. Tomaszek, (2011), Methane Emission from the

Nielisz Reservoir, Environment Protection Engineering, Vol. 37, 2011, No. 3

I - 84

Page 85: Study of Social and Economic Impacts of Construction of ...

4. Hapsari, C. (2011), Studi Emisi Karbondioksida (CO2) dan Metana (CH4) Dari Kegiatan

Reduksi Sampah di Wilayah Surabaya Bagian Selatan, Jurusan Teknik Lingkungan,

FakultasTeknik Sipil dan Perencanaan, Institut Teknologi Sepuluh November. Surabaya.

5. International Rivers Press Release, (2007), India_Dams_Methane_Emissions. http:

www//.internationalrivers.org.

6. Kem. Kelautan dan Perikanan (2011), Kelautan dan Perikanan Dalam Angka 2011, Pusat

Data Statistik, Kementerian Kelautan dan Perikanan.

7. Keppler F. et al (2006), Methane emissions from terrestrial plants under aerobic

conditions. Nature 439. 187-191.

8. MED India net working for Health, (2007), Capture-and-Burn-Methane-in-Dams-a-New-

Proposition-to-Counter-Global-Warming. http://www.medindia.net/news

9. Pelletier, L, T. R. Moore, N. T. Roulet , M. Garneau , V. Beaulieu-Audy (2007),

Methane fluxes from three peatlands in the La Grande Rivière watershed, James Bay

lowland, Canada, Journal of Geophysical Research, vol. 112, G01018, 12 PP., 2007

10. P.M.Fearnside (2007), Why Hydropower is Not Clean Energy. http://scitizen.com/future-

energies/

11. Prihasto,S., A.K.Makarim, H.Pawitan, I.Anas, L.I.Amien dan E.Sumaini, (2008),

Indonesia Experience in Determining Country Spesific Emission Factor in Agriculture

Sector.

12. Puslitbang Sumber Daya Air 1995. Bendungan Besar di Indonesia. 80 hal.

13. US-EPA, (2010),Methane and Nitrous Oxide Emissions From Natural Sources, United

States Environmental Protection Agency, Office of Atmospheric Programs, Washington

DC.

14. US-EPA, (2011), Greenhouse Emissions, United States Environmental Protection

Agency.

15. US-EPA, (2011), Ruminant Livestock, United States Environmental Protection Agency.

16. Wawan Herwan et al 2010. Potensi Emisi Gas Metana dari Genangan Air Waduk

Kaskade Saguling-Cirata-Jatiluhur. MakalaH Kolokium Puslitbang Sumber Daya Air

2011.

17. Vincent, L.St. Louis, Carol A. Kelly, Eric Duchemin, John W. M. Rudd, and David M.

Rosenberg, (2000), Reservoir Surfaces as Sources of Greenhouse Gases to the

Atmosphere: A Global Estimate, Bio Science 50(9):766-775.

18. Wahyu Purwanta, (2009), Perhitungan Emisi Gas Rumah Kaca (GRK) dari Sektor

Sampah Perkotaan di Indonesia, Jurnal. Tek.Lingkungan, Vol 10, No. 1, Jakarta.

19. West System, 2006, Portable Diffuse Fluxmeter, Pontedera, Pisa

20. W.V. Department of Health and Human Resources (2006), Methane in West Virginia

Ground Water, West Virginia.

21. Zakarya,I.A., H. A. Tajaradin, I. Abustan dan N. Ismail, (2008), Relationship between

Methane Production and Chemical Oxygen Demand (COD) in Anaerobic Digestion of

Food Waste, ICCBT 2008 - D - (03) - pp29-36

I - 85

Page 86: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

European Working Group "Management of dam incidents"

Case study: Finland

Mr. Juha Laasonen Fortum Power & Heat Oy, Power Solutions, Finland)

[email protected]

ABSTRACT European ICOLD Working Group "Management of Dam Incidents" was established in Venice Italy in April 2013 to study European dam safety practices and experiences. The study will comprise at least following items: the dam safety legislation, the guidelines and the documentation related to the dam incidents, the training activities of dam incidents, the roles of the authorities and the dam owner, the safety arrangements practices and the analysis of the dam incidents and failures. The management of the dam safety at the tailings dams is included in the scope. The objectives of the Working Group are to improve the practices handling dam incidents and to collect the best practices of the member countries. In this paper the work on Finnish ICOLD committee are presented by introducing some characteristics of Finnish dam safety legislation and experiences. Keywords: dam safety, management, legislation, dam incidents. 1. INTRODUCTION The dam owner’s responsibility is to ensure safety in the construction, maintenance and operation of a dam and reduce the hazard and the consequences, which the dam incident or accident may cause. The dam is monitored and inspected in order to detect changes or abnormal operation. The upgrading or the repair of the dam is carried out to avoid any dam accidents or incidents. However the changes in the dam condition may occur instantly and without warning. The dam owner shall start emergency repair. The alarming, evacuations and rescue operations shall be initiated, if the situation is critical (Figure 1). European ICOLD Working Group "Management of Dam Incidents" was established in Venice Italy in April 2013 to study European dam safety practices and experiences. The study will comprise at least following items: the dam safety legislation, the guidelines and the documentation related to the dam incidents, the training activities of dam incidents, the roles of the authorities and the dam owner, the safety arrangements practices and the analysis of the dam incidents and failures. The tailings dams are included in the scope. The objectives of the Working Group are to collect experiences and the best practices and improve the practices handling dam incidents. Possibly the recommendations may be given. Although best European dam safety practices for managing dam incidents are collected. The objectives is also to improve national dam safety practices. FINCOLD has established

I - 86

Page 87: Study of Social and Economic Impacts of Construction of ...

a national working group to collect and analyze Finnish experiences. In this paper is described some Finnish dam safety practices and experiences. The paper includes the issues on Finnish dam safety legislation, practices on emergency preparedness plans and training of rescue actions also some dam safety incidents are presented.

Figure 1. Dam safety activities and players 2. FINNISH DAM SAFETY LEGISLATION RELATED TO MANAGEMENT OF DAM INCIDENTS Finnish dam safety legislation was enacted in 1984. The dam safety legislation was presented in the act, the decree and the guidelines. However the dam safety practices described in the guidelines had not any legislative ground. Therefore Finnish dam safety legislation was renewed and the practices were included in the Dam Safety Act (429/2009) and in Government Decree on Dam Safety (319/2010). In addition the renewed dam safety legislation are applied to the tailings dams. The dam break hazard analysis and the dam owner's emergency action plan have to prepared for the high consequence class dams (class 1-dam) (Section 12 in Dam Safety Act (429/2009). The dam hazard analysis is further described in Section 6 of Government Decree on Dam Safety (319/2010) and it contains dam break flood wave analysis, the determination of the maximum coverage of dam break flood flow (flood hazard area), identification of the objects (people at risk, private and communal houses, industry, etc.)

Dam safety

Normal operation ChangesAbnormal operation

DamBreach

Measurements

Inspections

Detection

History dataCorrectivemeasures

AlarmRescue

Evacuation

Data Analysis

Dam safety reportsStructural safety

- appropriate design

Instructions for Monitoring and

Maintenance.

Emergency Action Planning

Rescue Actions

Failure Mode

Operation

Management

Dam rehabilitation and repair activities

AuthoritiesLegislation, State of art practices, ICOLD

Dam safety authorities Rescue authorities

I - 87

Page 88: Study of Social and Economic Impacts of Construction of ...

in the flood hazard area and an estimation of the damages. The information and the documentation of the dam break hazard analysis are used in the preparation of the emergency action plan and rescue service plan. The measures to prevent personal accidents in case of dam incident and to prevent and to limit the damages at the dam are presented in dam owner's emergency action plan (Section 7 in Government Decree on Dam Safety (319/2010). The measures shall protect humans, property and environment against damage. The dam owner shall alarm and report the dam incident. The plan is developed based on the dam failure scenarios and their possible hazard. The dam owner's organization and responsible persons with contact information are included. Possible ways to receiving information on the dam incident or hazard and the alarming of the authorities, personnel and people are described. The dam repair materials and its storage, the contractors and their equipment and own staff are listed with contact information. The document shall continuously updated. Specific technical requirement for class 1 and 2 dams is that the crest throughout its length must be passable to traffic (Section 4 and 5 in Government Decree on Dam Safety (319/2010). The access of the dam maintenance must be ensured during the flood and dam accidents. Dam Safety Act (494/2009) comprises 7 chapters and "the preparations for the accidents and actions in the event of accidents" are described in the Chapter 5. The dam owner with due consideration of the dam hazard must take the necessary action to prevent dam accident and to limit the damages caused by an accident (Section 24: Preventing accidents). The dam safety authority submits the information in its possession necessary for preparing the rescue service plans as requested by the rescue authority (Section 25: Rescue Service Plans). Provisions on rescue activity are laid down in the Rescue Act. The owner of a dam and dam safety authority must assist the head of the rescue activity in performing rescue activity. In addition, the dam safety authority participates, where necessary, in the work of the steering group (Section 26: Rescue activity). The declaration of an emergency and an exceptional situation are described in Section 27. It also states that the dam owner must notify the dam safety authority without delay. 3. RESCUE SERVICE PLANS AND TRAINING OF RESCUE ACTIONS The operations of the rescue authorities are guide by Rescue Act (379/2011). The officer in charge of the rescue operation has the overall charge and is responsible for maintaining the situation picture and for coordinating the operations (Section 35: Command of rescue operations in situations involving co-operation). External emergency plans are prepared for the waste sites for extractive waste referred to in section 45a(2) of the Environmental Protection Act (86/2000) (Section 48: External emergency plans for sites posing a particular hazard), which may be applied some tailings dams with hazardous chemical content. The training on the rescue actions based on dam break flood analysis has become a practice in Finland. First exercise was held in Rescdam-project in 2001 (Finnish Environment Institute, 2001). The dam breach situation of Kyrkösjärvi embankment dam was simulated in the exercise. The rescue and dam safety authorities were responsible for the execution. The objectives of the exercise was to test and improve: the emergency

I - 88

Page 89: Study of Social and Economic Impacts of Construction of ...

action plan, the alarming system and its coverage area, the operation of different parties in the crisis management center, the co-operation of the authorities and the volunteers, the leadership of the regional rescue operations, the intercommunications and the communication during the dam breach accidents. Second exercise was held in 2006. The dam breach of Seitakorva embankment dam in Northern Finland was simulated in the exercise. Third dam exercise will be held in 2014. 4. DAM INCIDENTS IN FINLAND The dam owner is responsible to give notice concerning an exceptional situation (dam incident) to the dam safety authority without delay (Section 27 in Dam Safety Act 494/2009). The dam safety authority is collecting the dam incident reports and some preliminary analysis has been carried out (Kirves, 2010). The earth fill dams with glacial till has had problems with internal erosion in Finland. Several cases with increased leakages, sink holes and turbid water has occurred. The springs at Peltokoski embankment dam appeared during the first fill of the reservoir in 1950's and second one in 1980's. In late winter 1987 the spring collapsed approx. 60 meters from the left embankment dam. A large sink hole of 3 meter deep and a settlement of 29 cm at the dam crest were formed (Figure 2). The collapsed bank was repaired by constructing inverse filter with stones on the surface and with grouting of the embankment. Two Thompson overflow weir were constructed behind the inverse filter. Total leakage was 35 l/s. The water was clear without any sediment suspension. Main reason for the internal erosion was the leakages through the fissured bedrock (Laasonen, 2010).

Figure 2. A large sink hole appeared at the place of spring in 1987 (Laasonen, 2010) Uljua homogeneous earth fill dam is situated in the River Siikajoki watercourse. The leakage was noticed during the first filling in 1970, which was turbid after one month. The

I - 89

Page 90: Study of Social and Economic Impacts of Construction of ...

embankment dam was repaired with cement grouting. The cause was estimated as possible frost action in the upper part of the moraine core (glacial till) and deficiencies in the fine filter. Further a turbid water was found in the tailrace channel in 1990. Several sink holes of 3 meter diameter was found at the bottom of the reservoir. The leakage through the fissured bedrock was considered as the cause. Melo embankment dam is situated in the River Kokemäenjoki. The leakage and a sink hole with the depth of 3.5 meters and a diameter of about 4 meters was noticed in 2005. The leakage was repaired with sheet piling and with grouting. The repair activities lasted 10 months. The cause for the internal erosion is considered the differential settlement of the core at the cast-in-pile, which was considered under the core. Pamilo embankment dam in the eastern part of Finland has had several dam incidents. first one during the first filling and the latest sink holes appeared in 2008 and 2012. The sink holes were filled and emergency grouting was carried out. Several causes for the internal erosion have been considered improper construction of the core (the frosted moraine core was not removed), the deficiencies of the filter and the leakages through the fissured bedrock. The emergency grouting were carried out in all the cases. In addition extensive site investigations were started in order to find out the cause of the internal erosion (Figure 3).

Figure 3. The site investigations at Pamilo embankment dam. The causes of the internal erosion have been the deficiencies with the filter, insufficient filter coverage between the ground moraine and the embankment dam, frost action in the core, the differential settlements of the moraine core due to the partial sheet piling and fissured bedrock under the moraine.

I - 90

Page 91: Study of Social and Economic Impacts of Construction of ...

6. CONCLUSIONS The work on European ICOLD Working Group "Management of Dam Incidents" has started. Some characteristics of Finnish dam safety legislation and experiences are presented in this paper. It requires more detailed analysis of the case studies i.e. how the emergency cases were handled. The internal erosion cases presented in here show one type of the dam incidents. Several other hazards and uncertainties e.g. malfunction of the mechanical and electrical equipment of the gates can lead to a dam incident. The management of dam incidents requires comprehensive understanding of the dam risks and its mitigation measures. Each dam is an individual structure with specific features. However the "Management of dam incident"-study may improve dam owner's understanding and give tools to handle the abnormal situation. The questionnaire is prepared for collection of European practices and experiences. The preparation of the conclusions requires discussions in the workshops to understand different aspects and opinions. REFERENCES

Kirves, R. (2010): Häiriötilanteet Suomen padoilla (Incidents at Finnish dams), in Finnish. Häme Centre for Economic Development, Transport and Environment, 48 p. Finland. http://www.ymparisto.fi/download/noname/%7B4CE06AE1-83AE-4D71-85FF-C6E1610C1F13%7D/57453

Laasonen, J. & J. Autio (2010). Maapatojen sisäinen eroosio - pohjoismainen ongelma (The internal erosion - Nordic problem of embankment dams). in Finnish. FINCOLD. Finnish National Committee on Large Dams 1960 -2010. History and activities. 152 p. FINCOLD. Finland. pp. 112-125.

Laasonen, J. (2010) Internal erosion and duration of grouting works. Case History of a small embankment dam. Proceedings of 8th ICOLD European Club Symposium. Dam Safety - Sustainability in a Changing Environment. 22nd - 23rd September 2010. Innsbruck, Austria (Edited by ATCOLD). ISBN 978-3-85125-118-0. pp. 393-396.

Laasonen, J. (2012). Dam owner's perspective to the dam safety legislation in Finland. 3rd National Symposium and Exposition on Dam Safety. October 10-12, 2012. Proceedings. Editors: Dr. Hasan Tosun, Dr. Murat Türköz & Dr. Hasan Savas. 646 p. Eskisihir, Turkey. pp. 15-19.

Finnish Environment Institute (2001). Rescdam. Final report. Grant Agreement No Subv. 99/52623. Helsinki, Finland. http://ec.europa.eu/echo/civil_protection/civil/act_prog_rep/rescdam_rapportfin.pdf

I - 91

Page 92: Study of Social and Economic Impacts of Construction of ...

La Romaine Hydroelectric Complex, Canada hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj Management of the Riparian flow at Romaine 2

2(14pt)

during construction and reservoir filling

Jean-Pierre Tournier, Luc Roy, Redha Kara & Isabelle Thériault Hydro-Québec Équipement et services partagés, Montréal, Canada

[email protected]

ABSTRACT

Hydro-Québec is developing the Hydroelectric Complex of La Romaine, on the North shore of the

St Lawrence River, in Quebec, Canada. The project consists of building 4 generating stations with

a total installed capacity of 1550 MW and an energy output of 8 TWh. Environmental studies and

measures carried out before, during and after construction until 2040 will cost over $385 million

altogether.

The construction of the Complex started with the Romaine-2 facility, which will be commissioned

in 2014. Romaine-2 reservoir filling is planned to begin with the spring flood of 2014. Planning of

the reservoir filling and design of the outlet works present many challenges due to the riparian flow

requirements that have to be met and the important variation of the reservoir level during filling.

Hydro-Québec managed to find an environmentally acceptable, cost effective and reliable solution

to meet this requirement: riparian flows required during Romaine-2 reservoir filling will be

provided by three different structures that define the three phases of the reservoir filling: diversion,

dedicated structure and spillway.

The Romaine-2 river diversion is more complex than many previous diversions conducted in the

past 40 years, since it will be used to modulate discharge during the first phase of the reservoir

filling. A dedicated structure was required to ensure a minimum flow for the whole water level

range during the second phase of Romaine-2 reservoir filling. It will be, in fact, the first time that

Hydro-Québec (HQ) will simultaneously water up a reservoir against an asphalt core dam, use the

diversion gate to modulate discharge, use a temporary structure to fulfill the riparian flow

requirements and proceed to reservoir filling in three phases.

Keywords: Romaine Hydroelectric complex, Reservoir filling, ecological flow, riparian flow,

Diversion.

I - 92

Page 93: Study of Social and Economic Impacts of Construction of ...

1. ROMAINE-2 HYDROELECTRIC FACILITY

The La Romaine hydroelectric complex is located on the North Shore region of the Saint-

Lawrence river in the province of Québec (Canada). The project consists in building four

generating stations with a total installed capacity of 1550 MW and an annual energy

output of 8 TWh (see Figures 1 & 2).

Romaine-2 is the first facility to be developed and the first kilowatt is expected to be

produced in 2014. The project will continue with the construction of Romaine-1 and

Romaine-3 facilities and finally, Romaine-4, which should produce its first kilowatts in

2020. The total cost of the power generation project (without transmission infrastructure)

is estimated at $6,5 billion CAD (Alicescu and al., 2013).

The Romaine-2 layout includes a powerhouse equipped with two Francis generating units.

The nominal installed capacity is 320 MW for each unit. The headrace tunnel is 5.5 km

long and conveys the water from the intake structure to the powerhouse. The reservoir

closure is ensured by a 110 m high main dam and six dikes with heights up to 80 m

(asphalt core type). The main dam crosses the Romaine River at KP 90.4 and will create a

reservoir of approximately 86 km2 at the full supply level of 243.8 m.

On the left abutment of the dam, the spillway is equipped with three gated passages and

has a capacity of 3000 m3/s at full supply level. On the right abutment of the dam, one

finds the temporary diversion structure and an intake tunnel for the dedicated structure to

provide ecological flow during reservoir filling.

2. ROMAINE HYDROLOGICAL REGIME AND RIPARIAN FLOWS

The total catchment area of the Romaine river is 14 500 km² at the mouth of the Saint

Lawrence river. At its source, between the 440th and 217th kilometers, the Romaine river

has a long mildly longitudinal profile. Immediately upstream from the Romaine-4 dam to

the downstream of the Romaine-2 power plant, the river is deeply coffered on high rock

surfaces. On this portion, the river presents a high elevation difference which is close to

300 m with a steep slope. The large waterfall located at KP 52.5 marks the beginning of

the coastal plain. On this portion, the river is punctuated by a few rapids, but most of them

have a milder slope.

The hydrological regime of the Romaine River has been documented since 1956. A

hydrometric station belonging to the Centre d’Expertise Hydrique du Quèbec is located

16 kilometers from the mouth of the river. The area drained at this station is estimated at

13 140 km² and the average annual flow is 288 m³/s.

The Romaine-2 dam is built at KP 90.5 of the river and the catchment at this location has a

total area of 12 200 km². The average annual flow is 270 m³/s. A hydrometric station

operating at this location since 2001 shows that the natural hydrological regime is closely

correlated to the one measured at the kilometer 16 of the river. This allowed the production

of a long series of daily flows which were representative of the hydrological regime at

Romaine-2. Figure 3 shows superimposed hydrographs representing the cumulative natural

flow of the Romaine-2 site for the years 1956 to 2010.

I - 93

Page 94: Study of Social and Economic Impacts of Construction of ...

Figure 1. La Romaine Hydroelectric Complex, with its four facilities

Figure 2. Schematic Profile of La Romaine Hydroelectric Complex

I - 94

Page 95: Study of Social and Economic Impacts of Construction of ...

The hydrological regime of the Romaine River is characterized by important flows during

the spring flood caused by the melting of the accumulated snow during winter. The flood

begins on average at the end of April and the flows remain higher than the average flow

until the end of June. The peak of the flood is attained around the end of May; at that time

the average maximum flow will be 1450m³/s at this location. The summer/fall regime is

characterized by low flow and floods caused by rainfall resulting in large flow variability.

The winter regime is characterized by low flow generally at the beginning of December.

The minimum flow generally occurs in mid-April and varies between 35 and 85 m³/s

depending on the year.

The operation of the hydroelectric scheme for the entire La Romaine complex will change

the hydrological regime of the Romaine river, this will occur as soon as the Romaine-2 site

becomes operational in 2014. The reservoir levels will generally be close to the maximum

operating level in the month of December. This will favor a larger production of electricity

during the winter months, where the demand for energy increases significantly. Reservoir

management foresees a progressive drawdown during winter; the objective is to have

access to a large portion of the active storage before the spring flood. The turbined flows

during the spring floods will be closer to the maximum power plant capacity. The

reservoirs will fill rapidly during the spring flood and the spillways could be used during

more important floods. During the summer/fall period, the reservoirs will be operating with

the purpose of optimizing the hydroelectric output of the complex within the operating

constraints (dam safety, environmental needs).

Figure 3. Daily flows hydrographs reconstructed at Romaine-2 for the period 1956-2010

0

500

1000

1500

2000

2500

01 02 03 04 05 06 07 08 09 10 11 12Month

Flo

w (

m³/

s)

I - 95

Page 96: Study of Social and Economic Impacts of Construction of ...

In order to favor the natural habitat and favorable living conditions of aquatic species, an

ecological flow regime has been established for the Romaine complex. The basic principle

that has been adopted is to guarantee a minimum flow from KP 51.5 located downstream

of the Romaine-1 site. In fact, downstream of Romaine-1 all the way to the river mouth,

the water level is not influenced by a structure and the hydraulic conditions depend

essentially on the outflow from the upstream site.

The ecological flow regime was established following the environmental impact study,

which included an inventory of the present aquatic species, the surveying of many potential

sites or the inventory of aquatic habitats and the hydraulic modeling which allows

evaluating the area of productive aquatic habitats for different flow conditions.

The minimum required flow varies according to a specific period of the year and its

amplitude depends on the biological function associated to that specific period. Table 1

presents the minimum flows required downstream of Romaine-1. These flows apply

primarily during the operational phase, as well as the particular requirement during the

filling period; this will be described in the next section.

Table 1. Minimum flow required downstream Romaine-1 (KP 51.5) after reservoir filling

Period Minimum flow Motive/Intention

November 16th to June 6th 140 m³/s Survival of fish eggs

June 7th to July 7th 200 m³/s Downstream migration of

fish

July 8th to October 15th 170 m³/s Alimentation

October 16th to November 15th 200 m³/s Spawning

3. ROMAINE-2 RESERVOIR FILLING AND OUTLET WORKS

At its maximum operating level, the Romaine-2 reservoir length will be around 65 km and

will cover a surface area of approximately 86 km2. To take advantage of the considerable

inflow during the spring period, the reservoir filling is planned to begin in April 2014. The

upstream water level at the beginning of the filling period will be around 146 m and must

reach the maximum operating level of 243.8 m, for a range close to 100 m. The

corresponding total volume of the reservoir is around 3 720 million cubic meters.

During the filling of the reservoir, Hydro-Quebec is committed to maintain a minimum

flow downstream of Romaine-1, based on the same principle adopted for the operation

phase. Nevertheless, the minimum required flows during the filling period can be different

from those presented in Table 1.

Due to the large variation of the water level during the filling period, planning and design

of the environmental flow release structures represented a great challenge. The structures

initially envisaged for the construction and operation phase, namely the temporary

diversion and the spillway, were supposed to be used also as flow release structures. But a

dedicated flow release structure was also needed to cover the entire range of water levels

outside the operation limits of the two other structures.

Hence, three structures are planned to ensure that during the filling period, the minimum

required flow at KP 51.5 is met. These three structures identify the 3 phases of the

reservoir filling. The minimum required flow for each phase, the design specifics of these

structures and their operation limits are summarised in the following sections.

I - 96

Page 97: Study of Social and Economic Impacts of Construction of ...

Figure 4. Layout of dam area with the outlet works for the 3 phases of Romaine-2 reservoir filling

Figure 5. Schematic view of the 3 phases of Romaine-2 reservoir filling

3.1 Phase 1: Diversion

The aim of the Romaine-2 temporary diversion is to allow an unrestricted flow of the river

during the construction period; the construction area is protected by cofferdams and the

enclosed area is pumped out creating a dry work environment. The diversion consists of a

tunnel dug through bedrock with a concrete intake structure equipped with gates allowing

the closure of the tunnel to begin the filling. The design flow capacity of the temporary

diversion is 2115 m3/s.

Phase 3

Phase 2

Phase 1

I - 97

Page 98: Study of Social and Economic Impacts of Construction of ...

During the first stage of filling, the minimum required flow downstream at KP 51.5 is

140 m3/s. When taking into account the different tributaries between Romaine-2 and

Romaine-1, the returned flow could be less. The temporary diversion was designed to

regulate the ecological flow during the first phase of filling.

The control of the environmental flow is achieved by manoeuvring one of the two

diversion gates; the gates are manoeuvred by a hoist system. Small scale models and

numerical models were conducted during the design phase to make sure that each structure

functioned properly, to determine the design criteria and to establish its operational mode.

Among the elements that were validated was the position of a hydraulic jump that takes

place downstream of the diversion gate. The position of the hydraulic jump was a critical

element during the design phase. To ensure that the hydraulic jump is far from the gate,

the intake concrete structure was placed asymmetrically with respect to the tunnel

alignment. The gate used for flow regulation and the tunnel are in the same flow axis.

Besides the geometry, the position of the hydraulic jump is a function of the outflow and

the hydraulic head or the upstream water level. The tests on the small scale models were

conducted under different condition to identify the minimal required gate opening as a

function of the upstream water level to ensure that the hydraulic jump takes places at least

6 meters from the gate. The maximum pressures and speeds at different location in the

diversion channel were also measured for the design of mechanical equipment.

The temporary diversion operational mode was established to ensure an environmental

flow during phase 1 of the Romaine-2 reservoir filling .The filling can begin once a

minimum inflow of 250 m3/s is reached, in other terms, once the inflow is larger than the

flow that needs to be released via the diversion. The minimum water level required to use

the temporary diversion for the release of the environmental flow was set at 148 m. To

reach this level, a short period of time with the gates closed is required; this duration is not

long enough for the KP 51.5 flow to drop below the minimum required mark. The

diversion gate that will be used for flow regulation shall thereafter be left partially open to

release a flow of 225 m3/s for an upstream level of 148 m. The gate opening will be

adjusted periodically with rising water levels. The temporary diversion will be used until

the water level reaches 165 m, the released flow at Romaine-2 will then be around

135 m3/s. The duration of this phase is 5 days on average but it can vary from 2 to 8 days

depending on hydrological conditions. The second phase of the filling can then begin and

the temporary diversion can be permanently closed.

3.2 Phase 2: Dedicated structure

For phase 2 of the reservoir filling, a new dedicated structure was built in order to provide

the minimal flow during that period. Given the characteristics of the spillway which was

planned for phase 3, the planned structure for phase 2 will have to be used with an

upstream water level varying between 165 m and 232 m. This considerable variation in the

hydraulic head influenced the mechanical equipment selection.

The flow to be provided at Romaine-2 during phase 2 of filling was another important

design criterion. During the feasibility studies and the different stages required to obtain

proper government authorizations, Hydro-Quebec analyzed different alternatives with the

aim of maintaining adequate conditions for the habitat of the aquatic species downstream,

while maintaining an acceptable filling rate to meet its project deadline.

I - 98

Page 99: Study of Social and Economic Impacts of Construction of ...

Considering that phase 2 of filling will coincide essentially with the spring flood period

and that a significant natural inflow will come from the tributaries downstream, an

ecological flow from Romaine-2 varying between 20 m³/s and 50 m³/s was accepted by

the governmental authorities. To provide the required maximum flow for the maximum

predicted hydraulic head, high head gates (Jet flow) were selected for this structure.

The selected gates and structure configuration should allow a simple and secure operation

during filling. The design of the equipment should be demonstrated within similar

operating conditions. Alike the temporary diversion, the hydraulic operating conditions of

this structure were analyzed numerically and on small scale model 1:25; the energy

dissipation downstream of the control gates was one of the main subjects of interest.

The selected configuration for this temporary diversion structure consisted of one tunnel

dug through bedrock with an entrance located near that of the diversion channel but at a

slightly higher level. This tunnel connects to the temporary diversion tunnel upstream of

the Romaine-2 main dam centerline (Figure 6).

Figure 6. Schematic view of the dedicated structure

The flow within the first section of the tunnel will be pressurized. Following this, the flow

will then be divided in the two conduits, each controlled by a gate installed in the gates

chamber. Thereafter, the flow falls into a plunge pool that discharges into a free-surface

flow tunnel connected to the temporary diversion tunnel.

For levels varying between 165 m and 179 m, the structure's two gates will be completely

open and provide a total flow varying between 35 m³/s and 50 m³/s depending on the

upstream level. Once the reservoir level reaches elevation 179 m, the gates will be closed

progressively in a symmetric way to maintain the flow close to 50 m³/s. As soon as the

level reaches 231.7 m, the spillway can be used and phase 2 will end with the closure of

the gates of the dedicated structure. This filling phase has an average duration of 37 days,

but it may vary between 22 and 100 days depending on the inflow.

I - 99

Page 100: Study of Social and Economic Impacts of Construction of ...

3.3 Phase 3: Spillway

The spillway is located on the left bank of the Romaine River. It has three gates of 8.85 m

width and the invert of the spillway is at elevation 228.3 m. The discharge capacity at the

maximum operating level of 243.8 m is 3000 m³/s. The spillway is capable of evacuating

the 1:10000 years flood with a maximum encroachment on freeboard of 0.3 m.

The use of the spillway to contribute to the minimum required flow requires that the

upstream level reaches a certain elevation which will allow restituting a sufficient

discharge. The minimum required flows at kilometer 51.5 for phase 3 of filling are listed in

table 2. For example, to restitute a 200 m³/s flow with three gates fully opened an upstream

level of 231.7m is required.

Table 2. Minimum flow required downstream Romaine-1 during stage 3 of reservoir filling

Period Minimum flow

April 1st to May 31

st 70 m³/s

June 1st to June 30th 140 m³/s

July 1st to September 30th 170 m³/s

October 1st to October 31st 200 m³/s

November 1st to end of the filling the less between 140 m³/s and the

natural flow at Romaine-1

Since the minimum required flows are defined for the downstream location of Romaine-1,

the spillway discharge may be set as a function of the natural inflows of the tributaries

downstream. The spillway gates can be used with partial openings; for example, an

opening of 1 m with a reservoir level at 243.8 m will provide approximately 100 m³/s flow

for each gate. Furthermore, when the first generating unit will be in operation, the outflow

will be provided by the powerhouse which will allow energy generation at Romaine-2.

The outflow of the Romaine-2 reservoir during phase 3 filling will vary primarily between

70 m³/s and 200 m³/s. However, once the maximum operating level is attained or during

an important flood, the released flow can be considerably higher. This filling phase will

last an average of 47 days but may also be completed in 10 days only in the case of high

inflow. Conversely of a low runoff occurs, phase 3 of filling will extend to the winter

period of 2014-2015 and will be completed only during the spring flood season of 2015.

4. FLOW CONDITIONS DOWNSTREAM DURING RESERVOIR FILLING

Numerical simulations of the Romaine-2 reservoir filling have been performed to establish

the hydraulic conditions for the different periods previously mentioned. These simulations

helped the designers identify the probable dates and durations of each of the filling phases.

Furthermore, by including the tributaries downstream of Romaine-2, the flows at specific

sites were available to establish hydrological conditions during the filling period. These

results were very useful for the design stage, for the environmental impact study and for

the planning of some construction works which will take place downstream of Romaine-2

during the filling.

I - 100

Page 101: Study of Social and Economic Impacts of Construction of ...

Maintaining the minimum flow during the filling of the Romaine-2 reservoir prevents 90

km of the river from drying.out Knowing that the flow values were determined after the

analysis of the aquatic wildlife needs; this attenuation measure limits the lowering of the

water level in the river in correlation to the natural conditions to a value which is between

0.6 m to 1.6 m depending on the location. This will also allow the navigation to be

maintained during the filling period for the most of the currently used segments.

CONCLUSION

In order to favor the natural habitat and living conditions of aquatic species, an ecological

flow regime was established following a thorough environmental impact study. Planning

of the reservoir filling and design of the outlet works presented many challenges due to the

riparian flow requirements and the important changes of reservoir level during filling.

Hydro-Quebec managed to find a solution environmentally acceptable, cost effective and

reliable. Ecological flows required during Romaine-2 reservoir filling will be provided by

three different structures: diversion tunnel, dedicated structure and spillway. It will be the

first time that Hydro-Québec will use the diversion gate to modulate discharge and will

use a dedicated temporary structure to provide the riparian flow requirements.

ACKNOWLEDGEMENTS

The authors wish to acknowledge Hydro Québec for permission to publish this article.

Appreciation is also extended to a number of colleagues for their support and willingness

to provide review and technical information.

REFERENCES

Alicescu, V., Tournier, J.-P., & Kara, R. (2013). Developing great hydroelectric projects

in a challenging social and economical environment: La Romaine complex, situated

in northern Quebec, Canada. Canadian Dam Association 2013 Annual Conference,

Montreal, Canada.

Bérubé M. (2013). Les principaux effets du complexe de la Romaine sur le milieu

aquatique. Canadian Dam Association 2013 Annual Conference, Montreal, Canada.

Génivar (2007). Complexe de la Romaine. Détermination du régime de débits réservés.

Rapport sectoriel. Hydro-Québec Équipement. Montréal, Canada.

Hydro-Québec (2007). Complexe de la Romaine. Étude d’impact sur l’environnement

(10 volumes). Hydro-Québec Production. Montréal, Canada.

Hydro-Québec (2009). Complexe de la Romaine. Réévaluation des impacts sur les

poissons et leurs habitats en présence d’un régime de débit réservé pendant la

seconde étape du remplissage Complément à l’étude d’impact sur l’environnement

du complexe de la Romaine. Hydro-Québec Production. Montréal, Canada.

I - 101

Page 102: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Technical, Socio-Economic and Environmental aspects

in converting Devsari H.E.P. (252MW)

from Storage to Run of the River Scheme

Deepak Nakhasi & Harsh Bhaskar Mehta SJVN Ltd, Shimla, India

[email protected]

ABSTRACT: India ranks third in the world after China, USA and Russia in terms of number of dams. India has so far constructed about 4818 large dams which have provided about 225 BCM of storage. Another 375 large dams with storages of about 63.9 BCM are under construction. Large dams in India alone are estimated to have submerged 37500 sq km of land area. About 10 million of people has been displaced or affected. While on one hand, storage schemes yield multipurpose benefits like irrigation, hydropower, flood and silt control, on the other hand various associated issues like environmental degradation, Resettlement and Rehabilitation and earthquake hazards also need proper attention and solution. More than 45,000 dams constructed around the world have helped many communities and countries’ economies in utilizing and harnessing water resources from half of the world’s dammed rivers. Dams supported 30- 40% of the entire irrigated area of the world and thus supported 12-16% global food production. Around 12% of all dams supply water for drinking and sanitation. The dams of 75 countries have a flood control function to safeguard nearby communities. But, the above mentioned benefits from dams are just one side of the story. On the other side are the social and environmental impacts. While Hydropower provides about 19% (2,650 TWh/yr) to more than half of 63 countries’ electricity supply, it can have adverse impacts on the environment and can be mitigated if well managed. Construction of Diversion dam as part of Run of the River development instead of Storage dam is one such solution. Devsari Hydro Electric Project (DHEP) in Uttarakhand, India was originally conceived as storage scheme with 90 m high concrete gravity dam having installed capacity and design energy as 300 MW and 856 MU respectively. However, in view of huge submergence involved (522 ha) and other technical and environmental issues, it was modified into a Run of the River (RoR) scheme with much less submergence (82 ha) having 35 m high concrete gravity dam with installed capacity of 252 MW. This paper discusses the various alternatives for arriving at the most optimum solution involving least submergence and maximum power benefits taking into considerations various technical, socio- economic and environmental issues involved. Key words: Hydropower, Technical, Socioeconomic, Environmental, Dam

I - 102

Page 103: Study of Social and Economic Impacts of Construction of ...

1. BRIEF DESCRIPTION OF DEVSARI HYDRO ELECTRIC PROJECT Devsari HEP is project located in Chamoli District of Uttrakahand having a installed capacity of 252 MW. It is located on River Pinder which originated from Pindari Glacier. It is run-of –the- river scheme with all components except dam and pothead yard, located underground. Its diversion structure 1.75 km downstream of confluence River Pinder and Kailganga is a concrete gravity dam 35 m (from river bed level) high, having five low level sluices to pass design discharge of 6969 cumec and facility for flushing of silt annually. The live storage of the Devsari dam reservoir with FRL at El 1300 m is 9.02 MCM .The reservoir shall also act as desilting basin. The head race tunnel carrying water to the surge shaft is 17.9 km long having 6.9 m diameter designed for discharge of 120.76 cumec. The surge shaft of 21.5 m diameter has a depth of 78 m. It is restricted orifice type. One steel lined vertical pressure shaft, 4.8 m dia having length of 248 m take off from the surge shaft and connect to three units of power plant after trifurcating into 2.77 m dia meter branches .Each of the three units are Francis turbine operating under rated head of 230.42 m utilizing a discharged of 120.76 cumec These are housed in an underground cavern of size 80 m(l)X20m(w)X 39.86 m(h).The layout of the project is shown.(see Fig. 1.) .

Figure1. Layout of the Devsari H.E.P., Uttarakhand

2. ALTERNATIVE STUDIES CONDUCTED FOR CONVERSION FROM STORAGE TO RUN-OF –THE RIVER SCHEME

Following four alternative studies were carried out taking into consideration Technical, Socio- economic and environmental factors

I - 103

Page 104: Study of Social and Economic Impacts of Construction of ...

• Alternative 1 90 m high dam at 1.75 km D/S of confluence of River Pinder and Kail Ganga having FRL= El 1370 m with TWL= El 1120 m and HRT Length =12.445 km

• Alternative 2 60 m high dam at 1.75 km D/S of confluence of River Pinder and Kail Ganga having FRL= El 1325 m with TWL= El 1120 m and HRT length=12.445 km

• Alternative 3 35 m high dam at 1.75 km D/S of confluence of River Pinder and Kail Ganga having FRL = El 1300 m with TWL = El 1120 m and HRT length =12.445 km

• Alternative 4

35 m high dam at 1.75 km D/S of confluence of River Pinder and Kail Ganga having FRL =El 1300 m with TWL =El 1046.5 m and HRT length=17.9 km

3. ALTERNATIVE 1: 90 M HIGH DAM AT 1.75 KM D/S OF CONFLUENCE OF RIVER PINDER AND KAIL GANGA HAVING FRL= EL 1370 M WITH TWL= EL 1120 M AND HRT LENGTH =12.445 KM

3.1 Technical Considerations In this alternative, dam is located at 1.75 km D/S from confluence of Pinder river with Kailgnaga. In the PFR prepared for this alternative ,the installed capacity was 300 MW based on design discharge of 149.37 cumec .However during detailed studies conducted based on the topographical, hydrological and geological data it was found that installed capacity shall be 250 MW with following features given in table -1.

Table1. Features of the Alternative-1

Components Detail Installed Capacity 250 MW Dam Location 1.75 km d/s of confluence Dam height 90m -from river bed level FRL El 1370m Gross Storage 192 MCM Live Storage 83.5MCM HRT Length 12.445 km Design Discharge 120.76 cumec Powerhouse Location Downstream of Pranmati Nallah Tail water Level El 1120 m Design Energy 890MU

Besides the above factors, feasibility of constructing 90 m high dam at the present locations has been found to be unviable on following consideration:

I - 104

Page 105: Study of Social and Economic Impacts of Construction of ...

3.1.1 Geology Physical inspection of left bank at dam site shows that the river terraces deposits occupied 4-5m above river level almost 100m upstream of dam axis of left abutment. Also, along the dam axis, left abutment is occupied with slope wash materials and thereafter the rock appears to lie under a veneer of debris. The rock exposures are not visible at higher levels which indicate that lot of stripping will be required for the left abutment. The rocks are also traversed by three set of joints i.e., one set parallel to foliation with 2-3 cm opening and another two sets inclined and perpendicular to the foliation. The strike of foliation is northeast-southwest with 50°-60°dip in northwest direction i.e. dipping towards river side. The right bank occupied by an overburden of 12-15m thick slope wash material below the road level. Above the road level and along dam axis, exposure of augen gneiss/mylonitic gneiss with occasionally pyritiferous muscovite schists and micaceous quartzites with well-developed foliation joints are seen. Rocks are exposed on the right bank of river bed as well as on Debal-Tharali road section which is approximately 88m above the River bed level. The quartzite-phyllite sequence of rocks exposed at the site strikes N10E°-S10W° and dip 40° towards NW i.e. downstream. The rocks are traversed by few sets of joints. A thrust is observed near confluence of Kail Ganga and Pinder river and truncated by another fault which is aligned parallel to the Pinder river i.e. NW-SE direction(GSI, Dehradun, 2007). The Devsari HEP reservoir area is devoid of any lime/calcareous formations of highly previous gravelly material. The ground in this area contains fractured and sheared quartzite/phyllite and schists which are relative permeable. This may result in water loss from the reservoir if water level is increased above an altitude of El 1335m. There are no adverse features for seepage losses from the reservoir below this level. Hence, the geology of reservoir is not suitable for constructing a dam above El 1335 m, both in Kailganga valley and Pinder valley because of presence of multiple shears and disturbed rock strata. A fault trending NNE-SSW has been noticed along river Kail Ganga (see Fig 2). These disturbed strata on saturation with the filling of dam beyond El 1335 m may result in multiple slides and destabilization of both the banks in the reservoir. Since the rock/strata above El 1335m is not water tight and whole area cannot be treated, if water level is increased above El 1335m, this might result in heavy water loss from the reservoir.

I - 105

Page 106: Study of Social and Economic Impacts of Construction of ...

Figure2. Geological map of the reservoir area

3.2 Socio-economic considerations 3.2.1 Submergence The storage scheme with 90m dam height involves large submergence involving 522 ha of total land (203.6 ha of Agriculture Private land, 47 ha of Private scrub land, 182.7 ha of forest land and 88.7 ha of river bed). 13 villages were expected to be submerged. Besides the above villages, the storage scheme involved submergence of many historical/religious places and public structures such as Main road leading to Deval Market and other villages. This road goes upto the border connecting number of villages on route and is main road being used for Nanda Devi Raj Jat Yatra and Rupkund. It could have submeregd Nanda Devi Temple at Purna, Shiv mandir at Sailkhola village (1346m) and Shiv Mandir near Devsari bridge. The photographs showing the important structures/historical place are below (see Fig.3 and Fig.4)

I - 106

Page 107: Study of Social and Economic Impacts of Construction of ...

Figure3. Historical Nanda Devi Temple

Figure4.Historical Shiv Temple 3.3 Environmental Considerations The Pinder valley upstream of confluence is full of dense forest consisting of Deodar, Pine, Chir and the protected species viz. Banz Oak (the major species given below). The storage scheme will involve submergence/cutting of more than 20,000 trees.

I - 107

Page 108: Study of Social and Economic Impacts of Construction of ...

3.4 Discussions on Alternative-1 From studies carried out as mentioned above, it was decided that going ahead with a storage scheme having 90m high dam was not feasible from technical, socio-economic and environmental considerations. 4. ALTERNATIVE 2: 60 M HIGH DAM AT 1.75 KM D/S OF CONFLUENCE OF RIVER PINDER AND KAIL GANGA HAVING FRL= EL 1325 M WITH TWL= EL 1120 M AND HRT LENGTH=12.445 KM. 4.1 Technical considerations In this alternative study dam height has been considered 60m at the same location. With this alternative, the installed capacity of the project works out to 201 MW. Description of the Alternative -2 is shown in Table-2 below. Table2. Description of the Alternative 2

Components Details

Installed Capacity 201 MW Dam height(from river bed level) 60m Dam Location 1.75 km d/s of confluence FRL El 1325m HRT Length 12.445 km Design Discharge 120.76 cumec Powerhouse Location Downstream of Pranmati Nallah Tail water Level El 1120 m Design Energy 753.36MU

Besides lesser installed capacity, feasibility of constructing 60 m high dam at the present location has been found to be unviable on the grounds explained below. 4.1.1 Geology As discussed under alternate 1(a), the geology of the reservoir area was still not favorable for the construction of 60m high dam as many shears/discontinuities exposed in the Kailganga valleys around El + 1315m on the road to Melkhet near bridge may get activated by the water level of the reservoir resulting in multiple slides and destabilization of left bank of Kailganga river. 4.2 Socio-economic considerations 4.2.1 Submergence The scheme with 60m dam height involved submergence of 220 ha of total land involving 3 villages.

I - 108

Page 109: Study of Social and Economic Impacts of Construction of ...

This scheme also involved submergence of historical/religious places and public structures such as: Road leading from Dewal to Melkhet and beyond upto the border connecting number of villages shall get submerged at many reaches on route in addition to Nanda Devi Temple at Purna and Shiv Mandir near Devsari Bridge. 4.3 Environmental Considerations The upstream Pinder valley is full of dense forest consisting of Deodar, Pine, Chir and the protected species viz. Banz Oak (the major species given below). This scheme will still involve submergence/cutting of more than 10,000 trees. 4.4 Discussions on Alternative-2 From the studies carried out as mentioned above, it was opined clearly lead to conclusion that going ahead with a scheme with 60m high dam was also not feasible from Technical, socio-economic and environmental considerations as it would have involved submergence of religious/historical places and could be not favorable to local sentiments. 5. ALTERNATIVE 3: 35 M HIGH DAM AT 1.75 KM D/S OF CONFLUENCE OF RIVER PINDER AND KAIL GANGA HAVING FRL= EL 1300 M WITH TWL= EL 1120 M AND HRT LENGTH=12.445 KM 5.1 Technical Considerations Feasibility of constructing 35 m high dam at the present location is explained below: In this alternative study, dam height has been considered as 35m at the same location. With this alternative, the installed capacity of the project works out to 176 MW. Description of the Alternative 3 is shown in table: 3.

Table3. Description of the Alternative 3

Components Details Installed Capacity 176 MW Dam height(from river bed level) 35 m Dam Location 1.75 km d/s of confluence FRL El 1300m HRT Length 12.44 km Design Discharge 120.76 cumec Powerhouse Location Downstream of Pranmati Nallah Tail water Level El 1120m Design Energy 646 MU

I - 109

Page 110: Study of Social and Economic Impacts of Construction of ...

5.1.1 Geology The geology of the reservoir area with a 35m high dam was found favorable for the construction as most of the shears/discontinuities exposed in the Pinder and Kailganga valleys are above El 1315m. Whereas with 35 m high dam, the FRL remains at El 1300m as such and there is no chance of the shears/discontinuities getting charged by the reservoir level. On inspection from left bank of the Pinder river, it was noticed that rock is exposed upto the level of + 1300m on right bank and chances of water loss from the reservoir is negligible. 5.2 Socio-economic considerations 5.2.1 Submergence The storage scheme with 35 m dam height involves minimum submergence of 82 ha of total land including 12 ha of Agriculture Private land, 70 ha of forest land and a part of one Shoding village involving 26 families is being displaced. This scheme does not involve submergence of any historical/religious places and public structures.

5.3 Environmental Considerations This scheme involves cutting of only about 2000 trees in submergence area. 5.4 Discussions on Alternative-3 The studies carried out as mentioned above lead to conclusion that this alternative involved minimum submergence and was most viable dam height from Technical socio economic, and Environmental consideration. However, another alternative was considered to optimize energy generation discussed here under as Alternative No 4, in which power House has been shifted further downstream. 6. ALTERNATIVE 4: 35 M HIGH DAM AT 1.75 KM D/S OF CONFLUENCE OF RIVER PINDER AND KAIL GANGA HAVING FRL= EL 1300 M WITH TWL= EL 1046.5 M AND HRT LENGTH=17.9 KM 6.1 Technical considerations In this alternative study dam height has been considered as 35m at the same location but Power House was shifted downstream from the original location to Simli gad. With this alternative, the installed capacity of the project works out to 252 MW. Description of the alternative -4 is shown at table-4.

Table4. Description of the alternative 4

Components Details Installed Capacity 252 MW

I - 110

Page 111: Study of Social and Economic Impacts of Construction of ...

Dam height 35m -from river bed level Dam Location 1.75 km d/s of confluence

FRL El 1300 m HRT Length 17.903 km

Design Discharge 120.76 cumec Powerhouse Location Upstream of Simli Gaad

Tail water Level El 1046.45m Design Energy 937 MU

In this scheme, the dam location remained at the same place as mentioned in Alternative -3 and all the benefits of Alternative 3 were available for this alternative too. 6.2 Discussions on Alternative-4 The studies carried out with 35m high dam, as mentioned above, lead to conclusion that it was most viable scheme from Technical, Socio-economic, and Environmental aspects. 7. COMPARISON OF VARIOUS ALTERNATIVES

The comparison of the storage and RoR alternatives is summarized below (see table 5)

Table5. Comparison of various alternatives

Details Alternative 1 Alternative 2 Alternative 3 Alternative 4 Location 1.75 km d/s of

confluence 1.75 km d/s of confluence

1.75 km d/s of confluence

1.75 km d/s of confluence

Dam Height 90 m 60 m 35 m 35 m FRL El 1370m El 1325m El 1300m El 1300m MDDL El 1355m El 1310m EL 1295m El 1295 m Gross Storage

192MCM 65.32 MCM 9.02 MCM 9.02MCM

Live Storage 83.5 MCM 28.64 MCM 3.21 MCM 3.21 MCM HRT Length 12.445 km 12.445 km 12.445 km 17.9 km Design Discharge

120.76 cumec 120.76 cumec 120.76 cumec 120.76 cumec

Powerhouse Location

D/s of Pranmati Nallah

D/s of Pranmati Nallah

D/s of Pranmati Nallah

Near Simli gad

Installed capacity

250 MW 201 MW 176 MW 252 MW

Tail water level

El 1120m El 1120m El 1120m El 1046.5 m

Design Energy

890 MU 753.60 MU 646 MU 937 MU

I - 111

Page 112: Study of Social and Economic Impacts of Construction of ...

8. LOCATION UPSTREAM OF CONFLUENCE OF RIVER PINDER AND KAIL GANGA In addition to above alternative location upstream of the confluence was also studied taking into consideration technical, socio economic, environmental angle. Considering the above aspects, it was not feasible and viable to construct a high dam upstream of confluence on Pinder river upto Milikhet Village. Kailganga water will not be available for use and will remain unutilized. The available design discharge would be only about 87 cumec due to deduction of Kail ganga discharge which contribute 30% of discharge to the Pinder river below the confluence. With this design discharge, the installed capacity would be further reduced to 145 MW. With reduced inflows, it would have been uneconomical to construct a storage dam. 9. DISCUSSION AND CONCLUSION Keeping in view the various technical, Social-economic and Environmental considerations, Alternative 4 with 35 m high concrete dam having 17.9 km long HRT was considered for adoption. The installed capacity of the project shall be 252 MW and design energy of 937 MU. The submergence involved shall only be 82 ha with only 26 families of one village getting displaced. ACKNOWLEDGMENT This paper is made possible through the help and support from Site Engineers and Geologist of Devsari H.E.P, Tharali, Uttarakhand, India and colleagues in Civil Design Department, SJVN Ltd., Shimla, India. Our acknowledgment of gratitude toward the following significant advisors and contributors: We would like to thank Er.K.L.Aumta, AGM (Civil Design) and Er. Vinod Kumar, Sr. Engineer (Civil Design) for their most support and encouragement. They kindly read our paper and offered invaluable detailed advices on the theme and grammar of the paper. REFERENCES Report on studies conducted by SJVN Ltd on “Conversion of Storage scheme to RoR scheme“

as per observations of Standing Technical Committee(STC) submitted to CEA vide letter no SJVN /DHEP/CEA/11-239-241 dated 07/12/2011.

I - 112

Page 113: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Implementation of the Hydropower Sustainability Assessment Protocol:

ProProtocols:jsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf

fffffjfjjfkkfjjj

Romanche-Gavet’s project under construction in France

Emmanuel BRANCHE Senior Economist Engineer, Sustainable Development Department, Hydropower Division, EDF

[email protected]

ABSTRACT: The Hydropower Sustainability Assessment Protocol (HSAP) is a framework to assess the

performance of hydropower projects according to a defined set of sustainability topics,

encompassing environmental, social, technical, and financial issues. Developed by the

International Hydropower Association (IHA) in partnership with a range of government, civil

society and private sector stakeholders, the Protocol is a product of intensive and transparent

dialogue concerning the selection of sustainability topics and the definition of good and best

practice in each of these topics. The main objective of an official assessment is to obtain impartial

and verifiable findings on the performance of the project in relation to the sustainability issues set

out in the tool.

The Electricité de France (EDF) Romanche-Gavet project is a 94 MW project in the

implementation stage, located on the Romanche’s river in south-eastern France. The project will

replace six facilities on the Romanche River which were built in the early 20th century and have a

total capacity of 82 MW, thereby increasing average annual generation by over 30%.

An official assessment by external accredited assessors was carried out over the period May to

July 2013. This paper will present the sustainability profile of Romanche-Gavet’s project under

construction. It has relatively limited adverse environmental and social impacts, and has the

potential to deliver long term benefits for the local community. The findings of this assessment

reflect very high performance against the Protocol topics and criteria. EDF and its partners meet

this high level of performance through a combination of corporate management systems,

compliance with applicable legal requirements, and an open working relationship between the

EDF people and the local community.

Keywords: Sustainability, assessment, social & environmental, dam construction, governance,

stakeholder engagement and participation.

1. WHAT IS THE HYDROPOWER SUSTAINABILITY ASSESSMENT

PROTOCOL? [Blank line 10 pt]

1.1. Introduction

Hydropower is the world’s largest source of renewable energy and plays a vital role in

reducing the world’s dependence on carbon. As a renewable energy, it is important that

hydropower is also developed sustainably.

The Hydropower Sustainability Assessment Protocol (HSAP) is a new tool that promotes

and improves the sustainable use of hydropower. It provides a common language that

I - 113

Page 114: Study of Social and Economic Impacts of Construction of ...

allows governments, civil society, financial institutions and the hydropower sector to talk

about issues of sustainability.

The HSAP offers a way of assessing the performance of hydropower in more than 20

sustainability topics. Assessments are intended to be objective and are based on

documented evidence, and the results are presented in a standardized way, making it easy

to see how existing facilities are performing and how new projects are being developed.

The HSAP is a new tool that promotes and improves the sustainable use of hydropower. It

provides a common language that allows governments, civil society, financial institutions

and the hydropower sector to talk about issues of sustainability. The HSAP:

Is a framework for assessing the sustainability of hydropower projects,

Distils hydropower sustainability into more than 20 clearly-defined topics,

Provides a consistent, globally-applicable methodology,

Is governed by a multi-stakeholder Council,

Is regulated by a Charter and Terms and Conditions of use.

The Protocol is the result of intensive review from 2008 to 2010 by the Hydropower

Sustainability Assessment Forum. The Forum’s members came from: social and

environmental NGOs (Oxfam, The Nature Conservancy, Transparency International,

WWF); governments (China, Germany, Iceland, Norway, Zambia); commercial and

development banks (Equator Principles Financial Institutions, The World Bank

[observer]); and the hydropower sector, represented by IHA (International Hydropower

Association). Many of these organizations are now represented in the Hydropower

Sustainability Assessment Council.

1.2. The Structure of the HSAP

The HSAP can be used at any stage of hydropower development, from the very earliest

planning stages, right through to operation. It has also been designed to work on projects

and facilities anywhere in the world.

To assess the sustainability of hydropower projects at all stages of development, the

Protocol comprises five documents – a Background document and four assessment tools

for the different stages of the project life cycle as described in figure 1 below: [Blank line 10 pt

Figure 1. Protocol Assessment Tools and Major Decision Points [Blank line 10 pt

HSAP has been designed to work on projects and facilities anywhere in the world.

I - 114

Page 115: Study of Social and Economic Impacts of Construction of ...

1.3. The Sustainability Topics

Sustainable development requires people to look for synergies and trade-offs amongst

economic, social and environmental values. This balance should be achieved and ensured

in a transparent and accountable manner, taking advantage of expanding knowledge,

multiple perspectives, and new ideas and technologies.

Within each HSAP assessment tool is a set of topics important to forming a view on the

overall sustainability of that project at that point in its life cycle. Topics, when taken

together, provide the list of issues that must be considered to confidently form a view on

the overall sustainability of a hydropower project at a particular point in its life cycle.

The HSAP offers a way of assessing the performance of hydropower in more than 20

sustainability topics. Assessments are intended to be objective and are based on

documented evidence, and the results are presented in a standardized way, making it easy

to see how existing facilities are performing and how new projects are being developed.

The table 1 below shows some of the topics addressed during an assessment: [Blank line 10 pt

Table 1. Sustainability topics addressed during an assessment [Blank line 10 pt

Environmental Social Economic

Financial Technical Cross-Cutting

Biodiversity and

Invasive Species Indigenous People Financial Viability Siting and Design Climate Change

Water Quality Resettlement Economical

Viability

Hydrological

Resources Human Rights

Erosion

Sedimentation Public Health Project Benefits

Asset Reliability

and Efficiency Gender

Downstream Flow Cultural Heritage Procurement Infrastructure Safety Livelihoods

Blank line 10 pt]

1.4. The Sustainability Profile [Blank line 10 pt]

The Preparation, Implementation and Operation assessment tools enable development of a

sustainability profile for the project under assessment. For each topic, scoring statements

describe what should be exhibited by the project to address that important sustainability

issue. It is recognised that different organisations may have the primary responsibility for

different sustainability topics. Because it is likely that these responsibilities vary amongst

countries and at project life cycle stages, no specification on organisational responsibilities

is made in the HSAP scoring statements. It would be expected in the assessment reports to

indicate where organisational responsibilities lie.

In the Preparation, Implementation and Operation assessment tools, each topic is scored

from Level 1 to 5. The Level 3 and Level 5 statements provide meaningful and

recognisable levels of performance against which the other scores are calibrated.

Level 3 describes basic good practice on a particular sustainability topic. Level 3

statements have been designed with the idea that projects in all contexts should be working

toward such practice, even in regions with minimal resources or capacities or with projects

of smaller scales and complexities. Note that the HSAP does not state that Level 3 is a

standard that must be achieved; expectations on performance levels are defined by

organisations that make decisions or form views based on assessments.

Level 5 describes proven best practice on a particular sustainability issue that is

demonstrable in multiple country contexts. Level 5 statements have been designed with the

I - 115

Page 116: Study of Social and Economic Impacts of Construction of ...

idea that they are goals that are not easy to reach. However, they have been proven that

they can be attained in multiple country contexts, and not only by the largest projects with

the most resources at their disposal. 5s on all topics would be very difficult to reach,

because practical decisions need to be made on priorities for corporate/project objectives

and availability/allocation of resources (time, money, personnel) and effort.

The spider diagram provides a snapshot of how a project scores against the HSAP. This

sits at the front of a full assessment on each topic. This format allows for an overview of

the entire project as well as the ability to find more information on specific topics if

required. For each sustainability topic assessed, performance is scored from 1 to 5, with 5

being proven best-practice, and presented in an easy-to-read profile, as presented in figure

2 below on an illustrative case:

Figure 2. Spider diagram of an illustrative HSAP’s sustainability profile

1.5. The Governance

The Protocol will be overseen by the Hydropower Sustainability Assessment Council, a

multi-stakeholder body building on the success of the Forum that helped the International

Hydropower Association (IHA) develop the Protocol.

The Council will include representatives from social and community organisations,

environmental organisations, governments from around the world, banks and investors,

and the hydropower sector.

The Council will work to ensure that all voices are heard with regard to the use of the

Protocol and its future development.

It will make decisions by consensus, and follow principles of transparency and goodwill.

I - 116

Page 117: Study of Social and Economic Impacts of Construction of ...

The Council will be formed of several Chambers, each reporting back to the elected

Governance Committee. The Governance Committee is responsible for upholding the

integrity of the HSAP and its use.

IHA acts as a Management Entity within the Council. IHA is responsible for day-to-day

operations, as well as other tasks such as overseeing training and accreditation in the use of

the HSAP and serving as the secretariat for the Governance Committee.

2. SUSTAINABILITY ASSESSMENT OF ROMANCHE-GAVET [Blank line 10 pt]

2.1. Presentation of Romanche-Gavet project

The Romanche‐Gavet project is a 94 MW project in the implementation stage, located on

the right bank of the middle section of the Romanche river, 30 km from Grenoble, in the

Isère department in south‐eastern France.

The project will replace six facilities on the Romanche River which were built in the early

20th century and have a total capacity of 82 MW. Romanche‐Gavet has an expected

average generation output of 560 GWh/yr, greater than the average output of 405 GWh of

the six facilities to be replaced.

Under the French concession system, the French State remains the owner of the facilities.

A range of governmental and regulatory authorities are also involved in the preparation

and implementation of the new project, and the decommissioning of the existing plants.

EDF (Électricité de France SA) holds two concessions concerning the Romanche‐Gavet

project:

Concession ‘Moyenne Romanche’ (middle Romanche) to operate the six existing

plants, with decommissioning required by 2020;

Concession ‘Gavet’ for the construction of the new plant, and its operation until

2070. The main features of the new plant are:

o Head of 270 m;

o An intake with a maximum capacity of 41 m3/s;

o A headrace tunnel, 9.3 km in length and 4.7 m in diameter;

o A vertical surge shaft, 180 m deep with an excavated diameter of 5 m;

o A steel‐lined pressure shaft, 170 m deep and 3.3 m in diameter;

o An underground power plant excavated 160 m below ground;

o Two Francis turbines of 47 MW;

o A tailrace tunnel, 170 m in length with an excavated diameter of 5.3 m;

o Outlet structures consisting of a regulating weir and gates, and a concrete

structure housing four energy dissipators; and

o A new 63 kV transmission line.

Apart from the intake and outlet structures and the transmission line, all structures of the

project will be wholly underground. The transmission line will be partially underground.

The reservoir will have an insignificant capacity, but will be kept level at El 705, and the

plant will be operated as run‐of‐river.

The facilities to be decommissioned are, from upstream to downstream: Livet, Les Vernes,

Les Roberts, Riouperoux, Les Clavaux, and Pierre Eybesse. The structures to be removed

will include power intakes, galleries, headrace channels, penstocks, powerhouses,

generating units and transmission lines.

The Figure 3 below presents a schematic view of the Romanche-Gavet’s project.

I - 117

Page 118: Study of Social and Economic Impacts of Construction of ...

Figure 3. Schematic view of Gavet-Romanche’s project

Implementation and operation of the new plant, and decommissioning of the old plants is

managed by Unité de Production Alpes (UP Alpes), one of five units of production

(corresponding to regions of France) in EDF’s Hydropower Generation and Engineering

Division (Division Production Ingénierie Hydraulique, DPIH). UP Alpes is the region for

the northern Alps.

UP Alpes has commissioned the DPIH’s Centre d’Ingénierie Hydraulique (CIH) to manage

implementation of the new plant and decommissioning, through two separate projects.

EDF is part of the multinational EDF Group, which also owns or has holdings in

transmission companies in France, and utilities across Europe and internationally. EDF

Group is 80% owned by the French State.

2.2. EDF’s objectives for this assessment

EDF, as a Sustainability Partner of IHA, has received capacity building around the

Protocol. This assessment took part within the Hydro4LIFE program (a European

Commission-funded project to assist the implementation of the Protocol in the European

Union Life+).

The main objective of an official assessment is to obtain impartial and verifiable findings

on the performance of the Romanche‐Gavet project in relation to the sustainability issues

set out in the implementation and preparation tools.

In addition to this main goal for the assessment of Romanche‐Gavet EDF expects:

To identify how appropriate the HSAP is for EDF and France in general;

To benchmark EDF to international companies and best practices;

To evaluate the sustainability of the Romanche‐Gavet project (the biggest project in

development in France) by preparing this official assessment;

To identify risks and thus to find improvement opportunities in the project both

during construction phase of the new plant and preparation of the decommissioning

of the six existing HPPs; and

To ensure transparency of the project and engagement of stakeholders.

I - 118

Page 119: Study of Social and Economic Impacts of Construction of ...

2.3. The Assessment Process

The assessment has been conducted using the Implementation assessment tool, which

contains 20 individual topics addressing governance, technical, financial, social and

environmental issues.

It is important to note that this assessment addresses the entire Romanche‐Gavet project,

including both the new project that is under implementation, and the decommissioning

project which is under preparation.

Reference has been made to the Preparation tool in specific cases where it offers relevant

additional guidance for the assessment of the decommissioning project.

This assessment was carried out as part of the IHA – EDF Sustainability Partnership. IHA

provided a team of independent accredited assessors to conduct the assessment. The on‐site

phase was conducted over 10‐14 June 2013, and comprised a site visit, and interviews held

mainly at the Gavet Maison Romanche Energie and in Grenoble, but also at Saint Egreve,

Vif, and videoconference with Paris and the University of Liège in Belgium.

There were 46 people interviewed within 41 meetings during the on-site assessment:

Internal EDF: 12

External EDF: 34 (AAPPMA, ABF, Agence Eau Rhône-Mediterranée-Corse, AIG,

Alstom, APAVE, Association Patrimoine Romanche, CBR, CG38, CLE,

Conservatoire d'espaces naturels Isère – Avenir, DREAL, FRAPNA, habitant de

Gavet, maire-adjoint de Gavet, GC Conseil, Mission locale, ONEMA, Musée de

Rioupéroux, SIERG, SPIE, Médecine du travail, Université de Liège, VCT).

It should be noted that 354 documents have been presented and considered as evidences for

this official assessment.

2.3. The findings of this assessment for Romanche-Gavet

Romanche‐Gavet has relatively limited adverse environmental and social impacts, and has

the potential to deliver long term benefits for the local community. The design of the

project directly addresses the need to reduce adverse impacts of hydropower generation in

the Romanche valley through the removal of the old plants and water transport

infrastructure, improvement in conditions for recreation and tourism, and use of some of

the decommissioned plants for cultural heritage conservation or economic purposes.

The findings of this assessment reflect very high performance against the Protocol topics

and criteria. EDF and its partners meet this high level of performance through a

combination of EDF’s corporate management systems, careful compliance with applicable

legal requirements, and an open working relationship between the EDF project office and

the local community.

Romanche‐Gavet satisfies the Protocol’s criteria of ‘proven best practice’ on eleven out of

eighteen topics: Communications and Consultation; Integrated Project Management,

Infrastructure Safety; Financial Viability; Project Benefits; Procurement; Project‐affected

Communities and Livelihoods; Public Health; Biodiversity and Invasive Species;

Reservoir Preparation and Filling; and Downstream Flow Regimes.

It meets or exceeds the Protocol’s criteria of ‘basic good practice’ on all remaining topics.

On six of these, basic good practice is exceeded, owing to only one significant gap against

proven best practice. Most of these gaps concern the absence of management processes to

anticipate and respond to opportunities that become evident during implementation (on the

Management criterion of the Protocol).

I - 119

Page 120: Study of Social and Economic Impacts of Construction of ...

One remaining topics performs with two gaps against proven best practice, resulting in a

score equal to basic good practice under the Protocol’s scoring system. On I‐13 Cultural

Heritage, there is an absence of adequate processes both to respond to the risk that EDF

will be required by its concession obligations to destroy heritage, and to respond to the

opportunity to conserve heritage for the economic development of the valley (on the

Management criterion). In addition, there are no plans to mitigate the loss of some of less

valued components of the heritage of the decommissioned plants (Outcomes criterion).

EDF is not the owner of the facilities, and these gaps are not a reflection on EDF’s

performance, but result from the authorities’ governance of the decommissioning process.

As described above, the performance of the Romanche-Gavet project is very high. The

results show a striking pattern: no significant gaps on the Stakeholder Engagement,

Stakeholder Support, and Conformance/ Compliance criteria; very few on Assessment and

Outcomes; and on the Management criterion, gaps across a number of topics that reflect

the absence of processes to anticipate and respond to opportunities, which at a level of

proven best practice is defined as beyond what a project would be required to do manage

its impacts responsibly.

Two topics, I‐10 Resettlement and I‐11 Indigenous Peoples, are Not Relevant to

Romanche‐Gavet. The scores for all topics are summarized in the following Figure 4 that

presents the sustainability profile of this project:

Figure 4. Sustainability Profile of Romanche-Gavet project

This spider diagram provides the sustainability profile of the project, i.e. a snapshot of how

the project scores against the HSAP. A score of 5 represents the proven best-practice, and

3 the basic-good-practice.

Protocol assessments in the public domain are shown on the HSAP website. Comments on

those reports can be made within 60 days of their publication date. It should be noted that

I - 120

Page 121: Study of Social and Economic Impacts of Construction of ...

no comments were received for the Romanche-Gavet project by public, NGO, etc. during

this period of comments.

3. CONCLUSIONS [Blank line 10 pt]

Hydropower utilities (developers and operators) face challenges in proving the

sustainability of their projects. There is broad agreement among industry experts that

sustainability is not as easily quantified as engineering or economics. In addition,

measuring the impact of sustainability on the financial performance of a business/strategy

is a similarly difficult task.

Based on this first EDF’s hydropower official assessment, the HSAP provides a conclusive

framework for communicating sustainability topics both internally and with the public at

large.

The Romanche-Gavet’s assessment succeeded in identifying concrete value drivers, and

insights gained during its pioneering execution in France might pave the way for

embedding the HSAP into gated project decision-making processes. [Blank line 10 pt]

[Blank line 10 pt]

ACKNOWLEDGEMENT Emmanuel BRANCHE would like to thank all EDF staff involved, and all EDF interviewees and

external interviewees that accepted participating in this official assessment, and providing their

time to gather and provide a wealth of evidence. The author also would like to thank the assessment

team for its tremendous work (Doug Smith, Senior Sustainability Specialist, International

Hydropower Association; Simon Howard, Sustainability Specialist, International Hydropower

Association; Dr Bernt Rydgren, ÅF Industry; Inger Poveda Björklund, Senior Consultant, ÅF

Hydropower). [Blank line 9 pt]

[Blank line 9 pt]

REFERENCES [Blank line 9 pt]

IHA. (2011): Hydropower Sustainability Assessment Protocol, International Hydropower

Association , November 2010 The full report could be downloaded for free at:

http://www.hydrosustainability.org/getattachment/7e212656-9d26-4ebc-96b8-1f27eaebc2ed/The-

Hydropower-Sustainability-Assessment-Protocol.aspx Smith, D, Howard, S, Rydgren, B and Poveda Björklund, I. (2013): Hydropower

Sustainability Assessment Protocol - Official Assessment EDF Romanche-Gavet

France Final, Hydropower Sustainability Assessment Accredited Assessors,

September 2013 The full report could be downloaded at:

http://www.hydrosustainability.org/IHAHydro4Life/media/ProtocolAssessments/PDF%20Reports/Ro

manche-Gavet-Final-Report-18-Sep-2013.pdf?ext=.pdf

I - 121

Page 122: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Silvan Project

Implementation by Participation and Impacts on the Society, Economy and Environment

Önder Özen

Deputy Coordinator, Dam Projects Coordination Department, İLCİ Holding & TRCOLD Member, Ankara, Turkey [email protected]

Ergün Üzücek Head of Dams and HEPPs, General Directorate of State Hydraulic Works & TRCOLD Member, Ankara, Turkey

Tuncer Dinçergök Deputy Head of Dams and HEPPs, General Directorate of State Hydraulic Works & TRCOLD Secretary General, Ankara, Turkey

ABSTRACT Turkey, being one of the leading countries in terms of hydro potential development, has numerous completed and ongoing projects ranging from small hydro schemes to large hydro schemes. The Southeastern Anatolian Project (GAP) is one of the World’s biggest social and economic development projects including 22 dams and 19 HEPPs which will create an irrigable land of 18’000 km2 by utilizing the hydro potential of Euphrates and Tigris rivers. With an approximate investment value of $3.5 billion, Silvan Project, located in Diyarbakır, Turkey, is one of the largest components of GAP and is the last step to complete GAP. The project includes 8 dams, 1 hydropower station, 242’000 meters of irrigation channel, 2 tunnels with a total length of 15’360 meters and 21 pumping stations. After completion, the project will create 2’570 km2 of irrigable land, employment opportunity to 320’000 people and will have a great impact on the social and the economic development of the region. The annual income is estimated to be $63 million from energy production and $460 million for the agricultural development. Taking into consideration the social impacts combining with the economic development, it is upmost importance that the Governmental Institutions and the Public cooperate at the upmost level to realize the project as soon as possible. This paper focuses on the steps taken by the Government for the public and private sector participation in the project and the effects on society and the government in terms of social, economic and environmental factors. Keywords: Development, Public & Private Sector Participation 1. INTRODUCTION Silvan Project, being one of the largest components of Southeastern Anatolian Project (GAP), was initially planned as a water resources development package within the framework of a development program in provinces of Southeastern Turkey in the 1970’s.

I - 122

Page 123: Study of Social and Economic Impacts of Construction of ...

Within time, the project has evolved to a multi-sectoral, socio-economic development program in the 1980’s. The Silvan Scheme has finalized in 2001 with Southeastern Anatolian Project Silvan Project Planning Report. The project has been implemented by State Hydraulic Works of Turkey (DSİ) and GAP Regional Development Administration (GAP-RDA), a separate entity responsible for the coordination of development of the Region in terms of economic, social and environmental development. Once completed, Silvan Project will create an irrigable land of 2’570 km2, employment opportunity to 320’000 people and annual income of $63 million and $460 million from energy production and agricultural development, respectively. 2. PROJECT DEFINITION Silvan Project is located in Silvan of Diyarbakır, Turkey. The main purpose of the project is to increase the development level of the region by utilizing the hydro potential of Ambar, Kuruçay, Pamukçay, Salat, Sinan and Batman creeks, which are tributaries of Tigris River. The project includes 8 dams, 1 hydropower station, 242’000 meters of irrigation channel, 2 water conveying tunnels with a total length of 15’360 meters and 21 pumping stations. Table 1 summarizes the main components and Figure 1 shows the general layout of Silvan Project. Table 1. Main components of Silvan Project

Component Short Information Silvan Dam and HEPP Concrete faced rock fill dam with a height of 174.5 meters.

Hydropower plant has an installed capacity of 160 MW with an annual energy production of 681 GWh. The storage capacity is 6’840 hm3 and will irrigate a land of 2’454 km2.

Babakaya Water Conveying Tunnel

TBM twin tunnels with an internal diameter of 7.00 meters and length of 10’210 meters.

Silvan Water Conveying Tunnel

TBM twin tunnels with an internal diameter of 7.00 meters and length of 5’150 meters.

Irrigation Channels Irrigation channels with a total length of 242’000 meters. Karacalar Storage Dam Clay core rock fill dam with a height of 33.5 meters with a storage

capacity of 24.49 hm3 and will irrigate a land of 51 km2. Kıbrıs Storage Dam Clay core rock fill dam with a height of 33.5 meters with a storage

capacity of 14.24 hm3 and will irrigate a land of 31 km2. Bulaklıdere Storage Dam Clay core rock fill dam with a height of 31.0 meters with a storage

capacity of 24.49 hm3 and will irrigate a land of 59 km2. Başlar Storage Dam Clay core rock fill dam with a height of 25.5 meters with a storage

capacity of 28.87 hm3 and will irrigate a land of 43 km2. Pamukçay Storage Dam Clay core rock fill dam with a height of 31.5 meters with a storage

capacity of 37.60 hm3 and will irrigate a land of 51 km2. Kuruçay Storage Dam Clay core rock fill dam with a height of 32.0 meters with a storage

capacity of 43.27 hm3 and will irrigate a land of 60 km2. Ambar Storage Dam Clay core rock fill dam with a height of 41.0 meters with a storage

capacity of 132.11 hm3 and will irrigate a land of 135 km2. Pumping Stations Various pumping stations with pumping capacities ranging from 0.5

m3/s to 26.36 m3/s.

I - 123

Page 124: Study of Social and Economic Impacts of Construction of ...

Figure 1. General layout of Silvan Project The majority of water which will be utilized for irrigation will be obtained from Silvan Dam reservoir (Silvan Dam itself will irrigate an area of 2’024 km2 and also support the storage dams for an irrigation area of 431 km2). The water will be taken from the reservoir by Babakaya and Silvan Tunnels and will be distributed to the west and east side of the main channel. The capacity of the east side main channel is 5.38 m3/s with a length of 15’773 meters and the capacity of the west side main channel is 208.32 m3/s with a length of 116’534 meters. Additionally, a channel with a capacity of 26.36 m3/s with a length of 126’846 meters will be constructed for pumping irrigation. The storage dams will also have irrigation channels with capacities ranging from 0.79 m3/s to 15.21 m3/s. Silvan Project includes construction of numerous dams and long channels with water distribution pipelines. Since construction of such a project requires a lot of money and time, the project is divided into 4 stages defined in time intervals of 6 years. Within completion of each stage, some part of the land will be able to be irrigated. Since the development will be in stages, the amount of water that will be conveyed from Silvan Reservoir will be increased in time, thus the energy production of Silvan Dam will decrease from 681 GWh to 88.41 GWh. Table 2 shows the development stages of the project. Figure 2 and Figure 3 shows the irrigable land amount for each stage and water usage, respectively. Table 2. Development stages of Silvan Project

Stage Development Plan Stage 1 Silvan Dam and HEPP

Babakaya and Silvan Tunnels Silvan east and west main channels construction starts

Stage 2 Karacalar, Kıbrıs, Bulaklıdere and Başlar storage dams and related components

I - 124

Page 125: Study of Social and Economic Impacts of Construction of ...

71.6 km of west main channel and related components East main channel and related components

Stage 3 Pamukçay, Kuruçay and Ambar storage dams and related components West main channel Various pumping facilities

Stage 4 P5 pumping irrigation and related components

Figure 2. Total irrigable land for each stage

Figure 3. Water usage for irrigation and energy production for each stage 3. AIMS OF THE PROJECT Being one of the major components of GAP, Silvan Project is a multi-sectoral development project which will utilize the water potential of Tigris River’s creeks for a sustainable development for irrigation, flood control, drought control and hydropower generation for Silvan, Diyarbakır area. Being an integrated project, the project aims to improve economic development as well as the social development. The development areas can be divided into 3 categories; agricultural development, industrial development and social development. The main aims of Silvan Project are given as follows:

Stage 1 Stage 2 Stage 3 Stage 4

To

tal i

rrig

able

lan

d (

km

2 )

0

500

1000

1500

2000

2500

3000

857

2143

2570

Stage 1 Stage 2 Stage 3 Stage 4

0

500

1000

1500

2000

2500

IrrigationEnergy

Wat

er u

sag

e (m

illio

n3/y

ear

)

0

654

2056

450

1597

1791

1410

254

I - 125

Page 126: Study of Social and Economic Impacts of Construction of ...

Management and development of water resources for irrigation, industrial and urban purposes

Improvement of land usage by optimizing crop patterns and agricultural applications Promoting agro-industry Increase the level of social services, education and employment opportunities 4. CURRENT STATUS OF THE PROJECT As stated in Chapter 2, the project is planned to be developed in stages since it is a large scale and multi sectoral huge project which requires an investment time of about 20 years and cost of $3.5 billion. Although the global economic crisis has some effect on the project finance, the construction works as defined in the stages of the project are ongoing and summarized in Table 3. As can be inferred from the table, there are some deviations from the original plan. The reason for this deviation is to utilize some of the storage dams earlier than planned so that the irrigation operations planned for these dams can be started as early as possible without Silvan Reservoirs contribution. Since the irrigation capacities will not be maximized until Silvan Reservoir contribution is completed, the overall benefits and planning will not be affected, however the society will get used to new and modern agricultural methods. Table 3. Current status of the Project

Component Construction Status Silvan Dam and HEPP The construction has started in year 2012 and planned to be

completed in year 2016. Silvan Tunnel The construction has started in year 2012 and planned to be

completed in year 2017. Babakaya Tunnel The construction has started in year 2012 and planned to be

completed in year 2015. Pamukçay Dam The construction has started in year 2010 and completed in year

2013. Ambar Dam The construction has started in year 2011 and planned to be

completed in year 2015. Figure 4 shows some photos from the ongoing construction works for Silvan, Pamukçay and Ambar dams and Silvan Tunnel, respectively. 5. PROJECT IMPLEMENTATION STRATEGIES As part of Southeastern Anatolian Project, Silvan Project is an integrated sustainable socio-economic development project focusing on investments end development in agriculture, industry, education, health and infrastructure building both urban and rural. After completion, the project will create 2’570 km2 of irrigable land, employment opportunity to 320’000 people and will have a great impact on the social and economic development of the region. Taking into consideration the social impacts combining with the economic development, it is upmost importance, even an obligation, that the Governmental Institutions and the Public cooperate and coordinate at the upmost level to realize the project as soon as and as effective as possible.

I - 126

Page 127: Study of Social and Economic Impacts of Construction of ...

Figure 3. Some photos from the Silvan Project construction works In addition to the Government and Public cooperation, it is also compulsory to attract private sector to the region so that the economic development and rapid increase in employment speed is maximized. To be able to achieve this aim, not only the hydro potential should be developed but also the transportation, energy, industrial and urban infrastructure services so that access of firms to financing sources, building incentive mechanisms in line with the production features of the region, making services by other agencies in the region more effective are improved. Taking into consideration interaction of such different areas should be achieved for a complete realization of the project, one should conclude that extensive planning and coordination is required for the implementation of the project. The above said points are being realized by mobilizing local initiatives and by joint cooperation of different agencies. 5.1. Implementation Principles The implementation principles are basically as follows:

The environmental effects will be minimized as much as possible both in short and long term

A sustainable agricultural and industrial development plan will be implemented The public and the private sector participation will be maximized The programming and the implementation will be based on partnerships and cooperation

and special attention will be given to inter-agency coordination and action synchronization The implementation will be differentiated with respect to both centers with high

development potential and rural/urban settlements Self-sufficiency principle will be taken as the main approach for economic and social

support schemes Efficiency will be ensured in terms of resource utilization by detailed and time based

prioritization The municipalities will be involved in implementation and coordination

I - 127

Page 128: Study of Social and Economic Impacts of Construction of ...

5.2. Implementation Policies and Strategies The basic policies for implementation of Silvan Project are as follows:

To be able to provide new business opportunities, economic growth will be maintained by the opportunities created by Silvan Project

The productivity and competitiveness of enterprises will be enhanced by bringing in more flexibility to labor markets

The quality of labor force will be improved through active employment policies so that the employment will expand in parallel to regions economic growth

Institutional capacity will be increased so that the services delivery is more effective and makes the region more attractive by introducing various incentives

The trade with the bordering countries will be increased To be able to improve the business environments, the competitive power of the region will be increased by developing a production culture and developing labor force in parallel to economic development. After full development of Silvan Project, the economic relations with bordering countries will be expanded so that the goods produced from the region can be exported. The labor market, which is one of the most important parameters for development, will be enhanced by providing education and practices so that further skills and qualifications are gained. Labor productivity will be increased, productive employment opportunities will be provided and finding creative jobs will be encouraged. The Silvan Project construction, itself will create a lot of employment opportunities and will add quality to the labor force of the region. The cooperation between private sector, universities and the public sector will be increased and the administrative defects will be eliminated which is expected to create a dynamic and competitive social and business development environment. To be able to implement the mentioned policies the following strategies are being followed:

People’s participation in project development and implementation will be ensured for sustainable development. To ensure participation, emphasis will be given to training and organization of people in all related matters and dimensions.

To be able to minimize the costs, priority is being given to efforts to streamline information exchange between the project’s planners, executors and its users

The efforts for the project development will be supported by public administration and efficient coordination is being achieved between the parties

A variety of financing methods including private sector, public-private partnership models and direct foreign investments will be supported

5.3. Actions The actions for the implementation of the Silvan Project are summarized in Table 4. Table 4. Summary of actions for the implementation of Silvan Project

Action Responsible Institutions To attract private sector investments, the system of incentives developed for the country as a whole are being re-arranged by taking into consideration regional and sectoral characteristics.

Undersecrecretariat of Treasury

Special programs are being implemented to increase Regions’ export capacity

Undersecrecretariat of Foreign trade

I - 128

Page 129: Study of Social and Economic Impacts of Construction of ...

Cooperation between enterprises are supported Ministry of Industry and Defense

The financing opportunities are being increased Undersecrecretariat of Treasury, Development Bank, Agricultural Bank

Investment projects are being supported Small and Medium Industry Development Organization

Cultural assets will be protected and promoted Ministry of Culture and Tourism, General Directorate of Foundation

Forests will be expended and dams will be protected from erosion Ministry of Environment and Forestry

Agricultural productivity is being increased and agro-based industry will be promoted

Ministry of Agriculture and Rural Affairs

Enrollment ratio in secondary education will be raised to 95% Ministry of National Education

Labor force training programs will be expanded Turkish Employment Institution

Delivery of training and consultancy services to people who wants to start their own business is being provided

Turkish Employment Institution

A grant programme for creating employment will be developed and implemented

Turkish Employment Institution

Continuous education centers will be established Dicle University Health infrastructure is being increased Ministry of Health Social status of women are being increased Governorships, GAP

Regional Development Agency

In projects under construction, priority is given to main channel construction

State Hydraulic Works

Irrigation network will be completed as soon as possible State Hydraulic Works On farm drainage works will be completed State Hydraulic Works Energy transmission lines to be renewed, completed Turkish Electricity

Distribution Company Waste water network will be improved and treatment facilities will be built

Municipalities

Although numerous agencies and institutions are involved in the implementation of Silvan project, 2 of them become prominent, namely GAP Regional Development Administration (GAP-RDA) and State Hydraulic Works (DSİ). GAP RDA was established upon the Law Decree no 388 to ensure rapid development of the project by administering and coordination of different stakeholders involved or effected by the project in 1989. DSİ, established in 1954, on the other hand, is one of the most important and active institutions of Turkey responsible for the planning, designing and developing water resources. It has succeeded many projects and made a great contribution to the development of Turkey. 6. SOCIAL, ECONOMIC AND ENVIRONMENTAL EFFECTS 6.1. Social Effects

I - 129

Page 130: Study of Social and Economic Impacts of Construction of ...

Silvan Project’s main target is to create a sustainable development model which at the end will decrease the difference between the region and Turkey’s other regions social and economic development. Within this framework, as briefly summarized in the previous chapters, numerous organizations and institutions are involved for the social development of the region. Being known that economic development is one of the first priorities for the social development, for the time being the most of the focus is given on the timely completion of the Silvan Project Construction. The social effects of the project are summarized below:

The ratio of literacy level especially for women will be increased. According to the statistical data, the literacy level for women has increased from 71.9% to 90% between years 1990 and 2012.

A participatory and democratic culture is being developed in the region. With the establishment of community-based women’s Centers (ÇATOMs), women and

girls are receiving health care services and gain skills in areas such as hygiene, home economics and income generation. In the long term, the abilities and knowledge gained from these centers will be transferred to the children which at the end will increase the regions social development level and economy.

“Start Your Own Business” trainings are being received by the local people. Such initiatives will make the people to interact with the developed areas more densely and this will increase the social and economic perspective of the regions people.

With the establishment of youth centers, the living standards of the low income families’ children are being developed.

The education quality is being increased. For example the number of students per teacher has decreased from 31.1 to 30.4 between years 1990~2012.

The quality of health services is being increased with a high rate. The number of hospitals has been increased from 722 to 857 between years 1990~2012, whereas number of persons per doctor has decreased from 2152 to 750 (this data is for all the GAP region)

Infant mortality rate has decreased to 0.031 from 0.066 Since the project is a long term project, it is expected that the social impacts will be more visible in the long term. However, according to the initial observations and raw data, the project has a positive effect on the society. 6.2. Economic Effects With an approximate investment value of $3.5 billion, Silvan Project will create 2’570 km2 of irrigable land, employment opportunity to 320’000 people and will have a great impact on the social and the economic development of the region. The annual income is estimated to be $63 million from energy production and $460 million for the agricultural development.

The net annual income from the agricultural land will increase by 640% in case the full development of Silvan Project is achieved.

The net annual income per family will be increased by 475% in case the full development of Silvan Project is achieved.

The need for labor will increase 78.15 days per year, which will increase the employment ratio.

The gross domestic product composition will increase to 29.8% from 15.69% and to 47.00% from 44.75 for the industrial and services sectors, respectively.

I - 130

Page 131: Study of Social and Economic Impacts of Construction of ...

6.3. Environmental Effects and Measures Silvan Project is a large scale project extended in the whole Silvan region. The environmental effects during construction will be minimized by applying standard practice measures during construction works. There will be some expropriation and resettlement operation, especially for the reservoir areas. A total number of 31’400 people in the whole project area will be resettled because of the reservoir creation. The total forest area of 150km2 will be inundated and a total area of about 50km2 will be expropriated. The forest areas will be deforested before impounding operation and new forest areas will be created. There is no historical areas being effected from Silvan Project. The main focus in fact is given to minimize the environmental effects after full development of the project which will be due to irrigation and industrial development. The mitigation of all environmental impacts, included in the environmental management plans, covers all direct and indirect impacts in all phases and the plans will be followed strictly. The potential environmental impacts in terms of hydrology, pollution, geology, ecology and health are assessed and positive and negative effects and relevant mitigation measures are defined.

The GAP Administration gives priority to projects related to the environment to balance the possible effect of dams, promoting water recycling and avoiding environmental problems such as salinity and waterlogging.

Eco-City approaches are being promoted. Municipalities are being promoted for the utilization of treatment facilities since the

industrial activities are being expected to be increased after project development. Some hotspot areas are determined so that the effects of the project on the environment can

be followed closely. The farmers are being trained to promote soil conservation The project will not affect the aquatic ecosystem since there is no fish live in the creeks. There is a wide variety of land ecosystem in the region. Although the project components

are not expected to give damage to this ecosystem it is expected that after full development, there is risk of contamination from disease and insect control methods for the agriculture. To minimize this effect, the farmers are being educated for the optimum usage of chemicals and organic farming is being promoted.

7. CONCLUSIONS Silvan Project is a social development project giving focus on sustainable development. As defined by World Commission on Environment and Development for sustainable development, the project will “meet the needs of present without compromising the ability of future generations to meet their own needs”. Under the above said perspective there is a huge amount of issues such as social, economic, cultural, gender, health, agricultural and environmental. To handle such variety of issues, human being is selected as the main focus of the project both as an object and an agent for the project. Numerous Governmental, Private institutors and Society are cooperating for the realization of the project with the Government’s support.

I - 131

Page 132: Study of Social and Economic Impacts of Construction of ...

Once completed, it is expected that the regions’ social and economic level will be increased considerably with a sustainable development project. ACKNOWLEDGEMENT The writers wish to thank to State Hydraulic Works and GAP Regional Development Agency for providing of information related to the Silvan Project. Also we want to acknowledge the people who has been involved in the project from the project planning stage to the construction stages for the realization of such kind of a project. Their past efforts and future efforts will never be forgotten by the Turkish Nation.

REFERENCES

Suİş Engineering and Consultancy & Sial Engineering and Consultancy (2001): GAP Silvan Project Planning Report, Ankara, Turkey

Muammer, Y.Ö. (2004): Southeastern Anatolian Project (GAP) as Sustainable Development Project, Fourth Biennal Rosenberg International Forum on Water Policy, Ankara, Turkey

GAP Regional Development Administration (2008): Southeastern Anatolian Project Action Plan (2008-2012), Ankara, Turkey

Ali, E.E. (2006): Social and Economic Impacts of the Southeastern Anatolia Projects, Thesis Submitted to the Graduate School of Natural and Applied Sciences of Middle East Technical University, METU, Ankara, Turkey

I - 132

Page 133: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

and Construction of Hydropower project (14pt)

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf

fffffjfjjfkkfjjj

Study on environment friendly hydropower project construction

2(14pt)

Xu Zeping China Institute of Water Resources and Hydropower Research

Beijing 100048, China ([email protected])

ABSTRACT With the rising level on social and economic development and people’s consciousness on

evironment protection, environment impacts of dam construction are more and more concerned.

For most of the developing counties, to protect environment and ecological system in the

development of hydropower resources is the important issue in its sustainable development. How to

harmonize the development of hydropower resources and the protection of evironment, and to

reach the win-win goal for economic benefits and environment protection is the key problem that

should be considered in dam construction. By analyzing the impacts of hydropower project on

environment and ecological system, the paper discussed the ecological and environmental

concerns in the design and construction of hydropower project and proposed some mitigation

measures. Besides, the creteria for building an ecological friendly project are also studied.

Keywords: hydropower, environment, design, construction.

1. INTRODUCTION

As a clean energy resource, hydropower is always considered as the key aspect in energy

development. For most of developing counties, its modernization needs the development of

hydropower resources. But, on the other hand, the ecological and environmental problems

caused by dam construction will directly related to the sustainable development of river

basin. How to harmonize the development of hydropower resources and the protection of

environment and ecological system, and to make people friendly living with nature will

become an importment issues for dam industry. It could be expected that the restriction

from the requirement of environment protection will become more and more important

factors for hydropower development.

The ecological and environmental impacts of hydropower development involve many

problems. Among these, engineering design and construction is one of the important

aspects. In the traditional construction manner of hydropower project, large amount open

excavation of mountains and earth borrow for dam filling are the common practices of civil

works. Thus, the local environment will be severely damaged. In the future, this rough

construction method will be restricted by the consideration of environment protection.

I - 133

Page 134: Study of Social and Economic Impacts of Construction of ...

How to shift traditional idea of project design and construction and to build environmental

friendly project is an urgent problem to be solved by present hydropower engineers.

Fro protecting environment during design and construction of a hydropower project, the

first thing is to follow the principal of sustainable development in the design. The concept

of environment protection should be fully considered in every aspects of the project, such

as: selection of dam-site and dam type, general layout, etc. During construction, all the

feasible environment friendly measures should be applied. Take an example of earth and

rockfill dam, large-scale open excavation of abutment should be avoided and most of the

affiliated structures could be set underground. But even though, it still has the problems of

utilizing the excavated material. In the design and construction, the discarded or rejected

material should be minimized to keep the balance of excavation and filling. Besides, in the

construction of earth dam, the clay material for core is usually taken from farmland, which

could cause ruin of arable land. To extend scope of core material usage by systematic

researches, such as using weathered material or other wide gradation gravelly soil, reduce

or not use farmland clay material, is also an important way to construct environment

friendly hydropower project.

2. ENVIRONMENTAL IMPACTS OF HYDROPOWER PROJECT

During past practices of hydropower development, the impacts on environment are often

neglected. In recent year, with economic development and people’s awareness of

environment problems, the protection of ecological system and environment has gained

more and more attentions. But then, it should also be point out, when dealing with the

problems of hydropower development and environment protection, the negative effects are

more emphasized. In fact, the effect of hydropower development on environment has both

negative and positive aspect. As a clean and renewable resource, hydropower plays an

important role in reducing greenhouse gas emission and air pollution. In river flood control

and flood disaster mitigation, the functions of large capacity reservoir are even more

important and could not be superseded. Besides, a well-planned and properly operated

hydropower project may create a better environment. At the same time, by rational

distribution of water resources, the environment of those ecological weakly or endangered

areas could be improved, such as the ecological water supply for Talimu Lake and

Baiyangdian Lake in China.

Based on present knowledge, the main negative impacts of hydropower development could

be summarized as follows:

(1) Impact on river ecology. After dam construction, the natural river flow was blocked.

It could alter the river flow regime and the original rules of sediment movement.

Furthermore, the hydrological characteristics of upstream, downstream and estuary

will also be changed. All these could result in ecological environment changes of

the whole river.

(2) Impacts of inundation. After dam construction, many people will be resettled. This

issue is more severe in China for its large population. Besides, the rising water level

will inundate farmlands, mineral resources and culture relics. Especially, for some

I - 134

Page 135: Study of Social and Economic Impacts of Construction of ...

remote area, reservoir inundation may destroy the particular local culture heritage.

(3) Impacts on biodiversity in the river basin area. The construction of dam and the

existence of reservoir could lead to rapid changes of ecological environment in

dam-site area and reservoir area. The natural habitat may be damaged. Plant and

animalcule resources may be seriously affected which might even lead to the lost of

some species. At present, the most concerned problem is the impact on migrating

fish. Besides, the impact on forest resources by civil works such as: excavation,

slop cutting, access road construction, etc. is also one of the important issues.

(4) Geological disaster caused by reservoir. After dam construction, the variation of

hydrological and geological environment in reservoir area may lead to some

geological disasters caused by reservoir impoundment, such as: landslide, bank

collapse, etc.

(5) Water interception or river break caused by water diversion project or diversion

type power station. Water diversion project and diversion type power station that

are not properly planned could lead to water interception of the river. It may cause

ecological problems and difficulties for local people’s livelihood.

(6) Ecological impacts of dam-site area caused by civil works. Construction of large-

scale hydropower project will involve many civil works, such as: slope cutting,

quarry or borrow area excavation, river diversion, spoil dumping, etc. Improper

dealing with these works will cause soil erosion or mud-rock flow. At the same

time, the vegetation and landscape will also be affected. Besides, improper dispose

of the redundant excavated material or discarded concrete will also have some

impacts on environment.

(7) Dam breaching. After dam construction, the safety of dam will be a kind of risk

that may cause fatal flood to the people living downstream. If the safety measures

and mitigation measures are not sufficient, it may bring about great losses of

people’s life and properties.

In the past practices of hydropower project construction in China, the basic principals are

safety, economic and technically feasible. With the social progress and economic

development, environment protection in hydropower development is greatly concerned. In

recent years, the report of feasibility study or preliminary design of a hydropower project

must include an independent chapter on environment assessment. But even though, in most

of the cases, ecological and environmental problems are still not highly emphasized in

decision making. In the design and construction of future’s hydropower project, the

requirement on economic, social, ecological will be higher and higher. So, environment

problem should be put in a very important (or principal) position. In every stage, like:

planning, investigation, design, construction and operation, ecology and environment

I - 135

Page 136: Study of Social and Economic Impacts of Construction of ...

protection should be considered with priority. This is a win-win strategy for resources

development and ecological environment protection.

3. CONSTRUCTION OF AN ENVIRONMENT FRIENDLY PROJECT

To construct an environment friendly hydropower project, the most important aspect is the

idea of decision makers. Actually, every hydropower project has multi-functions. For the

past projects, economic benefit is more emphasized. In the future, the construction goal of

all the hydropower projects must follow the principal of sustainable development and the

factors of social, ecology and environment should be put in an important and conditional

position.

Construction of an environment friendly hydropower project should consider many

influential factors. In the engineering design of a project, the concept of ecological design,

which is accepted in industry in 1990’s, should be used for reference. Ecological design,

also called green design, life circle design or environment design, is a kind of design

method that could include ecological factors in consideration and help designer to

determine the correct direction in decision making. Ecological design request the factors of

environment be considered in the every stages of the project and to mitigate environment

impacts in the whole life circle of the project. All these efforts will finally lead to a

sustainable hydropower project.

By taking examples of embankment dam and rockfill dam, several aspects on environment

issues in the design and construction of hydropower project are discussed as follows:

3.1. Determination of dam site and dam type

In conventional design concept of earth and rockfill dam, dam site and dam axis are mainly

determined by topography, geology, general layout and construction conditions. For

different dam site, its environmental and ecological impacts could not be the same. In the

planning and design, several possible plans should be presented for comparing the

ecological and environment impacts. The final decision will be made by integrated

consideration of ecological, environmental, economic and technical aspects. Here, the main

considerations on ecological environment are: inundation of natural habitat for wildlife and

plants, protection of peculiar terrestrial wildlife, protection of culture relics, avoiding soil

erosion, etc. Inundation caused by dam construction is unavoidable. In some cases, by

creating artificial ecological protection area, the environment losses could be partly

compensated. But the adjustment of dam site or reservoir water level may be the ultimate

solution, although it may cause some economic losses.

In the design of earth and rockfill dam, the most commonly used dam types are:

homogenous earth dam, central core or inclined core rockfill dam, concrete faced rockfill

dam, etc. As a dam mainly use local materials, earth and rockfill dam usually have great

advantages in economic comparison. But as its large volumes and most of the construction

I - 136

Page 137: Study of Social and Economic Impacts of Construction of ...

materials will come from excavation, the construction impacts on ecological environment

are also obvious. For some cases, the clay core material may take from arable lands, which

could directly destroy farmlands. Thus, for dam type selection, local situations and

material sources should be fully considered to minimize the impacts on ecological

environment, such as: using sandy gravel material in flood plain, using excavated material

of tunnel or spillway excavation, using other materials substitute the clay core by meeting

the same requirement for strength and permeability.

As the relatively weak scour resistance of earth and rockfill dam, it cannot bear reservoir

water overflow. For reducing breaching risk, the selection of dam site and dam type will

also need careful studies on reservoir bank stability, to let the dam site keep a certain

distance from the potential landslide area.

3.2. General layout

In addition to dam, the general layout of a hydropower project will also includes flood

discharge structures, powerhouse, navigation structures, fish pass, etc. Besides, it also

involves: cofferdam, diversion structures, access road, etc. A rational layout of hydropower

project should minimize the impacts on environment.

In the layout of rockfill dam, there are four kinds of powerhouse, which are: bank side

powerhouse, downstream powerhouse, separate bank side powerhouse and underground

powerhouse. For the bank side powerhouse, it usually involves high slope excavation. To

avoid this effect, the powerhouse could be arranged at downstream side of the dam or

underground by considering the topography and geology conditions.

Figure 1 Typical underground powerhouse

In the construction of hydropower project, the arrangement of access road and camps will

also have certain effects on the environment of dam site area. The access road should keep

away from the ecological corridor of wildlife to minimize the related impacts. When

necessary, tunnel connecting can be used for avoiding large-scale excavation. At the same

I - 137

Page 138: Study of Social and Economic Impacts of Construction of ...

time, the road engineering should also ensure proper drainage to protect natural waterways

and minimize erosion.

In the layout of flood discharge structure, the effect of scouring and atomized rain is one of

the main reasons for causing bank slide. For rockfill dam, whether the spillway is properly

designed will directly relate to the safety of the dam.

3.3. Section design and material sources

In the section design of rockfill dam, the main target is the zoning of different materials. In

the past, some research works were carried out in rational utilization of different materials

for the dams. But the start point for these research works are mainly focus on economic

benefit or due to the lack of available materials. Problems on ecological environment are

seldom considered as the main factor in decision-making.

Figure 2 Typical section of rockfill dam

Except for the homogenous earth dam, most of rockfill dams are generally composed with

different material zones, which include: impermeable zone, filter zone, transitional zone

and permeable zone. For rockfill dam, especially for high rockfill dam, this zoning

structure is very important. In the zoning design, the basic principal is try to use local

materials adequately, and rational put the materials in different zones according to its

engineering properties, distribution in time and space and the impacts on dam structure. In

the consideration of environment, the primary issue is the source of construction materials.

As the large volume of rockfill dam, the amount of fill material is huge. What material can

be used? Where these materials come from? The decision of the questions will definitely

have direct impacts on environment of engineering area. In the past practices, core

materials are usually taken from the deep overburden area near dam site. These areas are

usually suitable for plant growth. Large-scale excavation may destroy the original plant

ecology. Besides, in some cases, the core material is directly taken from farmland. This

could destroy many arable lands and further affect local people’s livelihood and cause

social problems. The rockfill material of rockfill dam may involve large-scale quarry

excavation and thus may cause the damage of natural habitat and biodiversity. By

I - 138

Page 139: Study of Social and Economic Impacts of Construction of ...

considering the above facts, in the dam section design, the selected materials should have

less environment impacts. And on the other hand, the range of materials usage could also

be expanded by further research on the engineering properties of construction materials. In

this field, Chinese scholars have done a lot of research works and made fruitful

achievements. Such as: the weathered rock material was used as core material in Lubuge

Project, wide gradation gravelly soil were used as core materials in Pubugou Project, soft

rock materials were used in Daao, Yutiao and Panshitou CFRDs.

For reducing the environmental impacts of quarry and borrow area excavation, the

excavated materials from the construction of other structures should be fully used to get a

balance between excavation and fill. By using the excavated materials sufficiently, the

amount of quarry excavation will be reduced or even not be used. For example, for

Tianshenqiao-1 CFRD, the spillway was arranged at a solution limestone saddle with

large-scale excavation of approach channel. Although the excavation amount was

increased, all the excavated materials were use for dam construction. The 180 million

cubic miters rockfill of the dam was mainly come from spillway excavation. Another

example is the Ming tomb pumped storage station. The upper reservoir was formed by

excavation. All the excavated materials were used for dam construction. No special quarry

was used. Thus, the environment and landscape of the circumjacent area were protected.

For the fully use of the excavated material, the zoning and slope of the dam were also

modified in the final design.

In planning the source of construction material, the quarry and borrow area should be set in

the upstream inundated area. If the topography and geology condition are not allowed,

corresponding ecological compensation measures should be considered in the planning.

Such as: to creation artificial wetlands with the function of ecological improvement by

using the low areas formed by material excavation.

Figure 3 Ming Tomb pumped storage station

3.4. Application of the ecological friendly construction methods

I - 139

Page 140: Study of Social and Economic Impacts of Construction of ...

The principals for building an environment friendly hydropower project should be: to

minimize the damage of the natural environment, to harmonize the engineering structure

and environment.

Specially, the every aspects of construction process should be restricted by the

requirements of environment protection. The construction organization and

implementation must be elaborate. By using information technology and GPS technology,

the scale of excavation and fill should be accurately controlled. For the contractors,

effective review and supervision should be carried out in camp setting, auxiliary facilities,

waste dispose, waste water treatment, management of workers, etc.

For the application of construction material, it should be keep in mind the principal of

harmony with natural environment. The green and ecological friendly materials should be

used with priority. When building slope protection or earth retaining structures, proper

drainage passage should be arranged. The best materials for this structure should be that

with pore canal, easy for plant growing, accord with living environment of local aquatic

animals or amphibious animals. An example is shown in Fig. 4. The protection of slope

foot is a placed rockfill structure. The material and appearance of this structure has a

natural form. The gaps can be used for plant growth and animal living.

Figure 4 Earth retaining structure by placed rockfill

Besides, for the structure of riverbank protection, gabions made by high strength

geosynthetic are usually better than concrete structure in adapting environment. As its

flexibility in adapting deformation and friendly for plant growth, gabion structure always

provides better landscape. Also, the earth retaining structures constructed by geosynthetic

or geo-grid and the slope protection net made by geodynthetic can adapt the topography

conditions of engineering site. At the same time, the surface of the structure can be jetted

with grass seed or planted with tress. When grasses or trees grow up, the structure will get

I - 140

Page 141: Study of Social and Economic Impacts of Construction of ...

along the surrounding environment. In addition to the function of landscape, it can also

provide living environment for small animals or insects.

Figure 5 Bank protection by gabion Figure 6 Culvert pipe passage

For keeping biodiversity in dam site area, the natural passage of animals should not be

blocked by access road construction. The original waterway system in dam site area will

also be protected. These passage or drainage could be established by bridge or culvert pipe.

3.5. Ecological rejuvenation after construction

From the procedures of hydropower project development, although some environmental

protection measures are applied in design and construction, the impacts on ecological

environment still cannot be fully avoided. As compensation measures, ecological

rejuvenation after construction should also be considered in the construction of an

environment friendly project. For this purpose, the first thing is the clear classification of

the ecological and environmental damages caused by project construction. Ecological

rejuvenation and treatment measures should be considered in advance during design and

construction. And the measures will be properly applied after project construction. The

main contents of ecological rejuvenation will be: recovery of forest resources, recovery of

landscape, setting artificial fish hatcheries, setting protected area for wildlife rescue, waste

water treatment, recovery of the quarry or borrow area pits or using it to create artificial

wet lands. Here, ecological rejuvenation does not only means recovery or compensation.

With proper measures, a more beautiful ecological environment can be created. Such as:

create valuable lands by using waste rockfill or by leveling the quarry or borrow area, keep

the cultivated soil of the quarry surface and pave it on the ground for agriculture, soil and

water conservation measures at dam site, developing new scenery sight by using dam

created lake, etc.

4. CONCLUSION

I - 141

Page 142: Study of Social and Economic Impacts of Construction of ...

In summary, the development of hydropower resources needs comprehensive consideration

and review of the social, economical and ecological factors. By investigating the past

experiences and applying proper mitigation measures, the negative impacts of hydropower

project construction can be minimized to an acceptable level while its huge economic

benefit and positive ecological effects can be fully bring into play. The key for this goal is

to establish a design principals based on sustainable development. Former engineers

mainly care on how to construct a safe and economic viable dam. The development of

future’s hydropower project requires engineers to responsible both on hydropower

construction and environment protection. To establish a framework on ecological friendly

hydropower project construction is the only way to harmonize the resources development

and ecological environmental protection.

ACKNOWLEDGEMENT The author thanks Professor Jiang Guocheng’s comments on the paper and also appreciates chief

engineers He Shaoling and Yang Xiaoqing’s review.

REFERENCES

Proceedings of Symposium on Environmental Considerations for Sustainable Dam Project,

ICOLD 72nd Annual Meeting, May 16-22, 2004, Seoul, Korea.

Final Proceedings of Symposium on Benefits and Concerns about Dams, 13th Sept. 2001,

Dresden.

I - 142

Page 143: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

Integrated Water Resource Planning for South Africa: Water Use Efficiency hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj

T Nditwani, Chief Water Resource Planner, Directorate: National Water Resource Planning Department of Water Affairs and Forestry, Private Bag X313, Pretoria 000, Republic of South Africa (RSA)

[email protected]

ABSTRACT: INTEGRATED WATER RESOURCE PLANNING FOR SOUTH

AFRICA: WATER USE EFFICIENCY South Africa is a water scarce country with a very uneven distribution of rainfall and the resultant

run-off in its rivers. This is further exacerbated by the fact that the large urban development's took

place far from the largest available water resources. The rainfall is very erratic with long droughts

followed by periods of above normal flows and floods. The only way to utilize the water was to

develop dams to store the water for use over the long dry periods. Over the years many dams were

built to supply water for irrigation projects, as well as to supply the metropolitan areas and

industries. Complex interbasin transfers were required to link catchments where water was

available with those where water was short. The Department of Water Affairs has in years

identified the need to develop to ensure sufficient water for users. Reconciliation Strategies have

been, or are in the process of being developed. The studies include scenarios of future water

requirements, determine all possible options to manage water requirements and increase

efficiency, determine options to supply more water from ground and surface resources, provide for

the possible impacts of climate change and propose strategies to reconcile the growing

requirements with the available resources. While the strategies differ in the detail from area to

area, a number of common strategies emerged: (a water conservation and water demand

management will have to be undertaken for all the areas to ensure more efficient use of water.

Keywords: Efficiency, Reconciliation, Strategy, Water and Availability.

1. INTRODUCTION

While the Reconciliation Strategies differ in the detail from area to area, a number of

common strategies emerged: (a water conservation and water demand management will

have to be undertaken for all the areas to ensure more efficient use of water. These are

targets that would entail a reduction in the requirements of a minimum of 15% over a

period of five years. The implementation of such measures will now receive high priority

to keep the assurance of supply to these areas at reasonable levels until other measures that

require longer lead periods, can be implemented. (b) The re-use, or recycling, of water.

Feasibility studies will now be done in all cases where re-use has been indicated as a

potential augmentation source. (c) Further surface water development and associated inter-

basin transfers would be required. These will only be implemented after careful

investigations. From the investigations undertaken it has become clear that large-scale

desalination of seawater is on the horizon as a viable option for the coastal metropolitan

areas. Strategy steering committees are being formed to ensure that the strategies are

I - 143

Page 144: Study of Social and Economic Impacts of Construction of ...

implemented, as well as to update the strategies as new information on growing water

requirements and information from feasibility studies become available.

Planned and unplanned Water Conservation/ Water Demand Management (WC/WDM)

has been taking place in the past, however, dedicated programmes of loss control,

increasing efficiencies and consumer awareness are now key activities essential to make

the slogan “some for all” a reality.

The Government as custodian of the water resources are combining efforts with

municipalities (responsible for service provision) to formulate integrated water resource

management plans, referred to as Reconciliation Strategies.

Reconciliation Strategies are developed for all significant water resources in SA

encompassing detail plans of action which stipulates how sufficient water can be made

available for next thirty years.

Two strategies, the first for the Vaal River System located in the centre of the country and

the other covering the KZN Coastal Metropolitan area in the east demonstrate that by

combing demand side management and augmentation interventions offers effective water

management solutions.

2. OBJECTIVE

This paper aims to present the SA Government’s view on WC/WDM as reflected in the

recently published strategies such as Water for Growth and Development Framework

(WfGDF), National Development Plan, National Water Resource Strategy and how it is

incorporated in detailed Reconciliation Strategies as to :

Describe the water supply situation for one coastal and one inland system and

present the current planning activities.

Present a proposed WC/WDM communication strategy.

Suggest the integration of WC/WDM planning into other water resource

management processes.

The Western Cape Water Supply System supports the country’s second largest

economy and provides water to more than 3 million people clustered around the

City of Cape Town. Of the current available system yield of 556 million m3/a, 493

million m3 was used in 2008, 63% for domestic and industrial purposes, 32% for

irrigation and 5% by smaller surrounding towns.

3. VAAL RIVER SYSTEM

The Vaal River System with the main component as the Vaal Dam (see Figure 1) provides

water to about 12 million people producing 40% of the country’s economic output and

supply cooling water to most of the thermal electrical power stations in Southern African –

a strategic asset fueling the economies of the region.

I - 144

Page 145: Study of Social and Economic Impacts of Construction of ...

Figure 1. Vaal Dam

In a nutshell the five point strategy (see Figure 2) to secure enough water from the Vaal

River System encompasses:

• Eradicate unlawful irrigation water use by 2014;

• Roll out WC/WDM programs to achieve the target savings by 2015 – Project 15%;

• Implement Phase 2 of the Lesotho Highlands Water Project to deliver water to the

VRS by the year 2020;

• Mine water effluent (acid mine drainage) must be treated and ready for use by

2015.

• Continuation of the Strategy Steering Committee to monitor implementation and

adjust the actions to adapt to changes in the socio-economic landscape.

I - 145

Page 146: Study of Social and Economic Impacts of Construction of ...

Figure 2. Vaal River System Reconciliation Strategy

4. KWAZULU-NATAL

Kwa-Zulu Natal metropolitan area is third largest contributor to the national economy and

second largest population concentration in SA. It is the economic hub of KwaZulu-Natal

and very important for the economic well-being of the province. The area is experiencing

rapid growth in water demand because of the influx of people from the rural areas and

economic growth.

I - 146

Page 147: Study of Social and Economic Impacts of Construction of ...

Figure 3. Midmar Dam

To overcome the current deficit in water supply (red area in Figure 4) various

interventions are needed including:

Implementation of priority infrastructure projects (Spring Grove Dam and

conveyance infrastructure).

WC/WDM measures to subdue the growing water use.

Studies investigating the feasibility of:

o Reuse of treated effluent.

o Large dam development in adjacent river with transfer infrastructure.

o Desalination of see water at a large scale – possible alternative to the large dam

option.

I - 147

Page 148: Study of Social and Economic Impacts of Construction of ...

Figure 4. Kwa-Zulu Natal Reconciliation Strategy Graph

The re-use feasibility study by EThekwini Metropolitan Municipality encompassed:

Direct and indirect re-use options were investigated.

Study considered, infrastructure, social, financial and environmental aspects to

compare alternatives.

Although it was found that direct re-use is technically and economically preferred,

objections to direct re-use by communities require review of the approach.

5. RECONCILIATION STRATEGY COMPONENTS

The questions, how much water is needed, what resources are available, and which

interventions are needed to achieve a balance between demand and supply are answered at

the centre of Figure 5.

I - 148

Page 149: Study of Social and Economic Impacts of Construction of ...

Figure 5. Reconciliation Strategy Components

The coloured boxes list the aspects that are synthesise when formulating a suitable strategy

to reconcile the water resources with the requirements.

6. RIGOROUS RISK ANALYSIS: FOUNDATION FOR RECONCILIATION

STRATEGIES

Developing a reconciliation strategy requires rigorous risk analysis (see Figure 6).

I - 149

Page 150: Study of Social and Economic Impacts of Construction of ...

Figure 6. Schematic Representation of Rigorous Water Resource Analysis

7. RIGOROUS RISK ANALYSIS: FOUNDATION FOR RECONCILIATION

STRATEGIES

All municipalities are required to prepare detail WC/WDM project plans supported by

motivated funding requirements.

The four largest municipalities give progress twice a year at the Strategy Steering

Committee (SSC) meeting, indicating what savings have been achieved, highlighting

successes, hurdles and identifying opportunities.

Progress reports and media releases serve to communication outcomes to institutional

managers and the public – a means to promote Integrated Water Resource Management

and overcome inefficient silo-thinking.

Table 1.Project 15% Facts

None Revenue Water (%) 34

Saving Target (million m3/annum) 196

Capital required over 10 years (US$/ year) 75 million

Operation requirement (US$/ year 35 million

(Excludes assets renewal and replacement costs)

I - 150

Page 151: Study of Social and Economic Impacts of Construction of ...

8. COMMUNICATION STRATEGY

The overarching aim is to spread the message, “water is a precious resource worth

conservation”, among all involved in the water provision cycle including the public.

Formulate coherent messages from government and municipalities informed by progress

with the implementation of the reconciliation strategies.

Solicit participation of water users, local municipalities, to take up WC/WDM in their

areas of influence.

The most important element of the communication strategy must be open information

sharing, by conveying messages of successes, hurdles and opportunities.

8. CONCLUSION

WC/WDM measures and the efficient us to water are key components of each

reconciliation strategy.

Multiple interventions are needed to maintain a positive water balance over the

planning horizons.

Clearly defined actions assigned to responsible institutions such as Government,

Municipalities, Water Service Providers or bulk water users are key factors for

successful implementation of the reconciliation strategies.

Continuous monitoring against targets is essential to track progress and timeously

respond with appropriate adaptive management measures

REFERENCES

Department of Water Affairs and Forestry, South Africa, Report No. PWMA

08/000/00/0304. Internal Strategic Perspective: Upper Vaal Water Management

Area. Compiled by PDNA, WRP Consulting Engineers (Pty) Ltd, WMB and Kwezi-

V3 on behalf of the Directorate: National Water Resource Planning, 2004. Pretoria,

South Africa.

I - 151

Page 152: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH, 2014

PUBLIC SAFETY AROUND THE DAMS IN SLOVENIA

Nina Humar, Hidrotehnik d.d., Ljubljana, Slovenia

[email protected]

Andrej Kryžanowski Faculty of civil engineering, Ljubljana , Slovenia

[email protected]

ABSTRACT Until recently, public safety has been a rather neglected topic in Slovenia. To ensure public safety, safety-aware companies have used the existing legislation governing the provision of safety in construction sites and on identified bathing waters. As in Slovenia, water and waterside land (watercourses, water bodies) is mostly characterised as public asset, there was, in general, a lack of legislative basis that would enable the managers to restrict movement and activities in the areas lying within close proximity to dams. However, the accident at the Blanca HPP and the recent review of the state of water management works in Slovenia have shown the necessity of dedicating more attention to the problem of public safety and public awareness. As an upgrade of the analysis of the current state and instructions for improvement of public awareness and emergency procedures for the population, an on-line presentation of dams, their characteristics and problems associated with their existence, which also touched upon the problems originating from insufficient maintenance, problems and risks caused by improper operation, exploitation of the dams and the reservoir area was prepared for the Ministry of Defence. The paper presents the current situation of public safety in Slovenia and searches for the opportunities to make a better use of the existing legislation and for rapid actions that could contribute to improve the situation in this area. Keywords: Dam safety, upgrade of the monitoring system, operative monitoring, early warning system, public defense

I - 152

Page 153: Study of Social and Economic Impacts of Construction of ...

1. INTRODUCTION

For a long time in Slovenia, the problem of public safety around dams had been somehow misunderstood and only partially treated. This aspect of safety was often confused with the aspect of public protection. The attempts to raise public awareness often revolved around the discussion about the impact of the dam on the environment and space. However, the majority of the owners and managers adopted some basics measures to ensure better public safety. Accidents that occurred in the last years on some of the dams as well as the recent review of the state of the Slovene dams with water management purpose have prompted the reflection and discussion about the responsibility for such accidents, resulting in people and owner awareness that something should be done to increase and encourage a broader view of the problem. In recent decades, several accidents occurred on the dams in Slovenia: • Mavčiče (1993) as a consequence of irregular operation of hydro mechanical

equipment • Drtijščica (2010) as a consequence of improper design of dam evacuation structures • Formin (2012) as a consequence of improper operating regime of a hydropower plant

chain during extreme floods

Luckily, only material damage was caused in all the events, despite the potential threat to human life based on the degree of the events. Of more concern are cases that caused human casualties through negligence and disregard of safety measures of participants in the accidents: • Blanca (2008) – the accident caused 13 fatalities due to disregard of safety protocols

and failure to comply with restrictions of movement at the HPP Blanca construction site

• Solkan (2012) – the accident caused one fatality due to disregard of warning signs regarding the risk of operational waves downstream the dam

It is only after the accident on the Blanca dam that the responsible parties – the authorities and involved organizations – started to look at the problem as a whole, not only from the perspective of ensuring the safe operation and prevention of access by unauthorized persons to vital equipment or parts of the dam, but also from the perspective of identifying the possible hazards and ensure safety of the beneficiaries of dams and reservoir and of the river as well as the safe use of the reservoir and possible consequences of interaction between the public and the dam, reducing in this way the possibility of occurrence of situations that could cause significant damage on the dam, the population and stakeholders. 2. THE IMPACT OF THE PURPOSE ON THE APPROACH OF PUBLIC

SAFETY There are over 68 dams in Slovenia, 39 of them are large dams according to the current ICOLD categorization (35 higher than 15 m). The first dam was constructed in 1769, while the majority of dams were constructed between 1950 and 1990. While smaller reservoirs are mainly intended for water management and irrigation, among large reservoirs those intended for hydro power production prevail. The primary purpose of 54% of aforementioned 39 large dams is hydropower production, 35% of dams were constructed for flood protection, water management and irrigation, and 5% of the dams were constructed for commercial purposes such as recreation. In many cases different during the

I - 153

Page 154: Study of Social and Economic Impacts of Construction of ...

life of a dam unforeseen uses of the reservoir (for example recreation, nature protected areas) and in dam influence area join the basic design purpose of the dam; indeed,this unforeseen “associated uses” of the reservoirs have significant affect on the normal operation and maintenance and can even cause major problems.

Figure 1: Dams in Slovenia A major part of large dams in Slovenia is state-owned, i.e. only few are owned by private companies or municipalities. According to legislation, the owner is responsible for dam safety and also for the safety of the facility in terms of safe use and exploitation. In most cases the management and operation is entrusted to different public and semi-private companies (hydro power companies and water management companies etc.). These companies take care of the operation and maintenance of the dams as well as the performance of monitoring. However, there is a major difference between the dams for hydropower production and the dams for water management purposes: the dam meant for hydropower production are handed over to the concessionaires with a full concession, which transfers all the obligations of the owner to the concessionaires, including the management of the financial assets. In these cases the concessionaire is responsible for dam and public safety in the area of influence. Dams for water management purposes rarely have incomes as high as dams for hydropower purposes; the funds for regular maintenance and also the activities to ensure safety of dams and public safety, as well as the approval of all activities depends on the government services. Therefore, the responsibility itself is shared and unclear. Large dams are under the supervision of the Ministry of Agriculture and the Environment (2012) and the Inspectorate of RS for Agriculture and the Environment. The emergency

I - 154

Page 155: Study of Social and Economic Impacts of Construction of ...

preparedness plans are under the supervision of the Ministry of Defence. Smaller and medium size dams are not explicitly subject to Inspectorate’s supervision. But the supervision covers mainly the basic control of proper operation and the availability and the adequacy of the operational documentation, rather than the safety aspect of the dams and proper use of the reservoir. At first sight more attention to public safety is being paid on the dams for hydropower production. The access to the dam site is in most cases completely restricted. Indeed, the recent accident on HPPs excluded the liability of the operators who are under a legal obligation to define the platform for provision of public safety at the stage of spatial contextualisation of dams and the elaboration of the EIA study (Environmental Impact Assessment). On the other hand, dams for different water management purposes are easily accessed. Access is limited only in areas of lifting mechanisms and to the control facility. The range of measures to ensure public safety is therefore somewhat limited, but jet far from being absent and sometimes oriented even more in elimination of possible hazards.

Picture 2: The dams for water management are easily accessible – signs warning about dangers, and restriction of movement

For the dams owned by private owners, the extent of measures to ensure public safety still vary depending on operator awareness, but is in general much more limited than in both cases mentioned above and sometimes even absent.

I - 155

Page 156: Study of Social and Economic Impacts of Construction of ...

Figure 3: Privately owned dam very poorly mantained – a picnic area downstream of the dam

3. OVERVIEW OF THE PUBLIC SAFETY AROUND DAMS AND CURRENT SITUATION

Already before Slovenia’s declaration of independence, there were no legal provisions that would refer only to measures for public safety around dams and many owners have relied on other provisions and acts, such as the former Construction Act and Occupational Safety Act and Rules on the provision of security in mobile construction sites. Today we still lack provisions that would stipulate the requirements for the provision of measures to ensure public safety. Although the requirements have not changed much, a look at the current state of public safety reveals that the measures for public safety around dams in Former Yugoslavia were conceived wider and were stringent than they are now in Slovenia. If we give a very general overview of the measures that were intentionally or unintentionally adopted and implemented on the dams in the past, we can say that the level of care for public safety (although taken to protect the equipment more than to protect the beneficiaries from injuries or damage) was higher in the Former Yugoslavia, since already the access to the infrastructure and facilities was more restricted than nowadays. Today, as in the past, the scope of the measures for provision of safety depends on the purpose of the dam. The range of measures that were in some way related to the security and public safety was understandably higher for the dams for hydropower production already in Former Yugoslavia. The reason for this less strict approach could be found in the change of the classification and definition of these structures, particularly the dams retaining water. The water is defined as a public good by the Water law. That means that the infrastructure that was once classified as the infrastructure of national importance is now considered as water infrastructure in many cases and therefore the object of public good or the area of influence is considered such. The decision to limit the access to the dam site and to the impact area and restriction of activities in the areas of influence is therefore hardly made by the owner (especially when the owner is the state itself).

I - 156

Page 157: Study of Social and Economic Impacts of Construction of ...

Figure 4: Restriction of the access to the mechanical equipment On the other hand, parties such as environmentalists and fishermen, supported by the Environment Protection Act and Nature Conservation Art, are very firm and opinionated when setting the conditions that can also affect the operation and maintenance of the dam. When comparing the dams built in the former country to the dams built after the independence we can see that:

• The dams built after the independence are easier accessible and less protected • There are less restrictions in terms of use and associated use (recreation, fishery

ect.) • Due to unregulated property ownership, there is high interference of owners of the

land in proximity of the dam and the reservoir and in the impact area As in the past, today the care for public safety is higher on dams for hydroelectric production, but it is still largely based on the aspect or principle of preventing direct access of unauthorized persons to the dam site and equipment, and not on the identification of hazards that could lead to malfunction, damage and, finally, injuries or casualties. Therefore associated uses of the reservoir, the recreation areas downstream of the dam or navigation in the reservoir still remain improperly addressed – with inadequate or absent signs, audio signals and detected (unpunished) access and without a legal basis for objection to environmentalists conditions (e.g. the expansion of Natura 2000 sites is underway without regard to other stakeholders). After the accident on the Blanca dam, an attempt has been made by the Ministry of Defence to raise the public awareness and to draw the owners and public attention to the problem of ensuring dam safety and safe operation. As a result of the study, some recommendations were elaborated to ensure safe operation and appropriate action in

I - 157

Page 158: Study of Social and Economic Impacts of Construction of ...

response to all the situation a dam may face. In addition, some proposals to improve public safety in normal and exceptional conditions have been prepared. Although the attempt to inform the people – both those who deal with dams on a daily basis and those who are only occasional users – about the hazards and possible measures resonated strongly, the awareness, particularly of general population, visitors and users still fail to detect the hazards associated with improper use of the dams. This mainly reflects in the setting-up of public areas (picnic places, cottages etc.) where people gather and stay downstream of the dams, where the impacts of the operation of the facilities can be still detected, or in sailing, swimming or navigation in close proximity to the facilities for the evacuation of water, gates etc.

Figure 5: Children paddling upstream of the gates

As mentioned, the main problem of providing public safety is that dams retaining water have been classified as water infrastructure and that water is defined as public good. This is one of the main reasons why restrictions of movement in dam areas are rarely put in place. Most dams can be easily reached from land or water and are often seen by the public as a great place for leisure activities and recreation. 4. UTILIZATION OF EXISTING LEGAL PROVISIONS GRANTING SAFE USE

AND PUBLIC SAFETY

The legislation concerning dam safety may be scattered and loose, but there is, in fact, no legislation addressing the problem of public safety around the dams. Despite the absence of the legislation covering the public safety directly, we can find many provisions that can be used as a basis for provision of public safety around dams.

I - 158

Page 159: Study of Social and Economic Impacts of Construction of ...

Even though it is written for employers and employees, the basis of public safety is laid down by the Occupational Health and Safety Act which imposes the employer to provide the necessary actions to ensure the safety of workers and other persons present in the work process, including prevention, elimination and control of hazards at work, information and training, with proper organization and necessary material resources. The employer should take into account the following basic principles:

- Avoiding hazards; - Risk assessment; - Managing the risks at source; - Adapting to Technical Progress; - Replacing the dangerous by the non-dangerous or the less dangerous; - Developing a comprehensive security policy; - Giving collective protective measures priority over individual protective measures; - Giving appropriate instructions and information to workers.

The Construction Act stipulates that each construction should meet one, several or all of the following essential requirements in all phases of life, i.e. mechanical resistance and stability, fire safety, hygiene and health protection, environmental protection, and safety of use. According to the Waters Act everyone has the duty to protect the quality and quantity of water and reduce the environmental consequences to a minimum. The law imposes to the owners of the infrastructure intended for hydropower production, irrigation to ensure safety of the facility and equipment from harmful effects of water, and sets the restrictions associated with the general use of water and water infrastructure that offer the basis for public protection. For the dams with the reservoirs retaining water the Act on Protection against drowning should be considered, as well as the Rules on technical measures and requirements for the safe operation of natural and organized pools and nevertheless the Act on natural and other disasters protection. The Act on Protection Against Drowning says that the owner or other person entitled to water and waterside land or the water rights holder must ensure the conditions for the prevention or mitigation of drowning and conditions for water rescue. The laws mentioned above are complemented by the Penal Code (the section thirty “Offences against the general safety of people and property deals with and section thirty two “Offences against the environment and natural resources”), as well as the Rules on technical measures and requirements for the safe operation of natural and organized pools and, last but not least, the Protection Against Natural and Other Disasters Act (Regulation on the provision of occupational health and safety at temporary or mobile construction sites). The listed provision set the basis for the organisation of Public Safety around dam, but on the other hand, the Water law demands from the owner of the dam and reservoir, coastal or other land also to permit harmless passage over the property to the water and allow the general use of water, unless the water, coastal or other facilities are meant for the use of water, to ensure the safety of navigation and protection against drowning in natural pools, constructions intended for the protection of waters against pollution, and constructions

I - 159

Page 160: Study of Social and Economic Impacts of Construction of ...

intended for national defence, protection and rescue of people, animals and property. He also must allow the use of coastal land for gathering, disposal of items for swimming, diving, ice skating, sailing, etc and other activities, i.e. if with such use no damage is caused to the owner of the waterside land. According to the law, it is not allowed to place obstacles that would prevent free passage to or next the water. Indeed, these stipulations make it harder to adopt and implement restrictions and measures needed for provision of public safety. Even though the legislation stipulates that water infrastructure may be used for other purposes, if these purposes are not in contradiction with, or restricting, the activities for which the infrastructure was originally built – despite the fact that the owner of the structure is given the opportunity to exclude any general use at the site of the structure if this is necessary due to protection of human life and health – in the case of state-owned dams for water management purposes, the state rarely resorts to such measures. Apart the free passage and use of the waterside for the activities of general use, the law also allows for the construction of additional agro-forestry buildings at the waterside land in the floor width of 15 metres from the boundaries of the land to the outer limits of coastal land in the water policy areas outside the village and in this way expands the possibility of improper use and access of non-authorized persons.

Figure 6: Additional use – Reservoir used for fish breeding

5. CONCLUSIONS

For a long time in Slovenia, the problem of public safety around dams had been misunderstood and neglected. This aspect of safety was often confused with the aspect of public protection in cases of extreme conditions or natural disasters connected with dam break of floods. Accidents that occurred in the last years on some of the dams as well as

I - 160

Page 161: Study of Social and Economic Impacts of Construction of ...

the recent review of the state of the Slovene dams with water management purpose have prompted the reflection and discussion about the responsibility for such accidents, resulting in people and owner awareness that something should be done to increase and encourage a broader view of the problem., but accidents. The overview of the legal provisions shows there is no legislation addressing the problem of public safety around the dams directly. Despite the absence of the legislation covering this aspect of safety, we can find many provisions that can be used as a basis to ensure of public safety around dams. The main problem is the classification water and water courses as public good. This definition reflects on both: the dams with water management, as well as the dams using water (i.e. hydropower production), since the range of actions to prevent injuries and fatalities is limited by the provisions relating to water as a public good. The other problem is the still is still not sufficient public and owners awareness about the possible hazards that a dam and its operation may bring along. REFERENCES Rajar, R, Kryžanowski, A., (1994): Self-induced opening of spillway gates on the Mavčiče

dam – Slovenia, 18th Congress on large dams ICOLD, Vol.1, Q68, Durban, South Africa

Humar, N., Žvanut, P., Detela, I., Širca, A., Polič, M, Ravnikar - Turk, M., Kryžanowski, A., (2013): VODPREG - state of dams for water management purpose in Slovenia, Ministry of defence of Republic of Slovenia, Slovenia

Humar, N., Kryžanowski, A. (2012): Drtijjščica case study – restoration of the stilling basin for improvement of hydraulic conditions, 24th Congress on large dams ICOLD, Q94, Kyoto, Japan

Occupational Health and Safety Act – Official Gazette N°56/1999 and amendments 64/2001, 43/2011

Water act – Official Gazette N°67/2002 and amendments 57/2008, 57/2012, 100/2013 Construction Act – Official Gazette N°110/2002 and amendments 97/2003, 41/2004,

45/2004, 47/2004, 62/2004, 102/2004, 126/2007, 57/2009 108/2009, 20/2011 57/2012, 110/2013

Penalty code - Official Gaztte N°55/2008 and amendments 39/2009, 55/2009, 56/2011, 91/2011, 34/2012, 50/2012, 63/2013

Act on Protection against drowning - Official Gazette N°44/2000 and amendments, 26/2007, 42/2007, 9/2011

http://sl.wikipedia.org/wiki/Zadnji_spust_po_Savi

I - 161

Page 162: Study of Social and Economic Impacts of Construction of ...

MANAGEMENT AT DOWNSTREAM OF Ir. H. DJUANDA DAM

WITH PUBLIC PARTICIPATION

Djuanda, H. Rachmadyanto & L. Agustini Jasa Tirta II Public Corporation, Purwakarta, Indonesia

[email protected]

ABSTRACT: Government Regulation No. 7/2010, about Jasa Tirta II Public Corporation (PJT II), establishes

duties and responsibilities of water resource management which advancing and aligning social,

environmental and economic functions in water resource management, organize qualified and

sufficient public water utilization for fulfilling lives of many people, including provision of surface

water for daily basic needs; irrigation water through existing systems; flood control; water

resources conservation and development of drinking water provision system and sanitation for

households.

The main problems in water resources management are the environmental issues that arise

because of interaction between economic activities and limited environmental capacity, either

because of natural influence or due to human activities itself, including reduced water quality,

flooding, inefficiency of irrigation water, etc. Community involvement is required considering these

problems arise as a result of society activities itself.

PJT II is trying to align social, environmental and economic functions in water resources

management by growing public awareness and participation in management and utilization of

available water resources in the form of Pilot Demonstration Activity (PDA). Community

empowerment that have been done among others are: community based compost production,

provision of clean water and sanitation, water management at paddy fields to improve water

delivery efficiency, and river bank management with community participation approach.

The results from these activities are improving community empowerment to preserve water

resources and assist the government in the implementation of water resource conservation, control

the destructive force of water, and increase the economic value of water resources management.

Keywords: PDA, community empowerment

1. INTRODUCTION

Government Regulation No. 7/2010 about Jasa Tirta II Public Corporation (PJT II)

establishes the duties and responsibilities of water resources management in the working

area of PJT II with advancing and aligning social, economic and environmental functions

I - 162

Page 163: Study of Social and Economic Impacts of Construction of ...

of water resource management, organize qualified and sufficient public water utilization

for fulfilling lives of many people, including provision of surface water for daily basic

needs; irrigation water provision for agricultural community in the existing irrigation

systems; flood control; water resources conservation and development of drinking water

provision system and sanitation for households.

The main problems in the water resources management are the environmental issues that

arise because of the interaction between economic activities and limited environmental

capacity, either because of the natural influence or due to human activities, including

decreased water quality, flooding, irrigation water use inefficiency, etc.

PJT II continues its efforts to overcome those problems emerged in existing water sources

in PJT II working area, such as quantity and quality of water, operation and maintenance of

infrastructure and services to public. Community involvement optimization is required

considering these problems arise as a result of the society activities itself.

PJT II is trying to align social, environmental and economic functions in water resources

management by growing public awareness and participation in management and utilization

of available water resources in the form of Pilot Demonstration Activity (PDA).

Implementation of PDA on community development, in the R & D fields, that has been

done by PJT II, among others : (1) source of water quality: compost production from rivers

and channels waste with community based, (2) sanitation: clean water and sanitation

provision around banks of West Tarum Canal, (3) food security: water management in

paddy fields on Jatiluhur irrigation system in order to improve the efficiency of water

distribution, and (4) disaster mitigation: Citarum river bank management with community

participation approach.

The PDA activities undertaken by PJT II plays role as to increase community

empowerment in maintaining water sources, and assist the government in water resources

conservation implementation, water damaged control, as well as increasing the economic

value of water resources management. PDA models is very useful to (1) increase public

awareness and involvement in environmental management, (2) improve the effectiveness

and efficiency in water delivery, (3) facilitate the channel maintenance, (4) as it also to

explore business potential in water resources management.

2. METHODOLOGY

Implementation of the PDA programs in of R & D field that were conducted by PJT II

always involve and empower communities as stakeholders of water resource management.

PDA implementation and community empowerment methodology of each R and D field

that have been done can be seen below.

2.1. Compost production from river and channels waste with community based

Appropriate technology such as compost, in addition to the pollution load reduction on

water bodies, it also has economic value where the revenue generated could be used as

source of fund for the activities. Compost production is done through local communities

empowerment assisted by PJT II. The compost produced will be marketed externally to the

farmers, florists, etc. or internally to PJT II to support conservation programs carried out

regularly.

I - 163

Page 164: Study of Social and Economic Impacts of Construction of ...

These activities will raise public awareness and participation in utilizing organic waste in

rivers, channels and agricultural into compost, will provide availability of organic

fertilizer/compost as one of the alternative fertilizer for artificial fertilizers/chemicals, as

well as exploring business potential in organic waste utilization into compost.

Basic framework of the implementation:

a. Site selection, the selected location is a location that has potential of compost base

material, local community groups as a potential manager of compost production, and

areas for compost making processes with minimum of ± 100 m2.

b. Work program socialization, conducted by PJT II on the working groups and related

agencies in the location, in collaboration with local communities, community leaders

and Non- Governmental Organizations (NGOs). It contains, among others, purpose of

the activities, parties will be involved, scope and stages work, responsibilities and

contributions, including the role of the local community, and financing aspects.

c. Preliminary studies, after accepted socialization, further maturation of the work plan

conducted through initial study (preliminary study), with study outputs, among others,

are raw materials volume and its continuity, community groups that can be empowered,

involvement of local authorities/other parties, implementing organization/manager

plan, working area design, implementation guidelines/SOP, and identification of

markets and marketing mechanisms plan of fertilizer product.

d. Empowerment of communities/farmers, at the beginning of the implementation process,

community/farmers empowerment as prospective managers/implementers was

conducted with several inserts, among others, are understanding of compost

production, understanding the use of cutting machines, implementing

organizations/managers plan, understanding of marketing concepts, etc. The

empowerment mechanism is in form of on-site training by bringing instructors/resource

persons.

e. The results of compost production.

f. Compost marketing, based on the existing market potential and marketing mechanisms

that have been agreed within the corridor of PJT II regulations, such as plantation,

ornamental plant industries, residential (household), and agriculture, both direct sales

to the buyer, or through the second party (distributor/stall).

g. Monitoring and evaluation, carried out at every stage of the implementation in order to

optimize the results of the intent and purpose of the PDA's.

Compost production methodology is adapted from a book titled "Membuat Kompos"

written by H.S. Murbandono and published in 2000. It contains the basic process of

making compost, raw material selection, preparation of ingredients pile, pile temperature

and humidity monitoring, maturation, sifting, as well as packaging and storage.

2.2. Water supply and sanitation provision around banks of West Tarum Canal

(WTC)

The demolition of individual water uptake from WTC by domestic and small home

industries, through direct pipes installation into the canal (illegal water extraction) and

construction of latrines/floating toilets, should be done on some stretches of WTC, in order

to improve the quality of water resource management in the PJT II working area. This

activity was aimed to reduce illegal water extractions, which interfere the process of water

distribution in WTC, facilitate canal maintenance, growing community awareness and

I - 164

Page 165: Study of Social and Economic Impacts of Construction of ...

participation in managing the banks of WTC, improving people's access to clean water and

sanitation and exploring business potential in clear water supply from WTC.

The basic framework of the implementation:

a. Site selection, there are many water uptakes, at WTC, by domestic and small home

industries on individual basis through direct pipes installation into the canal (illegal

water extraction) and construction of latrines/floating toilets.

b. Work program socialization, it was conducted by the relevant unit of PJT II working

together with local village/district officers, community leaders and NGOs that exist for

mutual understanding, with substance among others are objectives of the activity,

parties that will be involved, scope and phases of work, responsibility and the

contribution of each parties, including the role of the local community, and financing

aspects.

c. Availability and water provision analysis, quantification of clean water provision was

done by analyzing the total population (number of households) around the area to be

served, with some assumptions: 1) the individual demand 100-150 liters/person/day, 2)

20 - 30% water losses, 3) the maximum operating hours of water treatment plant is 20

hours, 4) the maximum capacity of water treatment plant is 5 liters/sec for delivering

services up to 350 - 400 households. Based on the number of households that will be

served, it can be calculated the quantity of water demand.

d. Land preparation and design, land required: 1) building retrieval (intake), 2) retrieval

pipe from the intake to the water treatment plant, 3) water treatment plant construction

and distribution pipelines. Land for intake construction is determined based on field

recommendations issued by PJT II. Not subject to any financing for this the land use.

The land for pipes and water treatment plant construction is owned by local community

which was submitted for this activity based on community agreement mediated by

local village/district officers. Written documentation of the agreements made should be

pursued and can be obtained at the time of dissemination of the activities.

e. Construction, technical criteria of the intake and public toilet construction shall comply

with the detail criteria set forth in technical recommendations provided by authorized

unit in PJT II. Water measuring devices should be placed before the intake pump or

before the distribution line, to determine the amount of water taken. The intake and

sanitation constuction should be design so as not to be influenced by the existing

buildings around it and secure against the influencing technical forces.

f. Operation and maintenance, operations and maintenance mechanism (O&M) was

arranged based on mutual agreement between PJT II and the community, with the

concept of local community’s empowerment, through existing organizations such as

Koperasi, NGO and Taruna Karya.

g. Monitoring and evaluation, done periodically and in particular to the potential

problems.

2.3. Water management in paddy field on Jatiluhur Irrigation System in order to

improve efficiency of water distribution

Efficiency of water resources utilization is needed in order to improve the quality of water

resource management in the PJT II working area, by providing a model of community-

based agricultural activities with collaboration between PJT II, water users soceity

(farmers) and agricultural extension (Ministry of Agriculture). An increase in the

efficiency of water and fertilizer through technical guidance could reduce production costs.

Therefore community can be more involved in the management of irrigation infrastructure.

I - 165

Page 166: Study of Social and Economic Impacts of Construction of ...

The purpose of the PDA program is to 1) provide information on paddy irrigation

requirements, the effect of doses of water and fertilizer on paddy productivity in intensive

rice fields, 2) provide recommendations of water efficient irrigation techniques and

efficient fertilizer for paddy in intensive rice fields, and 3) increasing community

awareness and participation as a model of community empowerment in irrigation

management.

The basic framework of the implementation:

a. Site selection, with the criteria of lands with good-stable rice production per planting

season, based on the results in the last 5 years production (more than 5

tons/ha/planting season), lands with irrigation water use intensity is greater than 5,000

m3/planting season/ha and lands with a relatively stable embankment and watertight

condition.

b. Seed selection, rice seed that was recommended to be planted is non- hybrid varieties,

such as Ciherang, Muncul and Ketan.

c. Seedbed, was held on a special area of each farmer , including tillage, making beds and

trenches, urea fertilization, and seeding.

d. Land preparation, plowed land, then left for a week in a state of wet. After the first

plowing, the second plowing was done, then raked up into mud and flattened.

e. Planting, planting is done with treatment spacing of 25 x 25 cm, legowo system 4 and

5, the amount of seed planted 2 - 5 seeds (still the traditional systems).

f. Fertilizer, the non-organic fertilizer recommended for every area of 1 ha is 100 kg

urea, 300 kg Fonska, 125 kg SP36 and 75 kg KCL.

g. Plant maintenance, weeding is done at the age of 2 MST (one day before the first

subsequent fertilization), 28 days after planting (fast growing weeds) and ahead of

subsequent fertilization 7 MST.

h. Harvest, performed at physiologically ripe seed or plant has yellowed over 90 %. How

to harvest in general is by cutting the 20 cm part of rice from the ground and separate

the pithy full parts.

i. Monitoring and evaluation, done periodically and in particular to the potential

problems.

Criteria for the implementation of irrigation water provision:

a. Water delivery technique, disconnected irrigation techniques is an interrupted irrigation

techniques of so that inundation does not occur. Irrigation provision is given according

to crop needs with time interval determined based on the results of soil analysis and/or

based on observations of field conditions. The supply of water is based on conditions at

the time the observations were made, when Macak Rambu has occurred at the paddy

field.

b. Crop water requirements analysis, performed based on the estimated water

requirements of plants according to the FAO method. Crop water needs are reflected

through water demand deficit in the period characterized by the ratio ETR ETM < 0.80

(Balitklimat, 2009). If the ETR/ETM close to 1, means that the plants use water

effectively, which in turn will result in higher production. Conversely, when the

ETR/ETM less than 0.80 means that plants experience water shortages or water stress

and will lead to a fall in production.

c. Water provision quantification, measured during the growth of rice (ranging from land

preparation to harvesting), requires measurement tools that are relatively accurate but

I - 166

Page 167: Study of Social and Economic Impacts of Construction of ...

easy to operate and inexpensive in installation. A triangular (V - Notch) weir to

estimate the discharge was built at the intake gate. Observation of water level at the

weir is done on daily basis. As for calculating the additional water due to rain, rain

gauge will be installed at the demonstration plot observations.

2.4. Management of Citarum river banks with community participation approach

The decrease in the capacity of Citarum River at the downstream which is caused by

sedimentation, also caused by a variety of community activities, such as illegal

settlements, waste and perennials that grow on the banks of the river which is intended for

the drainage of flood discharge. PJT II is very interested in natural resource management,

especially in the lower reaches of the Citarum River. It is in line with the basic tasks of

PJT II, in particular watershed management, such as protection, development, and use of

water and water resources.

This activity is aiming to arrange riparian land which involving surrounding community, to

organize and restore the function of the Citarum river banks at the downstream in

accordance with the flood drainage capacity, to prevent flooding in Bekasi and Karawang

Regency which causes loss of agriculture, aquaculture, property and possible loss of life,

to increase community participation in the river banks management, to increase the

business potential on the river banks through land dues participation.

The basic framework of the implementation:

a. Site selection, through surveys and investigations carried out on the banks of the

Citarum River with abundant crops that intrude the flood discharge and on locations

where many flood discharge function changes expected.

b. Work program socialization, conducted by the authorized unit of PJT II in coordination

with local village/district officers, community leaders and existing NGOs for mutual

understanding. Substances delivered among others are objectives of the activity, the

parties involved, the scope and phases of work, responsibilities and contributions of

each party, including the participation of local communities, plans for enforcement

action at the field against squatters, crops that obstruct water flow nuisance, and

financing aspects.

c. Preliminary studies, after socialization accepted, further maturation of the work plan

done through the initial study (preliminary study) with some relust such as, the volume

of raw materials and its continuity, community groups can be empowered, involvement

of local authorities /other party, plan of implementing organization/manager, work area

design, implementation guidelines/SOP, and identification of markets and plan of

productmarketing mechanisms.

d. Preparation, logging and land clearing done in the area of the Citarum River

embankment which extensive agreed in socialization and coordination, using saws

(chain saw), axes, machetes and as well as other tools recommended by PJT II.

e. Land management, land plots pattern adapted to the existing Stewardship Permit

(SIPL) and the field is determined by considering the recommendations of PJT II, the

manufacture of land plots bounded by the size of the dike (3 x 5) meters, and the

construction of a simple irrigation system.

f. The selection of plants and planting seedlings, plant species and varieties to be planted

is done by coordinating with the Department of Agriculture and local government

plantation, cultivation and selection must consider the useful life of the plant which is

less than 3 - 4 months.

I - 167

Page 168: Study of Social and Economic Impacts of Construction of ...

g. Operation and maintenance, maintenance and care of plants is done by groups of

farmers, together compose guidelines for the implementation of O&M, in the

formulation of the O&M mechanism and O&M cost needed.

h. Monitoring and evaluation, done periodically and in particular to the potential

problems

3. THE RESULT

The results of the implementation of water resource management programs by engaging

and foster public awareness and participation in management and utilization of water

resources available, in the form of a PDA, that has been done by PJT II period from 2010 -

2011 include:

3.1. Compost production from river and channels waste with community based

a. The selected locations are Cibeet Syphon and Curug Weir.

b. The production analysis was estimated ± 5 m3/day. Cpacity analysis at early stages of

production assumed to be ± 637.5 kg/day.

c. Optimum land requires was 200 m2.

d. The estimated need for tools and materials for composting are tool counter, 0.1875

liters per day activator, bags of 13 pieces/day, 1 liter/day solar and 0.1 liters/day engine

oil.

e. Needs minimal 3 manpower to implement composting with the estimated load time is 8

hours of work per person per day.

f. Operational costs were calculated based on operating costs estimation alone and

materials supplied by PJT II. Estimated operational costs required for the composting

of Rp 231,000/day.

g. Estimated revenue of Rp 406,500 per day.

The problems that arose were improper composting, required clear goals of marketing

either directly to consumers or through cooperation with relevant agencies, man power

from the local community and authorities, must maintain continuity and cohesiveness of

work, and explained the expenditure and revenue composting with direct supervision from

PJT II.

3.2. Water supply and sanitation provision around banks of West Tarum Canal

(WTC)

a. The location selected was in B.Tb. 19.d, West Telukjambe District, Karawang

Regency.

b. The capacity is 5 liters per second. WTP in Rural Margakaya serve 100 households and

280 families are served from WTP Rural Karangmulya.

c. An area of approximately 20 m2 was donated by the community through the Village

Head for this activity.

d. The water supply system managed by the community, then Perum Jasa Tirta II in this

case acts as a provider of raw water for the drinking water provision.

The problems that arose were intention and purpose of the activity could not succesfully

delivered to the community partly due behavior of people and their understanding about

I - 168

Page 169: Study of Social and Economic Impacts of Construction of ...

the activity was not maximal, the intention of local community to construct their own

facilities sometimes make the yield and quality of the building was not optimal, and

society is always eager to get external funding continuously, this is not in line with the

concept of community empowerment is the mission activities.

3.3. Water management in paddy field on Jatiluhur Irrigation System in order to

improve efficienc 1 ) The location selected

a. Selected location was at B.Tt.5 East Tarum Canal, Khanewal district.

b. The study concluded that intermittent irrigation technique was providing irrigation dose

equivalent to only 67% of the dose in conventional irrigation.

c. The intermittent irrigation techniques dose was at 5118.00 m3/MT/ha.

d. The productivity was very low due to air attacks that have marred the brown plant

hopper (± 20 % of the experimental plots).

e. Statistical test results showed that the water savings that can be made through the

application of intermittent irrigation did not affect the rice production.

The problems that arose the very were climatic conditions reduced the dosage, the

topography of the land was very diverse, some rice fields were relatively very broad, does

not have a stable and impermeable, and water delivery to the field requires very good

supervision from the interpreter/analyst at a local wetland observation.

3.4. Management of Citarum river banks with community participation approach

a. Selected location was at the lower reaches of the Citarum River, the Tunggak Jati

Village, West Karawang District, Karawang Regency (in the working area Division II).

b. The coordination with the local community, the Department of Agriculture and

Plantation of Karawang District, and university students from UNSIKA.

c. Based on the soil research plants that were tested are local varieties of maize plants and

Bangkok, local varieties of soybean plants, and local varieties of peanut plants.

d. The area of plots for each crop were corn crop of 3000 m2, 2000 m

2 peanuts and soy

beans of 2000 m2.

e. From pasca flooding, which occurred in March of 2010, the critical locations that have

vegetation were located on the banks of the downstream of Citarum River barriers,

namely: the right and left banks of nearby Kedung Gede Bridge at the Tanjung Pura to

Purwadana Village; right riverbank at Purwadana to Teluk Jambe village, as well as the

right banks of the Teluk Jambe village until Walahar Weir.

The problems that arose were the compensation for the crops is high, understanding and

the purpose of the activity from government officials/community leaders/NGOs involved is

less, generally are low-income people, flooding will make the plants harvest failed.

4. CONCLUSIONS AND RECOMMENDATIONS

Research and development activities of water resources management with the pattern of

community development were done through pilot activities (PDAs) such as 1) to reduce

the organic solid waste in a river or channel by making compost, 2) the arrangement of

illegal water intakes and floating latrines/toilets on West Tarum Canal that contributes

pollution load and decrease the aesthetic value of raw water supply for drinking water, 3)

structuring riparian land with crop patterns as well as organize and restore function in

I - 169

Page 170: Study of Social and Economic Impacts of Construction of ...

accordance with the flood drainage capacity of Citarum River banks, and 4) water saving

agriculture and fertilizer through coaching techniques with coordination PJT II, farmers,

and agricultural extension (Ministry of Agriculture).

Through these PDAs, information, science and technology transfer in natural resource

management from competent actors/agencies/individuals to the community as and

stakeholders , can be done effectively and efficiently. People understood the stages of the

process, follow/engage in activities and participate to benefit from these activities.

PDA's activities can be applied to other locations to increase community empowerment in

water resources management, water resources conservation, control the destructive force of

water, and increasing economic value. Through these PDAs it were useful to increase

public awareness and involvement in environmental management, to improve the

effectiveness and efficiency in water delivery, facilitate the maintenance of the channel,

and to explore business potential in water resources management.

I - 170

Page 171: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

ENHANCING COMMUNITY PARTICIPATION IN DAM MANAGEMENT

(PREPAIRING EMERGENCY ACTION PLAN) USING VISUAL

COMMUNICATION MEDIA CONCEPT

(Case Study : Krisak Dam, Wonogiri, Central Java, Indonesia)

Juliastuti Civil Engineering Department, Bina Nusantara University,Jakarta, Indonesia

[email protected]

Sari Wulandari Visual Communication Design Department, Bina Nusantara University,Jakarta, Indonesia

I - 171

ABSTRACT

Dam performance degradation that also affects dam safety is related with a well-known

problem, which is change of land use both upstream and downstream, and lack of care

from the society to take care the area surrounding the dam. However, the local rules say

that society have the same right to take place in dam building and maintenance. So, we

need to have an activity that involves the society around it.

Much of the program that involves society around it has been done in DOISP (Dam

Operational and Improvement Safety Program) that have purpose to maintain the dam

itself and water catchment area and to educate the society itself so they could help in

maintaining both of them. Beside that for preparing if the dam collapse, using

information and knowledge of both profile and characteristics of a dam collapse

scenario, to know the action for preparing before the disaster, what to do at the disaster

itself, and disaster recovery efforts. Then we need to socialize to the society about this

disaster scenario using integrated information, from government to people, both in

content and method of distribution, so when the disaster itself happens, everyone already

have that awareness and preparedness, reducing disaster casualties.

For that we need to have visual communication design team to help us make the

information itself, to persuade people, give understanding, give the information, even

make signs on the field so people could identify the problem fast and exact, especially

when the disaster happens. This paper will explain one of the Emergency Action Plan

which already been done to society around Krisak Dam, that based on Dam Break

Analysis calculation they created a Emergency Action Plan guideline using visual

communication media concept.

Keywords: Emergency Action Plan, Visual Communication Design, Dam Break Analysis

Page 172: Study of Social and Economic Impacts of Construction of ...

1. INTRODUCTION

Based on the Government Regulation of Indonesia number 37 of 2010 on Large Dam

(PP 37/2010) which refers to the ICOLD Regulation (International Committee on Large

Dam) : every dam required to have Emergency Action Plan (EAP). The purpose of the

EAP is to minimize the risk of loss of life and property which may be caused by dam

break which would cause flooding in downstream areas which have population higher

than upstream areas. The EAP will be socialized to every stakeholders including people

that live around dam which are potential to be victims when dam break happen.

Thus the public eventualy need to have been given by information and knowledge about

disaster that might happen, preparation in facing of disaster, the action to be taken when

disaster occurs as well as how to handle it. The information has to be socialized to the

community through an integrated and systemic information, between public and

Governments that are represented by the BPBD (Badan Penanggulangan Bencana

Daerah), both in content and ways of distributing information so that when disasters

happen all parties have vigilance and readiness.

In the socialization, Visual Communication Design play important roles in order to give

information, education, urge people in persuasive way, even make a field marker system

so that the public can identify the information easily, quickly and precisely, especially

when disasters occur.

2. THE ROLE OF VISUAL COMMUNICATION DESIGN IN CREATING

INFORMATION MEDIA TO SUPPORT EAP

For EAP purpose, Visual Communication Design used information design which

presenting information in a way that fosters efficient and effective understanding of it.

The term has come to be used specifically for graphic design for displaying information

effectively, rather than just attractively or for artistic expression. Information design is

closely related to the field of data visualization and is often taught as part of graphic

design courses.

Some of Visual Communication Design convey message by graphic design. It takes

graphics because they communicatie preverbally. Viewers see and get them before they

ever read a word. In fact graphics may be all that foreign, illiterate, or even busy or

stressed viewer get, so they depend on universal images that tell the story without

words. Other viewers use their first graphic impression to make the decision.

Map is one of various forms of information design media which use graphic. In the

Information Design discussed some of the principles which include Cognitive

Principles, principles of communication, Aesthetic Principles, so the factors that can

affect successful a information design can be optimized. Information Design created to

help explain things and use language, typography, graphic design, systems and business

process improvement as a tool.

It is important to make integrated information system that involves several media that

will support each other according to their functions. A leaflet that contains a map of the

evacuation and other informations regarding anything that need to be prepared in the

I - 172

Page 173: Study of Social and Economic Impacts of Construction of ...

face of a disaster and what to do when a disaster occurs, will support a directional sign

which serve people to go into a safe place.

3. DESIGN CONCEPT IN MAKING VISUAL COMMUNICATION MATERIAL

FOR EAP

These are some stages to make the concept of visual communication material which will

be used to disseminate EAP:

- Bathimetry and Tachimetry survey

- Topography survey

- Hydrology analysis

- Dam Break Analysis

- Innudation map

- Social Economic survey

- EAP Draft

- Consult with stakeholder (goverment, community leaders, BPBD and others )

- Approval Draft

- Making leaflet and animation

- Dissemination

4. CASE STUDY

4.1 Krisak Dam

The Krisak Dam is located in the Singodutan Village, Wonogiri District, Central

Java Province, ± 8 km southeast of Solo. Krisak Dam is the aging dam in Indonesia

because it was built 1943. Thats why the risk of dam break is higher than the other

dam. The area of watershed Krisak dam is ± 3,46 km2. Currently the dam is managed

by the Central River Region (BBWS) Bengawan Solo and Central Water Resources

Managament (Balai PSDA) Bengawan Solo. The type of dam is homegenous earth

dam to purpose for irrigation. At downstream is a residential areas. Livelihood of the

population is primarily farming.

Figure 1. Krisak Dam Location

Technical data of Krisak dam are follows:

I - 173

Page 174: Study of Social and Economic Impacts of Construction of ...

1. General

- Location Village/District : Singodutan

- Regency : Wonogiri

- Province : Central Java

- Benefits : Irigation 1.500 ha

- Year of Construction : 1943

- Manager : Balai PSDA/BBWS Bengawan Solo

- Catchment Area : 3.46 km2

- Annual Rainfall : 1.900 mm

2. Reservoir

- Flood Water Elevation : El.+ 113,75 m

- Normal Water Elevation : El.+ 113,50 m, 3.72 million m3

- Minimum Water Elevation : El.+ 102.92 m

- Volume Reservoir on:

- Dead Storage : 1,025 million m3

- Effective Storage : 2,692 million m3

3. Dam

- Type : Homogenous Earth Dam

- Height : 20 m

- Length : 350 m

- Width : 5 m

- Crest Elevation : El.+ 114,50 m

4. Spillway

- Type : Free flow Ogee

- Flood Design (PMF) : -

- Elevation : El.+ 113,50 m

- Length : 33 m

5. Instrumentation

- Piezometer : 28 Unit, hydraulic

Figure 2 Cross Section

I - 174

Page 175: Study of Social and Economic Impacts of Construction of ...

4.2 Existing Condition

In 1998, the elevation of crest dam is become 115.50 WSL (the original of elevation

crest dam is 114.5 WSL . Based on the hidrology study, the spillway can reduse

discharge from 136.46 m3/s to 62 m

2/s. All piezometer have broken. V Notch need to

be improved and no lighting. The capacity of resevoir is to reduse from 3.72 million m3

to 2.55 million m3 because of sedimentation.

Crest Dam

Downstream

Outlet

Spillway

Figure 3. Existing Condition

4.3 Dam Break Analysis

Dam break analysis would lead to the occurrence of flash floods in the downstream area

of dam. In order to guide the preparation of Emergency Action Plan Krisak Dam, the

areas expected to be affected by flooding would be mapped.

Map of flooding Krisak collapse will be made in several possible mechanisms and

conditions of the collapse of the dam, so that it can be seen flooding the greatest impact,

which will be designated as a flood inundation map Krisak Dam.

Impacts do not occur at the same flooding from one area to another area, so the flood

map will be divided into multiple zones based on the depth of the flood hazard area. In

addition to the flooding maps will be posted information about the arrival time along the

river. Preparation of flood maps consists of three activities:

- analysis of dam collapse

- inundation maps

- evacuation route

I - 175

Page 176: Study of Social and Economic Impacts of Construction of ...

Some activities that should be carried out to make a guide for Preparation Emergency

Action Plan are :

- Topography and Tachimetry Analysis

- Hidrology Analysis

- Dam Break Analysis

Figure 4 Situation Map Krisak Dam

(Based on measurement and calculation)

Figure 5 Krisak Dam Hydrograph

(Based on calculation)

The analysis of dam break is performed by a variety of alternative conditions

that can cause the collapse of the dam, while the parameters condition are:

- At the top of dam elevation (on the overtopping)

- At lower, the middle and upper dam elevation (on the piping)

Analysis of the collapse of the dam using a standard formula that is used in

Indonesia (including the metric unit used).

For calculations using a software Zhongxing-HY21.

a. Overtopping

To evaluate overtopping, the modelling based on reservoir routing dam.

Reservoir routing of Dam Krisak based on the PMF Q = 136.46 m3/sec.

b. Piping

To evaluate piping, the modelling consist 2 (two) conditions, i.e normal

condition and the PMF conditions. In each of these conditions, will be analyzed

at three (3) approximate locations piping : at the bottom of the dam, middle and

the upper of the dam.

c. Result

As has been explained that the analysis of the collapse of the Krisak Dam

reviewed based on overtopping for PMF condition, and piping, which under

normal condition and the PMF condition.

From the analysis using software Zhongxing-HY21, known maximum flood

height due to collapse of the Krisak dam along the downstream dam for PMF,

both due to overtopping and piping is 3.50 m. This results ( for two conditions)

are not much different, only the collapse models are different. As for the piping ,

the maximum flood height due to collapse of the Krisak Dam along the

downstream dam is 2.10 m.

The result of overtopping calculation results can be seen in the figure below:

0,00

20,00

40,00

60,00

80,00

100,00

120,00

140,00

160,00

0 5 10 15 20 25 30 35

Deb

it (

m3/d

t)

Waktu (jam)

Hidrograf Banjir Waduk Krisak(Metode Nakayasu)

QPMF, Qp = 136,46 m3/dt

Q1000, Qp = 37,18 m3/dt

Q100, Qp = 31,79 m3/dt

Q25, Qp = 24,95 m3/dt

I - 176

Page 177: Study of Social and Economic Impacts of Construction of ...

2 hour

3 hour

5 hour

7 hour

10 hour

15 hour

Figure 6 Dam Break due to Overtopping

Figure 7. Inundation Map due to

Overtopping (Arrival)

Figure 8. Inundation Map due to Overtopping

(Receding)

Based on dam break analysis and social survey , the risk areas of flooding

covering 4 villages : Singodutan, Kaliancar, Gemantar and Jaten which time of

arrival, recending time, distance and risk population can be see at Table 1.

I - 177

Page 178: Study of Social and Economic Impacts of Construction of ...

Table 1. The Risk Area of Flooding

4.4 Evacuation Route

To determine the evacuation route is based on the inundation map of dam break, where

the determination of the path is based on capacity, distance, elevation , transportation

and social-economic survey (see table 2 and Fig. 9).

Table 2. Evacuation Location

I - 178

Page 179: Study of Social and Economic Impacts of Construction of ...

Figure 9. Evacuation Route

I - 179

Page 180: Study of Social and Economic Impacts of Construction of ...

5. COMMUNICATION VISUAL CONCEPT FOR DISSEMINATION EAP

GUIDE

In order to socialize the EAP to the community, they certainly needs to know in advance

the situation and conditions of the environment where they live. They understand the

importance of EAP, what is important to prepare, and not lose the orientation when the

disaster occurred.

Therefore need to make a communication media that can convey that information to the

public. One of the popular media used by the society is leaflet. It can keep information for

long time and can be read back anytime, anywhere and easily to produced. It is important

to note that to visualize the information on the leaflet should be done properly by arrange

the layout hierarchical so reader can get the point easily, especially when emergency case

occur. Some group of information with bold or big typography used to make emphasis and

eye-catcher.

In this leaflet contained some information that is important to note in the EAP

communication material:

Cover:

- Title and mandatories

- profile of EAP

- equipments need to be prepared

- what people have to do

- who to call in case of emergency

Inside:

- a map of the location and evacuation routes

- location outside to evacuate

- evacuation process

Figure 10. Visual Communication Design for EAP in Leaflet (cover)

Kesbangpol dan Linmas

Kab.Wonogiri Telp : 0273-325373 Balai PSDA Bengawan Solo

Telp: 0271-825361

HUBUNGI !

I - 180

Page 181: Study of Social and Economic Impacts of Construction of ...

Figure 11. Visual Communication Design for EAP in Leaflet (inside)

In addition to leaflet, can be used audio-visual electronic media for media integration

besides leaflet for dissemination the information. Through this medium cold use sound and

motion picture in text an infographic so that the information presented could more

memorable. This audio visual media can be aired on local television or played on public

screen at village halls.

6. CONCLUTION

- In order to conveying information about disaster alert to the people, need to get

accurate data for everything telated to evacuation such as :

1. The system and procedure for prepare and execution

2. People need to be given information as clear as possible and easy to remember

that when disaster occurred people can taking action directly, quickly and

properly.

- With involvement in a social campaign for disaster preparedness by Visual

Communication Design, all of these information are expected to be conveyed in an

integrated, effective and efficient communication through infographic visualization

on leaflets, video and signage.

7. REFFERENCES

- Mollerup, Per, (2005) Wayshowing: A guide to environmental Signage Principles &

Practices, Baden: Lars Muller Publishers,.

- O'Grady, Jenn, Ken Visocky, (2008) The Information Design Handbook, Mies,

Switzerland : Rotovision.

- Samara, Timothy. (2005). Publication Design Workbook. Beverly: Rockport Publishers.

- Knight, Carolyn. (2003). Layout: Making It Fit. Gloucester: Rockport Publishers Inc.

Jalur evakuasi desa : Brajan

Lokasi pengungsian : Terminal Adipura

Jarak : 0,5 km

Jalur evakuasi desa : Gempeng

Lokasi pengungsian : Balai Gempeng

Jarak : 0,5 km

Jalur evakuasi desa : Singodutan

Lokasi pengungsian : Balai Dusun

Sanggrahan

Jarak : 0,5 km

Jalur evakuasi desa : Tenongan-Gunan

Lokasi pengungsian : Masjid Nurul Fikri

Jarak : 1 km

I - 181

Page 182: Study of Social and Economic Impacts of Construction of ...

1

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH

, 2014

Landslide Prevention On Reservoir of Upper Cisokan Pumped Storage Hydropower

Based on Community Development

Buchari Zainal Arifin & Nurmala Fauzia PT PLN (Persero) Unit Induk Pembangunan VI, Bandung, Indonesia

[email protected]

ABSTRACT: Indonesia, as one of the developing countries, in the process of growing, hence needs huge amount of electrical energy supply. Specifically for the Java-Bali region, the peak load in 2012 reached 21.237.000 MW, an increasing of 7.59%. In order to meet the electricity needs during peak hours, PT PLN (Persero) is building Upper Cisokan Pumped Storage Hydropower 4x260MW. This power plant is the first pump system in Indonesia. The working principle is storing energy in the form of water pumped from the lower reservoir into the upper reservoir during off-peak load and at high electrical demand (peak load), the water released from the upper reservoir into the lower reservoir to generate electricity. It will always change the reservoir water level fluctuations at 19,5 meters in 6,5 hours. Changes in water level fluctuations can rapidly influence reservoir slope stability, thereby potentially having catastrophic landslideExamination

. of the reservoir slopes through investigations Light Detection and Ranging(LIDAR)

Map, Study of Watershed Management Plan, Previous Reports, and the physical properties of geological parameters. Based on these data, further modeling is conducted using the program Slope / W, it was found that there is potential land slide due to the low safety factor. Through this research, it can be seen the influence of the pumped storage operating system on the reservoir slopes. Prevention of lanslide is done by involving the community through disaster prevention, emergency response, rehabilitation, etc. Thus, the slopes of which may potentially collapse can be done early treatment, so the slopes are out of landslide danger and no fatalities when the upper cisokan pumped storage hydropower operating

.

Keywords: Pumped Storage System, Water level fluctuations, Safety Factor, Slope Stability, Community Development 1. INTRODUCTION Hardiyatmo (2006) states that the mass movement of soil or often called a landslide is one of the natural disasters that frequently hit the hills in the wet tropics. This mass movement is the process of establishing equilibrium in the world caused by a variety of factors, both natural factors and human factors. Cruden (1991, in Deasy, 2010) briefly explain that the landslide is the movement of a mass of rock, debris or soil material down the slope.

I - 182

Page 183: Study of Social and Economic Impacts of Construction of ...

2

Terzaghi cause avalanches divide into two, namely: 1. External effect: the effect of shear forces resulting in increased without any change

in the shear strength of the soil. For example: sharpen the slope of the cliff, deepening the excavation and erosion of the river;

2. Internal effect: increasing the influence of pore water pressure in the slope. According to Terzaghi, which became one of the causes landslide is the increasing influence of pore water pressure in the slope (Hardiyatmo, 1992). Lower water levels suddenly (rapid drawdown) resulted in the addition of loads by heavy layers previously submerged land becomes submerged. Upper Cisokan Pumped Storage Hydropower is a power plant with the first pump system in Indonesia. With the principle works, it will always be a change of reservoir water level fluctuations, both at the upper reservoir and lower reservoir. Changes in water level fluctuations that can rapidly affect the stability of slopes around the reservoir. 2. GEOLOGICAL CONDITION Upper Cisokan Pumped Storage Hydropower will be located in the Cisokan River which has a mountainous topography with altitude ranging from 700 m to 1000 m. As one of the tributaries of the Citarum River, Cisokan River comes from Sukanegara and meandering in a deep gorges. Strata of geological formations including Oligosen (Rajamandala Formation), Miocene (Citarum Formation), Pliosen (Pb Formation), as shown in Figure 1.

Figure 1.

Geological map in Area of Upper Cisokan Pumped Storage Hydropower

3. LAND USE CONDITION Interpretation of satellite imagery results produce land use maps of 7 classes of land use, such as: forest, garden / farm, residence, rice, bush / scrub, moor / farms and water bodies, as can be seen in Table.1 and Figure 2.

I - 183

Page 184: Study of Social and Economic Impacts of Construction of ...

3

No. Table 1. Land Use Condition

Land Use Wide (Ha) Percentages 1 Forest 14.915 39,85%

2 Garden/ Farm 5.993 16,01% 3 Residence 1.283 3,43% 4 Rice 6.121 16,36% 5 Bush/ Scrub 5.855 15,65% 6 Moor/ Farm 3.034 8,11% 7 Water Bodies 241 0,59% Total 37.441 100%

Figure 2. Land use satellite imagery interpretation

3. LANDSLIDE AVALANCHE The selection of areas which may experience sliding slope under the influence of the upper reservoir water level fluctuations are determined for the slopes (7 pieces area) which located around the area of the Upper Reservoir based on sliding trail has gone before, as shown in Figure 3. The slope piece then modeled using program Slope / W to determine the stability of the slope on the pieces. As each piece in each area shown in Figure 4.

Figure 3. Traces of previous avalanches

Forest40%

Garden/ Farm16%Residence

3%

Rice16%

Bush/Scrub16%

Moor/farm8%

Water bodies1%

I - 184

Page 185: Study of Social and Economic Impacts of Construction of ...

4

4. SLOPE MODELLING USING SLOPE/W Slope stability analysis was conducted using slices ( Slice Method) with a field of circular sliding through the program Slope / W analysis of the slope stability due to the change of water level fluctuations in the upper reservoir modeling performed with several conditions , among others : First , Low Water Level ( LWL ) the height of the water surface elevation of 777.5 above sea level. Secondly , the High Water Level ( HWL ) with a height of water level of 796.5 above sea level. Third , Full Water Level ( FWL ) the height of the water surface elevation of 799.5 above sea level. In this condition that the modeled water surface elevation exceeds the elevation of HWL due to very high rainfall and ground water level equal to the height of the soil surface . Fourth , Low Water Level ' ( LWL ' ) which is the current state of the model has undergone rapid drawdown of the initial height above sea level of 796.5 and the final height of 777.5 above sea level. The physical properties of geological input parameters include: unit weight , cohesion and friction angle . The physical properties of each geological layer on slopes that were analyzed are described in Table 2.

Rock Class Table 2. Physical properties of geology

CL D Top Soil Unit Weight (kN/m³) 25 23 15.64 ~ 16.30 Cohesion (MPa) 0.5 0.1 17 ~ 18 Friction Angle (degree) 38 36 28.5 ~ 30.1

Figure 4. Map of Potential Sliding Area

I - 185

Page 186: Study of Social and Economic Impacts of Construction of ...

5

4. RESULT OF SLOPE MODELLING The results of the calculation of slope stability analysis using program Slope / W which covers the area around the Upper Reservoir experienced a catastrophic landslide potential are presented in Table 3. Table 3. The Value of Safety Factor Base on Slope

AREA DAN POTONGAN FAKTOR AMAN PADA SETIAP KONDISI MUKA AIR LWL HWL FWL LWL'

AREA A 1-1' 4.00 1.84 1.74 0.75 2-2' - 3.18 3.31 1.79

AREA B 1-1' 2.15 2.08 2.09 1.49 2-2' 2.80 2.79 2.79 1.68

AREA C 1-1' 1.82 2.59 2.72 1.67 2-2' 0.74 2.55 2.54 1.68 3-3' 1.60 3.42 3.41 2.10 4-4' 1.26 5.85 5.79 3.53

AREA D 1-1' 7.01 1.30 1.42 0.35 2-2' - 2.21 3.77 2.68

AREA E 1-1' 1.05 2.02 1.95 1.41 AREA F 1-1' 10.44 2.74 3.23 1.30

2-2' 4.92 2.45 2.48 1.28 AREA G 1-1' 3.01 1.99 2.06 1.26

2-2' 0.96 1.63 1.64 0.99 5. LANDSLIDE PREVENTION BASED ON COMMUNTY DEVELOPMENT One way to prevent the occurrence of landslides is to empower the community . This method provides the opportunity for the public to participate directly in the avalanche prevention programs . The detailed stages of the process of empowerment is through the facility to : 1 . Policing needs and participatory problem analysis 2 . Formulation of alternatives and the selection of actions based on priorities 3 . Action plans ( activities , outcomes , ukutan success , time , person in charge , location

and cost ) 4 . Developing the capacity and capability of community groups 5 . Implementation of action plan 6 . Cooperation and information networks as well as access to venture capital 7 .Strengthening community institutions to study and determine the water resource

management decisions are made and action plans 8 . Periodic monitoring and evaluation of participatory 9 . Independent Community empowerment assumes and believes that people have the ability to solve their own problems through certain facilities by other parties . That means there must be mutual

I - 186

Page 187: Study of Social and Economic Impacts of Construction of ...

6

trust between the companion and the accompanying ( departments, agencies , NGOs , companies , etc. ) who do empowerment Build participation is determined by the type of participation that will be realized . Some types of participation reflects the different degrees of involvement , such as : 1 . Manipulative and decorative 2 . Passive 3 . Provide information and consultation 4 . Material incentives 5 . Functional 6 . Interactive participation 7 .Self Mobilization

Figure 5. Flowchart of stakeholder participation on PLTA Cisokan

6. CONCLUSION Some of the conclusions obtained from the results of the study are as follows: 1. Based on observations, it is known that the reservoir area Upper Cisokan Pumped

Storage Hydropower potential is experiencing catastrophic landslide in Upper Reservoir area, it is marked with a landslide scars that are found in the area;

FORUM SADAR BENCANA

COMPANY (BUMN)

VILLAGE

HIGHER EDUCATION

PROVINCE ADMINISTRATION

DISTRICT ADMINISTRATION

DISTRICT ADMINISTRATION

COMDEV DONOR AGENCIES

I - 187

Page 188: Study of Social and Economic Impacts of Construction of ...

7

2. Modeling using program Slope / W to get that on the slopes (7 pieces area) around the upper reservoir was found as a result of fluctuations in the potential sliding the upper reservoir when the water level of Upper Cisokan Pumped Storage Hydropower operational, namely: Area A (piece 1-1 '), area C (pieces 2-2 '), area D (pieces 1-1'), area E (pieces 1-1 ') and area G (pieces 2-2');

3. In general, potential landslide dominated when the reservoir water level decline (rapid drawdown) at the level of a LWL 'than when impounding at an altitude of LWL

4. landslide prevention through community development programs proven to be effective in order to prevent a sustainable basis. besides it along with environmental protection, stakeholders can also empower the local community progress.

REFERENCES Ambarsari, Deasy, 2010, Evaluasi dan Analisis Stabilitas Lereng Di Desa Tenglik

Kecamatan Tawangmangu Karanganyar Jawa Tengah, Jurusan Teknik Sipil dan Lingkungan FT UGM, Yogyakarta.

Anonim, 2004, Geostudio Tutorials, Geo-slope International Ltd, Alberta, Canada Bowles, Joseph E., 1984, Sifat-Sifat Fisis Dan Geoteknis Tanah (Mekanika Tanah), Edisi

2, Erlangga, Jakarta. Hardiyatmo, H.C., 2006, Penanganan Tanah Longsor dan Erosi, Edisi Ke-4, Gadjah Mada

University Press, Yogyakarta. Karnawati, D., 2005, Bencana Alam dan Gerakan Massa Tanah di Indonesia dan Upaya Penanggulangannya, Jurusan Teknik Geologi FT.UGM,Yogyakarta. PT PLN (Persero), Suplementary Study of Upper Cisokan Pumped Storage Hydroelectric

Power Plant Project, Newjec. United States Geological Survey, 2011, Lanslide Types and Processes,

www.pubs.usgs.gov. PT PLN (Persero), Preliminary Geotechnical Baseline Report of Upper Cisokan Pumped

Storage Hydroelectric Power Plant Project,Sinotech JV. PT PLN (Persero), Laporan Studi Pengelolaan Daerah Aliran Sungai Cisokan Hulu untuk

Menunjang PLTA Upper Cisokan Pumped Storage ,Geotrav Bhuana Survey.Author

I - 188

Page 189: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Strategies of public awareness on dams and reservoirs

J. Polimón Spanish National Committee on Large Dams (SPANCOLD), Spain

[email protected]

ABSTRACT: Public awareness relating to dams and reservoirs has become one of the main concerns of professionals and therefore of ICOLD and National Committees. The evolution of society in this subject has gone from a clear support to the construction of large dams to provide water needed for life and human and social development, to a contrary position. Especially in countries with a high level in the development of their water resources, this allows them to think that these needs are already resolved. This approach has two serious drawbacks: 1) in many countries water is needed to have a reasonable standard of living and to alleviate the effects of arid climates and droughts, and 2) the expected effects of climate change make it clear that we need to adapt the strategy in water management to a new scenarios, even in developed countries, as seen in the flooding of large areas of Europe and America in the years 2012 and 2013. . Given these new situations ICOLD, through its Department of Communication and its Committee on Public Awareness and Education (COPAE), is developing a comprehensive information strategy to provide the public with objective data on the benefits of dams, reservoirs and regulating rivers. This strategy is being implemented in some countries by their National Committees. A good example of these new activities is the SPANCOLD mirror Committee of COPAE, named CIPE, which has a composition in which, besides engineers (some with extensive experience in communication), there are journalists, environmentalists, historians, geographers and other professionals with experience in communication. The strategy implemented by SPANCOLD and its special features are given in this paper. Keywords: public awareness, benefits of dams, communication with media

I - 189

Page 190: Study of Social and Economic Impacts of Construction of ...

INTRODUCTION Public awareness relating to dams and reservoirs has become one of the main concerns of professionals and therefore of ICOLD and National Committees. The evolution of society in this subject has gone from a clear support to the construction of large dams to provide water needed for life and human and social development, to a contrary position. Especially in countries with a high level in the development of their water resources, this allows them to think that these needs are already resolved. This approach has two serious drawbacks: 1) in many countries water is needed to have a reasonable standard of living and to alleviate the effects of arid climates and droughts, and 2) the expected effects of climate change make it clear that we need to adapt the strategy in water management to a new scenarios, even in developed countries, as seen in the flooding of large areas of Europe and America in the years 2012 and 2013. Given these new situations ICOLD, through its Department of Communication and its Committee on Public Awareness and Education (COPAE), is developing a comprehensive information strategy to provide the public with objective data on the benefits of dams, reservoirs and regulating rivers. This strategy is being implemented in some countries by their National Committees. A good example of these new activities is the SPANCOLD mirror Committee of COPAE, named CIPE, which has a composition in which, besides engineers (some with extensive experience in communication), there are journalists, environmentalists, historians, geographers and other professionals with experience in communication. The communication strategy is divided into a set of strategies that should cover the following aspects: direct and clear information to the public, information through the media, dissemination of positive news about the dams and reservoirs, collection and dissemination of historical data, frequent relationship with the media (to be always available to answer their questions or doubts) and to support the media giving them accurate information to help them to present it in the right way (verbal notes, figures, graphics, photos, videos, documentaries, etc..) depending on the medium to be used (press, radio, TV, case reports, monographs, etc.).

Then, these strategies are described below.

LESSONS LEARNED IN COMMUNICATING TO SOCIETY 2.0

Some years ago, the communication to the public was given only by the traditional media mentioned above. Today´s society called 2.0 has new available communication tools (blogs, social networks, etc.) and we have to use them to communicate the benefits of dams and reservoirs. These new tools allow direct dialogue with the receptors of content, but this may be a double – edged sword. See Figure 1.

On the one hand provides the following benefits:

I - 190

Page 191: Study of Social and Economic Impacts of Construction of ...

⎯ Allows you to answer and debate with opponents of the dams, which in most cases (made based on personal experience) do not know really how dams work, how a flood can be managed or that dams have a monitoring system.

Figure 1. Society 2.0. Media available.

⎯ Allow virally spread content. A post on a topic that appeals to the public can become a viral phenomenon and reach millions of users.

⎯ SPANCOLD experience shows that when you explain face to face the operation of a dam and existing security tools to a person unaware of these issues, it is often possible to convince them. This is much more difficult but even sometimes people laden with prejudices against dams may accept some positive arguments.

The counterpart of these advantages can be summarized in the following:

I - 191

Page 192: Study of Social and Economic Impacts of Construction of ...

⎯ Opponents of the dams very commonly used a counterexample as strategy to discredit dams. If a thousand large dams that have worked perfectly ( regulating floods , increasing the security of supplies and irrigation , generating hydroelectric power, etc. . ) but if a dam has generated a problem, is sure they speak only about that dam, ignoring the great services that other dams have rendered to society.

⎯ Another problem in communicating the benefits of dams is the demagoguery that is determined by the use of malicious slogans, by the opponents of the dams, that easily captures the public opinion. Against that, the explanation of the benefits of dams is often filled with technical nuances that are hard to convert into easily assimilated slogans to make them have a high circulation.

⎯ Finally, dams have become more a part of the political confrontation, so that sometimes the politicians use their benefits or their problems as part of their political message in search of votes.

The lessons learned from these experiences, and we consider them very useful to communicate the benefits of dams, are:

⎯ It is necessary to value the importance of reservoirs for the society in the media. In Spain of the information given in the newspaper is the volume stored by the dams , which fortunately is an indicator of the concern that society has for existing water reserves . Apart from this interesting fact, that does not happen in almost any other country, other strategies to add value to the reservoirs can be the following two:

• Publishing Media press releases by the agencies responsible for the operation of a reservoir whenever the use of a reservoir reported a benefit to society.

• Publishing directly in social networks, like Twitter, using short and very clear (impacting) messages.

For instance, the following messages may be used by both media: traditional and social networks:

• Every time a reservoir (or set of reservoirs) regulates a flood. In this case there is the possibility of using slogans and catchy phrases for the public such as:

• "The reservoir received water entries higher than 2,000 m3/s, maintaining at all times an outlet lower than 200 m3/s, avoiding major damage downstream.

• "The large amount of incoming water in the reservoir was controlled at all times and the simultaneous use of several dams allowed to store all the water."

I - 192

Page 193: Study of Social and Economic Impacts of Construction of ...

• "Despite the severe weather drought, the water impounded will ensure irrigation season."

• "The abundant reserves in reservoir XXX this year are recharging the aquifer YYY" .

• The existence and location of reservoirs to hold top-level sporting or popular events.

• World championship triathlon in a reservoir allows press releases such as "The XXXX reservoir hosts world championship triathlon"; "over a thousand athletes participated in the event" "an economic impact of XXX million Euros are expected" Obviously if there was no dam could not do the championship, and this represents a generation of economic benefits to be transmitted to the community surrounding the reservoir.

• Even can be used for other popular events well known by the public. For example, in Asturias (Spain) the first weekend of August there is an international canoe race attracting a lot of tourist coming to " The Sella River race". When there are drought the upstream water reservoirs of the stretch where the event takes place increase the flow during the race and it is held successfully.

STRATEGIES TO MEDIA

As for the press and media, SPANCOLD has decided to launch, through its Spanish Committee on Public Awareness (named CIPE in Spanish) the following activities to convey to the public the benefits , the usefulness and necessity of the construction of dams and the maintenance and conservation of existing dams and reservoirs .

First, CIPE has conducted an approach to specialized journalist working in issues of public infrastructures and environment both major national agencies (EFE, Europa Press, Colpisa, Servimedia ) and in the major national newspapers (El País, El Mundo, ABC, La Razón).

CIPE is also approaching to specialized journalists working in financial newspapers (Expansión, Cinco Días, El Economista), or in large regional media (Vanguardia, El Periódico, Voz de Galicia, El Correo, ... ) , as well as radios, TVs and larger audience digital media.

Once identified these journalists CIPE has developed a list that, besides these journalists, it has been included the main columnists, radio commentators and TVs and other leading opinion makers.

Every 15 days, it is sent via email to this list of journalists a comprehensive summary of the most important news related to dams and a series of articles on topics related to dams.

I - 193

Page 194: Study of Social and Economic Impacts of Construction of ...

This email consists of headlines and summaries, on which interested journalists can click for the full news or article.

News relating to matters such as new construction projects of dams, maintenance and repair, technical improvements, operation of early warning systems (SAIH), contribution of dams and reservoirs in flood prevention, irrigation, power generation, recreation, fishing, water sports, etc.

This summary includes headlines and also a short summary of various articles written by members of CIPE about history and culture related to the dams (Roman dams in Spain, dams of particular cultural or technological value,...).

SPANCOLD is considering to held annually a breakfast briefing with the media in which an annual report on all activity related to dams in the relevant year will be presented . The contents of this report will also be used for publication in subsequent press releases that will be dosed properly for a period of one or two months to keep the attention of the media.

The report will be also distributed to SPANCOLD members and will serve as a working document but also giving prestige to the sector. The report will be presented to the media, and also to the sector at a side event.

Periodically, it will be organized “one to one” meetings to present the world of dams and reservoirs to the journalists who figure in the list of media. The objective is to become a reference on dams, prescriber and source of opinion and information for the media at the time of writing or making articles, reports or add additional information when related to the world of dam’s news.

SPANCOLD, through its CIPE experts will develop an agenda to be sent to the media with the names and contact addresses of the members of CIPE. These experts will be ranked according to their specialties, their academic records and outstanding professionals.

Through this agenda, it will be possible to strengthen the contact with the media and to facilitate the work of journalists. Thus, they will have within their reach in newsrooms a tool that allows them to find information sources for reports, news or monographs.

Another foreseen action that will perform to help spread among the general public the benefits and advantages of dams and reservoirs for the society is the call for a journalism awards for the best information on dams.

These annual awards, would have a cash prize not too high but that makes them interesting, where there is a winner and several accesits, and can be established for different categories, such as newspaper articles, radio or TV reports.

With these awards it would be possible to encourage journalists to publish articles and make programs and reports glossing benefits of dams and reservoirs, as well as increase the level of awareness of the work on dams by the media.

I - 194

Page 195: Study of Social and Economic Impacts of Construction of ...

Both the presentation of the awards as the ceremony will be also utilized to turn them into events that convene every journalist in the water and energy sector, and where they can meet with policymakers, with officials from the sector: administration, water supply, hydropower, engineering, construction, maintenance of dams and reservoir management, with the assistance of engineers and technicians in the field of dams.

Finally, SPANCOLD will contact Network Television to explore the possibility that these chains produce and broadcast documentaries on construction and operation of dams, flood management by watershed, functioning SAIH in periods of heavy rainfall , new techniques to repair dams, developed by Spanish companies, etc. CONCLUSSION Social networks ironically very used against technological advances and in particular against dams and reservoirs, are a powerful tool that our sector have to use to transmit directly to the public the benefits of dams. For this purpose, a short message spread virally is much more effective than any technical report full of good details that neither the public nor the media can understand. At the same time, it is our duty to help the media and to prepare good and easy to understand information to support them in the correct transmission of the benefits of dams and reservoirs to the public. ACKNOWLEDGEMENT The author wishes to express his gratitude to the members of CIPE (Spanish Committee on Public Awareness and Education) and also acknowledges the special contributions made by engineers E. Echeverría and P. Sánchez-Ortega, and journalist D. Jalón. REFERENCES ICOLD COPAE (Committee On Public Awareness and Education) Meetings Minutes, Kyoto 2012 and Seattle 2013.

I - 195

Page 196: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Multi-Criteria Studies for the Sustainable Management of Excavation Waste

from three major Pumped Storage Power Plant Projects in Spain.

V. Mendiola, M.E. Polanco & A. Zamora

Gas Natural Fenosa engineering [email protected]

ABSTRACT: In order to meet the challenge of integrating renewable energy into an efficient and flexible electricity market, Gas Natural Fenosa is developing three major Pumped Storage Power Plant (PSP´s) Projects in Galicia (North-western Spain): PSP Belesar III with 212 MW, PSP Salas-Conchas with 371 MW and PSP Edrada with 763 MW. For the design of the three aforementioned projects, Gas Natural Fenosa has been reviewing the state of the art of technology and has included sustainability and security criteria. The necessary construction work to build these new projects will involve the execution of approximately 22 km of tunnels as well as several shafts and caverns. These actions will generate a significant volume of excess excavation material of around 3,600,000 m3 for which a final deposit will need to be found if its re-use as a raw material is not possible. Both the high volume of material to be managed as well as the complex orography and social dispersion in the territory in addition to the significant natural, sociocultural and landscape wealth of the area around the three sites have made it necessary to conduct an extensive study of alternatives to define the most appropriate locations for the deposit of these materials and the final distribution as well as the rehabilitation projects associated with each one. Thus, the result aims to not only take into account traditional technical and economic criteria such as the proximity to the extraction points, morphology and capacity of the final deposits, etc. but also other factors such as landscape integration, biodiversity projection and the minimisation of disturbances to the resident population and heritage-related elements. Keywords: Hydroelectric, sustainability, excavation materials, mine waste management 1. INTRODUCTION Hydroelectric energy has had different roles throughout the history of Spanish electricity generation. In the first third of the 20th century, Spain was an eminently hydroelectric power producer. With the passing of time, hydroelectric energy made room for co-existence with different energy sources which were on the rise.

I - 196

Page 197: Study of Social and Economic Impacts of Construction of ...

In the 21st century, Spain faced a new challenge: the integration of different renewable energy sources which have significantly increased as far as their participation in the Generation System, especially wind energy which is non-manageable. This new context includes, among other elements:

a very diversified generation “mix” with non-manageable energies very demanding greenhouse gas reduction objectives and the highest environmental quality standards

.

Hydroelectric energy can introduce a stabilizing and organization function to the system with one of the already contrasted technology: “Pumped Storage Power Plants”. Thus a new generation of large power hydroelectric projects is developed which will be implemented in parallel to the new wind energy projects, with the technical and environmental optimisation of the already existing infrastructures as the main design criteria. In this context, Gas Natural Fenosa has three major pumped storage power plant projects underway in north-western Spain: Belesar III PSP with 210 MW (Fig.1), Salas-Conchas PSP with 380 MW (Fig.2) and Edrada PSP with 770 MW (Fig.3). The main characteristics of these power plants are shown in Table 1.

Table 1. Characteristics of the GNF PSPs in Spain Belesar III PSP Salas-Conchas PSP Edrada PSP Situation Miño River Salas and Limia rivers Mao and Sil

rivers Upper Reservoir Belesar Salas Edrada Lower Reservoir Peares Conchas San Esteban Flow rate (m3/s) Turbine mode 180 150 150 Pumping mode 167 124 115 Max turbine output power (MW) 210 380 770 Tunnel length (km) 4 10 8 Power plant type Cavern Cavern Cavern The underground work necessary to build these new projects will generate a significant volume of excess material for which a final deposit will be needed if it cannot be re-used as raw material. This article outlines all of the criteria that have been considered when selecting the different areas, as well as the preventive and corrective measures proposed, so the new generation of Gas Natural Fenosa hydroelectric projects in Spain provide an example of sustainable technological development.

I - 197

Page 198: Study of Social and Economic Impacts of Construction of ...

Figure 1. General isometric sketch and characteristics of the Belesar III PSP Project

Figure 2. General layout and characteristics of the Salas-Conchas PSP Project

Figure 3. General isometric sketch and characteristics of the Edrada PSP Project

I - 198

Page 199: Study of Social and Economic Impacts of Construction of ...

2. ISSUE The works necessary to build these new projects involve the execution of approximately 22 km of tunnels (between permanent hydraulic or access tunnels, and auxiliary tunnels for the construction phase), in addition to several shafts and caverns. These actions will generate a significant volume of excess excavation material of around 3,600,000 m3 (Table 2) for which a final deposit will be needed. The bulking factor considered to estimate the final volume needed was 1.6.

Table 2. Excavation material volume Belesar III PSP Salas-Conchas PSP Edrada PSP Situation Lugo Orense Orense Excavation material volume (m3)

608,000 1,880,000 1,100,000

The high standards required in order for the projects to be considered Environmentally Feasible, such as those outlined and the Gas Natural Fenosa corporate policy, have meant that environmental and socio-cultural criteria must be taken into consideration along with the traditional technical and economic criteria during the design and selection of alternatives phase for these deposit areas (Fig. 4).

Figure 4. Limiting environmental and socio-cultural factors for the selection of alternatives. 3. STUDIES DEVELOPED Both the high volume of material to be managed as well as the complex orography and social dispersion seen in the territory, added to the important natural, socio-cultural and landscape wealth of the environment at the three sites, have made it necessary to conduct a broad study of alternatives to select the most appropriate areas to deposit these materials,

I - 199

Page 200: Study of Social and Economic Impacts of Construction of ...

and decide upon the final conformation as well as the restoration projects associated to each one of them. An exhaustive analysis and selection work plan has been followed to conduct the specific studies of deposit area alternatives for the materials, including the following phases:

1. Phase I: Identification of potential material deposit areas.

Firstly, the volume of material to be deposited was analysed and a preliminary territory study was conducted to identify the population centres and the presence of natural spaces as environmental conditioning factors.

Later, the corresponding field work was done for in situ reconnaissance of the territory and to verify the environmental conditioning factors identified.

Based on the results obtained from these preliminary studies, a first proposal of areas that could potentially hold the materials from the excavation of these sites was made.

2. Phase II: Selection of material deposit areas.

The following limiting environmental and socio-cultural conditioning factors were considered in order to estimate the feasibility or exclusion of the different areas identified in the prior phase (Fig. 5):

The material deposit areas will be situated as close as possible to the worksite, so as to reduce the haulage distance from the extraction point to the deposit point as much as possible.

To the extent possible, the accesses to these surface areas will be already existing roads that are feasible for use by lorries, with the aperture of a new one only proposed if essential, and as long as the environmental feasibility is guaranteed.

Crossing villages while transferring the materials will be avoided to the extent possible, meaning the accesses to the surfaces selected from the excavation area are to be outside said villages.

No protected areas or unique natural assets of high ecological interest will be affected.

No historical or archaeological heritage elements will be affected.

The possible landscape impacts that may be considered severe or critical will lead to the rejection of the enclave. This impact rating is understood to be after any landscape integration measures are applied.

The morphological conformation of the deposit area will be respected, avoiding any surfaces with strong slopes which could compromise the stability or where the stabilisation measures would be complicated and very costly, as long as there are other more reasonable alternatives.

I - 200

Page 201: Study of Social and Economic Impacts of Construction of ...

Figure 5. Result of the study to choose the material deposit areas for the Salas-Conchas PSP which

considers environmental, social and archaeological aspects. The ideal situation would be to be able to find degraded areas (old quarries, mainly) near the worksite which could hold the excavation volume or a good portion of it, and later backfill it and complete the landscape integration. This would meet a dual objective, situating a significant volume of material in an area already affected by prior activity, and recovering said space in the environment. One example of this is the old Belesar dam quarry, which will be restored with materials from the Belesar III PSP underground works to recover the landscape by integrating it into the environment.

Below is an example of the results obtained to identify the material deposit areas for the Salas-Conchas PSP (Fig. 6).

Figure 6. Salas-Conchas PSP deposit area selection criteria.

FEASIBLE ALTERNATIVE

.

NON-FEASIBLE ALTERNATIVE

I - 201

Page 202: Study of Social and Economic Impacts of Construction of ...

3. Phase III: Landscape integration.

With an aim to reduce the impact on the landscape in the deposit areas selected, a series of measures is proposed for its integration and restoration.

These measures have been established individually for each specific surface, in accordance with the different environmental characteristics and their locations.

Firstly, the deposit surfaces have been sized considering the slope and land topography, on the one hand, and the material height limits on the other. Thus, the aim is to achieve topographic integration into the environment so the visibility is as low as possible.

Later, and in order to achieve total environmental integration, the accumulations formed will be re-planted with native and easily-rooted plant species.

Below is an example of the landscape integration in a deposit area (Fig. 7). Advanced infographic simulation technologies were used to optimise the results of this integration.

Figure 7. Landscape integration of the Edrada PSP deposit area. Current situation, situation without applying any type of measure, and future situation with landscape integration measures.

I - 202

Page 203: Study of Social and Economic Impacts of Construction of ...

4. RESULTS AND SPECIAL CASES The resources and knowledge invested have made it possible to find the best locations for the deposit areas as well as for the most suitable connecting roads from the worksite generation point, in the effort to seek the least possible environmental and social impact, and incorporating territorial sustainability. Below are some cases that need to be highlighted: A) Recovery of degraded areas There was a search for degraded sites such as old abandoned quarries (Fig. 8), some of which had even remained following the construction of the original dams and reservoirs to repair the topography with the excess excavation materials from new projects and thus correct the impacts of the construction of the infrastructures completed decades before.

Figure 8. Current and future situation of the old Belesar dam quarry which will be restored with

materials from the Belesar III PSP project work, thereby recovering the landscape. Nonetheless, some of these quarries over time have become ideal habitats for species of high ecological interest and are now classified as protected. These naturalised quarries have been excluded as deposit areas (Fig. 9).

Figure 9. Salas-Conchas PSP. A naturalised quarry protected as a priority habitat (“temporary Mediterranean lagoons”) near the Salas reservoir.

B) Environmental restrictions on deposit area delimitations. In the particular case of deposit areas A.13 and A.17 for the Salas-Conchas PSP, the size was restricted to prevent potential environmental effects. To minimise the impact on the Corga de Dormes creek “reception basin” in the case of area A.13 and the future use of the area partially re-populated with pine trees by the government in the case of A.17. (Fig. 10).

I - 203

Page 204: Study of Social and Economic Impacts of Construction of ...

Figure 10. Delimited material deposit areas. C) Special measures for hauling the excess excavation material. In the specific case of the Edrada PSP project, the main material outlet will be situated next to the “San Esteban" lower reservoir which is hidden in a deep valley near protected areas, with important natural and landscape value. The difference in level that must be overcome between the bottom of the valley and the upper plateau would require opening up new roads on the slope and intense lorry traffic, which would cause significant effects on the well-conserved natural and social environment. To prevent this situation, a system has been planned to evacuate more than half of the excavation materials by means of conveyor belts that will run through the open corridor of an existing penstock on the slope (Fig. 11).

Figure 11. System to bring up excavation materials from the Edrada PSP project through the existing penstock corridor on the slope (left image shows the current state and the right image shows the state

expected with a conveyor belt). D) The opening of new roads to minimise the environmental and socio-cultural impacts of

hauling the material. The opening of new access proposed for the Salas-Conchas PSP project was designed to avoid affecting the nearby population centres, the local cultural heritage and high quality tree masses (Fig. 12), and thus seeking the lowest possible environmental and social impact.

I - 204

Page 205: Study of Social and Economic Impacts of Construction of ...

Figure 12. New layouts for the Salas-Conchas PSP accesses.

5. CONCLUSIONS AND RECOMMENDATIONS FOR SIMILAR CASES Considering prior experience with power plants of this type, companies must help improve and optimise the technology and project designs by introducing environmental, social and cultural aspects in the early phases of the work. The significant volume of excess excavation material generated with this kind of work, along with the high environmental standards required by all parties involved in this type of project, means more and more detailed studies and analyses are required in order to determine the final destination for these materials from the design phase. Conducting multi-criteria studies to select material deposit alternatives, as well as the participation of a multi-disciplinary environmental and socio-cultural team are key during the design phases to reaching the best solution possible in all areas, and preventing problems in the procedural phase (denial of environmental feasibility or longer processing periods) as well as in the construction phase (work stopped because impacts were not adequately forecasted). In order to do these studies, environmental and social surveys are required to provide data from representative periods so the infrastructure can be well fitted during the design phase. The selection criteria used in these studies, as well as the preventive and corrective proposed measures, will along with the rest of the aspects considered in the design phase, contribute to make the new generation of hydroelectric projects in Spain an example of sustainable development. REFERENCES

GNF Engineering (2010): Estudio de Impacto Ambiental de Belesar III Peares III, Spain.

GNF Engineering (2011): Estudio de Impacto Ambiental de CHR Salas - Conchas”, Spain.

GNF Engineering (2012): Estudio de Impacto Ambiental de CHR Edrada, Spain.

I - 205

Page 206: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST – 6TH , 2014

Blasting Vibration Control in Residential Area near Cheragh - Vays Dam

Amir Hafezquran Mahab-Ghodss Consulting Engineers, Cheragh-Vays dam, Saqqez, Kurdistan, Iran

[email protected]

ABSTRACT Blasting operation for rock excavation is a most common activity in dam construction projects. The reduction of ground and air vibration to the defined level and control of fly-rock phenomena are important environmental aspects of rock blasting near residential area. Geological conditions, distance of existing structures from the blast point, structures resistance degree and charge weight per delay are the most important parameters that should be considered in blasting design to ground vibration control. The design of blasting parameters for rock quarry of Cheragh-Vays dam is studied in this paper from environmental point of view. Two villages with weak clay houses, dam structures and an earth materials slope with critical potential to sliding are the main structures that should be considered in defining of ground and air vibration levels. Keywords: blasting, ground vibration, environmental aspects, dam. 1. INTRODUCTION Blasting operation is a most common and economic method for rock excavation during dam, tunnel, highway, mining and foundation construction activities. Detonation of confined charges can produce high under-pressure gas and expand the blast-hole up to 10 times from the original volume in a very short time (Matti 1999). This process cause crack propagation in surrounding rock and finally yield to rock breaking. Based on early studies only 20% to 30% of explosive energy are used for rock fragmentation (Singh et al. 1993). The rest energy generates undesirable environmental effects such as ground vibration, fly-rock, air blast and noise (Duncan et al. 2004). Blasting program near residential area should be accurately planned to protect peoples and structures from undesirable and deleterious effect of blasting environmental damages (Mostafa 2000 and Birol et al. 2010). The parameters which affect the blast induced vibration are classified in controllable and uncontrollable categories (Lopez et al. 1995). The controllable are parameters mainly related to blasting design and explosive characteristic

I - 206

Page 207: Study of Social and Economic Impacts of Construction of ...

and uncontrollable parameters mainly are geological and topographical conditions. (Mostafa 2000 and Birol et al. 2010) 2. A REVIEW TO THE GROUND VIBRATION CRITERIA Ground vibration is a major environmental problem in blasting operation. Although ground vibration can be described in terms of displacement, velocity and acceleration of the ground particles, but particle velocity is the best predictor for measurement of structural damage from blasting vibrations (Siskind et al. 1976, ISRM 1992, Dowding 1996 and Hustrulid 1999). The particle velocity is a measure of the ground particle velocity during passage of the shockwave. The main parameters that affect particle velocity include: Explosive charge weight per delay, Distance from blast point and frequency of vibration (Hustrulid 1999). Several researchers have studied ground vibrations from blasting and have developed empirical formulas for ground vibration estimation. The general form of these formulas can be described as follows:

푉 = 퐾푄 푅 (1) Where: Vp (mm/s) is the peak particle velocity; Q (kg) is the maximum charge weight per delay; R (m) is the distance from blast point; K, m and n are empirical site constants. For determining the constants for a given site, number of blast tests are performed and the peak particle velocities of the ground are recorded. Then, the peak particle velocities (PPV) are plotted on log-log scaled axes as a function of scaled distance (R/Qs) based on 95% confidence level, where s is a root scaling. The square-root, cubic-root and two-thirds scaling equations which are the widely used formulas for determining of the particle velocity are summarized in table 1(Liang 2011).

Table 1. The Widely Predictor Equation for Particle Velocity Square-root scaling formula proposed by USBM Vp = K1(Q1/2/R)α1

Cubic-root scaling formula Vp = K2(Q1/3/R)α2 Two-thirds scaling formula proposed by Indian Standard Vp = K3(Q2/3/R)α3

Where K and α are the site constants. Based on Liang et al (2011), both cubic-root and square-root scaling formulas give good fitting results, whereas two-thirds scaling formula produce poor fitting result. They recommended square-root scaling formula for scaled distance less than 0.1 and cubic-root scaling formula for otherwise. The Office of Surface Mining (1983) has established the following peak particle velocities (PPV) for safe blasting near residential area as a function of distance from blasting site. This reference also has proposed the scaled distance factor (SD) as a safe blasting criterion in absence of seismic monitoring based on square-root scaling function (see table 2). The U.S. Bureau of Mines (1971) defines three types of structural damages due to blast induced vibrations as follow: Cosmetic or Threshold damage, Minor damage and Major damage. The USBM (1971) also has established damage criterion for residential dwellings based on peak particle velocity (see table 3).

I - 207

Page 208: Study of Social and Economic Impacts of Construction of ...

Table 2. The Recommended SD and PPV as a Function of Distance from Blasting (OSM, 1983)

Distance from Blast Point (m) PPV (mm/s) SD (m/kg1/2) 0-90 41 18.1

91-150 34 20.4 151-300 30 22.1 301-900 25 24.9 901-1500 23 26.9

>1500 19 30.5

Table 3. The Damage Criterion based on PPV (after USBM, 1971 PPV(mm/s) Damage

<51 No damage 51 - 102 Plaster cracking 102 - 178 Minor damage

>178 Major damage Despite that the allowable level of ground vibration criteria has been proposed by several organizations, this was not enough to protect structures from blast induced vibration damages, because the vibration frequency and type of structure has not been seen in this criteria (Abdel-Rasoul 2000). Mostafa (2000) has summarized the most important peak particle velocities limit criteria based on vibration frequency and type of structure (figure 2 and table 4).

Figure 2. The OSM and USBM frequency-depended criteria for safe blasting

Based on table 4, different peak particle velocities levels for safe blasting near different types of structures are suggested by different standards. Svinkin (2007) has compared the OSM criteria with the German standard for example. He concluded that the German standard criteria for residences are very conservative and its specified limit levels are not damage-based. The German standard criterion intends to minimize human perceptions and complaints; therefore the German standard and the OSM criteria have the different applications. According to Svinkin (2007), measurement of ground vibrations is not an appropriate approach for protecting of structures form blasting damages, because ground vibration criteria does not take into account soil-structure interaction and natural frequencies

19 mm/s

50 mm/s

2.5

25

250

0.1

1

10

1 10 100

PPV

(mm

/s)

PPV(

in/s

)

Blast Vibration Frequency (Hz)

Maximum Allowable Parrticle Velocity (OSM 1983)

13 mm/sPlaster

Drywall19 mm/s

50 mm/s

2.5

25

250

0.1

1

10

1 10 100

PPV

(mm

/s)

PPV

(in/s

)

Blast Vibration Frequency (Hz)

Maximum Allowable Particle Velocity (USBM, 1980)

I - 208

Page 209: Study of Social and Economic Impacts of Construction of ...

of structures. He proposed the direct measurement of structural vibrations as a good criterion for safe blasting near different types of structures and defines the frequency-independent safe limit of 51 mm/s for multi-story residential, commercial and industrial buildings.

Table 4. The Most Important PPV Limit Criteria based on Structure Type and Frequency Office of Surface Mining Standard (OSM, 1982)

Type of structures PPV (mm/s) in frequency range <10 Hz 10 – 40 Hz >40 Hz

Sensitive or protected structures 13 13 13 Older homes more than 20 years old 19 25 51 Modern homes less than 20 years old 25 38 51 Structures with safety consideration 51 51 51 Structures resistant to dynamic loads PPV determined by engineer

British Standard Type of building PPV (mm/s) in frequency range

4 to 15 Hz 15 Hz and above Reinforced or framed structures. 50 50

Unreinforced or light framed structures. 15 to 20 20 to 50 Indian Standard

Owner Type of structures PPV (mm/s) in frequency range <8 Hz 8 – 25 Hz >25 Hz

Belonging to the owner

Domestic Houses 10 15 25 Industrial Building 15 25 50 Sensitive Structure 2 5 10

Not belonging to the owner

Domestic Houses 10 15 25 Industrial Building 15 25 50

German Standard French Standard Structure

Type PPV (mm/s) in frequency

range Structure

Type PPV (mm/s) in frequency

range <10 Hz

10-50 Hz

50-100 Hz

<10 Hz

10-50 Hz

50-100 Hz

Commercial 20 20-40 40-50 Resistant 8 12 15 Residential 5 5-15 15-20 Sensitive 6 9 12 Sensitive 3 3-8 8-10 Very Sensitive 4 6 9

Critical slopes should be protected from high vibration velocity, because these slopes may be unstable under high dynamic loads. Unfortunately, the few existing criteria of blast induced vibrations for soil and rock slopes are still questionable, and further investigations need to solve this problem (Wong 2000, Svinkin 2007 and Choi et al, 2012). Svinkin (2007) has collected numbers of case histories which studying the effect of blast induced vibration on soil slopes. Qasimi (2005) and Charlie (1992) have reported blast induced vibration limits of 130 and 160 mm/s for occurrence of zero effective stress condition in loose and dense saturated sand, respectively. Choi et al (2012) have mentioned the problem of establishing safe ground vibration limits for cut slopes. They reported the Russian criterion as an only clear blast vibration criterion for pit slopes. The peak particle velocity of 60 mm/s and 120 mm/s for repetitive blasting conditions has proposed by Russian criteria for saturated sandy slopes and soil slopes, respectively. Blasting operation near uncured concrete is a most common activity in almost all of dam construction projects. Under these circumstances, explosive charge weights per delay should

I - 209

Page 210: Study of Social and Economic Impacts of Construction of ...

be designed based on the age of the concrete, the distance of the concrete from the blast, and the type of structure in order to protect uncured concrete from blast induced vibration damages (Duncan et al. 2004). Table 5 show the peak particle velocity limits based on the concrete age. In this table, df is a frequency attenuation factor as a function of distance from blasting, and equal to 1 for distance below 15 meters and decrease to 0.6 for distances over 80 meters (Oriard et al. 1980). Table 5. The Peak Particle Velocity for Blasting near Uncured Concrete (Oriard et al, 1980)

Time from batching (hours)

PPV for non-structural fill, mass concrete (mm/s)

PPV for structural concrete walls and slabs (mm/s).

0-4 100df 50df 4-24 25df 6df

24-72 40df 25df 72-168 75df 50df

168-240 200df 125df >240 375df 250df

3. CHERGH-VAYS DAM SPECIFICATIONS The Cheragh-vays dam is under construction in the northwestern Iran at Kurdistan province (see figure 2). The dam is clay core rock-fill dam type with a height of 67 meters, 980000 cubic meters embankment volume and 270 meters crest length. The dam is designed for supplying drinking water of Saqqez city and irrigation purposes.

Figure 2. The general view of under-construction Cheragh-vays dam 4. BLASTING PROGRAM OF ER QUARRY The rock-fill materials of Cheragh-Vays dam are supplied from the ER quarry located 500 meters upstream the dam axes. The quarry is located in the Sanandaj - Sirjan zone and consists of strong grano-diorite to diorite igneous rocks with seams of schist and hydrothermal quartz. The blasting program for rock-fill material excavation from ER quarry planned based on the probability of vibration damage to near structures. The project aims to limit blasting to one blast per day, carried out during afternoon hours, in order to minimize

I - 210

Page 211: Study of Social and Economic Impacts of Construction of ...

impacts on residents. ANFO, gelatin dynamite and electric delay detonator were used as explosives in ER quarry blasting. The main structures that should be considered in defining of vibration level are presented in table 4 (see also figure 3).

Table 4. The Main Structures near ER Quarry Structure type Minimum distance from blasting site (m)

Cheragh-vayse village 350 Mazoj-dareh village 1200

Dam body 300 to 500 landslide 150

structural concrete of bottom outlet 250 The ER quarry is divided in three zone (1 to 3) based on structure resistance and distance from near structures. The Cheragh-vays village, the bottom outlet structural concrete and the landslide area are the important structures witch affect the maximum charge weights per delay based on structure resistance and/or distance from blasting point (figure 3)

Figure 3. The plan view of structures near ER quarry Before to define a safe blasting program for ER quarry, the safe vibration limit of individual structures should be determined based on the Iranian Standards (Code No. 410). This standard propose the square-root scaling distance method for the peak particle velocity limits. The maximum charge weights per delay at ER quarry is determined based on the scaled distance method (SD) because of absence of seismic monitoring data. 4.1. Residential Area Two villages with old weak clay houses are located in south and east of the ER quarry at the minimum distance of 400 and 1200 meters, respectively. Before starting the blasting, houses

I - 211

Page 212: Study of Social and Economic Impacts of Construction of ...

of the villages have inspected and several old cracks have found in the walls of the houses (figure 4). Svinkin (2007) has points out that structures with existing damage may be affected by blast in a greater degree than sound and it is necessary to inspect such structures before and after blasting. The safe vibration limit based on the Iranian standard is 50 mm/s for new drywall houses. This standard also has proposed 25 and 12.5 mm/s as a safe vibration limits for old wet hoses under single and repetitive blasting, respectively.

Figure 4. The picture of weak clay house at Cheragh-vays village Figure 5 shows the peak particle velocity limits against scaled distance for Cheragh-vays village, landslide area and structural concrete of bottom outlet structure. The peak particle velocity of 15 mm/s is selected for safe vibration limit in weak clay houses near ER quarry, based on Iranian standard. The scaled distance of 36 m/kg0.5 was selected to protect village’s houses from blast vibration damages. This value is selected based on the OSM (1982) criterion for square-root scaling in absence of seismic monitoring, as proposed by Iranian standard. Figure 6 shows the maximum allowable charge weights per delay as a function of distance from Cheragh-vays village, landslide area and bottom outlet structural concrete, based on peak particle velocity proposed in figure 5. Comparing Figures 5 and 6 show that the maximum charge weights per delay for zones 1 to 3 of ER quarry were 120, 190 and 280 kilograms respectively, in order to protect villages’ houses from blast vibration damages. In zones 1, the vibration limit of Cheragh-vays village houses is the most effective parameter in determining the allowable charge weights per delay due to their distance from blasting site. In zone 2, the maximum charge weight per delay was determined based on the vibration limits of bottom outlet structure or Cheragh-vays village, depending on the age of concrete in bottom outlet structure. In zone 3, the maximum allowable charge weights per delay are determined based on uncured concrete (age 1 to 7 days) of bottom outlet, landslide in rainy condition and Cheragh-vays village houses, respectively. In absence of uncured concrete in bottom outlet structure, the allowable charge weight per delay in zone 3 was determined based on landslide area vibration limit in rainy condition and Cheragh-vays houses vibration limit in dry conditions.

Old Crack

I - 212

Page 213: Study of Social and Economic Impacts of Construction of ...

Figure 5. Peak particle velocity against scaled distance for structures near ER quarry

Figure 6. The maximum charge weight per delay as a function of distance from structures 4.2. Landslide Area During the excavation of diversion tunnel portal, the rock wedge failure was take place with a volume of 2000 cubic meters, and therewith about 140000 m3 earth material with an average depth of 12 m slide for about 1 to 2 meters. Figure 6 shows the longitudinal section of the landslide area. This landslide is stabilized temporarily, by removal of about 40000 m3 of soil materials, for dam construction period. With refer to figure 4, the distance of ER quarry from landslide area is between 150 to 450 meters. The peak particle velocity of 70 and 120 mm/s were selected for safe ground vibration levels for landslide area at rainy and dry conditions, respectively. Figure 5 shows the maximum charge weights per delay for landslide area at saturated condition based on safe vibration limit of 70 mm/s and square-root scaling method. Comparing Figures 3 and 6 show that only in rainy condition and absence of uncured concrete in bottom outlet structure, the landslide

15

36

70

12.5

25

5025.310

100

10

PPV

(mm

/s)

SD (m/kg0.5)

village houses and bottom outlet concrete (age 1 to 3 days)

landslide (rainy conditon)

bottom outlet concrete (age 3 to 7 days)

Zone 3

250350

Zone 2Zone 1

150250350450550 450

250350450550

0

100

200

300

400

500

600

350 450 550 650

Max

imum

char

ge p

er d

elay

(kg)

Distance from structuers (m)

Cheragh-vays villagelandslide (rainy condition)bottom outlet concrete (age 1 to 3 days)bottom outlet concrete (age 3 to 7 days)

I - 213

Page 214: Study of Social and Economic Impacts of Construction of ...

may be the most effective structure for determining the maximum charge weight per delay in zone 3.

Figure 6. The longitudinal section of the landslide area 4.3. Bottom outlet structure Bottom outlet structure consist of 900 cubic meters structural concrete located at distance of 250 to 300 meters from ER quarry. Blasting in ER quarry is not allowed if the age of structural concrete is below 24 hours. The particle velocity and the allowable charge weights per delay for structural concrete of bottom outlet structure, based on the age of concrete and distance from blasting site, is shown in figure 5 and 6, respectively. Due to the low volume of concrete in bottom outlet structure, number of blasting limitations due to this structure was not considerable compared to other structures. 5. CONCLUSIONS The blasting program for ER quarry is planned based on near structures resistance to ground vibration. The vibration limit for clay houses of Cheragh-vays village was the effective parameter in determining the allowable charge weights per delay. The peak particle velocity of 15 mm/s and scaled distance of 36 m/kg0.5 were selected based on the OSM (1982) criterion for square-root scaling in absence of seismic monitoring, as proposed by Iranian Standard. This approach was very conservative and increased the rock excavation costs for about 30 percent. Although, the uncured concrete of bottom outlet structure is more sensitive to blast vibration than other structures, but because of the low concrete volume of bottom outlet structure, number of blasting limitations due to this structure was not considerable compared to others.

6. REFERENCES Al-Qassimi, M.E., Charlie, W.A., and Woeller, D. (2005): Blast Induced Ground Motion

and Pore Pressure Measurements. Geotechnical Testing Journal, ASTM, V. 28, No. 1: pp. 9-21.

I - 214

Page 215: Study of Social and Economic Impacts of Construction of ...

Abdel-Rasoul, E. (2000): Measurement and Analysis of the Effect of Ground Vibrations Induced by Blasting at the Limestone Quarries of the Egyptian Cement Company, Proceedings of ICEHM 2000, pp. 54- 71, Cairo University, Egypt.

Birol, E. and Ercan, A. (2010): Evaluation of Parameters affected on the Blast Induced Ground Vibration (BIGV) by using Relation Diagram Method (RDM), Acta Montanistica Slovaca, pp. 261-268, www.actamont.tuke.sk.

Choi, B.H., Ryu, C.H., Deb, D., Jung, Y.B. and Jeong, J.H. (2012): Case Study of Establishing a safe Blasting Criterion for the Pit Slopes of an Open-Pit Coal Mine, International Journal of Rock Mechanics and Mining Sciences, Vol. 53, pp. 1-10, Elsevier.

Charlie, W.A., Jacobs, P.J. and Doehring, D.O. 1992. Blast-Induced Liquefaction of an Alluvial Sand Deposit. Geotechnical Testing journal, ASTM, V.15, No.1: 14-23.

Dowding, C.H. (1996): Construction Vibrations, Prentice –Hall Inc., New Jersey. Duncan C. W. and Christopher W. M. (2004): Rock Slope Engineering, based on the third

edition by Hock, E. and Bray, J., Spon Press, London. Hustrulid, W. (1999): Blasting Principles for Open Pit Mining, A.A.Balkema, Rotterdam. International Society for Rock Mechanics, (1992): Suggested Method for Blast Vibration

Monitoring, International Journal of Rock Mechanics and Mining Science, Vol. 29, pp. 143-156, Pergamon Press Ltd, Great Britain.

Kumar, K. B. (2010): Blast Vibration Studies in Surface Mines, bachelor thesis, Rourkela National Institute of Technology, India.

Liang, Q., An, Y., Zhao, L., Li, D. and Yan, L. (2011): Comparative Study on Calculation Methods of Blasting Vibration Velocity, Journal of Rock Mechanics and Rock Engineering, Vol. 44, pp. 93-101, Springer.

Lopez, C.E., Lopez, J.E. and Javier, F.A. (1995): Drilling and Blasting of Rocks, A.A. Balkema, Rotterdam.

Matti H. editor in chief (1999): Rock Excavation Handbook, Sandvik -Tamrock Corp., www.metal.ntua.gr

Oriard, L.L. and Coulson, J.H. (1980): Blast Vibration Criteria for Mass Concrete. Minimizing Detrimental Construction Vibrations. ASCE Preprint 80-175, ASCE, pp. 103–23. New York.

Office of Surface Mining Reclamation and Enforcement (OSM, 1982): Use of Explosives and Training, Examination, and Certification of blasters, Proposed Regulations, US Dept. of the Interior, Surface Mining Law Regulations, Federal Register, Vol.47, No. 57 http://arblast.osmre.gov/

Svinkin, M.R. (2007): Assessment of Safe Ground and Structure Vibrations from Blasting, Vienna Conference Proceedings, European Federation of Explosives Engineers.

Singh, B., Pal RoY, P., Singh, R.B., Bagchi, A., Singh, M.M. and Nabiullah, M. (1993): Blasting in Ground Excavation and Mines, A.A.Balkema, Rotterdam.

The Iranian Ministry of Industries and Mines. (2008): Technical Regulations for Explosives and Rock Blasting in Mines (Code No. 410), http://www.mim.gov.ir.

Tantawy Mohamed, M. (2010): Vibration Control, Chapter 16, www. intechopen.com Wong, H. and Pang, P. (2000): Assessment of Stability of Slopes subjected to Blasting

Vibrations, the Government of the Special Administrative Region, Hong Kong.

I - 215

Page 216: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

A survey about passive defense, and lake dam's requirements to water fronts

hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj and how to construct a floating waterfronts in accordance with changes in

2(14pt)

Water levels in dams

Meysam Rezaei Ahvanouei MA student Azad University of Semnan-Iran, Director Manager of Sad Rah Abnie co.

[email protected]

Hamid Ehsani head of department, Semnan regional water authority

Mahyar Rezaei Ahvanouei MA student, Azad University of Damghan, board of directors of Sad Rah Abnie co

ABSTRACT

Design, accomplishment, and construction of floating water fronts in order to innovation,

localization, technical knowledge transition, and alignments of those aims with current needs in

dams, make movements and national efforts in comparison with Islamic Republic of Iran principles

and macroeconomic policies, and at last, the unique feature of this kind of structures like flexibility,

safety, strength, and longevity, reducing the costs and preventing exit exchange, fast constructions,

… are just parts of good results of powerful and active personnel of Sad Rah Abnie co. in this

country. Profile design, construction and accomplishment, and benefits of using this kind of water

front structures, that has been using for the first time in dam waters, are concluded in this article.

Keywords: water front, float, dam, passive defense

INTRODUCTION

Passive Defense and depending on it, implementation of hydraulic structures in order to

achieve the objectives of passive defense has been always of special importance, but

because of its difficulty to implement Hydraulic Structures, less contractors are willing to

implement these projects. Engineering company of Sad,Rah,Abnie (SRA) arrived on this

realm by timely understanding of the role and importance of wharf on dam to connect land,

water and lake patrolling and after a short time due to the presence in the manufacturing

processes of several dams of the country, including dam of Damghan, Kaboudval, Qara

Aghach, Kine vars, Changureh etc. and also activities in the form of contractors of

operation, maintenance and repair in Reservoir Dam of Damghan and having experienced

workers, necessary expertise and identifying the problems in country dams achieved the

technical knowledge of the work and is capable to design, implement and support the

project of pontoon piers in all hydroelectric installations of Iran.

1 - Introduction to Passive Defense

I - 216

Page 217: Study of Social and Economic Impacts of Construction of ...

It is referred to a set of actions that doesn’t require using weapons and one can avoid

financial losses to critical military and civilian equipment and installations and also human

casualties and minimize the damages and casualties by implementing it. Expediency

Discernment Council defines passive defense as:

A package of non-military measures that increases deterrence, reduces vulnerability,

sustains necessary activities, promotes national stability and facilitates crisis management

in the face of enemy threats and military actions is called passive defense.

2. Introduction of wharf

Warf is a structure along the beach which forms and constitutes the boundary between land

and sea or lake and it is almost the most important components of a port. (Figure 1

Figure1. Wharf executed by the company Sad,Rah,Abnie (SRA) on Damghan lake dam.

3 - Types wharf in terms of use

Based on type of use and regional conditions and its material, Wharf has different types:

Wharfs are divided into following types based on their application:

1. Commercial wharf: as its name implies, it is used for the transport of goods from land

to sea or vice versa, and it plays an important role for exporting as a key and effective

element in country economy.

2. Military wharf: it is used to transport military equipment and instruments.

3. Fishing wharf: it is used for berthing boats of fishermen.

4. Petroleum wharf: it is used for berthing and anchorage of oil tugs and of particular

types to transport petroleum materials.

5. Resort wharf: as its name suggests, it is used for public use and tourism and also as

stations for sport and sailing and also for berthing paddle, bicycle, wind and other boats.

4. Types of wharf in terms of structural specifications.

In designing the wharf installation, selecting the type and also wharf structure information

generally is of great importance. In other words, different factors such as geotechnical

I - 217

Page 218: Study of Social and Economic Impacts of Construction of ...

characteristics, financial credit, economic factors, executive facilities etc. should be

considered in designing.

Most wharfs are composed of different types as follows:

1 – Wharf with foundation consisted of steel piles

2 - Wharf with foundation consisted of reformer concrete piles with cylindrical steel

surfaces

3 - Wharf with foundation consisted of prefabricated concrete pile

4 – Polymeric (synthetic) wharfs

1-4 Steel Wharfs

This type of wharf is one of the most commonly used types of docks. Since many of

constructed wharf in the world have been constructed by such a structure, contractors have

sufficient experience in manufacturing this kind of docks and in addition to a problem

which exists in the construction such as need for infrastructure and piling, steel structures

are highly susceptible to mechanical and chemical corrosion in aqueous environments and

even using different methods of cathodic, epoxy and resin protection and due to the many

problems in maintenance, durability of such foundations are not satisfactory and it is

relatively short.

2-4 Concrete wharf with steel surface This type of structure has better tolerance to corrosion than the two previously mentioned,

but the same infrastructure problems and implementation difficulties of wharf still remain.

3-4 Prefabricated concrete wharf

This type of wharf had been widely used in the past, but its use has declined gradually.

This structure include problems such as transportation and displacement after raising and

also the difficulty or impossibility of increasing the length of piles during construction, as a

result of arisen changes in consisting materials of land, these piles are susceptible to

mechanical and chemical corrosion especially in areas where tidal waves hit the

foundations.

4-4 Polymeric Wharf

This type of wharf is of the new generation of wharfs and is constructed by using special

polymeric materials and in floating form and in terms of application, it is divided into a

variety of recreational, passenger, fishing, rescue, etc. floating wharf.

As you know building a wharf by destroying terrains needs drying water areas and piling

for making infrastructure, causing environmental adverse and especially that it is not

possible to pile behind dams and creating vibrations due to special conditions.

This made Design engineering Company of Dam, Road and Buildings (Sara) to study types

of wharf in order to preserve natural resources and optimal use of environment without

destroying it and avoid making any damage and artificial side effects and especially type of

use in dams and among which tries to develop and implement polymeric pontoon piers.

I - 218

Page 219: Study of Social and Economic Impacts of Construction of ...

The company of Dam, Roads, and Buildings is proud to take a major step in the innovation

process in our beloved homeland by design and implementation of this kind of wharf after

dehydrating on the surface of slope upstream dam (rip rap) for the first time in Iran dams.

5 – Polymeric floating wharf

In general, floating docks in the present century, for reasons previously mentioned, are

considered as the main rival of fixed docks and among which polymer pontoon piers are

better accepted in polypropylene wharf environment, etc. to (HDPE). In general these

kinds of docks are usually produced using raw material of HDPE as cube -shaped tanks,

nearly all four floating vessels form together a cube with dimensions of 100 cm. Each tank

has four earrings to connect to other tanks. This connection is done with the help of

another piece called pins. In order to increase resistance to hit and connecting boats to the

wharfs, the other pieces have been used called bumpers and hooks.

6 - The main reasons to select polymer pontoon piers in dams

1 - To avoid artificial effects

2 - No need for piling and drying Lake Floor

3 – No need to special and significant preparation on the ramp and the dam body

4 – Resistance of wharf parts against climate changes especially damaging ultraviolet

radiation (UV) with respect to additives used in polymer structure

5 – Possibility to increase dimension and area of wharf in future development plans

6 - Resistant to various chemical and mechanical corrosions

7 – Wharf pieces can be used in special seasons or can be transported somewhere else

due to its easy installation and collection

8 – Its easy anchorage

9 - The possibility of replacing the defective parts with ease and no disruption of wharf

servicing

7 – Design of pontoon piers at Dam

Factors influencing the design can be defined as follows:

1 - The dead loads: consist of weight of the wharf main body and all its associated

accessories

2 - Live loads: consist of weight of the equipment on it and weight of moving persons

3 - Environmental loads: that can influence wharf in different ways. Most notably are

wind, water flow, and waves.

4 - Coastal slope of implementation place

5 - Suitable anchorage of wharf

6 - Considering the safety

The design of this structure was done based static load carrying capacity of at least 320 kg

per square meter of pontoon piers. In addition due to the lack of proper infrastructure in rip

rap slope and on the rocks, geotextile fiber technology also called the land cloth has been

used with polymer thread and coating, resistant to sunlight (Anti UV) and rot and capsules

filled with sand. (Figure 2)

I - 219

Page 220: Study of Social and Economic Impacts of Construction of ...

Figure2. Design of pontoon piers at Dam

This material is made of polyester and polypropylene filaments and due to its

characteristics such as very fast implementation, comfortable, low weight, high strength,

low cost, long lasting, non- environmental degradation, and uniformity in implementation

and due to physical, mechanical, hydraulic conditions and needed durability to protect the

body of wharf against the massive stone, geotextiles have been considered as the most

appropriate option in design for the company of Sad, Rah, Abnie (SRA). Also, considering

the tensile force applied to the anchorage, a concrete structure was used in the vicinity of

the dam crest and due to the special design system; anchorage has been executed securely

from above. In wharf slope, using special polymer stairs and aligner plate and polymeric

railings designed for this task has established a safe approach to traffic.

CONCLUSIONS However, any maneuver on lakes of dams by staff of exploitation including passive

defense, collecting illegal fishing gears, patrolling to investigate environmental factors on

the lake, the possibility of recreational trip, tourists visit the lake behind dams . . . the

existence of wharf on dam and water installations seems necessary and the company of

Sad, Rah, Abnie (SRA) knows it as his function to be pioneer in country in the design,

manufacture and installation of wharf on dam according to different development projects

and maintenance, repair, installation of instrumentation, exploitation and data processing

of instrumentation in dams which this was accomplished in Shahid Shahcheraghi Reservoir

Dam of city of Damghan-Iran for the first time.

ACKNOWLEDGEMENT

I - 220

Page 221: Study of Social and Economic Impacts of Construction of ...

At the end, we would like to appreciate the unsparing guidance and cooperation of

respected employer and supervisor of the time of implementing project (Regional Water

Authority Company, Semnan) and his bravely welcomes of the implementation of above

schemes that was conducted for the first time in the country dams.

I - 221

Page 222: Study of Social and Economic Impacts of Construction of ...

THE KARALLOE MULTIPURPOSE DAMFOR ENVIRONMENTAL AND RAW WATER DEVELOPMENT

Agus Setiawan1, Hariyono Utomo1, Eka Rahendra1, Subandi1,Andika Kuswidyawan2 & Arif Paputungan3

1)The Pompengan Jeneberang Large River Basin Organization, Makassar, Indonesia2)Water Resources Engineering Student, Muhammadiyah University, Makassar, Indonesia

3)Water Resources Consultant of Pompengan Large River Basin Organization , Makassar, [email protected]

ABSTRACTThe serious problem of Jeneponto regency is a raw water crisis and the environmental decreasingduring dry season. No secure water to the existing Kelara irrigation, rice cropping is not sufficient.Existing irrigation system uses the open channels with a lot of risk: evaporation, infiltration andillegal pumping. The Local Government Raw Water Treatment Plant (RWTP) cannot supply the clearwater to the costumers as a target. In rainy season, the regulate flooding inundates public facilities inthe rural and urban area for a long time. To solve the problem, it will be applied 3 terms; (1) in theshort term, in the middle of 2014, the Karalloe multipurpose dam will be constructed a concretefaced rock fill type, continued with conservation development works to increase existingenvironmental and secure water to the reservoir. The reservoir will restore 30 million m3 water fromKaralloe river. 50% of raw water will be supplied to 7.199 ha of existing Kelara irrigation area and50 % will be supplied to RWTP for increasing the clear water for the urban (2) in the middle time, theconstruction will be continued by the improvement of existing irrigation. (3) In the long term, waterresource structure will be constructed like the sediment control dams, sand pocket dams in theupstream of the dam to anticipate erosion and sedimentation to the dam, and construction ofreinforced concrete pipe or the raw water transmission main to supply the reservoir water to RWTP.The construction will be continued by Jeneponto river improvement as a recharge of raw water. In thefuture, the expected result with the karalloe multipurpose dam will solve the raw water crisis for theexisting environmental, clean water and irrigation development.

Keywords: Karalloe multipurpose dam, Environmental, raw water, irrigation development, GlobalClimate change

1. INTRODUCTION

The Jeneponto regency has a serious water crisis to be solved by the Karalloe dam. Highestdeforestation and eroded has a high sedimentation to damage the lowest area so the regulateflooding inundate urban area for a long time during rainy season. During the dry season theraw water crisis to the regency (district) is a serious problem too. A Jeneponto river is a jointriver between Karalloe River and Kellara River, which come from Lompo Batang mountain,flows to Bontosunggu, a capital city of Jeneponto regency. In the upstream (U/S) ofJeneponto regency, no reservoir to restore those rivers so that in dry season, the existing rawwater is not enough to be supplied to the raw water treatment plant and not enough to besupplied to the existing Kellara technical irrigation area so the rice cropping is not optimizealthough existing Kellara and Karalloe weirs are facilitated to support the irrigation area wereconstructed in 1976. In the rainy season, regulate flooding inundate the urban and ruralJeneponto. In related with the problem mentioned above, on July 4, 2012, the governmentdeclared that the Karalloe Multipurpose Dam will be constructed to solve the raw water crisis

I - 222

Page 223: Study of Social and Economic Impacts of Construction of ...

and regulate flooding. The problem will be managed by sustainable, integrated waterresources management, in the short term, the middle term and the long term.

2. SOCIAL AND ENVIRONMENTAL ASPECTS OF DAM

Systematically, social and environmental aspects of the karalloe multipurpose dam as asolution for the environmental and raw water development in Jeneponto regency will relatedto greenhouse gas effect of Karalloe multipurpose dam, public participation for the Karalloemultipurpose dam and Kellara irrigation scheme, institutional aspects on the Karalloe dam,land acquisition and resettlement for the Karalloe dam, Environmental management duringKaralloe dam construction will be written briefly:

2.1. Greenhouse Gas Effect of Karalloe Multipurpose Dam

For securing and sustainable raw water in the Karalloe multipurpose reservoir, conservationmust be developed. Conservation development can increase O2 and reduce CO2 to secure theexisting environmental and raw water in reservoir for increasing irrigation and clear water.The concentration of Green House Gas in the atmosphere had been increasing slowly.Anomalies in the concentration patterns of CO2 and CH4 have been correlated with thedevelopment of existing Kellara irrigation, agriculture, floras, fauna and human life.Theoretically, the greenhouse gas effect of dams is the principal cause of climate change.Some regions of the world are experiencing heat waves, severe droughts, and wildfires whileother regions are facing unusually strong monsoons, widespread flooding, and rain-inducedlandslides. For these extreme events, people around the world are facing some form ofclimate related crisis with increasing frequency. International efforts to advise countries on

I - 223

Page 224: Study of Social and Economic Impacts of Construction of ...

how to reduce their greenhouse gas emissions and cope with climate change are ongoing.National strategies for sustainable development are being implemented by many countries aswell as programs to monitor and mitigate greenhouse gas emissions. Winning the battle toslow down and cope with climate change will be a long term challenge which will likelyrequire substantial changes in the behavioral patterns of society. Climate change is giving riseto all kinds of environmental changes. It results in heat waves, droughts and fires in someregions, and in other regions, floods and freak storms. Even though not everyone isconvinced that the changes in climate are abnormal or anthropogenic, there is widespreadevidence from many independent sources suggesting that the earth is getting warmer.Temperatures over land and ocean are rising. Temperature records are being exceeded inmany regions of the world; extreme events are becoming more frequent. Some of the inter-annual climate variations, which are sometimes attributed to climate change, are undoubtedlydue to events such as El Nino. However, it has recently been hypothesized that the frequencyof El Nino events, which has almost doubled since 1980, might be due to the increase in theconcentration of greenhouse gases in the atmosphere. In this presentation of the greenhouseeffect, discuss the main causes of climate change, present information on the magnitude andimpact of climate change, mention some of the international efforts to deal with climatechange, and present some strategies for minimizing the increase in the atmosphericconcentration of greenhouse gases. Many technical solutions are being advanced by thescientific community to mitigate greenhouse gas emissions and to help adapt to climatechange, but these are unlikely to be sufficient to stop more global environmental changesunless tremendous progress is made in using resources more sustainably. The temperature ofthe Earth depends on the energy budget at the Earth's surface. The main source of energy isthe incoming short wave radiation from the sun.Approximately 30% of this radiation is reflected back into space by clouds and the Earth'ssurface. Having been warmed by the sun's radiation, the Earth cools itself by emitting longwave radiation back into space. Part of the long wave radiation emitted by the Earth isabsorbed by heat trapping gases in the Earth’s atmosphere such as water vapor (H2O), carbondioxide (CO2), methane (CH4), nitrous oxide (N2O), ozone (O3) and re-emitted in alldirections, including back towards the Earth's surface. Because it is analogous to the wayglass greenhouses trap solar energy, this phenomenon is known as the greenhouse effect andthose heat trapping gases in the atmosphere are known as greenhouse gases. The globalwarming potential of a gas gauges its effectiveness in warming the atmosphere. It is differentfor all Green House Gas, and CO2 is used as the reference. For example, over a century, akilogram of N2O is 298 times more effective at warming the atmosphere than a kilogram ofCO2. Hence the CO2 equivalent (CO2e) of N2O is 298. It is interesting to note that withoutthese greenhouse gases the temperature at the earth's surface would be about 33oC cooler. Forexample, from 8,000 to 2,000 years ago an anomalous increase in the atmospheric CO2 untilthe 1970s, as much CO2 concentration of about 40 ppm (parts per million) has beenattributed to forest clearing for the development of agriculture in Europe and China. A similarincrease in the concentration of methane of 250 parts per billion, which took place 5,000 to1,000 years ago has been ascribed to the spread of irrigated rice farming in Asia. It has beenestimated that the increase in concentration of these two gases increased the Earth'stemperature by about 0.8oC during that period. It had been released into the atmosphere fromthe clearing of land as from the burning of fossil fuels. However, since then, the contributionof fossil fuel combustion has become much more important. For example, over the past 20years, of the CO2 This large increase in energy-related CO emissions are estimated to havecome from the combustion of fossil fuels and the remainder from land use changes. The shareof Green House Gas emissions related to fossil fuel combustion is now growing at anaccelerating rate. During the last two centuries and particularly during the last 3 to 4 decades,

I - 224

Page 225: Study of Social and Economic Impacts of Construction of ...

the atmospheric concentrations of CO emissions are closely associated with the increase inthe world's population.

2.2. Public Participation for the Karalloe dam and Kelara Irrigation Scheme

The most significant part of the Water User Association for the Kellara Irrigation scheme(The irrigation) is in water scheduling and distribution. When irrigation water availability isadequate or between 4 and 6 m3/second, three Water User Association divides irrigationsupplies at the major diversion structure in proportion to their areas and then guard thosesettings. When the available water falls below 4 m3/Sec, the Water User Association switchto irrigation rotational procedures, involving 2.5, 2 and 2.5 days allocation for each of thethree Water User Association. Within each Water User Association sub-command, scheduleshas been developed for sharing water between day blocks and night blocks. Each block issplit again into roughly 1/3rd of their areas, with each sub-area getting an allocation for the1st, 2nd or the 3rd day. The Water User Association proposes the schedules and the gateoperators carry out their instructions for the setting of the gates. This kind of waterscheduling needs a high degree of cooperation among water users. It is unlikely thatgovernment operators could achieve satisfactory performance levels at the irrigation schemewithout the involvement of the Water User Association.

The federation leaders ensure that their members obey the scheduling rules and havedeveloped sanctions for persistent offenders. As can be seen from the description of theorganization for O&M described above, it is still in the process of adapting to the newnational policies. Farmers will continue to participate in irrigation O&M activities in severalways: (1) Farmers are mobilized on a voluntary group basis under traditional practices for

I - 225

Page 226: Study of Social and Economic Impacts of Construction of ...

twice a year, before the start of the planting to undertake light maintenance work in thesecondary canals, such as clearing sediment, grass cutting, small lining repairs. (2) Thefarmers decide on cropping patterns and water distribution schedules, and the head of regencyissues appropriate instructions based on these group decisions. The the Water UserAssociation have agreed on sanctions to be imposed on farmers who do not follow the agreedcrop and water schedules and then waste valuable water. (3) In previous years, farmerscollected funds informally for use in O&M where they saw a need. In 2005, the former alobbied to change the bylaws about water user fees going to the regency accountssuccessfully. Under the revised procedures, the Water User Association keeps the funds fortheir own internal the Water User Association. In 2006, the farmers will strictly enforcepayment by members of at a level of Rp.25,000/season/ha and 20% of members have so farpaid these amounts. (4) The farmers have greatly expanded the area cultivated in secondcropping (palawija) during the dry season so that more area can be planted. In 2005 thispalawija area had increased to 2,500 ha, with only 1,500 ha of paddy. (5) In 2003, theKaralloe weir sluice gate stems seized up and could not be closed. The government at thattime had no funds for repair so the farmers paid for the repair themselves. (6) The end of2005, a serious landslide with the sedimentation deposit into the main canal, cutting offirrigation flows at a critical time before wet season plantings. The irrigation maintenancefunds through national budget, but no money available for this work. At the initiative of theWater User Association leaders, reparation of landslide work was initiated by requestingregency assistance with heavy equipment and the Water User Association arranged to providethe necessary labor to clear the blockage.Lessons and learned in the irrigation: (1) Rehabilitation of an operating irrigation needs fullparticipation of the beneficiaries and a multidisciplinary approach involving farmer groupstrengthening, improved agricultural practices, training in O&M and repairs to the irrigationinfrastructure. Placing a lot of emphasis on construction works at the expense of thesepreceding activities can lead to disappointing results. (2) The whole-heat support of localgovernment is an essential prerequisite for successful participation. The JenepontoGovernment leader must give his full attention and support to the improvement measuresproposed for the irrigation scheme. (3) The appropriate emphasis for improvement worksshould be improving the water management and crop production development. An overallwater management study, carried out before improvement works start will be highly usefuland effective in producing a successful strategy. Full consultation is needed with allstakeholders to be focused for the real problems and proposing real solutions. (4) Thepromise of funds for rehabilitation can be a great incentive for farmers to change negativeperceptions and increasing participation in necessary irrigation O&M activities. (5)Participation must be meaningful and involve empowerment of farmers. Previous attempts touse the Water User Association as a government tax collector failed because the benefits ofparticipation were one sided. (6) Participation can be improved by the sustained use ofneutral groups as who can be trusted by farmers (consultants or NGOs) as an intermediariesand a facilitator for irrigation scheme improvements. (7) The participation model must besuitable for local conditions, not a standard and uniform system imposed from above. Forexample, in the irrigation scheme, the sizes of the Water User Association areas are not equal,the main canal was left out of the water scheduling, and efforts were made to ensure that thetraditional local leaders were involved from an early stage, thereby co-opting potentialopposition. (8) Designing the Water User Association sub-commands of unequal sizes areasis not a problem. It is much more important that the Federations are granted total control ofthe water in their areas (9) A step-by-step approach to initiating irrigation physical,organizational and management improvements is recommended. At the irrigation scheme, therehabilitation was carried out in several separate stages, with the early stages generating

I - 226

Page 227: Study of Social and Economic Impacts of Construction of ...

significant benefits for all, which in turn led to a greater willingness to participate andcooperate in future activities and stages. (10) Continued support and training after physicalworks are completed generate positive additional impacts on active participatory watermanagement and outcomes. (11) comparative study conducted outside of the geographicalscheme area, including alternative cultural settings, proved to be highly effective indemonstrating modern O&M practices, the farmers were comparative studied to East Javairrigation schemes where the Water User Association leaders had a high level of positiveinvolvement in O&M matters.The Kellara irrigation schemes lies wholly within the Jeneponto regency within 5 Sub districtand 24 Villages. The scheme area covers 7,199 ha, divided into 2,157 tertiary blocks, with 51the Water User Association and 11,264 farmers. In an attempt to resolve the dilemmasituation to maintain sustainable rice production on the one hand, while keeping pace theproductivity level with the increasing population growth on the other, an emphasis has beengiven to irrigation development and management based on a participatory approach. Theprogram had been set up to reduce central government's burden on Operation andMaintenance (O&M) costs, aiming for sustainable irrigation O&M by virtue of ParticipatoryIrrigation Management approach. Under the said program, a number of policy adjustments onwater resources had been enacted. Further to this, Participatory Irrigation Managementattempts have also been carried out including: turning over to the Water User Association , ofsmall irrigation schemes; encouragement of Irrigation Service Fee; Irrigation ManagementTransfer ; Participatory design and construction program; field laboratories for visual processof learning by doing, and other such government initiatives. However, it turned up that theattempts has been going very slowly and yet, still tended to be sustainable. This has beenpartially suspected by the fact that the economy of the farmers and farming conditions underthe fragmented land ownership, which in fact, are already small, has been marginalized. Inthe water resources development within thirty years until 1997 through government leddevelopment projects. However, the institutional development to sustain this progress gotinsufficient attention. From the lessons learned before the multidimensional crisis, it has beenrecognized that the severe crisis had been due to the chronic neglect of the farmers roles inalmost the entire process of development, rehabilitation, and routine operation andmaintenance of irrigation infrastructures.At the present time, access road to the Karalloe multipurpose dam has been completed to becontinued to the dam construction. The dam is constructed by the Pompengan JeneberangLarge River Basin Organization under Directorate General of Water Resources, Ministry ofPublic Works to restore water of Karalloe river. In the future time , about 30 million m3water come from the reservoir will irrigate the 7,004 ha Kelara irrigation area through 70 kmsecondary canals. The last time, without the Karalloe dam, the irrigated area had declined toless than 1,000 ha or which is equivalent to 16% designed capacity every year so farmersneed additional water and irrigation improvement. The shortage of water led to permanentsocial discord and the farmers themselves destroyed and damaged the irrigation works inattempts to divert water away from their neighbors’ lands and into their own fields. Therewere no water sharing plans or staggered plantings and coordination of irrigation and watermanagement was poor. A storage dam was proposed as a solution to the water shortages byKaralloe dam. It was recognized that the existing irrigation and agricultural land resourceswere vastly underutilized due mainly to poor water management. Better irrigation and watermanagement was not possible without full commitment, cooperation and participation of thefarmers and the local community. Hence a study was undertaken between 1998 and 2000,with the aim to clarify the real causes of the water shortages by collecting and analyzing dataand information on the project from both government officials and local farmers, and bymaking recommendations for improvements. Measures aimed to improve irrigation and water

I - 227

Page 228: Study of Social and Economic Impacts of Construction of ...

management were implemented between 1999 and 2002 using participatory methodologiespromoting farmer participation. Based on the WMIS, indicate that (1) The main canalcarrying capacity was too small, reduced to 25% of the total requirement by defects in thecanal, and limited to 50% by the carrying capacity of the tunnels. (2) The secondary systemwas in a poor condition, with heavy sedimentation and sanitation, and many broken andleaking (3). The tertiary system was either non-existent or in a poor state of repair. (4). Watermanagement was very problematic due to a lack of farmer commitment and involvement,possibly arising from the continuing shortages of water and the special character of the localpeople.

2.3. Institutional Aspects on the Karalloe Multipurpose Dam

Based on The No.7 Law of 2004 on water resources, O&M responsibility is assigned by threeadministrative levels. It is (1) Central (2) Province (3) District or regency with thedesignation of responsibility depending on schemes area as (a) >3,000 ha (b) 3,000-1,000 ha(c)<1,000 ha. The Water Use Association is delegated the responsibility for the constructionand O&M of tertiary systems. Under the revised arrangements, the central government willtake responsibility for the irrigation scheme, given its size.

The mechanisms and organizations are still evolving, but will certainly involve partnerships,mutually agreed between the different administrative levels for implementation of O&M,depending on the abilities and willingness to participate of each level. Given the positiveexperience and clear benefits of good water management practices seen over the past eightyears, the provincial and district governments, the Water Use Association and the farmerbeneficiaries are all well prepared and ready for whatever the new arrangements will bring

I - 228

Page 229: Study of Social and Economic Impacts of Construction of ...

and hopefully the outcome will lead to a further increase in productivity of the irrigationsystem.

2.4. Land Acquisition and Resettlement for the Karalloe Multipurpose Dam

The Karalloe multipurpose dam is feasible to be constructed to solve the raw water crisis andto the regulate flooding. Based on data of the Karraloe dam that the dam will be constructedusing a rock fill dam with concrete face type, to store Karalloe river located in Gowa regency.The height, crest width and length of the dam is 75.18 m, 11 m, 325 m.

The dam is supported by 182 km2 Catchment area, 22 km Karalloe river length with 2.495mm/year annual average rainfall, 28.47 m3/second Q max, 3 m3/Sec Q min, 239.65 mmaximum water level, 89.20 m minimum water level. The reservoir has 30 million m3effective storage capacities with 1.6 km2 surface area will be inundated 3 villages, thegovernment will provide land acquisitions of the inundation villages and relocate about 90families to new location (resettlement Site).

2.5. Environmental Management During Construction of the Karalloe Dam

The Karalloe multipurpose dam will store 30 million m3 raw water to be constructed in hillyarea located in Taring Village, Biringbulu Sub District, Gowa Regency, located in the upperstream of Jeneponto regency to supply the raw water to the rural and urban Jenepontoregency for example 15 m3/Sec raw water for 7.199 ha of the existing technical irrigationarea, 0.3 m3/Sec for clean water, 380 Volt 50 Hz for micro hydro electricity power, 30 m3

I - 229

Page 230: Study of Social and Economic Impacts of Construction of ...

for flood control including flushing of drainage. Another purpose of the raw water will beused tourist development. The sketch informs the development of water resources structureswill be constructed and developed after the final construction of the dam for instanceconstruction of the Sediment Control Dam, Sand Pocket Dam, Conservation Dam, includingdevelopment of conservation and reforestation are located in the U/S of the dam to preventand minimize the sedimentation in the reservoir. Construction of Raw Water TransmissionMain including construction of Raw Water Treatment Plant will be located in the D/S of thedam to support increasing of clean water. During construction, environmental improvementworks or conservation development must be done to anticipate next disaster, an erosion or alandslide in the upper of the dam and to secure water to reservoir for existing irrigation andenvironmental development.

3. CONCLUSION AND RECOMMENDATION

The 30 million m3 of raw water come from Karalloe reservoir constructed in Gowa regencyis the best solution for securing and providing a sustainable existing environmentalprotection and the existing Kellara irrigation development in Jeneponto regency so the damwill be constructed in 2014. It is recommended that during and after the completed ofconstruction, all exiting water resources in Jeneponto including the Karalloe dam, Kelarairrigation scheme and such river as Karalloe, Jeneponto, Kelara must be managed by theenvironment, sustainable integrated water resources management for sustainable existingenvironmental protection and raw water development including the conservation orforestation development.

ACKNOWLEDGEMENT

Thanks to a committee of the 82nd ICOLD Annual Meeting and symposium to approve andlet this paper to be presented at the meeting for transferring and sharing the dams in globalenvironmental challenges knowledge among participants.

REFERENCES

A. Hafied A. Gany, (2007): Problems and Perspectives of Participatory IrrigationManagement Under The Small Land Holding Condition: with a Special Reference toIndonesian Practice, ICID Publisher, Tehran, Iran

Agus Setiawan, Hariyono Utomo, Subandi and Zainal Arifin, (2013): Karalloe MultpurposeReservoir for Raw Water Crisis, Indonesia Hydraulic Engineers AssociationPublisher, Jakarta, Indonesia

Anonym, (2012): No. 7 of 2004 Indonesia Law on Water Resources, DGWR Publisher,Jakarta, Indonesia

Andal Persada Utama Consultant PT, (2012): Environmental Risk Analysis of KaralloeMultipurpose Dam, Andal Persada Publisher, Makassar, Indonesia

Bintang Tirta Pratama PT, (2013): Detailed Design of Karalloe Dam Supletion Channel, BTPPublisher, Makassar, Indonesia

Biosfera Widhy Engineering Consultant PT., (2012): Study of Land Acquisition andResettlement Action Plan of the Karalloe Multipurpose Dam, BWEC Publisher,Makassar, Indonesia

CTIE Co., Ltd and associates with Indonesia Consultant, (2000): Consulting Services onComprehensive Water Resources Management Plan Study for Maros JenepontoWatershed, CTIE Publisher, Makassar, Indonesia

I - 230

Page 231: Study of Social and Economic Impacts of Construction of ...

Directorate General of Water Resources, Yayasan Air Adi Eka and JICA, (2013): RiverManagement in Indonesia, DGWR Publisher, Jakarta, Indonesia

INACOLD, JBIC, DISIMP and Nippon Koei, Co.Ltd., (2005): Workshop on Concrete FacedRockfill Dam (CFRD), Hand out of Design and Construction CFRD, ICOLDBulletin, DGWR Publisher, Jakarta, Indonesia

Mettana Engineering Consultant PT, (2012): Detailed Design Review of KaralloeMultipurpose Dam, Mettana Publisher, Makassar, Indonesia.

Mohamad Hasan and Syamsudin Mansoer, (2007): Participatory Irrigation Management InKelara Karalloe Irrigation Project, South Sulawesi, Indonesia, ICID Publisher,Tehran, Iran

Nippon Koei Co., Ltd and associates with Indonesia Consultant , (2008): Consulting Serviceson SSIMP-III, Kellara Karalloe Dam Study/Design of Canal and Related Structures ofKelara Primary Canal, Nippon Koei Co., Ltd Publisher, Makassar, Indonesia

R. L. Desjardins, (2013): Climate Change - A Long-term Global Environmental Challenge,Elsevier International Journal Publisher, San Diego, CA 92101, USA

I - 231

Page 232: Study of Social and Economic Impacts of Construction of ...

THE SADDANG MULTIPURPOSE DAM FOR ANTICIPATEFLOODING AND ENVIRONMENTAL DEVELOPMENT

Sumardji1, Eka Rahendra1, Subandi1, Andi M. Irham1,M. K. Nizam Lembah2 & Sukarman3

1)The Pompengan Jeneberang Large River Basin Organization, Makassar, Indonesia2)Directorate of Rivers and Coastal, Directorate General of Water Resources, Jakarta, Indonesia

3)Water Resources Consultant of Pompengan Large River Basin Organization , Makassar, [email protected]

ABSTRACTA case of Saddang river is serious problem, not only in rainy season but also in dry season. Floodingof the river cannot be controlled by the Benteng barrage, nothing to be done by the farmers exceptwaiting for flooding escape. In the dry season, it is not enough water to irrigate all fields because ofwater lost so that no increasing of rice cropping. Briefly, the flood and irrigation water crisis inconnection with the global climate change, caused of: (1) Saddang dike over-topping so that about3.951 ha of 93.724 Ha of irrigation structures in a bad condition (2) A lot of sedimentation depositedin the existing irrigation channel (3) No integrated and sustainable in operation dan maintenance ofthe channel (4) All irrigation channel are opened channel with the risk of water lost caused of illegalirrigation pumping, evaporation and infiltration. To solve the problem mentioned above: (1) In shortterm; Saddang dike and irrigation channel must be repaired urgently and Environmentalimprovement work must be done, a good conservation must be developed to stabilize the the riverdischarge, it will be useful to anticipate next flooding (2) in the middle term; a multipurpose dammust be constructed in the upper stream of the existing Benteng barrage to store and to controlSaddang river (3) In the long term; the existing opened Irrigation channel must be changed with theclosed irrigation channel by the concrete reinforce pipe to anticipate: illegal irrigation pumping,evaporation and infiltration. The result expected that with these methods: No flooding, no illegalirrigation pumping, no evaporation, no infiltration, securing water for food and rural communityunder climate change, increasing of food cropping, securing water to 7,574 km2 of The River Basinfor environmental development.

Keywords: Saddang multipurpose dam, environmental development, Anticipate flooding.

1. INTRODUCTION

Saddang river’s 150 km length cover to the 5,453 km² watershed is the biggest river amongrivers in the Saddang river basin, the river crosses the South Sulawesi and the West SulawesiProvince. This basin covers 7,574 km² area and consists of 74 watersheds. Noted that themore than 10 existing rivers flow to estuary through saddang river. In the present, Saddangriver has a serious problem, not only in rainy season but also in dry season. Flooding inundateabout 93.724 Ha fields, it is not be controlled by the Benteng barrage, nothing to be done bythe farmers except waiting for flooding escape. In the dry season, it is not enough water toirrigate all fields because of water lost so that no increasing of rice cropping. Briefly, theflood and irrigation water crisis in connection with the global climate change, caused of: (1)Saddang dike over topping so that about 3.951 ha of 93.724 Ha of irrigation structures in abad condition (2) A lot of sedimentation deposited in the existing irrigation channel (3) Nointegrated and sustainable in operation and maintenance of the channel (4) All irrigationchannel are opened channel with the risk of water lost caused of illegal irrigation pumping,evaporation and infiltration. To solve the problem mentioned above: (1) In short term;Saddang dike and irrigation channel must be repaired urgently and Environmental

I - 232

Page 233: Study of Social and Economic Impacts of Construction of ...

improvement work must be done, a good conservation must be developed to stabilize the theriver discharge, it will be useful to anticipate next flooding (2) in the middle term; amultipurpose dam must be constructed in the upper stream of the existing Benteng barrage tostore and to control Saddang river (3) In the long term; the existing opened Irrigation channelmust be changed with the closed irrigation channel by the concrete reinforce pipe toanticipate: illegal irrigation pumping, evaporation and infiltration.

The result expected that with these methods: No flooding, no illegal irrigation pumping, noevaporation, no infiltration, securing water for food and rural community under climatechange, increasing of food cropping and securing water to 7,574 km2 of the existing RiverBasin for environmental development.

2. SOCIAL AND ENVIRONMENTAL ASPECTS OF SADDANG DAM

Systematically, social and environmental aspects for the saddang multipurpose dam foranticipate flooding and environmental development will be related with green house gaseffect of dam, public participation for a proposal of multipurpose dam and existing irrigationscheme, institutional aspects on the dam, land acquisition and resettlement for the dam andenvironmental management during dam construction will be written briefly:

2.1 Green House Gas Effects of Saddang Multipurpose Dam

In related with the proposal of The saddang multipurpose dam for anticipate flooding andenvironmental development, the green house gas effect of the Sadang multipurpose must beconsidered that the conservation improvement work for securing water of the reservoir and to

I - 233

Page 234: Study of Social and Economic Impacts of Construction of ...

anticipate flooding with restore the Saddang flooding, because to increase Oxygen (O2) andto reduce dioxide (CO2) for sustainable existing environmental. Theoretically, that inlandwater bodies, such as freshwater lakes, are known to be net emitters of CO2 and methane(CH4). In recent years, significant greenhouse house gas emissions from tropical, arboreal,and mid-latitude reservoirs have also been reported. The extended version of the MERGE(Model for Evaluating the Regional and Global Effects of Greenhouse Gas ReductionPolicies) has been used to project Indonesian’s energy production, consumption and export tothe year 2100, for a reference scenario and mitigation scenarios. In addition to theinternational trade of energy, coal has been included in this version. The study also analyzesthe interaction between the forest sector and energy policy and finally analyzes the directeffect of international climate policy on deforestation in Indonesia.

Then, the MERGE has been extended to analyze emissions of air pollutants. The model usesthe base scenarios from IPCC 2000, with extensions to include mitigation scenarios, toproject concentrations of air pollutants and their impacts on human health and the economy.In the Indonesian energy sector, coal production grows gradually and gas production morestrongly in the reference scenario, whereas oil production falls rapidly. Oil imports increase,while coal exports decrease; gas is imported later. If all countries reduce their emissions,including Indonesia, coal production increases slightly less than in the reference scenariotowards the end of century. Oil imports are higher and gas imports slightly lower than in thereference scenario. The effects of fossil fuel emission reduction on deforestation are slightlyless than in the reference case. The cost of slowing deforestation in Indonesia increasesexponentially by a factor of approximately 20 by the year 2100. Saddang river basin wouldgain the profits from slowing deforestation since the revenue from slowing deforestation ishigher than the costs. The health problems associated with sulfur dioxide (SO2) and nitrogen

I - 234

Page 235: Study of Social and Economic Impacts of Construction of ...

dioxide (NO2) concentrations resulting from fossil fuel use reach higher levels if OECDcountries reduce their emission, since Indonesian oil imports increase. However, if allIndonesia river basin adopt the Kyoto protocol, the health problems are lower than in thereference case. Human activities are increasingly modifying the Earth’s climate. Theseeffects add to natural influences that have been present over Earth’s history. Human impactson the climate system include increasing concentrations of atmospheric greenhouse gases(e.g., carbon dioxide, chlorofluorocarbons and their substitutes, methane, nitrous oxide, etc),air pollution, and land alteration. Atmospheric carbon dioxide concentrations have increasedsince the mid-1700s through fossil fuel burning and changes in land use, with more than 80%of this increase occurring since 1900. Moreover, research indicates that increased levels ofcarbon dioxide will remain in the atmosphere for hundreds of years. It is virtually certain thatincreasing atmospheric concentrations of carbon dioxide and other greenhouse gases willcause global surface climate to be warmer. The 1992 United Nations Framework Conventionon Climate Change states as an objective the “stabilization of greenhouse gas concentrationsin the atmosphere at a level that would prevent dangerous anthropogenic interference with theclimate system”. Developed countries and countries with economies in transition are requiredto reduce their aggregate net emissions. Indonesia has the fourth biggest population in theworld, and is one of the countries prepared to meet its commitment as a party to theConvention. Furthermore, Indonesia has significant reserves of coal, natural gas, and oil assources of energy and also as emissions. The emissions from forestry and land use changecan also affect climate change be significantly. Scientists’ understanding of the fundamentalprocesses responsible for global climate change has greatly improved during the last decade,including better representation of carbon, water, and other biogeochemical cycles in climatemodels. Yet, model projections of future global warming vary, because of differing estimatesof population growth, economic activity, greenhouse gas emission rates, changes inatmospheric particulate concentrations and their effects, and also because of uncertainties inclimate models. The MERGE is a powerful tool for analyzing mitigation policies to deal withthe global climate change issues. The MERGE consists of four major parts: (1) economicmodel, (2) energy model, (3) climate model, and (4) climate change impact (damage) model.In the MERGE model, Indonesia is included only in the Rest of the World (ROW) region.However, an analysis of the individual role of Indonesia in relation to international climatepolicies is important for the country to develop a meaningful national climate policy. Themain question is whether Indonesian national policy has a significant impact on internationalclimate policies and global climate change. To study this question, we add a separate regionfor Indonesia in MERGE as a tenth region. The MERGE model to include coal as a tradablegood and added a new forest model to analyse forest change, especially for Indonesia.Finally, we applied the reference scenarios from the Intergovernmental Panel on ClimateChange (IPCC, 2000) and the IPCC scenario with various mitigation scenarios, in order toestimate air pollution.

2.2. Public participation for Saddang Multipurpose Dam

Public participation concept approach is a consequence of the intervention of the governmentfor these decades in irrigation management system, while the farmers has been neglected, ofwhich make them has a new mindset, that the operation and management system of theirrigation system, even in the tertiary system is the responsibility of the government as theauthority. When the quantity of water became not sufficient as result of the decreasingservice capability of the infrastructure, the farmers just waiting for the government to repair,even just for the tertiary canal or cleaning the canal, while the tight money policy after theeconomic and financial crisis, the government become more difficult to handle these matter.

I - 235

Page 236: Study of Social and Economic Impacts of Construction of ...

As the result, so many people speak about the failure of the government in agriculturalsystem, which means the prepare own rice has been failed. Thus the government must importrice. To avoid this situation, idea about farmers participation rise up. At the beginning,participation concept approach, starting with the result of a study, that the farmers notparticipate and to take the responsibility, because the infrastructure of which has been builtnot suitable to the needs of the farmers. So the recommendation said, that the farmers must beinvolve since planning and design, Implementation and Operation and Maintenance System(IOMS) in order to get the participation from the farmers. Actually right, because when theyinvolve in the work they will have the sense of belongings, and than they will participate inIOMS, especially at the tertiary system. Water resources participation implementation is theparadigm in irrigation management as a part of the management in, is a consequence ofseveral phenomenon in all over the world, such as; human right with the democratic process,the right to have access to fresh water, the demand of fresh water, quantity and qualitybecome increase while the supply become decrease.

Participatory irrigation management for many years, during the early stage of irrigationdevelopment, the farming community considered irrigation as an “art” rather than“technology”. During which, most of irrigated agricultural undertakings were conducted bythe community members on the basis of mutual assistance. However, as irrigationdevelopment become more and more expanded to larger areas, the operation andmanagement become hardly conducted by the farming community on mutual assistance. Atthis stage, the operation and management of irrigation were then centered on technologicalapplication with subsequent subsidies by the government for both development andmanagement. Except for small scale irrigation, the operation and management were thenincreasingly dependent upon special irrigation technology, while the farming communities

I - 236

Page 237: Study of Social and Economic Impacts of Construction of ...

are still performing on the basis of the previous experiences. For which, irrigation operationand maintenance were conducted without much involving the farming communities as well asother stakeholders. As a result, many irrigation schemes, ranging from medium to large scalewere reportedly lack of operation and maintenance.

Being under the poor performance, the role of irrigation water for food production, health andenvironment has increasingly become susceptible in terms of accessibility to adequatequantity and reasonable quality, as well as timely distribution. Being the case, it is essential togive special thought about the new approach toward efficient irrigation water management,involving the water users, planners, and decision makers at all levels (participatory irrigationmanagement). Under the participatory irrigation management, the issues to address are notonly about irrigated agricultural engineering, sociology economics in isolation. Rather, itconcerns the challenging management issues, involving strategic approach, institutional, aswell as psycho-graphic elements of actors surroundings. The participatory approach involvesthe new and important roles of the water resources institutions, and most significantly, as thefundamental reform of the role sharing amongst the relevant government institutions as wellas the stakeholders.

2.3. Land Acquisition and Resettlement for Saddang Multipurpose Dam

Consequently, proposal of new multipurpose dam in upper site of existing Benteng barragemust be studied seriously because the construction of Saddang dam will be related with theland acquisition and resettlement problems. The main problems and constraints associatedwith land, soil and drainage among others are: (1) Lack of appropriate land resources, (i) Inmany areas of the developing world, there are few new areas of suitable agricultural landwhich can be economically developed using existing water resources; (ii) Marginal lands are

I - 237

Page 238: Study of Social and Economic Impacts of Construction of ...

being over-exploited and degraded under excessive population pressures. Productive land isbeing lost to rapid urban and industrial development; (2) Water quality constraints, (i) Some30 million hectares of land world wide are affected by continuing problems of water loggingand salinity; (ii) In water-short areas, soil is being degraded by irrigation with brackish water;(iii) In arid areas, the long-term effects on soil structure of irrigating with low quality urbaneffluent are uncertain; (3) Soil conservation technology, (i) Lack of appropriate techniquesfor reclaiming large areas of problem soils have still to be developed, while the provision offood supplies can hardly waiting till appropriate technique be developed; (ii) Problemsrelated to excessive water requirement for the newly developed agricultural lands.

2.4. Institutional Aspects on the Saddang Multipurpose Dam

Institutional aspects on the dam is Institutional demands for irrigation development andmanagement. Due to the dynamic shifts on a number living and livelihood aspects of thepeople, along the escalating growth of population, the economic and technologicaldevelopment, are becoming imperative. These include operation and management ofirrigation, both the perspective of technical and non technical concerns. For consistentimplementation of irrigation development as well as efficient operation and maintenance, it ishighly essential to have a well established institutional arrangement. For example, inattempting to set up an appropriate institution, a current institutional arrangement is currentlybeing undertaken in Saddang river basin. The activities are conducted in accordance with thegrowing demands and changes in irrigated agriculture. Under the dynamic progress ofinstitutional arrangement, it has been evident that the underlying changes and application ofirrigated agricultural technology are the determinant factors in the shaping the institutionalarrangement. The underlying approach for institutional adjustment has been on the basis ofappropriate balance between the economic demand and supply of irrigated agriculture in linewith the major principles of technological innovation. However, it is not unusual that theinstitutional set up is often determined by the political will of the ruling elite for insistingchange of the relevant regulatory instruments. Beside, the influence of certain politicalideology with adequate budgetary power could also become determinant factor that shouldnot be overlooked or under estimated.

2.5. Environmental Management During Saddang Multipurpose Dam Construction

Environmental management during construction must be implemented because the irrigationrelated with environmental problems are dominant with : (1) Water bond diseases. Inadequatemaintenance leads to silted and weeds in the gated channels, encouraging water-relateddiseases like malaria; (2) Silt transportation. Reservoirs are silting up at increasing rates ascatchments are denuded. Between 1980-2000, global storage capacity increased 25%,whereas lost capacity increased 140%, to stand at 10% of total capacity; (3) Agrochemicalcontaminants. Increased use of agrochemicals. Long-term impacts on human health and theenvironment are unknown. In the short term, fertilizers/pesticides end up in drains, promotingaccelerated growth of weeds and algae, and in aquifers; (4) Outbreak of plant disease lifecycle. Genetic diversity is being reduced as a few high yielding crop varieties predominate.The impact of a sudden outbreak of disease could be potentially devastating. Geneticallymodified crops offer potential but also bring extra risks to farmers’ livelihood, as well as tothe environment; (5) Impacts of saline water. Reuse of saline water can create long-termproblems. Disposal of saline water to sinks creates permanent degraded sites, with risks forfuture groundwater quality; and (6) Heath impacts on black water utilization. Food grown onblack water and sewage sludge potentially involves risks to human health. Increasingly tight

I - 238

Page 239: Study of Social and Economic Impacts of Construction of ...

standards of hygiene in industrialized nations may bar developing countries from exportingtheir agricultural production. Ecological aspects of irrigation is environmentally friendlyirrigation water management on paddy field, coping with water scarcity constraint, therewould be not much available alternatives but emphasizing the agricultural production systemfor applying for water saving effort, while the demands for production function as well as forenvironment must become the major consideration for determining the real time waterallocation. For rice cultivation, however, the water application principles have been by itsnature met several prerequisites for environmental conservation. However, with theescalation of chemical fertilizer application on agricultural lands, a number of negativeimpacts have been identified, including the growing up of nitrogen and phosphorusconcentration in surface and ground waters. These nutrients induced of water bodies.Furthermore, the prolong application of chemicals such as pesticides and weed control,pollutes rivers and lakes through runoff, or groundwater leaching. Given such negativeconsequences, the environmentally friendly irrigation development for paddy field becomesignificantly important goals in the near future. This is particularity true for the fact thatpopulation growth would always followed by escalation of food demands. In spite of thedeterminant factors, it is equally important to ensure the effective instruments for mitigatingthe water constraints, minimizing the negative impacts while enhancing the positive aspectsfor environmental sustainability.Enhancement of bio-environment functions of irrigated paddy field, since early time, thehuman nature has been attached to the behavior of consuming up the available naturalresources without considering the needs for minimizing or conserving extra consumption ofwater for socioeconomic livelihood. Consequently, the genetics’ diversities, species, andsustainable ecosystem have been under the outrageous threat. For a long time, the productionfunction of irrigated paddy fields have been maintained at the high level of productivity,which have also been conducted in complementary with the enhancement of ecology,environment and other external functions. Today, however, the external function of irrigatedpaddy field is regarded by many people as an intangible and less important, relative to theproduction functions. Therefore, external function of irrigation for public services, has onlybeen regarded as the secondary or even tertiary function, with subsequently addressed as thevery low development priority. In an attempt to preserve irrigated agricultural ecosystemtogether with the efforts to enhance conservation of bio-diversities, a number of endeavorscould be implemented. These among others are diversification of perennial plant varieties,with special scrutiny on the aggro-based environmental and hydro-based tourism industry.This arrangement could eventually attract domestic as well as foreign tourist to enjoy aggro-based recreation, water-based as well as bio-environment amenities, and other such leisureagriculture, as amongst the multifunctional and external functions of irrigated agriculture. Ingeneral, in environmentally friendly reservoir operation, the policy for operation ofmultipurpose reservoir is mostly geared toward the demands for fulfilling the water allocationas previously determined in the design, including the water supplies for irrigated agriculture,raw water for domestic and municipalities, industries and other such targets. Theconventional reservoir operations today, however, in most cases are not considering the waterallocation for maintaining the appropriate balance of water ecology and water forenvironmental sustainability. With the increasing concerns and problems associated withenvironmental impacts, the reservoir operation should also be adjusted in such a manner thatthe future reservoir operation has to incorporate the water allocation for maintaining theappropriate balance of water ecosystem, in particular, and environment in general. For futurereservoir operation, therefore, must strictly consider the multiple impacts of reservoiroperation. All the relevant parameters (tangible as well as the intangible one) should be takeninto consideration and incorporate them into the objective analysis. This aspect sounds,

I - 239

Page 240: Study of Social and Economic Impacts of Construction of ...

simple, but in reality it would become dilemma-tic challenges for future reservoir operators.This is particularly the case for reservoirs that had previously been designed and operated forsupporting the optimum internalize functions only, so that there is not much potential wateravailable for reservoir operation to meet the externalize functions.

3. CONCLUSION AND RECOMMENDATION

Regulate Saddang flooding is a problem for existing Saddang irrigation area in the rainyseason. Learning from the implementation experiences about the participation of the WaterUse Association in O&M system since HPSIS up to the WISMP and PISP except the WaterUse Association participation. The placement of CO, TPM have give much benefit becausethey work side by side with the farmers but the success of every places not the same, itdepends on the quality of CO/TPM and they personality, also the characteristic of thecommunity. In WISMP and PISP there is an increasing of the Water Use Associationparticipation, because they can do the construction work by direct pointed. It is recommendedthat to reach the target about the sustainable irrigation in the future, the farmers knowledgeabout agriculture and O&M system must be improve. . It is recommended that (1)empowering farmers or the Water Use Association must be done continual (2) The farmersmust be trainings on agriculture and irrigation system. (3) The recruitment of CO/TPM mustbe through a selection with certain criteria because they play an important role as themotivator and facilitator (4) The Saddang multipurpose dam must be constructed in upstreamof the existing Benteng barrage for anticipating the regulate flooding and for the irrigationdevelopment including the existing environmental protection.

ACKNOWLEDGEMENT

Thanks to committee of the 82nd ICOLD Annual Meeting and symposium to approve and letthis paper to be presented in the meeting for transferring and sharing the dams in globalenvironmental challenges knowledge among participants.

REFERENCES

A. Hafied A. Gany, (2007): Problems and Perspectives of Participatory IrrigationManagement Under The Small Land-Holding Condition: with a Special Reference toIndonesian Practice, ICID Publisher, Tehran, Iran

A. Hafied A. Gany, (2013): Potensial Impacts Mitigation and Adaptation of Climate Changeson Resources and Irrigated Agriculture in Indonesia, INACID-ICID Publisher, Jakarta,Indonesia

Anonym, (2012): No. 7 of 2004 Indonesia Law on Water Resources, DGWR Publisher,Jakarta, Indonesia

Armi Susandi, (2004): The Impact of International Greenhouse Gas Emissions Reduction onIndonesia, Max-Planck-Institut für Meteorologie Publisher, Hamburg, Deutschland

DGWR, Yayasan Air Adi Eka and JICA, (2013): River Management in Indonesia, DGWRPublisher, Jakarta, Indonesia

EV Arntzen, S Niehus, BL Miller, M. Richmond and AC. O. Toole, (2013); EvaluatingGreenhouse Gas Emissions from Hydropower Complexes on Large Rivers in EasternWashington, Elsevier International Journal Publisher, San Diego, CA 92101, USA

Nippon Koei Co., Ltd in associated with Local Consultant, (1999): Consulting EngineeringServices for Decentralized Irrigation System Improvement Project in Eastern Region ofIndonesia Phase II (DISIMP II), Nippon Koei Publisher, Makassar, Indonesia

I - 240

Page 241: Study of Social and Economic Impacts of Construction of ...

Philip H. Brown, Desiree Tullos, Bryan Tilt, Darrin Magee and Aaron T. Wolf, (2008):Modeling the costs and benefits of dam construction from a multidisciplinaryperspective, Elsevier International Journal Publisher, San Diego, USA

I - 241

Page 242: Study of Social and Economic Impacts of Construction of ...

INTERNATIONAL SYMPOSIUM ON

Bali, Indonesia, June 1ST

– 6TH

, 2014

ENVIRONMENTAL MANAGEMENT hhdTTjjhkljdjjsgshjhfsdkjhskslsl;s;s;;s;;s;;sjsjkjffffrtttttttfggjfgjgkfkjkjf fffffjfjjfkkfjjj ON THE PRE-CONSTRUCTION STAGE OF UCPS HEPP DEVELOPMENT

2(14pt)

[Blank line 11 pt]

T. Indora, A. Heryana & A. Nugroho PT PLN (Persero)UIP VI , Bandung, Indonesia

[email protected]

[Blank line 10 pt]

[Blank line 10 pt]

[Blank line 10 pt]

ABSTRACT: Based on RUPTL 2012-2021, stated that PLN will prioritize the development of geothermal and

hydropower. These two types of energy can go into the power system whenever they are ready,

even though still must consider the power demand and the plan of another power plant

development. In the RUPTL 2012-2021 also mentioned that if there is a potential, PLN prefer the

power generation using hydro energy, such as pumped storage, peaking hydroelectric power plant

with the reservoir. Hydro energy potential as a renewable energy in Indonesia is quite high. One of

hydroelectric power plant that will be built by PLN is Upper Cisokan Pumped Storage

hydroelectric power plant (UCPS HEPP) which has a power of 1040 MW (4 x 260 MW). UCPS

HEPP will use two dams, Upper Dam and Lower Dam. The land area that must be acquired is

covering 765 Ha, consisting of citizen lands and forest lands. UCPS HEPP development will use

government loans from the World Bank (World Bank). The World Bank pays close attention for the

impact that will arise from projects which use their loans. This paper will discuss generally about

environmental management related to UCPS HEPP development plan on pre-construction stage,

both from the Indonesian government and the World Bank, which is contained in the EIA, Land

Acquisition and Resettlement Plan (LARAP) and Environmental Management Plan (EMP).

Keyword: HEPP, Upper Cisokan Pumped Storage, EIA, LARAP, EMP

1. INTRODUCTION

Electrical energy demand in Indonesia will increase along with the increasing of

population and economic development. Based on the Power Supply Business Plan 2012-

2021, with projected population growth by an average of 1.6 to 1.7% and an average

economic growth of 6.9%, the projected electricity needs in 2021 amounted to 358, 3 TWh

(see Table 1.).

Electrical energy demand is not proportional to the availability of primary energy,

particularly derived from fossil. Meanwhile the primary energy from non-fossil has not

been fully utilized. Unconformity between the need and availability of the energy can pose

a threat the energy crises. Therefore, the government will not allow anymore power plant

development that would use fuel oil in its operations.

According to the Minister of Economy, Hatta Rajasa, in order to conserve the use of fuel in

this country, power plants must be built using the potential that exists in the area of

development. Minister of Energy and Mineral Resources, Jero Wacik, has four ways to

overcome the problem of energy in Indonesia. One way is to encourage the massive

I - 242

Page 243: Study of Social and Economic Impacts of Construction of ...

development of new and renewable energies. Among them are geothermal (30.000 MW),

hydropower (75.000 MW) and solar energy (50.000 MW).

Hydropower potential in Indonesia according to Hydro Power Potential Study (HPPS) in

1983 was 75.000 MW, and the figure is repeated again on the Hydro Power Inventory

Study in 1993. However on the report Master Plan Study for Hydro Power Development in

Indonesia by Nippon Koei in 2011, hydropower potential after further screening was

26.321 MW, consisting of projects that have been operating (4.338 MW), projects that

have been planned and are being constructed (5.956 MW) and new potential (16.027 MW).

Based on RUPTL 2012-2021, stated that PLN will prioritize the development of

geothermal and hydropower. These two types of energy can go into the power system

whenever they are ready, even though still must consider the power demand and the plan

of another power plant development. In the RUPTL 2012-2021 also mentioned that if there

is a potential, PLN prefer the power generation using hydro energy, such as pumped

storage, peaking hydroelectric power plant with the reservoir.

Table 1. Estimated Electrical Energy Demand and Electrification Ratio Growth Rates

2. UCPS HEPP

Upper Cisokan Pumped Storage Hydroelectric Power Plant (UCPS HEPP) will be

established with the main objective to improve the reliability of the electrical system of the

Java-Bali and bears peak loads. UCPS HEPP will utilize the hydropower potential of

Cisokan River and other nearby river flow located on the Sub Watershed of Cisokan

upstream areas. UCPS HEPP will be constructed in the geographic area of West Bandung

Regency and Cianjur Regency, West Java Province.

UCPS HEPP is designed using pumped storage system which is a system that is the first

and largest HEPP in Indonesia. UCPS HEPP will use two reservoirs, upper reservoir which

has the highest water level around 796.5 masl, will be made by stemming the Cirumanis

River (a tributary of Cisokan) and will be a puddle of ± 80 Ha, meanwhile the downstream

I - 243

Page 244: Study of Social and Economic Impacts of Construction of ...

reservoir (lower reservoir) which has the highest water level around 499,5 masl, will be

created by stemming the Cisokan River and will be a puddle of ± 260 Ha.

At peak load, the water will flow from the upper reservoir to the lower reservoir to

generate electricity of 1.040 MW. While at base load, then the water will be pumped from

the lower reservoir to the upper reservoir. The advantages to be gained from this

hydropower system is the revenue while generating electrical energy (when electricity

rates are high due to in the peak load time) after reduced by the cost to pump water from

the lower reservoir to the upper reservoir (when electricity rates are lower due to in the

base load time) and also reduced by other operating expenses.

Figure 1. Upper Reservoir and Lower Reservoir of UCPS HEPP

One of the advantages of UCPS HEPP is a necessity of smaller puddle than Saguling

HEPP or Cirata HEPP (see Table 2.).

Table 2. Comparison of Hydropower and Land Area

PT PLN (Persero) Unit Induk Pembangunan VI (PLN UIP VI) is given the task to control

the UCPS HEPP construction.

3. ENVIRONMENTAL CHALLENGES

Each power plant development will have an impact on the environment. PLN has a

challenge to be able to control even minimize the impact that will result from development

the power plant. UCPS HEPP development is in an area that has great potential impacts on

the environment, consisting of the changes in Geology-Physics, Biology and Social-

Economic-Culture. Since the funding for UCPS HEPP development comes from the loan

No. HEPP

Installed

Capacity

[MW]

Area of

Reservoir

[Ha]

Catchment

Capacity of Water

[million m3]

1 Saguling 700 5,600 614

2 Cirata 1,000 6,300 704

3 UCPS 1,040 340 79

I - 244

Page 245: Study of Social and Economic Impacts of Construction of ...

of World Bank, the concern about the environment is given by the Government of

Indonesia as well as by the World Bank. The World Bank pays close attention for the

impact that will arise from projects which use their loans. The World Bank has a policy to

support projects that will result in significant environmental degradation. Considering the

environmental problems due to development UCPS HEPP is very broad, then in this paper

will be presented a general overview of the challenges related to environmental

requirements in the pre-construction phase of UCPS HEPP development as follows:

3.1. EIA

In preparation for the construction of UCPS HEPP, PLN has conducted EIA studies in

2007, which was fitted with a study for the construction of 500 kV SUTET (2008) and

Acess Road development, Quarry and Fly Ash (2011). The challenges contained in the

EIA documents in the pre-construction phase, as shown in Table 3. below:

Table 3. Large and Important Impact On Pre-Construction Phase

3.2. Land Acquisition and Resettlement Action Plan (LARAP)

The purpose of the preparation of the Land Acquisition and Resettlement Action Plan

(LARAP) of the Upper Cisokan Pumped Storage HEPP is to prepare a report relating to

land acquisition and resettlement for people who their land will be used by PLN (Persero)

in the project planning and decision-making as a tool for the prospective donor. The

objective as follows:

1. To mitigate negative impacts of land acquisition activities, as a result the Project

Affected People (PAP) will not decrease the level of their life.

2. To give opportunity to the PAP to participate in the development process.

3. To obtain accurate data about the PAP and other data in accordance with the guidelines

applied in Indonesia and guidance of the prospective donors (World Bank), as

consideration for the implementation of LARAP.

4. To disseminate LARAP to the public associated with the transfer of assets, with the

aim to obtain the same perceptions and early get feedback from the PAP.

5. To develop guidance / general propose of the resettlement plan for displaced PAP.

6. To provide grievance redress mechanism and monitoring and evaluation procedure of

the LARAP implementation.

7. To formulate policies on complying the needs between GOI’s regulation and the World

Bank.

No. Activity

1. 1. Social unrest ofthe Project Affected People due to the administrative

requirements of land rights on the land acquisition process + the emergence of

land speculators.

2. Social unrest of the land owners due to the compensation that does not comply

with community expectations.

3. Social unrest of cultivators of land (landless) because it does not have the land to

stay or to earn a living.

4. Reduction in land ownership lead to reduction in revenue.

2. 1. Social unrest in the plans area of inundation because of concerns about

resettlement and life in a new place.

2. Social unrest in the resettlement plan (the recipient resident).

Big and Important Impact

Land Acquisition

Resettlement

I - 245

Page 246: Study of Social and Economic Impacts of Construction of ...

From the results of the LARAP there are some important things that need to be followed

up, as follows:

1. Community Response to Resettlement Plan

2. Formation of Land Acquisition Committee (LAC/P2T)

3. Formation of Independent Appraisal Agency licensed of the National Land Agency

(BPN)

4. Formation of Resettlement Policy Formulating Team (RPFT) and Resettlement

Implementing Team (RIT)

5. Formation of Grievances Task Force

6. Formation of Independent Monitoring Agency

7. Report Submission of Involved Institution

3.3 Environmental Management Plan (EMP)

UCPS HEPP has a comprehensive scheme of environmental management plan set out in

the Environmental Management Plan (EMP). This Environmental Management Plan

(EMP) identifies methods for PT PLN (Persero) to control and/or minimize the

environmental and social impacts of construction and operational activities associated with

the 1.040 MW Upper Cisokan Pumped Storage Hydro Electric Power Plant and 500 kV

Transmission Line. Implementation of this EMP will ensure that PLN, its contractors,

consultants, and subsidiary companies undertake construction and operation of the Scheme

with due regard to protecting and providing for the natural and social environment.

Social and environmental aspects that were identified in EMP studies that must be

completed in the pre-construction phase are as follows:

1. Permitting

2. Land Acquisition

3. Resettlement Plan

These three things mentioned above will be studied more deeply in a separate document

which is LARAP.

In addition, there are several things that must be prepared before the pre-construction work

begins, as follows:

1. Construction and Workers’ Camp Management Plan

2. Reservoir Land Clearance Management Plan

3. Social and Community Management Plan

4. Physical Cultural Resources Management Plan

5. Biodiversity Management Plan

6. Access Road Construction Environmental Management Plan

7. Transmission Line Environmental Management Plan

8. Quarry Environmental Management Plan

9. Operational Environmental Management Plan

a. Social and Community Relations Plan

b. Biodiversity Management Plan

c. Dams and Reservoir Management Plan

d. Watershed Management Plan

I - 246

Page 247: Study of Social and Economic Impacts of Construction of ...

4. ACTION PLAN

4.1 EIA

Based on the Environmental Management Plan, PLN got a mandate to do things as listed in

Table 4.

Table 4. Environmental Management Plan

4.2 LARAP

4.2.1 Community response to resettlement plan

PLN pays attention to the response arising from the Project Affected People to their

resettlement plan. There are two categories of responses that arise. The first category is

Project Affected People who want their resettlement managed by PLN, and the second

category is Project Affected People who want to move on their own volition.

Steps need to be taken:

A. Resettlement site managed by the government/project

1. PLN propose a permit to the District of Bandung Barat and Province of West Java to

use Kampung Munjul, Bojong village, Rongga sub-district, West Bandung district,

Kampung Pasir Taritih, Margaluyu village, Cibeber sub-district, Cianjur district; and

Kampung Nagrak, Giri Mulya village, Cibeber sub-district, Cianjur district.,as a

proposed resettlement site.

2. After the government permit has been granted, PLN conduct a feasibility study and

environmental carrying capacity for those two resettlement sites.

3. Site visit and consultation regarding location and perception of the PAPs.

4. Decision of resettlement site based on study result.

5. Consultation with PAPs on early design on resettlement plan and associated economic

measures based on local characteristics.

No. Activity

1. 1. The initiator, through the Land Acquisition Team conduct socialization in

cooperation with relevant agencies and involve community leaders, and all

stakeholders.

2. The initiator conduct meetings with the community to be affected by the project,

to discuss issues related to determining the amount of compensation and to

provide education on the use of cash compensation and compensation for useful

purposes.

3. Land acquisition system and the amount of compensation should be guided by

the applicable laws and regulations.

4. Especially for the landless will be handled refer to the Implementation

Procedures of the World Bank OP 4.12 on involuntary resettlement.

2. 1. The initiator conduct deliberation with the communities that will be moved as

well as receiving communities to talk about resident displacement plans.

2. The initiator provide training to the people who will be moved primarily related

to new business which could be developed at the site of the new settlement.

Resettlement

Environmental Management Plan

Land Acquisition

I - 247

Page 248: Study of Social and Economic Impacts of Construction of ...

6. Design and physical construction of resettlement including other facilities required by

the PAPs

7. Relocation of the PAPs to the resettlement site.

8. Monitoring and “treatment” to new settlers, covering socio-psychological aspects, and

economic development.

B. Resettlement on their own

1. The government should provide the PAPs with information on the development plan of

the sites that desired by the PAPs (in the surrounding project area).

2. Guiding and giving assistance to the PAPs who want to move out on their own with

small scale economic development.

3. The PAPs who want to move out by group (minimal 30 households) will be provided

with facilities such as road, drainage, and other necessary public facilities supported

financially by the PLN. To realize this promise, the PLN will establish a resettlement

unit with close working coordination with the resettlement implementing team.

4. Monitoring on economic development.

4.2.2 Formation of Land Acquisition Committee (P2T/LAC)

PLN will hand over the responsibility to the Government of West Java Province to

establish and set the Land Acquisition Committee (LAC) in West Java province, and at the

level of West Bandung Regency and Cianjur Regency. Aside from the LAC, Joint Team of

Local Government and PLN for Non Title Holders will do tasks to comply with the World

Bank OP 4.12. Joint Team will inventory personal investment of non title holders who may

have asset in the form of physical structures or agricultural crops.

4.2.3 Formation of Independent Appraisal Agency licensed of the National Land Agency

(BPN)

Land Price Appraisal Institution (licensed by BPN) is appointed to conduct the assessment

of land prices in this project. The independent appraisal consultants will determine

eligibility by following the LARAP criteria, of non title holders who may have asset in the

form of physical structures or agricultural crop of personal investment and appraising their

asset values. They will also assess the assistance eligibility for them.

4.2.4 Formation of Resettlement Policy Formulating Team (RPFT) and Resettlement

Implementing Team (RIT)

Resettlement Policy Formulating Team is an institution, which review resettlement

formula produced by consultants of LARAP to appropriate local government policy. The

resettlement Implementation Team will coordinate all resettlement implementation activities, including through setting up assistance and restoration of social and economic

life/income of PAP after developing project.

4.2.5 Formation of Grievances Task Force

The Task Force consists of PLN Officers and the hired experts. It has two main tasks

namely the first as an accompaniment to the people or PAP during this project; and the

second to accommodate and facilitate the public grievances related to the implementation

of this project.

4.2.6 Formation of Independent Monitoring Agency

I - 248

Page 249: Study of Social and Economic Impacts of Construction of ...

This team has function to monitor and directly serves as the implementing agencies and

monitors the impact evaluation of the overall project implementation.

4.3 EMP

EMP is a living document. Thus, all the information in the EMP must be kept up to date on

environmental management and monitoring plan which are considered no longer in line

with the original plan. Moreover PLN need to rearrange a more implementable plan if the

management plan listed in the EMP is still a general guideline.

In outline Biodiversity Management Plan has been prepared and become one of the sub-

plans under the EMP. Biodiversity management plan requires more effort to be completed

and be implemented before construction activities begin.

BMP should provide clear guidance on how to protect and restore the habitat at the project

site, as well as protecting and managing endangered species. It is expected that

implementation of BMPs through an adaptive approach. This requires periodic monitoring

of implementation, and plans which are flexible to allow for changes in the approach

(depending on the implementation and problems in the field)

5. CONCLUSION

From the above discussion there are several conclusions as follows:

1. Environmental management in relation to the construction of a hydropower plant that

uses the World Bank funds are complex activities involving many parties.

2. The results of LARAP are details of social aspect management efforts which are not

studied exhaustively in the EIA.

3. EMP document is a guide for PLN, Supervision Consultants and Contractors in

carrying out the construction and operation of UCPS HEPP. Some parts of the EMP

document must be rearranged to obtain more implementable plans.

REFERENCES

Rencana Usaha Penyediaan Tenaga Listrik PT PLN (Persero) 2012 – 2021.

Plasadana-Content Slution Agency. (2012): Pembangkit Berbahan Bakar Minyak, Sampai

Di sini, http://plasadana.com/content.php?id=1386

Kompas.com. (2013): Empat Cara Atasi Krisis Energi ala Jero Wacik.

http://bisniskeuangan.kompas.com/read/2013/10/21/1256087/Empat.Cara.Atasi.Krisis.

Energi.ala.Jero.Wacik.

PT PLN (Persero) Proyek Induk Pembangkit dan Jaringan Jawa, Bali dan Nusa Tenggara-

Proyek Pembangkit dan Jaringan Jawa Barat. (2007): Rencana Pengelolaan

Lingkungan PLTA Cisokan Hulu (Pumped Storage), Bandung, Indonesia.

PT PLN (Persero) and LPPM Unpad. (2011): Laporan Akhir LARAP Upper Cisokan Pump

Storage, Bandung, Indonesia.

PT PLN (Persero). (2011): Final Environmental Management Plan Upper Cisokan

Pumped Storage Hidro Power Scheme, Bandung, Indonesia.

I - 249


Recommended