+ All Categories
Home > Documents > Substation and supporting transmission infrastructure ... · MAP LEGEND 2014–2019 PLAN. ......

Substation and supporting transmission infrastructure ... · MAP LEGEND 2014–2019 PLAN. ......

Date post: 25-Jul-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
3
7701 S Stemmons, Corinth, TX 76210-1842 (940) 321-7800 [email protected] MAP LEGEND 2014–2019 PLAN Substation needed to serve future significant demand generated by commercial development attracted to the area along the Sam Rayburn Tollway/SH 121 corridor. Substation and transmission needed to serve growing residential and commercial load in west Frisco and to prevent overload on existing inline substations in that area. Substation and supporting transmission infrastructure needed to serve growing load north of the U.S. Highway 380 corridor. Substation and possible transmission infrastructure needed to serve growing communities with large homes and retail development in Collin County. Substation and transmission need identified for growth in Flower Mound, Bartonville and Double Oak and to prevent overload of existing substations in those areas. Substation and potential transmission infrastructure needed to serve the growing communities of Oak Point, Little Elm, and Lakewood Village pocketed inside the northern fingers of Lewisville Lake. Substation and potential transmission needed to serve the fast-growing residential and commercial development along the SH 121 corridor in this part of Collin County. Substation and potential transmission expansion needed to serve planned residential community development near Northlake, Argyle and south Denton. 1 2 3 4 5 6 7 8 3 1 2 4 5 6 7 8 Substation / transmission infrastructure project coming soon. GROWTH AREA 3 GROWING WITH YOU, PLANNING FOR YOU COSERV MEMBERS Published: 09-2014
Transcript
Page 1: Substation and supporting transmission infrastructure ... · MAP LEGEND 2014–2019 PLAN. ... (CCN). A CCN outlines attributes of the line, proposes ... 45 day process. 80 day process

7701 S Stemmons, Corinth, TX 76210-1842(940) 321-7800 [email protected]

MAP LEGEND 2014–2019 PLAN

Substation needed to serve future significant demand generated by commercial development attracted to the area along the Sam Rayburn Tollway/SH 121 corridor.

Substation and transmission needed to serve growing residential and commercial load in west Frisco and to prevent overload on existing inline substations in that area.

Substation and supporting transmission infrastructure needed to serve growing load north of the U.S. Highway 380 corridor.

Substation and possible transmission infrastructure needed to serve growing communities with large homes and retail development in Collin County.

Substation and transmission need identified for growth in Flower Mound, Bartonville and Double Oak and to prevent overload of existing substations in those areas.

Substation and potential transmission infrastructure needed to serve the growing communities of Oak Point, Little Elm, and Lakewood Village pocketed inside the northern fingers of Lewisville Lake.

Substation and potential transmission needed to serve the fast-growing residential and commercial development along the SH 121 corridor in this part of Collin County.

Substation and potential transmission expansion needed to serve planned residential community development near Northlake, Argyle and south Denton.

1

2

34

5

6

7

8

3

1

2

4

5

678

3

1

2

4

5

678

Substation / transmission infrastructure project

coming soon.

GROWTH AREA 3

GROWING WITH YOU,PLANNING FOR YOUCOSERV MEMBERS

Published: 09-2014

Page 2: Substation and supporting transmission infrastructure ... · MAP LEGEND 2014–2019 PLAN. ... (CCN). A CCN outlines attributes of the line, proposes ... 45 day process. 80 day process

»What is CoServ’s relationship to Brazos Electric? CoServ is a not-for-profit electric distribution cooperative. As one of the 16 members of Brazos Electric Cooperative, CoServ depends on Brazos to provide bulk power to the area. CoServ serves the end-use consumers. CoServ purchases electricity from Brazos Electric, which transmits power from generation plants to substations. At substations, CoServ distribution lines pick up electricity and distribute it to homes and businesses.

»Why is new electric infrastructure needed? CoServ delivers power to more than 180,000 homes and businesses. Just 12 years ago, our utility served 65,000 meters using 16 substations. This averages out to 4,000 meters served per substation. Today, the company serves 183,000 meters using 27 substations. This averages out to more than 6,300 meters per substation. Our service territory covers the same physical area, but the infrastructure needs to keep pace with the tremendous growth in residential and commercial development. Systemwide, meters served per average substation has grown by about 57 percent. Infrastructure must grow to keep up with population growth. Over the past decade, the North Texas population has increased by more than 1 million people, with increases of 74 percent in Collin County and 68 percent in Denton County. More residents and businesses result in a greater demand for energy, which requires new electric infrastructure. The need is undeniable.

CoServ’s mission is to provide safe, reliable energy solutions. The circles on the front cover designate areas where CoServ has forecasted the need for new substations to serve significant residential and business development. Note that Growth Area 3 is in the initial stage of a proposed substation project involving our wholesale power provider, Brazos Electric Cooperative.

When CoServ identifies a new substation need, we look to Brazos to determine potential substation sites and assess potential power transmission requirements. Brazos is required to follow the Public Utility Commission (PUC) process for proposing projects by applying for a Certificate of Convenience and Necessity (CCN). A CCN outlines attributes of the line, proposes potential routes, describes the need and identifies potential impacts on the surrounding community and environment. The PUC ultimately determines and orders the substation location and transmission line route. (Open to the inside of this brochure for a diagram of the CCN process.)

Before filing a CCN application, Brazos is required to conduct civic and public meetings and notify affected property owners along proposed routes and substation sites. This process will begin in September for affected landowners in Growth Area 3 who will have ample opportunity to participate in the CCN process and express their views to the PUC. Visit CoServ.com and click on the growth map for more details.

Rendition of proposed transmission line

Example of a substation

KEY TERMS » PUC Public Utility Commission of Texas

» CCN Certificate of Convenience and Necessity

» Transmission High voltage transfer of electricity from power plants to substations

» Substation Infrastructure that reduces voltage as it passes from transmission to distribution

»Distribution Medium voltage delivery of electricity to end users

Page 3: Substation and supporting transmission infrastructure ... · MAP LEGEND 2014–2019 PLAN. ... (CCN). A CCN outlines attributes of the line, proposes ... 45 day process. 80 day process

PUC Process for New Transmission FacilitiesPlanning/need for project

Routing Study and Environmental Assessment

Public Utility Commission (PUC) Processing

Uncontested CCNAdministrative Processing = 80 days

Intervention?

Yes

No

Delineate Study Area

Submit complete assessment

CCN Filing

Intervention Period

Provide NoticeDirect Mail / Public / City and CountyGovernment Agencies / Other Utilities

PUC Review / Recommendation

Staff Recommendation

Issues Resolution

Collect and review environmental / historical / archaeological data

Constraints and preliminary routes

Civic / public information meetings

Evaluate preferred / alternative routes

12 month process

CCN(Certificate of Convenience

and Necessity)Application Preparation

2 month process

45 day process

80 day process

Contested CCNERCOT Critical = 180 day process

All Other = 1 year processAdministrative Law Judge

Prepares Proposed Final Order

Exceptions and responses to proposed order

Approval

Project Completion

Motion for Rehearing Appeal of PUC Decision

Travis County District Court

Denial

Referred to State Office of Administrative Hearings (SOAH)

Prehearing conference(s)

Discovery

Pre-filed Testimony

Hearing on the Merits

Briefing

Proposal for Decision

12 month process

Surveying

Right-of-Way

Acquisition Permitting

Project Design Material

Acquisition Construction

Clearing

Soil Investigation

Structures

Conductor Installation

Clean-up

12–24 month process

KeyPlanning Phase

Routing and Environmental Assessment Phase

Application Phase

Regulatory Phase

Construction Phase

Project Completion

*Time frames typical of PUC process.

PUC Decision

Whole / Partial Grant / Denial

Published: 09-2014

WEARE

HERE


Recommended