Date post: | 25-Oct-2015 |
Category: |
Documents |
Upload: | kadir-gonzalez |
View: | 53 times |
Download: | 6 times |
07/07/2013
1
Substation Design can be broken down Substation Design can be broken down
into the following partsinto the following parts
� Planning
� Engineering
� Construction
� Operation
Substation Design is not independent Substation Design is not independent
from the rest of the T & D systemfrom the rest of the T & D system
� Has to interface with the transmission
system power levels and voltage
� Has to be compatible with the distribution
equipment and design philosophy.
PlanningPlanning
� Perhaps the most critical as it will determine
need, location, how it is connected to the
distribution and transmission system, etc.
� Let’s look at the planning steps
PlanningPlanning--GeneralGeneral
� General planning Philosophy
Substation Voltage Range
MVA
Location How many square miles per substation
Indoor or out door
Insulation type Air, SF6
SCADA Controlled
Reliability expected/ what types of customers will it serve
Economics- How much is a customer willing to pay for his electric?
Substation VoltageSubstation Voltage
� Usually determined already. From past history
and now what voltages are available.
� Usually these voltages are transmission type
voltages: 115,138,230,345,500,765kV etc.
� Or Subtransmission type voltages
23,25,34.5,46,69kV etc.
� Distribution voltages 4, 12.47,13.8,23,25,34.5kV
Substation SizeSubstation Size
� How big is your standard design going to
be. I.E. how much load do you want to
serve off of this substation. Will it be
10MVA, 20MVA, 30MVA, 40MVA etc.
� This will depend on the area to be served
and the type of customers to be served, and
reliability you want to achieve
07/07/2013
2
Indoor/ Outdoor,Air, SFIndoor/ Outdoor,Air, SF66
� Space requirements will generally
determine this. If space is small and the
location is in an urban area then you may
want to consider an indoor design possibly
using SF6.
� If space or location is not a concern then
most probably an outdoor air substation is
the most economical
SCADASCADA
� Is SCADA required? Many substation do
not have SCADA and many do. It depends
on what level reliability is expected of the
substation.
Reliability and EconomicsReliability and Economics� Probably the most concern in today’s society that depends almost
entirely of having electrical service.
� Everyone wants 100% continuous service, but are they willing to pay for it.
� You hear about 9 nines of reliability or they want electric service 99.9999999% of the time or want it off only about .000000001 or 1.9 cycles/year
� Typically we can give about 99.95% or about 5 hours that the electric is off per year. This would be composed of about 2 to 3 outages per year lasting longer than 1 minute. About 30 momentary interruptions lasting about 2 seconds each and about 150 to 200 voltage sags less than 90% voltage per year of which 60 are less than 80% voltage per year. This is per an EPRI study. And is an average.
� But the cost for this service is about $0.07/kWH. If we double the rate to $0.14/kWH we can increase reliability to about 99.97% generally so is the customer willing to pay for that increase?
� Pretty much our designs have evolved to the reliability we have based on what the customer is willing to pay.
Planning Planning --High SideHigh Side
� High Side Configuration
� Breakers or Airswitch types of Design
� Loop or Radial
� Protection and Relaying
� Reliability
� Loading
� Fault Current
� Maintenance
High Side PlanningHigh Side Planning
� Since the substation will be serving a lot of
distribution circuits an outage of the substation
will affect a lot of customers. Therefore you will
have to decide how to feed the substation to
provide the most reliability at the most economical
cost. Usually this means a looped line. Also can
an air switch be used to provide protection of the
substation instead of a circuit breaker?
07/07/2013
3
Example of a Radial Substation design
Example of a looped design
We also try to be economical We also try to be economical
with looped lines with looped lines
� Breakers are expensive, but they are the
only thing that can interrupt fault currents
switch can not. Switches can only be
opened when the line is de energized.
� But switches are cheaper than breakers, so
we have devised a way in which we can use
switches on our looped lines to save money
A B C
12X Y
For a fault breaker 1 and breaker 2 clear. During the time the line is
de energized switch X and Y open. Breakers 1 and 2 close. If the
fault is still there Breaker 1 opens and stays open. Switch Y detects
voltage so it closes. Substation B is restored.
This is called a Sectionalizing Station
XFault
A B C
12X Y
XFault
In this station design Switch X is closed and switch Y is open under normal
conditions. For a fault between switch X and Breaker 1. Breaker 1 opens Breaker 1
may try to close to see if the fault is still there if so it will open and stay open then
Switch X opens as the line is de energized and Switch Y closes restoring restoring
substation B
This is called a Transfer Station
� We use only sectionalizing stations on the
transmission system
� We use both sectionalizing and transfer stations on
the Sub transmission system as a transfer station is
cheaper. Substation C is less reliable as it has
only one feed in a transfer scheme.
� Transmission system looped lines are also more
reliable as they have overhead shield wires above
the phase wires which intercept lightning strokes.
07/07/2013
4
Planning Planning --TransformerTransformer
� Transformer bank configuration
3 single Phase or 1 three phase
High side connection (Delta or Wye)
Low side Connection (Delta or Wye)
Ratings (OA, FA, FA)
Voltage regulation
Fault Current
Protection
Maintenance
PlanningPlanning-- Low SideLow Side
�Low Side Configuration
�Breakers or Recloser
�Loop or Radial
�Protection and Relaying
�Reliability
�Loading
�Fault Current
�Maintenance
Need StandardsNeed Standards
� To have cost effective designs there needs to be a standard configuration that is done for every substation.
� For this to happen you need to have Standards.
A. Engineering Standards
B. Construction Standards
C. Material Specification
D. Operation and Maintenance Standards
E. Control Standards
Conductor
a. Calculating impedance
b. Ampacity
c. Underground type
d. Fault current calculations
e. Connected kVA
f. Voltage
Transformers
a. 2 bushings
b. 1 bushing
c. 1 phase & 3 phase
d. Polarity
e. Delta vs Wye
Standards need to include
f. Construction
g. Tank Heating
h. Ferro resonance
I. Grounding banks
J. Ungrounded Wye problems
k. Different types of connections and the
advantages/disadvantages of each
l. Economic evaluations
m. Standards
Voltage regulators and LTC.
a. Vars and Power equations
b. Vector diagrams
c. Regulator construction
d. Regulator connections
e. Line drop compensation
f. Loss evaluation
g. Standards
07/07/2013
5
Capacitors
a. Construction
b. Where to put
c. Current limiting fuses
d. Capacitor switching
e. Back to back capacitor switching
f. Loss evaluation
g. Series capacitors
Circuit protection
a. Breakers versus reclosers
b. Construction
c. Fault current calculations
d. Minimum fault currents
e. Overloads
f. Fuses
g. Inrush
h. Asymmetry and X/R
I. Standards
Over voltage protection
a. Sizing arresters
b. Insulation Coordination
c. Separation distance
d. Arrester connections
e. Arresters for PQ
f. Shielding of wires
g. Mechanism of lightning
Power quality and the distribution line
a. PQ disturbance categories
b. Harmonics
c. Cause of sags
d. Motor drives and customer equipment
e. Grounding
Distributed generation
So now you want to build a So now you want to build a
Substation Substation
� Need a plan
� Need a Single Line
� Need a Three Line
� Need Construction Prints
Deliver power to customersDeliver power to customers
� Many customers
� At their locations
� On Demand
� Ready to use
� High Reliability
� Stable Voltage
07/07/2013
6
On Demand and ready to useOn Demand and ready to use
� Must provide power at the instant of
demand—Can’t wait Can’t average
� Power must be provided at Utilization
voltage
- Usually 120V nominal in the United
States. Between 220 and 250 in most other
countries.
High Reliability, low voltage High Reliability, low voltage
fluctuationfluctuation� Incredible availability expectation
� Nine nines of availability required in some industries or about 1 cycle per year. We in the US average about 99.9% or about 9 hours per year.
� Stable voltage
-Power Quality anomalies are unacceptable
-Voltage flicker unacceptable
Therefore the mission of Therefore the mission of
Transmission and Distribution Transmission and Distribution
is tois to� Get electrical energy to the customer
� Have capacity to meet the instantaneous
demand
� Availability somewhere between 4 and 9
nines.
� Voltage regulation to between 3%
� And do it at the lowest possible cost!!
Some laws of T&DSome laws of T&D
� Power is most economically produced at central stations
� Power must be distributed to many small loads.
� Utilization voltage is worthless for moving power
� It is more economical to move power at high voltage
� High voltage equipment has a greater cost but much greater capacity.
� It is costly to change voltage levels
Power is most economically Power is most economically
produced at large central stations:produced at large central stations:
� Despite all the hype about “dispersed generation” a
tremendous economy of scale still exists in favor of large
generation.
� DG is popular because
- there is a fringe always ready to welcome a new idea.
- DG has some merit: close to the customer. It has to beat
only the efficiency of generation/TD combination.
- Small hi tech generators(45% efficient) can easily beat
older central generation stations(35% efficient)
� Large hi tech generators(52% efficient) can
still beat everything else, even when T&D
costs are added.
� But utilities are stuck with “sunk costs” of
older units.
07/07/2013
7
Power must be distributed to Power must be distributed to
many small load points.many small load points.
� At Allegheny Energy we have about 1.5
million electrical customers and an average
peak load of about 8kW
� We have a generation capacity of about
12000MW
Utilization Voltage is worthless Utilization Voltage is worthless
for moving power any distancefor moving power any distance
� 120-250 volt single phase can move power
only a few hundred meters before conductor
and loss cost, and voltage drop becomes
unacceptable.
� European systems with 416V(p-p)
secondaries, are another matter. Here the
secondary basically replaces the single
phase laterals in American systems.
It is more economical to move It is more economical to move
power at high voltage.power at high voltage.
� The higher the voltage the lower the cost
per kilowatt-mile.
� However, higher voltage equipment has
greater minimum costs and greater
minimum capacity. Therefore you must
arrange for that kilowatt to be part of a large
amount of power being moved as one block.
It is costly to change voltage It is costly to change voltage
levelslevels
� “Transformation” accomplishes nothing in
moving power
� It can be afforded, but increases costs.
� Its purpose is to permit splitting power more
economically.
Lower voltage and split Lower voltage and split
path.The fundamental rule of path.The fundamental rule of
power system layoutpower system layout� Every time voltage is reduced the pathway
is split.
� Idea is to keep splitting power into smaller
and smaller units as it is moved nearer the
customer, all the while keeping it at a
voltage level that is most economical for
that amount of power being moved.
� The way it has happened over the years is
that you started at utilization voltage then
you started to have problems as the lines
became longer so you looked at the cost of
building another generator verses raising the
voltage and the economics associated with
that.
07/07/2013
8
This structure gives rise to This structure gives rise to
T&D levelsT&D levels� Levels are:
- High voltage grid(transmission)
-Switching stations
-Subtransmission
-Substations
-Primary Feeder
-service transformers
-Secondary circuits
Levels of T&D systemsLevels of T&D systems
� Each covers the entire system
� Each is indispensable in service
� Each has more units than the level above it.
� On average, units of lower capacity than the level
above it
� A total capacity greater than the level above it.
� Each level divides the system into “service areas”
Reliability problems are Reliability problems are
usually on the distribution usually on the distribution
systemsystem
Distinguishing between Distinguishing between
Transmission and DistributionTransmission and Distribution� By voltage class- Transmission is above 34kV,
distribution is below it(Niagara Mohawk)
� Transmission is above 69kV(Allegheny power)
� By function: Distribution is anything feeding service transformers(Central Maine Power)
� By configuration: transmission is a network distribution is radial(Houston Light and Power)
� By purpose: Transmission is everything built at least partly for stability and operating requirements, distribution is everything built solely to distribute power to customers(ABB)
Distribution system Distribution system
componentscomponents� Transmission
� Subtransmission
� Distribution Substations
� Primary feeders
� Laterals and Branches
� Service transformers
� Secondary circuits
� Service drops
Transmission levelsTransmission levels
1.1MV 1.1MV –– 115kV115kV
� A network- many paths between any two
points
� Provides voltage stability, and dispatch
ability functions, as well as power delivery
� Power from any generator can be moved
anywhere.
07/07/2013
9
Subtransmission 23kV to Subtransmission 23kV to
230kV230kV
� Transmission level equipment that exists
solely to route power to distribution
substations.
� Occasionally radial, and hence relatively
unreliable
substationssubstations
� Lower voltage to the primary distribution
level, and split power routing amoung
feeders
� Typically, power system configuration
changes from transmission network to radial
feeders here.
Primary feeder levelPrimary feeder level
� Three Phase network as far as
construction(at least in urban areas)
� Usually operated radially by proper
positioning of open/closed switches
� Single phase laterals
Service transformers and Service transformers and
secondarysecondary
� Radial secondary system in most cases
� Transformer to customer ratio varies from
about 1:2 to 1:12 depending on the utility’s
system.
Sometimes all equipment Sometimes all equipment
including lateral service including lateral service
transformer secondary is transformer secondary is
identified as the service levelidentified as the service level
� Although different voltages, common
operating character: an outage must be
repaired to restore service.
� Quite common designation in Europe
At some utilities, system is operated as At some utilities, system is operated as
three levels distinguished by different three levels distinguished by different operating/outage characteristics.operating/outage characteristics.
� Grid: relatively small number of circuits, complicated
electrical behavior, outages do not necessarily cause
interruptions, repairs are very involved.
� Distribution: High number of circuits, radial simple
electrical behavior, outages cause interruptions, restoration
is usually by switching or repair.
� Service: very high number of circuits, radial, simple
electrical behavior, outages always cause interruptions,
restoration requires repairs, repairs are generally quick and
easy.
07/07/2013
10
A brief History lessonA brief History lesson
� Why do we use 50 hertz or 60 hertz?
� Why do we use three phase?
� Why do we have the voltage levels we
have?
50 hertz/ 60 hetz50 hertz/ 60 hetz
� The original power systems started out as DC. As you varied the voltage or speed of the generator you increased or decreased the power. However you were limited to the distance traveled before voltage drop became a problem. Therefore, you had to increase the size of the wire or put additional generators along the way. You could not change voltage levels as transformers do not work with DC. Voltage levels at the point of utilization in customers house were about 100 volts in the US. But do to voltage drop voltages were supplied 10 % higher at about 110volts.
� Because you could not distribute power very far with DC at 110 volts, AC became an attractive alternative. There were many articles about the effect of using AC as it was felt at the time it was very deadly. The reason AC was so attractive was because you can transform it from one voltage level to another using transformers. AC requires the use of synchronous generators and these generators must work at a constant speed. Transformers could be built to operate at about 25 Hz. And motor speeds could be matched to give motion to the prime mover at about 1500 RPMs. But with 25Hz you had objectionable light flicker. In the US they were building engines that operate at about 1800RPMs and in Europe they were building engines that operated at 1500RPMs. So if you build a 4 pole generator you get 50 and 60 hertz respectively.
� Now as you interconnect generators together you have to match frequencies so you now have systems in the US that are operating at 60 hertz and systems in Europe that are operating at 50 Hertz. If you were building a power system today you may consider again DC as you now have power electronics to do voltage conversions or you may consider AC systems operating in the 100’s of hertz as transformer size would be reduced. Airplanes use 400 Hz systems
Why 3 phase Why 3 phase � Why do we use 3 phase instead of 2 phase 4 phase, etc.
� Well three phase originated from the fact that generators were originally single phase. But for an induction motor to operate you needed more than one phase to give you a rotating field. If you put a winding on the generator at 90 degrees to the original winding you can get 2 phase. The same size generator can be used and you get 1.414 the amount of power out. You need three wires to take the power out of the machine.
� If you put three windings on the generator you can get 1.5 the amount of power out of the machine without increasing the size(of course the prime mover has to be sized accordingly) and you can take the power out with 3 wires.
� If you go to 4 phase you get 1.53 times the power
out and you need 4 wires.
� If you go to infinitely many phase you get 1.57
times the power out and you need infinitely many
wires.
� So it appears that the best choice is either two or 3
phase as you have 3 wires, but with 3 phase your
get 1.5 the amount of power out of a generator so
3 phase became the number of phases we use.
07/07/2013
11
Why the voltage levels we Why the voltage levels we
have.have.� In the US you had 110 volts, this then became 115
because of voltage drop and finally became 120 volts and that became the standard. If you multiple 115 times two you get 230v and take that times 10 you get 2300V. This became an industrial voltage for a delta system. Take this times 10 and you get 23kV a subtransmission voltage(if you take 2300 time 15 you get 34.5kV). Take this times 3 and you get 69kV and times 2 you get 138kV. If you take 120 times 2 and times 10 you get 2400V. Then times 3 you get 7200V times the 1.732 you get 12.47 times 2 you get 25kV.
� The 230kV is 2 time 115kV, 345 is 3 time
115kV
Delta verses WyeDelta verses Wye
� Delta requires only three wires
� Delta- one wire can be connected to ground and and the system can keep on functioning.
� Detecting line to ground faults can be a problem.
� Arcing faults can be a problem
� Wye systems can be grounded or ungrounded
� Wye systems have good fault sensing for line to ground faults
� Insulation levels only have to be 57.7 % of that needed for Delta systems for solidly grounded wye systems.
� Therefore most of the systems used these days are multigrounded wye.
What can you do when you What can you do when you
plan a Substationplan a Substation� If you are starting out with an entirely new system
and you are going to manufacture the equipment
yourself, you can choose frequency, voltage,
Number of phases, and whether it is delta or wye
connected if you chose 3 phase.
� If it is an existing system all you can do is pretty
much locate the new circuit route and where the
substation goes. But there is a lot of work
involved in that.
Radial Distribution SystemRadial Distribution System
� Majority of distribution is radial primary/secondary
� One source: Voltage and power flow downhill
� Often built as a network, but radialized by open Switches
� Contingency backup achieved by “transfer Zones”
switching segments to other feeders during an outage.
� Advantages
-Traditional: equipment available, understandable
-Economy: It is the cheapest in many ways
-Easy to engineer so it works well.
Loop Distribution SystemsLoop Distribution Systems
� Operates either as open or closed loop.—open
loop requires more expensive protection
� Either way, has an open, or at least “Zero flow”
point at all times
� Real concept is: contingency back up comes from
other side of the loop.
� Used through out Europe, Africa, and much of
Asia
07/07/2013
12
Feeder 1
Feeder 2
Substation
Loop support. The simplest
possible contingency backup
shown here is a loop feeder
layout. This involves
building feeders in pairs and
operating them with an open
tie between their ends.
Additional switches located
along the way permit
isolation of outage segments
Network DistributionNetwork Distribution
� Many types, all expensive compared to
radial
� Capacity cost is actually less than for radial
� Protection and control cost is much greater
than for radial
� Usually installed for reliability issues
� Most popular type is secondary network.
Interlaced Secondary NetworkInterlaced Secondary Network
� Radial feeders, network secondary
� Can be engineered to be incredibly robust
� Multiple radial feeders, feeding alternate
service transformers
A Wise Rule for problems on A Wise Rule for problems on
the Electrical Systemthe Electrical System� A wise old engineer once told me that
� 1. 80% of the problems experienced are cause by moisture.
� 2. 15% of the problems experienced are caused by a bad ground
� 3. The remaining problems are cause by exotic stuff such as ferroresonance, tank heating etc.
Service AreasService Areas
� Usually are designed to correspond to each
distribution circuit as it leaves the
substation
Service areas are dynamic Service areas are dynamic
from a planning standpointfrom a planning standpoint
� Service area transfers are an important
element of expansion planning.
� You can transfer load to another substation.
07/07/2013
13
T&D System CostsT&D System Costs
� Land
� Preparation
� Equipment
� Installation & Setup
� Losses
� Maintenance
Cost to upgrade usually Cost to upgrade usually
exceeds cost to build:exceeds cost to build:
� One mile of new 600KCM 3 phase overhead feeder cost about $186K to build, 14MVA capacity or $13,300/MVA/mile
� One mile of new 336KCM 3 phase overhead feeder cost about $140K to build, 9.3MVA capacity or $15,000/MVA/mile
� On mile of 336 can be upgraded to 600KCM for 226K or $48,000/MVA/mile
Reliability is assured through Reliability is assured through
Quick Service restorationQuick Service restoration� A majority of the equipment in the system
is in radial configuration– any failure causes some customer interruptions.
� The equipment is usually simple, and relatively inexpensive and easy to repair.
� Restoration time is predominately a function of identifying the problem and travel to the outage site.
Distribution: the most Distribution: the most
important part of the power important part of the power
systemsystem� Connected to the customer
� 52% on the investment
� 66% of the losses
� 90% of the reliability and power quality
issues
The System’s ApproachThe System’s Approach
� Concept: the various levels of the system are connected to one another
-transmission
-substation
-feeder
-secondary
As a result the layout and design at one level influences requirements of the other levels
MultiMulti--System LevelsSystem Levels
� Each level has costs constraints and
interactions within it, that are unique to it.
� But it also depends on the levels connected
to it, for example the feeders all must start
at the substation
07/07/2013
14
Thus the planner’s goal is not to Thus the planner’s goal is not to
optimize any one level, but to optimize any one level, but to
optimize the combination of levelsoptimize the combination of levels––
The whole systemThe whole system
� The way one level is designed impacts the electrical and economic performance of the other levels connected to it.
� In many cases, interactions with the other levels are the most important aspect of the design!!
� Planner’s goal is to design the best combination of levels: the best system!!
Example:Example:
The following four design The following four design
questionsquestions� How far apart should substation be?
� What size should substations be?
� What is the best transmission voltage?
� What is the best primary voltage?
� All are versions of the same question!
How far apart should How far apart should
substations be?substations be?
� If the substations are moved farther apart
then each will have a larger service area
� If the stations are 4 km apart then each
covers about 16 square km
� If the stations are 6 km apart then each
covers about 36 square km
If the substation has a larger If the substation has a larger
area each will have a larger area each will have a larger
load to serveload to serve� Need larger more expensive substations
� But fewer will be needed
Is it better to have fewer, but larger Is it better to have fewer, but larger
and more expensive substations?and more expensive substations?
� Certainly part of the answer depends on the cost of
the substations and how it varies depending on
size etc.
� Generally the answer considering only the
substation is yes. For example, it is usually
cheaper to build 5 50 MVA substations than 11
25MVA substations.
� However substation cost is not the only issue
Substation size influences Substation size influences
Transmission designTransmission design� The system design with larger substations need
more power on average delivered to each
� Hence, the transmission system must be capable of delivering larger amounts on power to each substation
� But there will be fewer lines needed, because with larger substations, there are fewer lines.
� Are fewer but larger transmission lines less expensive?
� Even when you answer this, this is not the complete answer.
07/07/2013
15
Impact of DistributionImpact of Distribution
� Fewer, larger substations means that feeders
must move power farther.
� Requires higher voltage
� May require more feeders
� May require reinforced feeders
� This is often then a major expense
Fewer but larger substations Fewer but larger substations
require feeders to move power require feeders to move power
fartherfarther� Any way you look at it, the larger, fewer, farther
apart substations are will require a stronger
distribution system- one that moves power farther
� This means a more expensive feeder system but
this greater expense might be justified by the
savings in substation and transmissions systems
costs due to their greater “economy of scale”
The point:The point:
� The economics and electrical behavior of
the substation, of the feeder, and of the
transmission levels need to be added
together to determine cost and performance
as a whole.
� This is what planners must concentrate on.
This concept is the key to the design This concept is the key to the design
of low cost, workable T&D systemsof low cost, workable T&D systems� In order to determine what is the best transmission system
voltage to use you need to do a couple of cases: Price 138kV using 4/0 wire and 954kCM wire and determine the load it can carry: Price 230kV using 4/0 wire and 954kCM wire and determine the load it can carry.
� Price the cost of a 230 to 12.5kV substation 12/16/20MVA and 18/24/30MVA substation. Price the cost of 138kV to 12.5kV Substation using the same loading. Do all four cases again for 34.5kV distribution.
� Price the cost of 12.5 kV distribution using 336kCM wire and then with 795kCM wire
� Price the cost of 34.5kV distribution using 336kCM wire and then with 795kCM wire. Determine how much MVA each will carry.
Don’t forget reliability Don’t forget reliability
� As feeder get longer reliability goes down.
� Reliability problems are the sum of failures
anywhere in the chain from generation to
customer.
� If one needs to improve reliability where is
the lowest cost fix that can be made.
System ApproachSystem Approach
� Important points are:
- interactions of levels means costs and
performance depend on all levels, not any one.
-Operating interaction is often more important in
optimal design than actual economic performance
at that level
-the goal is to design the best overall system
taking into account all levels
07/07/2013
16
Need to determine the appropriate Need to determine the appropriate
information for the distribution planning information for the distribution planning engineer to useengineer to use
� Standards Group
1. Determine the equipment that is going to be
used.
2. Make a construction standard to install the
equipment.
3. Determine the cost for construction.
4. Determine the special engineering
requirements for the most economical system.
Need to have a Financial Planning Need to have a Financial Planning
Group to develop a consistent way to Group to develop a consistent way to
evaluate projectsevaluate projects� A computer program is the usual method to
do the evaluation and the group provides the
financial parameters to put into the program
Distribution System ReliabilityDistribution System Reliability
� Reliability
� Service Quality
� Ways to improve both
What is Reliability?What is Reliability?
� Reliability analysis involves quantitative
measures of system performance regarding
interruption of services, through historical
data analysis and theoretical predictions
Why Bother?Why Bother?
� The purpose of reliability engineering is to maintain service quality standards with limited capital investments
� How much is reliability worth?
-repair and emergency crew expense
-loss of revenue
-public image
-loss of customers
Outages and InterruptionsOutages and Interruptions
� An outage is what happens to equipment
when not in service.
� An interruption is what happens when
insufficient equipment exists to serve the
customer
� Outages cause interruptions
07/07/2013
17
Two Aspects of Service Two Aspects of Service
ReliabilityReliability
� Frequency of interruptions- How often is
the power interrupted.
� Duration of interruptions- How long do
interruptions last.
Frequency and Duration are Frequency and Duration are
somewhat independent somewhat independent
aspects of reliabilityaspects of reliability� Frequency of interruptions is mostly a
function of engineering factors, equipment
selection, layout, design of protection, etc.
� Duration of interruption is mostly a function
of operating factors: number and location of
repair crews, speed in handling trouble
calls, and dispatching, etc.
� Customers react differently to frequency and duration of interruptions.
� To some customers, a short (2 second) interruption is nearly as serious as a longer one: computers, robotic control, synchronous motors.
� To others short interruptions create few problems
Types of interruptionsTypes of interruptions
� Instantaneous: An interruption restored
immediately by completely automatic
equipment. It is caused by a momentary
fault that produces no reaction from
protective equipment. According to IEEE
1250-1995 it is .5 to 30 cycles in duration
� Momentary: An interruption restored by
automatic operation of protection
equipment. From 30 cycles to 2 seconds
� Temporary: An interruption restored with
supervisory control usually between 2
seconds and 2 minutes
� Sustained: Any interruption that is not
instantaneous, momentary, or temporary.
Normally more than 2 minutes. Usually
involves manual switching and/or repair
work
07/07/2013
18
Interruptions are also Interruptions are also
distinguished by whether they distinguished by whether they
were planned:were planned:� Scheduled: The utility scheduled the
interruption for maintenance purposes, and
the customer was given advanced warning
� Forced: The interruption was not expected
and not scheduled. You may have to open a
line to make a repair.
Reliability IndicesReliability Indices
� Combine frequency, duration, and other factors into a single value, a measure of reliability on the system.
� There are lots of them
� SAIDI: System Average Interruption Duration Index The average total duration of interruptions per customer during a period (month, year)
� This is the total number of interruption minutes divided by the number of customers.
� SAIFI: System Average Interruption Frequency Index The average number of interruptions per customer during a period(month, year)
� This is the total number of customer interruptions divided by the number of customers.
CAIDI CAIDI
� CAIDI: Customer Average Interruption
Duration Index- The average total duration
of interruptions per customer that had an
interruption during a period (month, year)
� This is the total number of interruption
minutes divided by the number or
customers who had at least one interruption
during the period.
CAIFICAIFI
� CAIFI: Customer Average Interruption
Frequency Index-The average number of
interruptions per customer during a
period(month,year)
� This is the total number of customer
interruptions divided by the total number of
customers who had at least one interruption
during the period.
MAIFIMAIFI
� MAIFI: Momentary Average Interruption
Frequency Index-The average number momentary
interruptions per customer during a period(month,
year)
� This is the total number of customer interruptions
divided by the total number of customers.
� This is a necessary index because momentary
interruptions are not counted among interruptions
by many utilities.
Reliability Reporting can be Reliability Reporting can be
misleadingmisleading
� Tremendous difference in reliability levels
reported by utilities just because of
differences in definition.
� Cannot compare reliability statistics
reported by different utilities(at least across
US State Lines because of different
commissions)
07/07/2013
19
Variations in definitionsVariations in definitions
� Interruption length. Most utilities don’t report interruptions below some minimum duration. This is because they have no way of knowing what happened and to which customers.
� Customer- Some utilities report master metered customers as one customer, others estimate the impact on a household
� Start time- Some utilities estimate interruption duration as starting when the outage occurred, others when the interruption was reported to dispatching
Determining reliability levelsDetermining reliability levels
� Comparison of years method
� Gather interruption data for the past years, the more the better. Ten years would be good.
� Plot SAIDI verses SAIFI
� You should see a pattern and any years that fall outside of that pattern my be considered bad years.
ValueValue--based planning is not based planning is not
that simplethat simple
� Data is difficult to find
� Customer costs are nearly impossible to
determine except for large industries
� Takes lots of work
� Functions are often discontinuous.
Building reliability into a Building reliability into a
Substation DesignSubstation Design
� Remember that engineering, design and
layout influence mainly the number of
interruptions. Good design can reduce the
number. But good design has little
influence on the duration of the interruption.
Engineering’s influence on Engineering’s influence on
ReliabilityReliability� Design and layout can reduce frequency of outage:
-Using equipment that fails less often(correctly sized, etc.) conductors slapping
-Coordination of equipment(insulation coordination, etc.) so equipment is coordinated with design and layout. Electronic reclosers with sequence coordination.
-using layout that reduces the extent of equipment outages: Cutouts, etc.
Engineering can influence Engineering can influence
duration only in one respectduration only in one respect� Remember we are talking about sustained outages
� Feeder layout and switching locations can be
coordinated so that interruptions can be restored
quickly by switching.
� This provides the potential for shorter duration
interruptions but requires competency and
preparation on the part of the Operations
Department to use this capability.
07/07/2013
20
Building reliability into a Building reliability into a
distribution systemdistribution system
� Use good equipment
� Maintain it well
– By schedules as recommended
– RCM- Reliability Centered Maintenance, O&M
controlled by analysis of importance, diagnostic
data
� Operate it well
Layout makes a big differenceLayout makes a big difference
� Can apply concepts manually in day to day
planning
� You now have to remember you are adding
another layer of criteria/constraints on top of
voltage standards, operation guidelines, etc.
� It would be nice to have a computer program to
help, but we haven’t found one yet.
Reliability versus cost is really Reliability versus cost is really
the only issuethe only issue� The type of system makes a big difference
� Non-Linear: a little reliability costs little. More costs a lot
more.
� Reliability is easy to build into a power system
� The problem is doing it economical
reliability
co
st
Secondary networks with Secondary networks with
interlaced feeder systeminterlaced feeder system� Using secondary networks, parallel feeders, serve
every other service transformer from each
� If properly designed, the resulting system can
tolerate a lose of a feeder without an interruption
European 11kV loop systemEuropean 11kV loop system� All feeders operate as closed loops
� Essentially two radial feeders with closed tie, no
laterals
� Outage interrupts flow only to customers on
segment
� Expensive: requires close to two times conductor
capacity, and protection is expensive.
Normally
closed
Normally Closed
Open LoopOpen Loop
� Most typical European design
� Outage in this example drops ¼ to ½ of the
customers
� Still requires 2 times capacity, but
protection is simple
� Switching restores some service.
Normally
closed
Normally closed
Normally open
07/07/2013
21
Loop Feeder Systems are Loop Feeder Systems are
good design but expensivegood design but expensive
� Every feeder must be built to support twice
the load and twice the distance
� Planners can reduce number of customers
affected by outages by adding sectionalizers
Normally
closed
Normally
closed
Feeder must support all the load with either segment out at the substation
Loop Zonal Transfer SchemeLoop Zonal Transfer Scheme
Normally
closed
Normally closed
Normally
closed
Normally closed
Normally
closed
Normally closed
Normally
closed
Normally closed
Normally
closed
Normally closed
Requires less capacity but lower reliability because more
involved switching needed to balance loads during outages
American Radial SystemAmerican Radial System
� Basic concept is transfer of radial, not loop,
zones.
� The feeder is built from sections or zones,
each switchable to at least two other zones
� Support is given by switching as needed
after an outage
� Least expensive
ValueValue--based Planningbased Planning� This is probably the best way, but it is
complicated.
� Utilities cost increases as reliability increases
� Customer’s loss dollars decrease as as reliability increases.
� Add the two together and the low point in dollars is the optimal point.
� But who pays? The utility or the customer?
� Using smaller feeders.
� Improving sectionalizing and protection– Fuses and sectionalizers protect the rest of the feeder
from outages behind them
– Segmenting feeder into many protection sections avoids outages spreading interruptions to many customers
Adding more switching zones Adding more switching zones
generally does not improve generally does not improve
reliability greatlyreliability greatly
� Dividing each feeder up into five switchable
zones, instead of three will not improve
reliability greatly. May make it more
difficult to switch
� It will reduce cost as neighboring sections
need less contingency margin to pick up
load. They are picking up 1/5 of the feeder
instead of 1/3
Automation and ReliabilityAutomation and Reliability
� Automated distribution offers two
capabilities that improve reliability
1. Monitoring- you can see trouble coming and
know what equipment can take during
contingencies.
2. Automated switching(verses manual) is
faster, more flexible and can do more
involved switching
07/07/2013
22
Automation and where it Automation and where it
improves reliabilityimproves reliability� Monitoring of conditions by
– RTUs
– On-line trouble analysis
� Remote Switching– Fast, cuts outage duration, but not frequency of the
outage
– May include resetting protection for a new configuration
� Computerized operations management– On line analysis of restoration
– Crew tracking, optimization
Three Levels of Automation Three Levels of Automation
regarding Distribution regarding Distribution
SystemsSystems� Static systems- Fuses, manual switching.
� Automatic system- automatic sectionalizers,
and reclosers
� Automated system-remote control of
sectionizers, and switches
Measures to improve Measures to improve
Reliability and Service QualityReliability and Service Quality� Need new tools and methods: cannot achieve a
goal unless you can measure and direct progress toward it.
� Understand customer’s need for and valuation of reliability and service quality
� Shift from standard-driven to performance based design
� Optimize reliability within budget: reliability centered planning and reliability centered maintenance.
Capacitors, Reactive Power Capacitors, Reactive Power
and Feeder Planningand Feeder Planning
Power Flow on the Feeder Power Flow on the Feeder
System is ComplexSystem is Complex
� The two components of complex power
flow
4.8MW
3 .6MVAR
6 MVA
Here, a flow of 4.8MW is desired and
3.6MVAR is undesired creates a total
of 6MVA of flow
Real Power MW, useable, sellable,
does work. Requires capacity to
move it, creates both losses and
voltage drop as it moves
Reactive Power MVAR, unusable,
unsellable, does no work. Requires
capacity to move it, creates lines
losses, X & R component of line
creates voltage drop.
Power Factor Refers to the Power Factor Refers to the
Ratio of Real to Total FlowRatio of Real to Total Flow
� Total flow is the magnitude of complex
power flow:
Total = Real + Reactive2 2
Power Factor = Real/Total
The Power Factor=4.8/6.0 =80%
07/07/2013
23
Reactive Flow is commomly called Reactive Flow is commomly called
“VARs” (Volt Amperes Reactive) and it is “VARs” (Volt Amperes Reactive) and it is unwantedunwanted
� VARS take up capacity on the line as
shown the line has to be able to carry
current equivalent to 6MW(6MVA), but is
only delivering 4.8MW because of the VAR
Flow
� VARs create voltage drop- so they use up
economic reach
Reactive Power Flows(VARs) Reactive Power Flows(VARs)
are caused by Loadsare caused by Loads� Many loads=particularly wound devices like
motors and solenoids create a lag between voltage
and current, in effect, is the source of VARs.
Only purely resistive loads like incandescent
lights, etc. are free of reactive loads.
� VARs that flow at the load from the current
lagging the voltage by 90 degrees are considered +
+
-V I
-P
+Q
+P
+Q
-P
-Q
+P
-Q
Reference
Voltage
I
I I
I
V
Shunt Capacitors are used to Shunt Capacitors are used to
produce produce ––VARs or anti VARsVARs or anti VARs� A shunt capacitor installed anywhere on a feeder
will produce VARs, satisfying the load
downstream of it.
� In the example we have been using a 1MVAR
capacitor produces .985kVAR reducing the VAR
load to 2.65MVAR. As a result real power flow
can be increased to 5.4MW( at 12.5%
improvement) while keeping the total flow under
its 6MVA capacity loading
Shunt Capacitors are voltage Shunt Capacitors are voltage
sensitive devicessensitive devices� They produce their rated VAR output at their rated
nominal voltage
� The 1 MVAR capacitor only produced .985kVAR
because the voltage was less than 1.0 P.U.
� The VARs produced flow downstream to serve the
VAR demand farther out. If there are less VAR
demand than the capacitor’s output the VARs
move upstream toward the feeder source.
VAR Flow DiagramsVAR Flow Diagrams
5
4
3
2
1
0
MVAR
0 1 2 3
Miles
5
4
3
2
1
00 1 2 3
Voltage Drop
•A useful tool for the study of
VARs and VAR correction is the
VAR flow diagram, which is a
profile of the VAR flow on the
feeder
•Here a 3 mile long feeder trunk
has a uniform VAR load of
2MVAR per mile. The diagram
shows VAR flow at all points along
the feeder
•Also shown is the voltage drop
along the feeder(not uniform
because real load and conductor
size are not all uniform.
07/07/2013
24
The Effect of a Shunt Capacitor is The Effect of a Shunt Capacitor is
easy to plot and seeeasy to plot and see5
4
3
2
1
0
0 1 2 3
3000kVAR
CAP bank
Here a 3000 kVAR shunt capacitor
bank has been installed at a point 1.5
miles out of the feeder
It satisfies all the VAR demand needs
after it.
Impact on VAR flow is as shown. The
substation is cut in half and there is a
point of zero VAR flow just before the
capacitor location.
5
4
3
2
1
00 1 2 3
Flow diagrams can be used to study Flow diagrams can be used to study
how to improve capacitor utilizationhow to improve capacitor utilization
5
4
3
2
1
0
0 1 2 3
3000MVAR
CAP bank
5
4
3
2
1
0
0 1 2 3
3000MVAR
CAP bank
Here we see what happens when
you move the capacitor farther out
the feeder.
-the VAR-miles of flow in the
unshaded area are removed and the
VAR-miles of flow shaded yellow
are added.
-the capacitor feeds some of its
VARs back toward the substation
-In total, VAR-miles of flow are
reduced.
This is an improvement, because the total This is an improvement, because the total
VARVAR--miles of flow have been reduced miles of flow have been reduced substantiallysubstantially
6
5
4
3
2
1
0
0 1 2 3
VAR-miles of
flow reducedThe reduction is equivalent to the
unshaded area
-This represents VAR-miles of flow
that no longer exist.
-Voltage drop is improved.5
4
3
2
1
00 1 2 3
With cap
No cap
Voltage Drop
The Capacitor can be moved until the amount The Capacitor can be moved until the amount of MVARof MVAR--miles gained and lost from any farther miles gained and lost from any farther
movement is the samemovement is the same
5
4
3
2
1
0
0 1 2 3
3000MVAR
CAP bank
This occurs for the 3000KVAR bank when it reaches a location at 2.25
miles from the source. At this point the MVAR-miles on the feeder are at a
minimum.
Voltage drop will be even better.
Similarly, the impact of changing Similarly, the impact of changing
capacitor size can be studiedcapacitor size can be studied
5
4
3
2
1
0
0 1 2 3
4000kVAR
CAP bank•By increasing the size of the capacitor
to 4500kVAR, the VAR-miles shown
in the unshaded area are removed and
those in the shaded yellow area are
added
•The result again is an improvement
more were removed than added.
5
4
3
2
1
0
0 1 2 3
4500kVAR
CAP bank
The TwoThe Two--Thirds Rule for Thirds Rule for
Capacitor ApplicationCapacitor Application
5
4
3
2
1
0
0 1 2 3
4000kVAR
CAP bank
If this method is applied to determine both the optimum size and location of a
single capacitor, what capacitor size and location results in the minimum VAR-
miles- The result will be a 4000kVAR capacitor located at 2 miles from the
source.
This is a graphically derived two thirds rule for capacitors. Among all single
capacitor applications this minimizes the resulting VAR-miles.
07/07/2013
25
TwoTwo--thirds rule, cont.thirds rule, cont.
A traditional rule-of-thumb for capacitor application to a feeder is to place a capacitor equal to 2/3’s the VAR load of the feeder at a point 2/3’s of the distance from the substation.
The graphical method of capacitor impact analysis or an algebraic equivalent, can be used to confirm that this minimizes the total MVAR-miles, provided the VAR loading is uniform.
This rule is one of the most widely used guidelines in all power distribution. Most power engineers are aware of it and apply it. Most do not know however, that it can be applied by way of a simple graphic method shown here and that it can be generalized to more than one capacitor
Generalized Two Thirds RuleGeneralized Two Thirds Rule
� The impact of two capacitor banks can be
similarly represented graphically.
A bit of experimentation will show
that the best two capacitor solution is
two capacitors equal to 2/5’s of the
VAR load located at 2/5’s and 4/5’s
of the distance out from the
substation
5
4
3
2
1
0
0 1 2 3
2400MVAR
CAP bank
2/5*6000kVAR=2400kVAR
Generalized twoGeneralized two--thirds rule cont.thirds rule cont.
Inspection of such graphs, or algebraic
manipulation that accomplishes the same
can establish that for a feeder uniformly
loaded with a VAR load of Q, the optimal
size for each of N equally sized capacitors
is: Size of each of N banks=2Q/(2N+1) at
evenly spaced locations L=n*2l/(2N+1)
where n=1,2,….,N l = length of feeder
Generalized twoGeneralized two--thirds rule cont.thirds rule cont.
As a result the MVAR-miles on a feeder are reduced from Q*l/2(the amount without any capacitors ) to
Total MVAR-miles=(Q*l/2)/(2N+1)
Therefore the best two capacitor solution is two equally sized banks of 2/5 of the VAR load of the feeder, located 2/5’s and 4/5’s of the way from the substation, which reduces MVAR-miles to 1/5 of their previous level. The best three capacitor bank solution are banks of 2/7’s the VAR load, at locations of 2/7’s, 4/7’s, and 6/7’s out from the source and they will reduce the VAR-miles to 1/7 of their uncorrected level,etc.
The ultimate end of this series would be for N to be very large, which would distribute a very large number of very small capacitors, equal to the total VAR load of the feeder, spaced uniformly along its length. This would reduce
VAR-miles to zero.
A Lot of feeder loads aren’t A Lot of feeder loads aren’t
exactly uniformly distributedexactly uniformly distributed
5
4
3
2
1
0
0 1 2 3
A lot of feeders may have non uniform
VAR load.
For one thing, loading both real and
reactive is discrete, not continuous
However, modeling loading as a
continuous distribution adds little error,
but the wrong distribution along the
trunk adds considerable error.
At the left is a more representative
loading distribution which represents a
large trunk feeder serving a triangular
area of uniform area VAR load.
When distribution is not longer uniform, When distribution is not longer uniform,
the best capacitor location is not longer the best capacitor location is not longer given by the 2/3’s rule.given by the 2/3’s rule.
Here, a capacitor equal to 87% of the feeder
VAR load located 2.25 miles out is about
optimum for the triangular area loading.
5
4
3
2
1
0
0 1 2 3
07/07/2013
26
Many feeders have express portionsMany feeders have express portions-- they they
have no load on their initial lengthhave no load on their initial length
5
4
3
2
1
0
0 1 2 3
5
4
3
2
1
0
0 1 2 3
Shown here is the distribution of
VAR-miles for a feeder with a 1.66
mile express portion then with
6MVAR loading evenly spread along
the remaining 1.33 miles.
Optimum reduction in VAR miles is
from a capacitor equal to 100% of the
VAR loading located 77% of the way
out the feeder
Generalized 2/3’s ruleGeneralized 2/3’s rule
� The concepts outlined here-including the graphical
method of deriving a recommended size and
location for capacitors on a feeder, based on its
VAR load distribution will be called the
generalized 2/3’s rule
� When loading is not uniform, the capacitors in a
multi capacitor application are not necessary the
same size, nor are they evenly spaced.
General Capacitor Utilization Guidelines General Capacitor Utilization Guidelines
Based on the Generalized 2/3’s RuleBased on the Generalized 2/3’s Rule
� The MVAR-miles minimization method used above is basically a more flexible application of the 2/3’s rule, which can accommodate uneven VAR loadings. Therefore the following guidelines can be thought of as corollaries to the 2/3’s rule, applicable to situations distribution planners are more likely to face:
� On some typical feeders, the best single capacitor solution is a bank sized 7/8 of the feeder VAR load, located ¾ of the way out the feeder. The best 2 capacitor application is 45% of the VAR load at .3 the length and 50% load at .90 the length of the feeder
In cases where an express feeder trunk is used, the best single capacitor bank application is usually the bank size equal to the VAR load of the feeder, located at the halfway point of the VAR load in the loaded section. The best two capacitor solution is banks equal to ½ the VAR load located at ¼ and ¾ on the loaded portion length.(this is assumed to be uniform loaded)
Any large VAR load should be corrected at its location. In most cases a large or special load will create a very large VAR load at one point on the circuit. Analysis using graphical methods will show the best strategy for minimizing the impact is to install a capacitor equal to its VAR load at its location(ie cancel the VARS at their source)
The twoThe two--thirds rule works as thirds rule works as
well for feeders with brancheswell for feeders with branches
� It may be more difficult to apply, but it
works as well.
Incremental sizes and Incremental sizes and
maximum sizesmaximum sizes� Capacitors are usually available only in standard
unit sizes(100kVAR /phase units at 12.47kV) and
there is a limit to the size of bank that can be
installed at any one location. Typically no more
than 5 to six units per phase. In addition the fault
duty of capacitors must be considered. Large
banks may have to high of outrush current.
Therefore a planner may be limited to no more
than 1800kVAR.
07/07/2013
27
Using more capacitors generally improves Using more capacitors generally improves
the results(and increases the cost of the the results(and increases the cost of the capacitors)capacitors)
Expected reduction in MVAR-mile flow from the application of the
generalized 2/3’s rule as a function of the number of capacitors in %
# of Caps. % Reduction in MVAR-miles flow on a trunk
A uniformly loaded trunk A typical Feeder
1 66 77
2 80 87
3 86 93
4 89 95
5 91 96
6 93 97
In addition, power factor as seen at the In addition, power factor as seen at the
substation is improvedsubstation is improved
Corrected Power Factor at the substation After the application of the
generalized 2/3’s rule as a function of the uncorrected power factor
Uncorrected
PF
P.F. at the substation after the application of the caps
With one Capacitor With two Capacitors
90 99 100
80 97 99
70 95 98
60 91 97
50 87 94
40 80 91
Power Factor ProfilesPower Factor Profiles
0 1 2 3
1.0
0.9
0.8
0.7
A. Evenly loaded at 2MW and
2MVAR/mile 70%PF
0 1 2 3
1.0
0.9
0.8
0.7
C. Corrected with 2/3’s rule 2 caps
2400kVAR at 1.2 and 2.4 mile
0 1 2 3
1.0
0.9
0.8
0.7
B. Corrected with the 2/3’s rule 1
cap. 4000kVAR at 2 miles
0 1 2 3
1.0
0.9
0.8
0.7
D. Typical feeder cap 5400kVAR
at 2.25 miles
Power Factor ProfilesPower Factor Profiles
� Another useful tool is the power factor profile.
Among other things, it will amply demonstrate
that even when capacitors are used power factor is
not uniformly corrected.
� This demonstrates why about the best that can be
done is an average 90% power factor. It can be
corrected to better than that in some places, but
over the entire feeder an average of about 90% is
the best that can be done.
Shortcomings of the 2/3’s ruleShortcomings of the 2/3’s rule
The graphical MVAR-mile minimization method used in the examples
above is a very useful mechanism for illustrating the basics of VAR
capacitor interaction, and for deriving approximation guidelines, such
as the 2/3’s rule, for capacitor application. A number of important
factors are not considered however:
Complex power flow. Actual power flow is complex. The MVAR-mile
analysis deals only with VARs without recognizing that the impact and
importance is somewhat a function of real power flow too.
Economics. The value of VAR reduction depends on the cost of losses
and the need for additional capacity and reach released by the
improvement in power factor. Capacitor application ought to be based
on economic benefit versus cost analysis.
Shortcomings of the 2/3’s rule cont.Shortcomings of the 2/3’s rule cont.
Line impedance. Both the response of a feeder to changes in VAR flow
and the importance of reducing VAR flow vary depending on the
impedance of various line segments, whereas the approximate method
essentially treats all portions of the feeder as equivalently important.
Discontinuous Load. Actual kW and kVAR load on a feeder is
discontinuous, whereas we represented it as continuous.
Detailed analysis of capacitor interaction for each specific feeder, taking
in all the above, is necessary to optimize capacitor application.
Usually, application involves so many variables and is so complex and
complicated that computer analysis is necessary to produce any
improvement over intelligent application of the generalized rule
described.
07/07/2013
28
Switched CapacitorsSwitched Capacitors
� Many times, all or some of the capacitor
banks on a feeder will be switched-
connected some of the time and
disconnected some of the time.
� The reason is that the VAR load changes
over time and thus the need for the
capacitors to change.
Seasonal and daily variation in Seasonal and daily variation in
loadloadShown here are the daily MW and
MVAR loads for a feeder in the
southwest of the US
Both MW and MVAR vary by season
and time of day.
Note that the MVAR load varies more
than the MW. In summer, power factor
off peak is about .83 and on peak it is
.71
Therefore VAR requirements change
over time.
Mid Noon Mid
6
4
2
0
Summer peak day
Mid Noon Mid
6
4
2
0
Autumn Day
MW
MVAR
MW
MVAR
Overboosting VoltageOverboosting Voltage
In some cases when the VAR load is quite low, shunt capacitors can boost voltage above permitted levels, in such cases, they must be switched off when the load is low. The voltage boost at the end of the feeder, due to a capacitor, can be estimated as
Voltage rise(120volt scale)=.12(CkVA*X)/KV**2
Where X is the line reactance to the capacitor location and CkVA is the capacitor’s capacity. For example, 4000 kVAR at three miles on a 12.47kV feeder with X=.63, would boost voltage about 6.31volts
During periods of Low VAR Demand, leaving During periods of Low VAR Demand, leaving Capacitors connected to the feeder increases Capacitors connected to the feeder increases
VARVAR--mile flowmile flow
5
4
3
2
1
0
0 1 2 3
3-1800kVAR
CAP bank
Peak Conditions
5
4
3
2
1
0
0 1 2 3
Minimum Conditions
Here three capacitors minimize
VAR-miles at peak(top), but during
minimum load time, creates a
tremendous VAR flow back towards
the substation(bottom)
Power Factor Correction and Power Factor Correction and
X/R RatioX/R Ratio
0 1 2 3 4 5 6 7 8 9 10 11 12
Peak Load -MW
1.0
.8
.6
.4
.2
0
PW
Cost
$ m
illi
onIf VAR-miles were reduced to
zero on a feeder then there
would be no voltage drop
from the reactive component
of the impedance
In that case, voltage drop like
losses depends only on R and
big conductor would have a
longer reach
Power Factor correction
impacts larger conductors
more than small ones because
its impedance is mostly X not
R
70%
80%90%
100%
SummarySummary
� VAR flow on feeders uses capacity and shortens the economic reach
� VARs can be reduced by the installation of shunt capacitors
� The generalized two thirds rule permits analysis and understanding of VAR flow and corrective issues
� Power Factor can be corrected at best to about 90% on average, which improves voltage drop(economic reach) of conductors.
07/07/2013
29
Multi Feeder System PlanningMulti Feeder System Planning
� We will look at
� Feeders as part of a feeder system
� Upgrading configuration not line capacity
� A formula that estimates feeder system cost
� Guidelines to reduce cost
The systems Approach:The systems Approach:
Feeders are only part of the SystemFeeders are only part of the System
� A power delivery system consists of many levels of equipment, including sub-transmission, substations, feeders and service
� The recommended perspective for planning is to always view each level as part of a larger whole and plan it using a system’s approach. This means that when laying out a particular feeder, the goal is not to minimize its cost, but to plan it so it contributes to achieving the lowest overall total system cost.
Avoid “feederAvoid “feeder--atat--aa--time” myopiatime” myopia
This has been mentioned before, but this is the most common mistake made in distribution planning methodology.
It is common for distribution planners to focus on the study of one feeder at a time. Usually a feeder that has a new load, a voltage problem, etc. and a solution needs to be found. This feeder at a time focus is necessary in certain phases of planning, but it can lead to a kind of design myopia which is responsible for missed opportunities for savings and service quality improvement.