THE VALUATION TRIBUNAL FOR ENGLAND
Summary of Interim Decision: ndr, jurisdiction, whether a challenge to an entry in
the rating list through no valid completion notice being served should be by way of
judicial review or proposal. President found that the matter could be decided by way
of proposal.
Summary of Substantive Issue: ndr, deletion of list, whether completion notices
capable of being served, whether work structural, one building or parts treated as
buildings, appeals allowed for ground floor and first floor but dismissed for the
second floor.
Re: 1st Floor, The Horizon, 99 Burleys Way, Leicester,
2nd Floor, The Horizon, 99 Burleys Way, Leicester,
Ground Floor, The Horizon, 99 Burleys Way, Leicester,
Ground Floor, Thames Tower, 99 Burleys Way, Leicester,
1st Floor, Thames Tower, 99 Burleys Way, Leicester,
2nd Floor, Thames Tower, 99 Burleys Way, Leicester
APPEAL NOs: 246525454690/538N10
246525454849/538N10
246525454856/538N10
246525454862/538N10
246525454867/538N10
246525454875/538N10
BETWEEN: Delph Property Group Ltd (Appellant)
and
Mrs Janet Alexander (Respondent 1)
(Valuation Officer)
Leicester City Council (Respondent 2)
(Billing Authority)
BEFORE: Mr G Garland, President
SITTING AT: NSPCC National Training Centre, 3 Gilmour Close, Leicester LE4 1EZ
ON: 17 January 2018
AND AT: The Tribunal Offices, Leman St, London, E1 8EU
ON: 11 May 2018
APPEARANCES: Mr Luke Wilcox of Landmark Chambers for the Appellant
Mr George Mackenzie of Francis Taylor Building for the Valuation Office Agency
(Respondent 1).
Mr Tom Gosling of 23 Essex Street for the Billing Authority (Respondent 2)
Summary of Decision on Preliminary Points
1. The Tribunal has jurisdiction to hear the appeals.
2. Any time constraints to challenging the entry in the list on the basis that it
shows a hereditament that ought not to be shown must meet the regulatory
timeframe for proposals (and appeals where they apply) and, any other
regulatory requirements such as those in respect of the material day
provisions. The Tribunal cannot prescribe its own time constraints.
Summary of Decision on Substantive Point
3. In respect of the substantive matter I find that completion notices cannot be
served in accordance with s.46(A)(6) in respect of the Ground Floor and First
Floor as the parts under appeal were not produced by structural alterations of
those parts of the building and the entries in the Rating List are deleted for the
periods requested. In respect of the Second Floor I find that s.46 (A) (6) is
satisfied and the appeal is dismissed.
Introduction (containing agreed facts)
4. The property at 99 Burleys Way, Leicester (previously known as Thames
Tower and now known as The Horizon) was originally constructed in the
1970s as an office building with floor plates on the ground to second floors
comprising more than 1,200 m2 per floor. Above the wide frontage there was
a central tower forming the third to sixteenth floors of the building, with
available office space of less than 500 m2 per floor.
5. In late 2006 the then owners, Brampton Asset Management (Leicester) Ltd,
began a scheme of redevelopment with the tower floors being converted into
112 dwellings whilst the ground to second floors were refurbished but
remained office accommodation.
6. All rating assessments were deleted from the rating list with effect from 23
October 2006. At the time that works commenced the building included the
following hereditaments:
a. 1st, 2nd (Part) and 3rd to 9th Floors – RV £172,000
b. Part Ground Floor RV £31,500
c. Part Ground Floor (Stiches Clothing) RV £6,400
d. Part Second Floor RV £38,000
7. The residential accommodation created on the third to sixteenth floors came
into the council tax valuation list on various dates from the end of 2008.
8. There is no detailed schedule of works undertaken to the building available as
the former owner went into administration in 2010 and was subsequently
wound up. The contractor, J H Hallam, also went into liquidation in 2013.
9. The only evidence available relating to the works carried out to the offices
under appeal is provided by Corrigan Gore Project Management who, in 2010,
carried out a due diligence investigation into the building on behalf of the
Appellant, at the time of their purchase of the building which completed on 3
November 2010, and that provided by Leicester City Council for the hearing.
10. The ground floor offices comprised two separate office areas either side of the
central core and reception with the first and second floors being single spaces
but capable of division. The rating assessments for the office floors were
deleted from the rating list in accordance with Valuation Office Agency
practice at the time.
11. The works undertaken on the appeal floors were certified as complete by
Leicester City Council’s building control department for building regulations
purposes on 3 October 2008. An enquiry officer from Leicester City Council
conducted an inspection of the property on 27 January 2009 accompanied by
Ivan Lloyd, the managing agent of Brampton. The enquiry officer considered
the works to have reached practical completion and recommended service of
a completion notice.
12. The offices were marketed by agents as refurbished and available for letting
both by Brampton and, from November 2010, by Delph. At practical
completion of the refurbishment project, the offices were complete to what is
understood as ‘Category A’ that is beyond ‘shell and core’ with raised floors,
suspended ceilings, lighting, cooling and power cabling and sockets all
installed. The space was therefore available and ready for bespoke fit out by
the incoming tenant.
13. Completion Notices under Schedule 4A to the Local Government Finance Act
1988 were issued by post setting a completion date of 6 February 2009. The
precise date on which the notices were issued is unclear but they were
headed ‘Date of Service: 06/02/2009’. The notices were issued by ordinary
post and sent to the correspondence address held at Companies House for
both the company secretary and a director, rather than to the company’s
registered office address. It is not known whether this address was given
either by the company or by their agent for service of notices. The
memorandums drawn up by the Council’s enquiry officer on 3 February 2009,
subsequent to the meeting of 27 January 2009, record Brampton’s address as
20 Brampton Grove, London NW4 4AG.
14. It is not known whether the completion notices were received by the owner but
they were not returned undelivered to the council and the owner did not
appeal or challenge the notices, therefore in the absence of evidence to the
contrary one must conclude they were served.
15. The rating list was altered by the VO on 9 March 2009 to assess the three
separate floors from 9 February 2009 and the entries were carried forward
into the 2010 rating list. On 6 September 2010, with effect from 4 August
2010, the rating list was altered to change the address of the appeal floors
from ‘Thames Towers’ to ‘The Horizon’. No other changes to the
assessments were made at this time.
16. Following practical completion of the works in 2008, the following lettings took
place:
a. Small Ground Floor Suite of 106 m2 from March 2013
b. Large Ground Floor Suite of 600 m2 from June 2014
c. First Floor from March 2015.
17. At the time of the letting of both the large ground floor suite and the first floor,
the landlord and tenants entered into specific licenses for alterations and
fitting out works to take place.
The appeals and proceedings
18. On 31 March 2015, Delph’s former agent, Knight Frank, made proposals
seeking both the deletion of the hereditaments on the ground to second floors
and a reduction in the rateable values. The effective date of all the changes
sought was 1 April 2010. Altus Group was instructed to take over all the
proposals in July 2016 (which by then had become appeals) and recently
agreed a reduction in the rating assessments which left those appeals
seeking a deletion outstanding.
19. The detailed reasons in the proposal (appeals) were set out as being:
This assessment is incapable of occupation and should not have been
entered into the list. VTE decision 0119M27310/212N05 Tull Properties
Ltd V South Gloucestershire Council issued on 7th October 2013
determined that a refurbished building is not a new building so the
completion notice procedure is not valid. In addition under 120131
UKUT 0430 (LC) Aviva Investors and PPG Southern V Whitby (VO) it
was determined that a hereditament should only be assessed for rating
purposes when it is fully fitted out and ready for occupation . This
assessment is incapable of beneficial occupation for office purposes
and should be deleted.
20. The parties made application for the appeals to be treated as complex in
accordance with the Tribunal’s Consolidated Practice Statements (CPS3). I
agreed to the request and also decided to add the Billing Authority as a party
to the appeals, as in part the issues in dispute could have required evidence
on the service of the completion notices. The VTE made Directions which the
parties complied with and a bundle of evidence was provided prior to the
hearing.
Preliminary Issue - Jurisdiction
21. The first respondent raised a preliminary issue as to whether the VTE was
able to override, dis-apply or otherwise overlook the mandatory statutory
deeming provision in s.46A(2) of the Local Government Finance Act 1988 in
circumstances where a completion notice has not been quashed or set aside
by the High Court in judicial review.
22. The second respondent remained neutral on this point. I must add that this
argument was only introduced for the first time by the first Respondent within
his skeleton argument a week before the hearing. The Appellant initially
sought a postponement which I declined, bearing in mind the need to
progress cases and determine them promptly, but by the time of the hearing a
second skeleton argument addressing the issue had been provided, so the
case could proceed.
23. In order to decide this point it was necessary to review the legislation, case
law and previous decisions of this Tribunal.
24. I found the convenient way to set out the process by recording the wise
words of Mr Justice Holgate when he heard the judicial review application in
Reeves (VO) v. VTE (and others) [2015] EWHC 973 (Admin):
“5. The general legal principle is that a building in the course of
construction is treated as not constituting a hereditament for rating
purposes because it cannot be occupied for its intended purpose
(Arbuckle Smith & Co Limited v Greenock Corporation [1960] AC 813).
The same principle may also apply where a building cannot be
occupied while it is being modified so that it may be used for a new
purpose. But where a newly constructed or altered building becomes
capable of occupation for its intended purpose, it is then treated as a
hereditament which may be entered in the rating list (Porter (Valuation
officer) v Trustees of Gladman Sipps [2011] RA 337, paragraph 41).
6. These principles are supplemented by the completion notice code
contained in section 46A and Schedule 4A of the 1988 Act. Two types
of notice may be served. First, where a billing authority is of the view
that a new building can reasonably be expected to be completed within
three months, the authority is to serve a completion notice on the
owner of the building as soon as reasonably practicable (Schedule 4A,
paragraph 1(1)). The notice must specify the completion day proposed
by the authority (paragraph 2(1)), being no later than 3 months from the
date of service.
7. The second type of notice covers a situation where the billing
authority considers that a new building has already been completed
(paragraph 1(2)), in which case the completion date in the notice must
be the date upon which it is served (paragraph 2(3)).
8. In either case, if the owner does not agree with the completion
date specified in the notice he may appeal to the Valuation Tribunal for
England ("VTE") under paragraph 4(1). The only ground of appeal
under that provision is that the building to which the notice relates has
not been, or cannot reasonably be expected to be, completed by the
date stated in the notice.
9. In effect, Schedule 4A contains provisions for determining the
date on which the new building is deemed to be completed. Under
paragraph 3 an agreement may be made between the owner and the
billing authority as to the completion date, in which case the completion
notice is treated as having been withdrawn. Under paragraph 5 if no
appeal is made against the completion notice, and no agreement
reached under paragraph 3, the completion date is taken to be the date
stated in the notice. But where an appeal is made the completion date
is the date determined by the Tribunal (paragraph 4(2)).
10. Where an appeal against a completion notice is made, the only
question which the Tribunal is asked by Schedule 4A to answer is:
what is the completion date?”
25. The matter before me was “what is the correct approach for a challenge
where the Appellant was of the opinion that no valid completion notice had
been served” (my emphasis). I also considered it might be helpful to set out a
full review of the correct route for all of those matters that might be appealed
in connection with a completion notice dispute (as encouraged to do so in
Reeves).
26. In order to understand the point counsel for the Respondent was making, he
helpfully set out the legislation which for convenience I set out below. Section
42 of the Act which is referred to in s. 46A, provides as follows:
42.-Contents of local lists
(1) A local non-domestic rating list must show, for each day in each
chargeable financial year for which it is in force, each hereditament which
fulfils the following conditions on the day concerned-
(a) it is situated in the authority’s area,
(b) it is a relevant non-domestic hereditament,
(c) at least some of it is neither domestic property nor exempt from
local non-domestic rating, and
(d) it is not a hereditament which must be shown for the day in a central
non-domestic rating list.
27. Office premises are relevant non-domestic hereditaments within the meaning
of s. 42(1)(b) of the Act.
28. Counsel argued that the combined effect of s. 46A(2) and s. 42(1) is that
where a completion notice takes effect (whether because no appeal is made
against it or because the VTE determines the relevant completion day on a
statutory appeal under Sch. 4A to the Act), the Valuation Officer is bound to
enter it in the relevant local list with effect from the completion date.
29. The appeals before the Tribunal which were the subject of this dispute, were
made through a proposal seeking removal of the entry in the rating list on the
basis that the appeal hereditaments ‘ought not to be shown in the list’.
30. Counsel concluded that where the Valuation Officer is bound to enter a
hereditament into the relevant local rating list as a result of mandatory
statutory provisions, it cannot be said that a hereditament shown in the list
‘ought not to be shown in the list’ unless there is a subsequent material
change in circumstances which leads to a valid completion notice being
overtaken/superseded by later events.
31. In my view the correct way in which to challenge whether a ‘valid’ completion
notice was in force was through a proposal seeking a removal of the entry in
the rating list on the basis that it ‘ought not to be shown in the list’. I make this
decision for a number of reasons.
32. In Foster v. Chief Adjudication Officer and another [1993], Lord Bridge sitting
in the House of Lords found, when addressing the issue of the jurisdiction of
the social security commissioner, the following at page 764 (E):
It is said that, if the commissioner were intended to have power to hold
a provision in a regulation to be ultra vires and to determine whether or
not it was severable, one would expect to find that he was also
empowered to make a declaration to that effect, which he is not. This,
again, I find quite unconvincing. The commissioner has no power and
no authority to decide anything but the issue which arises in the case
before him, typically, as in this case, whether in particular
circumstances a claimant is or is not entitled to the benefit claimed. If
the success of the claim depends, as here, on whether a particular
provision in a regulation is both ultra vires and severable, the
commissioner’s decision of that question is merely incidental to his
decision as to whether the claim should be upheld or rejected. If not
appealed, his opinion on the question may be followed by other
commissioners, but it has, per se, no binding force in law. To my mind
it would be very surprising if the commissioners were empowered to
make declarations of any kind and the absence of such a power does
not, in my opinion, throw any light on the question presently in issue.
33. As counsel for the Appellant put to me, the Respondent’s opinion is incorrect
as he seems to have misunderstood what is being appealed and sought from
the Tribunal. A proposal to remove from the list a hereditament which ‘ought
not to be shown’ does so, on the basis that the hereditament is not complete
and no (valid) completion notice was served. The Tribunal simply had to find
whether or not there should be an entry in the list. There was no need for the
Tribunal to decide to quash the completion notice for which it held no power to
do so. As part of that test the Tribunal had to decide whether a (valid)
completion notice had been served and if it wasn’t, whether there should be
an entry in the list. If the building was complete and ready for occupation,
then the Tribunal would be justified in leaving the entry alone (as suggested in
Reeves).
34. This in a nutshell addresses counsel’s point. Mr Mackenzie’s starting point
was an assumption that a valid completion notice had been served and on
that basis the entry made and the list altered. If the Tribunal found that no
completion notice (valid) had been served, then the question was whether the
list was correct and the hereditament ought to be shown in it? When I say no
(valid) completion notice had been served, it might be on one of a number of
grounds. These included whether service took place or that whilst service
took place, the document purporting to be a completion notice was so
defective in law that it could not possibly be said to be a completion notice, or
as in the appeals before me, there is no provision in law to serve a completion
notice.
35. Counsel for the Appellant drew to my attention the Court of Appeal’s decision
in UKI (Kingsway) Ltd v Westminster City Council [2017] EWCA Civ 430
where the past President of this Tribunal was found to be correct in deleting
the rating list entry in accordance with a proposal when proper service had not
taken place. At no time did the Court of Appeal question jurisdiction, which of
course they were entitled to do so. The question wasn’t whether to quash the
completion notice but whether a completion notice had been served? If no
completion notice had been served then, in that appeal, there should be no
entry in the rating list as a completion notice was relied upon.
36. The decision of the President of the Upper Tribunal (Lands Chamber) in
Reeves (but when sitting as a High Court judge) found that a challenge to the
validity of a completion notice could be made through a proposal:
“60. I would add, in relation to paragraph 13 of the VTE's decision in
December 2013, a few comments. The making by this Court of an
order to quash the Tribunal's order to delete the hereditament from the
rating list does not render the VTE's decision on the invalidity of the
completion notice academic, or indeed improperly require the ratepayer
to re‑litigate an issue. The position remains that the deeming effect of
the completion notice could not be relied upon in this case. The correct
procedure for the ratepayer to have followed would have been to make
a proposal challenging the entry of Beluga House in the list. That could
have been dealt with at the same time as any completion notice
appeal. That course was open to the first interested party but was not
taken.”
37. Furthermore, despite the observations of Mr Justice Holgate that it wasn’t an
academic exercise in Reeves, the fact of the matter was that the decision in
Beluga House that no valid completion notice had been served and therefore
the building was not capable of occupation meant that the decision of this
Tribunal was ineffective. This resulted in the rating list being inaccurate, an
issue which concerned the President of the Lands Tribunal in Simpsons Malt
Ltd & Others v. Mr Craig Jones & Others (VOs) [2017] UKUT 460 (LC):
…That is not to say that the special features of rating are irrelevant,
including in particular the need, in the public interest, to ensure that the
rating list is accurate…
38. When questioned, Respondent’s counsel was of the opinion that a judicial
review challenge could only decide whether a valid completion notice had
been served. It could not alter the list (see Reeves). This meant that a
finding of such would only result in the Valuation Officer altering the rating list
if he were able to and felt inclined to do so. He would be under no obligation
to do so (although he would have a duty to maintain an accurate list but might
decide it remained accurate without a completion notice being served) and the
remedy would then be for the Appellant to make a proposal to delete the
entry.
39. It would appear to me that a solution was being proposed by the Respondent
which wouldn’t necessarily remedy the point in question.
40. As found in UKI Kingsway the service (or indeed the contents) of a completion
notice, which is a statutory notice and can have significant repercussions for
ratepayers, should not been taken lightly by the Billing Authority or in a
shambolic way. The onus is on the Billing Authority to ensure they undertake
the process properly. Indeed Valuation Officers should satisfy themselves
that the notice they receive complies with the law and that they are correctly
making an entry in the rating list. It would be wrong to require the recipient to
undertake judicial review as a check for both the Billing Authority and
Valuation Officer.
41. However, a word of caution for Tribunal panels and parties. The Tribunal
should not allow frivolous appeals seeking deletion of the entry in the rating
list where the completion notice can be read in such a way to give force to the
intention of the Billing Authority or that a challenge could be made through a
completion notice appeal.
42. The Tribunal put to counsel for the Respondent examples where it would be
clear to everyone that no valid completion notice had been served, one where
the date set was nine months in advance for the work to be completed and
the other where the notice failed to name the building to which it related.
Counsel was quite clear that despite the obvious flaws the Valuation Officer
would enter what he considered to be the properties in the list, even though
he knew the notices were defective and that the Appellants would need to
challenge the notices by judicial review. In fact, time and again the higher
courts have referred to the Tribunal dealing with matters that are obviously
wrong within its own jurisdiction without requiring parties to launch off into
expensive and often sterile litigation where the outcome is plain to all before it
begins: this must be the right and just approach.
43. I also add, that encouraging parties to seek judicial review when a much more
proportionate and less burdensome solution is available does not seem an
attractive proposition for the parties or the higher courts. Whilst the
Respondent Billing Authority remained neutral on this point, I’m not sure
continual visits to the High Court for judicial review applications would be an
attractive proposition to the vast majority of Billing Authorities in this country,
particularly when it comes to the added costs and delay in resolving disputes..
44. I have also reviewed the correct approach on a completion notice appeal. In
Reeves Mr Justice Holgate stated, when confronted with an argument as to
the matters the Tribunal can decide on a completion notice appeal, the
following:
“26. All of these points only serve to emphasise that the question
whether there is jurisdiction in a schedule 4A appeal to consider the
invalidity of a completion notice needs to be determined in a contested
case, or at least one where an undisputed assumption that jurisdiction
exists is tested with the assistance of counsel appointed as a friend of
the court. Full argument and citation of the relevant statutory
provisions and authorities would be necessary.”
45. For completeness, I have decided that the only issue for the Tribunal to
decide where an appeal is made against a completion notice is the date. This
is confirmed in Reeves (para. 10) and indeed was acknowledged by the past
President of this Tribunal in Prudential Assurance Company Limited v
Valuation Officer [2011] RA 490 and as recorded as such in Reeves when
confronted with a completion notice appeal:
“58. I therefore conclude from this review of the legislation that the
Tribunal in this case was not empowered to make the order that the
subject hereditament, namely Beluga House, be deleted from the 2005
rating list.
59. I do not find that conclusion surprising for a series of reasons.
First, the completion notice code simply provides a deeming provision
for the completion date of new buildings. However, a completion notice
may be invalid simply because it was incorrectly served or because the
new structure does not fall within the definition of a new building, that is
to say reasons which have nothing to do with the date when a new
development is completed. Second, treating a completion notice as
invalid merely prevents reliance upon that notice in order to create a
deemed completion date. Thirdly, that does not alter the continuing
duty of the valuation officer under section 41(1) of the 1988 Act to
maintain an accurate list based on the information that comes to his
attention. In most cases a building is likely to be completed at some
point in time, if not by the date deemed to be the completion date under
Schedule 4A. Fourthly, it seems to me to have been unlikely that
Parliament would have intended to confer on the VTE a power to direct
the deletion of a hereditament simply because a completion notice is
held to have been invalid and, as a result, the deeming provisions in
section 46A and Schedule 4A do not apply, bearing in mind the
valuation officer's continuing duty under section 41(1) and the fact that
he is not the originator of a completion notice.
…Indeed, at paragraph 6 of the decision in the Prudential case the
Tribunal took a completely different view of its jurisdiction, in contrast to
the present case, by stating that an appeal against a completion notice
under Schedule 4A is limited to challenging the date of completion and
does not cover any wider or more fundamental aspects”.
46. Both parties before me agreed that this was correct, and whilst not fully
argued , the wording of the legislation and the views of the High Court and the
past President of the Tribunal, confirm that. Therefore in respect of an appeal
against a completion notice the Tribunal can only decide the date. However,
Appellants would do well to heed the decision of the High Court in Reeves, in
that all the Tribunal can do is amend (or quash – see Spears Brothers v.
Rushmoor District Council [2006] RA 86) the notice, and this may still leave
an inaccuracy in the list.
47. Therefore, if an Appellant is of the opinion the outstanding work cannot be
completed within three months, an appeal against a completion notice will not
necessarily, if he is successful, produce the desired outcome which is a
removal of the entry from a rating list. It may be that, as in the case of
Reeves, the list is closed and no alteration can take place but it may also be
because despite the decision of the Tribunal, the Valuation Officer is satisfied
that the list is correct regardless of whether or not a completion notice exists
(a completion notice is not a prerequisite of a new entry in the Rating List).
Preliminary Issue - Time Constraints
48. There was a second preliminary point raised by the second Respondent in
respect of the appeals before me. Counsel stated there was an irrebuttable
presumption that the completion notices were valid arising from the
Appellant’s excessive delay in advancing the appeals (making proposals).
49. The completion notices were served on or about the 6 February 2009. The
original owner did not seek to challenge or appeal those notices. The
Appellant acquired its interest in the hereditaments on 3 November 2010,
following apparently extensive enquiries and investigations. It must have
known of the hereditaments’ appearance in the rating list and/or the
completion notices at the time. A challenge to the list on the basis of a lack of
a valid completion notice was not made until 31 March 2015. The Appellant
had provided no evidence to the contrary or to explain the delay.
50. In support of this contention the second Respondent relied on the decision of
the past President in Friends Life Company v. Alexander (VO) (June 2012 –
052019398853/036N10) where Professor Zellick recorded that a challenge to
a completion notice must be timely and excessive delay will create an
irrebuttable presumption that the notice is valid.
51. I can deal with this point quite shortly . Once I decided that the correct appeal
procedure was to submit a proposal on the grounds stated by the Appellant,
any time constraints must be the subject of those contained within the
relevant regulations. The artificial constraints created by Professor Zellick as
far as I can see have no statutory force and simply don’t exist.
52. This is not to criticise Professor Zellick, in fact I can see clearly what he was
seeking to achieve and indeed from reviewing a number of the decisions, the
very narrow point raised by the Respondent Valuation Officer earlier has
never been fully tested and, therefore the President was, in considering these
matters under a proposal, developing law which I believe to be correct (and
confirmed by the Court of Appeal). However, on the true construction of the
the law there is not a time limit that operates to frustrate the Appellants case.
53. Appellant’s counsel did make one concession on this point and that was to
clarify all he was seeking was to address the periods where he believed no
lawful completion notice had been served, the hereditaments were not
occupied and were not capable of occupation.
54. Time delays of such magnitude as provided in these appeals do not sit
happily with me. It might be very difficult for parties to ascertain the condition
of each hereditament at any one time. Indeed both the Respondents in this
appeal will consider they have been placed in a difficult position.
55. The persuasive or legal burden of proof on these appeals to satisfy me that
they were not capable of occupation during the period of dispute (provided I
find that no valid completion notice could have been served), and therefore
the Valuation Officer should not have entered them into the list, falls on the
Appellant. If he, in this appeal or any Appellant in any other, is unable to
satisfy the panel as to the condition of the hereditament under appeal, then
the appeal should not be allowed.
56. Finally these appeals (proposals) were not made by the initial owner or indeed
during the life of the hereditaments’ entries in the previous list. The question
to be asked was whether at the date the list was compiled (or when removal is
being sought) the entry in the list was correct on the basis that it allegedly
showed a hereditament that ought not to be shown. It would be quite wrong
in law to continue to allow an entry to exist where it relied exclusively on a
completion notice that has never been served or did not exist even when a
new list came into force or ownership of the building changed hands. This
does mean though that if at the ‘material day’ the hereditament was occupied
or indeed capable of occupation the appeal (if other panels follow my
reasoning) cannot be allowed.
57. As a result of my interim decision (published on 9 February 2018) the parties
were directed to advise me within 28 days of receipt whether:
a. The matter was to be appealed;
b. A substantive issue hearing was required; or
c. The appeals were to be settled.
58. I was advised by the parties that a substantive hearing was required and this
was arranged for Friday 11 May 2018 to determine whether the hereditaments
should have been entered in to the List.
The Substantive Issue
59. The parties referred me at the outset of the second hearing to the statement
of agreed facts where there had been a concession by the Respondents. It
was now agreed that the parts of the building in dispute were not capable of
beneficial occupation following practical completion of the works. In essence
this meant that if I found that completion notices had not (or could not have)
been served, the entries must be deleted for the periods in dispute.
60. The Appellant informed me that he wasn’t seeking deletion of all the entries
which arose through the service of completion notices for the life of the 2010
Rating List but a temporary removal in respect of the Ground Floor for the
period 1 April 2010 to 6 March 2013 and for the period 1 April 2010 to 15
March 2015 for the 1st Floor. In respect of the Second Floor I understood that
the deletion was sought for the period of the Rating List.
61. This left the following list of factual matters not agreed:
a. The condition of the property prior to the works being carried out;
b. The scope and extent of the works carried out;
c. Whether those works included alterations that were ‘structural’ in
nature; and
d. The condition that the property was in once the works had reached
practical completion.
62. I set out previously (paragraphs 24 onwards) the completion notice process
and what it sought to achieve. I was required by the parties to decide, and it
seemed to me the natural starting point, whether the whole of The Horizon
was a new property following the redevelopment works.
63. The first Respondent informed me, and it was not disputed by the Appellant,
that it was apparent from s.46A and the decision of the past President of this
Tribunal that there are two sub-categories of buildings which are ‘new
buildings’ (or part thereof) in accordance with s. 46A(1), namely:
a. Buildings which are new in the conventional sense, i.e. ‘brand new’
buildings (the conventional test); and
b. Buildings which are not ‘brand new’ but which qualify as ‘new buildings’
for the purposes of s.46A(1) because they have been so transformed
by alterations (and not necessarily structural alterations) that it is apt to
describe them as new buildings.
64. The first Respondent argued in the first instance that the whole of the building
(referred to as ‘the Building’) was a new building. He accepted that it was not
‘brand new’ but that the conversion of an office block, to offices and domestic
accommodation was such a significant change that it transformed the building
in to a new building.
65. The first Respondent drew my attention to the following changes:
a. prior to the redevelopment the Building was in an office-only use;
b. after the redevelopment the upper floors of the Building had been
wholly re-purposed for a residential use comprising 112 brand new
residential units;
c. the shear core of the Building had been altered and external balconies
added to the tower floors;
d. in order to support the residential use of the Tower floors, a ‘domestic
support’ area at Ground Floor level within the Building had been carved
out from the previous office unit;
e. the separation between residential and office uses at the Building was
reflected in the creation of separate access points within the Building
for these two separate uses;
f. the existing office accommodation at Ground, First and Second Floor
levels had been renewed to Category A specification in order to obtain
a letting;
g. the atrium of the premises comprising the Second Floor was in-filled to
create a roof terrace for the residential units; and
h. the Building was re-named in 2010 to reflect the fact that the
redevelopment had, in form and in substance, resulted in the creation
of a new building in Leicester.
66. In support of this he referred to the past President of this Tribunal’s decision in
Tull Properties Ltd V South Gloucestershire Council (0119M27310/212N05 -
issued on 7th October 2013) as to how he is able to form such a view. In that
appeal Professor Zellick stated:
“26. I have no hesitation in rejecting the respondents first argument that the
alterations to Beluga House created a “new building” according to the ordinary
meaning of that expression. In my judgment, it was plainly the same building
after the alterations as it was before. I am sure there can be buildings so
transformed by alterations that it is apt to describe them as new
buildings, but it takes more than a new floor, a lift, some windows,
additional lavatories and a reception desk. “(my emphasis in bold)
67. There had been a number of significant alterations to the building, but were
they so significant to transform it in to something else? I do not believe so.
With the exception of new cladding and the addition of balconies, the building
is basically the same. If you look at the skyline of the building before and after
you would notice little difference. The footprint of the shell has had little
significant change. I believe there would need to be a clear and significant
change to the shape or size of the building or to its character to create a new
building out of an existing one. A change of use from full non-domestic to part
non-domestic and domestic was not sufficient in my opinion to change its
character.
68. In conclusion I found that what occurred was not the creation of a ‘new
building’ but the redevelopment of an existing one. The identity of the
Building remained the same although it has moved from being purely office, to
office with domestic accommodation. I’m sure if the good folk of Leicester
were asked whether the building after the works was the same as before, the
answer would be yes but providing an additional facility, namely domestic
accommodation.
69. Furthermore, even if I am wrong on this point, the Billing Authority didn’t serve
one completion notice but a number for various parts. It is each of those parts
I needed to focus on as new buildings and in each case; they were not the
elements where significant alterations occurred to convert from offices to
domestic accommodation.
70. The question then for me to answer was whether each part meets the criteria
in s.46A(6)( that is the three areas subject to individual completion notices).
71. The past President set out in his decision in Tull Properties his understanding
of the law on this point:
“7. The legislation governing this matter is found in the Local Government
Finance Act 1988, s. 46A and Sched. 4A. The notice in this case was issued
under para. 1(1) of Sched. 4A, where a new building is incomplete but can be
completed within three months. The respondent contends that Beluga House
is a new building in the ordinary, everyday sense of the language or
alternatively that it falls within what Mr Lewsley calls the expanded meaning of
new building which is found in s. 46A(6), which is the only provision that
needs to be set out in full:
“In this section –
(a) “building” includes part of a building, and
(b) references to a new building include references to a building produced by
the structural alteration of an existing building where the existing building is
comprised in a hereditament which, by virtue of the alteration, becomes, or
becomes part of, a different hereditament or different hereditaments.”
8. I accept Mr Lewsley’s submission that subsection (6)(b) introduces an
alternative test so that under the Act the building must either be “new” under
subsection (1) or a building that satisfies the requirements of subsection (6)(b)
and is thus regarded as or deemed to be new for this specific purpose. He
calls this the expanded meaning which goes beyond the natural meaning in
ordinary English.
9. He asserts, and I accept, that the two components of the test under
subsection (6)(b) are –
(i) was the present building produced by the structural alteration of an
existing building; and
(ii) has the hereditament, by virtue of the alteration, become a different
hereditament or different hereditaments?
10. The questions for me, therefore, are (i) whether the works done to
Beluga House have produced a “new building” in the ordinary sense of
that expression or (ii) whether they constitute a structural alteration to the
hereditament which in consequence becomes a different hereditament or
hereditaments. There is no dispute over the meaning of “hereditament”, so
I shall not lengthen this decision by exploring its meaning. “
72. Counsel for the Appellant introduced six tests or hurdles when considering
this point. Similarly counsel for the first Respondent introduced four.
However, in my opinion all they were doing was breaking down Professor
Zellick’s approach in to smaller bite size chunks, which may be intellectually
interesting but of little real assistance in determining the issue: I prefer
Professor Zellick’s formula. There was one exception which does require
further investigation, and that is in connection with the language used.
73. Counsel for the Appellant argued that the existing building, to which the
structural works have taken place, must (prior to the works) have been
‘comprised in a hereditament’. Counsel argued that this suggested (and he
put no stronger word on the point) that where the existing building was
comprised in multiple hereditaments, s. 46A(6)(b) did not apply. Whilst he
conceded it produced a curious outcome, he argued that the reference to
‘hereditament’ singular was deliberate. That could be seen by the express
adoption, at the end of s.46A(6)(b), of the phrase ‘a different hereditament or
different hereditaments’ in the context of the post-works building.
74. Counsel for the first Respondent quite rightly drew me to the fact that when
interpreting legal provisions, unless clearly inappropriate, the singular term
should also be construed to mean the plural. Indeed, to do anything other
than this would create nonsense in cases such as these, where if the original
building as a whole was in one occupation and therefore one hereditament, it
would be treated differently to where the building was split. Not because of
any structural changes, but purely down to the nature of the occupations.
Indeed, there must be an argument that in the appeal before me there was
only one hereditament in one ownership prior to the work commencing.
Counsel for the first Respondent also drew my attention to other parts of the
legislation where the term ‘hereditament’ is used but can mean
‘hereditaments’. I am afraid that whilst, this was a bold and brave stance by
Mr Wilcox, it doesn’t even get out of the starting blocks and one argument I
am happy to dismiss without the need for further consideration.
75. This then leaves me with the questions set out by Professor Zellick. As
mentioned above both parties sought to break them down further which I
believed I did not need to do. The one concession I gave to Mr Wilcox was
that I had to be mindful that there must be a causative link between the
structural alteration and the building that is produced.
76. Much time was spent by the parties on the meaning of ‘structural alteration’.
One reference provided by the Appellant was the recent Court of Appeal
decision in Keith Newbigin (Valuation Officer) v. SJ & J Monk (A Firm) [2015]
EWCA Civ 78. This decision, in respect of the legal assumption of a state of
reasonable repair, was overturned by the Supreme Court. Counsel for the
Appellant informed me that the non-structural nature of the stripped-out
elements was not addressed by the Supreme Court and that this aspect of the
Court of Appeals approach remains undisturbed.
77. The state of the building was described by the Court of Appeal in the following
terms:
It was agreed that on 6 January 2012, which is the material date, the physical
state of the hereditament was as follows:
i) The first floor was vacant.
ii) The majority of the ceiling tiles and suspended ceiling grid and
light fittings had been removed.
iii) Approximately 50% of the raised floor had been removed.
iv) The comfort cooling system including all internal and external
plant had been removed.
v) The sanitary fittings had been removed and the block walls to
the WCs demolished.
vi) The electrical wiring had been stripped out.
vii) Plasterboard partitions had been erected and plastered to form
the outline for the WCs and a partition had been erected and
plastered across the floor at the east side of the building.
viii) First fix electrical installations to the WC area had been completed
and alterations made to the drainage.
78. The Court of Appeal held (at paragraph 30):
The subject-matter under discussion in our case is the hereditament as a
whole. In my judgment the replacement of the stripped out elements (none of
which was structural) can fairly be described as the replacement of subsidiary
parts of that whole. I would hold, therefore, applying Buckley LJ’s test that the
works in question can fairly be described as repairs…
79. One assumes that was a matter of fact, and indeed the elements described
would not appear to me to fall in to the category of ‘structural work’.
80. In Tull Properties the past President found that Beluga House didn’t meet the
test in s. 46A(6)(b). The work undertaken included the blocking up of
doorways, the creation of new windows, and the installation of new reception
areas and the enlargement of toilet areas.
81. Mr Wilcox concluded that all of the works undertaken at the buildings under
appeal were not structural and therefore didn’t meet the test. In support of his
contention, he referred to the Elliot Wood Partnership report of a structural
engineer which identified two areas where structural work had been
undertaken:
a. New balcony connections (not part of the buildings in dispute); and
b. Opening up of shear walls (also not relevant).
82. This report highlighted structural risks and was issued in May 2010 (two years
after the work). Clearly any item included in the list that covered work
undertaken during the conversion would be structural but its absence doesn’t
mean that structural alterations hadn’t taken place. The report wasn’t
prepared for the purpose of the hearing and the absence of any works from it
doesn’t mean they didn’t occur.
83. Mr Wilcox concluded that on the basis of the reports no structural alterations
occurred on any of the three floors in question. However, I am required to
examine all the evidence available given the limitations of the report.
The First Floor
84. It is not disputed by the parties that no structural alteration took place of any
consequence. On that basis a completion notice cannot be served and the
entry in the rating list must be deleted for the period 1 April 2010 to 15 March
2015.
The Second Floor
85. In respect of this area a large atrium in the ceiling was removed and in-filled.
Counsel for the second Respondent put to me that the external area had been
altered in both size and nature. It also created a roof garden above. This
was, in my opinion, a significant element of structural work with a large
amount of concrete and steel used. The works removed an atrium and
created an area of floor/roof which was utilised as a garden; by definition this
work must be structural as it clearly altered the use of the area involved and
even without of expert professional evidence from either side, it would defy
common sense to suggest these works were not of a structural nature.
Therefore, I find as a fact that as the works were structural in nature,
undertaken at the time of the conversion and affected the size and nature of
the floor it met the criteria set out by Professor Zellick in his two questions
(see above).
The Ground Floor
86. This was probably the hardest building to resolve. First of all, there appeared
to be little hard evidence of what did take place at the time of the works and
with the burden on the Appellant to prove his case, the evidence advanced
was not as clear cut as one might have hoped. However, having said that
there was some evidence of what took place and a number of assumptions
could be made from the layout of the area post the works as to what had
happened.
87. The parties don’t agree on whether any structural works were undertaken
during the redevelopment of the ground floor. From the evidence provided it
would appear an area was partitioned off to create a domestic entrance to the
flats above, a bin storage area and other associated services. An area
marked retail sales with a separate entrance on the plans was never
developed, leaving the only works described above that created what I have
called the ‘associated domestic support zone’.
88. On their own they would, in my opinion create a sufficient change to the
previous office area to create different hereditaments passing the second
question set by Professor Zellick. However, did any structural alterations
create these areas and consequently the Ground Floor in dispute? On the
findings of the Court of Appeal in Newbigin and the observations of Professor
Zellick in Tull Properties the works that took place could not be said to be
structural.
89. All parties seemed to consider that if I find for the Appellant in these appeals it
created a lacuna in the legislation, in that buildings which were developed but
not structurally altered could not be brought back in to the Rating List. The
Respondents argued that this cannot have been the intention of Parliament,
whereas the Appellant contended that I should not read words in to legislation
which were not present and created a different interpretation.
90. Simply put, as Professor Zellick found, I must read the legislation as it exists
and there is no scope for reading in to the statute words that are not there. It
may be that as a result of the Upper Tribunal decision in Porter v. Gladman
Sipps Tewkesbury Ltd [2011] UKUT 204 (LC) the test to bring a hereditament
in to the Rating List, or indeed back in to the Rating List, is much harder than
before and relies much more, if empty, on a completion notice being served.
But, that is the correct test as far as I can see and if a lacuna exists it is for
Parliament to address, not me.
91. On that basis the appeals in respect of the Ground Floor and First Floor are
allowed, whereas the appeal in respect of the Second Floor is dismissed.
92. May I conclude my extending my thanks to counsel for all parties for the most
professional and helpful way they conducted their arguments with a refreshing
brevity and lack of repetition, that one sees in some cases that have not been
as well prepared.
Order:
As a result of this decision the Valuation Officer is ordered to delete the entries in the
Rating List in accordance with Regulation 38 of the Valuation Tribunal for England
(Council Tax and Rating Appeals) (Procedure) Regulations 2009 as follows for the
periods stated:
Ground Floor, Thames Tower, 99 Burleys Way, Leicester for the period 1 April
2010 to 3 August 2010;
Ground Floor, The Horizon, 99 Burleys Way, Leicester for the period 4 August
2010 to 6 March 2013;
1st Floor, Thames Tower, 99 Burleys Way, Leicester for the period 1 April
2010 to 3 August 2010; and
1st Floor, The Horizon, 99 Burleys Way, Leicester for the period 4 August
2010 to 15 March 2015.
The Valuation Officer must comply with this Order within two weeks.
Mr G Garland
President
Mr J Bestow
Registrar
APPEAL NOs: 246525454690/538N10
246525454849/538N10
246525454856/538N10
246525454862/538N10
246525454867/538N10
22 May 2018 246525454875/538N10