+ All Categories
Home > Documents > SUMMER INTERNSHIP REPORT ON

SUMMER INTERNSHIP REPORT ON

Date post: 30-Dec-2016
Category:
Upload: leliem
View: 291 times
Download: 7 times
Share this document with a friend
83
SUMMER INTERNSHIP REPORT ON DETAILED PROCEDURE AND FINANCIAL MODELING FOR DEVELOPMENT OF A GREEN FIELD WIND POWER PROJECT UNDER THE GUIDANCE OF Mrs Sreelata Nilesh, Senior Fellow, CAMPS, NPTI & Mr Rajat Roy, Dy. Manager, Ecoren Energy India Pvt Ltd At Ecoren Energy India Pvt Ltd Submitted by PARTH BELANI ROLL NO: 1120812204 MBA (POWER MANAGEMENT) (Under the Ministry of Power, Govt. of India) Affiliated to MAHARSHI DAYANAND UNIVERSITY, ROTHAK AUGUST 2012
Transcript
Page 1: SUMMER INTERNSHIP REPORT ON

SUMMER INTERNSHIP REPORT ON

DETAILED PROCEDURE AND

FINANCIAL MODELING FOR DEVELOPMENT OF A GREEN FIELD WIND POWER

PROJECT

UNDER THE GUIDANCE OF

Mrs Sreelata Nilesh, Senior Fellow, CAMPS, NPTI

& Mr Rajat Roy, Dy. Manager, Ecoren Energy India Pvt Ltd

At

Ecoren Energy India Pvt Ltd

Submitted by

PARTH BELANI ROLL NO: 1120812204

MBA (POWER MANAGEMENT)

(Under the Ministry of Power, Govt. of India)

Affiliated to

MAHARSHI DAYANAND UNIVERSITY, ROTHAK

AUGUST 2012

Page 2: SUMMER INTERNSHIP REPORT ON

ii

TRAINING COMPLETION CERTIFICATE

Page 3: SUMMER INTERNSHIP REPORT ON

iii

DECLARATION

I, Parth Belani, Roll no. 1120812204, student of MBA (Power Management) at National

Power Training Institute, Faridabad, hereby declare that the summer training report

programme of the National Power Training Institute, Faridabad hereby declare that the

Summer Training Report entitled –

“DETAILED PROCEDURE AND FINANCIAL MODELING FOR DEVELOPMENT OF A

GREEN FIELD WIND POWER PROJECT”

Is an original work and the same has not been submitted to any other Institute for the award

of any other degree.

A Seminar presentation of the Training Report was made on ……………….. and the

suggestions as approved by the faculty were duly incorporated.

Presentation In charge Signature of the

Candidate (Faculty)

Countersigned

Director/Principal of the Institute

Page 4: SUMMER INTERNSHIP REPORT ON

iv

ACKNOWLEDGEMENT

I express my sincere thanks to Mr Rajat Roy (Business Development Manager), Ecoren

Energy India Private Limited for giving me a great opportunity to work in such an esteem

organization. I am solemnly thankful to Mr Rakesh Patel (Business Analyst), Ecoren Energy

India Private Limited for his guidance and support. I am also thankful to the entire staff of,

Ecoren Energy India Private Limited for sharing their knowledge and assistance.

I feel deep sense of gratitude towards Mr J.S.S. RAO, Principal Director, CAMPS (NPTI),

Mr S. K. Chaudhary, Principal Director, CAMPS, Mrs Indu Maheshwari, Dy. Director,

NPTI and Mrs Manju Mam, Dy. Director, NPTI, Dr Rohit Verma, Dy. Director, NPTI for

arranging my internship at Ecoren Energy India Private Limited. I also take this opportunity

to express my sincere thanks to Mrs Sreelata Nilesh (Senior Fellow), NPTI for being my

internal project guide and providing valuable inputs in the completion of this project.

.

Page 5: SUMMER INTERNSHIP REPORT ON

v

EXECUTIVE SUMMARY

In April 2012 Indian power sector reached a tremendous milestone of achieving 2,00,000

MW of total installed power capacity. Commencing with a meagre installed capacity of about

1360 MW in 1947, the year the country attained independence, India’s power sector grew

substantially over the last six and a half decades, and the installed capacity at the end of June

2012 stands at 2,05,340 MW. However contribution of renewable power is 24,833 MW,

which is only 12.1% of the total installed capacity. Further, the Government of India desires

to significantly improve the country's annual per capita consumption. The government has

not been successful in its efforts to achieve per capita consumption of 1000 units and to

ensure a minimum lifeline consumption of 1 unit per household per day as a merit good by

the year 2012. In order to achieve this scale of supply and ensure sufficient electricity to all at

reasonable rates, it is necessary to explore all possible options of generating and supplying

electricity.

Renewable energy sources can make important contributions to sustainable development.

Currently, their exploitation in commercial markets is low, mainly because of high cost and

technological constraints. Most renewable energy technologies are still at an early stage of

development. However wind power, compared to other renewable energy sources, has lower

costs and improved technology. Development of wind power projects, therefore, is a key to

India’s future economic growth looking at the benefits of wind energy and the energy deficit

the country is facing today. Nevertheless, investors’ lack of interest in wind energy sector is

conspicuous because of lack of procedural understanding of development of wind power

projects.

The need for defining an effective and comprehensive wind power project implementation

methodology for India is imperative. Not only there are growing uncertainties about the

critical as well as sub critical activities of wind power projects implementation, but the

information associated with them is meagre and highly dispersed in nature and is not easily

available. Insufficient information may lead to misleading decisions by project developers

and investor’s. Many wind power project investments are not implemented, not because of

financial, technical, commercial, managerial or regulatory aspects, but merely because of

procedural complexities and inadequate guidelines about them.

Page 6: SUMMER INTERNSHIP REPORT ON

vi

Therefore this study is intended to explicate a generalized methodology for wind power

project implementation. This methodology will act as a source of knowledge for wind energy

power project implementation to the stakeholders of the Indian power sector.

This report includes all the major steps that are required to take for putting in place a wind

power project. It starts with project and financial planning procedure followed by factors that

need to be taken into consideration for selecting a state of preference. The project then guides

about feasibility study, wind resource assessment, site survey, micro-siting, land acquisition,

financial planning & strategy, and power sale options. The project also includes financial

modelling that can help the investor in his decision of whether to accept or reject the project.

Page 7: SUMMER INTERNSHIP REPORT ON

vii

LIST OF ABBREVIATIONS

CDM Clean Development Mechanism

CPV Concentrated Photo Voltaic

CEA Central Electricity Authority

CERC Central Electricity Regulatory Commission

CUF Capacity Utilization Factor

IEGC Indian Electricity Grid Code

KWh Kilo Watt Hour

MNRE Ministry of New and Renewable Energy

MoP Ministry of Power

MW Megawatt

NLDC National Load Despatch Centre

NOC No Objection Certificate

O&M Operation & Maintenance

PLF Plant Load Factor

PPA Power Purchase Agreement

RE Renewable Energy

REC Renewable Energy Certificate

RET Renewable Energy Technology

RPO Renewable Purchase Obligation

SERC State Electricity Regulatory Commission

SHP Small Hydro Plant

SLDC State Load Despatch Centre

SNA State Nodal Agency

Page 8: SUMMER INTERNSHIP REPORT ON

viii

LIST OF TABLES

Table 1 : State wise Wind Power Till 2020 .......................................................................... 17

Table 2 : State Feed-in-Tariffs ............................................................................................. 18

Table 3 : Sharing of CDM Benefits in Different States ........................................................ 23

Table 4 : Reactive Energy Charges ...................................................................................... 23

Table 5 : State wise Banking Regulations ............................................................................ 24

Table 6 : State wise Transmission and Wheeling Charges ................................................... 25

Table 7 : REC Floor and Forbearance Prices of REC ........................................................... 44

Page 9: SUMMER INTERNSHIP REPORT ON

ix

LIST OF FIGURES

Figure 1 : Financial Planning Process .................................................................................. 15

Figure 2 : Wind Power Potential and Installed Capacity ...................................................... 16

Figure 3 : State wise Achievable wind Potential Till 2020 ................................................... 17

Figure 4 : Feed-in-Tariff...................................................................................................... 18

Figure 5: Feasibility Study .................................................................................................. 27

Figure 6 : CDM Timeframe ................................................................................................. 40

Figure 7 : CDM Project Cycle ............................................................................................. 41

Figure 8 : REC Procedure.................................................................................................... 44

Figure 9 : REC Mechanism ................................................................................................. 45

Figure 10 : Hurdles in Financial Closure ............................................................................. 51

Figure 11 : Power Sale Options ........................................................................................... 53

Figure 12 : Parameters of Financial Modelling .................................................................... 59

Figure 13 : Cost Estimate per Project Phase ........................................................................ 60

Figure 14 : Project Cash-flow and Key Indicators................................................................ 62

Figure 15 : Types of Risk in Various Phases of Project........................................................ 63

Page 10: SUMMER INTERNSHIP REPORT ON

x

Table of Contents

TRAINING COMPLETION CERTIFICATE ................................................................................................ ii

DECLARATION .................................................................................................................................. iii

ACKNOWLEDGEMENT ...................................................................................................................... iv

EXECUTIVE SUMMARY ....................................................................................................................... v

LIST OF ABBREVIATIONS ...................................................................................................................vii

LIST OF TABLES ................................................................................................................................ viii

LIST OF FIGURES ................................................................................................................................ix

Table of Contents .............................................................................................................................. x

CHAPTER 1: INTRODUCTION .............................................................................................................. 1

1.1 About the project..................................................................................................................... 1

1.2 Problem Statement .................................................................................................................. 2

1.3 Scope of Project ....................................................................................................................... 2

1.4 Objective of the project ........................................................................................................... 2

1.5 Methodology ........................................................................................................................... 2

1.6 About the organisation ............................................................................................................ 3

1.6.1 Critical Assessment of the Organization............................................................................. 4

CHAPTER 2: LITERATURE REVIEW AND POLICY FRAMEWORK ............................................................. 5

2.1 Literature Review ..................................................................................................................... 5

2.2 Policy Framework .................................................................................................................. 10

2.2.1 National Electricity Policy, 2005 ...................................................................................... 10

2.2.2 National Tariff Policy, 2006.............................................................................................. 10

2.2.3 Rural Electrification Policy, 2006 ..................................................................................... 11

CHAPTER 3: WPP DEVELOPMENT PROCEDURE ................................................................................ 12

3.1 Introduction - Wind Power Project development procedure .................................................. 12

3.2 Project and Financial Planning................................................................................................ 13

3.2.1 Project Planning .............................................................................................................. 13

3.2.2 Financial Planning ........................................................................................................... 13

3.3 Selection of State of preference ............................................................................................. 16

3.3.1 Wind Power Potential and Installed Capacity .................................................................. 16

3.3.2 Feed-in-Tariffs ................................................................................................................. 17

3.3.3 Special incentives and facilities by State Governments .................................................... 18

3.3.4 Simplicity of procedures followed in the State ................................................................. 20

3.3.5 Evacuation Infrastructure ................................................................................................ 21

Page 11: SUMMER INTERNSHIP REPORT ON

xi

3.3.6 Grid availability ............................................................................................................... 22

3.3.7 Regularity in the receipt of payment ............................................................................... 22

3.3.8 Sharing of CDM Benefits.................................................................................................. 22

3.3.9 Reactive Energy Charges ................................................................................................. 23

3.3.10 Banking ......................................................................................................................... 24

3.3.11 Transmission and wheeling charges............................................................................... 25

3.4 Site Identification ................................................................................................................... 25

3.5 Feasibility Study ..................................................................................................................... 26

3.5.1 Generalized activities for feasibility study of Wind Power Projects: ................................. 27

3.6 Mast Installation, Data Collection and Data Verification ......................................................... 31

3.6.1 Permission for Mast Installation and Subsequent Capacity Allocation ............................ 31

3.6.2 Installation of Wind Mast ................................................................................................ 33

3.6.3 Data collection ................................................................................................................ 33

3.6.4 Validation of Data through CWET .................................................................................... 34

3.7 Site Survey ............................................................................................................................. 34

3.7.1 Soil / Ground Conditions ................................................................................................. 34

3.7.2 Soil Erosion ..................................................................................................................... 34

3.7.3 Accessibility .................................................................................................................... 35

3.7.4 Closeness to Grid ............................................................................................................ 35

3.8 Wind Farm Layout.................................................................................................................. 36

3.8.1 Inter-turbine separation .................................................................................................. 36

3.8.2 Changes in elevation of area ........................................................................................... 37

3.8.3 Other factors ................................................................................................................... 37

3.8.4 Layout using software ..................................................................................................... 37

3.9 Land acquisition ..................................................................................................................... 37

3.10 Clean Development Mechanism ........................................................................................... 40

3.10.1 CDM project cycle ........................................................................................................ 41

3.11 Renewable Energy Certificates ............................................................................................. 43

3.11.1 Types of REC ................................................................................................................. 44

3.11.2 The operational framework for REC mechanism ............................................................ 44

3.12 Detailed Project Report ........................................................................................................ 47

3.12.1 Contents to be covered in a DPR ................................................................................... 48

3.13 Financing Strategy and Financial Closure .............................................................................. 49

3.13.1 Financing strategy ......................................................................................................... 49

Page 12: SUMMER INTERNSHIP REPORT ON

xii

3.13.2 Financial Closure ........................................................................................................... 50

3.14 Power Sale options .............................................................................................................. 53

3.15 Physical implementation of the Project ................................................................................ 54

3.15.1 Engineering ................................................................................................................... 54

3.15.2 Procurement ................................................................................................................. 55

3.15.3 Construction ................................................................................................................. 55

3.15.4 Testing and Commissioning ........................................................................................... 57

3.15.5 Operation and Maintenance ......................................................................................... 58

CHAPTER 4: FINANCIAL MODELLING ................................................................................................ 59

4.1 Cost estimates ....................................................................................................................... 59

4.2 Development of a project model ........................................................................................... 60

4.3 Analysis of financial indicators ............................................................................................... 61

4.4 Sensitivity Analysis ................................................................................................................. 62

4.5 Risk analysis ........................................................................................................................... 63

4.5.1 Assessing risk .................................................................................................................. 63

4.5.2 Managing Risk ................................................................................................................. 64

CHAPTER 5: SUMMARY.................................................................................................................... 65

5.1 Conclusion ............................................................................................................................. 65

5.2 Recommendations ................................................................................................................. 67

Bibliography .................................................................................................................................... 69

ANNEXURES .................................................................................................................................... 71

Page 13: SUMMER INTERNSHIP REPORT ON

1

CHAPTER 1: INTRODUCTION

1.1 About the project

In April 2012 Indian power sector crossed a remarkable milestone of crossing 200000 MW of

total installed capacity. On 30th

June 2012, the country’s total installed power capacity stood

at an enormous figure of 205340.26 MW, out of which total renewable energy was 24832.68

MW. The share of Wind energy in Renewable energy produced in India is very high at 70%.

Still, India’s goal of ‘energy security’ is far from achieved. India has peak demand power

shortage of 12% and the cost of Fossil fuel is increasing day by day. Also, in National Action

Plan for Climate Change (NAPCC), India has committed to increase its renewable energy

share to 15% by 2020. Development of renewable energy, therefore, is necessary if Indian

economy is to achieve sustainable growth at fast pace in the future.

Nevertheless, increasing the share to renewable energy in India’s energy mix is a difficult

task, renewable energy being far more expensive compared to the conventional energy.

Wind power is less expensive compared to all other potential sources of renewable energy

like solar power. Also, India has huge unexplored wind power potential. The estimated Indian

wind energy potential has been assumed by the Ministry of New and Renewable Energy in a

study conducted in the late 90's to be 45000 MW. A more recent study by C-WET, India's

wind energy potential is estimated to be more than 1,00,000 MW at a hub height of 80

metres. Therefore utilising wind potential seems to a one of the most credible way to achieve

India’s energy security.

The development of a wind power project is a complex task because of technical, managerial

and regulatory hurdles. Apart from that, different procedures are followed in different states

for various activities, which play its part in increasing the complexity. Hence this sector is not

attracting large investments. This Report, therefore, is an attempt to guide the investors to

understand the complex procedure of wind power development.

Page 14: SUMMER INTERNSHIP REPORT ON

2

1.2 Problem Statement

Development of wind power project, which is a necessary task for achieving India’s energy

security, is a complex task. Different tariffs, policies and procedures followed in various

Indian states add to this complexity. Apart from this, benefits like Accelerated Depreciation

(AD) and Generation Based Incentives (GBI) are abandoned. Hence the wind power sector,

compared to conventional energy sources, is less attractive to investors. Therefore there is a

need of a document that can guide the investors to understand the procedure of a WPP

development. This report is an attempt in this direction.

1.3 Scope of Project

This project is an attempt to be guideline to the cumbersome procedure of setting up a wind

power project. It deals with all the technical, economic and regulatory issues related to WPP

development. The differences in policies/procedures followed in different states in the

permission of wind resource assessment, land acquisition, feed-in-tariffs etc. are also covered

in this report so that it can be useful to understand the diversities in various states with regard

to wind power. This report also covers financial modelling of a wind power project which can

be a guideline for checking financial viability of a WPP.

1.4 Objective of the project

Wind power development is a riskier investment compared to the investments in conventional

sources of energy. In India, diversities in policies/procedures in different states make it even

more risky and hence unattractive. The objective of the project is to guide the investors in

understanding the procedure of development of wind power project. The intension is to

persuade investments in the wind power sector by making the understanding of WPP

development procedure simpler. By making the WPP development attractive by developing

more understandable, the project is intended to contribute in India’s pursuit of energy

security.

1.5 Methodology

The project has been prepared by gathering the dispersed information about various

proceedings of wind power project development. The regulations of State Electricity

Page 15: SUMMER INTERNSHIP REPORT ON

3

Regulatory Commissions (SERCs) of states with major wind energy potential have been

studied. These states include Andhra Pradesh, Karnataka, Gujarat, Rajasthan, Madhya

Pradesh, and Maharashtra. The guidelines published by various State Nodal Agencies (SNAs)

for procedures like land acquisition and capacity allocation have been gathered and

understood deeply for making this project useful. Experience of the Business Development

team of Ecoren Energy India Private Limited has added value to this project. All the

information gathered as mentioned above was then studied and put in proper sequence to

understand the flow of the development procedure. Technical books have been studied to add

major important technical issues and their solutions that need to be included in the project.

1.6 About the organisation

Launched in September, 2010, ECOREN ENERGY has been set up by a group of private

investors with the help of number of prominent Indian banks, and insurance companies.

Ecoren Energy India Private Limited is a renewable Independent Power Producer (IPP)

focused on development, owning and operating wind power projects across India. The

company is currently focusing on the states of Andhra Pradesh, Karnataka, Maharashtra,

Rajasthan, Madhya Pradesh and Gujarat for development of wind power projects. Ecoren is

led by visionary management with the objective of creating green and sustainable business

models and promoting renewable energy. Ecoren’s Vision is to demonstrate responsible

leadership in mainstreaming renewable sector in the energy space by innovation, cost-

effectiveness and profitable growth. Ecoren’s team comprised of talented and experience

individuals across the domains of Project management & execution, Regulatory, Technical,

Finance, Business Development and Wind Resource Assessment.

Page 16: SUMMER INTERNSHIP REPORT ON

4

The ECOREN Factor

Ecoren is distinctive in how it balances stakeholder value, with social responsibility to make

the world a better place and to do so profitably. The organisation keeps this philosophy in the

core of its values, and wants to achieve this with a sense of pride, ownership and long-term

commitment in all of its projects from start to finish.

1.6.1 Critical Assessment of the Organization

Strengths

Core Team of expert professionals.

Excellent work Culture

Knowledge management

Intellectual capital

Reporting performance

Technical expertise

Weaknesses

Relatively new organization

Small Workforce

Opportunities

Global shift towards Renewable energy

Liberalising Government perspective towards RE generators

Young and talented workforce of India

More stress on renewable energy

Threats

High degree of openness may lead to information leakage

Capture of efficient windy sites by older and bigger players in the wind power sector

Page 17: SUMMER INTERNSHIP REPORT ON

5

CHAPTER 2: LITERATURE REVIEW AND POLICY

FRAMEWORK

2.1 Literature Review

Literature has been prepared by authors all around the world explaining whole procedure

wind power project development or a part of the mighty procedure. The papers/journals

reviewed before preparation of this report, and a brief about them is explained here.

“Siting and output prediction for wind energy project planning”, a paper presented by B.H.

Bailey (AWS Sci., Albany, NY) at Power Engineering Society Winter Meeting, focuses on

outlay of wind farms. This paper summarizes and illustrates the steps involved when siting

and planning the design and performance of wind power plants. The topics covered are: site

screening techniques and parameters; wind resource mapping as a siting tool; the role and

design of wind measurement campaigns; optimizing wind plant turbine layout using

advanced modelling tools; predicting a site's long-term wind resource and annual wind plant

production; and due diligence reporting to obtain project financing.

A paper titled “Research of wind power project risk assessment based on Hierarchy-grey

Analytic Method” appeared in an international conference “Mechatronic science, Electric

Engineering and Computer (MEC), 2011”. The paper was presented by Younggui (Sch. of

Bus. Adm., North China Electrical. Power Univ., Baoding, China) et al on August 2011. This

report explains that Global environmental problems have become increasingly prominent.

Wind power as a clean and renewable energy, becomes various countries gradually in the pet

who seeks in the energy alternative process. Wind power in the global range has developed

rapidly, but it should realize that wind power project is also a risk in the process of

development cannot be avoided. This article needle wind power projects characteristic,

Hierarchy-grey Analytic Method is proposed based on the wind project risk assessment

methods. Through carries on the empirical analysis to some wind electricity project to draw

the conclusion. Then carries on the wind electricity project for the enterprise the risk

management to provide the basis.

On April 2008, at Electric Utility Deregulation and Restructuring and Power Technologies,

2008, Author N.R. Ullah (Chalmers University, Goteborg) et al presented a paper titled

“Detailed modelling for large scale wind power installations - a real project case study”. This

Page 18: SUMMER INTERNSHIP REPORT ON

6

paper reports on the modelling issues performed related to a feasibility study to investigate

the possibilities to connect the 640 MW off-shore wind power farm, planned for Krieger's

Flak 30 km south of Trelleborg (Sweden), to the E.ON 130 kV sub transmission system. The

aim of the entire study is to answer the question if such a connection is possible, and under

what conditions; it is not meant as a design project. Following a general connection design

discussion, the study comprises three major parts, fault current calculations, load flow

calculations, and dynamic simulations. Concerning the modelling aspects, much effort has

been put on details and scalability for the dynamic simulations.

In June 2010, at Energy Market (EEM), 2010, 7th International Conference on the European

a paper titled “Economic evaluation of wind generation projects in electricity markets” was

Mr Pereira A.J.C., Inst. Super. de Eng. de Coimbra, Inst. Politec. De Coimbra, Coimbra,

Portugal. In this paper the author explained the electricity markets. He evaluated economic

evaluation of WPPs in electricity markets. He explains that investments in new generation,

especially in renewables, grew up in several countries contributing to change the generation

mix. Among these new technologies, wind power became an important source in the sense

that the share in installed capacity is large in countries as Germany, Denmark, Spain and

Portugal namely considering the prices paid to the generated power. These subsidizing

schemes are in several cases responsible for a large amount of the final end user costs

meaning that in the future new ways of integrating this power in the grid have to be adopted.

This means that for investors it is important to evaluate from an economic point of view the

interest of new wind power projects admitting changes in current tariff schemes. For

regulatory agencies it is also important to investigate the impact of changes in current

schemes. This paper details an approach to characterize this type of investments in terms of

the Net Present Value, NPV, and the Internal Return Rate, IRR, so that more sounded

investment and policy decisions are adopted.

In August 2010, in the conference of Emergency Management and Management Sciences

(ICEMMS), Author Chongming Liu (North China Electrical Power University, Beijing,

China) et al presented a paper titled “Risk analysis and assessment of wind power project”. In

this report he explains that Wind power is a kind of renewable clean energy source, which

has a very important significance for energy conservation and social efficiency. But now,

wind power development has not yet formed a complete system, and there are different kinds

of risks exist in wind power project development process. This paper conduct a detailed study

for this, analyses the risk factors including natural disaster risks, technology risks, economic

Page 19: SUMMER INTERNSHIP REPORT ON

7

risks, and policy risks in four aspects, then construct a fuzzy comprehensive evaluation

model, and use the model in a wind power project on risk assessment, which verifies the

feasibility and effectiveness of the evaluation model.

Author J.I. Munoz et al presented a paper at PowerTech in Bucharest, in June 2009 which

was titled “Risk assessment of wind power generation project investments based on real

options”. This paper presents a decision-making tool for investment in a wind energy plant

using a real options approach. In the first part of the work, the volatilities of market prices

and wind regimes are obtained from geometric Brownian motion with mean reversion (GBM-

MR) and Weibull models, respectively. From these and other values, such as investment and

maintenance costs, the net present value (NPV) curve (made up of different values of NPV in

different periods) of the investment is calculated, as well as its average volatility. In the

second part, a real options valuation method is applied to calculate the value of the option to

invest. The volatility of the NPV curve reflecting different periods is inserted into a trinomial

investment option valuation tree. In this way, it's possible to calculate the probabilities of

investing right now, deferring the investment, or not investing at all. This powerful decision

tool allows wind energy investors to decide whether to invest in many different scenarios.

Several realistic case studies are presented to illustrate the decision-making method.

In September 2011, Consolidated Energy Consultants Limited (CECL) prepared a report

titled “Assessment of investment climate for wind power development in India” for Indian

Renewable Energy Development Agency (IREDA). This document explained indicated seven

key states in India where wind power potential is considerable. CECL explained Government

policy/guidelines, regulations by respective SERCs, guidelines from respective SNAs and

wind resource assessment in all key states. The report also included perception of investors

and financing/profitability. Based on these above mentioned factors, the ranking is given to

states. In the end, the report indicates constraints and barriers which are impediments in the

path of investments in wind power projects in India.

Author Salehi-Dobakhshari (Electrical Engineering department, Sharif University of

Technology, Tehran, Iran) et al presented a paper titled “Integration of large-scale wind farm

projects including system reliability analysis” at Renewable power generation, IET on

January 2011. His study intends to develop a comprehensive procedure for evaluating

locational value of a wind farm project incorporating reduction in transmission system losses,

load delivery point interruption cost and operating cost of generating units. The energy

Page 20: SUMMER INTERNSHIP REPORT ON

8

extracted from the wind farm in normal operation condition is considered to replace the

energy from fossil-fuelled conventional units. In addition, composite system reliability

analysis in the presence of wind power is carried out to evaluate total costs associated with

curtailed energy at different load points as well as generation of generating units in

contingency conditions. System reliability analysis related to large-scale wind farms, along

with operating cost and transmission losses analysis, can assist policy makers to prioritise

wind farm projects based on the total benefits of wind power including reliability benefits and

savings in fossil-fuelled energy sources.

Author Guangjie Wang (Sch. of Manage., Wuhan Univ. of Technol., Wuhan), at Wireless

Communications, Networking and Mobile Computing, 2008, presented a paper titled

“Technical-Economic Analysis of Wind Energy Projects in China” in Oct 2008. In this paper

he explains that the renewable energy consumption has been increased rapidly with high

economic growth in China. As one of the most promising renewable energy resource, wind

energy has become a major part of the plans for sustainable development. The technical-

economic analysis of the project reveals that the revenue from certified emission reductions

(CERs) of clean development mechanism (CDM) project can increase the profitability of the

project but it doesn't play a decisive role. The sensitivity analysis of single parameter shows

that investment, electricity price and production are the key parameters influencing the

effectiveness of projects. The status of wind energy projects in China is elaborated and the

four approaches of developing wind energy projects are proposed.

Author Martinez-Cesena (Electrical Energy & Power Syst. Group, Univ. of Manchester,

Manchester, UK) et al presented a paper titled “Wind Power Projects Planning Considering

Real Options for the Wind Resource Assessment” on January 2012. The paper explains that

Investments in wind power projects (WPPs) have increased in the last few years. This trend is

partially due to the availability of support schemes, which increase the economic

attractiveness of WPPs. Alternatively, the value of WPPs can be enhanced by improving

available techniques used for their planning and design. After reviewing WPP literature, it

was concluded that available tools for the planning and design of WPP could be improved by

addressing the uncertainty of the wind resource assessment (WRA), and this source of

uncertainty could be used to enhance the value of WPPs with real options (ROs) theory. ROs

theory is known for its potential to increase the expected worth of projects by exploiting the

value of flexibility within the projects' investment decisions and designs. Nevertheless, ROs

literature has to be extended to properly address the design of WPPs. Based on the gaps in

Page 21: SUMMER INTERNSHIP REPORT ON

9

ROs theory and WPPs planning, this paper proposes a methodology that relies on ROs theory

to incorporate WRA uncertainty in the planning and design process of WPPs. The

methodology is illustrated with a small case study and its potential to increase the value of

WPPs under different conditions is analysed for a wide range of case studies. The results

illustrate the circumstances and assumptions that can improve and weaken the effectiveness

of the methodology. It is concluded that the application of the proposed ROs methodology

results in increased value for WPPs in most scenarios.

Page 22: SUMMER INTERNSHIP REPORT ON

10

2.2 Policy Framework

2.2.1 National Electricity Policy, 2005

Clause 5.2.20: Non – Conventional Energy Sources

This clause talks about harnessing fully feasible potential of non – conventional energy

resources mainly small hydro, wind and bio-mass to create additional power generation. It

also talks that suitable promotional measures will be taken to encourage private sector

participation.

Clause 5.12: Cogeneration and Non-Conventional Energy Sources

5.12.1

This clause highlights the fact that there is an urgent need to promote generation of electricity

based on Non-conventional sources of energy as they are environment friendly. For this

purpose, efforts are to be made to reduce the capital cost of projects. Cost of energy can also

be reduced by promoting competition within such projects. At the same time, adequate

promotional measures would also have to be taken for development of technologies and a

sustained growth of these sources.

5.12.2

This clause restates what is mentioned In Electricity Act 2003 under section 86(1) (e) and

basically talks about to promote co-generation and generation of electricity from renewable

sources the state commissions are required to fix a percentage of renewable energy out of

total consumption of electricity in the area of distribution licensee.

Clause 5.6: Technology Development and R&D

This clause highlights the fact that special efforts are needed for research, development,

demonstration and commercialization of non-conventional energy systems. Such systems

would need to meet international standards, specifications and performance parameters.

2.2.2 National Tariff Policy, 2006

Clause 6.4: Non-conventional sources of energy generation including Co-generation:

a) In continuation to provisions of section 86(1) (e) of Electricity Act 2003, The clause

states that the procurement by distribution companies shall be done at preferential

tariffs determined by the Appropriate Commission as it will take some time before non-

conventional technologies can compete with conventional sources in terms of cost of

electricity.

Page 23: SUMMER INTERNSHIP REPORT ON

11

b) Procurement by Distribution Licensees for future requirements shall be done, as far as

possible, through competitive bidding process under Section 63 of the Electricity Act

within suppliers offering energy from same type of non-conventional sources.

c) The Central Commission should lay down guidelines for pricing non-firm power,

especially from non–conventional sources, to be followed in cases where such

procurement is not through competitive bidding.

d) In the Amendment in Tariff Policy the Ministry of Power has directed the State

Electricity Regulators to fix a percentage of energy purchase from solar power under

the RPOs. The solar power purchase obligation for States may start with 0.25% in

Phase I (by 2013) and go up to 3% by 2022 This will be complemented by solar

specific Renewable Energy Certificate (REC) mechanism to allow solar power

generation companies to sell certificates to the utilities to meet their solar power

purchase obligations.

2.2.3 Rural Electrification Policy, 2006

Clause 1.3:

This clause states that non-conventional energy sources such as solar, wind, biomass, small

hydro, geo-thermal; tidal etc. along with conventional sources can be appropriately and

optimally utilized to make available reliable supply of electricity to each and every

household.

Clause 3: Approach to Rural electrification:

3.3 Decentralized distributed generation facilities together with local distribution network

may be based either on conventional or non-conventional methods of electricity generation

whichever is more suitable and economical. Non-conventional sources of energy could be

utilized even where grid connectivity exists provided it is found to be cost effective.

Clause 8: Policy Provisions for Permitting Stand Alone Systems for Rural Areas

8.9 This clause highlights the fact that State Governments will have to create Institutions for

back-up services and technical support to systems based on non-conventional sources of

energy. Such services would be provided on cost basis so as to make the arrangements

sustainable.

Page 24: SUMMER INTERNSHIP REPORT ON

12

CHAPTER 3: WPP DEVELOPMENT PROCEDURE

3.1 Introduction - Wind Power Project development

procedure

The detailed procedure for setting up a wind power project is explained here. It consists of

following steps.

1. Project and Financial planning

2. Selection of state of preference

3. Site identification

4. Feasibility study

5. Wind mast installation, data collection and data verification

6. site survey

7. wind farm layout

8. Land acquisition

9. CDM related procedures

10. REC related procedures

11. DPR preparation

12. Financial strategy and financial closure

13. Decision regarding power sale options

14. Physical implementation of the project

The above mentioned tasks are the sub procedures of the wind power project development.

They are explained here in this chapter.

Page 25: SUMMER INTERNSHIP REPORT ON

13

3.2 Project and Financial Planning

3.2.1 Project Planning

The key to a successful project is in the planning. Project planning is done to increase the

likelihood that a project will be implemented efficiently, effectively and successfully. It

involves working out what one wants to do and how is one going to do it. Creating a project

plan is the first thing one should do when undertaking any kind of project.

In case of wind power projects, the overall project plan may be comprised of several points:

Business goal

Project scopes

Financial structure

Policy guidelines

Central govt. policy: MNRE

State govt. policy: SNA

List of constraints & assumption

Professional assistance

Technical planning

Permitting planning

Energy market analysis (who will buy the power)

Regulatory compliance

Legal aspects

Ease & cost of maintenance

Meeting the expectation & goals of stakeholders

Long term outlook & expansion opportunities

Gantt chart preparation

Schedule flexibility

3.2.2 Financial Planning

It includes three major decisions:

Decide how much you need (budgeting decisions)

Decide when you will need it (cash flow)

Decide where it will come from (financial planning)

Page 26: SUMMER INTERNSHIP REPORT ON

14

Wind power projects, like all renewable energy projects, have a strong financial component

which determines profitability or other goals, which incentives are used and how, who takes

risks and earns rewards, how the development budget is controlled, and what has to be done

to qualify for the intended financing.

Financial planning for WPP, like other RE power projects, comprises of following

parameters:

1) General project information

a. Rated capacity

b. PLF or CUF

c. Inflation

d. Start year

e. Project lifetime

2) Revenues - cash inflows

a. Ancillary products or benefits (like CDM, RECs etc.)

b. Cost recovery- Depreciation

c. Cost recovery- tax credits

d. Grants & incentives

e. Power purchase agreement or other sales agreement

3) Costs - cash outflow

a. Equipment cost including installation & site preparation

b. Balance of system(BOS) costs including all non-equipment Capital costs- such as

interconnection & civil works

c. Developer soft costs, such as developer planning, environmental studies licensing

& permitting & negotiation of PPA

d. loan interest

e. Recurrent costs, such as equipment replacement

f. Operation & maintenance

g. Site owner rent or royalties

h. Property tax

i. Project insurance

j. Income tax on revenue

Page 27: SUMMER INTERNSHIP REPORT ON

15

4) Financing costs – debt & equity

a. Loan debt

b. Debt percentage (the percentage of capital costs being covered by a loan)

c. Loan interest rate & term

d. Equity

e. Equity financing fees

f. Initial working capital

g. Debt financing fees

h. Discount rate

i. Scenario analysis

Figure 1 : Financial Planning Process

Page 28: SUMMER INTERNSHIP REPORT ON

16

3.3 Selection of State of preference

The selection of the state of preference is the next task after the planning procedure has been

completed. Following major factors are taken into consideration for selection of a state.

Developers give different weightages to these factors depending upon their own strengths and

weaknesses.

3.3.1 Wind Power Potential and Installed Capacity

Wind availability is the first major factor taken into consideration by the developer to select

the state for developing a wind power project. Out of the total wind power potential, the

unutilised part is what attracts the developer for setting up the WPP. The total wind energy

potential in India has been estimated at 49130 MW out of which more than 14000 MW has

been utilised by various developers. The state wise wind power potential and installed

capacities as on 31.12.2011 are shown below in the table.

Figure 2 : Wind Power Potential and Installed Capacity

(Source: MNRE & Directory Indian Windpower 2011)

Andhra Pradesh, Gujarat and Karnataka seem to be the most lucrative states as far as the

potential and installed capacity of the wind power is concerned, since these states have large

portion of their wind resource unutilised. Maharashtra and Rajasthan too have huge untapped

potential. In Tamil Nadu, On the other hand, almost all the windy sites have been already

occupied. Still, with advancement in the technology it is becoming viable to set up WPPs in

the less windy sites. State wise achievable wind potential till 2020 is given below.

5394

10609

8591

790 920

5439 5005 5374

7008

213

2641 1852

35 330

2560 1830

6613

4 0

2000

4000

6000

8000

10000

12000

Estimated Potential (MW) Installed capacity as on 31.12.2011 (MW)

Page 29: SUMMER INTERNSHIP REPORT ON

17

Table 1 : State wise Wind Power Till 2020

State Incremental (MW) Re-powering (MW)

Andhra Pradesh 7000-8000

Gujarat 6000-7000

Karnataka 5000 1000

Madhya Pradesh 3000-3500

Maharashtra 6000-7000

Rajasthan 4000-5000

Tamil Nadu 7000-8000 1500

Orissa 500

Chhattisgarh 500

Jharkhand 500

Total 39000-43000 2500

Figure 3 : State wise Achievable wind Potential Till 2020

[Source: CRIS analysis based on registered projects and pipeline of developers in various

states]

3.3.2 Feed-in-Tariffs

A feed-in tariff (FiT), also known as feed-in law, advanced renewable tariff or preferential

tariff is another important factor that affects the developers’ decision of selecting a state for

setting up of WPPs. FiT is a policy mechanism designed to encourage the adoption of

renewable energy sources and to help accelerate the transition toward grid parity for such

projects. The Feed-in-Tariffs declared by the SERCs of the key states are shown below.

Page 30: SUMMER INTERNSHIP REPORT ON

18

Table 2 : State Feed-in-Tariffs

States Tariff rate (Rs/Unit) Tariff Period

(Years)

Gujarat 3.56 25

Maharashtra

Wind zone – I 5.67

13 Wind zone – II 4.93

Wind zone – III 4.2

Wind zone – IV 3.78

Rajasthan Jaisalmer, Jodhpur and Balmer 4.46

20 Other districts 4.69

Madhya

Pradesh 4.35 25

Karnataka 3.7 10

Tamil Nadu 3.39 20

Andhra Pradesh 3.5 10

Figure 4 : Feed-in-Tariff

3.3.3 Special incentives and facilities by State Governments

Some state governments have declared special incentive or facilities to attract the wind / RE

developers which are explained here. The developers should study these incentives before

arriving to a decision of finalising the state of preference.

Government of Karnataka:

(From Karnataka Renewable Energy Policy 2009-14)

Green Energy Fund: Green Energy Fund shall be established to facilitate financing for

RE projects.

Consent from Departments & Statutory Clearances: KREDL shall obtain consent &

statutory clearances from concerned state departments for sites developed by them. In

case of private land KREDL shall assist the developers in this regard.

Allotment Committee: A committee under Chairmanship of Additional Chief

Secretary/Principle Secretary, Energy Department will consider allotment of capacity to

entrepreneurs.

Page 31: SUMMER INTERNSHIP REPORT ON

19

Settlements: Transactions shall be settled on monthly basis. Interest at the rate of State

Bank of India short term prime lending rate shall be payable for delayed payment beyond

a month.

Exemption from Demand Cut: Exemption of demand cut to the extent of 50% of

installed capacity assigned for captive use purpose, will be allowed.

Financial Incentives: Entry tax & other incentives shall be available to RE generation in

accordance with Industrial Policy 2009-10.

Letter of Credit: Facility of LOC shall be provided by the ESCOMS to developer and its

cost will be reimbursed to ESCOMs from Green Energy Fund.

Award Scheme: RE projects successfully commissioned during the original agreement

period will be awarded with a certificate with appreciation by the Govt. and a cash

incentive from Green Energy Fund.

Government of Madhya Pradesh:

(Notification No.6591-F18-10-XIII-93 dated 17.10.2006 as amended vide order No. F18-10-

XIII-93 dated 12.05.2008)

Green Energy Fund: will be created for facilitation of power generation through non-

conventional energy sources.

Exemption from Open Access Charges: Nonconventional Energy based power

generation shall be exempted from Open Access charges.

Projects will be eligible for all benefits available to new industries under the Industrial

Promotion Policy 2004.

However one discouraging factor for WPP owners included in the state wind policy is that

the 3rd party purchaser of wind energy will be allowed the facility of reduction in contract

demand.

Government of Maharashtra:

(From NCE Policy 2008)

Evacuation Arrangement: To be constructed with the approval of Transco/Discom by

the developer at his cost. 50% of the approved expenditure to be reimbursed out of Green

Energy Fund.

Page 32: SUMMER INTERNSHIP REPORT ON

20

Approach Road: To be constructed by MEDA out of Green Energy Fund. Repairs or

strengthening of existing roads to be done by developer at his cost.

Encouragement to Co-operative Sector: 11% of total share capital of the project shall

be paid from Green Energy Fund for projects set up by co-operative institutions.

Letter of Credit: The DISCOM shall provide the facility of LOC to the developer & the

cost involved to be reimbursed to the DISCOM out of Green Energy Fund.

Octroi / Entry Tax: Taxes actually paid shall be reimbursed by MEDA out of Green

Energy Fund.

Eligibility for Sanction

It is obligatory to sell 50% of electricity to the Distribution Company under a long

term agreement at the rate determined by MERC. Remaining 50% shall be sold within

the State.

Benefits under the policy shall be available to only such projects for which

infrastructure approval is accorded by the Govt.

Government of Rajasthan:

(From NCE Policy dated 25.10.2004 as amended vide letters dated 10.03.05, 16.07.05,

24.02.06, 30.11.06, 19.01.07 & 27.03.2008)

Merit Order Despatch Not applicable to Wind Power Project

Exemption from Electricity Duty: Energy sold to a 3rd party will be exempted from

payment of ED @50% for a period of 7 years from COD.

Relocation of project: Re-location of project, if justified shall be permitted without any

additional charge.

3.3.4 Simplicity of procedures followed in the State

Proactive and simplified procedure ensures smooth and timely completion of the project. The

index for attitude of the State agency gets reflected in quantum of capacity addition. Higher

capacity additions obviously indicate that investor faces least problems. Though this factor is

of primary consideration to the developer yet it is also relevant to IPP owners particularly

after completion of the project and routine O&M.

Page 33: SUMMER INTERNSHIP REPORT ON

21

The procedures required to be followed in different states at various stages (mast installation,

land acquisition, issue and redemption of REC etc.) of development of a WPP is explained in

the relevant topics of this report.

3.3.5 Evacuation Infrastructure

The evacuation infrastructure development for wind power project is very costly and time

consuming since the WPPs are generally in the remote sites where the grid connectivity is

usually not readily available. Whether this infrastructure has to be developed by the grid

utility or by the developer is a major factor for developer in his decision of selecting a state

for WPP development. Various states have different policies for the evacuation infrastructure

development which are explained here.

Andhra Pradesh: Cost to be borne by the developer.

Gujarat: Voltage level for evacuation shall be 66 kV and above. Govt. Policy (Amendment-

1) 2007 dated 07.01.2009 provides that owner will bear the entire cost up to 100 km; beyond

this limit GETCO will construct at its cost. Approved capital cost includes 38 lakhs per MW

towards cost of transmission line from project site to grid sub-station.

Karnataka and Madhya Pradesh: Cost to be borne by the developer. The capital costs

specified by the respective SERCs are inclusive of the power evacuation infrastructure.

Maharashtra: Cost to be borne by the developer. Capital Cost of Project/MW is inclusive of

cost of power evacuation infrastructure up to interconnection point. Capital cost is linked to

price indexation formula.

Rajasthan: A sum of Rs.2.00 Lakhs per MW is payable to RVPN as connectivity charges.

RVPN to develop evacuation system from Pooling Sub-station to Grid Substation. If

evacuation system is constructed by developer beyond pooling substation, Commission may

determine transmission tariff on case to case basis.

Tamil Nadu: To be borne by the Licensee if entire energy is sold to the Distribution

Licensee. For captive consumption and third party sale, cost will have to be borne by the

Developer but the work will be executed by the Licensee.

Page 34: SUMMER INTERNSHIP REPORT ON

22

3.3.6 Grid availability

This is a major problem primarily faced by WPP developers. Obtaining sanction and/or

commissioning of the project gets adversely affected due to non-availability of evacuation

facility. None of the states have so far made medium and long term plan to meet the demand

of Wind Power Sector. The short term solution as offered by them is proving to be in-

adequate because of higher growth rate now being observed. Even after commissioning of the

project, particularly in Tamil Nadu, the wind farm feeders are occasionally switched off

during high generation period which badly affects the investors. Therefore the WPPs must

consider the Grid availability conditions in the state in their decision of selecting a state for

WPP. Grid availability conditions are comparatively better in Andhra Pradesh, Gujarat and

Rajasthan.

3.3.7 Regularity in the receipt of payment

This is an important factor that IPP owners and Bankers would consider to ensure financial

viability of the project. The financial health of almost all State utilities is in bad shape.

Comparative ranking of the states carried out by Consolidated Energy Consultants Limited

(CECL) based on the general experience of IPP owners regarding timely receipt of payment

shows that Rajasthan, Gujarat and Karnataka are better compared to other states as far as

regularity in payment from the DISCOMs is concerned.

3.3.8 Sharing of CDM Benefits

The Clean Development Mechanism (CDM) is a project-based mechanism that allows public

or private entities to invest in greenhouse gas (GHG) mitigating activities in developing

countries and earn abatement credits, which can then be applied against their own GHG

emissions or sold in the open market. For wind power producers, CDM benefits may become

a source of revenue which can improve their project IRR by 1-1.5% and can make the project

financially viable. CERC and different SERCs have declared sharing of the CDM benefits

differently between the DISCOMs and the Developers. The WPP developers should examine

the sharing of CDM benefits and its impact on the revenue in various states before arriving to

a conclusion of finalising the state of preference.

Page 35: SUMMER INTERNSHIP REPORT ON

23

The regulations regarding sharing of CDM benefits between the developers and the

distribution licensees in different states are explained in the following table.

Table 3 : Sharing of CDM Benefits in Different States

State Sharing of CDM benefits

CERC

regulation, 2009

100% to developers in the 1st year, reducing 10% every year till the

sharing becomes 50:50 between developer and beneficiary.

Gujarat As per CERC regulation

Maharashtra As per CERC regulation

Rajasthan 75% to developer, 25% to Distribution licensee. Share of the licensee

shall be fully passed on to consumers.

M.P. As per CERC regulation

Karnataka As per CERC regulation

Tamil Nadu 100% 1st year, reducing 10% yearly up to 50:50

A.P. 90% to developer and 10% to beneficiaries.

3.3.9 Reactive Energy Charges

Table 4 : Reactive Energy Charges

State Reactive Energy Charges

Gujarat Upto 10% reactive power consumption - 10 paisa/Kvarh

Above 10% reactive power consumption - 25paisa/kvarh above 10%

Maharashtra 25 paisa/Kvarh with 5% escalation per year

Rajasthan 5.75 paisa/Kvarh escalating 25 paise per year

M.P. 27 paisa /Kvarh

Tamil Nadu 25 paise/Kvarh upto 10% and double beyond

A.P. 10 paise/Kvarh upto10% and 25 paise above10

Reactive power consumption of wind turbine generators is high, especially during Start-up.

Sometimes the reactive power consumption during start up is equivalent to the kW power

rating of the turbine. This reactive power has traditionally always been imported from the

grid. Although Wind turbine generators now-a-days are commonly fitted with reactive

compensation systems of various ratings, there is requirement of reactive power consumption

from the grid during start-ups and for voltage control. Hence, the reactive power charges

Page 36: SUMMER INTERNSHIP REPORT ON

24

applicable in the various states should be considered by the developer. The Reactive Energy

charges in in various states are indicated in the following table.

3.3.10 Banking

Power banking is like cash banking whereby wind power producers feed in the electricity

generated by their wind mills to the state grid and then draw that power for captive use within

the period specified by the Appropriate Commission. Despite the development of latest

technology in the wind energy sector it is still not possible to declare the exact wind power

generation. Hence, to help the wind power generators and attract investment, some states

have come up with the provision of banking of wind power. The banking charges are

applicable as decided by the Appropriate Commission. In Banking, only the transactions of

energy take place; there is no transaction of currency. Banking regulations in key states are

explained in the following table.

Table 5 : State wise Banking Regulations

State Banking Regulations

Gujarat Only for captive use. Allowed for one month.

Maharashtra

Allowed for a year (only for captive). Surplus energy is limited to 10% of

injected to grid up to 31st march and purchased by state at lowest Tod slab

rate of HT.

Rajasthan

Allowed only for 6 months from April to September and October to March.

Banking is not permitted from December to February. Surplus energy is

paid at 60% of large industrial tariff.

M.P.

Permitted for a period of a financial year at 2% charge. Consumption of

banked energy is subject to approval of Discom. Surplus energy at the end

of banking period to be procured by the Discom as per the decision of the

MPERC.

Karnataka

Permitted for 12 months at 2@ charge. Energy banked beyond the

prescribed time will be utilised and paid for by the Karnataka Power

Transmission Co. Ltd/Distribution Licensee concerned at tariff applicable as

per KERC norms.

Tamil Nadu Allowed for 1 year at 5% banking charge.

A.P. Not allowed. Surplus power is paid at 75% of lowest bid tariff.

Page 37: SUMMER INTERNSHIP REPORT ON

25

3.3.11 Transmission and wheeling charges

Transmission and Wheeling charges, specified by SERCs of the key states, as a percentage of

the total energy transmitted are given in the following table. The losses assumed for

computation of the transmission and wheeling charges should also be taken into

consideration.

Table 6 : State wise Transmission and Wheeling Charges

State Transmission and wheeling charges

Gujarat

1) For 66KV and above - charges and losses are those applicable to open

access consumers

2) For below 66KV - charges are those applicable to open access consumers;

considering

i) For more than one WEGs - Losses at 10% and shared in the ratio of

4:6 between transmission and distribution

ii) For one WEG - losses at 7% and shared in the ratio of 4:3 between

transmission and distribution.

Maharashtra

Transmission losses 4.85% and wheeling losses 0 to 9% according to the

voltage level.

Transmission charges - Rs 126.86/KW/month (long term), Rs 31.72/KW/month

(short term).

Wheeling charges - Rs 0 to 245/kw/month according to voltage level.

Rajasthan

Transmission loss - from 4.4 to 8% at different voltage levels

Transmission charges - Rs 76/kw/month

Wheeling charges 5.5 paise/kwh

M.P. 2% of the energy injected

Karnataka 5% and Rs. 1.15/kwh for third party sale

Tamil Nadu 5% of energy injected

A.P. 5% of energy injected

3.4 Site Identification

After finalising the state to develop a WPP the next task is to select the best possible sites for

installation of WPP. Following factors should be taken into consideration for selection of site.

Page 38: SUMMER INTERNSHIP REPORT ON

26

There must be evidence of significant wind speed. Wind power density should be

greater than or equal to 200 watt/m2.

Locations like hills, ridges, plateaus, mountains etc. are preferred as these sites have

more wind speeds compared to their surrounding locations.

The available area should be taken into consideration. Generally 15-25 acre/MW of

land is required, but this may vary depending upon the micro-siting.

Wind direction and wind shear – The sites with constant speeds and directions are

more effective for wind power production and hence has plants at such sites have

higher PLFs.

Land cover pattern should be studies as it affects wind speeds at various heights.

Accessibility – The heavy transportation vehicles should be able to reach to the

location of the proposed WPP at reasonable cost of road construction and

transportation.

Land ownership (Private/revenue/forest) also is an important factor to be considered.

Additional forest/environment clearances are required for occupying a forest land. On

the other hand, the developer may face problems like non-convicibility of owners in

occupation of private land.

Prior commitments of the land – The developer needs ensure that the proposed land is

not already committed to any other WPP developer.

Sites approved by C-WET must be given preference as the technical and regulatory

work to occupy such sites reduces compared to other sites.

There must be reasonable access to electrical transmission.

The terrain must be favourable to construction.

Apart from these several other factors need to be taken into consideration like - Cost

of land, rehabilitation issues, scope for future expansion, labour and skills availability,

minimum impact on labours etc.

3.5 Feasibility Study

Feasibility study is a preliminary study that is done to determine a project‘s viability through

identifying potential return on investment as well as any fatal flow in the project if any. The

results of the study are used to determine whether to proceed with the project or not. It

provides a structured method that focuses on problems, identifies objectives, evaluates

Page 39: SUMMER INTERNSHIP REPORT ON

27

alternatives, and aids in the selection of the best solution. It also describes current market

situations, explores outcomes, and assesses the range of costs and benefits associated with the

recommended action. In short, the technical and commercial viability of the project is

checked in the feasibility study. After studying the outcomes of the feasibility study the

owner choses whether to proceed further with the project or not.

Feasibility Tasks:

Site inspection

Wind resource review

Investigation of interconnection opportunities

Selection of suitable process and technology

Capacity fixation on the basis of project

Capital cost study

Profitability analysis

Fatal flaws review

Grant research and application development

Investigation of site access

3.5.1 Generalized activities for feasibility study of Wind Power Projects:

A. Wind Resource Assessment

The first consideration in choosing a site is the wind availability. It is the most important

factor affecting the viability of the project. To determine whether to have a project or not, it is

necessary to conduct a resource assessment. Professional resource assessment is necessary to

raise debt financing, necessary approvals/ clearances before proceeding further. In some

cases, technology providers may be able to help in identifying options, the best location or

technology to be used.

Feasibility

Study

Commercial

Viability

Technical

Viability

Figure 5: Feasibility Study

Page 40: SUMMER INTERNSHIP REPORT ON

28

B. Technology selection

Various wind energy technologies are available for generating power. However each

technology has its own merits & demerits. Therefore the project viability depends on the

selection of appropriate technology.

Various technological choices have to be made for the following:

Size and capacity of the turbines

Hub height

Rated and cut-in wind speeds

Vertical or Horizontal axes

Active and passive yaw

Type of rotor controls

Airfoil nomenclature

Tip-speed ratio

Pitch control and stall control

Rotor diameter

Rotor solidity

Betz limit

Number of blades

Blade composition

Type of generator

Type of hub

Type of towers

Type of drive trains

C. Preliminary design

Preliminary design includes engineering the project‘s details, including equipments locations,

wiring, control systems, roads and foundations. The design of the scheme should be

completed at a level adequate for costing and a bill of quantities to be determined. Hence, the

design should be adequate for tendering purposes, and would include general arrangement

and layout drawings. Prominent aspects of the works can be categorized into:

Civil works

Generating equipment

Grid inter-connection design

Page 41: SUMMER INTERNSHIP REPORT ON

29

Optimum system capacity

Size & layout of structures & equipment

If possible, the designers will therefore need to work closely with the machinery suppliers, so

that specific equipment parameters can be considered as the basis of the design.

D. Grid connectivity

Check for an appropriate connection point near site

Conversations with those who have an understanding of the system in the area where you

propose to connect your project and contact local utility or Discom. It provides following

information:

i. Understanding the transmission & distribution system

ii. Power line capacity

iii. Substation capacity

iv. Existing protection scheme of power system

v. Conductor size

vi. Cost estimates for transmission upgrades

Next step is to approach transmission utility , with an application, which includes the

following:

i. Feasibility study

ii. System impact study

iii. Facility study

iv. Interconnection agreement

The final step is executing the agreements and constructing the additional infrastructure

needed to get your energy on the grid.

E. Environmental impact Assessment

An environmental impact assessment (EIA) is an assessment of the possible impact—positive

or negative—that a proposed project may have on the environment, together consisting of the

natural, social and economic aspects. The purpose of the assessment is to ensure that decision

makers consider the ensuing environmental impacts when deciding whether to proceed with a

project. The Ministry of Environment and Forests of India have been in a great effort in

Environmental Impact Assessment in India. The main laws in nation are Water Act (1974),

The Indian Wildlife (Protection) Act (1972), The Air (Prevention and Control of Pollution)

Page 42: SUMMER INTERNSHIP REPORT ON

30

Act (1981) and The Environment (Protection) Act (1986). The responsible body for this is

Central Pollution Control Board (CPCB). Wind-power generation has very low emissions on

a life cycle basis, but has a number of environmental effects that may limit its potential. The

following is required before the project implementation.

Land use analysis- Helps in assessing the changes in land use pattern for setting up wind

energy stations

Air pollution

Impact on flora & fauna

Visual impact assessment

Noise impact assessment

Hydrological assessment

Impact on communication signal

On-site contamination & hazardous material issue

Waste water management practices

Depletion of water resources

Economic effects on local economy (e.g. creation of jobs)

Mitigating measures- ways in which any adverse environmental impact may be

minimized

F. Social impact assessment

Social impact assessment includes the processes of analysing, monitoring and managing the

intended and unintended social consequences, both positive and negative, of planned

interventions (policies, programs, plans, projects) and any social change processes invoked

by those interventions. Its primary purpose is to bring about a more sustainable and equitable

biophysical and human environment. SIA is often carried out as part of, or in addition to,

Environmental Impact Assessment, but it has not yet been as widely adopted as EIA in

formal planning systems, often playing a minor role in combined environmental and social

assessments. The Social Impact Assessment is analysed taking into account the effects of the

RE power project implementation on the population around the site region under various

aspects such as:

Displacement of Habitat due to project implementation

Page 43: SUMMER INTERNSHIP REPORT ON

31

Proximity to populated area

Worker health & safety issues

Local population deprived of use of their domestic fuel (Biomass)

Improved Power Availability situation for the local population

Adequate Direct & Indirect employment opportunities to Rural Local population

G. Economic viability

The purpose of an economic analysis is to demonstrate that the proposed project achieves

optimum utilization of resources and is of sufficient economic merit to justify an investment

in it. The analysis is therefore first made in the planning stage of the project, before any

financial arrangements are discussed or entered into. The financing agencies will generally

wish to see and approve the results of the analysis prior to making a commitment on

financing the whole or part of the project. Economic analysis is always comparative. Sound

economic evaluation of the proposed project during pre-feasibility and feasibility analysis is a

fundamental requirement, particularly when the project requires a bank‘s assistance and

financial commitment. The economic viability of the project is tested by financial modelling,

which is explained in Chapter 4 of this report.

3.6 Mast Installation, Data Collection and Data

Verification

3.6.1 Permission for Mast Installation and Subsequent Capacity

Allocation

After finalising the site for the mast installation, the developer of a Wind Power Project has

to take permission for installation of mast. A Land Option Agreement gives the developer the

first right to develop the land for a wind farm. It should precedent the erection of masts to

ensure that the data remains with the owner of the mast. It generally includes the following

The right of first refusal to develop the land for renewable

Details of the wind resource measurement agreement

Detail of data use if no turbine is installed.

Different procedures are followed in different states for obtaining the permission for mast

installation. First of all, the developer has to contact the State Nodal Agency for the

permission for installation of a mast. The SNA issues the permit if the land is either private

Page 44: SUMMER INTERNSHIP REPORT ON

32

or revenue land. If the site for mast installation falls into forest land, the permission from

forest department is also required. The procedure that needs to be followed in different states

is explained below.

Andhra Pradesh, Rajasthan and Orissa

If the site is within the radius specified by the corresponding SNA (25 Km in Orissa)

from the CWET mast, land is directly allotted on the Capacity Allotment basis, i.e.in

terms of MW as per asked by the developer.

Otherwise, application for land allotment for Wind Resource Assessment has to be

submitted by the developer to the SNA. The area within the radius specified by the SNA

(AP and Orissa - 5 km, Rajasthan – 10 Km) from the proposed mast location will be

blocked for 2 years for wind resource assessment.

An application in the forest department is required for land allocation if mast location is

in forest land. A fee of 1 lac per mast has to be paid to the forest department. This is

applicable in all the states.

Only the owner’s consent is required if the proposed mast location is in the private land.

Approval for capacity allocation is sought from the SNA after the wind resource

assessment is done.

Karnataka and Madhya Pradesh

In Karnataka and Madhya Pradesh, site for the mast installation is indicated and applied

for permission to SNA. The SNA gives permission directly on capacity allotment basis.

Maharashtra:

No permission is required from MEDA for mast installation. Permission from forest

department is needed if the proposed mast location is in the forest land (fees of Rs 1

lakh/mast).

The data collected is then registered with CWET. CWET examines and approves the

data.

MEDA, based on approval from CWET, certifies that the area within 10 Km radius from

the mast is windy.

An application, along with the MEDA certificate has to be submitted in forest

department for land diversion.

Page 45: SUMMER INTERNSHIP REPORT ON

33

MEDA allots the land on Capacity Allocation basis.

Gujarat:

Mast installation is to be done directly after the purchase of the land and no permission is

required from GEDA. CWET and GEDA are only need to be informed about installation

of mast.

Approval from forest department is required if the proposed location for mast installation

is in the forest land for which the fees are Rs 1 Lakh/mast.

3.6.2 Installation of Wind Mast

Wind Mast installation is started after the permission has been received from the SNA/forest

department.

Experienced teams, skilled at installing wind monitoring met masts and equipment to the

highest standards are required for the Wind Mast Installation. Generally, consultants who

have core competency in the mast installation are hired. The consultants also provide wind

monitoring product for the specific application and install instrumentation.

3.6.3 Data collection

MNRE published guidelines for wind data measurement on 20.06.2008. The

following basic parameters are needed to be collected with the installed masts, for

minimum 12 months.

Wind speed (measure by anemometer)

Wind direction (measure by wind vane)

Wind shear - Increase in wind speed at greater height above ground

Wind speed distribution

Temperature (measure by temperature sensor)

Vertical wind speed (optional)

Change in temperature with height (optional)

Barometric pressure (optional)

Roughness of terrain (obstacles presence like nearby trees, buildings etc.)

Page 46: SUMMER INTERNSHIP REPORT ON

34

Wind power can be measure by:

WPD (W/m2) = ½*air density*rotor swept area*(wind speed) 3

3.6.4 Validation of Data through CWET

The data collected though the mast has to be verified through CWET. The CWET Verifies

the method and procedure of wind monitoring including installation details, sensors

calibrations and data collection by the company at the station and prepares report

accordingly. The cost is to be paid by the developer. The Developer also has to arrange site

visits for the CWET scientists for verification of ground realities if the CWET asks for the

same.

3.7 Site Survey

After the data has been approved by the CWET, team of the developer makes a visit to the

site to conduct a site survey. Primary feasibility of the site for a wind farm development is

checked at this stage.

3.7.1 Soil / Ground Conditions

Wind turbine generators require very solid foundations to secure that large structure in high

wind conditions. Therefore soil conditions must be assessed to determine the stability of the

ground. The location, type and cost of the foundation are largely determined by ground

conditions.

3.7.2 Soil Erosion

With proper construction techniques, and good maintenance, a well-designed wind farm

should have no impact on soil erosion. Control of these issues is relatively well understood

and a part of good practice in the civil construction industry. On-site inspection of the soil

and ground conditions is used not just for the design of roads and foundations but also in the

development of the environmental management plan for the project which will implement the

techniques appropriate to the site for the control of soil erosion and maintenance of surface

and ground water quality.

Page 47: SUMMER INTERNSHIP REPORT ON

35

Where possible all removed soil is used on site. Run off is diverted away from disturbed soil

and controlled using artificial barrier or existing vegetation.

Physical characteristics of the land are checked to ensure suitability for the wind farm

development. For example, the located site should not be morass, a water body or a rocky

surface.

The wind farm cannot be located in a tribal land, a wildlife sanctuary or a national park

according to the land acquisition laws and hence the ownership of the land also has to be

known. However this may have been checked by the developer while applying for the mast

installation.

3.7.3 Accessibility

Accessibility to wind farm site is important for construction and for the on-going operation

and maintenance of the wind farm. Construction access is usually more problematic because

of the large vehicles and loads that need to be brought onto site. The turbines are brought

onto site in large sections and erected using very large cranes. Local roads need to be

sufficient to allow the delivery of the turbine components and construction equipment.

During the life of the wind farm the access tracks to each wind turbine, established during the

initial construction, would be maintained and are sufficient for the service vehicles.

Steep gradients and unstable surfaces are generally avoided because of the added cost of

cutting suitable gradients and stabilising loose surfaces.

3.7.4 Closeness to Grid

Suitable grid connection is vital for a wind farm. Because the large amount of electricity has

to be transmitted from the wind farm’s switchyard to the existing electricity grid, the cost of

overhead transmission line increases with increase in the distance. This increases the capital

cost, which ultimately affects the economic feasibility of the project. Unfortunately, the

windy sites are many times distant from the existing grid, and hence despite increase in the

cost, sometimes it is better to move further away from the power line, despite the increased

cost simply because the more distant site is so much more productive.

Page 48: SUMMER INTERNSHIP REPORT ON

36

3.8 Wind Farm Layout

Wind farm layout preparation is the next step in the project development. It means finalising

the exact locations of wind turbines in the site. The objective of the layout is to maximise the

Capacity Utilisation Factor (CUF) for the given site conditions.

3.8.1 Inter-turbine separation

It is determined by several factors and we need to compromise between these factors

optimally. At the extremes they need far enough apart to allow the turbines to follow the

wind without colliding with each other. Likewise we do not want them so far apart that the

cost of the interconnecting cables is prohibitively expensive.

The main determinant of separation distance is wind speed and turbulence. A wind turbine

generator necessarily removes some of the energy from the wind and causes turbulence. So

downwind there is an area where it is not economic to place another wind turbine generator.

The surrounding unaffected wind will impart some of its wind energy to this slow and

turbulent wind and the turbulence will be dampened and the wind speed will come back that

of the surrounding wind. We normally will wait until it comes back to about 98 to 99% of the

original power level before placing another machine downwind. The volume of air that is

affected is determined by the diameter of rotor. So separation distances can be expressed in

multiples of the rotor diameter.

The rule of thumb used for a downwind separation of wind turbine generators of between 5D

and 7D (Where D stands for the rotor diameter). The influence of a wind turbine generator

across the wind is nowhere near as great and could place a wind turbine as close as 1D apart

across the wind. However the wind does not come from only one direction, so we cannot do

this in reality.

In general wind turbine generators will be separated by 3D to 5D distances across the

prevailing wind energy direction and by 5D to 7D distances with the prevailing wind energy

directions.

Layout issues involve more than inter turbine separation. In most cases, the development of a

wind farm layout will be much more complex. Again several factors will come into play to

varying degrees according to site conditions.

Page 49: SUMMER INTERNSHIP REPORT ON

37

3.8.2 Changes in elevation of area

For example, a ridgeline that spans across the prevailing wind direction may result in a line

(or lines) of wind turbine generators following the contours of the ridge. In undulating areas,

there is no point placing a turbine behind a small hill (where wind speeds will be significantly

lower) simply because you have reached an appropriate inter turbine separation distance if

moving another few meters can significantly increase the wind energy.

3.8.3 Other factors

The noise level to which nearby residents will be exposed to, avoiding areas of important

native vegetation, or avoiding sites of cultural or archaeological significance etc. also affect

the layout of the wind farm.

3.8.4 Layout using software

Complicated three dimensional computer models help us to prepare the layout to maximise

the wind turbine locations considering all the above mentioned factors. A team of developer

visits the site and checks whether this optimum layout indicated by the software is feasible in

reality or not. The Changes suggested by the team is done and optimum layout is re-prepared

considering the constraints mentioned by the layout team.

3.9 Land acquisition

After the site for the project has been finalised and the siting is done, the developer must

gain legal control over the proposed project site. This usually means acquiring interests in

land, whether by purchasing the land, leasing it (which could include an option to purchase),

or obtaining easements. Outright purchase normally provides the maximum amount of

security and rights over the project land, but is also usually the most expensive option.

Leases should be carefully developed so that they clearly address issues important to the

project developer and landowner at the time the lease starts as well as years later during

project operations. In many cases, the people who originally negotiate a lease will not be

involved later in the operating period of the project, so it is important that any understanding

between the parties be properly addressed in the written lease to prevent future

misunderstandings.

A well-executed lease is an important part of the project development process. Before the

Page 50: SUMMER INTERNSHIP REPORT ON

38

purchase and installation of wind turbines it should be ensured that the lease provides clear,

unimpeded rights for use of the land over the long term.

The most important portions of the land lease are:

The length of the agreement

What other uses are acceptable on the land surrounding the wind turbines

The payment structure.

These and other major land lease provisions are described below.

A real property agreement will address major issues such as:

(a) Type of land available

1. Revenue land

2. Private land

3. Forest land

4. Others

(b) Nature of land

1. Urban

2. Rural

3. Agricultural

4. Industrial

(c) Duration of the agreement

(d) Compensation

(e) The scope of the land subject to the agreement

(f) Permitted uses of the land,

(g) Property-related taxes

(h) Assumption of liabilities

(i) Assignment of contract rights by the developer

(j) Termination of the agreement

(k) Remediation of the land and dispute resolution

Other land issues that may be applicable:

a) Securing a right to purchase or lease land within a prescribed future timeframe through an

Option to Purchase or Lease.

b) Obtaining a right to match the terms of purchase or lease to a third party through Right of

Page 51: SUMMER INTERNSHIP REPORT ON

39

First Refusal.

c) Ascertaining the restrictions on an owner's right to use property by means of covenants

on land

d) Possessing a secure legal right to develop the land by ensuring title to the land.

e) Conducting land surveys if title is uncertain, to preclude title-related questions, or if the

value of the project is sufficient to justify undertaking a peremptory survey.

f) Understanding the various land-related permits and approvals that will be required

(including land use permitting, conditional use permitting, environmental permitting,

building and electrical codes), paying particular attention to the length of time needed to

obtain the necessary permits.

g) Determining whether or not present zoning and land use permits the intended use, taking

into account the difficulty of obtaining zoning exceptions.

h) Addressing subsurface mineral rights.

i) Addressing water rights (including surface mineral)

As explained earlier, a Land Option Agreement, which precedes the erection of the mast,

gives the developer the first right to develop the land for a wind farm.

The Land Lease Agreement is the next step. It is much more detailed and should be

carefully reviewed by a qualified lawyer or expert. The land lease includes:

a) Length of lease

b) Royalty percentage with minimum or floor payment (preferred over flat fee or rent)

c) Extension options

d) Purchase agreement or Standard Offer Contract

e) Agreement not to conflict with normal activity on land without compensation

f) Arrangement for the installation to be part of land deed in case of transferal

g) Agreement by the developer to

minimize impact

compensate damages

assume liability

h) Access to land provisions

i) Decommissioning

j) Interconnection sites, depth of electrical wires

Page 52: SUMMER INTERNSHIP REPORT ON

40

3.10 Clean Development Mechanism

The Clean Development Mechanism (CDM) is a project-based mechanism that allows

public or private entities to invest in greenhouse gas (GHG) mitigating activities in

developing countries and earn abatement credits, which can then be applied against their

own GHG emissions or sold in the open market. The CDM has the dual objective of reducing

greenhouse gas emissions and contributing to sustainable development in the host country.

The Clean Development Mechanism exploits the efficiency gap between industrialized

countries and developing countries. In order to understand the potential of the CDM, one

needs to consider that emission reductions through a CDM project are not assessed in

absolute terms since developing countries have no reduction commitments, but in relative

terms: every new energy project is compared to a forecast of future emissions, the baseline.

CDM benefit under Kyoto Protocol has been availed by many WPPs in India. Ministry of

Environment and Forest (MoEF) is the Nodal Agency and a National CDM Authority

(NCDMA) has been established. There are quite a few agencies with foreign tie-up available

to assist in –

Registration and Certification by MoEF and UNFCCC

Trading of CER’s in market

Under the present conditions the net benefit available under long term contract is

about Rs. 0.50 per kWh after meeting all expenses at several stages. IPP Owners with foreign

tie-up are likely to do trading at higher rate.

There is however some reservation regarding availability of this benefit beyond 2012.

Figure 6 : CDM Timeframe

Page 53: SUMMER INTERNSHIP REPORT ON

41

3.10.1 CDM project cycle

Carrying out a CDM project and receiving final registration by the CDM Executive Board

requires multiple steps. These steps are regarded as the CDM project cycle, and are put in

place in order to safeguard the actual climate benefits of CDM project activities.

The project cycle can be seen in the figure below:

Figure 7 : CDM Project Cycle

Source: Adapted from "Using the CDM into energy planning – A case study from South Africa",

James-Smith, E

I. Project Design

This step involves developing a Project Design Document (PDD), which is a standard format

describing how the activity intends to fulfil the pre-requisites for registration as a CDM

project. The PDD consists of a general description of the project, its proposed baseline

methodology, a timeline and crediting period, a monitoring methodology, calculation of GHG

emissions by source and stakeholder comments. The host country Designated National

Authority (DNA) must issue statements on the PDD indicating that the government of the

host country participates voluntarily in the proposed activity and that the project assists the

host country in achieving sustainable development.

Page 54: SUMMER INTERNSHIP REPORT ON

42

II. Validation and Registration

Validation is a process involving an independent evaluation of the project activity by an

external auditor known as a Designated Operational Entity (DOE), which is hired by the

project participants (a list of DOEs can be downloaded from the UNFCCC website). The

DOE reviews the PDD in order to determine whether the project meets CDM requirements.

Once a project activity has been validated by a DOE a validation report is forwarded to the

Executive Board (EB) for registration as a CDM project. The registration of a project will be

final within eight weeks after the date of receipt by the EB unless at least three members of

the EB request a review of the project activity.

III. Monitoring

Once the project is operational the emissions that occur from the activity must be monitored.

This is done according to the monitoring plan submitted and approved in the PDD, which

indicates the method used for measuring emissions from the project and how data relevant for

these calculations will be collected and archived. The information on emission reductions

must be included in a monitoring report estimating the amount of CERs generated and

submitted to a DOE for verification.

IV. Verification and Certification

Verification is the independent review of the monitoring report submitted by the project

participants. A DOE different to that involved in the validation process carries out

verification (a list of DOEs can be downloaded from the UNFCCC website). The DOE must

ensure that the CERs have been generated according to the guidelines and conditions agreed

upon during the validation of the project. A verification report is then produced. The same

DOE that verified the project also certifies the CERs generated by the activity.

Certification is the written assurance from the DOE that the project achieved the stated level

of emission reductions and that these reductions were real, measurable and additional. The

certification report constitutes a request to the EB for issuance of CERs. Unless a project

participant or at least three members of the EB request a review within fifteen days the EB

will instruct the CDM registry to issue the CERs.

Page 55: SUMMER INTERNSHIP REPORT ON

43

3.11 Renewable Energy Certificates

Renewable Energy Certificate (REC) mechanism is a market based instrument to promote

renewable energy and facilitate compliance for Renewable Purchase Obligations (RPO) under

inter-state transaction of RE generation. REC mechanism is aimed at addressing mismatch

between availability of RE Sources in state and the requirement of the obligated entities to

meet the RPO.

Under this mechanism, the cost of electricity generation from renewable energy sources is

classified as cost of electricity generation equivalent to convention energy sources and the cost

of environmental attributes. These environmental attributes can be exchanged in the form of

RECs. Hence, the RE generator can either sell the energy at preferential tariff specified by

the ERC; or it can sell the power at normal tariff and sell the RECs on power exchanges.

In January 2010, honourable Central Electricity Regulatory Commission (CERC) announced

Regulation on Terms and Conditions for recognition and issuance of Renewable Energy

Certificate for Renewable Energy Generation. According to this regulation, a generating

company involved in electricity generation from renewable sources of energy will be eligible

to get Renewable Energy Certificate (REC) for their each 1 MWh (1000 unit) of generation

subject to:

It has got accreditation from State Nodal Agency

It does not have any PPA for the capacity related to such generation with distribution

licensee at preferential tariff (state regulated tariff), or

It sells electricity generated to either of the following

The distribution licensee at price not exceeding average pooled cost of power

purchase (APCPP) of the distribution licensee for last year

Any other licensee or to an open access consumer at mutually agreed price, or

through Power Exchange.

Captive RE Generators are also eligible for REC if such generators are:

Not availing promotional Wheeling

Not availing promotional Banking

Not getting any electricity tax/duty exemption from the state.

Page 56: SUMMER INTERNSHIP REPORT ON

44

3.11.1 Types of REC

According to the regulation, RECs will be issued in two categories: Solar RECs for

generation through Solar PV & Solar Thermal technology, and Non-Solar RECs for

generation through renewable sources other than solar. These RECs will be sold in a price

band of Floor Price (minimum price) and Forbearance Price (maximum price). Floor and

Forbearance price for Solar and Non-Solar RECs are given in table below:

Table 7 : REC Floor and Forbearance Prices of REC

Type of REC Floor Price in

(Rs./REC)

Forbearance

Price

(Rs./REC)

Solar REC 9300 13400

Non-Solar REC 1500 3300

3.11.2 The operational framework for REC mechanism

The operational framework for REC mechanism consists of four main steps as shown in the

figure below:

Figure 8 : REC Procedure

Page 57: SUMMER INTERNSHIP REPORT ON

45

Figure 9 : REC Mechanism

Step 1 - Accreditation:

The proposed REC mechanism requires a procedure for accrediting generation plants which

are eligible to receive RECs. Accreditation is done to assess and establish eligibility of

renewable energy plants to receive RECs. The process of accreditation is largely one time

activity where in plants are validated on its renewable nature and other pre-requisites to be

eligible for issuance of REC. The State Nodal Agency appointed by the State Electricity

Regulatory Commission (SERC) shall be responsible for Accreditation. Accreditation process

involves processing of application, verification of projects, transfer of information, creation

and operation of accounts etc. The process of accreditation of eligible renewable energy

projects would also involve verification of Applications (projects) and sites and hence the

accreditation agencies at state level would need to have adequate monitoring capability.

Step 2 - Registration

Every eligible entity shall apply for registration at central level. Only one central agency at

national level will be authorized to recognize attributes from renewable generation to avoid

Page 58: SUMMER INTERNSHIP REPORT ON

46

double counting. Registration will result in creation of an account for all the entities

participating in the mechanism.

Step 3 - Information of RE generation

Central agency would receive information about injection of RE power by the accredited RE

generators through State Load Dispatch Centre (SLDC) via Regional Load Dispatch Centre

(RLDC) and local distribution licensee.

Step-4 Issuance of REC by REC registry

The eligible entity shall receive a certificate for a specified quantity of electricity generated

and injected into the grid. One REC will be issued for each 1 MWh of electricity generated

from renewable energy plants. RECs will be created as electronic records in a register

(because electronic documents are easier to track than paper documents). The issued

certificates will be credited to the registered account of the plant operator/owner.

Step 5 - Exchange of REC

RE generators with REC certificates can exchange their certificate at a common platform viz.

the power exchange approved by CERC. Obligated entities (as defined by the SERCs in their

regulations fo r RPO o b l iga t io ns ) s ha l l buy REC through power exchange. The

p r ice discovery of REC will be based on the demand and supply of the REC in the market,

subject to a forbearance price (ceiling price) determined by CERC. REC exchange will be

connected to the central agency to keep record of all the transaction in the REC exchange.

Step-6 Monitoring Mechanism

It is proposed that a panel of auditors shall be empanelled by CERC at the central level. The

remuneration charges for such panel of auditors will be met out of the funds which Central

Agency may collect from eligible entities.

Step 7 - Compliance by Obligated Entities

Central registry will furnish details of REC purchase and redemption to respective SERCs to

enable them to assess compliance by obligated entities and impose penalties on them, if

applicable. As evolved by the Forum of Regulators, there is a provision for enforcement

mechanism in the draft model regulation for SERCs under section 86 (1) (e) of the Act. As

per this provision, in the event of default, obligated entities would be directed to deposit the

Page 59: SUMMER INTERNSHIP REPORT ON

47

amount required for purchase shortfall of REC at forbearance price (i.e. maximum price) of

REC in a separate fund, which cannot be utilized without approval of the concerned State

Commission. In addition to this enforcement mechanism the penalty under Section 142 of the

Electricity Act 2003 would also be applicable to the obligated entity. The concerned state

commission can empower an officer of the SNA to procure required shortfall of REC at the

cost and expense of distribution licensee.

3.12 Detailed Project Report

Detailed Project Report involves producing a comprehensive document that can be used as a

basis for investment decision making, approval of plans and designs, project planning, and

implementation scheduling for all types of infrastructure projects. Preparation of detailed

project report is further step in firming up the proposal. When an investment proposal is to be

approved on the basis of functional report and the proposal is a major proposal, it would be

necessary to prepare a detailed project report to firm up the proposal for the capital cost as

well as for the various facilities. It includes...

Project description

Examination of technological parameters

Description of the technology to be used

Broad technical specification

Evaluation of the existing resources

Schedule plan

Layouts and flow diagrams

Hence these reports are to be made before investment is made into project. Thus formulation

of investment is based on the studies made. These can be considered as pre-investment

decision. Detailed project report is not prepared only for the investment decision-making

approval, but also for execution of the project and for preparation of further plan. General

format for preparation of detailed project report (DPR) as prescribed by Indian renewable

energy development authority (IREDA):

Page 60: SUMMER INTERNSHIP REPORT ON

48

3.12.1 Contents to be covered in a DPR

Technical and Commercial:

Introduction

Site details

Resources at Site location

Selection of Technology

Technology Provider

Power evacuation/interconnection with grid

Technical specifications of various components involved

Estimation of annual energy output

Environment impact/protection activities

Socio-economic impact in the region due to project implementation

Project cost estimates and tariff

Estimated electrical works

Estimated Civil works, Foundations

Project implementation Schedule

Drawing and designs, Site map and project layout

CDM benefits

Financial analysis

Conclusions

Annexure

Overall Plant layout

Land clearances

Grid connectivity approval

MOU/letter of willingness for PPA

In-principal approval, if applicable

Single line diagram

Switchyard layout

Plant control system configuration

Page 61: SUMMER INTERNSHIP REPORT ON

49

3.13 Financing Strategy and Financial Closure

3.13.1 Financing strategy

Wind power projects are more complex and risky because they rely on the flow of wind;

therefore risk management and risk allocation are extremely important. Like all other RE

projects Wind power projects are very capital intensive, hence they are extremely sensitive to

the structure and the conditions of capital cost financing. Due to their long time horizon, RE

projects have a very long exposure period to risk. They also need long maturities and lower

interest rates. There is no golden rule or a standard set for funds for financing of WPPs, but

adequate mix of funds and conditions are required for the WPP to be financially viable. The

most common structures used to finance projects are Project Financing, Corporate Financing,

and Lease Financing.

i) Project financing

It refers to financing structures wherein the lender has recourse only or primarily to the

assets of the project and depends on the cash flows of the project for repayment.

ii) Corporate financing

It involves the use of internal company capital to finance a project directly, or the use of

internal company assets as collateral to obtain a loan from a bank or other lender. The

main implication is that the financing of the project is based on the risk profile of the

company as a whole, and not of the particular project.

iii) Lease financing

It involves the supplier of an asset financing the use and possibly also the eventual

purchase of the asset, on behalf of the project sponsor. Assets which are typically leased

include land, buildings, and specialized equipment. A lease may be combined with a

contract for operation and maintenance of the asset.

Sources of finance

The Project can be financed by one or combination of more than one of the following:

i. Equity financing

ii. Debt financing

iii. CDM project financing

General eligibility criteria for RE loans

Page 62: SUMMER INTERNSHIP REPORT ON

50

Who can apply?

a) Public, Private Ltd companies, NBFCs and registered Societies

b) Individuals, Proprietary and Partnership firms (with applicable conditions)

c) State Electricity Boards which are restructured or in the process of restructuring and

eligible to borrow loan from REC/PFC Eligibility

d) Project demonstrating techno commercial viability

e) Profit making companies with no accumulated losses.

f) Debt Equity Ratio not more than 3:1 (typically 5:1 in case of NBFCs)

g) No default to any government agency (IREDA/PFC/REC) and other FIs / Banks

h) No erosion of paid-up capital

3.13.2 Financial Closure

It is a legally binding commitment of equity holders & debt financiers to provide or mobilize

funding for the full cost of the project. It is a pre-requisite to project closure & post

implementation review. It ensures proper disposition of all project assets and helps in

comparison against budgeted cost. Project development covers a range of activities that are

required to realize a financial closure of the project. It encompasses the assessment of the

technical feasibility and economic viability, preparation of contracts with suppliers of

equipment and services and with purchasers of the produced energy, acquisition of land,

acquisition of various permits and detailed engineering of the project. All of these elements

have to be completed successfully in order to come to an investment decision. This phase

already may require significant investments, typically in the order of several percentage of

the total project cost. A project developer will hence assess the investment climate and weigh

each of the risk factors in order to have a maximum chance of reaching financial closure.

Typically the following risk factors will be assessed:

i. What is the average lead time for this type of project

ii. Will it be possible to get a permit and a good power purchase agreement (PPA)

iii. Will there be a financial support scheme when the project is ready for financial closure

iv. Will the project be bankable after all, and under what conditions and what can be done

to improve these conditions from the equity perspective

Page 63: SUMMER INTERNSHIP REPORT ON

51

Figure 10 : Hurdles in Financial Closure

[Source: KfW Development Bank. (2005). Financing Renewable Energy. Frankfurt: KfW

Bankengruppe]

An investor may be willing to take some risk as he will benefit from any upswings in project

returns, but lenders are much more risk averse and will demand for several securities that

ensure the payment of debt and interest. This is being translated in the financial parameters

that lenders apply, such as debt term, interest rate, and debt service coverage ratio. At the

stage of financial closure, the risk assessment will concern the remaining phases of the

project cycle only.

Financial closure includes:

Arrangement of equity for the project

Arrangement of security for bank/financial institution

Quotations for civil and structural work

Quotation for main plant and machinery and off site equipment

Preparation of DPR

Negotiation of terms and sanction of term and working capital loan

Insurance during transit and project construction

Subsidies/incentives, if any

Page 64: SUMMER INTERNSHIP REPORT ON

52

Finally, making a legally binding commitment with equity holders & debt

financiers to provide or mobilize funding for the full cost of the project.

Page 65: SUMMER INTERNSHIP REPORT ON

53

3.14 Power Sale options

There are two way of electricity sale for an RE generator in India, either through REC route

or at preferential tariff.

Figure 11 : Power Sale Options

1) Through non-REC route:

The RE generator can sale electricity generated to obligated entities at preferential tariff

determined by CERC/SERC from time to time. ‘Obligated entity’ means the entity

mandated under clause (e) of subsection (1) of section 86 of the Act to fulfil the renewable

purchase obligation.

Hence there are following options under this route of sale of power

Sale to any DISCOM at preferential tariff

Sale at Open Access consumer at mutually agreed price (above APPC)

State wise preferential tariffs are indicated in the topic 3.3.2 of this report.

2) Through REC route

The other method of revenue earning is sale of electricity to obligated entities at or below

APPC and receiving REC for each 1MWh of electricity. These RECs can be sold at Power

Page 66: SUMMER INTERNSHIP REPORT ON

54

Exchange between Floor Price and Forbearance price determine by Central agency. Hence

there are following options to sale electricity under this route:

Sale in open access at mutually agreed price not above APPC

Sale through power exchange at market determined price.

3.15 Physical implementation of the Project

3.15.1 Engineering

It involves decisions regarding the following after detailed technical studies

1) Detailed plant design

2) Equipment specifications of the following major equipments

a. Rotor

i. Diameter

ii. Area swept

iii. Nominal revolutions

iv. No. of blades

v. Air brake

b. Tower (Hub height)

c. Operational data

i. Cut in wind speed

ii. Cut off wind speed

iii. Nominal wind speed

d. Generator type

e. Gearbox type

f. Control type

3) System engineering- During system analysis, systems engineering analyses and reviews

the impact of operational characteristics, environmental factors, and minimum acceptable

functional requirements, and develops measures suitable for ranking alternative designs in

a consistent and objective manner. These measures should also consider cost and

schedule. This analysis either verifies that the existing requirements are appropriate or

develops new requirements which are more appropriate for the operation.

4) Civil engineering

Page 67: SUMMER INTERNSHIP REPORT ON

55

3.15.2 Procurement

Procurement is the acquisition of goods or commodities by a company, organization,

institution, or a person. This simply means the purchase of goods from suppliers at the lowest

possible cost. The best way to do this is to let the suppliers compete with each other so that

the expenses of the buyer are kept at a minimum.

Procurement cycle for renewable energy power project consists of following steps:

Information gathering: If the potential developer does not already have an established

relationship with suppliers of needed products and services (P/S), it is necessary to

search for suppliers who can satisfy the requirements.

Supplier contact: When one or more suitable suppliers have been identified, requests for

quotation, requests for proposals, requests for information or requests for tender may be

advertised, or direct contact may be made with the suppliers.

Background review: References for product/service quality are consulted, and any

requirements for follow-up services including installation, maintenance, and warranty are

investigated. Samples of the P/S being considered may be examined or trials undertaken.

Negotiation: Negotiations are undertaken, and price, availability, and customization

possibilities are established. Delivery schedules are negotiated, and a contract to acquire

the P/S is completed.

Fulfilment: Supplier preparation, expediting, shipment, delivery, and payment for the P/S

are completed, based on contract terms. Installation and training may also be included.

Consumption, maintenance, and disposal: During this phase, the company evaluates the

performance of the P/S and any accompanying service support, as they are consumed.

Renewal: When the P/S has been consumed and/or disposed of, the contract expires, or

the product or service is to be re-ordered, company experience with the P/S is reviewed.

If the P/S is to be re-ordered, the company determines whether to consider other

suppliers or to continue with the same supplier.

3.15.3 Construction

The construction phase of a project is typically the most expensive. Therefore, it makes sense

to ensure that a number of details have been finalized prior to embarking on this project

Page 68: SUMMER INTERNSHIP REPORT ON

56

component. The following is a list of issues that should have been completed prior to

construction phase:

1) Finalize Costs (with fixed price agreements where possible

2) Obtaining all the necessary clearances and approvals

3) Financing

Construction Considerations

Depending on the size of the project, owner may choose to do much of the work himself or

have the project done under contract. In either case, be well prepared both technically and

legally to undertake the work. There are a number of factors to consider when beginning

construction of a RE power project:

1) Construction Timing- The time of year for project construction can influence the pace

and quality of work.

2) Materials Supply

3) Construction Permits & Inspections

4) Work Scheduling

5) Project Management

Following construction activities are involved in construction of a WPP

i. Civil work

a) Road and drainage

b) Wind turbine foundation

c) Met mast foundation

d) Building housing electrical switchgear, SCADA central equipment and possible

spares and maintenance facilities

ii. Electrical works

a) Equipment at the point of connection, whether owned by the wind farm owner or by

electricity network operator

b) Underground cable network and/or overhead lines, forming radial feeder circuits to

string of wind turbine

c) Electrical switchgear for protection and disconnection of feeder circuits

d) Transformer and switchgear associated with individual turbine (although this is now

commonly located within the turbine and is supplied by the turbine supplier)

Page 69: SUMMER INTERNSHIP REPORT ON

57

e) Reactive compensation equipments, if necessary

f) Earth(grounding) electrodes and systems

g) SCADA system

Central computer

Signal cables to each turbine and met mast

Wind speed and other meteorological transducer on met masts

3.15.4 Testing and Commissioning

Commissioning is the process of ensuring that systems are designed, installed, functionally

tested, and capable of being operated and maintained to perform in conformity with the

design intent. Power plant commissioning is a critical part of the overall process of taking a

power plant from construction and installation through to full operation. Testing &

commissioning requirements should be clearly stated in the contracts specification. These

should include parameters to be tested, test conditions, test points, values expected and

acceptable tolerances.

Objectives of testing & commissioning works:

1) To verify proper functioning of the equipment/system after installation

2) To verify that the performance of the installed equipment/systems meet with the

specified design intent through a series of tests and adjustments

3) To capture and record performance data of the whole installation as the baseline for

future operation and maintenance

Scope of testing & commissioning works:

1) Inspection of all parts, systems and station auxiliaries

2) Functional checks on simpler devices and systems

3) Error checks on measuring instruments

4) Secondary injection tests on protective relays

5) Operational checks on control systems

6) Measurement of the operating parameters of generating units

7) Measurement of maximum power output of generating units

8) Measurement of the efficiency of generating units at different, loads

Page 70: SUMMER INTERNSHIP REPORT ON

58

Steps for testing & commissioning:

1) Obtain design drawings and specifications and to be thoroughly acquainted with the

design intent

2) Check manufacturer‘s operating instructions and statutory requirements

3) Physically inspect the installation and equipment to determine variations from designs

and/or specifications.

4) Check individual components, e.g. key switches, control equipment, circuit breaker

status, and etc. for proper position and settings for completeness of installation.

5) Check inclusion of manufacturer‘s typical equipment testing data or factors before T&C

of particular equipment.

3.15.5 Operation and Maintenance

With proper operation and maintenance functions the production can be maximised as well as

the life span of the wind turbines can be elongated. Maximizing availability and yield of each

turbine is the goal of the O&M personnel. They minimize operations and maintenance costs

for the remaining life of project by managing day-to-day tasks like providing day-ahead

forecasts, operating the wind farm in a safe manner, protecting assets etc. There are three

organizational models for O&M: Project owner manages O&M, third-party manages O&M,

and turbine manufacturer manages O&M for an extended period.

Page 71: SUMMER INTERNSHIP REPORT ON

59

CHAPTER 4: FINANCIAL MODELLING

Figure 12 : Parameters of Financial Modelling

4.1 Cost estimates

Detailed cost estimates are needed for determining the economic merit of a project,

appraising its financial implications and arranging finance for it. The estimates are made to a

reasonable approximation in the pre-feasibility phase and they are then refined, on the basis

of more extensive investigations, in the feasibility phase. Various costs are explained here.

a. Initial costs

i. Feasibility study

ii. Development

b. Construction costs

i. Engineering cost

ii. Equipment cost

iii. Balance of plant system cost

iv. Grid connectivity cost

v. Owner’s

Page 72: SUMMER INTERNSHIP REPORT ON

60

vi. Contingency costs

c. Annual costs

i. Loan cost – (interest and principal repayment)

ii. O&M cost

iii. Land lease & resource rental (if applicable)

iv. Property taxes

v. Insurance premium

vi. General & administrative costs

Contingencies- A contingency allowance should be included to account for

unforeseen annual expenses. Generally, the contingency allowance is calculated

based on an estimate percentage of all other annual costs.

Figure: Expense estimate per project phase

Figure 13 : Cost Estimate per Project Phase

Source:http://nwcommunityenergy.org/project-design-management/cost-management

4.2 Development of a project model

A financial model is the most critical element of the financial assessment process. Most

financial models are structured in a similar way and have the following features (whether

created as a project specific spread-sheet model or using an off-the-shelf project finance

package):

I. Assumptions – all of the input variables to the model are usually kept together in one

worksheet. Assumptions may be based on expert knowledge, forecasts, technical

performance specifications, contract prices or other sources. The source of each

assumption needs to be clearly identified so that investors can assess whether the

assumption is reasonable.

Page 73: SUMMER INTERNSHIP REPORT ON

61

II. Calculations – the input variables are combined in a number of calculations, including

tax, depreciation/amortisation, loan balance and interest payments, and revenue and

operating costs.

III. Outputs – in general, the outputs of a financial model will include:

Cash flow statement

Profit and loss

Balance sheet; and

Key financial indicators such as debt and interest ratios, debt service coverage

ratio, NPV and IRR

4.3 Analysis of financial indicators

Financial indicators are the mathematical tools which help the finance manager to take a

decision about whether to accept the project or reject the project. One or more of the

following financial indicators are used to check the viability of the project.

Cash flow – To determine if the project is economically viable a cash-flow evaluation of

the project should be done. The cash-flow analysis looks at overall project revenues and

expenses on a year by year basis over the life of the project.

Benefit-cost ratio (BCR) - It is the ratio between discounted total benefits and costs.

Net present value (NPV) - The NPV of an investment proposal may be defined as the

sum of the present values of all the cash inflows less the sum of present values of all the

cash outflows associated with a proposal.

Internal rate of return (IRR) - The IRR of a proposal is defined as the discount rate

which produces a zero NPV i.e., the IRR is the discount rate which will equate the

present value of cash inflows with the present value of cash outflows. The IRR is also

known as Marginal Rate of Return or Time Adjusted Rate of Return. Like the NPV,

the IRR is also based on the discounting techniques.

Payback period- The payback period is defined as the number of years required for

the proposals cumulating cash inflows to be equal to its cash outflows.

Page 74: SUMMER INTERNSHIP REPORT ON

62

Debt service coverage ratio (DSCR) - The DSCR is the total net operating income

divided by the debt service.

Figure 14 : Project Cash-flow and Key Indicators

4.4 Sensitivity Analysis

If a project appears to be financially viable, based on analysis of the relevant financial

indicators using conservative or at least central case assumptions, then a more detailed

sensitivity analysis will be undertaken. The objective of the sensitivity analysis is to establish

which of the input assumptions to the financial model has the greatest impact on the financial

outcome. It is important to understand both which variable can have the greatest impact, and

which is most likely to have the greatest impact, either singly or in combination with other

variables. The sensitivity analysis is related to the next stage, risk assessment and

management, since many of the key sensitivities can be contractually hedged to reduce the

Page 75: SUMMER INTERNSHIP REPORT ON

63

risk to the lender. For example, key supply and purchase contracts may be fixed by volume

and price.

4.5 Risk analysis

It is a technique to identify and assess factors that may jeopardize the success of a project or

achieving business goal. This technique also helps to define preventive measures to reduce

the probability of these factors from occurring and identify counter measures to successfully

deal with these constraints when they develop to avert possible negative effects on the

viability of the project.

Being prepared to face and manage risks is essential to any type of project development, and

renewable energy projects are certainly no exception. Renewable energy projects often have a

protracted period of at-risk investment. Lenders and investors will be particularly concerned

to assess all of the risks associated with a project and to agree, with the project sponsors, on

appropriate means to manage or mitigate those risks.

Types of risks associated with the project are indicated in the following figure.

Figure 15 : Types of Risk in Various Phases of Project

4.5.1 Assessing risk

The sponsors of the project will typically undertake their own risk assessment early in the

project planning process, as they will be exposed to the risks during the planning phase,

whereas the lenders will undertake their risk assessment at a later stage, focusing on

Page 76: SUMMER INTERNSHIP REPORT ON

64

construction and operation phase risks. At either stage, risk assessment is generally

undertaken through the steps described below.

Risk Identification

Risk Matrix

Quantitative Risk Assessment

4.5.2 Managing Risk

There are essentially three options for managing risks.

Change the project

Allocate the risk to the most appropriate party

Transfer the risk to a third party

Page 77: SUMMER INTERNSHIP REPORT ON

65

CHAPTER 5: SUMMARY

5.1 Conclusion

Wind energy is becoming very important in the energy mix of the country. This trend will

accelerate in the coming years due to reasons of India’s pursuit of energy security, issues

related to climate change, new technologies like bigger capacity turbines, and gradual

depletion of fossil fuels and their price volatility. Globally, wind energy, along with other

renewable energy technologies, is the new investment destination. This sector has continued

to show robust growth world over, which is evident in the acceleration in investment flows

into the sector.

One of the biggest barriers in the accelerated development of the wind energy is the lack of

basic understanding and knowledge about the complex procedure of project development.

The discrepancies in the procedures followed in different states of India add to these

difficulties. This study has tried to give an overview of project development cycle for wind

power project implementation.

Initially, the report guides the investors and developers in project and financial planning. The

aspects that the managers should take into consideration while project planning are indicated

which can help the managers to comprehensively plan the project so as to minimise the

difficulties in the later parts of the project. The report then guides the managers to three major

decisions regarding financial planning.

A major task for the investor / developer is the decision regarding finalising the state in which

he wants to set up WPP in. The project thoroughly covers all the major factors that the

developer must not miss while taking this important decision. These major factors – wind

power potential & installed capacity, Feed-in-Tariffs, incentives offered to WPPs, evacuation

infrastructure, grid connectivity, regularity in receipt of payment, sharing of CDM benefits,

reactive energy charges, banking, and transmission and wheeling charges – are explained in

brief in the report to guide the WPP developers to select the state which would be best for the

company to increase profitability and reduce complexities.

The report than elaborates the issues related to site identification. It guides the developer to

select the site which can maximise the future profits by maximizing the Capacity Utilisation

Factor and restricting the capital costs.

Page 78: SUMMER INTERNSHIP REPORT ON

66

The report also guides the developers in their approach to check the feasibility study of the

project. The developers are directed towards both, technical and commercial viability and as

well as other factors like environmental and social impact assessment.

Wind resource assessment on the site is a time consuming and expensive activity in WPP

development. There is no standardised procedure followed in all the states. The procedures

followed in all key states for mast installation, data collection and data verification has been

explained briefly in the report.

Wind power projects fail if the site isn’t suitable for development of the project. Soil

conditions, soil erosion, accessibility and closeness to grid must be checked before finalising

the site for WPP development. The report guides the developer about all these aspects of a

good site.

To maximise the output, a wind farm be designed in such a way so as to optimise the

available wind resource. This is ensured by preparing a most suitable layout for a wind farm.

The layout of the turbines should be prepared in such a way that the wind is not obstructed

into its way towards the turbines. The project guides the developers in preparation of best

possible wind farm layout and maximization of CUF.

Land acquisition is a major and one of the most crucial activities in the development of any

power project. If issues related to land acquisition are not dealt with properly, they can cause

serious damage to the profitability of the project. Hence, in this report, due importance is

given to the land acquisition related issues that the developers may face. Also the land

acquisition policies of the key states have been explain in brief.

The developer must not miss any opportunity to reap the benefits attached with renewable

energy generation. Clean Development Mechanism and Renewable Energy Certificates have

become important tools to make the renewable power projects financially viable. The project,

therefore elaborates these two new concepts. The procedures to get the project approved for

these mechanisms and cultivate the benefits have been explained in this project.

Wind power projects and highly capital intensive projects that require substantial debt portion

in their financial structure. Detailed project report is asked for by the Banks and financial

institutions before approving loans. This report provides guidelines to the investors for

preparation of the DPR.

Page 79: SUMMER INTERNSHIP REPORT ON

67

WPP, like all other capital intensive projects, should have the financial strategy so as to

maximise the profits and minimise the risk. This project gives guidelines to the managers to

optimise benefits by working out best possible financial strategy. He project also guides the

investors to get the financial closure done.

The revenues comes from sell of power, and hence the investor should choose the best

possible option for sale of power. The power can be sold through REC or non-REC route.

The benefits and constraints attached to both of these routes have been elaborated in the

report.

Taking into consideration the great range and variety of activities, it is quite clear that a

project steered in the right direction can be implemented with ease. It is hoped that this study

will help shorten the lead-time for wind power projects and will help Indian wind power

sector to accelerate from its current pace and help the country to achieve energy security.

5.2 Recommendations

From the detailed study of the project it can be understood that there is too much diversity in

various states with regard to feed in tariff, land acquisition, wind resource assessment etc.

Hence, the panning and feasibility study becomes cumbersome for the developer. For

example, financial feasibly has to be conducted using different FiTs for different states.

Because of completely different procedures/policies for land acquisition and WRA in

different states, prior experience of doing these activities in one state may not be helpful in

doing same activity in another state. Hence, these procedures should be standardised.

The transfer of forest land is more time consuming. There should be better coordination

between MNRE and MOEF.

As per CERC guidelines, the metering point for WPPs should be at wind-farm location and

hence the cost of grid connectivity should be borne by State utility, because this cost is not

included in project cost for determination of tariff. Even though, the cost of grid

interconnection has to be borne by the developers in many states. Sometimes, this makes the

project financially unviable for the developer. Therefore, either the cost of grid

Page 80: SUMMER INTERNSHIP REPORT ON

68

interconnection should be invariably borne by the state utility or such costs should be taken

into consideration while computing the tariff.

Because of low returns investors don’t find it attractive to invest in the wind energy sector.

The Generation Based Incentives which are discontinued since 1 April 2012 should be

restarted. The GBI should also be increased from above set 0.5 Rs/unit.

The investment in WPP development is also found riskier because of irregularity in payment

by the discoms to the generators. SERCs play a stricter role to make sure that all payments

are regularly made.

Page 81: SUMMER INTERNSHIP REPORT ON

69

Bibliography

1. MNRE annual report 2011-12

2. Assessment of Investment Climate for Wind Power Development in India for IREDA

by Consolidated Energy Consultants Ltd (CECL)

3. Wind Energy Engineering By Pramod Jain, MC GRAW HIL Publication

4. Report Indian wind energy outlook 2011

5. CERC (Terms and Conditions for Tariff determination from Renewable Energy)

resources, 2012

6. Forum of regulators - Assessment of achievable potential of new and renewable energy

resources in different states during 12 plan period and determination of RPO trajectory

and its impact on tariff

7. GEDA – instructions / guidelines / terms & conditions for setting up of wind farm

under developer approach

8. MNRE guidelines for wind measurement by private sector, 2008

9. MNRE guidelines for installation of wind turbine models in India

10. Wind Farm Siting Issues in Australia – Australian Government

11. CERC. (2010). Terms and conditions for recognition and issuance of Renewable

Energy.

12. ICRA – wind energy sector: key trends and outlook

13. North West community energy. 29 Jun. 2010 [http://nwcommunityenergy.org/project-

design-management/project-scope-plan]

14. Energy Alternatives India. 7 Jun. 2010

[http://www.eai.in/ref/services/project_report.html]

15. North West community energy. 2 Jul. 2010 [http://nwcommunityenergy.org/project-

design management/typical-project-phases/development-phase]

16. Stojmirovik, G. A Practical guide assessment & Implementation of small hydropower.

Hydro Tasmania Consulting.

17. Goldsmith, K. (1993). Economic & Financial Analysis of Hydropower Projects.

Trondheim: Norwegian Institute of Technology.

18. Eco Securities. Guidebook to financing CDM Projects. Kettingsraat.

19. Windustry. 8 Jun. 2010 [http://www.windustry.org/wind-basics/learn-about-wind-

energy/wind-basics-know-your-land/know-your-land]

Page 82: SUMMER INTERNSHIP REPORT ON

70

20. Kishore, V.; Renewable Energy Engineering and Technology. New Delhi: TERI.

21. Tetra Tech EC & Nixon Peabody LLP. (2008). Wind Energy Siting Handbook.

Washington.

22. Paul Gardner, A. G. Wind Energy- The facts.

23. UNEP. Environmental Due Diligence of Renewable Energy Projects.

24. Project legal documentation. (n.d.). Retrieved July 12, 2010, from RETScreen:

http://www.retscreen.net/ang/project_legal_documentation.php

25. Meike Soker, E. V. (2007). Renewable Energy and the Clean Development

Mechanism: Potential, Barriers and Ways forward. Wuppertal: Federal Ministry for the

Environment, Nature Conservation and Nuclear Safety.

26. AHEC, IIT Roorkee. (2008). Standards/Manuals/guidelines for Small Hydro

Development.

Page 83: SUMMER INTERNSHIP REPORT ON

71

ANNEXURES

ANNEXURE 1: Table: State wise potential and installed capacity of wind power

State Estimated

Potential

(MW)

Installed

capacity as

on

31.12.2011

(MW)

Installed

capacity

as %age

of

potential

Andhra Pradesh 5394 213 3.95%

Gujarat 10609 2641 24.89%

Karnataka 8591 1852 21.56%

Kerala 790 35 4.43%

Madhya Pradesh 920 330 35.87%

Maharashtra 5439 2560 47.07%

Rajasthan 5005 1830 36.56%

Tamil Nadu 5374 6613 123.06%

Others 7008 4 0.06%

Total 49130 16078 32.73%


Recommended