+ All Categories
Home > Documents > Summer Join us for our Flash Botox and · DYSPORT BOTOX OR XEOMIN $100 OFF each additional syringe...

Summer Join us for our Flash Botox and · DYSPORT BOTOX OR XEOMIN $100 OFF each additional syringe...

Date post: 22-Sep-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
1
6 Denver Citizen July 19-25, 2019 SCHEDULE YOUR APPOINTMENT TODAY OFFER: Patients must pay in full on Thursday, Aug. 8 or Friday, Aug. 9, 2019 to take advantage of the event pricing. Procedures may be scheduled on either of those days or at a later date. Patients may not buy additional product for future office visits. Summer Special Join us for our Flash Botox and Filler Event THURSDAY, AUG. 8 FRIDAY, AUG. 9 Call and book your appointment to take advantage of these great deals. per unit BOTOX OR XEOMIN DYSPORT $100 OFF each additional syringe of Belotero, or the full lines of Juvéderm, Restylane, or Radiesse $ 10 $ 3 . 20 $ 50 OFF 1ST SYRINGE of filler per unit 704.741.7179 19900 W. Catawba Ave., Suite B, Cornelius 888.883.4159 7476 Waterside Loop Rd., Suite 600, Denver County proceeds with wastewater plant expansion LINCOLNTON – Lincoln County is ready to move forward with the expansion of its wastewater treatment plant follow- ing a public hearing July 15. The hearing was required due to the county’s request for funding under the N.C. Department of Infrastructure, clean Water State Revolving Fund, a loan that will cover $14 million of the $26 million project, with an interest rate of 1.92 per- cent. Revenue bonds will be used to fund the remaining $12 million. The design of the expansion, which will double the plant’s capacity, has been com- pleted. The plant is at 86 percent of its current capacity of 3.3 million gallons per day, and expansion is needed to support the numerous housing developments expected to be built in Denver in the coming years. The county is also expanding its water treatment plant, and with a combined cost of approximately $40 million, coun- ty water and sewer rates are expected to continue an upward trend. Customer bills increased this summer and last, and one more increase is coming in July 2020. Expansion of the wastewater treatment plant is tentatively expected to be finished in April 2021. In other county business, commission- ers approved two funding requests from the public works department. The department sought approval to pur- chase a 2019 Mack Roll Off Truck that will replace a 2007 model that was wrecked in the past year. The $167,633.50 purchase was unanimously approved. The board also unanimously approved a $7.8 million contract with State Utilities Contractors to extend the waterline that runs along N.C. 73. In total, the project calls for a 24-inch line from Killian Creek to Ingleside Farm Road, a 16-inch line from Ingleside Farm Road to Lambs Way Road, a 12-inch line that will run along Ingleside Farm Road from N.C. 73 to Old Plank Road and a 12-inch line that will run along Old Plank Road from Ingleside Farm Road to the Duke Energy Lincoln Combustion Tur- bine Station. “What we’re trying to do is improve the looping of our major water lines so that we have redundant ways of feeding the sys- tem if there’s a main break on N.C. 16,” Public Works Director Don Chamblee said. by MATT CHAPMAN [email protected] The Lincoln County Board of Commissioners authorized a $7.8 million contract July 15 to extend the waterline that runs along N.C. 73. File photo
Transcript
Page 1: Summer Join us for our Flash Botox and · DYSPORT BOTOX OR XEOMIN $100 OFF each additional syringe of Belotero, or the full lines of Juvéderm, Restylane, or Radiesse $3. 20 $10 $50

6 Denver Citizen July 19-25, 2019

SCHEDULE YOUR APPOINTMENT TODAY

OFFER: Patients must pay in full on Thursday, Aug. 8 or Friday, Aug. 9, 2019 to take advantage of the event pricing. Procedures may be scheduled on either of those days or at a later date. Patients may not buy additional product for future office visits.

SCHEDULE YOUR APPOINTMENT TODAY

SummerSpecial

Join us for our Flash Botox and Filler Event

THURSDAY, AUG. 8 FRIDAY, AUG. 9 Call and book your appointment to take advantage of these great deals.

per unitBOTOX OR XEOMINDYSPORT

$100 OFF each additional syringe of Belotero, or the full lines of Juvéderm, Restylane, or Radiesse

$10 $3 . 20 $50 OFF 1ST SYRINGE

of filler

per unit

704.741.717919900 W. Catawba Ave., Suite B, Cornelius

888.883.41597476 Waterside Loop Rd., Suite 600, Denver

County proceeds with wastewater plant expansionLINCOLNTON – Lincoln County is

ready to move forward with the expansion of its wastewater treatment plant follow-ing a public hearing July 15.

The hearing was required due to the county’s request for funding under the N.C. Department of Infrastructure, clean Water State Revolving Fund, a loan that will cover $14 million of the $26 million project, with an interest rate of 1.92 per-cent. Revenue bonds will be used to fund the remaining $12 million.

The design of the expansion, which will double the plant’s capacity, has been com-pleted. The plant is at 86 percent of its current capacity of 3.3 million gallons per day, and expansion is needed to support the numerous housing developments expected to be built in Denver in the coming years.

The county is also expanding its water treatment plant, and with a combined cost of approximately $40 million, coun-ty water and sewer rates are expected to continue an upward trend. Customer bills increased this summer and last, and one more increase is coming in July 2020.

Expansion of the wastewater treatment

plant is tentatively expected to be fi nished in April 2021.

In other county business, commission-ers approved two funding requests from the public works department.

The department sought approval to pur-chase a 2019 Mack Roll Off Truck that will replace a 2007 model that was wrecked in the past year. The $167,633.50 purchase was unanimously approved.

The board also unanimously approved a $7.8 million contract with State Utilities Contractors to extend the waterline that runs along N.C. 73.

In total, the project calls for a 24-inch line from Killian Creek to Ingleside Farm Road, a 16-inch line from Ingleside Farm Road to Lambs Way Road, a 12-inch line that will run along Ingleside Farm Road from N.C. 73 to Old Plank Road and a 12-inch line that will run along Old Plank Road from Ingleside Farm Road to the Duke Energy Lincoln Combustion Tur-bine Station.

“What we’re trying to do is improve the looping of our major water lines so that we have redundant ways of feeding the sys-tem if there’s a main break on N.C. 16,” Public Works Director Don Chamblee said. ❏

by MATT [email protected]

The Lincoln County Board of Commissioners authorized a $7.8 million contract July 15 to extend the waterline that runs along N.C. 73.

File photo

Recommended