+ All Categories
Home > Documents > Summer Training in badarpur ntpc

Summer Training in badarpur ntpc

Date post: 02-Apr-2018
Category:
Upload: rohit-verma
View: 233 times
Download: 1 times
Share this document with a friend

of 54

Transcript
  • 7/27/2019 Summer Training in badarpur ntpc

    1/54

    Page 1

    INTRODUCTION

    National Thermal Power Corporation Limited was formed in 1975 to plan,

    promote and organize an integrated and efficient development of Central

    Sector Power Stations.

    The Singrauli Super Thermal Power Station was the first of the series of

    pithead power stations along with 400kV ac transmission line network. It is

    located on the banks of Govind Ballabh Pant Sagar (Rihand Reservoir),

    about 200km south of Varanasi in the Sonebhadra district of Uttar Pradesh.

    For coal transportation, a captive railway system with rapid loading and

    unloading facility known as Merry-Go Round (MGR), continuously hauls

    coal from the Jayant block of Singrauli coalfields to the plant site. The rake

    consists of 30 wagons and will deliver 1800 MT of coal in each cycle. The

    average daily consumption of coal is 25,000 MT per day i.e. 8.0 million

    tonnes per annum considering average calorific value of 4000 kcal/kg and

    7000 hrs of operation in an year for the ultimate capacity of the plant of

    2000 MW having 5 units of 200 MW each and 2 units of 500 MW each.

    The 5200MW generating units of Stage I are each equipped with coal-

    fired, regenerative, re-heat type steam generators with electrostatic

    precipitators, each generating 700 tonnes/hr of steam at 138 kg/cm 2 pressure

    and 535C temperature. The steam generator feeds steam to a condensing,

    horizontal, tandem compound 3-cylinder re-heat type turbo generator

    rotating at 3000 rpm and each generates 200 MW. Three phase generator

    transformer of 250 MVA capacity steps up the generation voltage from

    15.75 KV to 400 KV.

    Cooling water from the Rihand Reservoir is drawn through an approachchannel. It is then pumped into concrete intake duct by vertical pumps of

    15000 m 3/hr capacity each. From the ducts, the water is circulated through

    condensers and is then discharged into a duct from where it flows into an

    open channel. This open channel carries the water for a distance of 6 kms to

    affect sufficient cooling before it joins back into Rihand Reservoir.

    The 2500MW generating units of Stage II are each equipped with coal-

    fired, regenerative, re-heat type steam generators with electrostatic

  • 7/27/2019 Summer Training in badarpur ntpc

    2/54

  • 7/27/2019 Summer Training in badarpur ntpc

    3/54

    Page 3

    Circulating water system Ash handling system Compressed air system Hydrogen generating plant

    Growth of NTPC:

    Fig: figure of growth rate

    NTPC was ranked 3rd

    best employer and the No.1 Public sector undertaking

    among 220 major companies in India by Business Today Hewitt

    Association Best Employers Survey 2003.

    COAL TO STEAM STEAM TO MECHANICAL POWER

  • 7/27/2019 Summer Training in badarpur ntpc

    4/54

    Page 4

    MECHANICAL POWER TO ELECTRICITY SWITCHING AND TRANSMISSION

    COAL TO STEAM

    Coal from the coal wagons is unloaded in the coal handling plant. This coal

    is transported upto the raw coal bunkers with the help of belt conveyors.

    Coal is transported to bowl mills by coal feeders. The coal is pulverized in

    the bowl mill, where it is ground to a powder form. The mill consists of a

    round metallic table on which coal particles fall. This table is rotated with

    the help of a motor. There are three large steel rollers, which are spaced 120

    apart. When there is no coal, these rollers do not rotate but when the coal is

    fed to the table it packs up between the roller and the table and this forces

    the roller to rotate. Coal is crushed by the crushing action between the rollers

    and the rotating table. This crushed coal is taken away to the furnace through

    coal pipes with the help of hot and cold air mixture from the primary air

    (P.A.) fan. The P.A. fan takes atmospheric air, a part of which is sent to the

    air preheaters for heating while a part goes directly to the mill for

    temperature control. Atmospheric air from forced draft (F.D.0 fan is heatedin the air heaters and sent to the furnace as combustion air.

    Water from the boiler feed pump passes through economiser and reaches the

    boiler drum. Water from the drum passes through down comers and goes to

    bottom ring header. Water from the bottom ring header is divided to all the

    four sides of the furnace. Due to heat and the density difference water rises

    up in the water wall tubes. Water is partly converted into steam as it rises up

    in the furnace. This steam and water mixture is again taken to the boiler

    drum where the steam is separated from water. Water follows the same path

    while steam is sent to the superheaters for superheating. The superheaters

    are located inside the furnace and the steam is superheated (540C) and

    finally goes to the turbine.

    Flue gases from the furnace are extracted by the induced draft (I.D.) fan,

    which maintains a balanced draft in the furnace with F.D. fan. These flue

    gases emit their heat energy to various superheaters in the plant house and

    finally pass through the air preheaters and goes to the electrostatic

    precipitator where the ash particles are extracted. Electrostatic precipitators

  • 7/27/2019 Summer Training in badarpur ntpc

    5/54

    Page 5

    consist of metal plates, which are electrically charged. Ash particles are

    attracted to these plates, so that they do not pass through the chimney to

    pollute the atmosphere. Regular mechanical hammer blows cause theaccumulation of ash to fall to the bottom of the precipitator where they are

    collected in a hopper for disposal. This ash is mixed with water to form

    slurry and is pumped to ash dyke.

    STEAM TO MECHANICAL POWER

    From the boiler, a steam pipe conveys steam to the turbine through a stop

    valve (which can be used to shut off steam in an emergency) and through

    control valves that automatically regulate the supply of steam to the turbine.Stop valves and control valves are located in the steam chest and a governor,

    driven from the main turbine shaft, operates the control valves to regulate

    the amount of steam used (this depends upon the speed of the turbine and the

    amount of electricity required from the generator).

    Steam from the control valves enters the high pressure cylinder of the

    turbine, where it passes through a ring of stationary blades fixed to the

    cylindrical wall. These act as nozzles and direct the steam into a second ring

    of moving blades mounted on a disc secured to the turbine shaft. Thissecond ring turns the shafts as a result of the force of the steam. The

    stationary and moving blades together constitute a stage of the turbine and

    in practice many stages are necessary, so that the cylinder contains a number

    of rings of stationary blades with rings of moving blades arranged between

    them. The steam passes through each stage in turn until it reaches the end of

    the high pressure cylinder and in its passage some of its heat energy is

    changed into mechanical energy.

    The steam leaving the high pressure cylinder goes back to the boiler for

    reheating and returns by a further pipe to the intermediate pressure cylinder.Here it passes through another series of stationary and moving blades.

    Finally, the steam is taken to the low pressure cylinders, each of

    which it enters at the center flowing outwards in opposite directions

    through the rows of turbine blades an arrangement known as double

    flow to the extremities of the cylinder. As the steam gives up its heat

    energy to drive the turbine, its temperature and pressure fall and it

  • 7/27/2019 Summer Training in badarpur ntpc

    6/54

    Page 6

    expands. Because of this expansion the blades are much larger and

    longer towards the low pressure end of the turbine.

    The turbine shaft usually rotates at 3,000 rpm. This speed is determined by

    the frequency of the electrical system used in the country. In India, it is the

    speed at which a 2- pole generator is driven to generate alternating current at

    50 Hz.

    When as much energy as possible has been extracted from the steam it is

    exhausted directly to the condenser. This runs the length of the low pressure

    part of the turbine and may be beneath or on either side of it. The condenser

    consists of a large vessel containing some 20,000 tubes, each about 25 mm

    in diameter. Cold water from the water source i.e. the Rihand Reservoir iscirculated through these tubes and as the steam from the turbine passes

    round them it is rapidly condensed into water condensate. Because water has

    a much smaller comparative volume than steam, a vacuum is created in the

    condenser. This allows the steam pressure to reduce down to pressure below

    that of the normal atmosphere and more energy can be utilized.

    From the condenser, the condensate is pumped through low pressure heaters

    by the extraction pump, after which its pressure is raised to boiler pressure

    by the boiler feed pump. It is further passed through feed heaters to theeconomiser and the boiler for reconversion into steam.

    The cooling water drawn from the reservoir is returned directly to the source

    after use.

    MECHANICAL POWER TO ELECTRICITY

    The turbine shaft is mechanically coupled to the generator rotor shaft

    through thrust bearings. The steam rotates the turbine at 3000 rpm thus the

    rotor of the generator also rotates at 3000 rpm. This speed is necessary to

    generate electricity at a frequency of 50 Hz with a two pole turbo- generator.

  • 7/27/2019 Summer Training in badarpur ntpc

    7/54

    Page 7

    The rotor carries the field winding over it. This field winding is excited by a

    DC excitation system. The supply to the excitation system is tapped from the

    unit auxiliary transformer. The flux generated by this field current cuts thearmature coil. The armature coil is star- star connected and is induced with

    three phase emf. The emf is tapped with the help of slip rings and brushes.

    This emf is carried over to the generator transformer through a bus duct. The

    bus duct is voltage transformer grounded.

    The generator transformer has delta connection in the primary side and star

    connection in the secondary side. The generator bus supplies electric power

    per phase to the three-phase transformer or bank of three single-phase

    transformers. These transformers transmit electric power to the switchyard

    for further transmission. These transformers also supply the unit auxiliarytransformers required for the working of various electric motors, pumps and

    other equipments installed in the unit.

    SWITCHING AND TRANSMISSION

    The electricity is usually produced in the stator windings of large moderngenerators and is fed through terminal connections to one side of a generator

    transformer that steps up the voltage to 400KV. From here conductors carry

    it to a series of three switches comprising of an isolator, a circuit breaker and

    another isolator.

    The circuit breaker, which is a heavy- duty switch capable of operating in a

    fraction of second, is used to switch off the current flowing to the

    transmission lines. Once the current has been interrupted the isolators can be

    opened. These isolate the circuit breaker connected to its terminals. Here

    after the maintenance or repair work can be carried out safely.

    From the circuit breakers the current is taken to the busbar conductors,

    which run the length of the switching compound and then to another

    circuit breaker with its associated isolators, before being fed to the Grid.

    Each generator in a power station has its own transformer, circuit breaker

    and associated isolators but the electricity generated is fed into a common

    set of busbars.

  • 7/27/2019 Summer Training in badarpur ntpc

    8/54

    Page 8

    Circuit breakers work like combined switches and fuses but they have

    certain special features and are very different from the domestic switch and

    fuse. When electrical current is switched off by separating two contacts, anarc is created between them. At the voltage use in homes, this arc is very

    small and lasts for a fraction of a second but at very high voltages used for

    transmission, the size and power of the arc is considerable and it must be

    quickly quenched to prevent damage.

    Three phase, four-wire system is used for large power transmission, as it is

    cheaper than the single-phase two-wire system that supplies the home. Also

    power is generated in a three-phase system.

    The center of the power station is the control room. Here the engineersmonitor the output of electricity, supervising and controlling the operation of

    generating plant and high voltage switchgear and directing power to the grid

    system as required. Instruments on the control panels show the output and

    the existing condition of the whole main plant and a miniature diagram

    indicates the precise state of the electrical system.

    COAL HANDLING PLANT STEAM GENERATOR TURBINE TURBO- GENERATOR SWITCHYARD

  • 7/27/2019 Summer Training in badarpur ntpc

    9/54

    Page 9

    CONTROL & INSTRUMENTATIONAUXILIARY POWER DISTRIBUTION SYSTEM WATER TREATMENT PLANT CIRCULATING WATER SYSTEMASH HANDLING SYSTEMHYDROGEN GENERATING PLANT

    COAL HANDLING PLANT

    It is estimated that the coal required for a 2000MW Super Thermal Power

    Station is of the order of 8.4 million tonnes based on an average calorific

    value of 4000 kcal/kg and 7000 hours of operation per year.

    Two coal handling systems one for 5200MW units and the second for

    2500MW units have been provided. The capacity of each of the two

    conveying systems has been kept as 1200 tonnes/hour. Interconnection

  • 7/27/2019 Summer Training in badarpur ntpc

    10/54

    Page 10

    between the two coal handling systems has also been provided to transfer

    crushed coal from one crusher house to the other.

    The Merry-go Round (MGR) system has been provided for loading the coal

    at the Jayant mines and unloading the coal into the track hopper

    automatically when the wagons are moving at a predetermined speed of

    8km/hr. A closed loop of rail lines has been laid between the loading and

    unloading points and a rake of 30 bottom discharge type wagons of 60

    tonnes capacity each transport coal of size 0 to 200mm from mines and

    unload it into track hopper in 10 minutes. Automatic bottom opening type

    wagons discharge coal into track hopper while the rake travels over the

    hopper, the discharge door being automatically opened by a line sidetripping mechanism. The coal received at the track hopper is delivered to

    two parallel conveyors 1A &1B located on the sides through four nos. of

    rotary plough paddle feeders designed to handle maximum coal lump size of

    200mm. Double stream of conveyor system carries the coal to the crusher

    house, having four nos. crushers and vibrating screens each having a

    capacity of 600T/hr. The coal after being crushed from 200mm to 20mm

    size is conveyed to the boiler bunkers. The width of the conveyor belt is kept

    1400mm. The crushed coal from the crusher house, if not required, is

    stacked in the open stock yard. Two nos. of stacker cum reclaimer areprovided on rail track to handle maximum 20mm size coal lumps and have a

    capacity of 1200T/hr.

    Paddle FeedersFour nos. of traveling paddle feeders are provided to collect coal from the

    track hopper. They travel along the entire length of the hopper and transfer

    the coal from the hopper, uniformly to the pair of underground conveyors

    1A &1B. The paddle feeders move to and fro on the rail with the help of 4

    nos. of wheel mounted on the supporting structures. The wheels are drivenby electric motor of 415V supply.

    Belt Conveyor SystemThe belting system is designed for conveyor capacity of 1200T/hr and belt

    speed of 2.6metre/sec. The belt is of cotton fabric with rubber covers of

    adequate strength having width of 1400mm.

  • 7/27/2019 Summer Training in badarpur ntpc

    11/54

    Page 11

    Magnetic SeparatorsThis is an electromagnet placed above the conveyor to attract magnetic

    materials. Over this magnet there is one conveyor to transfer these materialsto chute provided for dumping at ground level. Because of this, continuous

    removal is possible and it is also not necessary to stop the electric supply to

    the magnetic separators for removal of separated material.

    Stacker and ReclaimerTwo nos. of traveling stacker/reclaimer each capable of both stacking and

    reclaiming are installed which operate on rail tracks running for adequate

    length to cover the entire coal storage yard. The belt of the stacker/reclaimer

    is mounted on a cantilever boom and has a capacity of 1200T/hr for bothstacking and reclaiming. The boom can revolve about the center of the

    receiving hopper and discharge/reclaim materials on/from both sides of the

    track anywhere between 28 meters radius of the boom. These units work in

    conjunction with the conveyor 9A & 9B.

    Crusher HouseThe plant has four nos. of crushers each capable of crushing coal of 200mm

    size at the rate of 600T/hr. the crusher with hammer tips is symmetrical in

    size and shape on either side. In case of wearing out of one side, the othercan be used by turning over the tips. These crushers are placed in the crusher

    house, which have special strong foundations to bear the vibrations due to

    running of the crushers.

    Vibrating FeederThe vibrating feeder is used for throwing the coal on the underground

    conveyor belt from where coal goes to the bunker. Coal from the stockyard,

    with the help of bulldozer, is taken to the vibrating feeder via reclaimer

    hopper and underground conveyor belt. In case the bunker requirement ismore than the capacity of crusher or stacker reclaimer, then with the help of

    bulldozer the coal is sent to the bunker from the stockyard, through these

    feeders.

  • 7/27/2019 Summer Training in badarpur ntpc

    12/54

    Page 12

  • 7/27/2019 Summer Training in badarpur ntpc

    13/54

    Page 13

    STEAM GENERATOR

    The steam generator used in Stage I of SSTPS has a primary steam flow of

    700 tonnes/hr at 139 kg/cm 2 pressure and 535C temperature at the

    superheater outlet. This boiler is tangentially fired, has balanced draft,

    natural circulation, radiant single reheat, dry bottom open door type and is

    direct fired with Indian bituminous pulverized coal. The steam generator

    used in Stage II of SSTPS has a primary steam flow of 1725 tonnes/hr at 178

    kg/cm 2 pressure and 540C temperature at the superheater outlet. This boiler

    is balanced draft, controlled circulation, dry bottom single drum type and is

    direct fired with Indian bituminous pulverized coal.

    The arrangement of main boiler and its accessories is as follows:

    The boiler structural are divided into two parts:

    Supporting Structures:Boiler supporting structure consists of a systematic arrangement of columns

    stiffened with horizontal beams and vertical diagonal bracings and comprise

    of low carbon steel material. It is composed of 18 main columns and 12

    auxiliary columns. The main columns support the main boiler components

    viz. drum, water wall membrane, panels, superheaters, reheaters,

    economisers, air preheater, burners and galleries at various levels. The

    auxiliary columns support the boiler platforms and other ducts coming inthat region. The total weight of supporting structures is about 970 M.T.

    Galleries and Stairways:Galleries and stairways around the combustion and heat recovery areas are

    provided for proper approach to the boiler. Stairways on both the sides of the

    boiler are provided. All the floors are covered with the floor gratings of

    required depth for walkway and are welded to the structure. Their total

    weight is 900 M.T.

  • 7/27/2019 Summer Training in badarpur ntpc

    14/54

    Page 14

    FurnaceA boiler furnace is that space under or adjacent to a boiler in which fuel isburned and from which the combustion products pass into the boiler proper.

    It provides a chamber in which combustion reaction can be isolated and

    confined so that the reaction remains a controlled force. In addition it

    provides support or enclosure for the firing equipment.

    In stage I, fusion welded furnace is used and in stage II controlled

    circulation furnace is used.

    Boiler DrumThe function of the boiler drum is to separate water from the steam

    generated in the furnace walls and to reduce the dissolved solid contents of

    the steam to below the prescribed limit of 1 ppm. The drum is located on the

    upper front of the boiler.

    In stage I, the drum weighs about 127 MT is apporx.15.7 m. long and is

    placed at a height of 53340 mm. It is made of carbon steel. It is designed for

    maximum pressure of 176 kg/cm 2 and maximum metal temperature of

    354C. In stage II, the drum is 22.07 m. long and is placed at a height of 72m. It is made of carbon steel. It is designed for maximum pressure of 204.9

    kg/cm 2 and maximum metal temperature of 366C.

    SuperheaterSuperheater is meant to raise the temperature of saturated steam by

    absorbing the heat from flue gases and thus increases the cycle efficiency

    economically. There are three stages of super heater besides the sidewalls

    and the extended walls. The first stage consists of horizontal superheater of

    convection mixed flow type with upper and lower bank located aboveeconomiser assembly in the rear pass. The upper bank terminates into hanger

    tubes, which are connected to outlet header of the first stage superheater.

    The second stage superheater consists of pendant platen, which is of radiant

    parallel flow type. The third stage superheater pendant spaced is of

    convection parallel flow type.

    In Stage I, the primary steam flow is 700 tonnes/hr at 139 kg/cm 2 pressure

    and 535C temperature at the superheater outlet. In Stage II, the primary

  • 7/27/2019 Summer Training in badarpur ntpc

    15/54

    Page 15

    steam flow is 1725 tonnes/hr at 178 kg/cm 2 pressure and 540C temperature

    at the superheater outlet.

    AttemperatorAttemperation or desuperheating is the reduction or removal of superheat

    from steam to the extent required. The characteristic performance of a

    superheater, which receives its heat by convection from gases flowing over

    it, is raising temperature with increasing output. To obtain some degree of

    control, the superheater must be designed for full temperature at some partial

    load. As a result, there will be excessive surface, with corresponding

    excessive temperatures at higher loads. Attemperator is used to reduce the

    steam temperature.

    EconomiserThe purpose of the economiser is to preheat the boiler feed water before it is

    introduced into the steam drum by recovering heat from the flue gases

    leaving the boiler. The economiser is located in the boiler rear gas pass

    below the rear horizontal superheater. The economiser is continuous loop

    type, without fins, and water flows in upward direction and gas in the

    downward direction.

    A single stage of economizer is used to absorb the heat from the flue gases

    and add this as sensible heat to the feed water before it enters into boiler

    drum. The economizer is non-steaming continuous plain tube type and of

    tubular construction.

    ReheaterA single reheat system is used to further increase the efficiency of the cycle

    by raising the temperature of already expanded steam. After passing through

    the high-pressure stage of the turbine, steam is returned to the reheated bytwo cold reheat lines. After being reheated to the designated temperature, the

    reheated system at 535 degree Celsius temperature and 24.5 kg/sq. cm

    pressure is returned to the intermediate pressure stage of the turbine via the

    hot reheat line.

    BurnersIn stage I, there are total twenty four pulverized coal burners for corner fired

    boilers and twelve oil burners provided each in between two pulverized fuel

  • 7/27/2019 Summer Training in badarpur ntpc

    16/54

    Page 16

    burner. The pulverized coal burners are arranged in such a way that the six

    mills supply the coal burners at four corners of the furnace.

    In stage II, there are total thirty-two pulverized coal burners for corner fired

    boilers and sixteen oil burners provided each in between two pulverized fuel

    burner. The pulverized coal burners are arranged in such a way that the eight

    mills supply the coal burners at four corners of the furnace.

    IgnitersThere are twelve side igniters per boiler in stage I and sixteen in stage II.

    The atomizing air for the igniter is taken from the service air compressors.

    The burners are located at three elevations in stage I and four elevations instage II. Each elevation has four oil burners and igniters. These elevations

    are normally referred to as AB elevation, CD elevation, EF elevation and

    GH elevation. Igniters are used for lighting the main oil gun. There are two

    igniter air fans to supply air for combustion of igniter oil.

  • 7/27/2019 Summer Training in badarpur ntpc

    17/54

    Page 17

  • 7/27/2019 Summer Training in badarpur ntpc

    18/54

    Page 18

    The arrangement of various boiler auxiliaries is as follows:

    Coal BunkerThese are in- process storage silos used for storing crushed coal from the

    coal handling system. Generally, are made up of welded steel plates. There

    are six such bunkers supplying coal to the corresponding mills in stage I and

    eight in stage II. These are located on top of the mills so as to aid in gravity

    feeding of coal.

    Coal FeederEach mill is provided with a drag link gravimetric feeder to transport raw

    coal from the bunker to the inlet chute, leading to mill at desired rate. Coalfeeders are essential as the mills do not have any storage provision therefore

    only that much coal should be sent to the mill that has to be directly sent to

    the furnace and this is decided by the load requirement.

    MillsThere are six mills in stage I, out of which five are required for operation at

    maximum load and one acts as standby. In stage II, there are eight mills and

    here six are required for operation and two act as standby. These are located

    adjacent to the furnace at 0 m level. These mills pulverize the coal to thedesired fineness to be fed to the furnace for combustion.

    Primary Air FanPrimary air fan is used to supply primary air to transport the pulverized coal

    from the mills/bunkers to the furnace and to dry up the coal in the path.

    There are two PA fans per unit and are designed to handle atmospheric air

    upto a temperature of 50C. These fans are driven by a 6.6KV motor each.

    They are located at 0 m level near the boiler.

    Air PreheaterAir preheater transfers heat from the flue gases to the cold primary and/ or

    secondary air by means of rotating heating surface elements. Beneath these

    regenerative type air preheaters, there exists a steam coil air preheater. These

    are located in the secondary pass of the furnace at a height of around 16 m

    level. Each unit has two such air preheaters.

  • 7/27/2019 Summer Training in badarpur ntpc

    19/54

    Page 19

    Forced Draft FanThe FD fan is designed for handling secondary air for the boiler. These fans

    are located at 0 m level near the PA fan. The fan is coupled with an 800Winduction motor and is commissioned to drive the cold air through the air

    preheater.

    Wind BoxThese act as distributing media for supplying secondary/ excess air to the

    furnace for combustion. These are generally located on the left and right

    sides of the furnace while facing the chimney.

    Scanner Air FanScanner fans are installed in the boiler for supplying continuously cooling

    air to the flame scanner provided for flame supervision. Normally one fan

    remains in service while the other one remains available as standby.

    Igniter Air FanIgniter fan provides necessary combustion air to all the igniters. Fan makes

    the suction from atmosphere directly and supplies air to the wind boxes of

    individual igniters at a fixed constant uncontrolled rate at ambient

    temperature.

    Electrostatic PrecipitatorTwo ESPs have been set up for each generating units to remove the major

    part of fly ash. Each ESP has 304 electrodes made of steel sheets. Between

    each pair of electrodes a unidirectional high voltage of 60kV is applied,

    connecting its negative polarity to emitting electrodes and positive to

    collecting electrodes. The flue gases that are normally neutral when pass

    between rows of these electrodes are ionized due to the emitting and the

    negative towards the collecting electrodes. Since dust particles have great

    affinity towards negative particles they get attached to them and are thus

    negatively charged. Thus the dust particles are deposited on the collecting

    electrodes and are dislodged from there by periodic rapping of electrodes

    and are drained to the ash disposal system through hoppers.

  • 7/27/2019 Summer Training in badarpur ntpc

    20/54

    Page 20

    Induced Draught FanInduced draught fan is used to drive the waste flue gases out of the chimney

    after they have been deprived almost all of their heat energy. A 1300 kWinduction motor is used to drive this fan. The major part of the energy

    transferred to the gas is the velocity energy after the impeller. The velocity

    energy is converted into pressure energy by the diffuser. Flow is controlled

    by changing the direction of gas entry to the impeller blades by providing

    adjustable guide vanes.

    Fig: induced draft fan

    ChimneyThese are tall RCC structures with single or multiple flues. The height of

    these chimneys helps in natural draught of the flue gases to the atmosphere.

    There are four chimneys in SSTPS- one for units 1, 2 and 3, second for units

  • 7/27/2019 Summer Training in badarpur ntpc

    21/54

    Page 21

    4 and 5 and one each for units 6 and 7.

    Fig: figure of chimney

    Seal Air FanThese are used for supplying seal air to the mills to prevent ingress of coal

    dust into gearbox lubrication oil. There are two fans per boiler.

  • 7/27/2019 Summer Training in badarpur ntpc

    22/54

    Page 22

    Soot Blowers

    The soot blowers are used for efficient on-load cleaning of furnace,

  • 7/27/2019 Summer Training in badarpur ntpc

    23/54

    Page 23

    superheaters, reheaters and regenerative air heaters. There are three types of

    soot blowers provided in the plant in requisite numbers. They are:

    1. Long retractable soot blowers2. Wall blower3. Air heater blower

    Superheated steam is tapped from the superheater for the purpose of soot

    blowing.

    In stage I, there are 20 long retractable soot blowers, 56 wall blowers and 2

    air heater blowers and in stage II, there are all together 104 soot blowers. All

    these soot blowers are operated together once in every eight hours for few

    minutes only.

    TURBINE

    A steam turbine has two main parts viz. the cylinder and the rotor. The

    cylinder (stator) is a cast iron or steel housing usually divided at the

    horizontal centerline. Its halves are bolted together for easy access. The

    cylinder contains fixed blades, vanes and nozzles that direct steam into

    moving blades carried by the rotor. Each fixed blade set is mounted in

    diaphragms located in front of each disc on the rotor, or directly in the

    casing. A disc and diaphragm together make a turbine stage. Steam turbine

    can have many stages. The rotor is a rotating shaft that carries the moving

    blades on the outer edges of either drums or discs. The blades rotate as the

    rotor rotates. The rotor of a large steam turbine consists of high, intermediate

    and low pressure sections.

    In a multiple stage turbine, steam at a high pressure and high temperature

    enters the first row of fixed blades or nozzles through an inlet valve or

    valves. As the steam passes through the fixed blades or nozzles it expands

    and its velocity increases. The high velocity jet of steam strikes the first set

    of moving blades. The kinetic energy of the steam changes into mechanicalenergy, causing the shaft to rotate. The steam then enters the next set of

    fixed blades and strikes the next row of moving blades.

  • 7/27/2019 Summer Training in badarpur ntpc

    24/54

    Page 24

    As the steam flows through the turbine, its pressure and temperature

    decreases, while its volume increases. The decrease in pressure and

    temperature occurs as the steam transmits energy to the shaft and performs

    work. After passing through the last turbine stage, the steam exhausts into

    the condenser or process steam system.

    ROTOR OF H.P. TURBINE

  • 7/27/2019 Summer Training in badarpur ntpc

    25/54

    Page 25

    Large turbines use both impulse and reaction types. These combination

    turbines have impulse blades at the high pressure end and reaction blades atthe low pressure end. The blade length and size increases throughout the

    turbine to use the expanding steam efficiently. Blade rows require seals to

    prevent steam leakage where the pressure drops. Seals for impulse blades are

    provided between the rotor and the diaphragm to stop leakage past the

    nozzle. Seals for reaction blades are provided at the tips of both the fixed

    and moving blades.

    In stage I, condensing, tandem reheat, impulse type turbine is installed. The

    HP cylinder has 12 stages, IP cylinder has 11 stages and LP cylinder has 42

    stages. The HP and IP parts are single flow cylinders and the LP part has

    double flow cylinder.

    In stage II, 3 cylinder, reheat, reaction type turbine is installed. The HP

    cylinder has 18 stages, IP cylinder has 142 stages and LP cylinder has 62

    stages. The HP part is a single- flow cylinder and the IP and LP parts are

    double flow cylinders.

    The arrangement of various turbine auxiliaries is as follows:

    Vacuum systemThis system comprises of condenser, ejector, CW pump and gland steam and

    gland steam coolers. The equipments under this system strive to maximize

    the work done of turbine by maintaining the rated vacuum limits.

    Condenser: There are two condensers entered to the two exhausters of the

    LP turbine. These are surface type condensers with two-pass arrangement.

    Cooling water is pumped into each condenser by a vertical CW pump

    through the inlet pipe. Steam exhausted from the LP turbine by washing theoutside of the condenser tubes losses its latent heat to the cooling water and

    is connected with water in the steam side of condenser. This condensate

    collects in the hot well, welded to the bottom of the condensers.

    Ejectors: there are two 100% capacity ejectors of the steam eject system.

    The purpose of the ejector is to evacuate air and other non-condensing gases

    from the condensers and thus maintain the vacuum in the condensers.

    C.W. Pumps: the pumps which supply the cooling water to the condensers

    are called the circulating water pumps. There are two such pumps in each

  • 7/27/2019 Summer Training in badarpur ntpc

    26/54

    Page 26

    unit. These pumps are normally vertical, wet-pit, mixed flow type, designed

    for continuous heavy duty.

    Condensate System:The steam after condensing in the condenser known as condensate is

    extracted out of the condenser hot well by condensate pump and taken to the

    deaerator through ejectors, gland steam cooler and series of LP heaters. This

    comprises of condensate pumps, low pressure heaters and deaerator.

    Condensate Pumps: the function of these pumps is to pump out the

    condensate to the deaerator through ejectors, gland steam coolers and LP

    heaters. These pumps have four stages and since the suction at a negativepressure, special arrangements have been made for providing sealing.

    L.P. Heaters: Turbine has been provided with non-controlled extractions

    which are utilized for heating the condensate, from turbine bleed steam.

    There are 4 LP heaters in which the last four extractions are used.

    Deaerator: The presence of certain gases, principally oxygen, carbon

    dioxide and ammonia, dissolved in water is generally considered harmful

    because of their corrosive attack on metals, particularly at high temperatures.

    The function of the deaerator unit is to remove dissolved gases from the

    boiler feed water by mechanical means.

    Feed Water System:This system helps in the supply of feed water to the boiler at requisite

    pressure and steam/ water ratio. This system comprises of boiler feed pumps,

    high pressure heaters and drip pumps.

    Boiler Feed Pump: The function of the boiler feed pump is that the water

    with the given operating temperature should flow continuously to the pumpunder a certain minimum pressure. It passes through the suction branch into

    the intake spiral and from there is directed to the first impeller. After leaving

    the impeller it passes through the distributing passages of the diffuser and

    thereby gets a certain pressure rise and at the same time it flows over to the

    guide vanes to the inlet of the next impeller. This will repeat from one stage

    to the other till it passes through the last impeller and the end diffuser. Thus

    the feed water reaching into the discharge space develops the necessary

    operating pressure.

  • 7/27/2019 Summer Training in badarpur ntpc

    27/54

    Page 27

    There are three boiler feed pumps in each unit in SSTPS. Two of these are

    turbine driven while one, which is a stand by is motor driven. The feed

    pump motor, which is the biggest motor in the whole plant, is a 9800 Winduction motor.

    H.P. Heaters: These are regenerative feed water heaters operating at high

    pressure and located by the side of turbine. These are generally vertical type

    and turbine bleed steam pipes are connected to them. HP heaters are

    connected in series on feed water side and by such arrangement, the feed

    water, after feed pump enters the HP heaters.

    Drip Pump: The steam that bleeds from the turbine after condensation is

    termed as drip/ drain. Two numbers of sectional multistage centrifugal

    horizontal pumps per unit are provided. Out of these one will be running and

    other is stand- by. These are especially suited for the purpose of pumpingfrom the space of high vacuum.

    Turbine Lubricating Oil System:Turbine lub- oil system seeks to provide proper lubrication of turbo-

    generator bearings and operation of barring gear. This consists of main oil

    pump (MOP), starting oil pump (SOP), AC standby oil pumps and

    emergency DC oil pump and jacking oil pump (JOP).

    Main Oil Pump: This is coupled with turbine rotor through a gear

    coupling. When the turbine is running at normal speed i.e. 3000 rpm or the

    turbine speed is more than 2800 rpm, then the desired quantity of oil to the

    governing system and to the lubrication system is supplied by this oil pump.

    Starting Oil Pump: It is a multistage centrifugal oil pump driven by AC

    electric motor. Starting oil pump is provided to meet the oil requirement of

    the turbo- set during starting and stopping. It also serves as stand by to main

    oil pump.

    AC Standby Oil Pump: This is a centrifugal pump driven by an AC electricmotor. It runs for 10 minutes in the beginning to remove air from the

    governing system and fill the oil system with oil. This pump automatically

    takes over under interlock condition when the oil pressure falls below a

    certain standard level. Thus this pump meets the requirement of lubrication

    system under emergency conditions.

    Jack Oil Pump: This pump enables the main bearing of the complete rotor

    assembly to be raised or floated in the bearing during turbine generator start

    up and during shut down, thus preventing damage to the bearings when shaft

  • 7/27/2019 Summer Training in badarpur ntpc

    28/54

    Page 28

    speeds are too low for hydrodynamic lubrication to take place. This pump

    takes suction from the main oil tank and after lifting the bearing the drain is

    connected back to the main oil tank.Oil Coolers: The oil of the lubrication and the governing systems is cooled

    in the oil coolers. The cooling medium for these coolers is circulating water.

    The pressure of the cooling is kept lower than that of oil to avoid its mixing

    with oil if the tubes rupture. There are five oil coolers out of which four are

    for continuous operation and one remains as standby. All the oil coolers are

    arranged to operate in parallel. The cooling water temperature is not more

    than 36C.

    Auxiliary Steam System:Some of the thermal cycle equipments/ systems require steam for primaryheating, actuation, sealing etc. This requirement is met by the auxiliary

    steam system.

  • 7/27/2019 Summer Training in badarpur ntpc

    29/54

    Page 29

  • 7/27/2019 Summer Training in badarpur ntpc

    30/54

    Page 30

    TURBO-GENERATOR

    The turbo-generator essentially consists of a fixed stator and a revolving

    rotor. The stator core carries a three phase winding in which alternating emf

    is induced, the rotor carrying field magnets and coils which provide the

    magnetic flux of the machine, set up by exciting the generator field current.

    The turbo-generator, one no. for each unit is of three phase, two-pole

    cylindrical rotor type which is directly driven by a steam turbine, at

    3000RPM.

    These generators have direct water-cooling for the stator winding and directhydrogen cooling for the rotor winding. The stator frame consists of a

    cylindrical center section and two end shields, which are gas tight and

    pressure resistant. It accommodates the electrically active parts of the stator

    i.e. the stator core and stator winding. The stator winding consists of a

    double layer, short-pitched lap winding with 540 transposition. The rotor

    shaft is a single solid forging. On the forged round rotor, slots are milled out

    to insert and secure the conductors of the generator excitation windings.

    Rotor windings consist of two cooling ducts and L-shaped strips of

    laminated insulator for slot insulation.

    The field current is supplied to the rotor winding through radial terminal

    bolts and two semi-circular conductors located in the hollow bores of the

    exciter and rotor shafts. The field current leads are connected to the exciter

    leads at the exciter coupling with Multi Kontakt plug-in contacts, which

    allow for unobstructed thermal expansion of the field current leads.

    The nameplate specifications of the generators are as follows:

    Generator# 1 to 5:MakeM/s BHEL

    Rated output200 MW/ 235 MVA

    Power factor0.85 lag

    Frequency50 Hz

    Terminal voltage15.75 KV

    Speed.3000 rpm

    Stator current.9050A

    Hydrogen pressure3.5 kg/cm 2

  • 7/27/2019 Summer Training in badarpur ntpc

    31/54

    Page 31

    Field current..2600 A

    No. of terminals brought out. Six (6)

    Generator# 6&7:Make..M/s KWU, Germany

    Supplied byM/s BHEL

    Type ..THDF 115/59

    Rated output..500MW/ 588MVA

    Power factor..0.85(lag)

    Frequency..50Hz

    Terminal voltage21KV

    Speed.3000RPMStator current.16,200A

    Hydrogen pressure.4 kg/cm 2

    Short circuit ratio0.48

    Field current4040A

    Class & Type of insulation.MICALASTIC(Similar to Class F)

    No. of terminals brought out...six (6)

    Excitation System

    For Stage I:In 200 MW turbo- generator, static excitation system is used. This excitation

    system consists of an excitation transformer. This is a step down

    transformer. The input to this transformer is taken directly from the

    generator bus. From the excitation transformer the output goes to a thyristor

    bridge which acts as full- converter and rectifies ac to dc. The thyristor

    bridge gives a controlled dc output. The output of the rectifier bridge then

    energizes the rotor of the synchronous generator. This output of the rectifier

    bridge is fed to the rotor of the generator with the help of slip- rings and

    brushes.

    For Stage II:In 500MW turbo-generator, brushless excitation system is used. Brushless

    exciter consists of a three-phase permanent magnet pilot exciter, whose

    output is rectified and controlled by the thyristor voltage regulator to provide

    a variable d.c. current for the revolving armature of the main exciter. The

    three-phase current is induced in the rotor of the main exciter and is rectified

    by the rotating diodes and fed to the field winding of the generator rotor.

    Since the rotating rectifier bridge is mounted on the rotor, slip rings are not

  • 7/27/2019 Summer Training in badarpur ntpc

    32/54

    Page 32

    required and the output of the rectifier is directly connected to the field

    winding through generator rotor shaft. A common shaft carries the rectifier

    wheels, the rotor of the main exciter and permanent magnet rotor of the pilotexciter. The main exciter is of 6-pole revolving armature type. The three

    phase pilot exciter is of 16-pole revolving field type.

    De-excitation of the machine is effected by driving the thyristor to inverter

    mode of operation causing the thyristor to supply maximum reverse voltage

    to the field winding of the main exciter. Approximately 0.5 seconds after the

    de-excitation command is received two field suppression contactors connect

    field suppression resistors in parallel to the main exciter field winding and

    following this a trip command is transmitted to the field circuit breaker via

    its trip coil. In the event of failure of electronic de-excitation throughinverter operation, de-excitation is effected with a delay of 0.5 seconds by

    the field suppression resistors.

    Hydrogen Cooling SystemThe rotor winding is cooled by hydrogen flowing through the radial

    ventilating ducts. It is designed for hydrogen pressure upto 3kg/sq. cm

    gauge. Hydrogen is cooled by the gas coolers mounted on the stator body.

    The hydrogen cooler water is cooled by water heat exchanger situated

    outside the machine. The purity of hydrogen permitted is 97-99%. Hydrogenis preferred to air as the cooling media because of its lower density and

    better thermal properties. While filling the generator for the very first time

    with hydrogen, air inside it is purged by CO 2 and CO 2 is purged by

    hydrogen. It is done in order to have safe filling of hydrogen. The hydrogen

    inside the generator is maintained dry by continuously circulating the gas

    through suitable hydrogen dryer.

    Temperature LimitsThe class B type insulation is provided on the generator windings. RTDs

    have been embedded in the windings for measurement of temperature.

    Winding and core temperature recorders have been set for tripping 105C

    for maximum temperature of stator winding. Rotor winding temperature is

    recorded by a special recorder, which functions on the principle of rotor

    winding resistance variation with temperature.

    Generator Sealing Oil System

  • 7/27/2019 Summer Training in badarpur ntpc

    33/54

    Page 33

    To prevent the leakage of hydrogen, used for cooling in the generator, along

    the generator shaft a seal oil system is applied. Shaft seals operate with flow

    of oil under pressure. A pressure regulating valve maintains a constantdifferential pressure of seal oil over hydrogen pressure in the generator.

    Vacuum treated oil is fed to the center of the seal ring assembly from the

    seal oil supply unit. From here the oil flows in both directions between the

    rings and the shaft, and thus a film is established in the constricted area,

    which prevents the leakage of hydrogen. The main seal oil pump is driven

    by a 440V ac motor. A dc motor supplied from the station battery drives an

    emergency oil pump, which starts automatically when seal oil pressure drops

    or ac motor trips due to any reason.

    Generator Stator Water Cooling SystemA closed loop stator water cooling system is used to maintain a constant rate

    of flow of demineralised cooling water to the stator winding at requisite

    temperature. The stator water cooling system consists of two 100% primary

    water to water heat exchanger, two 100% duty ac motor driven

    demineralised water pumps, two 100% water filters, one 100% magnetic

    filter, an expansion tank, specific heat measuring instruments etc. suitable

    resistance temperature detectors are provided for measuring the temperature

    of stator water at the inlet and outlet of stator winding.

    Generator Main Bus:Generator main bus connections consist of natural air-cooled continuous

    enclosure type isolated phase buses. No power circuit breakers are

    interposed between the generator and the main generating transformers.

    However, disconnecting links are provided for isolating purposes. The bus

    duct enclosure is made of aluminium alloy sheet. Sealed openings are

    provided in the bus-duct-run near the insulators for inspection and

    maintenance. There is a main bus duct which is circular with diameterapproximately 1000mm where as the tap-off duct is circular of diameter

    approximately 680mm.continuous current carrying capacity of main bus on

    nominal voltage of 15.75KV is 10000A. Temperature rise of conductors and

    for the enclosure (over the ambient of 50C) is 20C. The generator main

    bus has the three isolated phase buses connected in star connection. The

    neutral of the main bus is grounded through a Neutral Grounding

    Transformer (NGT) i.e. a common duct comes out from where the three

  • 7/27/2019 Summer Training in badarpur ntpc

    34/54

    Page 34

    isolated phase buses are joined at a common point and goes to the primary of

    the NGT.

    Generator Transformer

    For Stage I:

    For each unit in stage I one 250MVA, 15.75/ 400KV three phase outdoor

    transformer has been installed in the transformer yard. It is connected to the

    generator through isolated bus ducts. The LV winding is delta-connected and

    the HV winding is star-connected. The LV winding is delta-connected sothat if by chance there is a grounding fault in the generator then that fault

    current will not pass on to the transmission line further as it will keep

    circulating in the delta circuit itself. The HV side is star-connected because

    the phase voltage in case of star-connection is 1/ 3 times the line voltage

    and as the bus system used consists of isolated phase buses it is more

    economical to use star-connection as the for lower voltage lesser insulation

    will be required. Oil forced and water forced (OFWF) cooling is provided to

    get continuous nominal rating of the transformer. It is equipped with all

  • 7/27/2019 Summer Training in badarpur ntpc

    35/54

    Page 35

    standard measuring and controlling fittings and accessories like Buccholz

    relay, on-load tap changer, oil temperature indicator etc. deluge system is

    also provided around the transformer for fire protection.The nameplate specifications of generator transformers in stage I are as

    follows:

    Generator transformer # 1 to 5:MakeBHEL

    Manufacturing year.1981

    Type of coolingOFWF

    Rating..250MVA

    Temperature rise- Oil.40CWater.60C

    KV at no-load- HV400

    LV15.75

    Phase- HV3

    LV3

    Frequency.50Hz

    Vector GroupYnd11

    % Impedence...14%

    Amperes- HV360.9

    LV9184.9

    Insulation level- HV1425KVP

    LV95KVP

    Core & Winding weight..140550 kg

    Weight of oil49430 kg

    Total weight.237400 kg

    Quantity of oil..56820 liters

    For Stage II:

    The dual purpose of these transformers are to step up the output of 500MWgenerators from generation voltage of 21 KV to 400KV voltage for power

    distribution and if required shall be back charged from 400KV side and used

    to step down for feeding loads through unit auxiliary transformers.

    These transformers are installed in the transformer yard adjacent to the

    powerhouse building. The LV winding/ HV winding are delta/ star

    connected. The neutral terminal is solidly grounded. The vector group of

    these transformers when connected in a bank of three single- phase

  • 7/27/2019 Summer Training in badarpur ntpc

    36/54

    Page 36

    transformers is YNd11. These transformers are connected to respective

    generators through isolated bus ducts. No power circuit breakers or power

    switches are connected between generator and generator transformer.However, disconnecting links are provided at generating end for isolation

    purpose. These transformers are equipped with independent oil forced and

    water forced cooling system.

    Generator transformer # 6 & 7:MakeBHEL

    Manufacturing year.1985

    Type of coolingOFWF

    Rating..200MVATemperature rise- Oil.50C

    Water.60C

    KV at no-load- HV400/ 3

    LV21

    Phase- HV1

    LV1

    Frequency.50Hz

    Vector GroupYNd11

    % Impedence...14%

    Amperes- HV866.0

    LV9523.8

    Insulation level- HV1050KVP

    LV125KVP

    Core & Winding weight..1230- 50 kg

    Weight of oil27500 kg

    Total weight.179500 kg

    Quantity of oil..29540 liters

    400 KV SWITCHYARD AT SSTPS

    Switchyard is located 350 meters south of main powerhouse

    building. 400kV switchyard is having two numbers of double main

    and transfer bus system. Approximately 2000MW of SSTPS power

  • 7/27/2019 Summer Training in badarpur ntpc

    37/54

    Page 37

    is transmitted through 400kV switchyard. It is consisting of 23

    bays, which includes generator and interconnecting transformer

    (ICT) bays. 400kV is designed to limit the switching surge overvoltages to 2.5 P.U. and sustain temporary over voltage to 1.5 P.U.

    The symmetrical fault current is 40kA (rms). The basic insulation

    level (B.I.L.) is 1425kV. The switching surge is 1050kV. Each bus

    comprises of three phase strung buses with four sub-conductors per

    phase. ACSR MOOSE conductors are used for stringing on the

    gantries of the switchyard. It is tied up with double tension string

    assembly in twin/quadraple bundles with 450mm sub-conductor

    spacing. For connecting the breaker with isolators 4 IPS

    aluminium tubular buses in each bay are used. For intermediate

    supports, bus post insulators are provided. One double main

    transfer bus system having main buses 1 and 2 and transfer bus no.

    1 caters for Bay no. 1 to Bay no. 12. Similarly, second double main

    transfer bus system having main bus no. 3 and 4 and transfer bus

    no. 2 caters for Bay no. 14 to Bay no. 23. Bay no. 13 interconnects

  • 7/27/2019 Summer Training in badarpur ntpc

    38/54

    Page 38

    400kV main bus 1 to 3 and 2 to 4. There is no interconnection

    between transfer buses 1 and 2.

    Bay-wise description of various feeders is as follows: -

    1. 400KV Lucknow Line + 63MVAR Reactor2. 200MW 15.75KV Generator-53. 400KV Allahabad Line-2 + 80MVAR Reactor4. 200MW 15.75KV Generator-45. 400KV Bus Coupler-16. 200MW 15.75KV Generator-37. 400KV Anpara Line8. 200MW 15.75KV Generator-29. 400KV Allahabad Line-1 + 80MVAR Reactor10. 200MW 15.75KV Generator-111. 400KV Transfer Bus Coupler -112. 400KV Side of 100MVA 400/132KV ICT-113. 400KVBus Section 1&214. 400KV Side of 100MVA 400/132KV ICT-215. 400KV Vindhyachal-216. 400KV Transfer Bus Coupler-217. 400KV Vindhyachal Line-I18. 400KV Bus Coupler-219. 500MW 21KV Generator-620. 400KV Rihand Line-221. 500MW 21KV Generator-722. 400 KV Kanpur line23. 400 KV Rihand-I

    The bay width is 27.0m. Height of the gantry structure is 13.7m

    and intermediate gantry structure is 20.7m. Minimum ground

    clearance is 7.1m. Earthing mat is laid of 40mm diameter MS

    rounds throughout the switchyard and equipments grounding are

    done by 7512mm strips. Generator bays are connected to

    generator transformer secondary by overhead stringing.

  • 7/27/2019 Summer Training in badarpur ntpc

    39/54

    Page 39

    In SSTPS, transfer bus coupler scheme is applied. This scheme is

    applied to transfer the load on one breaker to another breaker for

    maintenance of a breaker. Suppose if a generating unit is supplyingpower to main bus 1. Now the breaker of the bay of this generating

    unit has to be repaired then it is not a practical and economic

    solution to trip the unit for this purpose. Therefore a parallel path is

    created for the flow of power through the transfer bus using the

    transfer bus coupler bay breaker to the main bus 1. For this first the

    isolator in the generator bay connecting the feeder to the transfer

    bus is closed. Then, in the TBC the breaker and associated

    isolators to the main bus 1 are closed. After this the TBC baybreaker is closed and this creates a parallel path for the power.

    Now the circuit breaker, which is to be repaired, of the generator

    bay is opened and then the associated isolators are also opened.

    The various equipments used in 400KV switchyard are as follows:ISOLATOR:An isolator is a switch, which can make or break an electric circuit

    when the circuit is to be switched on no-load. Isolators cannotoperate unless the breaker is open. Bus 1 and 2 isolators cannot be

    closed simultaneously. No isolator can operate when

    corresponding earth switch is on.

    There are two types of isolators used in the switchyard, namely the

    sequential isolator and the pantograph isolator. The sequential

    isolator is a two-post type in which the moving contact moves

    through 90 on its axis. The pantograph isolator has two moving

    contact arms designed in scissor-like fashion, which move throughonly 20 on its axis.

    Circuit Breaker:A circuit breaker is a switch, which can make or break the circuit

    on load and even on faults. It is heavy-duty equipment mainly

  • 7/27/2019 Summer Training in badarpur ntpc

    40/54

    Page 40

    utilized for protection of various circuits and operation at load. It is

    installed accompanied by two isolators.

    The various types of circuit breakers used in the switchyard are:

    1.Bulk oil circuit breaker2.Minimum oil circuit breaker3.Air blast circuit breaker4.Sulphur hexa-flouride circuit breaker

    These circuit breakers have been classified on the basis of their

    quenching mechanism. The various operating mechanisms used for

    these circuit breakers are spring operation, solenoid operation andpressure or pneumatic operation.

    Earth Switches:These are devices which are normally used to earth a particular

    system to avoid accident, which may happen due to induction on

    account of live adjoining circuit. These switches do not handle any

  • 7/27/2019 Summer Training in badarpur ntpc

    41/54

    Page 41

    appreciable current at all. These are simple mechanically operated

    switches.

    Lightening Arresters:Lightening arresters are equipments which are connected at the

    transformer terminals and the incoming terminals of the line for

    protection against lightening or any surges developing in the

    system. In this plant, valve type lightening arresters are used. Such

    LAs consist of nonlinear resistors in series with spark- gaps. The

    spark- gap assembly acts as a fast switch, which gets ionized

    (conducting) at specified voltage. The entire assembly is placed inporcelain housing, properly sealed to keep out dust and moisture.

    Wave Traps:Wave traps are parallel resonant circuits having negligible

    impedance to power frequency currents but having very high

    impedance to carrier frequency currents. They are used to keep

    carrier signals in the desired channel so as to avoid interference

    with or from adjacent carrier current channels and also to avoidloss of carrier current signal in the adjoining power circuits.

    Current Transformers:A current transformer is a step down transformer which produces a

    replica of the high current flowing in the circuit for measurement

    purposes. It is intended to operate normally with rated current of

    the network flowing through the primary winding which is inserted

    in series in the network. The secondary winding of the CT isconnected to measuring instruments and relays supplying a current

    which is proportional to and in phase with the current circulating in

    the primary except for the difference due to current error and phase

    displacement inherent in the design of the CT.

  • 7/27/2019 Summer Training in badarpur ntpc

    42/54

    Page 42

    Potential Transformer:Potential transformers step down the system voltages to

    sufficiently low for indication of the system voltage conditions,

    metering of the supply of energy, relaying and synchronizing. In

    400 KV switchyard capacitance voltage transformer is used. A set

    of CVT has been provided on each incoming/ outgoing line.

    Shunt Reactors:Shunt reactors are static capacitors, which are connected in parallel

    in the system, which produce reactive power in the power system.

    In long lines a shunt reactor is connected for reduction of line

    current, increase in voltage level at the load, reduction in system

    losses, increase in power factor of a source current and reduction in

    loading on source generators and circuits. They draw almost a

    fixed amount of leading current which is superimposed on the load

    current. This reduces the reactive component of the load current,

    thereby improving the power factor.

    CONTROL AND INSTRUMENTATION

    The control and instrumentation systems installed in the plant are installed to

    provide a comprehensive intelligence feedback on the important parameters

    viz. temperature, pressure, level and flow. These systems are mostly based

    on state of art microprocessor technology. They monitor the following

    systems: -

    SG C&I Systems:1. Furnace safeguard supervisory system for purging, automatic firing,

    flame monitoring, sequential start- up and shut down of mills, etc.2. Secondary air damper control system3. Auxiliary PRDS control system4. Soot blower control system5. Coal feeder controls6. Furnace temperature probes

    TG C&I Systems:1. Electro- hydraulic governing control system

  • 7/27/2019 Summer Training in badarpur ntpc

    43/54

    Page 43

    2. Automatic turbine run up system3. HP- LP bypass control system4. Turbine stress control system5. Automatic turbine testing system6. Turbine protection system7. Generator auxiliaries control system

    Steam & Water Analysis System:This system does line analysis of various parameters like conductivity,

    pH, dissolved oxygen, residual hydrazine, silica, sodium, phosphates,

    chlorides, etc. at all critical points in condensate, feed water and steam

    cycle.

    The C&I systems employ the Distributed Control Monitoring & Information

    System (DDCMIS) and Computerized Data Acquisition System. The

    DDCMIS employs state of art microprocessors and is based on latest proven

    technology. It performs the functions of sequencing and modulating

    controls, plant start up/ shut down, in all regimes of plant operation

    including emergency conditions. The main purpose of DAS is to acquire

    sensor data and to produce useful output information for plant operators in

    the form of displays and hard copies. This system combines special

    hardware and software to facilitate interfacing between plant and operator.In addition, it also performs plant performance calculations and process

    monitoring.

    AUXILIARY POWER DISTRIBUTION SYSTEM

    The auxiliary power distribution system distributes electrical power

    requirement to various loads, control circuits and other instrumentation

    circuits. The total load on auxiliaries in a power station is approximately 7%

    to 9% of the plant capacity or the actual power generated. This system is

    broadly divided into:-

    1. Unit Auxiliary Power Distribution SystemUnit auxiliaries are those which are directly associated with the

    generating unit such as ID and FD fans, boiler feed pumps, coal mills,

    mill fans, circulating water pumps etc. The interruption of supply for the

    auxiliary motors connected on the unit bus should not be there. For

    supplying power to these unit auxiliaries the generator is connected to

  • 7/27/2019 Summer Training in badarpur ntpc

    44/54

    Page 44

    generator transformer through isolated phase bus duct and also through

    two nos. of unit auxiliary transformers which step down the voltage to

    6.6 KV. The UATs are connected to the unit 6.6 KV bus system by 2500A, 6.6 KV bus ducts. Each transformer is connected to unit buses A & B.

    Medium voltage MOCB switchgear is used for feeding power to motors

    rated above 200 KW. Facility is provided to transfer unit load to station

    in the event of tripping of unit through changeover system.

    Unit Auxiliary Transformer # 1 to 5:MakeKA CKBRIDGE HEWITTIC AND

    EASUN LTD.

    Manufacturing year.1981

    Type of coolingONAN (75%) ONAF(100%)Rating (KVA).. 12000 16000

    Temperature rise- Oil.40C

    Water.50C

    KV at no-load- HV15.75

    LV6.9

    Phase- HV3

    LV3

    Frequency.50Hz

    Vector GroupDYn11Amperes- HV 439.8 586.53

    LV 1004.1 1338.8

    Insulation level- HV125 KVP

    LV60 KV P

    Core & Winding weight..19200 kg

    Weight of oil7100 kg

    Total weight.37799 kg

    Quantity of oil..8250 liters

    Unit Auxiliary Transformer # 6 to 7:MakeNGEF

    Manufacturing year.1986

    Type of coolingONAN (75%) ONAF(100%)

    Rating (KVA).. 17500 25000

    Temperature rise- Oil.50C

    Water.55C

    KV at no-load- HV21

  • 7/27/2019 Summer Training in badarpur ntpc

    45/54

    Page 45

    LV6.9

    Phase- HV3

    LV3Frequency.50Hz

    Vector GroupDYn1

    Amperes- HV 481.13 687.32

    LV 1664.3 2091.9

    Insulation level- HV125 KVP

    LV60 KVP

    Core & Winding weight..21.6 T

    Weight of oil7.3 T

    Total weight.42.2 TQuantity of oil..8296 liters

    2. Station Auxiliary Power Distribution SystemStation auxiliaries are those which are required for general station

    services such as coal and ash handling system, lighting system, water

    purifying system etc. interruption of supply for the auxiliary motors for

    the station bus for a short duration can be tolerated. There are four station

    transformers in the plant. These transformers are supplied from the 132

    KV yard. These transformers step down the voltage to 6.6 KV. The

    station transformers are resistance grounded.

    WATER TREATMENT PLANT

    Water treatment plant is to produce such a quality of feed water from which

    there should not be any scale formation causing resistance to heat transfer

    and thus failure of tubes, no corrosion and no priming or foaming problems.

    This helps in giving trouble free, uninterrupted supply of clean steam. In this

    plant, raw water is fed from the Rihand reservoir, which consists of ionic

    and non-ionic, dissolved and undissolved solids and gaseous impurities. The

    process of removing is show in the flow diagram: -

  • 7/27/2019 Summer Training in badarpur ntpc

    46/54

    Page 46

    Fig: -Block Diagram of water treatment Plant

    Pre-Treatment Plant

    This plant has a capacity to produce 600cu. M/hr. of clarified water to meetthe requirement of the DM plant. The various processes involved in the

    pretreatment of water are:

    ChlorinationChlorine is dosed in raw water inlet to aerator and further in clarified

    water tank in order to remove bacteria and other microorganisms. It is

    also effective in oxidation of Fe, Mn and H2S, removal of taste and

    odour producing compounds and oxidation of organic compounds byforming chloroderivatives of these compounds.

    AerationBy aeration the water absorbs oxygen from the atmosphere, which helps

    in oxidation of organic matter present in water. The iron dissolved in

    water is precipitated as Fe2O

    3.

    Coagulation

  • 7/27/2019 Summer Training in badarpur ntpc

    47/54

    Page 47

    After aeration, the water flows to the flash mixture where lime and alum

    are dozed by the pumps and then flows through a RCC channel by

    gravity. The added chemicals are thoroughly mixed with the raw waterwith the help of a stainless steel paddle fitted in the path. Chemical

    reaction takes place as under:

    Al2(SO

    4)

    3. 18H

    2O + 3Ca(OH)

    23CaSO

    4+ 2Al(OH)

    3

    + 18H2O

    Flocculation & ClarificationThe water is subjected to slow spiral motion and fine precipitates

    agglomerate to look distinctly as flocks. The clear water enters throughthe bottom opening. The scrapper attached to the rotating bridge scraps

    the settled sludge. The clear water overflows from the top of rotating

    bridge. The clear water overflow from the top of clarifier and led to

    clarified water storage tank.

    FiltrationThe clarified water is passed through four pressure filters in which graded

    anthracite coal is filled up. During this process suspended impurity and

    turbidity is filtered effectively. Now the water is passed through active

    carbon filter to remove residual chlorine and oil impurities. Then it is fed to

    ion-exchanger for removing mineral salts. In the cation exchanger cations

    such as Ca, Mg and Na react with strong cation exchange resin and stay with

    the reacted resin. Similar action takes place for removal of anions in the

    anion exchanger. In the end a mixed bed exchanger is kept which helps in

    removal of any left over anions or cations.

    CIRCULATING WATER SYSTEM

    Condenser Cooling Water System

    The CW system provides for pond cooling with Rihand Reservoir as the heat

    sink. Vertical wet pit type CW pumps draw water from the Rihand Reservoir

    through the approach canal and feed to the condensers. Hot water from the

    condensers is discharged back to the reservoir by means of discharge

    channel, which is common for stage I and stage II of the project. CW supply

    from CW pump house to the condensers and CW discharge from the

    condensers upto the discharge channel is through concrete ducts of

  • 7/27/2019 Summer Training in badarpur ntpc

    48/54

    Page 48

    horseshoe shape. Round the year there is a large variation in the water level

    of Rihand Reservoir. Minimum water level at the intake sump is 254 m and

    the maximum level is 271 m with operating floor level of the pump housebeing at 278.5 m total depth of the sump is 31 m. therefore there is large

    variation in the static lift of the CW pumps ranging from 7 m to 24 m. In

    SSTPS, the operating scheme used to overcome this problem is by varying

    the nos. of CW pumps in operation.

    In stage I, total 13 nos. of pumps have been installed while 10 pumps are

    required. Requirement of cooling water of each unit is 27000 m 3/hr. The

    rated capacity of each pump is 15000 m 3/hr with a total head of 31.5 m.

    These pumps are designed for continuous operation with cooling water of

    maximum temperature of 36C.

    In stage II, 3 nos. of CW pumps have been installed for each 500MW unit.

    The rated capacity of each pump is 27000 m 3/hr at 31.5 m head. The

    operating speed is 375 rpm and the driver is a 3MW, 6.6KV, 16- pole, 50 Hz

    induction motor. In case of low water level, three pumps feed to one unit and

    in case of higher water levels two CW pumps are sufficient for each unit.

    For intermediate water levels five pumps are operated for both the units and

    the interconnecting butterfly valves are kept open.

    Ahead of the CW pumps single flow type traveling water screens have beenprovided with a clear opening size of 9.5 mm square which prevent the

    debris from entering into the CW system.

    Equipment Cooling SystemThe equipment cooling system has been provided to remove the waste heat

    rejected from the various plant equipments and transfer it to the

    environment. The system is divided into two basic sub-systems:

    a) Primary circuit using DM water employed to pick up the heat load fromvarious auxiliary coolers and rejects the same to the plate type heat

    exchangers (PHE).

    b) Secondary circuit using raw water employed to pick up the heat loadfrom PHEs and reject the same to main circulating water discharge seal

    pit in transformer yard.

    The ECW system is capable of operating continuously during all modes of

    plant operation. The ECW system meets the requirements of auxiliary

    coolers other than the main condensers. The following auxiliary coolers are

    cooled by primary water:

  • 7/27/2019 Summer Training in badarpur ntpc

    49/54

    Page 49

    1. SG Package Coal mill lubricating oil coolers, regenerative air pre-heaters - guide

    bearing and support bearing oil coolers, water cooled access door infurnace hopper zones, lubricating oil coolers for FD/ ID/ PA fans and

    motors, coolers for ID fan hydraulic couplings, sample coolers, ID fan

    motors stator coolers, air heaters fire se, coal mill journal hydraulic

    system cooler, boiler circulation pumps.

    2. TG Package Turbine lubricating oil coolers, turbine control fluid coolers, generator

    hydrogen coolers, exciter coolers, generator seal oil coolers hydrogen

    and airside, primary water coolers.

    3.BFP Package Booster pump coolers, working oil coolers and lubricating oil coolersfor MDBFP, BFP oil coolers, BFP motor coolers.

    4. CEP Package Motor and thrust bearing coolers

    5. Oil coolers for generator transformers6. Auxiliary coolers for air compressors7. Primary sample coolers in SWAS panel room in control tower.

    The ECW heat exchangers are of plate type located at ground floor of TG

    hall and sized to provide 38C (max.) DM water at design flow condition.

    The pH of DM water in the closed loop is maintained around 9.5 by dosing

    sodium hydroxide. The sodium hydroxide solution is prepared in NaOH

    solution preparation tank and fed to the suction of DMCW pumps through

    2100% chemical dosing pumps.

    ASH HANDLING SYSTEM

    The ash handling system is continuous hydro sluicing type. It envisagescontinuous removal of bottom ash and fly ash in slurry form from the

    different zones of bottom ash and fly ash collections in the steam generating

    units. The bottom ash slurry is led to a bottom ash slurry sump at the boiler

    bottom from where it is transferred by means of vertical slurry pumps to the

    main fly ash slurry trench in electrostatic precipitator (E.P.) area. The fly ash

    slurry flows through gravity channels and aided by high pressure jetting

    water is led to the slurry sump in the main ash slurry pump house. The

    combined bottom ash and fly ash slurry from the main slurry sump is

  • 7/27/2019 Summer Training in badarpur ntpc

    50/54

    Page 50

    pumped to the disposal area by means of slurry pumps and disposal lines.

    The HP and LP water required for slurry formation and transportation is

    supplied by HP and LP pumps installed in ash water pump house.

    The entire ash handling system has been designed for removing and flushing

    the bottom ash and fly ash from both the units at the following rates:

    For Stage I:

    a) Fly ash 162 tonnes/hr (for phase I)

    108 tonnes/hr (for phase II)

    b) Bottom ash 36 tonnes/hr (for phase I)

    24 tonnes/hr (for phase II)

    For Stage II:

    a) Fly ash 320 tonnes/hrb) Bottom ash 72 tonnes/hr.The ash slurry disposal system has been designed to pump the ash slurry

    continuously from the slurry pump to the disposal area through pipelines at a

    rate of 700 m 3/hr for each unit of stage I and 1500m 3/hr for each unit of

    stage II.

    Bottom Ash Removal SystemThe bottom ash resulting from the combustion of coal in the boiler falls into

    the ash hopper provided under the furnace bottom. Each hopper is divided

    into two sections and each section is provided with adequately sized opening

    with gates. The ash is spray- quenched in these hoppers and gets discharged

    into the water impounded slag baths provided under each section. Each slag

    bath is provided with a continuously moving scraper feeder for transferring

    the wet slag ash to the respective clinker grinder. The crushed ash through

    clinker grinder gets discharged into the slopping ash trenches provided

    beneath them and from there aided by high pressure water jets, the slurry is

    led to the bottom ash slurry sump provided adjacent to the boiler bottom.

    From the sump the slurry is transported to the main ash slurry trench in E.P.

    area by bottom ash slurry pumps for its further disposal to dump area by

    means of slurry disposal pumps located in main ash slurry pump house.

    Fly Ash Removal SystemFly ash removal system envisages removal of ash from each of the

    electrostatic precipitators, economiser, air preheater and stack hoppers

    continuously through suitable vertical pipe connections. Flushing

  • 7/27/2019 Summer Training in badarpur ntpc

    51/54

    Page 51

    equipments are provided below them. The slurry from the economiser and

    air preheater flushing equipments is conveyed to the bottom ash slurry sump

    from where it is pumped along with bottom ash to the main ash slurry trenchin E.P. area.

    The fly ash slurry from ESP and stack gets discharged into the sloping ash

    channel provided beneath them. The slurry aided by high pressure water jets

    flows down the sluice channel to the slurry sump in ash slurry pump house

    for its further disposal to dump area by means of slurry pumps.

    Ash DykeThe ash dyke is provided for the disposal of fly ash and bottom ash in the

    form of slurry. Fly ash and bottom ash are collected in the slurry form in the

    sump of the ash slurry pump house. From there it is discharged through

    pipes into the ash dyke for the settlement of ash in the dyke. The ash free

    water is discharged into the Rihand Reservoir.

    There are three main ash slurry sumps, one common for units 1, 2 & 3,

    second common for units 4 & 5 and third common for 6 & 7. Low pressure

    water is used for thorough mixing and high pressure water is used for

    sluicing. Each ash slurry sump is located in an ash slurry pump house. Eachpump house has six vertical pumps for continuously conveying the ash

    slurry from the sump to the ash dyke.

    HYDROGEN GENERATION PLANT

    Hydrogen gas is used for generator cooling. So supply of pure hydrogen in

    the power station is essential for generator filling and maintaining of

    hydrogen gas pressure inside the generator casing.

    Hydrogen is prepared by electrolysis of pure demineralised water. When dc

    current is passed through water it decomposes the water into two elements,

    one volume of oxygen and two volumes of hydrogen. Pure distilled water is

    a bad conductor of electricity but if acid, alkali or salt is added it becomes a

    good conductor. To make economical use of electrolysis of water, a solution

    termed as electrolyte has be used which is prepared by adding NaOH or

    KOH with pure water. When current is passed through the electrolyte,

  • 7/27/2019 Summer Training in badarpur ntpc

    52/54

    Page 52

    hydrogen is given off at negative electrode, while oxygen is evolved at the

    positive electrode.

    A.C. power at 400/440 V, 3 phase, is changed to dc power in a transformer

    and rectifier arrangement. Dc output of the plant is controlled by means of a

    regulator. Dc from the terminals of the rectifier is supplied to the cells

    through busbars. Gas production is directly proportional to dc current

    passing through the solution of caustic potash and DM water.

    DM water of high purity is collected in a storage tank from where it is fed by

    gravity to the cell bank for make up. An automatic float valve is mounted in

    gas washing tank to provide a continuous supply of water in proportion to

    usage. The gases, after leaving the cells, pass upwardly to the collectionheaders and then through a water seal to atmosphere or to the gasholder as

    the case may be.

    Cooling water is supplied to the water seal, which regulates the pressure

    head against which the cells operate and also prevents any backward flow

    from the gasholder when the plant is not in operation. Valve is provided in

    between the gas washing tank and gasholder for directing the flow to

    atmosphere when desired.

    Hydrogen gas flows from the gas washing tank to a low pressure wet seal

    gasholder. From the gasholder it flows to a compressor, which compresses it

    to rated pressure. After the compressor it flows through carbon filter and

    through a silica gel dryer. The dry hydrogen is then stored in storage

    cylinders from where it goes to the power station for use. Hydrogen gas is

    normally sent to HP compressors from the gasholder where it is compressed

    to a rated pressure. From the HP compressors, hydrogen flows through an

    after cooler, which has moisture separator columns, and then to a point

    filling station where it is filled in portable cylinders.

    Oxygen produced in the process is let off to atmosphere.

  • 7/27/2019 Summer Training in badarpur ntpc

    53/54

    Page 53

    BIBLIOGRAPHYBIBLIOGRAPHYBIBLIOGRAPHYBIBLIOGRAPHY

    The information, facts and figures presented in the project have

    been collected from various sources. To mention a few,

    information have been collected from websites like

    www.google.comand www.wikipedia.org. Various documentaries

    have also been referred to for collecting valuable information. We

    have also referred to reference books. To mention a few, we

    referred electrical technology by B. L. Theraja and A.K. Theraja

    and Power systems by V.K. Mehta.

  • 7/27/2019 Summer Training in badarpur ntpc

    54/54


Recommended