Summitville Mine Superfund Site
INAP Meeting, October 7-8, 2009
Kevin W. Conroy, P.E.Golder Associates Inc.
Austin N. BuckinghamColorado Department of Public Health and Environment
Presentation Overview
� Site Facts, Features and History� Site Remedial Activities� Water Treatment Issues� New Treatment Facility Design
I would like to acknowledge the contributions of information andphotographs supplied by Austin Buckingham, Summitville Project Manager, CDPHE.
2
Site Facts
� Site Location� Rio Grand County, Colorado� Approximately 19 miles from South Fork, CO
� History� 1800’s through 1970’s: Historic underground mining� 1984: Galactic Resources takes over the site� 1986: Commenced open pit operations� 1992: Galactic Resources abandons the site� 1994: Added to NPL list� 1998: RI/FS begins� 2001: ROD signed
3
Site Features
� Site Features� Approximate 1,200 acre site� Average elevation ~11,500 feet amsl� Average annual snowfall of ~ 30 feet
4
Evolution of a Superfund Site
� December 1992: Galactic Resources abandons site� Poor planning� Insurmountable climactic conditions� Multiple operations violations� Cease and Desist order
� 1992-1994: Emergency response activities� Cyanide neutralization in Heap Leach Pad� Maintenance of Heap Leach Pad� Heap Leach Pad cap� Adit plugs
� May 31, 1994: Site added to NPL� 1998: RI/FS process begins� 2001: ROD signed
7
ROD Scope
� OU 0 – Interim Water Treatment� Various water treatment facilities � ~1000 gpm capacity.
� OU 1 – Heap Leach Pad detoxification and closure� Following cyanide-destruction and pad rinsing� Materials recontoured within the HLP basin� Cover-liner placed for containment and isolation
� OU 2 – Mine-waste excavation/consolidation and pit-backfilling� Cropsy waste-rock dump was backfilled into the pits� Cropsy-drainage rerouted into a new channel/pipe diversion� Both mine pits backfilled� North waste-rock dump recontoured and cap-cover fills placed
8
ROD Scope
� OU 3 – South Mountain Groundwater Assessment� Studies of the groundwater system within the remaining underground
mine workings� Complex fractured bedrock geology underlying the backfilled pits
and waste-rock areas showed mine-pool mitigation to be near-infeasible
� OU 4 – Site-wide Reclamation� Soil amendments incorporated on the cap-covers and revegetation
and erosion control commenced� Network of large rip-rapped drain-channels placed to convey runoff,
with several turn-outs installed along the perimeter toe-ditch to divert higher-flow “fresh” waters into Wightman Fork
9
ROD Scope
� OU 5 Final Remedy� On-going
� O&M of water treatment plant including management of mine pool� Continued site maintenance and monitoring� Surface water, sediment, and aquatic life monitoring in Alamosa River
and Terrace Reservoir
� Completed (balance of OU4 work)� Upgrade of select site ditches� Construction of groundwater interceptor drains� Construction of a Highwall ditch
� In Progress� Design and construction of a new water treatment plant� Upgrade of Wightman Fork Diversion� Rehabilitation of Reynolds Adit
10
Aluminum Load From Summitville
17
Summitville Altered Area Aluminum Load Allocation
Legacy Mines3%
SMSS36%
Natural Conditions61%
Aluminum Load in Alamosa River
18
Load Allocation at AR41.2 (lbs/year)
Upstream Stunner6%
Stunner44%
Summitville 15%
Summiville/Legacy1%
Jasper 7%
Jasper/Legacy0%
Summitville/Natural26%
Stunner/Legacy1%
Evolution of Discharge Criteria
� ROD Remedial Action Objective� Re-establish State aquatic use classifications and attainment of
water quality numeric criteria in segment 3c� Meet all non-waived criteria at end-of-pipe� CERCLA waiver for pH, iron and aluminum in segment 3b
� Remove to extent practicable at end-of-pipe� Use segment 3b as an extended mixing zone and meet waived criteria
at top of segment 3c
� Aluminum criteria became major issue� Aluminum criteria in segment 3b originally set at 0.087 mg/L (5/1 –
9/30) and 0.75 mg/L (10/1 – 4/30)� Bench and pilot plant studies completed in 2003
� One-stage process – 5.4 mg/L� Two-stage process – 0.12 mg/L
19
Evolution of Discharge Criteria
� Two-stage process originally selected� Objections raised by EPA � Poor ambient quality in Alamosa� High cost for minimal additional aluminum removal with no surety of
improvement in Alamosa quality� CDPHE completed a Use Attainability Analysis
� Modeling performed to predict contributions to Alamosa ambient quality
� No benefit from two-stage process could be predicted� CDPHE WQCC reviewed in June 2007 and agreed� Technology-based criteria based on single-stage plant adopted
20
Site Discharge Criteria
22
Parameter Units Segment 3b Value
Comments
Aluminum mg/L 0.041, 3 (TR); 0.317, 3 (TR)
Dissolved and total recoverable chronic seasonal standard from 5/1 to 6/30; and from 7/1 to 4/30
Arsenic mg/L 0.0076 (TR) Chronic value Cadmium mg/L 0.00039 Chronic value calculated at stream
hardness Copper mg/L 0.012 Acute (3b) and chronic (3c) values
calculated at stream hardness Iron mg/L 12 (TR) Chronic value Lead mg/L 0.0022 Chronic value calculated at stream
hardness Manganese mg/L 1.58 Chronic value calculated at stream
hardness Nickel mg/L 0.047 Chronic value calculated at stream
hardness Selenium mg/L 0.0046 Chronic value Silver mg/L 0.00006 Chronic value calculated at stream
hardness for trout Zinc mg/L 0.11 Chronic value calculated at stream
hardness pH SU 6.5 – 9 -
Site Water Quality
23
Parameter Units Average Maximum Projected Discharge
Goal Segment 3b
Parameters with discharge goals Aluminum mg/liter 136 245 5.4 0.041
Arsenic mg/liter TR 0.1 1.04 <0.1 0.0076 Cadmium mg/liter 0.13 0.32 <0.002 0.00039 Copper mg/liter 44 120 0.007 0.012 Iron mg/liter TR 156 644 0.12 12 Lead mg/liter 0.05 0.27 <0.001 0.0022 Manganese mg/liter 30 31 1.0 1.58 Nickel mg/liter 0.57 0.94 <0.04 0.047 Selenium mg/liter <0.02 -- <0.0046 0.0046 Zinc mg/liter 15.6 32 0.008 0.11 Parameters important in treatment plant design Calcium mg/liter 98 171 642 -- Chloride mg/liter 8 -- -- -- Magnesium mg/liter 39 63 22 -- Potassium mg/liter 4 -- -- -- TDS mg/liter 3,419 5,657 3,047 -- Sodium mg/liter 20 -- -- -- Sulfate mg/liter 2,165 3,786 1,990 --
Process Design
� Flow – 1,600 gpm� Based on hydrologic modeling� Balanced with SDI capacity
� Reaction System� pH 9.5 maximum� 45 minute retention time in Reaction Tank� Sludge recycle and lime fed to Mix Tank� Floc Tank prior to Clarifier
� Clarifier diameter � Diameter – 70 feet� 15 solids recycles� 12.5 ft2/STPD � 10% solids underflow
26
Process Design
� Lime usage� Slaker system to be used� 1,200 pounds per hour� 4,000 ft3 storage capacity
� Solids management� Production – 1.85 gr/L� 36 hours storage capacity� Filter press capacity – 225 ft3
� Polymer system� Dry polymer system
� Utilities� Redundant air compressors� Small membrane system for makeup water
27
Process Design
� Systems allowed for but not installed� Iron addition� Anti-scalent� Neutralization
� Material of construction� Epoxy coated steel – main tanks� Glass lined – clarifier tank� Polypropylene lined steel – low pH piping� HDPE – underground piping
28
Architectural Design
� Long design life (50 years)� Need to be self-sufficient
� Lab� Vehicle maintenance� Parts storage� Locker rooms
� Weather conditions� Snow drifting/loading and associated damage
� Architectural features� Precast concrete panels for lower 16 feet� Metal panels above� Sandwiched insulation� Flat roof structure
30
Civil/Structural Design
� Civil� Constrained site
� Topography not good� Relationship to SDI and existing utilities important
� Site drainage important� High groundwater levels� Seeps
� Geotechnical investigations� Soil borings� Lab testing� Geophysical investigation
� Foundation System� Drilled pier foundation system� Grade beams and structural slab
33
Miscellaneous Design Elements
� Fuel farm� New SDI pump system� Backup generator
� Life safety systems� Raise clarifier rake
� Extensive lightning protection system� Fire detection system� Communications
� Radio-based phones� Satellite-based Internet
35
What made the project a reality?
� Economic Stimulus money
� Willingness of regulatory community to understand the nature of ambient water quality in the Alamosa River
� Continued stakeholder involvement
� Excellent relationship between CDPHE and EPA Region 8
36