SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up...

Date post: 26-Mar-2015
Category:
Upload: christopher-clay
View: 216 times
Download: 2 times
Share this document with a friend
Popular Tags:
46
SunGuide SunGuide TM TM Software Development Project Software Development Project Release 3.1: I-95 Express Lanes Release 3.1: I-95 Express Lanes Design Review Follow-up Design Review Follow-up January 29, 2008 January 29, 2008
Transcript
Page 1: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

SunGuideSunGuideTMTM Software Development Project Software Development Project

Release 3.1: I-95 Express Lanes Release 3.1: I-95 Express Lanes Design Review Follow-upDesign Review Follow-up

January 29, 2008January 29, 2008

Page 2: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 2

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 3: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 3

Introductions

Page 4: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 4

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 5: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 5

ConOps and Requirements Status

Page 6: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 6

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 7: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 7

High Level Overview – Meeting High Level Overview – Meeting ObjectivesObjectives

Requirements and Design:

– Review high level design

– Provide clarification to SwRI’s initial design interpretation

– Present revised prototype screens

Not an objective:

– Revise requirements

Page 8: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 8

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 9: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 99

Admin Editor: System Admin Editor: System ConfigurationConfiguration

Page 10: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1010

Admin Editor: Defining Holidays/SpecialAdmin Editor: Defining Holidays/Special

Page 11: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1111

Admin Editor: SegmentsAdmin Editor: Segments

Page 12: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1212

Admin Editor: Daily Rate SchedulesAdmin Editor: Daily Rate Schedules

Page 13: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1313

Admin Editor: Import Rate ScheduleAdmin Editor: Import Rate Schedule

Page 14: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1414

Admin Editor: Configure Rate ScheduleAdmin Editor: Configure Rate Schedule

Page 15: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1515

Admin Editor: Segment/Rate Schedule Admin Editor: Segment/Rate Schedule AssociationAssociation

Page 16: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1616

Admin Editor: Segment/Rate Schedule Admin Editor: Segment/Rate Schedule AssociationAssociation

Page 17: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 17

Admin Editor: Toll Rate DMSAdmin Editor: Toll Rate DMS

Page 18: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 1818

Admin Editor: Toll Rate SignsAdmin Editor: Toll Rate Signs

Page 19: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 19

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 20: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 20

Operator Map Option #2 RevisionOperator Map Option #2 Revision

Page 21: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 21

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 22: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 22

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 23: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 23

Toll Viewer: Search ScreenToll Viewer: Search Screen

Page 24: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 24

Toll Viewer: General View ScreenToll Viewer: General View Screen

Page 25: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 25

Toll Viewer: Advanced User Toll Viewer: Advanced User ScreenScreen

Page 26: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 26

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 27: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 27

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 28: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 28

Toll Viewer DMZ Requirements Toll Viewer DMZ Requirements

7: A web based browser application shall be available for authorized users to view data related to the Express Lanes.

– SwRI recommends striking the word “authorized.” If not, then will need to define what is meant by “authorized” user.

7.2: Users shall be assigned permissions to use the Toll Viewer and the Detail Level that they will use.

– Strike this entire requirement assuming “authorized” is removed.

Page 29: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 29

Toll Viewer DMZ Server Setup Toll Viewer DMZ Server Setup

Toll Viewer Web

Application

DMS, Rate, & Event Archive

Tables

Toll Viewer Web Service

WorkstationIE 7

External Servers

SunGuide Servers

Page 30: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 30

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 31: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 31

Schedule ReviewSchedule Review

SwRI reviewed the V4.0 Requirements and prioritized the requirements marked as “Phase 1”

– The requirements were grouped into functions Each function was stratified according to one of the

following:

• Complete by 4/30/08 – Assume FAT gets moved to 1st part of April and IV&V occurs after 4/30/08

• Complete by 5/15/08

• Complete by 5/3/08

Page 32: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 32

Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 RequirementsVersion 4.0 Requirements

Can Complete by: 4/30/2008

Can Complete by: 5/15/2008

Can Complete by: 5/30/2008

Page 33: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 33

Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 Requirements Cont’dVersion 4.0 Requirements Cont’d

Development Completed: 3/31/08

Development Completed: 4/14/2008

Development Completed: 4/30/2008

Can Complete by: 4/30/2008

Can Complete by: 5/15/2008

Can Complete by: 5/30/2008

Page 34: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 34

Prioritization of Phase 1 of Prioritization of Phase 1 of Version 4.0 Requirements Cont’dVersion 4.0 Requirements Cont’d

Can Complete by: 4/30/2008

Can Complete by: 5/15/2008

Can Complete by: 5/30/2008

Page 35: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 35

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 36: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 36

Action ItemsAction Items

Page 37: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 37

Action Items - continuedAction Items - continued

Page 38: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 38

Action Items - continuedAction Items - continued

Page 39: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 39

Action Items - continuedAction Items - continued

Page 40: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 40

Action Items - continuedAction Items - continued

Page 41: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 41

Action Items - continuedAction Items - continued

Page 42: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 42

Action Items - continuedAction Items - continued

Page 43: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 43

Action Items - continuedAction Items - continued

Page 44: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 44

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support

Page 45: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 45

Discussion ?

Page 46: SunGuide TM Software Development Project Release 3.1: I-95 Express Lanes Design Review Follow-up January 29, 2008.

Jan 29, 2008R3.1 I-95 Express Lanes Design Review Follow-up 46

AgendaAgenda

Time Item Lead

8:30 – 8:45 Introductions and Opening Remarks Tillander

8:45 – 9:00 ConOps and Requirements Status Santana

9:00 – 9:15 High Level Overview – meeting objectives Heller

9:15 – 9:30 Admin Editor Updates Misra

9:30 – 10:15 Operator Map Option #2 Revision Misra

10:15 – 10:30 Break  

10:30 – 11:30 Toll Viewer Application Mock-up Updates Misra

11:30 – 12:45 Lunch

12:45 – 1:00 Toll Viewer SunGuide DMZ Setup Misra

1:00 – 1:30 Schedule Review Heller

1:30 – 3:30 Review Action Items From Jan. 9-10 Design Review Misra

3:00 – 3:30 Open Discussion All

FDOT PM Meeting

3:30 – 4:00 Testing

4:00 – 4:30 Support