+ All Categories
Home > Documents > SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to...

SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to...

Date post: 24-Mar-2020
Category:
Upload: others
View: 3 times
Download: 1 times
Share this document with a friend
29
SuperKEKB mechanical assembly in the IR -A report from a vacuum scientist- The 2019 international workshop on the high energy Circular Electron-Positron Collider (CEPC) Nov. 18-20, 2019, IHEP, Beijing, China Ken-ichi Kanazawa For all SuperKEKB IR fellows Accelerator Laboratory, KEK, Tsukuba, Japan CEPC2019 1
Transcript
Page 1: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

SuperKEKB mechanical assembly in the IR

-A report from a vacuum scientist-

The 2019 international workshop on the high energy Circular Electron-Positron Collider (CEPC)

Nov. 18-20, 2019, IHEP, Beijing, China

Ken-ichi Kanazawa For all SuperKEKB IR fellows

Accelerator Laboratory, KEK, Tsukuba, Japan

CEPC2019 1

Page 2: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Contents • Very short introduction of SuperKEKB • IR from Phase 1 to Phase 2 • BEAST II installation

– IP chamber – BPM-bellows tube

• QCS cryostat parts exchange – New cryostat head – QCS beam pipe

• Remote Vacuum Connection (RVC) • QCS-BEAST II connection • IR after QCS-BEAST II connection

CEPC2019 2

Page 3: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Very short introduction of SuperKEKB

SuperKEKB CEPC FCC-ee

Circumference 3 100 100 km

Crossing angle at IP 83 33 30 mrad

Commissioning history • Phase 1 (from 2016, 2 Mar. to 30 Jun.)

– No superconducting final focus magnets (QCS), No Belle II, No beam collision

• Phase 2 (2018, 19 Mar. to 17 Jul.) – With QCS, Belle II, and Beast II (for BG study),

without vertex detector (VXD) • Phase 3 (2019, 11 Mar ~ )

– With VXD (PXD incomplete)

This report is based on the work of this period

CEPC2019 3

Page 4: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

IR from Phase 1 to Phase 2

Belle II w. Beast II (Phase 2) w. VXD (Phase 3)

IP chamber

QCSL

QCS beam pipe QCS beam pipe

Moving stage Moving stage

Phase 1

QCS: Final focus superconducting magnet system RVC: Remote vacuum connection

QCSR BPM-bellows tube RVC

Phase 2

Electron (7 GeV)

Positron (4 GeV)

FWD (R-, Oho-, D2-side) BWD (L-, Nikko-, D1-side)

CEPC2019 4

Page 5: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

HIP = Hot Isostatic Pressing

(~10 µm) ~10 µm ~10 µm

Beam space design with minimum trap of HOM at the central part.

ID of the beam passage ≤ QCS beam pipe (HOM propagates away.) HOM is trapped at a merging volume of two passages.

Only taper parts are exposed to direct synchrotron radiation from the last bend.

Taper: to reduce the number of photons entering into the central part Ridges: to keep the direction of scattered photons away from Be

BEAST II installation

IP chamber: Design feature

material

coating

cooling

CEPC2019 5

Page 6: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

BEAST II installation

Assembling BEAST II around IP chamber

•The central straight part consists of double tube. Paraffin runs between them.

•Outer Be: 0.4 mm thick •Inner Be: 0.6 mm thick •Gap: 1 mm

M. Tobiyama

BEAST II

S. Tanaka

S. Tanaka

CEPC2019 6

Page 7: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

BEAST II installation

BPM-bellows tube between IP chamber and QCS BPM pick-up

Bellows unit with a conventional RF-bridge. (At present, no problem up to 800 mA) A comb-type structure cannot give a sufficient flexibility for a small diameter.

Cooling channel

CrCu CrCu

QCS side

CEPC2019 7

Page 8: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Beast II installation

Connecting BPM-bellows tube

BPM-bellows tubes (about 14 cm long) set on a lock flange for RVC

Travel limiter to limit the longitudinal displacement of the bellows.

Beast II assembling group strongly suggested that it is practically impossible to connect BPM-bellows tubes to the IP chamber after BEAST II is installed into Belle (especially in FWD). Therefore, The tubes were connected to the IP chamber before BEAST II installation.

M. Tobiyama Lock flange

CEPC2019 8

Page 9: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

The cable cage interfered with connecting work. It is temporally removed.

FWD The vacuum flanges of IP chamber is about 8 cm behind the cable cage.

Photo by M. Tobiyama

Beast II installation

Connecting BPM-bellows tube Cable cage

9 CEPC2019

Page 10: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

BWD The vacuum flanges of IP chamber is outside of the cable cage. Vacuum leak check

Photo by M. Tobiyama

Beast II installation

Connecting BPM-bellows tube

CEPC2019 10

Page 11: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Beast II installation (Nov. 18, 2017)

Photo by M. Tobiyama

CEPC2019 11

Page 12: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Beast II installation

Review of work

• It was necessary to connect semi-rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II structure strongly restrict the work space.

• Since a bellows is a fragile component, we need to establish a method how to replace it, even for such bellows set deep inside the detector. First idea was to extract VXD from Belle II. But Belle II people resisted this idea, and RVC was introduced. Present situation is: BPM-bellows tubes at BWD can be replaced while leaving VXD inside. On the other hand, at FWD, it is necessary to extract VXD to exchange them.

CEPC2019 12

Page 13: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCS cryostat parts exchange

New cryostat head A new front head which has a W-alloy face was prepared for each cryostat. The face is machined to install RVC on it.

RVC: Remote Vacuum Connection (picture later)

Exchange the cryostat head

Leak check of the cryostat

CEPC2019 13

Page 14: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCS cryostat parts exchange

Beam pipes for QCS

Heavy metal cap replaces the original cap after field measurement.

O-ring seal between beam pipes and the cryostat.

QC1LP QC2LP

QC1LE QC2LE BPM

Helium vessel

Bellows with O-ring seal

QCSL Cryostat

After field measurement, inner pipes of the cryostat were replaced with beam pipes. The beam pipe is made of stainless steel, with a 4 mm thick wall, and with water cooling channels on both sides. Inside surface is Cu (+TiN) coated. It is fixed to the QCS cryostat. The beam pipe has no pump. Pressure at the IP is about one order higher than the pressure at the end of the cryostat.

Beam pipe CEPC2019 14

Page 15: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCS cryostat parts exchange

QCS beam pipe installation

Beam pipe

G10 spacer

SI

BPM

Set beam pipe

Attach BPM and leak check

Leak check of the cryostat

Beam pipe is inserted using a special tool

Service window on the QCSR cryostat used to manually guide the beam pipe and to attach BPM

Connect BPM cable

Photo by Y. Arimoto

CEPC2019 15

Page 16: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCSL BPM

Photo by Y. Arimoto

QCS cryostat parts exchange

QCS beam pipe installation

Since QCSL has no service windows, the cryostat was disassembled for this work.

CEPC2019 16

Page 17: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCS cryostat parts exchange

Review of work • The QCSL cryostat was disassembled to install beam pipes.

− Magnet group checked marker positions on the cryostat after re-assembling. Roughly speaking, the front body is rotated anti-clockwise by 0.7 mrad seen from IP. The consistency of the measurement with the mechanical tolerance of the cryostat design is not yet given.

• It seems better to separate a cryostat and beam pipes mechanically. − A cryostat position can be adjustable after beam pipes are

connected. − Beam pipes can be heated up if necessary (ex. NEG coating). − Then, the design of RVC will be different.

CEPC2019 17

Page 18: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Remote Vacuum Connection (RVC)

RVC on the new QCS head

RVC is a mechanism introduced by Belle group to connect QCS beam pipes to BPM-bellows tubes by a remote manipulation. RVC was designed and produced by DESY.

Photo by DESY CEPC2019 18

Page 19: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

How RVC works 1/6

Two bellows units are attached to a single lock flange with a retainer.

Drawing by Karsten G.

CEPC2019 19

Page 20: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

These components (red+blue) rotate to catch the lock flange.

How RVC works 2/6

Drawing by Karsten G.

CEPC2019 20

Page 21: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

How RVC works 3/6

Drawing by Karsten G.

CEPC2019 21

Page 22: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

These connected components connected to the piston in the cylinder, shift to press the bellows flange to the cryostat.

Cylinder for dry N2 (about 50 bar)

How RVC works 4/6

Drawing by Karsten G.

CEPC2019 22

Page 23: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

This large light blue screw nut turns to lock the mechanism.

How RVC works 5/6

Drawing by Karsten G.

CEPC2019 23

Page 24: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

How RVC works 6/6

Drawing by Karsten G.

CEPC2019 24

Page 25: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCSR-Beast II connection (Jan. 9, 2018)

QCSR head FWD CDC tunnel

QCSR proceeding QCSR connected to Beast II Photo by I. Nakamura 25

CEPC2019

Page 26: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCSL-Beast II connection (Jan. 15, 2018)

Trouble!! A number of contact fingers are out of place. Contact fingers were miraculously

put in order by Karsten (DESY)

Karsten

Leak checking scene Photo by I. Nakamura

CEPC2019 26

Page 27: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

QCS-Beast II connection

Review of work • Just before QCSL-Beast II connection, it was found that

contact fingers of one BPM-bellows tube were out of place. This seems to be caused by an accidental large turning of the lock flange. Happily enough, this was repaired by Karsten. – However, after Phase 2 operation, discoloring due to discharge was

observed around these fingers. The deformed fingers did not fully recover their shape as fabricated.

• RVC worked completely well.

CEPC2019 27

Page 28: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

IR after QCS-BEAST II connection L-side(Nikko-side, D1-side, BWD) R-side (Oho-side, D2-side, FWD)

All magnets are re-installed, all beam pipes are connected. Cabling and other works are going on. CEPC2019 28

Page 29: SuperKEKB mechanical assembly in the IR• It was necessary to connect semi -rigid BPM cables to BPM-bellows tube before connecting the tube, because of limited work space. BEAST II

Finally concrete radiation shields cover accelerator components

Belle II

END CEPC2019 29


Recommended