Construction Supplier Selectionand Evaluation
Presented by Under guidanceVishal.R.Kachwah Of MIS :121420005 Prof. Dr. N.A.Hedaoo
2
OBJECTIVE OF THE STUDY
The main objective of the study is the following:
To understand the mechanism of suppliers selection in Construction supply
chain management.
To study the various supplier selection criterion to integrate suppliers in
construction supply chain.
The Supply Chain View
Suppliers Manufacturers Warehouses &Distribution Centers
Customers
Material CostsTransportation
CostsTransportation
Costs TransportationCostsInventory
CostsManufacturing Costs
Source Make Deliver Buy
Supply chain management is a means for dealing with these processes in a structured manner.
3
Flows in a Supply Chain
Customer
Material
Information
Funds
The flows resemble a chain reaction
Supplier
4
5
What Is Supply Chain Management (SCM)?
The rightProduct
HigherProfits
The rightTime
The rightCustomer
The rightQuantity
The rightStore
The rightPrice
=++ ++
Ach
ieve
s
A set of approaches used to efficiently Suppliers Manufacturers Warehouses Distribution centers
So that the product is produced and distributed In the right quantities To the right locations And at the right time
System costs are minimized and Service requirements are satisfied
+
6
Stages Of Supply Chain Management
Stage 1 (Supply chain assessment)
This stage the existing work procedure and work methodology are accessed.
Stage 2 (Supply chain redesign)
Existing work procedure are found out and steps are taken to improve the supply chain
Stage 3 (Supply chain control)
Close control over the working and check if the desired goals are achieved or not.
Stage 4 (Continuous supply chain improvement)
Keep on changing the supply chain the keep up with the changing requirements of the
organization.
Supply chain management in construction
7
General structure of construction supply chain (CSC)
CSC includes the flow of information ,materials, ser vices or products, and the flow funds between client, designer, contractor and supplier
8
Generic configuration of supply chain in construction industry 9
SUPPLIER SELECTION IN CONSRUCTION SUPPLY CHAIN
10
11
Construction Purchasing Mistakes
In most cases, construction organizations are not proficient at identifying
the capabilities of their suppliers.
They sometimes rationalize supplier decisions based on convenience.
They wait too late to assess the value added by suppliers and service
providers.
They do not recognize the impact of the economic changes on bulk
materials prices.
Barriers to Supply Chain Management
12
Failure to share project information
Fear of loss of control
Lack of self awareness
Lack of partner awareness
Inability to recognize project goals
Lack of understanding project owner
Lack of understanding of supply chain
13
Process-based evaluations assessment of the supplier’s production or service processthe construction organization will conduct an audit at the supplier’s site to assess the supplier’s operating systems.
Performance-based evaluationsAssessment of the supplier’s actual performance according to a variety of criteria, such as:delivery reliability, cost, and quality defect rate.
There are two main categories of supplier evaluations
Criteria for Supplier Evaluation
SUPPLIER SCORING AND ASSESSMENTWhen scoring and assessing suppliers, the following factors other than quoted price must be
considered:
Replenishment lead time
On time performance
Supply flexibility
Delivery frequency/minimum lot size
Supply quality
Inbound transportation cost
Pricing terms
Information coordination capability
Design collaboration capability
Exchange rates, taxes and duties
Supplier viability14
The impact of each factor on total cost is summarised in the following
Purchase Price of
Component
Inventory Transportation Cost
Product Introduction
TimeCycle Safety
Replenishment Lead Time XOn time Performance X
Supply Flexibility XDelivery Frequency X X X
Supply Quality X XInbound Transport Cost X
Pricing Terms X XInformation Coordination X X
Design Collaboration X X X X XExchange Rates and Taxes X
Supplier Viability X X
15
SUPPLIER EVALUATION SYSTEM
The three general types of supplier evaluation systems used today are
Categorical method,
Cost-Ration method,
Linear averaging method.
The guiding factor in deciding which system is best is;
• Ease of implementation
• Overall reliability of system.
It should be noted that implementation of the results is the matter of the buying organization’s judgment.
16
Supplier Cost Material Quality Speed Total
A Good (+1) Unsatisfactory (-1) Neutral (0) (0)
B Neutral (0) Good (+1) Good (+1) (+2)
C Neutral (0) Good (+1) Neutral (0) (+1)
Example of categorical method
17
The buyer develops a list of performance factors for each supplier
track of each area by assigning a “grade” in simple terms such as: “good,” “neutral,” and “unsatisfactory.”
The advantages associated with, it can be implemented immediately and is the least expensive
Example of cost ratio method
Supplier
Quality cost ratio
Delivery cost ratio
Service cost ratio
Total penalty
Quoted Price/Unit
(Rs.)
Net adjusted cost (Rs.)
AA 1% 1% 1% 3% 120 123.6BB 2% 2% 3% 7% 115 123.05CC 3% 1% 4% 8% 110 118.8
18
The first step is to determine the internal costs associated with quality, delivery, and service each element is converted to a cost ratio
An example of quality costs follows:
19
Supplier1 Supplier 2
Material Quality (weight = 50)
Acceptable lot 50 35
Total lot received 58 40
Quality Rating 86.2 87.5
Service (weight = 35)
On time delivery 52 38
Total lot received 58 40
Service Rating 89.7 95.0
Price (weight = 15)
Lowest price 75 75
Price submitted 75 82
Price Rating 100 91.5
Total Performance Rating 89.5 90.7
This method is the most commonly
used evaluation method.
Specific quantitative performance
factors are used to evaluate supplier
performance.
The most commonly used factors
are quality, service (delivery) and
price
Linear averaging method
* 89.49 = (.5 × 86.2) + (.35 × 89.7) + (.15 × 100) 90.7 = (.5 × 87.5) + (.35 × 95.0) + (.15 × 91.5)
Internal financial problems
Working capital problems
Slow payment from project owner
Inferior plans and specifications
Inadequate technical capabilities
Insufficient information technology
Lack of communication between supply chain partners
Productivity inefficiencies
Work quality problems
Work method problems
Delivery reliability problems
Bulk materials quality problems
20
Customer issue in supply chain management
21
Factor selected for studySelection procedure Quality and timely work
Selection criteria Client briefing
Phase in which involvement Attitude of client
Technical expertise Minimum skill requirement
Testing capability Proper coordination
Relationship with supplier Frequent design changes
Waste elimination process Material availability
Suppliers’ geographical reach The incentives
Resourcefulness Complacency of suppliers
Transparency and openness Early participation of supplier
A SURVEY STUDY OF SUPPLIER SELECTION ISSUES IN CONSTRUCTION SUPPLY CHAIN
22
Relative Importance Index (RII)Is the process where weight is given to each type of response as per the judgment of the user. In this case; Strongly Disagree = 1
Disagree = 2
Undecided = 3
Agree = 4
Strongly Agree = 5
Then RII for each option is calculated using the equation;
RII = (W1*n1 + W2*n2 + ….) / A*N
Where W = Weight of the option as decided by user, n = Number of responses under each option, A = Highest weight given and N = Total number of respondents.
References
1. Benton W C, Jr & Linda F. McHenry., [2010]. “Construction Purchasing and Supply Chain Management.” New Delhi: Tata McGraw Hill
2. O’Brein William.J., Formoso Carlos T., Vrijhoef Ruben and London Kerry A., [2009]. “Construction Supply Chain Management Handbook.” New York: Taylor and Francis Group
3. Vrijhoef Ruben & Koskela Lauri., [1999]. Role of “Supply Chain Management In Construction.” Research Paper. University of California
4. Study on “A SURVEY STUDY OF SUPPLIER SELECTION ISSUES IN CONSTRUCTION SUPPLY CHAIN” By Rohan Choudhury and Pratik Dave PGP ACM 23rd Batch (2009- 2011)
NICMR,Pune
Tendering (1)Technical know how (2)
Construction phase (3)
Technical expertise of supplier (4)
Testing capability (5)
New suppliers (6)
Penalty (7)
Responsiveness (8)
Consistent performance (9)
cooperative,not open and transparent (10)Past record (11)Guidelines by client (12)
Concerned for specialist work (13)
Technical competency (14)
Requirements in advance (15)
Informing early (16)
Manage from other site (17)
Encouragement (18)
Bank guarantee (19)
Cost saving (20)
0
0.25
0.5
0.75
1
Factors affecting Supplier Selection
RII
Understanding form study
While selecting supplier construction industry looks for consistent performance in terms of
quality and on time delivery.
Client expect their suppliers to be responsive.
Supplier should have a good testing capability to finish project as per established QA & QC.
Frequent design changes the supplier and subcontractors are informed well in advance.
Imposing penalty is the best way for preventing wastage at site.