Supporting
Water Operators Partnershipsin Indonesia
Presentationby
Javier Coloma Brotons, Urban Development Specialist, ADB
7/31/2019 Supporting Water Operators Partnerships in Indonesia
2/21
Outline dari Presentasi
Tantangan didalam penyediaan air bersihdi Indonesia
Program Kemitraan para operator air
(WOPs) Twinning partnerships
7/31/2019 Supporting Water Operators Partnerships in Indonesia
3/21
LATAR BELAKANG
Sebagian besar para operator air di Asia-Pacific termasuk di
Indonesia (PDAM/PD PAL) memiliki : Infrastruktur yang kurang memadai dan sudah tua
Lemah dalam hal organisasi
Kinerja pelayanan yang kurang baik
Kinerja keuangan yang lemah
Hubungan dengan pelanggan yang kurang baik
Tipikal tersebut diatas berdampak kepada :
Tingginya tingkat kehilangan air (NRW)
Cakupan dan tingkat pelayanan yang kurang memadai
Pendapatan yang kecil
Sistem sanitasi yang tidak tepat dan kurang memadai
7/31/2019 Supporting Water Operators Partnerships in Indonesia
4/21
45%Rata-rata NRW di Indonesia
Penurunan NRW harus menjadi prioritas utama
7/31/2019 Supporting Water Operators Partnerships in Indonesia
5/21
5%Cakupan pelayanan air limbahperkotaan.
Hanya beberapa kota yang memiliki jaringan air limbah
7/31/2019 Supporting Water Operators Partnerships in Indonesia
6/21
35%Besarnya biaya operasional untukenergy
Sistem operasi yang tidak efiktif membuat biaya operasionaltinggi
7/31/2019 Supporting Water Operators Partnerships in Indonesia
7/21
PROGRAM WOP ADB DI INDONESIA
Executing Agency Kementerian PU
Pendanaan bekerja sama dengan AusAID Durasi pelaksanaan January 2010 to 30 December 2012
Tujuan: Memperbaiki kinerja operasional dan keuangan PDAM . Menyediakan lingkungan yang memadai agar PDAM dapat
mengidentifikasi kebutuhan investasi jangka menengah danjangka panjang. Melengkapi inisiatip yang sedang berjalan didalam penyusunan
rencana bisnis PDAM.
Output yang diusulkan :
5 regional twinning partnerships dalam bidang NRW dan 2Sanitasi
2 domestik twinning partnerships dalam bidang NRW Workshop, training dan produk pengetahuan.
7/31/2019 Supporting Water Operators Partnerships in Indonesia
8/21
TWINNING PARTNERSHIPS
No Perusahaan penerima MentorAIR BERSIH1 PDAM Kabupaten Serang Ranhill, Malaysia2 PDAM Kabupaten Bandung Emasesa, Spain6 PDAM Kota Pekalongan PBA, Penang, Malaysia4 PDAM Kabupaten Bogor Water Corp. Australia5 PDAM Kota Banjarmasin K-Water, KoreaSANITASI6 PD PAL Kota Banjarmasin K-Water, Korea7 PDAM Kota Surakarta Emasesa, SpainTWINNING DOMESTIK8 PDAM Kabupaten Ciamis PDAM Palembang-Penang9 PDAM Kabupaten Tasikmalaya PDAM Palembang-Penang
7/31/2019 Supporting Water Operators Partnerships in Indonesia
9/21
KARAKTERISTIK PROGRAM TWINNING
Durasi 12-18 bulan
Diawali oleh kunjungan diagnosa selama satu minggu oleh mentor dan
ADB
Hasil diagnosa berupa rencana kerja dan MOU.
Rencana kerja fokus kepada inisiatip daerah percontohan (pilot area)
Kunjungan penerima kepada mentor untuk melihat yang dapat
diimplementasikan di tempat penerima.
Kunjungan 2 - 3 kali Mentor kepada penerima untuk pelaksanaan on-
the-job training
Penerima melaksanakan ' pekerjaan rumah ' diantara beberapakunjungan.
Program Twinning harus menghasilkan penurunan tingkat NRW di pilot
area atau perbaikan yang terukur di pengolahan air limbah.
7/31/2019 Supporting Water Operators Partnerships in Indonesia
10/21
Contoh : RANHILL-SERANG Twinning (NRW)
Tujuan
Pembentukan 4 DMA percontohan.
Memastikan 24/7 penyediaan air dengan perbaikan pengelolaantekanan.
Menentukan sistem pelaporan agar NRW dapat dipantau setiap
waktu.
Mengidentifikasi faktor NRW & mengukur dampak dari upayapenurunannya.
Aktivitas Kontrol Kebocoran air secara aktif
PDAM menyediakan:
Alat deteksi kebocoran, meter DMA, alat ukut tekanan dan debityang kompatibel dengan data logger.
Data loggers (dual channel flow & pressure)
7/31/2019 Supporting Water Operators Partnerships in Indonesia
11/21
CONTOH: K-WATER - PD PAL BANJARMASIN (SANITASI)
Tujuan
Membantu perbaikan operational dalam pengolahana air limbah
dan sistem pengumpulan di pilot area.
Mereview master plan air limbah & memberikan saran untuk
investasi rencana pengembangan lebih lanjut untuk pengolahan air
limbah dan jaringan sistem pengumpul.
PD PAL Banjarmasin diminta untuk:
Memperbaik i kualitas data untuk kualitas air limbah.
Menyediakan investasi untuk data sampling dan alat untuk
pemeriksaan kualitas air.
Mempertimbangkan alternatif untuk pengembangan lebih lanjut
terhadap sistem yang ada dengan penambahan 8 pengolahan air
skala kecil.
7/31/2019 Supporting Water Operators Partnerships in Indonesia
12/21
TERIMA KASIH
ADB weblink:http://www.adb.org/water/wop/wop.asp
WaterLinks website:http://www.waterlinks.org
ADB Project Officer:
Javier Coloma Brotons [email protected]
7/31/2019 Supporting Water Operators Partnerships in Indonesia
13/21
Scope:
- Energy Audit / Electricity Distribution / CO2 Emission:
Energy Conservation Measures
Transformer, Energy Motor / Pump Efficiency Test
Upgrade Equipment / New Technology
Review Operation Procedures (Standard and Sector specific)
- Other EE:
Demand Management: NRW and Water Conservancy
Economic Diameter of Distribution Pipes
ENERGY EFFICIENT WATER MANAGEMENT
7/31/2019 Supporting Water Operators Partnerships in Indonesia
14/21
Methodology
Assess New technologies based on electricity consumption
Calculate payback and recommend EE investment plan
Due Diligence: Equipment, References, Budget in each site Output
Decision to focus only on water production and not ondistribution, pending redesign (ring main vs. dedicatedpipelines) and hydraulic modeling of the network
ENERGY EFFICIENT WATER MANAGEMENT
7/31/2019 Supporting Water Operators Partnerships in Indonesia
15/21
Reliability
Safety
Energy Efficiency
Guarantee delivery
water service
Prevent Asset Damage & EnforceOHAS/ISO 18001
Enforce Asset Management
& ISO 24512
Steps
- Electricity Distribution Survey
- Linkage to ISO Certification and Continuous ImprovementProcess
- Critical Review of Process and Operation Procedures and linkageto CAPEX Investment Plan
- Preventative Maintenance Plan supporting EE
ENERGY EFFICIENT WATER MANAGEMENT
7/31/2019 Supporting Water Operators Partnerships in Indonesia
16/21
Conclusions:
Studies & audits are usually conservative: Greater savingsand shorter payback should be expected
Need for Combined Energy Audit with Process and Operation
Diagnostic (sector specific)
Refurbishment: Difficulty in shifting OPEX into CAPEX
Payback of investment: Is Grant funding warranted? How to
help financing EE in private projects?
Streamline energy efficiency into operations
Linkage with CDM, Climate Change
ENERGY EFFICIENT WATER MANAGEMENT
7/31/2019 Supporting Water Operators Partnerships in Indonesia
17/21
AusAID and ADB have agreed to explore the development of an
PDAM training/accreditation institute Initially focused on water supply, the institute would include
wastewater training as the sector develops
The institute will offer PDAM specific technical, managerial,financial management, planning and institutional/policy training
The institute will target PDAM managers and technical staff,sanitation operators, and local government decision-makers
The institute will have a central training center, complemented bysatellite regional centers, and potentially offer e-learning
The institute would work closely with PERPAMSI and other relevant(training) organizations
The institute should be able to funds its operations through fees
RATIONALE FOR A WATER ACADEMY
7/31/2019 Supporting Water Operators Partnerships in Indonesia
18/21
7/31/2019 Supporting Water Operators Partnerships in Indonesia
19/21
Management Training
Water Supply and Sanitation Utilities Management Water & Waste Water Management
Management SchoolMedium Level Professional Training (Operations)
Water Production
-Water Balance
-Storage
Water Distribution
-GIS
-Hydraulic Modeling
-Pressure Management
Sewerage
-Hydraulic Modeling
-Pipe rehabilitation and
cleansing
Water Treatment
Waste Water Treatment
-Process efficiency
-Electromechanical
-Automation
Clients Management
-Customer attention
-Billing and payment
Organization and Control of Water
Network Installation (Foreman)Installation & Maintenance of Water
Network s or Sewers (Operator)
Water Treatment Plant
Waste Water Treatment Plant (Operator)
Medium Level Operators Training (TechnicalSpecialization)
Technical Operators Training (Short Duration)
Training in Labor Risk Prevention
- Health
- Safety
-Confined spaces work
Training for Foreman & Operators
- Welding
- Pump Maintenance
- Basic Hydraulics
- Basic Electricity
-
Basic IT
7/31/2019 Supporting Water Operators Partnerships in Indonesia
20/21
INITIAL KEY STEPS FOR WATER ACADEMY
Determine relevant training initiatives currently provided byPERPAMSI, domestic universities,(international) organizations
Review training mechanisms/modalities in Indonesia thatcould complement traditional classroom training
Determine current/future capacity building needs of PDAMsand PD PALs
Draft a curriculum and curriculum management plan
Determine capacity of existing organizations to take upmanagement of water academy (e.g., PERPAMSI, ITB)
Develop a detailed three year budget and options for revenuegeneration
Determine appropriate management/legal structure
7/31/2019 Supporting Water Operators Partnerships in Indonesia
21/21
THANK YOU