Coiled Tubing Introduction Surface equipment BHA assemblies Some problems and observations 3/14/2009 1 George E. King Engineering GEKEngineering.com
Transcript
Page 1: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Coiled Tubing Introduction

• Surface equipment

• BHA assemblies

• Some problems and observations

3/14/2009 1George E. King Engineering

GEKEngineering.com

Page 2: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Coiled Tubing Introduction

• Surface equipment

• BHA assemblies

• Some problems and observations

3/14/2009 2George E. King Engineering

GEKEngineering.com

Page 3: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 3George E. King Engineering

GEKEngineering.com

Page 4: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

World Wide CT RecordsLargest CT in Use 3-1/2"Max Depth 24,000'Max Horizontal 17,000' (80 deg)-Wytch BPLongest BHA 1500' - perf guns - UKLongest Strings 23,000' of 2-3/8"

28,000' of 1-1/2Max Wellhead Pressure 9800 psiMax Deployment Press 4500 psiMax BH Temp 700F - Mex, 780F JapanMax Acid at Temp 28% at 280F in DubaiCT in H2S 75% in Greece

98%/300F- Gulf of Mexico(string used one time)

CT in CO2 15% - (string ruined)3/14/2009 4George E. King Engineering

GEKEngineering.com

Page 5: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Power Pack

InjectorReelOperator’s Cab

Transportsand Pumpers

wind

Typical CT Layout

3/14/2009 5George E. King Engineering

GEKEngineering.com

Page 6: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

CT Reel Configurations

•CT Reels available in number of configurations–Truck mounted (fixed) - permanently fixed to the truck

chassis–Truck mounted (skid) - may be changed out–Skid mounted - for offshore operations–Trailer mounted - for large capacity (length) or heavy weight

strings–CT logging reel - fitted with electrical swivel/collector–Special application reel - typically for completion applications

•Local conditions/nature of CT operations determinetype of reel required

3/14/2009 6George E. King Engineering

GEKEngineering.com

Page 7: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 7George E. King Engineering

GEKEngineering.com

Page 8: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 8George E. King Engineering

GEKEngineering.com

Page 9: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Coiled Tubing Rig up in Alaska. Two wells on the same pad are being.

3/14/2009 9George E. King Engineering

GEKEngineering.com

Page 10: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 10George E. King Engineering

GEKEngineering.com

Page 11: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

CT Equipment Basics

• Components– Coil

– Power pack

– Component Controls

– Reel

– Injector (with guidearch)

– Well Control Components

3/14/2009 11George E. King Engineering

GEKEngineering.com

Page 12: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Coil Types and Availability

• CT diameters

• CT wall thickness

• CT tapered strings

• CT strength ranges

• CT metal choices

• Composite CT

3/14/2009 12George E. King Engineering

GEKEngineering.com

Page 13: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

CT Diameters

• 1/2, 3/4 and 1” early diameters

• 1-1/4” and 1-1/2” workhorses (1-3/4)

• 1-3/4 to 2-3/8” larger workstrings (3-1/2)

• 3-1/2 and 4-1/2” (and larger) - flowlines

3/14/2009 13George E. King Engineering

GEKEngineering.com

Page 14: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

CT production for For 1996

• 1” 1.52 MM ft

• 1.25” 14.2 MM ft

• 1.5” 6.2 MM ft

• 1.75” 3.3 MM ft

• 2” 1.22 MM ft

• 2-3/8” 0.56 MM ft

• 2-7/8” 0.43 MM ft

• 3-1/2 0.45 MM ft

• 4&4.5” 0.125 MM ft

3/14/2009 14George E. King Engineering

GEKEngineering.com

Page 15: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Tapered Strings

• Common is I.D. taper - weld area taper

• Uncommon is O.D. taper - deeper wells, some hydraulic problems

3/14/2009 15George E. King Engineering

GEKEngineering.com

Page 16: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Junction weldin flat strip

Butt Weld – early string joiner and common repair weld.

3/14/2009 16George E. King Engineering

GEKEngineering.com

Page 17: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Bias weldin flat strip

The bias weld offsets the weld ends on the strip as it is formed into a tube – much stronger.

3/14/2009 17George E. King Engineering

GEKEngineering.com

Page 18: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Field Welds

• Always a Butt weld.

• Can decrease tensile strength of CT by 50% or more.

• Quality of field welds varies enormously

• Avoid field welds when you can.– Upper part of tubing is worst place for a butt

weld.

3/14/2009 18George E. King Engineering

GEKEngineering.com

Page 19: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Material Strengths

• 55,000 psi (limited)

• 70,000 to 80,000 psi (still in use)

• 100,000+ psi (now very common)

3/14/2009 19George E. King Engineering

GEKEngineering.com

Page 20: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Trade-Offs

• strength vs cost• ductility/weakness vs strength/cost• corrosion possibilities• strength vs service life

• In general, high strength CT lasts longer and is more fatigue resistant. But, what about corrosion? Hardness matters. Stress Corrosion cracking and embrittlement.

3/14/2009 20George E. King Engineering

GEKEngineering.com

Page 21: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Analysis of Coiled Tubing

Mod A606 Mod A607Carbon 0.08-0.15 0.08-0.17Manganese 0.60-0.90 0.60-0.90Phosphorus 0.030 max 0.025 maxSulfur 0.005 max 0.005 maxSilicon 0.30-0.50 0.30-0.45Chromium 0.45-0.70 0.40-0.60Nickel 0.25 max 0.10 maxCopper 0.40 max 0.40 maxMolobidum 0.21 max 0.08-0.15Cb-V 0.02-0.043/14/2009 21

George E. King Engineering GEKEngineering.com

Page 22: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Yield Strength HRB HRC Min. Elong.(psi)

50,000 2270,000 85-94 30%80,000 90-98 28%90,000 94 22 25%100,000 20-25 22% est.110,000 22-28 18% est

SPE 46052

New CT Properties

3/14/2009 22George E. King Engineering

GEKEngineering.com

Page 23: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Composites

• Limited Use

• Composites lighter/more flexible than steel.

• More costly than steel

• Limitations:– Creep under load

– Temperature

– Downhole Buckling resistance

3/14/2009 23George E. King Engineering

GEKEngineering.com

Page 24: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Surface Equipment

• Power Pack

• Reel

• Controls

• Injector

• Seals

3/14/2009 24George E. King Engineering

GEKEngineering.com

Page 25: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Power pack – usually diesel driven hydraulic pumps.

Requirements set by equipment in use.

3/14/2009 25George E. King Engineering

GEKEngineering.com

Page 26: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Typical Layout of Control Cabin Controls and Instruments (1)

Layer 1OPEN

STRIPPER# 2

LEVELWIND ARM

UP

DOWN

EMERGENCYTRACTION SUPPLY

INJECTOR INSIDE TRACTION PRESSURE

1500 PSI MAX

TOP

ON

OFF

ON

OFF

ON

OFF

MIDDLE

BOTTOM

INSIDE TRACTION

PRESSURE ADJUST

INSIDE TRACTIONSUPPLY PRESSURE

BLEEDPRESSURE

INJECTOR OUTSIDETENSION PRESSURE

150 PSI MAX

PRESSURE

PRESSURE

PRESSURE

STRIPPER# 1

RETRACT NEUTRAL PACKRETRACT NEUTRAL PACK

STRIPPER SYSTEM PRESSURE5000 PSI MAX

STRIPPERPRESSURE ADJUSTAIR REG. CONTROL

# 2STRIPPER

# 1STRIPPER

BOP SUPPLYBOP PRESSURE BOP SUPPLY PRESSURE

ON

OFF

CLOSE OPEN CLOSE OPEN

CLOSE OPEN CLOSE OPEN

BLIND RAM

PIPE RAM

SHEAR RAM

SLIP RAMBOP

HIGH

LOW

INJECTORSPEED

REEL BRAKE

OFF

REEL PRESSURE

REEL PRESSURE ADJUST

REEL CONTROLLEVELWINDOVERRIDE

INSIDE TRACTIONPRESSURE DRAIN

CLOSE

INJECTORMOTOR PRESSURE

INJECTOR MOTOR PRESSURE ADJUST

INJECTORCONTROL

INJECTOR DIRECTIONALCONTROL VALVEPILOT PRESSURE

PRIORITY PRESSURE2,000 PSI MAX

IN

OUT

ON

OFF

ON

OFF

AIP SUPPLYPRESSURE

30 GPMPUMP

60 GPMPUMP

THROTTLE

ENGINESTOP EMERGENCY

STOP

AIR HORN

INJECTOR CHAINLUBRICATION

REEL TUBINGLUBRICATION

WELLHEAD PRESSURECIRCULATING PRESSURE

TUBING WEIGHT INDICATOR

SchlumbergerDowell

Looks more complex, but main data is from load, wellhead pressure and annular pressure.

Main controls are injector head and coil spooling.

3/14/2009 26George E. King Engineering

GEKEngineering.com

Page 27: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 27George E. King Engineering

GEKEngineering.com

Page 28: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 28George E. King Engineering

GEKEngineering.com

Page 29: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Principal Gauges–Wellhead Pressure Gauge

• displays wellhead pressure at the BOP pressure port

–Circulating Pressure Gauge• displays pressure at the reel-manifold pressure sensor

–Weight Indicator• displays weight exerted by the tubing on the injector head

3/14/2009 29George E. King Engineering

GEKEngineering.com

Page 30: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 30George E. King Engineering

GEKEngineering.com

Page 31: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Running Speeds

• First time into a well - 40 to 70 ft/min

• Normal run in operations - 50 to 100 ft/min

• Spool-out? – depends on the well, the BHA, coil equipment, friction and operator.

• Runaway - experienced 800 to 900 ft/min.

3/14/2009 31George E. King Engineering

GEKEngineering.com

Page 32: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Typical CT Reel - Side View

3/14/2009 32George E. King Engineering

GEKEngineering.com

Page 33: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 33George E. King Engineering

GEKEngineering.com

Page 34: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

What’s Different Than Jointed Pipe?

All fluids injected from the surface enter the CT at the bed-wrap end. All fluid has to travel through all of the coil.

That influences friction since friction is near constant w/ CT whether you a injecting fluid at 1 foot into the well or 10,000 ft into the well.

3/14/2009 34George E. King Engineering

GEKEngineering.com

Page 35: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Some of the extra fittings in the input plumbing allow a ball to be inserted and “dropped” (pumped through the coil). The ball travel may take several minutes to clear the coil and enter the well.

3/14/2009 35George E. King Engineering

GEKEngineering.com

Page 36: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

A flow control manifold. This one allow reverse circulation through coiled tubing.

3/14/2009 36George E. King Engineering

GEKEngineering.com

Page 37: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Reel Drum Capacity

B

A

Freeboard

C

Freeboard is normally not much of an issue, but can become very important if the CT is not spooled tightly and the drum is nearly full for a deep well CT job.

3/14/2009 37George E. King Engineering

GEKEngineering.com

Page 38: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 38George E. King Engineering

GEKEngineering.com

Page 39: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 39George E. King Engineering

GEKEngineering.com

Page 40: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Reel Information for Various Sizes of CT

CT Diam. Reel Hub Diam. Guide Arch (Reel Width) Approx. Capacity(in) (in) (in) (in) (ft)0.75 48 48

1 60 48-541.25 72 48-72 117 175001.5 84 (48)-72 128 15000

1.75 96 72-96 148 180002 96 72-96

2.375 108 90-1202.875 108 90-120

3.5 120 90-120

Selected Reel Diameter Information

3/14/2009 40George E. King Engineering

GEKEngineering.com

Page 41: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

The level-wind (like a bait-casting fishing reel) helps feed the coil onto the reel.

3/14/2009 41George E. King Engineering

GEKEngineering.com

Page 42: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Depth Measurement Equipment

•Depth measuring equipment -Electronic or mechanical•Frequently mounted on injector head

•Depth information commonly acquired by two methods:• Friction-wheel counter between injector chains and stripper

• Encoder assembly on injector-head chain drive shaft

3/14/2009 42George E. King Engineering

GEKEngineering.com

Page 43: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Guide Arch

•Guide arch–Turn tubing through angle between wellhead and CT

reel

–CT supported by rollers at ±10-in. intervals around gooseneck

• guide arch radius significantly affects fatigue in CT string

3/14/2009 43George E. King Engineering

GEKEngineering.com

Page 44: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Comparison of Guide Arch Sizes

50-in. radius(HR 240)

120-in. radius(HR 480)

72-in. radius(HR 260)

3/14/2009 44George E. King Engineering

GEKEngineering.com

Page 45: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Recommended Guide Arch RadiiCoiled

Tubing OD (in.)

0.7501.0001.2501.5001.7502.0002.3752.8753.500

Typical Reel Core Radius

(in.)

2420-3025-3630-4035-4840-4848-5454-5865-70

Typical Guide Arch Radius

(in.)

4848-5448-7248-7272-9672-96

90-12090-12096-120

3/14/2009 45George E. King Engineering

GEKEngineering.com

Page 46: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

CT Injectors

• Injector

• Gripper Design and Effect on the Tube

• Power Requirements

• Load Cells

• Wear and Failure Points

• Control vs “micro” control

3/14/2009 46George E. King Engineering

GEKEngineering.com

Page 47: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Head Components•Principal components of injector head:–Drive and brake system–Chain assembly–Traction and tension system–Guide-arch assembly

•Secondary or support systems:–Weight indicator–Depth sensor mounts–Stripper mount

3/14/2009 47George E. King Engineering

GEKEngineering.com

Page 48: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Head Drive Systems•Injector heads hydraulically driven–Two or four hydraulic motors–Motors connected/synchronized through gear system–Drive directed to chain drive sprockets via drive shafts–Rotation/speed of motors controlled by valve on power pack–Hydraulic system pressure/rate controlled from CTU control

console–Pressure relief/crossover relief valves

• protect tubing/hydraulic components

3/14/2009 48George E. King Engineering

GEKEngineering.com

Page 49: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Typical Injector Head

Stripper assembly

Gooseneck or guide-arch

Injector drive motor

3/14/2009 49George E. King Engineering

GEKEngineering.com

Page 50: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 50George E. King Engineering

GEKEngineering.com

Page 51: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Head Brake Systems•Brake hydraulically controlled–Hydraulic pressure required to release brake

• fail-safe in operation

–Application of brake is automatic• controlled by drive system hydraulic pressure• applied when hydraulic pressure below preset value

•Some hydraulic motors have high/low gear option–Selected remotely from the CTU the control console–Allows injector head to operate more efficiently

3/14/2009 51George E. King Engineering

GEKEngineering.com

Page 52: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Head Chain Assembly•Most injector heads have two sets of opposing endlesschains–Series of gripper blocks mounted on each chain–Gripping profile of each block suits a specific tubing size

•Entire CT string load held by face of the gripper blockor insert–Often achieved under significant force–Selection/operation/maintenance of chain components

should minimize risk of damage to CT string

3/14/2009 52George E. King Engineering

GEKEngineering.com

Page 53: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Injector Head Chain Gripper Inserts•Removable gripper inserts on most injector heads

–Run range of tubing sizes without removing/replacing entirechain assembly

–Reduce time/effort required to reconfigure injector head• when running a different size of CT string• when running a tapered CT string

–Reduce cost of replacement when worn

3/14/2009 53George E. King Engineering

GEKEngineering.com

Page 54: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 54George E. King Engineering

GEKEngineering.com

Page 55: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Ribbed injector block.

3/14/2009 55George E. King Engineering

GEKEngineering.com

Page 56: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Smooth faced injector

3/14/2009 56George E. King Engineering

GEKEngineering.com

Page 57: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

SS800 Chain Assembly

3/14/2009 57George E. King Engineering

GEKEngineering.com

Page 58: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 58George E. King Engineering

GEKEngineering.com

Page 59: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Bottom sprocket on injector.

3/14/2009 59George E. King Engineering

GEKEngineering.com

Page 60: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 60George E. King Engineering

GEKEngineering.com

Page 61: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Traction and Tension Systems•Injector head traction or inside chain tensioner system–Also known as skate system–Provides force to securely grip tubing–Force applied through 3 separate sets of hydraulic cylinders

• reduces risk of major operating failure if component fails

•Outside chain tensioner system–Ensures adequate tension in chain section outside vertical

drive plane–Tension provided by hydraulic rams

3/14/2009 61George E. King Engineering

GEKEngineering.com

Page 62: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Backpressure Adjusted to Provide Suitable Tension

Incorrect

Correct

3/14/2009 62George E. King Engineering

GEKEngineering.com

Page 63: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 63George E. King Engineering

GEKEngineering.com

Page 64: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 64George E. King Engineering

GEKEngineering.com

Page 65: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Coiled Tubing Deployment

Kill Line

, 50.8 mm

Flowline,

101.6 mm

Wellhead

ESD(Tester)

Flow Line,

101.6 mm

Drilling Spool,

179.4 mm, 35 MPa

Coiled Tubing BOP

179.4 mm, 35 MPa Blind/Shear RamSlip/Pipe Ram

Flow Spool

Annular Preventer

Conventional Rig BOP

BHA

Deployment BOP

179.4 mm, 35 MPa

Gate Valve,

179.4 mmLocating

RamUpper

Pipe Ram

Lower Pipe/Slip Ram

Deployment BOP

BJ Services

3/14/2009 65George E. King Engineering

GEKEngineering.com

Page 66: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Physical Brace

• If there is a long space (length is a variable with pipe diameter, wall, and buckling force) then a brace between the bottom of the injector and the first seal is necessary.

3/14/2009 66George E. King Engineering

GEKEngineering.com

Page 67: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Snubbing/Stripping Forces on CT

• Force to push CT through stuffing box/stripper (opposite running)

• Force on CT from Well Head Pressures -(upward)

• Force to overcome friction (opposite running)• Force from weight of CT & BHA (downward)

3/14/2009 67George E. King Engineering

GEKEngineering.com

Page 68: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

0

10

20

30

40

50

60

70

80

90

100

0 2000 4000 6000 8000 10000 12000

Load

Nec

essa

ry, l

bs

Wellhead Pressure, psi

Load Necessary to Pull Wireline into Wellhead

0

0

0

0

0.072”

0.108”

Problem in rig up height and lubricator length.

3/14/2009 68George E. King Engineering

GEKEngineering.com

Page 69: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Pressure Induced Snubbing Force VS Well Head Pressure for Various Coiled Tubing Sizes, (Must add stripper friction force)

0

20000

40000

60000

80000

100000

120000

140000

160000

0 2000 4000 6000 8000 10000 12000 14000 16000

Well Head Pressure, psi

Base

Snu

bbin

g Fo

rce,

lbs

1" CT

1-1/4" CT

1-1/2" CT

1-3/4" CT

2" CT

2-3/8" CT

2-7/8" CT

3.5" CT

Snubbing Force on CT at Wellhead

3/14/2009 69George E. King Engineering

GEKEngineering.com

Page 70: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

3/14/2009 70George E. King Engineering

GEKEngineering.com

Page 71: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Gap between the injector and the stuffing box – The pipe in this area is very susceptible to bending – Note the brace around the CT.

3/14/2009 71George E. King Engineering

GEKEngineering.com

Page 72: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Seals

• Stuffing Box - Primary sealing mechanism for isolating the wellbore. Positioned above the BOP, just underneath the injector head. A connector attaches the box to the BOP.

• BOP - multi-level control for closing in the well, shearing the CT, sealing around the CT and gripping the CT. May be used in pairs in extreme applications.

3/14/2009 72George E. King Engineering

GEKEngineering.com

Page 73: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Weight Indicator Equipment

Front weight sensor

Rear weight sensor

3/14/2009 73George E. King Engineering

GEKEngineering.com

Page 74: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Typical Loads: 1.5” CT, 5000 psi

• snub force = (1.767 in2 x 5000 psi)=8835 lb

• stuffing box friction (drag force=2000 lb

• total =10835 lbat start of the CT run-in

3/14/2009 74George E. King Engineering

GEKEngineering.com

Page 75: Surface equipment BHA assemblies Some problems and ... · PDF fileCoiled Tubing Introduction • Surface equipment • BHA assemblies • Some problems and observations 3/14/2009 1

Load Changes w/CT inserted

• 1.5:, 0.109” wall, 1.623 lb/ft• one foot of CT in well = 10833 lb

• 1000’ CT in well=10835-(1000 x 1.623)=9212 lbs

• 10,000’ CT in well= 10835-(10,000x1.623)= -5395 lbs

• this assumes no wall friction