Surface Water Surface Water Treatment Treatment Plant Plant
Transcript
Page 1: Surface Water Treament Plant

Surface Water Surface Water Treatment Treatment

PlantPlant

Page 2: Surface Water Treament Plant

Project Details

Water Resource ManagementHDR Engineering, Inc.

MUI Services, LLCEnprotec/Hibbs & Todd, Inc. (eHT)

Construction ManagementEngineering Team

TBDWater Transmission Mains

TBDPrestressed Concrete Clearwell

Pepper‐Lawson Construction, LPPhase I (10 MGD) Surface Water Treatment Plant

Double Oak Construction, Inc.Mass Grading & Raw Water Reservoir

Water Resource ManagementConstruction Management

ContractorContract

Project Funding: MUD ReimbursementWinter, 2011

Project Number: WA0901Estimated Completion

Surface Water Treatment Plant$50,953,873 

Funding SourceTotal Estimated Cost

8850 1/2 #1 Sienna Ranch Road (see map on first slide)

Project Location

Construct 10 million gallon surface water treatment plant and distribution system.

Project Description

Page 3: Surface Water Treament Plant

Project BackgroundThe City of Missouri City is responding to groundwater reduction goals established by the Fort Bend County Subsidence District. In cooperation with public water systems within Missouri City’s ETJ, a Groundwater Use Reduction Plan is being developed to meet the required conversion from groundwater to surface water. The Groundwater Use Reduction Plan identifies the municipal utility districts (MUDs) comprising Sienna Plantation for the initial conversion from groundwater to surface water as the source of potable water supply. Other public water systems within Missouri City’s ETJ will be targeted for conversion in future years as required to meet groundwater use reduction goals.

The new plant will be constructed on property to be owned and controlled by the City of Missouri City. The new plant will supply water to a number of municipal utility districts in the area.

The raw water source for the new Missouri City plant consists of raw surface water from the Brazos River segment number 1202 by way of the Briscoe Canal, owned and operated by the Gulf Coast Water Authority (GCWA). The raw water intake point for the new source will be the Briscoe Canal. No treatment of any kind is currently present at the source intake point.

Page 4: Surface Water Treament Plant

Joint Groundwater Reduction Plan

Thunderbird Utility DistrictFort Bend MUD 23

The Manors Property Owners AssociationFort Bend MUD 149

Sienna Plantation MUD 3Fort Bend MUD 129

Sienna Plantation MUD 2Fort Bend County MUD 49

Sienna Plantation MUD 12Fort Bend County MUD 48

Sienna Plantation MUD 10Fort Bend County MUD 47

Sienna Plantation MUD 1Fort Bend County MUD 46

Quail Valley Utility DistrictFort Bend County MUD 42

Palmer Plantation MUD 2Fort Bend County MUD 26

Palmer Plantation MUD 1Fort Bend County MUD 115

Meadow Creek MUDFirst Colony MUD 9

Lake Shore HarbourEstates of Silver Ridge

Lake Olympia Civic AssociationCity of Missouri City

Fort Bend MUD 24Blue Ridge MUD

Page 5: Surface Water Treament Plant

Project Pilot Study

The location for the pilot testing systems will be at the Gulf Coast Water Authority’s Briscoe Canal Intake. The intake location is fenced, with adequate power and adequate ancillary services available.The pilot testing will serve a valuable purpose for design of the disinfection protocol. Pilot testing may also reveal benefits associated with use of UV/peroxide in the finished water.

Page 6: Surface Water Treament Plant

Target Conversion Schedule to thePotable Water Transmission System

Delivery Point (“Water Plant”) Anticipated Year On‐Line (Conversion)

Sienna 1 and 2 Water Treatment Plant Start‐up (Winter 2011)

Sienna 4 and 5 As Development Occurs – Anticipated not later than 2015

FB 46‐149 2016

Vicksburg‐Jt. Powers 2016

Missouri City 3 2018

FB 115‐129 2030

Page 7: Surface Water Treament Plant

Treatment Plant Process Flow

Page 8: Surface Water Treament Plant

Pilot Study

Membrane Filtration Pilot Study Protocol for the City of Missouri City Water Treatment Plant was prepared to collect essential information necessary to design the new 10 million gallon per day (mgd) surface water treatment plant. The Protocol has been structured to generate essential information for design of pretreatment , membrane, post‐membrane and disinfection systems for the facility.

Page 9: Surface Water Treament Plant

Site for future Surface Water Treatment Plant

Page 10: Surface Water Treament Plant

Mass Grading Contract

The Mass Grading project is the first step in preparing the site for the actual plant. It is includes site preparation and raw water reservoirs.

Page 11: Surface Water Treament Plant

Construction Progress July

Raw Water Pump Station

Page 12: Surface Water Treament Plant

Construction Progress August

Raw Water

Pump Station

Page 13: Surface Water Treament Plant

Construction Progress September

Foundation for the 

Membrane Building

Page 14: Surface Water Treament Plant

Construction Progress October 8th

Page 15: Surface Water Treament Plant

Construction Progress October

Page 16: Surface Water Treament Plant

Construction Progress November