SW 8 th Ave Extension Agreement. Agreement with Town of Tioga, LLC. Total Project: Extension of SW 8 th Ave between SW 122 nd St and SW 143 rd St. Two travel lanes, bike lanes, sidewalk, multiuse path, street trees - PowerPoint PPT Presentation
Popular Tags:
5
SW 8 th Ave Extension Agreement Agreement with Town of Tioga, LLC
Transcript
Page 1: SW 8 th  Ave  Extension Agreement

SW 8th Ave Extension Agreement

Agreement with Town of Tioga, LLC

Page 2: SW 8 th  Ave  Extension Agreement

SW 8th Ave Extension

Total Cost Estimate: $6,420,000Total Estimate for Agreement Portion: $3,700,000Developer responsible for 9.7% of CostRemainder reimbursed through SW Impact Fee FundFDOT CIGP Grant: $2,400,000

Total Project: Extension of SW 8th Ave between SW 122nd St and SW 143rd St. Two travel lanes, bike lanes, sidewalk, multiuse path, street trees

This Agreement: Design and Construction of the portion

between SW 122nd and SW 133rd Way

Page 3: SW 8 th  Ave  Extension Agreement

SW 8th Ave Concept Design

Page 4: SW 8 th  Ave  Extension Agreement

SW 8th Ave Concept Design

Page 5: SW 8 th  Ave  Extension Agreement

Staff Recommendation

The Board of County Commissioners approve the agreement with Town of Tioga, LLC to design and construct the SW 8th Avenue extension between SW 122nd St and SW 133rd Way and authorize the Chair's signature.