SWAMP THINGS SWCS 2016 Winter Conference Swamp Mat Considerations for Linear Projects Daniel Rukakoski, PWS, CWS, PSS Principal Environmental Scientist Tighe & Bond 53 Southampton Rd. Westfield, MA 01085 413.875.1312 [email protected]
Transcript
Page 1: Swamp Mat Considerations for Linear Projects

SWAMP THINGS SWCS 2016 Winter Conference

Swamp Mat Considerations for Linear Projects

Daniel Rukakoski, PWS, CWS, PSSPrincipal Environmental ScientistTighe & Bond53 Southampton Rd.Westfield, MA [email protected]

Page 2: Swamp Mat Considerations for Linear Projects

Overview

■ Why Use Swamp Mats?

■ Site Evaluation Considerations

■ Pre-Construction Planning

■ Site Inspections

■ Swamp Mat Removal and Restoration

Page 3: Swamp Mat Considerations for Linear Projects

Why Use Swamp Mats?

■ Minimize Environmental Impact

– Compressed soils– Habitat degradation– Invasive species colonization– Regulatory impacts

Page 4: Swamp Mat Considerations for Linear Projects

Why Use Swamp Mats?

■ Avoid Permanent Stream Crossings

Page 5: Swamp Mat Considerations for Linear Projects

Why Use Swap Mats?

Minimize Impacts to Maintained Lawn

Avoid impacts to agricultural land Minimize impacts to other utilities

Swamp Mats as Retaining Walls

Page 6: Swamp Mat Considerations for Linear Projects

Why Use Swamp Mats?

■ Facilitate Site Access and Work

Allow use of Heavy Equipment

Provide access to difficult areas

Provide stable work platform

Page 7: Swamp Mat Considerations for Linear Projects

Why Use Swamp Mats?

■ Allow for Year Round Construction

Summer

Winter- Snow Cover

Spring- Flooded Conditions

Fall

Page 8: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Scope of Work- Nature of Facility

Distribution ROW: 40 feet

115 kV/345 kV Transmission ROW: 180 feet

115 kV Transmission ROW: 100 feet

345 kV Transmssion ROW: 450 feet

Page 9: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Equipment and Work Area Evaluations

Insulator ReplacementWork Pads: 16’X30’

Line ReconductoringWork Pads: 60’X60’

Structure ReplacementWork Pads: 150’ X 150’

Page 10: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Existing Access– Historic Roads– ATV Access

Page 11: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Access Alternatives

Off ROW Access

Page 12: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Access Alternatives

Access from Opposite Side

Page 13: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Length of Crossings/ Stream SpanningStream Spanning

Length of Crossing

Page 14: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Hydrologic Regime

Scrub-ShrubOpen Water

Floodplain Perennial StreamsPerennial Stream

Page 15: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Hydrologic Regime

Open Water

Floodplain Perennial Streams

Page 16: Swamp Mat Considerations for Linear Projects

Site Evaluation Considerations

■ Steepness of Terrain

Page 17: Swamp Mat Considerations for Linear Projects

Pre-Construction Planning

■ Review of Existing Data– Previous projects– GIS resources– Aerial photos– Soil mapping

Page 18: Swamp Mat Considerations for Linear Projects

Pre-Construction Planning

■ Resource Area Delineations

Page 19: Swamp Mat Considerations for Linear Projects

Pre-Construction Planning

■ Preliminary Mapping

DPR3

Page 20: Swamp Mat Considerations for Linear Projects

Slide 19

DPR3 Do we have any NERC preliminary mapping we could use?Daniel P. Rukakoski, 3/8/2016

Page 21: Swamp Mat Considerations for Linear Projects

Pre-Construction Planning

■ Site Walk

Page 22: Swamp Mat Considerations for Linear Projects

Pre-Construction Planning

■ Final Mapping

Page 23: Swamp Mat Considerations for Linear Projects

Site Inspections

■ Purpose– Permit Requirement

■ Inspection Issues– Adhering to plans– Housekeeping– Sediment tracking– Soil/Spoil Management– Dewatering

Page 24: Swamp Mat Considerations for Linear Projects

Swamp Mat Removal and Restoration in Wetland

Before Construction-2/20/2012

11/12/2012

Pre-Construction: 02/20/2012

Post Construction: 9/6/2013Restoration: 11/12/2012

During Construction: New Structure

Installation07/21/2012

Page 25: Swamp Mat Considerations for Linear Projects

Mat Removal and Restoration in Upland

June 25, 2013

July 26, 2013 August 30, 2013

May 25, 2016

Page 26: Swamp Mat Considerations for Linear Projects

Mat Removal Considerations

■ Remove by “backing out” of site■ Address rutting■ Seed/mulch areas of disturbed soil■ Remove invasives from mats■ Recover sediment and broken mats

Page 27: Swamp Mat Considerations for Linear Projects

Tighe&BondEngineers / Environmental Specialists

www.tighebond.com

Questions?

Swamp Mat as a Viewing Deck