+ All Categories
Home > Documents > SWARM Generic Statement of Work for...

SWARM Generic Statement of Work for...

Date post: 27-Apr-2018
Category:
Upload: buidang
View: 216 times
Download: 0 times
Share this document with a friend
52
Transcript

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page IIFile: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

DOCUMENT CHANGE DETAILS

ISSUE DATA SHEET DESCRIPTION

1 24.03.2006 all First Formal Issue

2 10.04.2006 all Approved issue for ITT

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of Work

for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page IIIFile: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

CONTENTS

1. INTRODUCTION .................................................................................................................................... 2 1.1 Scope .............................................................................................................................................. 2 1.2 Applicability ..................................................................................................................................... 2

2. REFERENCES....................................................................................................................................... 3 2.1 Requirements Tree.......................................................................................................................... 3 2.2 Documents ...................................................................................................................................... 3

2.2.1 Applicable Documents .......................................................................................................... 3 2.2.2 Reference Documents .......................................................................................................... 4

2.3 Abbreviation List.............................................................................................................................. 5

3. EQUIPMENT MODEL & CATEGORY DEFINITION .............................................................................. 8 3.1 Equipment Model Definitions .......................................................................................................... 8

3.1.1 Lot Samples of EEE Components ........................................................................................ 8 3.1.2 Technology Samples............................................................................................................. 8 3.1.3 Breadboard Model (BB) ........................................................................................................ 8 3.1.4 Engineering Model (EM) ....................................................................................................... 8 3.1.5 Engineering Qualification Model (EQM)................................................................................ 9 3.1.6 Qualification Model (QM) ...................................................................................................... 9 3.1.7 Protoflight Model (PFM) ...................................................................................................... 10 3.1.8 Flight Model (FM) ................................................................................................................ 10 3.1.9 Flight Spare model (FS) ...................................................................................................... 10 3.1.10 Spare Kit (SK) ................................................................................................................... 10

3.2 Equipment Category Definitions.................................................................................................... 11 3.2.1 Fully Recurring Equipment - Category A ............................................................................ 11 3.2.2 Recurring Equipment with Limited Changes - Category B ................................................. 11 3.2.3 Modified Equipment - Category C....................................................................................... 12 3.2.4 New Equipment - Category D ............................................................................................. 12

4. WORKFLOW ........................................................................................................................................ 13 4.1 Fully Recurring Equipment - Category A....................................................................................... 13 4.2 Recurring Equipment with Limited Changes - Category B............................................................ 14 4.3 Modified Equipment - Category C ................................................................................................. 15 4.4 New Equipment - Category D........................................................................................................ 16

5. REVIEWS AND BOARDS DEFINITION............................................................................................... 17 5.1 Reviews......................................................................................................................................... 17

5.1.1 Kick-Off Review................................................................................................................... 17 5.1.2 Equipment Qualification Status Review (EQSR) ................................................................ 17

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of Work

for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page IVFile: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5.1.3 Design Reviews .................................................................................................................. 18 5.1.4 Manufacturing Readiness Review (MRR)........................................................................... 19 5.1.5 Qualification Review (QR)................................................................................................... 19 5.1.6 Test Readiness Review (TRR)............................................................................................ 19 5.1.7 Test Review (TR, or Test Review Board, TRB) .................................................................. 19 5.1.8 Delivery Review (DR, or Delivery Review Board, DRB) ..................................................... 20

5.2 Boards ........................................................................................................................................... 21 5.2.1 Parts Control Board (PCB).................................................................................................. 21 5.2.2 Materials & Processes Control Board (MPCB) ................................................................... 21 5.2.3 Non-Conformance Review Board (NRB) ............................................................................ 22

6. MANAGEMENT REQUIREMENTS...................................................................................................... 23

7. PRODUCT ASSURANCE REQUIREMENTS ...................................................................................... 24

8. ENGINEERING REQUIREMENTS ...................................................................................................... 25 8.1 General.......................................................................................................................................... 25 8.2 Equipment Design ......................................................................................................................... 25 8.3 Interfaces....................................................................................................................................... 25 8.4 Operations..................................................................................................................................... 26 8.5 Analyses........................................................................................................................................ 26 8.6 Verification Task............................................................................................................................ 27

9. EXPORT CONTROL REQUIREMENTS.............................................................................................. 28 9.1 General.......................................................................................................................................... 28 9.2 EU Export Control Requirements.................................................................................................. 28 9.3 Direct “US Supplier” ...................................................................................................................... 28

9.3.1 Inputs from EADS Astrium to Support Subcontractor's Application.................................... 28 9.3.2 Description of Subcontractor's Responsibilities .................................................................. 29 9.3.3 Outputs from Subcontractor ................................................................................................ 29

9.4 Requirements for Lower Tiers ‘’US Suppliers’’.............................................................................. 29

10. MANUFACTURING & TEST REQUIREMENTS ................................................................................ 31 10.1 Introduction.................................................................................................................................. 31 10.2 Manufacturing and Production .................................................................................................... 31 10.3 Assembly Integration and Verification......................................................................................... 31

10.3.1 MAIV Planning .................................................................................................................. 31 10.3.2 General Test Requirements.............................................................................................. 31 10.3.3 Life Tests........................................................................................................................... 32 10.3.4 Test Failure ....................................................................................................................... 32 10.3.5 Verification Control............................................................................................................ 33

10.4 Ground Support Equipment ........................................................................................................ 34

11. SUPPORT TASKS ............................................................................................................................. 36

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of Work

for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page VFile: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

11.1 Introduction.................................................................................................................................. 36 11.2 Support to Higher Level Reviews................................................................................................ 36 11.3 Support to AIV at Higher Level.................................................................................................... 36

11.3.1 EGSE Operation Support.................................................................................................. 36 11.3.2 Integration and Test Support ............................................................................................ 37

12. APPENDIX A DOCUMENTATION REQUIREMENTS LIST .............................................................. 38

13. APPENDIX B INTERFACE DATA REQUIREMENTS........................................................................ 39 13.1 Computer Aided Drawing and Design (CAD) data...................................................................... 39

13.1.1 EADS Astrium CAD system .............................................................................................. 39 13.1.2 CAD Data Exchanges ....................................................................................................... 39 13.1.3 General Preparation of CAD Data .................................................................................... 41 13.1.4 CAD Data Deliveries ......................................................................................................... 41

13.2 Engineering Data......................................................................................................................... 42 13.2.1 EADS Astrium Engineering Data Repository.................................................................... 42 13.2.2 Engineering Data Exchange ............................................................................................. 43

TABLES

Table 13.2-1: Definition of Site names related to file naming convention for data exchange .................. 44 Table 13.2-2: Definition of Type names related to file naming convention for data exchange ................ 44 Table 13.2-3: Definition of Version, Release and Update Number related to file naming convention for

data exchange .................................................................................................................................. 44 Table 13.2-4: Definition of information in electronic format for data exchange between EADS Astrium

and subcontractors ........................................................................................................................... 46

FIGURES

Figure 13.1-1: Flowchart for CAD data exchange.................................................................................... 40 Figure 13.2-1: Overview on Users of Swarm Engineering Database Repository .................................... 42 Figure 13.2-2: Data Exchange Process for Swarm.................................................................................. 43

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 1File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

INTENTIONALLY BLANK

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 2File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

1. INTRODUCTION

1.1 Scope

Together with the equipment specific SOW, this Generic SOW describes the tasks necessary to be performed by the Equipment Subcontractor in the frame of a SWARM equipment supply contract or work order with EADS Astrium GmbH or EADS Astrium Ltd.. In the context of this document, EADS Astrium refers to either EADS Astrium GmbH, or EADS ASTRIUM Ltd. as defined in the contract.

In the context of this document, the term "equipment" shall be interpreted as the product in subject either being

• hardware or

• software or

• a hardware with embedded software or

• services.

The SOW defines the activities from beginning of the contract until equipment contract closure, i.e.:

• The design, development, qualification, production, test and delivery of the equipment hardware and software

• The provision for documentation, data and numerical models, test equipment, tooling and support equipment and transportation as required to support the higher level assembly, integration, and verification

• The provision of equipment related support activities and services as required by EADS Astrium for conduction of the higher level tasks

This generic SOW is amended by an Equipment Specific SOW which considers the essentials of the particular equipment and the special project requirements.

The subcontractor shall be responsible for the provision of all materials, manpower, facilities, supplies, tools, equipment, documentation and support services as may be required to design, manufacture, assemble, test and deliver to EADS Astrium the end products and services as specified in the Statement of Work (SoW) and referred to as the “equipment”.

1.2 Applicability

This Generic SOW is applicable for all flight or ground equipment procured in the SWARM project.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 3File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

2. REFERENCES

2.1 Requirements Tree

This Generic Statement of Work, amended by the Equipment specific Statement of Work defines the tasks to be performed in frame of the Equipment Supply Contract, on basis of the technical and quality requirements.

For illustration, the requirements tree and the order of precedence is shown in the figure below.

Figure: Requirements Tree with Level of Precedence

For SWARM, the General Design and Interface Requirements are included in the Equipment Specification.

2.2 Documents

2.2.1 Applicable Documents

The work defined in this SOW shall be performed in accordance with the requirements contained in the following applicable documents, in their latest issue and revision as agreed with EADS Astrium.

Equipment Specific SOW

For SWARM

Contract (level1)

Generic Equipment SOW

(level3)

- Specific

Equipment

Requirements

-

- General Design

& I/F Req’s

- Equipment PA

Requirements

(level 4b)

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 4File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

The following documents are applicable:

Title Doc. No.

AD 1 Not used

AD 2 Equipment Specification Note 1)

AD 3 SWARM PA Requirements for Subcontractors SW-RS-EAD-PA-0001

AD 4 Software PA Requirements for Subcontractors SW-RS-EAD-PA-0014

AD 5 Management Requirements Document for Subcontractors SW-RS-EAD-SY-0003

AD 6 Document Contents Guidelines for Subcontractors SW-LI-EAD-SY-0005

AD 7 Swarm Engineering Data Repository Development Plan SW-PL-EAD-SY-0019

Notes:

1) as defined in the equipment specific SOW

ECSS standards shall be considered in their latest issues as defined in the Equipment Specification [AD 2], the SWARM Product Assurance Requirements [AD 3], and in the Management Requirements [AD 5] to be Applicable Documents.

2.2.2 Reference Documents

The following documents are referred in the SOW:

Title Doc. No.

RD 1 Swarm General Supporting Information SW-LI-EAD-SY-0004

RD 2

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 5File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

2.3 Abbreviation List Abbreviation Description

ABCL As Build Configuration List

AIT Assemly Integration and Test

AR Acceptance Review

BB Bread Board model

CDR Critical Design Review

CIDL Configuration Item Data List

COTS Commercial Off-the Shelf

DCL Declared Components List

DML Declared Materials List

DOS [US] Department of State

DPA Destructive Parts Analysis

DPL Declared Processes List

DR(B) Delivery Review (Board)

DTC [US] Department of Trade Control

EICD Electrical Interface Control Document

EIDP End Item Data Package

EM Engineering Model

EMC Electro Magnetic Analysis

ESD Electro Static Discharge

EQM Engineering Qualification Model

EQSR Equipment Qualification Status Review

FGSE Fluidic Ground Support Equipment

FM Flight Model

FMECA Failure Mode Effects & Criticality Analysis

FS Flight Spare

GDIR General Design and Interface Requirements

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 6File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Abbreviation Description

GSE Ground Support Equipment

ICD Interface Control Document

ITAR International Traffic in Arms Regulations

KIP Key Inspection Point

MAIV Mechanical Assembly Integration and Verification

MDVE Model-based Development and Verification Environment

MGSE Mechanical Ground Support Equipment

MICD Mechanical Interface Control Document

MIP Mandatory Inspection Point

MD Mechanical Dummy

MPCB Materials & Processes Control Board

MRR Manufacturing Release Review

NCR Non Conformance Report

NRB Non-Conformance Review Board

OGSE Optical Ground Support Equipment

PA Product Assurance

PCB Parts Control Board

PDR Preliminary Design Review

PFM Proto Flight Model

PMP Parts, Materials, and Processes

PSA Parts Stress Analysis

QM Qualification Model

QR Qualification Review

QSR Quality Summary Report

RFD Request for Deviation

RFW Request for Waiver

RID Review Item Discrepancy

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 7File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Abbreviation Description

RoHS Restriction of the use of certain Hazardous Substances

SDB Satellite Data Base

SK Spare Kit

SOW Statement of Work

SVF Software Verification Facility

TAA Technical Assistance Agreement

TC Telecommand

TD Thermal Dummy

TM Telemetry

TR Test Results review

TRB Test Review Board

TRR Test Readiness Review

VCD Verification Control Document

WCA Worst Case Analysis

WEEE Waste of Electrical and Electronic Equipment

For further abbreviations and terms used refer to the Swarm General Supporting Information [RD 1].

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 8File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

3. EQUIPMENT MODEL & CATEGORY DEFINITION

3.1 Equipment Model Definitions

The ECSS Standard ECSS-E-10-02A, Annex B, defines equipment models in general. For SWARM, specific model definitions shall apply as following.

3.1.1 Lot Samples of EEE Components

Samples are required for DPA on each procured part lot as defined in the PA requirements [AD 3].

3.1.2 Technology Samples

Technology samples are not normally deliverable, however EADS Astrium may request manufacturing, test and delivery of the following:

• unused materials and parts,

• witness or coupon samples of painting, adhesive and bonding processes of any critical or new technologies,

• witness of coupon samples for in-process manufacturing control.

Any Technology Sample shall be kept with full traceability during the warranty period, as a minimum.

3.1.3 Breadboard Model (BB)

A BB is functionally and electrically representative of the full equipment or part of it and it is used to validate a new or critical feature of the design. There are no specific requirements for configuration and interface control. BB shall normally not be used to validate software. For deviations approval of EADS Astrium is necessary.

3.1.4 Engineering Model (EM)

An Engineering Model shall be fully representative of Flight Models in form, fit, and functions. A lower standard for electrical components, materials and processes may be used. However, the standard shall be the highest possible achievable within given schedule and cost constraints but using the same manufacturer, the same type and the same package as for the Flight Models. Any redundancies which may be provided in the flight standard model shall be provided in the EM unless otherwise agreed with EADS Astrium. If redundancy is not required, the switching functions associated with redundant functions shall be demonstrated.

EMs are intended to be used for the functional and electrical / EMC performance as well as ground station compatibility verification at higher level. Participation of the EM to the higher level AIT program in combination with flight models has to be considered. Therefore, compatibility to all FM interfaces in

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 9File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

AIT program is required; e.g. gold plated connectors, pins and sockets are necessary. The use of connector savers might conflict with test on higher level and require agreement of EADS Astrium. The Equipment Subcontractor shall apply configuration control and as-build status reporting to EMs. Testing shall be done in accordance with Equipment Subcontractor issued plans approved by EADS Astrium. Test reports shall be prepared and issued.

For particular applications in the higher level AIT, the build status and test requirements may deviate from the above. Any such case is defined in the equipment specific Statement of Work.

3.1.5 Engineering Qualification Model (EQM)

An EQM shall be fully representative of Flight Model in form, fit and functions, i.e. including electrical, thermal, mechanical, optical etc. fidelity. A lower level of electrical components may be used. The standard of these components shall be the highest achievable within the schedule and cost constraints but using the same manufacturer, the same type and the same package as for the Flight Models. However, the selected components shall withstand the environmental loads applied during qualification testing. Only the testing and the screening of the parts might be different compared to the Flight Models. Any and all redundancies which may be provided in a Flight Model shall be provided in the EQM.

The EQM shall be subject to the full equipment level qualification test sequence. Participation of the EQM to the higher level AIT program in combination with flight models has to be considered. Therefore, compatibility to all FM interfaces in AIT program is required; E.g. gold plated connectors, pins and sockets are necessary. The use of connector savers might conflict with test on higher level and require agreement of EADS Astrium. The EQM shall be build to full flight standard in accordance with the PA and configuration management requirements except for EEE parts (see above). Testing shall be done in accordance with Equipment Subcontractors issued plans approved by EADS Astrium. Test reports shall be prepared and issued.

3.1.6 Qualification Model (QM)

A QM shall be built to full flight standard in accordance with the PA requirements for Flight Models. Flight Standard parts shall be used with the same manufacturers, the same types, the same packages and the same level of testing and screening as for the Flight Models.

When it is necessary to demonstrate and qualify the life capability of an equipment subject to wear-out, qualification must be achieved by the life test of a QM.

A QM shall be subject to the full equipment level qualification testing. EADS Astrium shall approve the relevant test plans and reports to establish qualification.

As for the QM hardware (and software, if applicable), the QM test plans, procedures and reports shall be issued and configured.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 10File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

3.1.7 Protoflight Model (PFM)

A PFM shall be built to full flight standard in accordance with the PA requirements for Flight Models. Flight Standard parts shall be used.

Protoflight models shall be subjected to protoflight qualification and acceptance testing. EADS Astrium shall approve the relevant test plans and test reports to establish protoqualification and acceptance for flight.

PFM test plans, procedures and reports shall be issued and configured.

Following successful protoflight model testing, the PFM will be used during protoflight model testing of the satellite protoflight model and shall successfully withstand these environmental tests in order to achieve full qualification.

If more than one of the same standard equipment is required for use on the satellite, only one of these needs to be a PFM unless otherwise specified.

3.1.8 Flight Model (FM)

A FM shall be built to full flight standard in accordance with the PA requirements for Flight Models. Flight Standard parts shall be used.

Flight models shall be subject to flight acceptance testing. EADS Astrium shall approve the relevant test plans and test reports to establish acceptance for flight.

FM test plans, procedures and reports shall be issued and configured.

3.1.9 Flight Spare model (FS)

A FS shall be of the same built standard as the PFM or FM.

An EQM or QM could be used as FS if convenient (e.g. acceptable parts level) after proper refurbishment. The detailed requirements on the FS if applicable, shall be on top of those of EQM and QM respectively and are to be defined in the Equipment Specific SOW.

3.1.10 Spare Kit (SK)

The need for Spare Kits is defined in the Equipment Specific SOW. In general, Spare Kits shall allow for repair of any "random" failure that might occur to the equipment and within a maximum allowable repair time of typically 3 weeks. It shall therefore comprise each of the EEE parts in the maximum number in which it is used on any one board, all boards (unassembled, including Mother Board),, , one connector per type, etc. Any other Long Lead Item or element requiring a procurement period or pre-integration steps being not compliant with the repair time, as well as sub-assemblies or modules which cannot be dis-assembled for repair shall form part of the Spare Kit, too. All these elements are to be separately prepared, regrouped, kitted and stored under consideration of the PA requirements or delivered, in accordance to the Equipment Specific SOW, under consideration of any export licenses if applicable.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 11File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

The spare kit shall be defined individually for the equipment and shall not be mixed with similar parts which are spares of another unit.

All spare parts, components and assemblies procured or manufactured in support of the repair facility shall fulfil all the applicable specifications and be fully interchangeable with the flight part, component or assembly.

Spare parts may not be required for casing, structural, and harness elements.

3.2 Equipment Category Definitions

The use of recurring items (available design from other programmes) and of common items (currently under development in the frame of other programmes) shall be considered wherever possible. The Subcontractor shall demonstrate that all items comply with Swarm requirements. In case the Swarm requirements are more stringent than the original design requirements the Subcontractor shall take the necessary steps to provide compliance (analysis, delta qualification or qualifications as appropriate). The Subcontractor shall monitor any changes, part obsolescence deviations or waivers raised on these items, which could affect the Swarm programme.

With respect to recurrent mechanisms the Subcontractor shall demonstrate that the intended use for Swarm is within the scope of the original application for which these mechanisms have been qualified.

It is the responsibility of the subcontractor to fully justify and demonstrate the qualification of his items and the resulting categorisation.

With this background, the equipment shall be categorised as A, B, C, or D according to the rules defined below.

The Subcontractor shall describe in detail his approach in the Design, Development and Verification Plan. The appropriate workflow per category as outlined in section 4 below shall be used as guideline.

3.2.1 Fully Recurring Equipment - Category A

Equipment which is fully identical to one already qualified for comparable mission environmental requirements, with no changes in design, manufacturing, materials, parts, processes. The qualification test programme in heritage shall be at least as severe as that imposed by that of SWARM.

The demonstration of the validity of the equipment definition has to be provided by a detailed qualification status list/report.

3.2.2 Recurring Equipment with Limited Changes - Category B

Recurring equipment with no modifications that was already tested and qualified but subjected to less severe qualification programme or to a different environment.

Minor modifications to the existing design or applied processes, either in design, manufacturing, materials, parts which do not significantly invalidate the existing qualification are allowable.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 12File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Delta design and/or delta qualification are needed and shall be agreed on a case-by-case basis.

Re-classification to Category C shall be possible on the basis of the EQSR.

3.2.3 Modified Equipment - Category C

Equipment similar to one already qualified or flown, with major or significant changes in design, manufacturing, materials, parts, processes. Formal design reviews and a delta or full qualification programme are needed. They shall be decided on a case-by-case basis.

3.2.4 New Equipment - Category D

Newly designed and developed equipment. A full qualification test programme shall be imposed.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 13File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

4. WORKFLOW

This chapter defines the logical flow of work to be performed on equipment along the required reviews, dependant on its category as defined in Section 3 above.

The subcontractor is encouraged

• to optimize the review sequence in order to consider the schedule necessities of SWARM and to improve the production flow of his deliverable models, but without increasing the risk nor invalidating the need of full qualification,

• to propose combined reviews as far as reasonable and efficient, pending agreement of EADS Astrium (e.g. EQSR combined with Kick-off or MRR).

4.1 Fully Recurring Equipment - Category A

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 14File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

4.2 Recurring Equipment with Limited Changes - Category B

Note: PFM TRB, DRB, and QR may be combined

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 15File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

4.3 Modified Equipment - Category C

START SUPPLYCONTRACT

KICK-OFFREVIEW

Equipment Functional Baselineapproved

Equipment Requirements

Vendor Proposal

PDR

CDR

Equipment Requirements

Preliminary Design Data Package

Equipment Requirements

Detailed Design Data Package

Equipment Development Baselineapproved

Equipment Design/QualificationBaseline approved for

EQM, QM & PFM Production

(E)QMMRR

(E)QMTRR

(E)QMTRB

PFMMRR

PFMTRR

PFMTRB

PFMDRB

QREquipment Requirements

Full Product documentation

Equipment Production Baselineapproved for Flight Model

Production

FM MRR

FM TRR

FM TRB

FM DRB

MODIFIEDEQUIPMENT

EQSREquipment Requirements& available Data Package

Equipment DevelopmentBaseline provisionally approved(PDR needed, or approved (no

PDR)

Note: the qualification can be done on an EQM, QM, or PFM, whatever is appropriate for the equipment / instrument.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 16File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

4.4 New Equipment - Category D

Note: the qualification can be done on an EQM, QM, or PFM, whatever is appropriate for the equipment / instrument.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 17File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5. REVIEWS AND BOARDS DEFINITION

Reviews and boards will be held for control and guidance of all project activities at Equipment Subcontractor. The reviews/boards will be chaired by EADS Astrium. The relevant documentation shall be reviewed before the review meeting. Comments shall be given to the Subcontractor in advance to the meeting as far as possible. The review meeting can either be held at Subcontractor's premises or via tele/videoconference. Due to the evidence of project transparency, ESA will be invited by EADS Astrium to share the review.

Due to its significance in terms of risk, the Design Review organisation is of more formal type and described in the corresponding chapter below.

5.1 Reviews

5.1.1 Kick-Off Review

The purpose of the Kick-Off Review is to address all questions left open regarding EADS Astrium requirements or the Subcontractor proposal. The contractual baseline, including design and development, performance, verification and delivery shall be confirmed. The declaration of the review success by EADS Astrium gives the go-ahead for the activities to be defined during the Kick-off Review.

5.1.2 Equipment Qualification Status Review (EQSR)

The EQSR generally do not apply to equipment falling into the category D, “New Equipment”. The purpose of the EQSR is to formally review the design standard, build standard, configuration, and qualification status of the equipment against the programme requirements. The maturity of the equipment design, compatibility with equipment interfaces and its ability to satisfy the performance requirements placed on it shall be formally acknowledged.

The qualification status of all parts, materials and processes used in the manufacturing of the equipment shall be presented and reviewed as part of the EQSR. Evidence of equipment qualification tests from other programmes, this being at equipment, sub-assembly, components/parts, and software level, shall be given as appropriate. The review shall also establish the adequacy of the test plan and test procedures of flight equipment.

The main outputs of the EQSR are the confirmation or change of the equipment category as proposed by the subcontractor and the decision upon the development and qualification plan and models in the case of modified equipment design or build standard.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 18File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5.1.3 Design Reviews

5.1.3.1 Preliminary Design Review (PDR)

A PDR is generally not needed for recurring equipment (Category A) and usually not needed for equipment with limited modifications in design, build or environment (Category B).

The purpose of the PDR is to formally agree the preliminary design of the equipment. The selected design concept and its feasibility shall be presented, together with the trade-off analyses performed in the design selection process. External interfaces of the equipment shall be reviewed for compatibility with the system design and frozen at that stage. A successful PDR means that the equipment development baseline is agreed and satisfies the functional baseline requirements, and that detailed design is authorised. If any aspect of this review is considered unacceptable a close-out process shall be followed to concur on an agreed development baseline.

5.1.3.2 Critical Design Review (CDR)

A CDR is generally not needed for recurring equipment (Category A) and for equipment with limited modifications in design, build or environment (Category B).

The purpose of the CDR is to formally agree the detailed design of the equipment. It verifies the compatibility of equipment interfaces and compliance of the detailed design with the performance requirements, and establishes the adequacy of plans and preparations for manufacture and test of flight equipment. The supporting analyses which form part of the Design Review Data Package are reviewed at the CDR. A successful CDR means that the equipment design baseline is agreed on the basis of the detailed design documentation reviewed and approved at the CDR.

5.1.3.3 Design Review Organisation

Design Review meetings shall be held at the subcontractor's premises where the work is normally performed, unless agreement is obtained from EADS Astrium for an alternative location.

• 15 working days prior this meeting, a complete Data Package shall be received by EADS Astrium. This time period could be extended based on the complexity of the equipment, and in the case of a review of this Data Package by ESA. Thus, the 15 days lead time need to be confirmed by EADS Astrium case-by-case.

• EADS Astrium review the Data Package and provide comments written on Review Item Discrepancies (RID). As a goal, the RIDs from EADS Astrium and its customer ESA (if any) will be sent to the subcontractor as far as possible 10 working days after reception of the Data Package. The subcontractor shall be prepared to accept further RIDs during the subject review meeting.

• The subcontractor shall answer to each RID . Responses to the RIDs received before the review meeting shall be provided to EADS Astrium 5 working days after RIDs reception, but not later than during the review meeting.

• A Design Review meeting shall be held under the control of the EADS Astrium chairman. Minutes shall be written by EADS Astrium, identifying all the conclusions and

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 19File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

recommendations. EADS Astrium shall identify which of the action items must be completed before the review can be considered successfully completed.

• The review shall be considered successful after EADS Astrium agreement on the closure of the here-above major action items. In this case, the Astrium chairman formally closes the review.

5.1.4 Manufacturing Readiness Review (MRR)

The purpose of the MRR is to verify that all activities necessary prior to the start of manufacture of qualification, protoflight or flight models are complete and all the necessary documentation and resources are in place to enable manufacture to commence. If some activities are not completed at the time of the MRR, it is part of the review to assess the open issues and to decide if manufacturing may commence concurrently to the closure of the open issue action items.

5.1.5 Qualification Review (QR)

The purpose of the QR is to formally review the qualification and/or delta-qualification test results and to demonstrate the qualification of the equipment. Life tests shall be completed before the QR, whenever practicable. When it is not practicable, provisional qualification may be granted subject to life test results. In addition, all qualification activities of parts, processes and materials as required by PCB or MPCB shall be completed satisfactorily at the QR to grant full qualification status.

5.1.6 Test Readiness Review (TRR)

The purpose of the TRR is to review the readiness of the equipment to be tested, and the readiness of test documentation, test procedures, test programmes, test software, test facilities and test personnel. TRR shall be held before performing acceptance, qualification, protoflight and environmental tests on the equipment or batch of equipment as agreed with EADS Astrium.

The Subcontractor shall have an established process whereby designated personnel certify that the test item, equipment, protective devices, cabling, procedures and supporting documentation have been reviewed and found to be complete and adequate prior to the application of power and initiation of environmental testing.

5.1.7 Test Review (TR, or Test Review Board, TRB)

The purpose of the TR, or frequently called TRB, is to summarise the Subcontractors analysis on the test results, and in the case of NCRs to decide which actions have to be taken.

EADS Astrium shall be provided with a complete set of the test data to be reviewed in sufficient time in advance to the TR.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 20File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5.1.8 Delivery Review (DR, or Delivery Review Board, DRB)

The purpose of the DR, or frequently called DRB, after satisfactory completion of all tests and inspections is to verify:

• That the equipment and all deliverables satisfy all contractual requirements

• That the EIDP is a complete and accurate history of the equipment

• That all non-conformances and concessions have been satisfactorily closed and there are no outstanding actions

• The hardware status through a visual inspection of the equipment, its container and the associated tooling whenever applicable

• The packing, packaging, adequate configuration and protection of the equipment for shipment

• The release of shipment after successful DR.

All actions still open at the time of delivery shall be closed through formal close-out agreed by EADS Astrium in order to close the DR.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 21File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5.2 Boards

5.2.1 Parts Control Board (PCB)

The selection of EEE parts and their usage approval for the Equipment are implemented through Part Control Boards (PCBs) chaired by the EEE Parts Manager representing the SWARM Product Assurance of EADS Astrium and held with the Subcontractor.

The PCB is put under EADS Astrium Product Assurance control and may be composed by designer, system representative, any other experts (radiations, assembly, …) from both EADS Astrium and the Subcontractor. ESA representative may also use the right to participate as a PCB member.

Depending on the progress of the Equipment Purchase, the main PCB activities are :

• Review and approval of the Subcontractor's EEE parts management plan and any associated document

• Parts approval including evaluation activities (by means of Subcontractor DCL)

• Purchase status (including schedule, dispatching, delivery schedule) ,

• Problem resolution (non conformances, RFD, RFW, ...).

5.2.2 Materials & Processes Control Board (MPCB)

Materials and Processes shall preferably be selected from a valid Materials/Processes List of a recognised authority (CNES, ESA, NASA, MIL, etc…) or from previously flown space hardware. For each equipment a declared materials list, including mechanical parts (DML) and a declared processes list (DPL) is kept up to date during development and manufacturing until delivery.

The Subcontractor shall notify to EADS Astrium as early as possible intended the use of new or unproven materials/processes, together with proposed testing and analysis, and the subsequent update of the DML/DPL.

A Materials & Processes Control Board (MPCB) shall be established between EADS Astrium and with support from Subcontractors’ representatives from design, technology, inspection, test, manufacturing, and product assurance. ESA has the right to participate in the MPCB process. The MPCB shall:

• Evaluate and approve the DML and DPL

• Ensure that PMP management is conducted in accordance with the project requirements.

• Ensure that PMP implementation is performed in accordance with design and manufacturing documents (mandatory inspection points and key inspection points) and to request audits and/or technical reviews where considered necessary.

• Support investigations to resolve PMP non-conformances.

Non qualified materials/processes or open MPCB actions might have major schedule impacts on equipment manufacturing.

Where deemed necessary a MPCB meeting may be convened.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 22File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

5.2.3 Non-Conformance Review Board (NRB)

During the NRB meeting, the following points are presented and reviewed :

• the detailed circumstances of the non conformance

• the different analyses, tests or simulations performed to understand the cause of the non conformance

• the consequences of the non conformance the Subcontractors’ investigations results

For Major NCR's, the EADS Astrium Product Assurance shall ensure with the active support of the Subcontractor the determination of corrective actions to eliminate the cause(s) of the non conformance and prevent any recurrence. Typical corrective actions consist of changes to tools, equipment, facilities, processes, materials, drawings, specifications, procedures, etc.

For Minor NCR's the above responsibility remains with the Subcontractor's PA. EADS Astrium is to be informed about the existence of such NCR, the progress, and the close-out with a right to re-classify to Major NCR or to veto the corrective action or the close-out.

The NRB determines also preventive actions to avoid the occurrence of the non conformance on similar items, as appropriate.

The NCR is closed-out only after :

• All related actions have been performed and their results successfully verified.

• All necessary inspections and tests have been performed, and their results verified and reported on or traceable from the NCR.

• Related RFWs are approved.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 23File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

6. MANAGEMENT REQUIREMENTS

The Subcontractor shall perform the work in line with management requirements specified in the Management Requirements Specification [AD 5].

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 24File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

7. PRODUCT ASSURANCE REQUIREMENTS

The Subcontractor shall perform the work in line with PA Requirements specified in the PA Requirements Specification [AD 3].

Any software developed or re-used for the deliverable items shall respect the Software PA Requirements [AD 4].

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 25File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

8. ENGINEERING REQUIREMENTS

8.1 General

The Equipment Subcontractor shall co-ordinate all technical activities and the interfaces between the different disciplines involved and shall manage the technical and commercial interfaces to EADS Astrium and to the lower tier subcontractors and suppliers.

He shall analyse all requirements imposed by the applicable documents and shall derive/analyse respective means to maintain compliance to the specification or propose a well founded other alternative with minor impact on the compliance status to EADS Astrium.

If necessary the Equipment Subcontractor shall establish and maintain requirement specifications for the lower level configuration items.

8.2 Equipment Design

The Equipment Subcontractor shall perform all design activities necessary to define the equipment under his responsibility such that it meets all applicable requirements.

In case the equipment includes a controller with software, the software development shall ensure that the development process is performed in accordance with the SW PA Requirements [AD 4] and the relevant ECSS referred to therein.

Company internal software development standards shall be compared to the above mentioned documents via compliance matrix. The acceptance of company internal standards is subject to approval by EADS Astrium.

8.3 Interfaces

The Equipment Subcontractor shall perform interface engineering, design and manufacturing to assure the compatibility and coherence of all physical and operational interfaces of the Subcontractor's equipment.

The interface engineering between spacecraft system and Subcontractor equipment will be performed by EADS Astrium. The Subcontractor shall review, complement and comment on the spacecraft ICDs and finally confirm the interfaces related to his equipment by signature. For this purpose, the Subcontractor shall issue an Interface Control Document for his equipment.

After approval of the ICD by EADS Astrium this issue is binding for the Subcontractor. Any change needs the approval of EADS Astrium.

EADS Astrium reserves the right to define and provide machine readable formats like EXCEL tables of XML (e.g. for harness data). Then the subcontractor shall migrate, maintain and deliver interface data

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 26File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

in this format. For the task of interface data exchange, the Subcontractor shall obey conventions and rules given by EADS Astrium.

Appendix B provides an overview on the interface data and required formats. More specific requirements are specified in the equipment specific SoW.

8.4 Operations

The Equipment Subcontractor shall investigate the operation and control of the equipment in relation to the satellite operations and control.

He shall generate and maintain a User Manual for his equipment (derived from ECSS-E-70, Part 2, equipment user manual content). As part of the User Manual, he shall develop flight operations procedures for his equipment. The flight operation procedure steps shall use correct references to the TM/TC definitions.

In case the Subcontractor delivers equipment which is either a PUS packet terminal for the on-board data handling or non-PUS terminal equipments which can submit telemetry and receive telecommands (provide a data interface), EADS Astrium will provide an empty TM/TC Database (in MS Access 2003 format tbc.). The definition of the database and its user manual will be provided in a set of documents (e.g. Satellite Database ICD, SDB). The applicability for which equipment type which tables in the TM/TC database are to be populated is defined in [AD 7] SW-PL-EAD-SY-0019, Swarm Engineering Data Repository Development Plan. The subcontractor shall migrate, maintain and deliver the database with the telemetry and telecommand data for his equipment in accordance with the Packet Utilization Standard and the Satellite Database ICD.

8.5 Analyses

The Equipment Subcontractor shall perform all analyses (e.g. thermal, structural, radiation, RAMS, electrical) necessary to properly design, manufacture and verify the items under his responsibility wrt the requirements made applicable in this SOW. The analyses shall at least encompass but not be limited to the analyses explicitly required in the SOW.

The mathematical models and the necessary software tools shall be established by the Equipment Subcontractor unless commercially available. The analyses results, the tools and the math models shall be described.

Tools and models developed under the contract shall be delivered to EADS Astrium. In case the model is used during operations and/or check-out on spacecraft level an adequate manual shall be provided.

The analyses shall be performed / updated in accordance with the design progress of the equipment and its lower level items. The analyses shall be described in a self standing way to allow an effective review and understanding.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 27File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

8.6 Verification Task

The Equipment Subcontractor shall demonstrate that:

• the design conforms to the requirements (qualification)

• the flight hardware and software complies to the qualified design, is free of workmanship errors and is fully functional (acceptance)

• The requirements to be verified are identified in the applicable specifications by a unique requirements numbers.

The verification of the requirements shall be performed on equipment level, wherever possible. Verification on lower level is permitted. Higher level verification needs approval by EADS Astrium.

The Subcontractor shall maintain a Verification Control Document (VCD) which lists all applicable requirements and the correlated verification activities.

More specific verification tasks, e.g. for software, are covered by the Specific SoW.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 28File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

9. EXPORT CONTROL REQUIREMENTS

9.1 General

The Equipment Subcontractor shall be responsible for ensuring compliance with all Export Control Requirements of the European Union and the United States of America regarding exportation or re-exportation of the goods and/or materials which are the subject of the present contract from EADS Astrium. In order to achieve this, the Subcontractor shall be responsible for obtaining the following tasks:

• Identify whether your product is listed in the EU Export Control List and/or whether a national export license from your government is necessary and available or not and inform EADS Astrium accordingly.

• Identify US-ITAR and US-EAR parts in your equipment and prove compliance with the existing US re-export law.

• Identify TAA's (Technical Assistance Agreements)

• Provide copies of all licenses and TAA's identified above.

• Certify your right to export your equipment to EADS Astrium GmbH (and to EADS Astrium Ltd if applicable), which (in case of US-licenses) also allows EADS Astrium to re-export the equipment to other intermediate consignees and to the end user ESA as destination and the launch site.

9.2 EU Export Control Requirements

Concerning the export /re-export regulations of the subcontractor's country, the subcontractor has to follow the rules of its government and/or the regulations of the EU.

9.3 Direct “US Supplier”

When the Subcontractor to EADS Astrium is a “Direct US Supplier”, the following provisions shall apply between EADS Astrium and the Subcontractor:

9.3.1 Inputs from EADS Astrium to Support Subcontractor's Application

• EADS Astrium cover letter

• DSP-83 (for agreements or an export licence for classified 'defence articles')

• EADS Astrium control plan, if available

• EADS Astrium accountability plan (for DSP-5 export licence only)

• Minutes of meetings, if any to the subject

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 29File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

• EADS Astrium information and requirements related to the agreement

9.3.2 Description of Subcontractor's Responsibilities

To draft the documentation that has to be prepared to make the application to the DOS;

To take into account in the documentation the information that EADS Astrium has transmitted via the cover letter, the DSP-83 (for agreements or an export of classified 'defence articles) and associated documents;

To inform EADS Astrium about any omission in the submitted cover letter and / or missing document and not to venture any input as a replacement for a missing information;

To send the drafted relevant documentation to EADS Astrium for internal review before submission to the DOS;

To inform EADS Astrium about the status of the application (preparation, submission, staffing, authorisation, provisos…);

To pass on to EADS Astrium the DOS authorisation (i.e. the DTC original case number (for agreements) or the licence number (for DSP-5 licence) , the text of the authorisation and provisos);

According to the ITAR regulation, to do the identification of the hardware, software, technical data and information which are exported in the frame of the authorised agreement or export licence.

9.3.3 Outputs from Subcontractor

Drafted documentation including final issue that is submitted to the DOS;

TAA or Distribution Agreement as agreed with EADS Astrium, submitted to the DOS authorisation and countersigned by both parties after DOS approval when applicable;

DSP-5 submitted to the DOS authorisation when applicable;

DTC original case number and licence number;

Copy of the DOS authorisation, including provisos;

Technical data and information identified as 'defence articles' as required by the ITAR rules;

H/W, S/W and relevant documentation (EIDP, etc) identified as 'ITAR controlled' as required by DOS.

9.4 Requirements for Lower Tiers ‘’US Suppliers’’

When the Subcontractor to EADS Astrium is not a “Direct US Supplier” but cooperates with US Suppliers as Lower Tiers Suppliers, the requirements of paragraph 9.3 shall be applied between the Subcontractor and its “Direct US Suppliers” and at any level between a Lower Tiers Supplier and its “Direct US Supplier”, with all references to “EADS Astrium” changed to refer to the Subcontractor or EADS Astrium.

In addition, the subcontractor to EADS Astrium shall:

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 30File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

• Advise the DTC original case number(s) and licence number(s) to EADS Astrium;

• Provide copy(ies) of the DOS authorisation(s), including provisos, to EADS Astrium;

• Provide a copy of his own control plan, to EADS Astrium;

• Ensure that all 'technical data and information' passed on to EADS Astrium or that all data and information supplied to EADS Astrium which incorporates such 'technical data and information' are identified as 'defence articles' as required by the ITAR rules;

• Ensure that all 'H/W, S/W and relevant documentation (EIDP, etc)' passed on to EADS Astrium or that all hardware, software and documentation incorporating any items subject to such ITAR control, are identified as 'ITAR controlled' as required by DOS.

• Flow down all the provisions of Paragraph 9.3 and above mutatis mutandis to each of his lower tier Suppliers, down to the lowest tier of supply contract, unless otherwise agreed with EADS Astrium. Hence, the Subcontractor shall ensure that the relevant data is provided to him by these lower tier Suppliers, and passed up to EADS Astrium..

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 31File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

10. MANUFACTURING & TEST REQUIREMENTS

10.1 Introduction

The applicability of this section depends on design and development heritage and the according categorisation of the equipment. Compliance to the tasks and documentation required in this section may be established by reference to precursor projects. In any such case the subcontractor shall provide the evidence of his compliance to the SOW.

10.2 Manufacturing and Production

The subcontractor shall maintain adequate facilities and personnel resources to sustain manufacturing, assembly, testing, handling and transportation of hardware at all levels during the programme in compliance with programme schedules. He shall ensure that the standards of in-house and subcontracted manufacture are compatible with the requirements set forth in the PA Requirements.

The subcontractor shall ensure that adequate documentation is available prior to start of any hardware manufacture to describe all manufacturing processes, flow diagrams, planning, process control, material application data, personnel, and facility certification.

The above shall be applied to production of software items mutatis mutandis.

In line with the PA Requirements [AD 3], all relevant process steps shall be recorded in the Equipment Log Book.

10.3 Assembly Integration and Verification

10.3.1 MAIV Planning

The subcontractor shall generate, maintain and implement the MAIV Planning, defining all the activities necessary to achieve the complete equipment manufacturing, integration, and verification of his product. For simplification, this planning can be presented as part of the Design, Development, and Verification Plan.

10.3.2 General Test Requirements

The subcontractor shall carry out all development, qualification and acceptance testing in accordance with the approved Verification Plan, and any additional testing necessary to demonstrate the performance requirements are met.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 32File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Equipment level testing intended for formal close-out of requirements shall be performed in a flight representative configuration (i.e. flight hardware and software, flight interfaces) to the maximum extend possible. This request shall also be applied to any removable extensions (e.g. PROMs).

In general and as far as feasible the subcontractor shall test on the highest integration level under his control.

10.3.3 Life Tests

Equipments which are susceptible to wear, degradation, fatigue, or creep during their projected lifetime (including time for fabrication, storage, ground testing and flight) shall be subjected to life tests, under conditions representative of their intended usage.

Life tests shall be conducted on an accelerated basis to the maximum extent possible, considering the dominant degradation factor (e.g. actuation for mechanical actuators).

Each equipment submitted to an accelerated life test shall demonstrate an adequate margin to be agreed on a case by case basis according to the applicable standards. It is desirable that the life test proceeds beyond that limit to the maximum extent practical in order to provide additional assurance of the design margins.

Accelerated or real tests are considered as part of the qualification programme and as such shall be conducted on after environmental qualification tests.

Following life testing, all equipment tested shall be disassembled and examined for any abnormality or trends in degradation, and EADS Astrium informed of the results.

Life test reporting may be provided to cover equipment which have been life tested on previous flight programmes.

No life test sample (e.g. EEE parts, boards, units) shall be used for flight applications.

10.3.4 Test Failure

Any failure during tests shall be reported verbally or by e-mail without delay (in advance to the formal issue of the related NCR).

Any failure during qualification and acceptance tests as well as any failure of qualification models, prototype models and flight models (as applicable) during the warranty period, shall be analyzed by the subcontractor and a copy of this failure analysis report including corrective actions shall be provided by the subcontractor.

Retro-fit of deliverable Breadboard or Engineering Models: In case of failures or weaknesses causing a modification of the flight models (PFM and FM), deliverable Breadboard Models or Engineering Models shall be reworked by the subcontractor on his own cost to avoid differences between the flight equipment and their equivalents for ground tests.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 33File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

10.3.5 Verification Control

The equipment specification is available in the EADS Astrium DOORS database, thus giving to each requirement a unique identifier. These identifiers shall be used for tracking of the verification planning, execution and reporting on the level of individual requirements.

The subcontractor shall define the verification method as well as an appropriate assignment of the verification level per requirement (with a preliminary definition included in his proposal).

For verification against a requirement the following methods are allowed:

• Test T

• Analysis A

• Review of Design R

• Inspection I

Generally, the verification of equipment requirements shall be performed on equipment level. This may be delegated to lower level pending approval of EADS Astrium.

The subcontractor shall maintain a Verification Control Document (VCD) which lists all applicable requirements and the correlated verification activities in particular the methods and integration level on which verification will be performed.

The VCD shall cover the qualification and the acceptance program.

The verification control document shall preferably be maintained using DOORS in accordance to the instructions and conventions for DOORS usage in the project, which will be provided by EADS Astrium. If verification close out is intended on lower level, the corresponding lower level specifications shall also be prepared, and the verification planning and tracking made using DOORS, preferably.

In case that the Subcontractor cannot work with DOORS, he is requested to propose an alternative, electronic format. However, any alternative format requires agreement of EADS Astrium.

This is required to enable a tracing of requirements and their verification close out down to lower then the equipment level. The VCD shall be provided to each major review and be part of the End Item Data Packages.

The Verification Matrix shall be frozen and mutually agreed by the Subcontractor and the EADS Astrium by CDR.

The Subcontractor shall demonstrate by AR that the verification of each requirement has been successfully completed. He shall do this by means of the Verification Control Document.

The Verification Programme shall comply with the Swarm PA Requirements [AD 3] and Software PA Requirements [AD 4].

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 34File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

10.4 Ground Support Equipment

The subcontractor shall be responsible for the provision, maintenance, calibration and validation of all the necessary test equipment (e.g. electrical, mechanical, optical, thermal, fluidic, software) for manufacture and test of the deliverable equipments.

All test fixtures and facilities shall be calibrated and validated. Validation routines shall be configured and the results shall be stored at the Subcontractor plant against any test related investigations.

The equipment GSE may be subdivided into two categories: deliverable GSE for use in the higher level AIT programme and launch campaign, and non deliverable GSE needed for the sole purpose of the equipment AIT. The number of models of each type of GSE shall be in accordance with the deliverable items list and the utilisation for equipment AIT.

Besides the safety and liability requirements defined by applicable laws, the deliverable GSE shall comply with the requirements presented in the equipment specification, with the PA and Safety requirements being part of the PA Requirements Specification [AD 3], as well as with the design implementation requirements for EGSE, OGSE, MGSE, TGSE, and FGSE. Formal verification control as defined in previous section shall be applied also to GSE requirements, as a minimum to those requirements affecting safety and flight interfaces. In order to limit the effort for GSE verification in a “stand alone” configuration, the verification “by use” may be an acceptable method for all deliverable GSE that is used also for equipment level AIT.

In case of deliverable GSE, the equipment shall be delivered with all the necessary documentation required for the operation and for the maintenance of the GSE.

The design of equipment GSE to be delivered to higher level AIT shall be validated by use in the frame of equipment AIT. According warranty agreements shall be closed with vendors of COTS equipment included in the GSE.

The subcontractor shall ensure that the deliverable GSE is able to fulfil its requirements and is correctly and sufficiently documented. The subcontractor shall ensure that maintainability requirements are fulfilled and define a maintenance plan.

GSE which is not a deliverable item to EADS Astrium may be constituted from the subcontractor's or his lower level supplier's inventory of laboratory and test equipment. In any such case, the GSE shall be kept available to SWARM and operational throughout the warranty period or latest until lift-off of all SWARM spacecraft.

The subcontractor shall ensure that these GSE and related documentation, manuals and software are subject to configuration management and control.

WEEE - Waste Electrical and Electronic Equipment /

RoHS - Restriction on the use of certain Hazardous Substances:

The subcontractor guarantees the compliance with EC WEEE directive 2002/96/EC and RoHS directive 2002/95/EC and their respective implementations into national laws. Therefore, inter alia, the subcontractor will take back the supplied electric- and electronic equipment after end of their livetime according to these rules without charge to EADS Astrium.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 35File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

CE (Declaration of Conformity):

The subcontractor shall ensure that the delivered GSE is "CE marked" to indicate the compliance with the applicable EU New Approach Directive (98/34/EC and 98/48/EC), irrespective of the GSE sites of usage.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 36File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

11. SUPPORT TASKS

11.1 Introduction

In order to be able to provide technical support after delivery of the equipment the subcontractor shall ensure that technically qualified and project experienced personnel can be made available to support the activities at higher level. This shall cover the period between equipment delivery up to lift-off of all SWARM spacecraft.

Furthermore if the project should foresee a storage period before launch, then the constraints of this storage shall be considered and the equipment needed for retest and possible repair kept in working order by the subcontractor until notice has been made that this is no longer required.

11.2 Support to Higher Level Reviews

The subcontractor shall support reviews at higher level by preparation of presentation material for the perimeter of his equipment and by personnel attendance if required to treat equipment related topics at higher level reviews.

11.3 Support to AIV at Higher Level

11.3.1 EGSE Operation Support

For each of the equipment EGSE to be used at higher level, the subcontractor shall provide support as follows:

On site support to equipment integration with other EGSE elements and the flight equipment to be provided for the first EGSE model of each type to be delivered (estimate duration several days)

• user teaching and training sessions based on the subcontractors estimated effort

• fast maintenance / repair service on a time and material basis (when not covered by warranty), including:

o 24 hour response time for fast trouble shooting and first aid advice to the check-out team (weekends to be included during critical test periods)

o Replacement/repair service for commercial equipment to guarantee a minimum equipment outage of not more than 48 hours

• regular maintenance / calibration up to launch (or longer if required for mission support) for both commercial equipment and own production

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 37File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

11.3.2 Integration and Test Support

The subcontractor shall support the integration and test of the equipment at higher level by the following activities:

• Assistance to the integration and operation commissioning on the satellite/ subsystem.

• Assistance to satellite/ subsystem related special function and performance tests

The subcontractor shall commit to providing further support on time and material cost basis (when not covered by warranty), including in particular 24 hour response time for fast trouble shooting and first aid advice to the satellite AIV team for all models (weekends to be included during critical test periods)

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 38File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

12. APPENDIX A DOCUMENTATION REQUIREMENTS LIST

The set of documents required to be delivered is defined in the Specific SoW.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 39File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

13. APPENDIX B INTERFACE DATA REQUIREMENTS

13.1 Computer Aided Drawing and Design (CAD) data

13.1.1 EADS Astrium CAD system

Note: As the Swarm configuration is under control of EADS Astrium Ltd. The CAD data have to be compliant with their system.

The EADS Astrium standard CAD system is: CATIA© version CATIA V5.14.4 (English) Any change will be notified by EADS Astrium and impacts reviewed with the Supplier.

13.1.2 CAD Data Exchanges

For accommodation or analysis purpose, CAD models shall be provided for every equipment to be delivered to EADS Astrium. The standard format, for CATIA© data exchanges between the Supplier and EADS Astrium is the CATIA© version format, native or catexport.

Should the Supplier use another CAD tool system, the Supplier shall be responsible for performing and guaranteeing the conversion into the EADS Astrium CATIA© version data format.

The level of detail / degree of complexity of the deliverable CAD models shall be discussed and agreed with EADS Astrium so that the file size is not unnecessarily big.

The rules shall be defined and be confirmed by both sides in a written form. The data exchange agreement (DEA) shall at least contain/define:

◊ Kind of data exchanged

◊ rules for the structure, naming and numbering of the files

◊ A reference to this document to define the general requirements for data transfer

◊ The data quality (volumes or solids with history / structure of models / max. filesize)

◊ Procedure for the control / acceptance of the data

◊ The type of transfer (CD / FTP)

Figure 13.1-1 shows a typical flowchart for the data transfer process.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 40File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Figure 13.1-1: Flowchart for CAD data exchange

A general test of the data exchange process shall take place BEFORE the main project work starts!

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 41File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

13.1.3 General Preparation of CAD Data

To minimize the effort of dealing with the exchanged data, the following topics shall be regarded before the transfer:

◊ delete all unnecessary geometry (e. g. hidden parts, standard parts, parts inside a box, when the

◊ box is needed for clash detection only)

◊ delete all supporting elements where possible (e. g. wireframes for 3D geometry)

◊ all geometry / drawings must be updated

◊ all links to local libraries / catalogs must be eliminated

◊ Country specific characters like ß, Ä or â are not allowed for any text or description (2D and 3D)

◊ Special characters in the file names are not allowed. In order to stay compatible with Unix and Windows OSs, only the following have to be used:

Characters A…Z, a…z

Numbers: 0…9

Symbols: _ (underscore), - (minus sign)

For more details on the CAD models and associated level of refining required per type of equipment, the Supplier shall refer to the equipment specific SOW.

13.1.4 CAD Data Deliveries

The CAD models to be delivered to EADS Astrium are overall configuration information only, i.e. similar to the I/F information to be given in the ICD.

Finite Element Models and/or Thermal Mathematical Models may be required in addition.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 42File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

13.2 Engineering Data

13.2.1 EADS Astrium Engineering Data Repository

The EADS Astrium Swarm Engineering Data Repository comprises the needs for information of various engineering disciplines in order to develop and test the Swarm satellites.

Figure 13.2-1 depicts the users which are linked to the Swarm Engineering Data Repository. This repository consists of various dedicated database or information in electronic format. The required data or information is indicated at the links between the user and the repository.

The following section will provide a definition on how these data shall be provided from equipment / unit suppliers to EADS Astrium Swarm prime team but excluding CAD Model which is described in section 13.1 .

SwarmEngineering Data

Repository Electrical ArchitectureElectrical InterfacesGrounding DiagramHarness to Pin AllocationsAssembly Constraints (w.r.t EMC & Harness)EMC PropertiesMagnetic Properties

Telemetry & TelecommandsUser Manual (Functions, Modes)Flight Operations

Contact SurfaceHeat fluxPower dissipation vs. equipment modesThermal Mathematical Models orFinite Element Models

Telemetry & TelecommandsUser Manual (Functions & Modes)Flight OperationsCAD ModelInterface Description & DrawingsAssembly Drawings

Telemetry & TelecommandsUser Manual (Functions, Modes)Flight Operations (incl. Safe Mode)Simulation Models

Mass & Mass Properties (CoG, MoI)VolumeAssembly DrawingsAssembly ConstraintsCAD ModelFinite Element Models

AIT Engineering

Operations Engineering

Electrical EngineeringThermal Engineering

AOCS Engineering

Mechanical Engineering

Figure 13.2-1: Overview on Users of Swarm Engineering Database Repository

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 43File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

13.2.2 Engineering Data Exchange

This section describes the required data and data format and the process in order to exchange the data between supplier to the Swarm Prime at EADS Astrium.

Locally at each site where parts of the data of the Swarm Engineering Data Repository are generated, the relevant but identical part of the Swarm Engineering Data Repository shall be established. For instance the Swarm Satellite Database (S-SDB) shall be established at On-Board Software subcontractor and at EADS Astrium level to support a proper definition, verification and exchange of the relevant data.

Therefore the delivery of any data shall be according the following process depicted in Figure 13.2-2.

Prepare Data

Verify Data

Notice of transfer of Data

Notice of receipt of Data

Verify Data

Notice of Acceptance

Exchange Standardsin Data Format

Agree onData format & transfer

N

Selected Transfer Media

Sender

Receiver

Precondition !

Figure 13.2-2: Data Exchange Process for Swarm

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 44File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

This means the subcontractor prepares & verifies the data in a defined format for the data

for a defined data transfer media.

according Swarm project naming conventions (e.g. for S-SDB telecommand and telemetry descriptions)

in a defined format for filenames to indicate where the data has been populated

nnnn_XXXX_V_x_y_z

C the Central (=Master) SDBOPS generated by Operations Team at PrimeOBSW deliveries from OBC S/W contractorACC deliveries from ACC contractorASM deliveries from ASM contractorEFI deliveries from EFI contractor

nnnn Name GPS deliveries from GPS contractorSTR deliveries from STR contractorVFM deliveries from VFM contractorESOC deliveries to ESOCAIV deliveries to Prime AIV / EGSETBD to be defined by delivery from other contractors

Table 13.2-1: Definition of Site names related to file naming convention for data exchange

SDB Satellite DatabaseSMOD Simulation ModelTMM Thermal Mathematical ModelFEMT Finite Elemet Model Thermal

XXXX Type FEMS Finite Elemet Model Mechanical/StructuralTMD Thermal DataMPD Mass Property Data (CoG, MoI)HCPA Harness Connector to Pin Allocation ListFOP Flight Operations ProcedureTBD to be defined, for delivery of any other data

Table 13.2-2: Definition of Type names related to file naming convention for data exchange

x x = Version Number

V_x_y_zversion / release y

y = Release Number (is reset when Version is incremented)

z z = Update Number (is reset when Version is incremented)

Table 13.2-3: Definition of Version, Release and Update Number related to file naming convention for data exchange

New Versions are generated in case of a significant change (e.g. a new subsystem / instrument or new onboard software is included).

New Releases are documented by a ’Release Note’ and will be generated for each ’Delivery’ (from subcontractor to Prime and / or from EADS Astrium to ESA).

A new Update is generated whenever needed (e.g. when change requests have been incorporated and are to be tested).

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 45File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

The following table provides the list of data to be exchanged (please note this list may not be complete, therefore please refer also to the equipment specific SoW for details) and the Software type (e.g. drawing, MS Excel, MS Access).

Item Description Format Mass, Power Consumption & Dissipation and data rate properties

Maximum equipment mass including connectors and other parts Power Consumption vs. Equipment Modes Power Dissipation vs. Equipment Modes Data Rate vs. Equipment Modes Applicability of which tables are to be populated for equipments & materials(tbc) are defined in [AD 7] SW-PL-EAD-SY-0019

MS Access, MS Excel

Volume Lay out of the equipment in 3 dimensions with each dimension given as maximum including equipment connectors and other parts

CAD Model

Thermal data Contact surface (with shaping) with each size at a precision of 10% Heat flux (with repartition if non-homogeneous) at a precision of 10 % Dissipation for each operational mode(including start up, heating, different functioning modes if any) with a precision of 10 %

MS Excel or MS Word

Connector location

Connectors identification, position and orientation (electrical, waveguide, coax) on each side of the equipment.

CAD Model

Fixing location Position of all fixings. CAD Model Grounding stud

Location and number of grounding stud CAD Model

Unit TM/TC Parameter & Packet Definitions

Definition of telecommands with associated type. Definition of of telemetry with associated type. For Pus packet and non-PUS packet terminals which are data terminals. Applicability of which tables in the S-SDB are to be populated for PUS and non-PUS terminals are defined in [AD 7] SW-PL-EAD-SY-0019 An S-SDB tool will be provided by EADS Astrium

MS Access

Harness Connector Pin Allocation Table

Allocation of harness signals to unit connector pins Applicability of which tables in Harness to Pin Allocation DB are to be populated for equipments having electrical interfaces are defined in [AD 7] SW-PL-EAD-SY-0019 Example will be provided by EADS Astrium

Either MS Access or MS Excel

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of

Work for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 46File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc

Item Description Format Unit User Manual

According DRD, but including Functional Block Diagram and Correlation to Modes and related Telemetry / Telecommands Example will be provided by EADS Astrium in the DRD

Word format

Unit Flight Operations Procedures

Flight Operations Procedures; to be delivered as part of the User Manual Example will be provided by EADS Astrium

Word format

Electrical Interface schematics

Complete equivalent interface schematics with EEE properties

Drawing

Grounding diagram

Unit internal grounding diagram including designation of grounding and isolation, interface types, grounding lines both for signal and power lines.

Drawing

Assembly Constraints

Maximum Distance affordable between units within the assembly Specific requirements if any (twisting, shielding, intermediate harness length, etc.)

CAD Model and overall configuration drawing or ICD

Magnetic Properties

Magnetic Vector Position and Orientation MS Excel

EMC Properties

Definition of Notches, Frequency Plan, a.s.f. MS Excel

Table 13.2-4: Definition of information in electronic format for data exchange between EADS Astrium and subcontractors

Deliveries for information defined in Table 13.2-4 shall be provided in the format as defined above when delivering the ICD document except for User Manual, S-SDB and Flight Operations Procedures. The delivery of ICD is defined in the Documents Requirements List of the specific SoW.

The delivery of the User Manual is defined according the Document Requiremenst List in the specific SoW.

The delivery of the unit S-SDB and of Unit Flight Operations Procedures shall be triggered by event. Events are for instance Software Updates or major updates to ICD.

SWARM Doc. No: SW-SW-EAD-SY-0003

Issue: 2

SWARM Generic Statement of Work

for Equipment Date: 10.04.2006

© EADS Astrium GmbH Page 47File: SW-SW-EAD-SY-0003_2_SWARM_generic_SoW.doc


Recommended