Table of ContentsSWOT Analysis.......................................................2Business Case........................................................3Project Charter......................................................5Project Organizational Chart - Sample....................7Team Contract.......................................................8Stakeholder Analysis.............................................9Project acceptance form.......................................10Kick off meeting...................................................11Project Management Plan.....................................13Scope statement..................................................15Preliminary budget..............................................16Work Breakdown Structure (WBS)........................17Communications plan...........................................18Project Schedule Worksheet.................................19Risk Register.......................................................20Risk control sheet................................................21Deliverable Acceptance Form...............................22Change Request Form..........................................23Document distribution record...............................24Progress report....................................................25Communication record.........................................26Project Deliverable Approval Form........................27Project meeting...................................................28Quality Management............................................29Change Request...................................................30Final Report.........................................................32Close-Out Checklist..............................................33
2-1
2-3
Strengths(positive tangible and intangible attributes,
internal to an organization)
Weakness(factors within organizations control that detract
ability to attain desired goal)
Opportunities(external factors that might move
organization/project forward)
Threats(external factors, beyond organization’s control,
that may jeopardize mission)
Business Case
Project Identification
Project Name:____________________ __________ Date:_______________
Agency:___________________________________
Business Unit/Program Area:______________________
Project Sponsor:___________________ Project Manager:_________________
Business Need/Problem:
Solution (as described in Proposed Solution):
Consistency/Fit with Organization’s Mission:
2-4
Anticipated Benefits: (both qualitative and quantitative)
Original Cost Estimate: (from Proposed Solution)
Cost/Benefit Analysis:
Special Fund Sources:
2-5
Project Charter
Project Identification
Project Name:__________________ Date:_________________________
Project Manager:________________ Project Sponsor:________________
Project Description
Project Background:
Project Objective:
Critical Success Factors:
Required Resources:
Constraints:
Project Authority:
2-6
Project Charter Approval
Project Sponsor Name:___________________________________Action: Approve: Reject: Comments:
Project Sponsor Signature:________________________________Date:___________________
Agreement to Secure Required Resources
Approver Name:____________________ Role:________________________________Approver Comments:
Approver Signature:______________________________________Date:___________________
2-7
Project Organizational Chart - Sample
Project SteeringCommittee
Project Champion
Team 4Team 3Team 2Team 1
SupplierProject ManagersTeam Leads
Project Manager
Project Sponsor
2-8
Team ContractProject Name:Project Team Members’ Names and Sign-off:
Name Date
Code of Conduct: As a project team, we will:
Participation: We will:
Communication: We will:
Problem Solving: We will:
Meeting Guidelines: We will:
2-9
Stakeholder Analysis
Project Name:
KEY STAKEHOLDERSStakeholder 1 Stakeholder 2 Stakeholder 3 Stakeholder 4
Organization
Role on project
Unique facts about stakeholder
Level of interest
Level of influence
Suggestions on managing relationships
2-10
Project acceptance formProject Name: ___________________ Date: ________________________Project Sponsor: _________________ Project Manager: _______________
Project Sponsor Information
Project Sponsor Name: _________________________Action: Accept: Reject:
Project Sponsor Comments:
Project Sponsor Signature: _______________________________Date: _______________________
Project Manager Information
___________________________________Name (Print)
___________________________________ __________Signature Date
2-11
Kick off meeting
Project Initiation Kick-off Meeting Agenda
Project: ____________________________Date: __________________Time: From: __________ To:__________Location: ____________________________
Invitees:
Attendees:
AgendaPresenter Name Time (minutes)
Introductions
Sponsor’s Statement
Project Request & Background
Project Goals & Objectives
Project Scope
Roles & Responsibilities
Next Steps
Questions
Additional Information
Handouts:
2-12
Project Initiation Kick-off Meeting
Project: ______________________________Date: __________________Time: From: __________ To:__________Location: ____________________________
DecisionsDecision Made Impact Action
Required?
IssuesIssue Description Impact Action
Required?
Action Items for Follow UpAction Responsible Target Date
2-13
Project Management PlanThe Project Management Plan, also referred to as PMP, is a working document that will be updated throughout the project as required and varies with each project.
The sections outlined in this PMP sample are as follows: Project Name Introduction/Overview of the Project Project Organization Management and Technical Processes
o Management Processeso Technical Processes
Work to Be Preformed Schedule Information Budget Information Reference to Other Project Planning Documents
Some other possible sections: Contributing Authors Revision History Distributing List
Contributing Authors
Name Of Individual Title Section Number & Title
Revision HistoryVersion Description Author Date
Distribution List
Date Name of Individual Title Department
2-14
Project Management Plan Version 1.0
Date
Project Name:
Introduction/Overview of Project
Project Organization
Management and Technical Processes
Management Processes:
Technical Processes:
Work to Be Performed
Schedule Information
Budget Information
References to Other Project Planning Documents
2-15
Scope statement
Project Name:_____________________ Date:___________________
Project Sponsor: ___________________Project Manager: __________
A. Business Need/Problem:
B. Project Objectives (from Project Charter):
C. Project Results:
D. Project Content:
2-16
Preliminary budgetProject Identification
Project Name: ___________________ Date: ________________________Project Sponsor: _________________ Project Manager: _______________
Budget Information
PhaseProcess/Task
Labor Cost Material Cost Travel Cost Other Cost
Total Cost
Planned Date of Expenditure
TOTAL Budget
Comments: (list any assumptions pertaining to the costs entered above.)
2-17
Work Breakdown Structure (WBS)Date:
Project Name:
1.0Main category 11.1 Subcategory1.2 Subcategory
1.2.1 Sub-subcategory1.2.2 Sub-subcategory
1.3 Subcategory1.4 Subcategory
2.0Main category 22.1 Subcategory2.2 Subcategory
2.2.1 Sub-subcategory2.2.2 Sub-subcategory
2.3 Subcategory2.4 Subcategory
3.0Main category 33.1Subcategory3.2Subcategory
3.2.1 Sub-subcategory3.2.2 Sub-subcategory
3.3Subcategory3.4Subcategory
4.0Main category 44.1Subcategory4.2Subcategory
4.2.1 Sub-subcategory4.2.2 Sub-subcategory
4.3Subcategory4.4Subcategory
2-18
Communications plan
Project Identification
Project Name: ______________________ Date: _______________________
Project Sponsor: ____________________ Project Manager: ____________________
Stakeholder Message/Information Need Delivery Vehicle Frequency
Project Sponsor
Project Manager
Project Team Member
Quality Team Member
Procurement Team Member
Other Stakeholder
Existing Systems:
Method for Updating the Communications Plan:
Other Communications Information
2-19
Project Schedule Worksheet
Project Identification
Project Name: ___________________Date: _____________________
Project Sponsor: _________________Project Manager: ____________
Project Schedule Information
Phase Process Task Estimated Hours
Dependent Upon
Role
2-20
Risk Register
Risk Register for: ______________________
Date: ______________________
Project Name:
ID No. Rank Risk Description Category Root Cause
Triggers Potential Responses
Risk Owner
Probability
Impact Status
2-21
Risk control sheet Risk item no. _____________ Revision ________________ WBS impacted _____
Risk description:
Risk impact:
Risk solution(s):
Solution(s) impact:
Authorization: _________________________ Date: ____________________
2-22
Deliverable Acceptance FormProject Name:Deliverable Name:Project Manager:Project Sponsor:
(We), the undersigned, acknowledge and accept delivery of the work completed for this deliverable on behalf of our organization. My (Our) signature(s) attest(s) to my (our) agreement that this deliverable has been completed. No further work should be done on this deliverable. If the deliverable is not acceptable, reasons are stated and corrective actions are described.
Name Title Signature Date
1. Was this deliverable completed to your satisfaction? Yes No ____
2. Please provide the main reasons for your satisfaction or dissatisfaction with this deliverable.
3. If the deliverable is not acceptable, describe in detail what additional work must be done to complete it.
Contact’s signature for resubmission of deliverable if found unacceptable:
___________________________________________________
2-23
Change Request Form
Project Name:Date Request Submitted:Title of Change Request:Change Order Number:Submitted by:Change Category: Scope Schedule Cost Technology Other
Description of change requested:
Events that made this change necessary or desirable:
Justification for the change/why it is needed/desired to continue/complete the project:
Impact of the proposed change on:Scope:Schedule:Cost:Staffing:Risk:Other:
Suggested implementation if the change request is approved:
Required approvals:Name/Title Date Approve/Reject
2-24
Progress report
To: _____________________ Report Period Ending: ___________From: ___________________ Project Name:___________________
The tasks I completed this reporting period are:
The tasks I plan to complete next reporting period are:
I lost time due to: (Specify hours and cause):
Issues:Description Date
Identified
Target Date
Impact
Scheduled Vacation/Training:Description Start Date End
Date# of Hours
Time Reporting by Task Task ID Description
Original Estimate
Hrs this
Week
ETC Hrs to
Date
Reporting Period Total
2-26
Project Deliverable Approval FormProject Identification
Project Name: ___________________Date: ____________________Project Sponsor: _________________Project Manager: ___________
Deliverable Information
Project Phase: _______________________Date: _______ ________ Deliverable Name: ___________________ Author: ______________
Acceptance Criteria
Criteria:
Reviewer InformationReviewer Name:____________________ Role: ____________________
Deliverable Name: ____________________________________________
Recommended Action: Approve: Reject: Reviewer Comments:
Reviewer Signature: _______________________ Date: ________________
Approver InformationApprover Name: __________________ Role: ___________________Action: Approve: Reject: Approver Comments:
Approver Signature: ________________________Date: _________________
Project Manager Information
___________________________________Name (Print)
___________________________________ __________Signature Date
2-28
Project meeting Date: Time:
Meeting called by: Type of Meeting:
Attendees:
Please bring:
Agenda topicsPerson responsible Allotted time
1.
2.
3.
4.
5.
Other information:
2-30
Quality Management
Project Name: ___________________ Date: _____________________
Project Sponsor: _________________ Project Manager: ___________
PART A. QUALITY PLANNING – IDENTIFIED QUALITY STANDARDS
PART B: QUALITY ASSURANCE ACTIVITIES
PART C: QUALITY CONTROL ACTIVITIES
2-31
Change Request
Project Identification
Project Name: ___________________________________Project Manager: _________________________________
Change Request Information
Request Date: ________________Requested By: ________________ Agency: ________________________
Description of Change:
Scope Impact:
Schedule Impact:
Quality Impact
Cost Impact:
Reviewer Information
Reviewer Name: _______________________ Role: _________________________Deliverable Name: _______________________________________________________Recommended Action: Approve: Reject: Reviewer Comments:
2-32
Reviewer Signature: ______________________________________Date: ______________________
Approver Information
Approver Name: ________________________ Role: _____________________Action: Approve: Reject: Approver Comments:
Approver Signature: _______________________________Date: ___________________
Project Manager Information
___________________________________Name (Print)
___________________________________ __________Signature Date
2-33
Final Report
Project Name: Date:1. Project Objectives
2. Summary of Project Results
3. Original and Actual Schedule
4. Original and Actual Budget
5. Project Assessment
6. Transition Plan
Attachments:
A. Key Project Management Documentation
B. Product-Related Documentation
2-35
Close-Out Checklist Project acceptance with sign-off from customer, project sponsor and steering
committee
Lessons Learned session
Post Implementation Evaluation Report (PIER)
Outstanding work recognition
Project Team celebration
Resource disbursement – employees, facilities, systems
Final Project Report
Contract Closure and inspections if required
2-36