ID Task Mode Task Name Duration Start Finish 1 2 Signing of Supply agreement 1 day Sat 3/26/16 Sat 3/26/16 3 Site visit to Synergy 1 day Mon 4/4/16 Mon 4/4/16 4 Provide foundation compliance 1 day Mon 4/4/16 Mon 4/4/16 5 Finalize Equipment GA - inspection on replacement requirement 2 days Tue 4/5/16 Wed 4/6/16 6 BOM List 1 day Thu 4/7/16 Thu 4/7/16 7 8 Material Procurement 45 days Fri 4/8/16 Thu 6/9/16 9 internal Ambient Vaporizer 45 days Mon 4/4/16 Fri 6/3/16 10 Valves and Regulators replacement 45 days Mon 4/4/16 Fri 6/3/16 11 To find out on transfering of JKKP file, PMT 235, Ownership and original drawing or document. 50 days Tue 4/5/16 Mon 6/13/16 12 Get Qoute on cranage, skylift & low loader once finalise the delivery date 7 days Tue 5/3/16 Wed 5/11/16 13 Appoint cranage, skylift & low loader (Bkt Minyak) 2 days Wed 6/1/16 Thu 6/2/16 14 Appoint cranage and skylift(Kajang) 2 days Wed 6/1/16 Thu 6/2/16 15 16 SYNERGY Site work 17 Pre-Fabrication Work civil and roof structural ( by Synergy) 45 days Mon 4/4/16 Fri 6/3/16 18 Plinth Construction & curing 15 days Fri 5/13/16 Thu 6/2/16 19 Fencing and Gate fabrication Mon 4/4/16 20 Qoute for stirage cleaning, touich up, install PBU system 3 days Mon 4/25/16 Wed 4/27/16 21 Cleaning of storage tank & touch up 3 days Mon 6/6/16 Wed 6/8/16 22 Install Internal Pressure build up system 3 days Mon 6/6/16 Wed 6/8/16 23 KOM (Kick Off Meeting at site) 1 day Tue 6/21/16 Tue 6/21/16 24 Cranage - lifting tank SIG Bkt Minyak site 1 day Wed 6/22/16 Wed 6/22/16 25 Storage tank transportation 1 day Wed 6/22/16 Wed 6/22/16 26 Final Work - Position of VIE 1 day Thu 6/23/16 Thu 6/23/16 27 Arrival of Storage tank 1 day Thu 6/23/16 Thu 6/23/16 28 Cranage - lifting tank Synergy site 1 day Thu 6/23/16 Thu 6/23/16 29 Purging of Storage Tank, Vacuum reading 2 days Thu 6/23/16 Fri 6/24/16 30 Transfill Liquid into Storage tank 1 day Thu 6/23/16 Thu 6/23/16 31 Analysis on Storage tank 1 day Thu 6/23/16 Thu 6/23/16 32 ORI 1 day Thu 6/23/16 Thu 6/23/16 33 System Test & Commissioning 1 day Thu 6/23/16 Thu 6/23/16 34 Training to customer 1 day Fri 6/24/16 Fri 6/24/16 35 Hand Over 1 day Fri 6/24/16 Fri 6/24/16 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Mar 27, '16 Apr 3, '16 Apr 10, '16 Apr 17, '16 Apr 24, '16 May 1, '16 May 8, '16 May 15, '16 May 22, '16 May 29, '16 Jun 5, '16 Jun 12, '16 Jun 19, '16 Ju Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Synergy Gas & Welding CO2 tank
Transcript

ID Task Mode

Task Name Duration Start Finish

1

2 Signing of Supply agreement 1 day Sat 3/26/16 Sat 3/26/16

3 Site visit to Synergy 1 day Mon 4/4/16 Mon 4/4/16

4 Provide foundation compliance 1 day Mon 4/4/16 Mon 4/4/16

5 Finalize Equipment GA - inspection on replacement requirement

2 days Tue 4/5/16 Wed 4/6/16

6 BOM List 1 day Thu 4/7/16 Thu 4/7/16

7

8 Material Procurement 45 days Fri 4/8/16 Thu 6/9/16

9 internal Ambient Vaporizer 45 days Mon 4/4/16 Fri 6/3/16

10 Valves and Regulators replacement 45 days Mon 4/4/16 Fri 6/3/16

11 To find out on transfering of JKKP file, PMT 235, Ownership and original drawing or document.

50 days Tue 4/5/16 Mon 6/13/16

12 Get Qoute on cranage, skylift & low loader once finalise the delivery date

7 days Tue 5/3/16 Wed 5/11/16

13 Appoint cranage, skylift & low loader (Bkt Minyak)

2 days Wed 6/1/16 Thu 6/2/16

14 Appoint cranage and skylift(Kajang) 2 days Wed 6/1/16 Thu 6/2/16

15

16 SYNERGY Site work

17 Pre-Fabrication Work civil and roof structural (by Synergy)

45 days Mon 4/4/16 Fri 6/3/16

18 Plinth Construction & curing 15 days Fri 5/13/16 Thu 6/2/16

19 Fencing and Gate fabrication Mon 4/4/16

20 Qoute for stirage cleaning, touich up, install PBU system

3 days Mon 4/25/16 Wed 4/27/16

21 Cleaning of storage tank & touch up 3 days Mon 6/6/16 Wed 6/8/16

22 Install Internal Pressure build up system 3 days Mon 6/6/16 Wed 6/8/16

23 KOM (Kick Off Meeting at site) 1 day Tue 6/21/16 Tue 6/21/16

24 Cranage - lifting tank SIG Bkt Minyak site 1 day Wed 6/22/16 Wed 6/22/16

25 Storage tank transportation 1 day Wed 6/22/16 Wed 6/22/16

26 Final Work - Position of VIE 1 day Thu 6/23/16 Thu 6/23/16

27 Arrival of Storage tank 1 day Thu 6/23/16 Thu 6/23/16

28 Cranage - lifting tank Synergy site 1 day Thu 6/23/16 Thu 6/23/16

29 Purging of Storage Tank, Vacuum reading 2 days Thu 6/23/16 Fri 6/24/16

30 Transfill Liquid into Storage tank 1 day Thu 6/23/16 Thu 6/23/16

31 Analysis on Storage tank 1 day Thu 6/23/16 Thu 6/23/16

32 ORI 1 day Thu 6/23/16 Thu 6/23/16

33 System Test & Commissioning 1 day Thu 6/23/16 Thu 6/23/16

34 Training to customer 1 day Fri 6/24/16 Fri 6/24/16

35 Hand Over 1 day Fri 6/24/16 Fri 6/24/16

T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SMar 27, '16 Apr 3, '16 Apr 10, '16 Apr 17, '16 Apr 24, '16 May 1, '16 May 8, '16 May 15, '16 May 22, '16 May 29, '16 Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 1

Synergy Gas & Welding CO2 tank

Synergy Project

Phase 1: Moving of VIE tank from SIG Penang to Synergy

Date of commencement: 22nd June 2016 (Wednesday)

Agenda:

- Monitor the condition of the CO2 storage tank

- Ensure the pressure inside tank is more than 5 bar (prevent dry ice formation)

- Ensure no liquid CO2 inside the tank

- To test the safety relief valve and ensure that both are in correct set pressure (350 psi or 24

bar)

- To test the Differential Pressure Gauge (DP Gauge or Liquid Level Gauge) and ensure it’s in

the within the tolerance errors ( Instrument Used – CPP 30 Test Pump, Pneumatic Wikai )

- To take the vacuum reading of the tank

- To plan and lift the tank in a correct manner in order to protect all the valves and instrument

assembly from being damaged

- To lift the tank from a vertical position into a horizontal position and move it onto a low

loader

- Ensure the tank to reach Synergy by morning in the next day

Result:

DP gauge reading (liquid level) – 0 tonne of CO2

Pressure reading – 8.5 barg

Safety relief valve – Set pressure for 1st relief valve – 24.0 barg

Set pressure for 2nd relief valve – 24.2 barg

Vacuum reading – 0.126 torr or 0.01934 psi

DP gauge testing –

Instrument reading

Actual Reading Percentage Error

mBar tonne of CO2 tonne of CO2 %

90.6 2.182 1.80 17.51 %

181.2 4.364 3.78 13.38 %

271.8 6.546 5.75 12.16 %

362.4 8.728 7.75 11.21 %

453 10.910 9.75 10.63 %

543.6 13.092 11.80 9.87 %

634.2 15.274 13.8 9.65 %

724.8 17.456 15.8 9.49 %

815.4 19.638 17.8 9.36 %

906 21.820 19.8 9.26 %

Status – Completed on 15th June 2016 and the overall condition of the tank is fine

Phase 2: Positioning of VIE tank onto fabricated support

Date of commencement: 23rd June 2016 (Thursday)

Agenda:

- To position the VIE tank from horizontal position into a vertical positon

- To move the VIE tank onto the fabricated support with a proper alignment

- To wall plug the VIE tank onto the platform as a mean indication of finalizing the position of

the VIE tank

Result:

Status: Completed on 23rd June 2016

Phase 3: Welding and to connect the PBC (Pressure Building Coil) onto the tank

Date of commencement: 24 to 25th June 2016 (Friday to Saturday)

Agenda:

- To fabricate two square flange with gasket for the PBC unit

- To weld a 1” schedule 40 pipe to both of the square flanges

- To thread 1” NPT pipe connection for the Pressure Build-up Regulator (2 of them in total)

- To weld the remaining socket weld ball valve to connect the PBC from V7 to V13

- To build sufficient base support to withstand the weight of both the PBC and regulator

Result:

Status: Completed on 25th June 2016

Phase 4: To clean and repaint the tank

Date of commencement: 28th June 2016 (Tuesday)

Agenda:

- To remove the existing SIG symbol

- To clean the dust from the tank

- To repaint the tank

Result:

Status: Completed on 2nd July 2016

Phase 5: To fill liquid carbon dioxide (20 tonnes) into the VIE tank

Date of commencement: 29th June 2016 (Friday)

Agenda:

- To fill 20 tonnes of LCO into the VIE tank (by Cyromaster and monitored by Gopa)

- To analyze the carbon dioxide purity after liquid filling (by QA Nilai, Mr Lai)

- To train Synergy personnel onto the refilling process and pressure building coil (by Gopa)

Result:

Liquid level after filling – 17 tonnes of CO2

VIE Pressure – 19 bar

Gas purity analysis – 99.6 to 99.7 %

Refilling training by Gopa to Synergy personnel – Done, however need more training onto the

technical stuff

Status: Completed on 29th July 2016

SYNERGY GAS & WELDING SDN. BHD.

Document No.

WORK INSTRUCTION

Title: Carbon Dioxide Refilling

Rev. No.

00

Page

1 of 3

Approved By

1.0 Purpose

To define the procedure for refilling liquid for carbon dioxide cylinder.

2.0 Scope

This procedure applies to production supervisor & operators for standard

procedure of baking out moisture from cylinders.

3.0 Definition

Nil

4.0 Related Documents

Appendix 1 Carbon Dioxide Refilling Station (P&ID)

5.0 Procedure (For refilling carbon dioxide cylinder)

Pre-operation

5.1 Ensure that the pressure within the storage tank at 15 bar and above (18 bar to

20 barg would be the best). If the pressure is lower than 15 bar, then operator

can use the Pressure Building Coil (PBC) to increase the tank pressure to 19

bar (refer to Section 6.0).

5.2 Ensure that the P1100 is filled with oil (where the sight glass is full can be

seen).

5.3 Ensure that all valves within the refilling station has been closed or shut.

Operation

It is important to cool down the pump before starting it and appropriate pressurization

procedures should be followed to ensure that no dry ice formation (solid carbon

dioxide).

5.3 First, open the pump return valve (V-4) as shown in the appendix figure to

allow pressurization of the line to be taken place. Then, open switch the 3-way

valve (V-3) where the flow can be directed from pump to storage tank.

5.4 After the pressurization process, open the liquid supply line (V-1) to begin the

cooling process. The cooling process will take around 10 to 15 minutes,

however, the process itself can be accelerated by opening the vent/cooling

valve (V-2) until liquid phase can be seen flowing out and the pump cylinder

is icing. When the cooling is sufficient, close the vent valve (V-2) and start the

SYNERGY GAS & WELDING SDN. BHD.

Document No.

WORK INSTRUCTION

Title: Carbon Dioxide Refilling

Rev. No.

00

Page

2 of 3

Approved By

pump. (* Make sure that the 3-way valve is flowing from the pump to the

storage tank to prevent overpressure).

5.5 With the pump is running, place both gas cylinders onto the weighing

machines. Then, connect the flex hoses to both of the cylinders and open the

cylinder head valve on both. (* Always remember and ensure that the cylinder

valve is opened to prevent over-pressure within the line which can be

dangerous.)

5.6 Then, turn the 3-way valve (V-3) to allow the flow direction coming from the

pump to the refilling line and open the line valve (V-5) to begin the filling

process. (* Make sure that the line valve at V-6 is closed.)

5.7 After the refilling process is done where the weight has reaches its appropriate

capacity, close the line valve (V-5) and open the line valve (V-6) so the other

gas cylinder can be filled. While waiting, remove the flex hose on the first gas

cylinder and remove it from the weighting machine. The new gas cylinder

then can be put onto the weighing machine waiting to be refilled, the process

can be repeated from 5.4 to continue the refilling process.

Post-operation

5.9 To shut the refilling station, first close all the line valve (V-5) and (V-6) and

turn the 3-way valve to the direction flowing from pump to storage tank.

5.10 Then only proceed to stop the pump and close both valves at (V-1) and (V-4)

to ensure no more liquid and vapour is flowing into the line. Finally, vent the

remaining liquid and gas by opening the vent valve (V-2) until the remaining

pressure dropped to zero.

6.0 Procedure (For building tank pressure)

To build the tank pressure

6.1 If the tank pressure is lower than 15 bar, operators can build the tank pressure

itself by following the procedures below. First, ensure that the valves from

Bottom Fill and Gas Balancer are closed.

6.2 Then slowly open the valve at (V-7) and wait for a few minutes, this will

allow time for the liquid to vaporize into gas with high pressure.

6.3 Open the valve at (V-8) and (V-9) to allow the high pressure gas to flow into

the tank to increase the tank pressure. This process might takes around 10

minutes and more. If the pressure increased to 18 bar, then proceed to close

valve at (V-7), (V-8) and (V-9). The operators can then proceed to refill for

the carbon dioxide cylinders.

SYNERGY GAS & WELDING SDN. BHD.

Document No.

WORK INSTRUCTION

Title: Carbon Dioxide Refilling

Rev. No.

00

Page

3 of 3

Approved By

APPENDIX 1: Carbon Dioxide Refilling Station (P&ID)

CONFIDENTIAL

THIS DRAWING IS OWNED BY SOUTHERN

INDUSTRIAL GAS SDN BHD, CONTAINS

PROPRIETY INFORMATION AND SHOULD

NOT BE DISTRIBUTED, COPIED,

REPRODUCED FOR ANY OTHER

PURPOSES WITHOUT PROPER

AUTHORIZATION.

SYNERGY GAS & WELDING

SDN BHD

15, Jalan P2/18, Seksyen 2, Bandar

Teknologi Kajang, 43500 Semenyih,

Selangor D. E.

TEL: 03-8723 6881 FAX: 03-8724 6881

DRAWING TITLE:

Appendix 1: Carbon Dioxide

Refilling Station (P&ID)

DRAWING NO.

DRAWN BY

CHECKED BY

APPROVED BY

DATE

SCALE

GENERAL NOTES/ REMARKS:

REV.

DRAWN

BY.

CHECKED

BY.

DATEREMARKS

Synergy

Bottom

Fill

Gas

Balancer

Pressure

Gauge

Differential Pressure

Gauge (in tonnes CO ₂)

CO2 Storage

Tank

(20 tonnes)

Pressure

Gauge

Burst Disc:

2000 psi

Relief Valve:

1200 psi

Relief Valve:

1000 psi

Check

Valve

Vent/ Cooling

Valve

P 1100

Pump

3-way Valve

(L shape)

Thermal

Relief Valve:

1200 psi

V-1

V-2

V-3

V-4

V-5

V-6

Normally

Open

Normally

Open

Y-strainer

Carbon Dioxide

Cylinder 1

V-7

V-8

V-9

Relief Valve:

350 psi

Pressure

Building Coil

Regulator:

275 psi

(19 barg)

Carbon Dioxide

Cylinder 2

Liquid Phase

Gas Phase

ADRIAN MAH

29/7/2016