Page 1 of 43 Date: 11 February 2020 Reference: RFP 2020/001 Request for proposals (RFP 2020/001) System Design and Implementation for intelligent Business Process Management System for Accreditation Process 2.0 1. Background 1.1 The Green Climate Fund (the “GCF”, or the “Fund”) was established with the purpose of making a significant and ambitious contribution to the global efforts towards attaining the goals set by the international community to combat climate change. In the context of sustainable development, the Fund will promote a paradigm shift towards low-emission and climate-resilient development pathways by providing support to developing countries to limit or reduce their greenhouse gas emissions and to adapt to the impacts of climate change. The Fund’s headquarters are located in Songdo, Incheon City, Republic of Korea. 1.2 The GCF was designated as an operating entity of the financial mechanism of the United Nations Framework Convention on Climate Change (“UNFCCC”). It is governed and supervised by a Board that has responsibility for funding decisions pursuant to the Governing Instrument for the Green Climate Fund (the “Governing Instrument”). It is supported by an independent Secretariat, accountable to the Board, having management capabilities to execute day-to-day operations of the GCF, providing administrative, legal and financial expertise. 2. Invitation 2.1 Through this request for proposals (“RFP”), the GCF is seeking to contract a qualified, reputable and experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation Process 2.0. The terms of reference included in Annex 1 provides the details of the assignment and expected deliverables. 2.2 Proposals must be submitted to the GCF no later than 11 March at 17:00 hrs (time) Korean time. 2.3 The RFP includes the following annexes: Annex 1 Terms of Reference Annex 2 Requirement for Firm’s Proposals Annex 3 Evaluation Criteria Annex 4 Company Profile Form Annex 5 Acknowledgement Letter Annex 6 Annex 7 Timeline Model Contract 2.4 The terms set forth in this RFP, including all the annexes listed above, will form part of any contract, should the GCF accept your proposal. Any such contract will require compliance with all factual statements and representations made in the proposal, subject to any modifications agreed to by the GCF in the context of any negotiations entered into it. 2.5 The GCF may, at its discretion, cancel the requirement in part or in whole. It also reserves the right to accept or reject any proposal and to annul the selection process and reject all proposals at any time prior to selection, without thereby incurring any liability to proposers/firms.
Transcript
Page 1: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 1 of 43

Date: 11 February 2020 Reference: RFP 2020/001

Request for proposals (RFP 2020/001)

System Design and Implementation for intelligent Business Process Management System for Accreditation Process 2.0

1. Background 1.1 The Green Climate Fund (the “GCF”, or the “Fund”) was established with the purpose of making a

significant and ambitious contribution to the global efforts towards attaining the goals set by the international community to combat climate change. In the context of sustainable development, the Fund will promote a paradigm shift towards low-emission and climate-resilient development pathways by providing support to developing countries to limit or reduce their greenhouse gas emissions and to adapt to the impacts of climate change. The Fund’s headquarters are located in Songdo, Incheon City, Republic of Korea.

1.2 The GCF was designated as an operating entity of the financial mechanism of the United Nations Framework Convention on Climate Change (“UNFCCC”). It is governed and supervised by a Board that has responsibility for funding decisions pursuant to the Governing Instrument for the Green Climate Fund (the “Governing Instrument”). It is supported by an independent Secretariat, accountable to the Board, having management capabilities to execute day-to-day operations of the GCF, providing administrative, legal and financial expertise.

2. Invitation 2.1 Through this request for proposals (“RFP”), the GCF is seeking to contract a qualified, reputable and

experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation Process 2.0. The terms of reference included in Annex 1 provides the details of the assignment and expected deliverables.

2.2 Proposals must be submitted to the GCF no later than 11 March at 17:00 hrs (time) Korean time.

2.3 The RFP includes the following annexes: Annex 1 Terms of Reference Annex 2 Requirement for Firm’s Proposals Annex 3 Evaluation Criteria Annex 4 Company Profile Form Annex 5 Acknowledgement Letter Annex 6 Annex 7

Timeline Model Contract

2.4 The terms set forth in this RFP, including all the annexes listed above, will form part of any contract,

should the GCF accept your proposal. Any such contract will require compliance with all factual statements and representations made in the proposal, subject to any modifications agreed to by the GCF in the context of any negotiations entered into it.

2.5 The GCF may, at its discretion, cancel the requirement in part or in whole. It also reserves the right to accept or reject any proposal and to annul the selection process and reject all proposals at any time prior to selection, without thereby incurring any liability to proposers/firms.

Page 2: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 2 of 43

2.6 Proposers may withdraw their proposal after submission provided that written notice of withdrawal is received by the GCF prior to the deadline prescribed for submission of proposals. No proposal may be modified subsequent to the deadline for submission of proposals. No proposal may be withdrawn in the interval between the deadline for submission of proposals and the expiration of the period of proposal validity.

2.7 All proposals shall remain valid and open for acceptance for a period of 90 calendar days after the deadline for submission of proposals. A proposal valid for a shorter period may be rejected. In exceptional circumstances, the GCF may solicit the proposer’s consent to an extension of the period of validity. The request and the responses thereto shall be made in writing.

2.8 Effective with the release of this solicitation, all communications relating to this RFP must be directed only to the Head of Procurement by email at [email protected]. Proposers must not communicate with any other personnel of the GCF regarding this RFP.

2.9 This RFP is issued under the GCF Administrative Guidelines on Procurement 1. Information regarding the guidelines can be found at

http://www.greenclimate.fund/documents/20182/574763/GCF_policy_-_Administrative_Guidelines_on_Procurement.pdf/b767d68e-f8b7-46d1-a18c-b6541f3dc010

3. Joint Venture, Consortium or Association 3.1 If the Proposer is a group of legal entities that will form or have formed a joint venture, consortium or

association at the time of the submission of the Proposal, they shall confirm in their Proposal that:

(i) they have designated one party to act as a lead entity, duly vested with authority to legally bind the members of the joint venture jointly and severally,

(ii) if they are awarded the contract, the contract shall be entered into, by and between GCF and the designated lead entity, who shall be acting for and on behalf of all the member entities comprising the joint venture.

3.2 After the Proposal has been submitted to GCF, the lead entity identified to represent the joint venture shall

not be altered without the prior written consent of the GCF. Furthermore, neither the lead entity nor the member entities of the joint venture can submit another proposal:

a) either in its own capacity; nor b) as a lead entity or a member entity for another joint venture submitting another Proposal.

3.3 The description of the organization of the joint venture/consortium/association must clearly define the

expected role of each of the entity in the joint venture in delivering the requirements of the RFP, both in the Proposal and the Joint Venture Agreement. All entities that comprise the joint venture shall be subject to the eligibility and qualification assessment by GCF.

3.4 Where a joint venture is presenting its track record and experience in a similar undertaking as those

required in the RFP, it should present such information in the following manner:

a) Those that were undertaken together by the joint venture; and b) Those that were undertaken by the individual entities of the joint venture expected to be involved in the performance of the services defined in the RFP.

3.5 Previous contracts completed by individual experts working privately but who are permanently or

were temporarily associated with any of the member firms cannot be claimed as the experience of the joint venture or those of its members, but should only be claimed by the individual experts themselves in their presentation of their individual credentials.

1 Annex II “Corporate Procurement Guidelines on the Use of Consultants”

Page 3: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 3 of 43

3.6 If a joint venture’s Proposal is determined by the GCF as the most responsive Proposal that offers the

best value for money, the GCF shall award the contract to the joint venture, in the name of its designated lead entity. The lead entity shall sign the contract for and on behalf of all other member entities.

4. Request for Clarification of RFP Documents 4.1 A prospective proposer requiring any clarification of the solicitation documents may notify the GCF in

writing to the email address [email protected] by the specified date and time mentioned in Annex 6. The subject line of the email must have the reference number and title of the RFP i.e. 2020/001 – intelligent Business Process Management System for Accreditation Process 2.0. The GCF will respond in writing to any request for clarification of the solicitation documents that it receives by the due date published in Annex 6. Written copies of the GCF response (including an explanation of the query but without identifying the source of inquiry) will be posted on the GCF website and/or communicated via email.

5. Amendments to RFP Documents 5.1 At any time prior to the deadline for submission of proposals, the GCF may, for any reason, whether at

its own initiative or in response to a clarification requested by a prospective proposer, modify the RFP documents by amendment. The amendments will also be posted on the GCF website and/or communicated via email.

5.2 In order to allow prospective proposers reasonable time in which to take the amendment into account in preparing their proposals, the GCF may, at its sole discretion, extend the deadline for the submission of proposal.

6. Language of Proposals 6.1 The proposals prepared by the proposer and all correspondence and documents relating to the proposal

exchanged by the proposer and the GCF, shall be written in English. Supporting documents and printed literature furnished by the proposer may be in another language provided they are accompanied by an appropriate translation of all relevant passages in English. In any such case, for interpretation of the proposal, the translation shall prevail. The sole responsibility for translation and the accuracy thereof shall be the responsibility of the proposer.

7. Submission of Proposals 7.1 Format and form of submission of bids: Bidders are requested to send a Bid preferably2 through the

GCF Supplier portal at https://gcf.supplier.ariba.com (a supplier manual can be found on the GCF website https://www.greenclimate.fund/who-we-are/procurement as an attachment under this RFP) or via email to [email protected], and copied to: [email protected].

i) Submission through the Supplier Portal (SAP Ariba) 1. Open https://gcf.supplier.ariba.com/ 2. Click Register Now 3. Fill in Company Information, Fill in User account information and details under ‘Tell us more

about your business’ 4. Check ‘I have read and agree to the Terms of Use and ‘I have read and agree to the SAP Ariba

Privacy Statement’ then click ‘Register’ 5. Check your email and click the activation link.

2 Suppliers shall note that GCF will be phasing out e-mail submission in the near future, therefore suppliers are

encouraged to register and submit their Bid/Proposal through the GCF Supplier portal (SAP Ariba)

Page 4: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 4 of 43

6. Fill in additional information required, click Save and Close. 7. Your company information will be submitted to GCF and will be reviewed and approved. Once

you register, please send an email to [email protected] with the RFP number and title as the email reference and confirm that you are interested in submitting a bid. You will then be invited to participate in the RFP. You will receive the RFP event notification email from the Green Climate Fund with a link to access the RFP. This link can be used only once. If you require to access the portal after you have activated the link, you can log in on https://gcf.supplier.ariba.com with your user name and password.

8. Review Prerequisites and Click ‘I accept the terms of this agreement’ 9. Open the Technical Section of the RFP section and download the RFP document and technical

proposal submission forms 10. Open the Financial Section of the RFP and download the financial bid submission forms 11. When ready to submit your bid, upload the technical bid under the TECHNICAL section and the

financial bid under the FINANCIAL section. Please do not enter or upload any financial information under the TECHNICAL section.

12. Click ‘Submit Entire Response’ to submit bid. (For detailed instructions on how to access and submit a bid, see the supplier manual)

ii) Submission via email

Two separate files (technical and financial bids) should be attached to the email as below. The Technical file should be named as follows:

RFP 2020/S/001 – TECHNICAL PROPOSAL - (name of proposer) The financial file should be named as follows:

RFP 2020/S/001 – FINANCIAL PROPOSAL - (name of proposer). The subject line of the email should be as follows:

RFP 2020/S/001 – design and implementation for iBPMS (name of proposer).

7.2 The Financial Proposal MUST be password protected. The authorized procurement officer will contact the bidders that pass the qualifying technical score for the password to open the Financial Proposal. Bidders should NOT send the password to the financial proposal until they are requested to do so by the procurement officer. Financial Proposals that are submitted without password protection may be rejected for non-compliance. Financial Proposals that are submitted without password protection may be rejected for non-compliance.

7.3 All prospective proposers are kindly requested to return the completed Acknowledgement Letter of RFP

receipt (Appendix 5) by the date indicated in Appendix 6, duly signed by an authorized representative, via email, advising whether it intends to submit a proposal by the designated closing date/time. Please also notify the Procurement Specialist immediately if any part of this RFP is missing and/or illegible.

8. Late proposals 8.1 Any proposals received by the GCF after the deadline for submission of proposals prescribed in Annex

6 of this document may be rejected.

9. Opening of Technical Proposals 9.1 Technical Proposals will be opened on the date indicated in Annex 6. The purpose of this public opening

is to record the names of proposers having submitted proposals by the due date and time. Only technical proposals will be opened at the public opening. The financial proposals will not be opened. Proposers

Page 5: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 5 of 43

submitting proposals are welcome to send one (1) representative, with proper authorization from their company, to observe the opening and recording of proposals received.

10. Opening of Financial Proposals 10.1 GCF shall notify in writing those Proposers that have achieved the minimum qualifying technical score

and request for passwords of the Financial Proposals.

11. Corrupt, Fraudulent, Coercive, Collusive and other Prohibited Practices. 11.1 The GCF requires that all GCF staff, proposers/bidders, suppliers, service providers and any other person

or entity involved in GCF-related activities observe the highest standard of ethics during the procurement and execution of all contracts. The GCF may reject any proposal put forward by proposers, or where applicable, terminate their contract, if it is determined that they have engaged in corrupt, fraudulent, coercive, collusive or other prohibited practices.

12. Conflict of Interest 12.1 In their proposal, proposers must (i) confirm that, based on their current best knowledge, there are no

real or potential conflicts of interest involved in rendering Services for the GCF, and (ii) set out their policy on dealing with conflicts of interest should these arise.

13. Confidentiality 13.1 Information relating to the evaluation of proposals and recommendations concerning selection of Firms will not be disclosed to Firms that submitted proposals.

Page 6: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 6 of 43

Annex I – Terms of Reference: Green Climate Fund’s intelligent Business Process Management System for Accreditation Process 2.0

I. Background and Objective

1.1 Background: The Green Climate Fund (GCF) aims to make a significant and ambitious contribution for global efforts towards attaining the goals set by the international community to combat climate change. It is set to become the main vehicle for securing and distributing finance and its resources supporting a range of activities that reduce emissions or foster resilience. The Fund channelizes its finance to the climate change related projects through a network of entities that are accredited to the GCF through a rigorous accreditation process.

GCF plays a key role in exchanging sensitive information while channelling new, additional, adequate and predictable financial resources to developing countries and catalyses climate finance, both public and private, at the international and national levels. The standard security operational procedure, as well as the security considerations of ICT systems, especially security and reliability of the fund’s file repository regime is critical on playing this important role.

The Fund’s current Online Accreditation System (OAS) 1.0, has been handling its accreditation process for entities was developed in very early days of the Fund with the tweaks and fixes to handle ever-changing business requirements. However, to significantly improve and enhance the efficiencies and transparency required to achieve the Fund’s strategic objectives, the Fund sees of a new system to replace the current one, which tentatively is named as OAS 2.0.

1.2 Objective: The Fund would like to develop a new system that will: 1) significantly improve the current workflow and also cover the wider scope of the entire accreditation process, including pre-accreditation and re-accreditation, 2) seamlessly interface to/integration with other existing systems such as the iPMS and financial system, 3) provide further visibility of overall status of the process in dashboards and reports to align GCF strategic goal of improving efficiency and transparency.

During the ICT’s consultation with the industry’s leading research and advisory firms including Gartner and Forrester, and communications to peer institutions such as United Nations, World Food Programme, Asian Development Bank, it is identified that the approach to the project should neither be 1) out-of-box SaaS (Solution as a Service) products, as the accreditation process is mostly unique based on the Fund’s mandates and guidelines on how we handle the accreditation, nor 2) complete custom development, as the process, with some similarity of the business process elements used by other financial institutions’ eligibility, evaluation or underwriting process, can still be accommodated by the modern business process management platforms, called intelligent Business Process Management System. (iBPMS)

The project thus will be characterized as enterprise-level in-depth configuration of industry leading iBPMS platform to provide the best possible user experience for all stakeholders of the

Page 7: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 7 of 43

Fund’s accreditation business process, from online submission of the application, review and approval, to re-accreditation and everything in between.

II. Scope and Technical Requirements for the Project

2.1 Scope Summary: iBPMS platform licenses and implementation professional services required for 1) developing Online Accreditation System 2.0, and 2) securing the cutting-edge capacity for automating other core business processes based on the procured iBPMS platform.

2.2 Business Process Requirements: For illustrative diagram and business requirements, refer to the Annex I-A. Illustrative Accreditation Business Process Maps and Detailed Requirements at the end of this Annex document. Below are the key requirements summary that the proposed system should fully comply.

Phase Use-case Details

Pre-accreditation

Request for eligibility for application

Applicants creates an account, uploading required documents for the Secretariat to check eligibility for application

Accreditation

Applicant raises accreditation request

Applicants fill-in the application form. The form is attachment heavy where almost all questions requires documented evidence of the response to be uploaded.

Application received and preliminary checks

The secretariat reviews the application and check if the application is complete enough to ask the applicant for application fees.

Issuance of invoice of accreditation fees and check if fees are paid

Systemic ways to inform finance team the invoice details and be informed by finance team that the payment is successfully received

Secretariat Review (Stage I)

Multiple rounds of application sent-back and re-submission stages expected with clarification questions from the Secretariat and response from applicants. The review stage involves collecting review comments from multiple reviewers simultaneously. The system requires to handle parallel review workflow (review requested, review comments provisioning, review completed) with proper email alerts and other triggers, and at the end of the review process, the task manager should be able to consolidate the review comments and send the final version to the applicants.

Consulting firms checking completeness (Stage I)

Consulting firms also make review comments. The individuals from the firm also needs to easily access the form and documents and provide necessary comments to be responded by applicants

Page 8: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 8 of 43

Accreditation Panel review (Stage II)

Similar back and forth to be done with expert panel and the applicant. The secretariat needs to monitor the process and progress of this phase.

Board Decision (Stage II)

The system captures the progress of the board decision as a separate workflow stage

Legal Arrangement (Stage III)

The system captures the progress of the legal arrangement as a separate workflow stage and also captures the condition progress related to execution and effectiveness of the agreement

Post-Accreditation

Annual self-assessment by AEs

Applicants review the accreditation application and perform self-assessment

Mid-term reviews The secretariat reviews the status of accredited entity at the middle of the accreditation contract

Re-accreditation At the end of the contracted period, the applicant again applies for re-accreditation, based on the previous application and all the attachment (the changes from the previous interaction to be uploaded to the system for accreditation process)

2.3 iBPMS Platform Technical Capability Requirements

Requirements Details Interaction Management

Be able to orchestrate multiple types of activities and interactions at runtime to support the work that people, systems and "things" do in order to produce specific business outcomes. Particularly entry, storage and retrieval of the structured information about the entities applying for accreditation, beyond a simple user/applicant management scheme of registration process. The platform should be able to manage the workflow involving sequential and parallel workflow, including accreditation review process.

High-productivity app authoring

The platform includes development tools for both citizen and IT developers. The platform allows developers to quickly and easily build a process-centric application. Applications built on the platform use a metadata model to manage the complete life cycle of business processes.

Monitoring and business alignment

The platform continuously tracks conditions in processes, cases and other behaviors in near real time to provide process intelligence. The platform includes components that display information on dashboards, send notifications (including alerts) or trigger automatic responses in applications, processes or devices. The platform provides tools for managers and executives to track summary-level results against high-level operational, tactical or strategic business objectives.

Page 9: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 9 of 43

Rules and Decision Management

The platform provides software facilities such as rule engines, recommendation engines or decision management engines that provide guidance for making human or automated decisions according to business directives or policy statements.

AI based Analytics

The platform is capable to provide AI-based analytic services that supports orchestration for making smarter decisions about the flow progress of work, or within an activity step to improve other aspects of the application.

AI based RPA (Robotic Process Automation) capabilities

Whenever possible, AI/ML capability provides further insights to the proess discovery, optimization, improvement and decision support, while the platform should feature native RPA capabilities to be utilized along with BPM to handle short-term process automation to increase efficiencies of the business process

Interoperability RestAPI endpoints for further integration to other systems, along with capability of integrating external data source in similar way to the internal data source while designing the business process.

Process Discovery and Optimization

The platform provides capabilities that accelerate the time to discover and optimize behaviors (for example, processes, tasks, policies) needed to improve business outcomes, including analyzing past execution history or simulation of proposed behaviors.

Context and behavior history

The platform maintains a log of process events, decisions, collaborations, and other kinds of context data (from external applications and databases) to be utilized in dynamic and improvisational interactions taking place during the business process and also for audit purposes.

Out-of-box mobile-ready, responsive modern UI

Without extensive html/css make-over efforts, the out-of-box interface already is user-friendly and modern enough to launch the application. At least the dashboard/reporting part of the app should be approachable via mobile devices

Cloud-first architecture

Platform should show strong evidence that the vendor is considering cloud as the primary option and actively leverage cloud-native technology, instead of simply replicating the same architecture to cloud from its on-premise offerings

Single Sign-On Supports Okta, SAML2/OpenID SSO authentication for both business users and customers use-cases

Document Management Capabilities

Platform should be able to handle attached documents and unstructured data with version control, intelligent search and sort, and other document management capabilities to deal with document-heavy OAS 2.0 form requirements

Platform References

Proven reference sites utilizing the platform to handle the business process, preferably in nonprofit sector, financial sector or international institutions, comparable to the Fund

Partner Ecosystem

Robust partner ecosystem supporting the implementation and operation of the platform, along with third-party apps and components marketplace and strong customer success stories and evidances

Future Proof Technology

Platform has proven record of evaluation against foreseeable additional use-cases including intelligent process centric applications, continuous

Page 10: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 10 of 43

process improvement, business transformation, digitized process, case management.

2.4 Implementation: Professional Service Requirements

Requirements Details Subject Matter Experience

Implementation project references comparable to the Fund (at least 5 recent project references in details)

Agile Project Management

Capability of incorporating agile methodologies into the project management to deal with on-going changes of the business requirements of the Fund

Business Requirements Discovery

Capability and proven record of guiding the client to further identify and discover business requirements and translate the requirements seamlessly into technical requirements for the system configuration

Migration Capability of analyzing the existing OAS 1.0 data to recommend the migration strategies and options, and capability of executing migration activities in the most efficient and effective manner

Integration Capability of analyzing relevant other systems to recommend the integration strategy, and capability of working with the client’s development team to execute any required integration via RestAPI or any other possible options identified

Test Automation Support

Capability to provide support for automated testing of the developed workflows

Training and Support

Capability to provide regular support and per-hour based additional professional services requested to improve and extend the system on-demand basis. Capability to provide both remote and on-site training.

2.5 Required Platform Licenses: The Fund seeks for cloud annual subscription model for the platform licenses. In addition to the initially required users for OAS 2.0, per user cost during the contracted period should be indicated in the financial proposal.

Named Users Number of Users Usage of system

GCF Internal Admin 10 More than 50 hours per month Accreditation Panel 10 Consulting Firm 1 20 Consulting Firm 2 20 GCF Non-core Users

20 Less than 50 hours per month

GCF Management 20 Less than 10 hours per month

Accreditation Applicants

Per access basis users. Active during accreditation, condition review, yearly-review and reaccreditation processes. Need to have unlimited users or a special model (customer account). Assume 300 Accreditation Cases (or External Users) per year accessing the system sporadically for cost comparison.

Page 11: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 11 of 43

III. Activities and Deliverables

3.1 Activities: On-site presence expected for at least requirement discovery phase, while the parties would seek the most efficient and effective option between on-site work and remote work for other phases.

3.2 Timeline: The entire project delivery is expected to be completed within 6 months. As the Fund is expecting to have its first re-accreditation case in July 2020, any creative suggestions (including agile proto-tying with reduced requirements as a parallel phase) to cater the first few re-accreditation cases during the implementation period would be highly appreciated.

3.3 Phase-wise Deliverables

The table as under lists deliverables from this Work Package. Phase Deliverables

(from Contractor) GCF Responsibilities

Planning Project Plan including the sections for Scope, Scheduling, Resources, Quality Assurance and Communications Planning

- Review and accept the project plan

- Agree with GCF resource allocations and project tolerances and estimates

Requirements discovery

Requirements analysis document set

Appointment of project sponsor, project manager, and technical lead Participation in requirement identification Confirm deliverables

System Design - System design document set Review and provide feedback

on the system design documents Confirm deliverables

Development and unit test

- User Interface, Data Structure, Workflow and Integration Configuration of the system

- Unit test results

Review and provide feedback on the configuration Assess the feasibility of integration to GCF systems Confirm deliverables

System and Integration test

- SSO integration to OKTA (GCF Apps Portal)

- Data integration to iPMS and other GCF systems

- Test automation scripts

Assess the feasibility of integration to GCF systems Confirm deliverables

Data Migration - Migrated data in the new system

Confirm deliverables

Page 12: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 12 of 43

User Acceptance Test

- System Demonstration for User Acceptance - User Training and Manual

Lead the UAT arrangement Confirm deliverables

Deployment and handover

- System in Production System Administration Documentation - System Admin Training

Confirm deliverables

IV. Performance Standard/Acceptance Criteria

4.1 For each phase of this project, deliverables and productivity of works will be measured according to the performance / acceptance criteria as in the table under.

Phase Performance / Acceptance Criteria Requirements discovery

The reports and document set fully and correctly entails the business needs as expressed by GCF in aspects and areas of business processes

System Design The design and architecture conform all the business and technical requirements agreed during the requirements discovery phase The design and architecture conform the industry standards The design and architecture consider future

revision/extension/upgrade/migration

Development and unit test

The form, workflow, data model, user interface, alert/triggers, business rules conform all the technical requirements and conform the system design principles and guidelines. The result of unit test shows that the system captures all the

use-case scenarios including foreseeable outlier cases, and the system shows how to handle any potential system error situation

System and integration test

The system shall be seamlessly integrated to GCF Apps Portal (based on OKTA technology) to provide SSO experience The system, if needed, shall be able to provide different

authentication logic for internal and external users The system shall be able to sync the data to and from the

Fund’s iPMS (integrated Project Management System) to further integrate the data flow of the Fund climate business The system provides the best-effort interaction to the Fund’s

existing accounting system for invoice drafting and payment checking of accreditation fees All end-to-end workflows/processes including the normal

paths and alternate paths identified during requirements discovery phase are successfully executable through automated test scripts provided by the implementation partner.

Data Migration Based on the migration scope determined during the requirement discovery phase, the existing data (the application form and attachments) shall be migrated to the system

Page 13: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 13 of 43

User Acceptance Test

The internal user group test and accept the system configuration fulfilling the business requirements The external user group test and accept the system

configuration fulfilling the business requirements The system shall be tested to be light and flexible enough to

accommodate harsh internet environment of some of the developing countries

Deployment and handover

Conduct the pilot re-accreditation process to be successfully initiated and processed using the production environment

4.2 Quality Metrics Quality of work and outputs from this Work Package will be measured according to the criteria as under.

Area Quality Measurement Criteria Project Resources Project resources showed professionalism through the

whole engagement in the project. Project resources showed enough skills and experiences

required to perform tasks assigned for the Work Package. Project resources demonstrated behaviours that fully

conform to GCF’s code of business conduct and GCF’s general guidance on work environment management policies. Project resources’ fully complied to the guidelines of

usage of GCF’s facilities, system environments, tools, communication environment and any properties under the governance of GCF.

Project Deliverables All identified project deliverables should meet the acceptance criteria as specified in the Quality Assurance Section of the Project Plan.

V. Service Level Agreement

In performing and executing this project, it is fully committed by the Contractor that

The implementation and configuration will be performed to the maximum quality desirable implying that all specified deliverables meet the agreed upon acceptance criteria as indicated in the Quality Assurance section of the Project Plan

The overall schedule of the project will be maintained to the designated and agreed upon timeline as baselined in the project plan with tolerances indicated therein

Timely communication and project reporting as per the communication plan (included will be made throughout the whole period of this engagement to ensure prevention of

Page 14: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 14 of 43

any problem or issue that may arise through the whole work and at the same time to enable proactive enhancement of the quality of the assessment to be performed.

Support, training and extended professional service options must be included in the technical bid with the plans, options and contents, and also in the financial bid with the unit price.

VI. Team Structure

The project team will be composed of with resources specified as under;

Role Responsibility GCF Counterparts Project Manager

Responsible for managing and coordinating the overall project. Single point of contact for escalations,

billing issues, personnel matters, contract extensions.

GCF ICT Project Manager

Lead Architect

Responsible for overall technical configuration

GCF Integration and Implementation Specialist

Page 15: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 15 of 43

Annex I-A. Illustrative Accreditation Business Process Maps and Detailed Requirements

The process maps and requirements below are illustrative and only for the reference purpose, and subject to change during the business requirement discovery phase.

I. Pre-Accreditation

Table I.1. OAS requests review OAS requests review Objectives 1. To achieve online communication,

instead of emails, for the management of workflows of OAS requests;

Actors Applicant entities and Secretariat Activities/Functions 1. Applicant to submit the requests and

upload supporting documents as required;

2. Secretariat to review the requests and provide feedback to all applicants;

Page 16: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 16 of 43

3. Secretariat to issue the account to certain applicants only;

4. The system to send automatic notification containing login information of the account to both the Secretariat and the applicant entity;

5. The system to send automatic notifications in case of any status update; and

6. The system to store information of each request being submitted, each round of feedback being provided and each account being issued.

Inputs Submission of the applicant entity’s OAS request (and the nomination letter from the NDA if the entity is a direct access entity)

Outputs 1. Generation of OAS accounts 2. OAS account login information to

applicant entity; and 3. Automated notification to the Secretariat

and the applicant entity Triggers Submission of OAS request Dependencies 1. NDA nomination letter submitted, if a

direct access entity, and acknowledged by the Secretariat

2. Sufficient supporting documents submitted by the entity, reviewed and approved by the Secretariat

Data stores/elements Dates (of submission, feedback provided, issuance, etc) Workflow history (Note: To be added later, as agreed from the previous meeting that we do not need to worry about this item at this stage)

Page 17: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 17 of 43

II. Accreditation

Table II.1. Accreditation – application submission Accreditation Application submission Objectives To receive and acknowledge the applicant’s

application Actors Applicant entities and the Secretariat Activities/Functions 1. Applicant to submit the accreditation

application through the system 2. The system to automatically notify the

Secretariat of the submission 3. The system to automatically acknowledge the

receipt of the submission to the applicant (using the template acknowledgement email with tailored information, if possible)

4. The Secretariat to change the status of workflow

5. The system to archive the date of submission, entity information (name, focal points, country, region, public/private, access modality, etc), application criteria (size, fiduciary and ESS)

Page 18: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 18 of 43

Inputs Filling out the application and uploading the supporting documents online as required

Outputs A complete application by the applicant entity

Triggers Submission of the accreditation application Dependencies OAS account Data stores/elements Date of submission;

Entity information (name, focal points, country, region, public/private, access modality, etc); Application criteria (size, fiduciary and ESS)

Table II.2. Accreditation – preliminary check

Accreditation Preliminary check [Note: the review is done based on the submitted application, but the review comment is released via emails] Objectives To check on the applicant’s application

criteria for the purpose of determining the accreditation fees and issuing the invoice

Actors Secretariat and applicant entities Activities/Functions 1. Secretariat to conduct a preliminary check

on Sections 1 to 3 Scenario 1: if further information needed 2. Secretariat to send questions or comments

to the applicant entity, requesting further information; [Note: this step is currently done through emails, going forward we would like to explore the feasibility of doing this on the system.]

3. Applicant to upload further information online as response to the Secretariat’s questions

Scenario 2: if complete 4. Secretariat to inform the applicant entity of

the invoice preparation and next steps through emails

Inputs Application Outputs Sufficient supporting documents for

application criteria to determine the accreditation scope and accreditation fees

Triggers Submission of application Dependencies Submission of application and sufficient

supporting documents for application criteria

Data stores/elements N/A

Page 19: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 19 of 43

Table II.3. Accreditation – fees and invoices Accreditation Fees and invoices [Note: there is no online system for this workstream] Objectives To prepare invoice template (with tailored

information and fees) for Finance to issue to the applicant entity

Actors Secretariat (Accreditation and Finance) Activities/Functions 1. Accreditation team to prepare the invoice

template and send to Finance team 2. Finance team to generate official invoice and

issue to the applicant entity 3. Finance team to monitor and confirm the

receipt of payment from the applicant entity 4. Accreditation team to archive the invoice

and payment information Inputs Application criteria

Invoice template (automatic generation from the system if possible)

Outputs Invoice Triggers Sufficient supporting documents for

application criteria Dependencies Sufficient supporting documents for

application criteria Data stores/elements Date of invoice preparation

Date of invoice issuance Invoice number Amount of fees Application criteria Date of payment receipt Payment amount

Table II.4. Accreditation – Stage I institutional assessment and completeness check

Accreditation Stage I review Objectives - Secretariat to review the application Sections

1 to 7 and release questions to applicant entities

Note: going forward the Secretariat may only need to review the application Sections 1 to 3, pending the Board’s discussion on the updated accreditation framework - Applicant entities to review the Secretariat’s

questions and provide further information, allowing the entity to be progressed to Stage II (Step 1) review by the Accreditation Panel

Actors Secretariat (i.e. Administrators and Employees), two consultancy firms and applicant entities

Page 20: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 20 of 43

Activities/Functions 1. Secretariat (Accreditation and Procurement) to prepare and assign Statement of Work (SoW) to consultancy firms and receive countersigned SoW Note: this workstream is done offline

2. Secretariat to grant online access to reviewers for applications assigned in the SoW

3. Consultancy firms to conduct the review as assigned in the SoW

4. Consultancy firms send to the Secretariat review remarks and questions Note: this is done offline in word files offline and communications are through emails; going forward we would like to conduct the review online

5. Secretariat to review and conduct quality assurance on the remarks and questions by the consultancy firms

6. Secretariat to release the questions to the applicant entity and update the status of the application

7. Applicant entity to respond to the questions and upload further information onto the system

8. Applicant to resubmit the application 9. Secretariat to conduct subsequent rounds of

review until the completion (or near completion) of Stage I

10. Secretariat to inform applicant entities of completion of Stage I and progress the entity to Stage II (Step 1) review

11. Secretariat to inform the Accreditation panel of new entities progressed to Stage I (Step 1) review

12. Secretariat to archive relevant information (refer the item below related to data stores)

Inputs Application by applicant entities Review remarks by consultancy firms

Outputs Stage I review (word file and online) Triggers Payment of accreditation fees Dependencies Countersigned SoW Data stores/elements Date of each version and response

Timesheet by consultancy firms Time spent by the Secretariat Stage I pipeline dashboard (by region and by status)

Page 21: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 21 of 43

Table II.5. Accreditation – Stage II review by the Accreditation Panel Accreditation Stage II (Step I) review Objectives Accreditation Panel (AP) to review the

application Sections 4 to 7 and release questions to applicant entities Applicant entities to review the AP’s questions and provide further information to complete Stage II (Step I) pending AP’s recommendation

Actors AP, expert consultants to the AP, applicant entities and the Secretariat (i.e. Administrators)

Activities/Functions 1. Secretariat to grant online access to reviewers for applications

2. AP to conduct the review and send to the applicant entity

3. AP Assistant/Secretariat to update the status of workflow

4. Applicant entity to respond to the questions and upload further information onto the system

5. Applicant to resubmit the application 6. AP Assistant/Secretariat to update the status

of workflow 7. AP to conduct subsequent rounds of review

until the completion of Stage II (Step 1) 8. AP to place conditions, if there are any, to

complete Stage II (Step 1) 9. Secretariat to inform applicant entities of

completion of Stage II (Step 1) review 10. Secretariat to archive relevant information

(refer the item below related to data stores) Inputs Application by applicant entities

Stage I review remarks Outputs Stage II (Step 1) review (word file and online) Triggers Completion of Stage I Dependencies Stage I review remarks Data stores/elements Date of each version and response

Timesheet by AP members and experts and the Secretariat Stage II pipeline dashboard (by region and by status)

Page 22: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 22 of 43

Table II.6. Accreditation – Stage II (Step 2) Board decision and Stage III legal agreement Accreditation Stage II (Step II) Board decision Note: offline, however, data stores needed as shown below Data stores/elements Date of accreditation

Decision number Board meeting Accreditation type

Stage III legal agreement Note: offline, however, data stores needed as shown below Data stores/elements Date of AMA signing and AMA

effectiveness Table II.7. Accreditation conditions

Accreditation Conditions [Note: there is no online system for conditions review, but iPMS is used for presenting the status of conditions closure] Objectives To receive and review supporting

documents uploaded by the Accredited Entities (AEs) to close conditions, pending AP’s review and decision

Actors AP members and experts, AEs and Secretariat

Activities/Functions 1. AEs to submit supporting documents on the system

2. System to automatically acknowledge the receipt

3. AP to conduct review on the supporting documents

4. AP to decide whether the conditions are fulfilled

5. Secretariat to update the status on the iPMS Inputs Stage II (Step 1) AP review remarks Outputs Closure of conditions Triggers Timeframe of conditions

AE’s submission of supporting documents to close conditions

Dependencies AE’s supporting documents Data stores/elements Interlinked with iPMS

Page 23: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 23 of 43

III. Post-Accreditation (including re-accreditation)

Table III.1. Institutional monitoring and reporting - annual self-assessment Institutional monitoring and reporting Annual self-assessment Objectives To receive and review AEs’ annual self-

assessment Actors Secretariat (with AP when needed), AEs Activities/Functions 1. AEs to submit annual self-assessment, being

able to build their assessment upon the original accreditation application

2. Secretariat to review and check whether there are any updates in terms of AEs’ policies and procedures that impact their role as an AE

3. If substantial updates found, the AP may need to review

Inputs Annual self-assessment template Outputs Annual self-assessment review Triggers Timeframe on a yearly basis Dependencies AE’s original application Data stores/elements Dates of submission and each version

Conclusions

Page 24: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 24 of 43

Table III.2. Institutional monitoring and reporting – mid-term review Institutional monitoring and reporting Mid-term review Objectives To receive and review AEs’ mid-term

review Actors AP (with support of Secretariat), AEs Activities/Functions 1. AEs to submit mid-term review

2. AP to review and check Inputs Mid-term review template Outputs Mid-term review Triggers Timeframe of year 2.5 Dependencies AE’s original application Data stores/elements Dates of submission and each version

Conclusions Table III.3 Re-accreditation

Re-accreditation Objectives To receive and review the re-

accreditation applications Actors AEs, Secretariat, AP, consultancy firms

and consultants Activities/Functions 1. Same as Table 3.4 and Table 3.5 Inputs Re-accreditation application template Outputs Re-accreditation application review Triggers Timeframe: six months prior to the end

of 5-year accreditation period Dependencies Original application Data stores/elements Date of each version and response

Timesheet by consultancy firms and the AP Time spent by the Secretariat Re-accreditation pipeline dashboard (by region and by status)

Page 25: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 25 of 43

Annex 2 Requirements for Firms’ Proposals Technical Proposal The technical proposal will be submitted in a separate file and will address all aspects of the Terms of Reference. The Technical Proposal shall have all the necessary details in response to the Terms of Reference and the proposer shall fill in the technical Forms (TECH Forms) which follow in this annex and which must be filled in accordingly.

Page 26: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 26 of 43

TECH Forms Form TECH-1: Technical Proposal Submission Form

[Location, Date] To: [Name and address of Client] To whom it may concern: We, the undersigned, offer to provide the consulting services for [Insert title of assignment] in accordance with your Request for Proposal dated [Insert Date] and our Proposal. We are hereby submitting our Proposal, which includes this Technical Proposal, and a Financial. We are submitting our Proposal in association with: [Insert a list with full name and address of each associated Consultant if submitting as an association]

We hereby declare that all the information and statements made in this Proposal are true and accept that any misinterpretation contained in it may lead to our disqualification. If negotiations are held during the period of validity of the Proposal, i.e., before the date indicated in Paragraph Reference 2.6 of the RFP, we undertake to negotiate on the basis of the proposed staff, methodology and approach. Our Proposal is binding upon us and subject to the modifications resulting from Contract negotiations. We undertake, if our Proposal is accepted, to initiate the consulting services related to the assignment. We understand you are not bound to accept any Proposal you receive. We remain, Yours sincerely, Authorized Signature [In full and initials]: Name and Title of Signatory: Name of Firm: Address:

Page 27: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 27 of 43

Form TECH-2: Firm’s Organization and Experience

A - Organization

[Provide here a brief (two pages) description of the background and organization of your firm/entity and each associate for this assignment.]

Page 28: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 28 of 43

B - Experience

[Using the format below, provide information on each assignment for which your firm, and each associate for this assignment, was legally contracted either individually as a corporate entity or as one of the major companies within an association, for carrying out consulting services similar to the ones requested under this assignment. Use not more than 20 pages.]

Assignment name:

Approx. value of the contract (in current US$ or Euro):

Country: Location within country:

Duration of assignment (months):

Name of Client:

Total No of staff-months of the assignment:

Address:

Approx. value of the services provided by your firm under the contract (in current US$ or Euro):

Start date (month/year): Completion date (month/year):

No of professional staff-months provided by associated Consultants:

Name of associated Consultants, if any:

Name of senior professional staff of your firm involved and functions performed (indicate most significant profiles such as Project Director/ Coordinator, Team Leader):

Narrative description of Project: Description of actual services provided by your staff within the assignment:

Firm’s Name:

Page 29: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 29 of 43

Form TECH-3: Comments and Suggestions on the Terms of Reference and on Counterpart Staff and Facilities to be Provided by the Client

On the Terms of Reference

[Present and justify here any modifications or improvement to the Terms of Reference you are proposing to improve performance in carrying out the assignment (such as deleting some activity you consider unnecessary, or adding another, or proposing a different phasing of the activities). Such suggestions should be concise and to the point, and incorporated in your Proposal.]

Page 30: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 30 of 43

Form TECH-4: Description of Approach, Methodology and Work Plan for Performing the Assignment

[Technical approach, methodology and work plan are key components of the Technical Proposal. You are suggested to present your Technical Proposal (Not more than 40 pages, inclusive of charts and diagrams) divided into the following three chapters:

a) Technical Approach and Methodology, b) Work Plan, and c) Organization and Staffing,

a) Technical Approach and Methodology. In this chapter you should explain your understanding of the objectives of the assignment, approach to the services, methodology for carrying out the activities and obtaining the expected output, and the degree of detail of such output. You should highlight the problems being addressed and their importance, and explain the technical approach you would adopt to address them. You should also explain the methodologies you propose to adopt and highlight the compatibility of those methodologies with the proposed approach. b) Work Plan. In this chapter you should propose the main activities of the assignment, their content and duration, phasing and interrelations, milestones (including interim approvals by the Client), and delivery dates of the reports. The proposed work plan should be consistent with the technical approach and methodology, showing understanding of the Terms of Reference and ability to translate them into a feasible working plan. A list of the final documents, including reports, drawings, and tables to be delivered as final output, should be included here. The work plan should be consistent with the Work Schedule of Form TECH-8.

c) Organization and Staffing. In this chapter you should propose the structure and composition of your team. You should list the main disciplines of the assignment, the key expert responsible, and proposed technical and support staff.]

Page 31: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 31 of 43

Financial Proposal The Proposer is required to prepare and submit the Financial Proposal in an envelope separately sealed from the Technical Proposal and included inside the outer envelope to contain both separately sealed proposals. The Financial Proposal should be inclusive of the taxes where applicable3 , and the applicable taxes should be clearly specified. Please do not include any cost related to travel. Any agreed travel shall be subject to applicable guidelines in GCF and relevant costs will be managed accordingly. Airfare tickets shall be provided for Economy class only.

3 (a) Under Article 10 of the Headquarters Agreement, the property of the Green Climate Fund (“Fund”), including the property of any offices, subsidiary bodies or facilities established by the Fund, the Fund’s operations and transactions, and any property of the Fund in transit to or from the Headquarters, are:

(i) Exempt from all direct taxes, except those which are, in fact, no more than charges for public utility services;

(ii) Exempt from all indirect taxes, including any value-added tax and/or other similar tax, and excise duties levied on important purchases of goods and services for official purposes; and

(iii) Exempt from customs duties, prohibitions and restrictions on imports and exports in respect of articles of any kind imported or exported by the Fund for its official use, except for prohibitions and restrictions on imports or exports relating to health and safety.

(b) under bilateral agreements concluded between the GCF and certain countries, the GCF may be exempt from all taxation and from all customs duties, and from any obligation for the payment, withholding or collection of any tax or duty.

Page 32: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 32 of 43

FIN Forms Form FIN-1: Financial Proposal Submission Form

[Location, Date] To: [Name and address of Client] To whom it may concern: We, the undersigned, offer to provide the design and implementation for [Insert title of assignment] in accordance with your Request for Proposal dated [Insert Date] and our Technical Proposal. Our attached Financial Proposal is for the sum of [Insert amount(s) in words and figures1]. This amount is inclusive of the taxes where applicable2. Our Financial Proposal shall be binding upon us subject to the modifications resulting from Contract negotiations, up to expiration of the validity period of the Proposal, i.e. before the date indicated in Paragraph 2.6 of this RFP. We understand you are not bound to accept any Proposal you receive. We remain,

Yours sincerely,

Authorized Signature [In full and initials]: Name and Title of Signatory: Name of Firm: Address:

1 Amounts must coincide with the ones indicated under Total Cost of Financial proposal in Form FIN-2. 2 (a) Under Article 10 of the Headquarters Agreement, the property of the Green Climate Fund (“Fund”), including the property of any offices, subsidiary bodies or facilities established by the Fund, the Fund’s operations and transactions, and any property of the Fund in transit to or from the Headquarters, are: (i) Exempt from all direct taxes, except those which are, in fact, no more than charges for public utility services; (ii) Exempt from all indirect taxes, including any value-added tax and/or other similar tax, and excise duties levied on important purchases of goods and services for official purposes; and (iii) Exempt from customs duties, prohibitions and restrictions on imports and exports in respect of articles of any kind imported or exported by the Fund for its official use, except for prohibitions and restrictions on imports or exports relating to health and safety. (b) under bilateral agreements concluded between the GCF and certain countries, the GCF may be exempt from

all taxation and from all customs duties, and from any obligation for the payment, withholding or collection of any tax or duty.

Page 33: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 33 of 43

Form FIN-2: Financial Proposal Submission Template

A. Cost Breakdown

Deliverable Quantity Cost (in

USD) Cost Breakdown and Remarks (Please specify detailed breakdown of the cost for each deliverable, including any professional services costs)

I. Solution Cost

I. 1. Annual Subscription of Cloud Hosted iBPMS Platform User Licenses, as illustrated in Annex I. 2.5 (If there is no cloud hosting available for proposing platform, please clearly indicate that the platform requires GCF infrastructure (VPC, etc.))

100 Users (with different usage patterns. See Annex I.2.5)

I. 2. (Optional) Additional Per Year Per User platform license

Per User Per Year (List all user-type options, and indicate the cost of each options. If there is quantity discount tiers, please also describe them as well.)

II. Implementation and Integration

II. 1. Professional services related to technical implementation of OAS 2.0 as indicated in Annex I.

Total Service Charge

II. 2. (Optional) Additional Professional Service for developing a new module on the proposed platform, integration to other systems, or enhancement of the existing module

Hourly Rate (List all grade levels if applicable)

Page 34: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 34 of 43

B. Total Cost of Financial Proposal

Item

Costs

Indicate with Currency

Total Costs of Financial Proposal (I.1 + II. 1 of Table A)

Page 35: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 35 of 43

Annex 3 Evaluation Criteria A. Evaluation and Comparison of Proposals 1. The proposals will be evaluated in a three-stage procedure, starting with administrative compliance to

ensure the proposals includes all necessary required documents and is duly signed by the authorized representative. Evaluation of the technical proposal will follow and will be completed prior to any financial proposal being opened and evaluated. The financial proposal will be considered only if the submissions fulfil the minimum technical requirements.

B. Acceptance of Submissions 2. All proposers are expected to adhere to the requirements for submitting a proposal. Any proposals that

fail to comply will be disqualified from further consideration as part of this evaluation. In particular:

• Full compliance with the formal requirements for submitting a proposal • Submission of all requested documentation • Acceptance of the GCF Model contract – Where the proposer notes issues, these must be raised as part of the technical proposal for consideration during evaluation

3. The Technical Proposal shall include:

• A brief description, including ownership details, date and place of incorporation of the firm, objectives of the firm, partnerships, qualifications, certificates, etc.;

• Details to demonstrate vast experience in working with relevant multilateral development funds and familiarity with their operations; and

• Demonstration of the firm’s deep understanding of the GCF, mandate/business model and Investment Framework.

C. Evaluation of Technical Proposal

4. A reviewing committee shall be established to evaluate each technical proposal. The technical proposal

is evaluated individually on the basis of its responsiveness to the technical requirements and will be assessed and scored according to the evaluation criteria below and as per scores in the table.

Evaluation Criteria

Summary of Technical Proposal Evaluation Forms Score Weight

Points Obtainable

1 Expertise of Firm / Organization 30% 300

2 Proposed Methodology, Approach and Implementation Plan 35% 350

3 Management Structure and Key Personnel 35% 350

TOTAL 100% 1000

Page 36: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 36 of 43

Technical Proposal Evaluation (FORM I)

Expertise of the Firm/Organization Points Obtainable

1.1 Reputation of Organization and Staff / Credibility / Reliability / Industry Standing

• firms can provide relevant documents (certificate, report etc…) as applicable

50

1.2 General Organizational Capability which is likely to affect the implementation

- Financial Stability

- Loose consortium, Holding company or One firm

- Age/size of the firm

- Strength of the Project Management Support

- Project Financing Capacity

- Project Management Control

75

1.3 Proportion of firm’s own engagement in the implementation

• firms shall state clearly (if that is the case) which part (s) of the tasks/Deliverables they intend to sub-contract

25

1.4 Quality assurance procedure, warranty 75

1.5 Relevance of:

- Specialized Knowledge

- Experience on Similar Programme / Projects

- Experience on Projects in the Region

75

SUB TOTAL 300

Technical Proposal Evaluation (FORM II)

Proposed Methodology, Approach and Implementation Plan Points Obtainable

2.1 To what degree does the Proposer understand the task? 25

2.2 Have the important aspects of the task been addressed in sufficient detail?

25

2.3 Are the different components of the project adequately weighted relative to one another?

20

Page 37: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 37 of 43

2.4 Is the proposal based on a thorough assessment and understanding of the project context and was this data input properly used in the preparation of the proposal?

50

2.5 Is the conceptual framework adopted appropriate for the task? 50

2.6 Is the scope of task well defined and does it correspond to the ToR? 100

2.7 Is the presentation clear and are the sequence of activities and the planning logical, realistic and promise efficient implementation to the project?

80

SUB TOTAL 350

Technical Proposal Evaluation (FORM III)

Management Structure and Key Personnel Points Obtainable

3.1 Task/Project Team /Team Leader

General Qualification: Suitability for the Project

International experience 50

Training experience 25

Professional experience in the area of specialization (BPM, AI, RPA etc.) 150

Knowledge of Workflows Design, Document Databases & UI design and related technical sectors

100

English language qualification 25

SUB TOTAL 350

Technical proposals that score at least 750 points out of 1000 will be considered as qualified for the review of financial proposal. Any proposal less than that will be disqualified from proceeding to the next step and its financial proposal shall be returned unopened following the award of the contract. D. Evaluation of Financial Proposal

The financial proposal of all proposers which have attained the minimum score in the technical evaluation will be evaluated subsequently. The lowest evaluated Financial Proposal (Fm) is given the maximum financial score (Sf) of 100. The formula for determining the financial scores (Sf) of all other Proposals is calculated as following: Sf = 100 x Fm/ F, in which “Sf” is the financial score, “Fm” is the lowest price, and “F” is the price of the proposal under consideration. E. Consolidated evaluation

The weights given to the Technical (T) and Financial (P) Proposals are:

Page 38: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 38 of 43

T = 0.80, and P = 0.20 Proposals will be ranked according to their combined technical (St) and financial (Sf) scores using the weights (T = the weight given to the Technical Proposal; P = the weight given to the Financial Proposal; T + P = 1) as following: S = St x T% + Sf x P%. The firm achieving the highest combined technical and financial score will be invited for contract negotiations. F. Award

The Award will be made to the responsive proposer who achieves the highest combined technical and financial score, following negotiation of an acceptable contract. GCF reserves the right to conduct negotiations with the Proposer regarding the contents of their offer. The award will be in effect only after acceptance by the selected proposer of the terms and conditions and the technical requirements.

Page 39: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 39 of 43

Annex 4 Company Profile Form Please respond to all questions.

Company details - vendor’s name

Name:

General Information

Primary contact for sales/client services

Address Postal Code: Country: Telephone: Fax: E-mail: Web site: Parent company, if any Subsidiaries, Associates, and/or Overseas Rep(s), if any

Year established Registration Number Type of organization Public enterprise ( )

Private company ( ) Organization sponsored (assisted by Government) ( ) Other (please specify): ….. ( )

Type of Business Manufacturer ( ) Retailer ( ) Authorized Agent ( ) Consulting Company ( ) Other (please specify): ….. ( )

Summary of main business activities

No. of employees (by location)

Staff turnover rate In-house working language (s)

Bank Name: Bank Address: Account Holder: Account Number: IBAN: SWIFT:

Prior experience with international organizations

List contracts with international organizations in the last three years BRIEFLY list recent contracts that used relevant tools, technologies, and techniques: Attach additional sheets if necessary. 1 2 3

Page 40: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 40 of 43

Environmental Policy

Does your company have a written statement of its environmental policy? YES ( ) Please attach copy NO ( )

Contract disputes

List any disputes your company has been involved in over the last three years

References

List suitable reference projects and contacts. What options would there be for a site visit to a reference project and/or the vendor’s site? 1 2 3

Partners

If this is a part bid, list relevant recent experience of working with partners. Are there already formal or informal preferred partnership agreements in place? 1 2 3

Conflict of interest

Are there any likely circumstances or contracts in place that may introduce a conflict of interest with the parties to this contract? If so, explain how this will be mitigated 1 2

Certification

I, the undersigned, confirm that the information provided in this annex is correct. In the event of changes, details will be provided. Name: __________________________ Title: _________________________ Signature: __________________________ Date: _________________________

Page 41: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 41 of 43

Annex 5 Acknowledgment Letter

To whom it may concern,

We, the undersigned, acknowledge receipt of your Request for Proposal (RFP) No. RFP/2020/S/001 dated 11 February 2020, and hereby confirm that we:

[ ] INTEND [ ] DO NOT INTEND

to submit a proposal to the secretariat of the Green Climate Fund (GCF) by the deadline date of 9 March 2020, and that we:

[ ] INTEND [ ] DO NOT INTEND

to send one (1) authorized representative to observe the public opening procedure on 11 March 2020 17:30 Hrs Korean Time (Note: attendance to the public opening procedure is optional.) We acknowledge that this RFP is confidential and proprietary to the GCF, and contains privileged information.

Name of Authorized Representative:________________________________________

Signature: ________________________________________ Title: ________________________________________ Name and Address of Vendor: ________________________________________ ________________________________________ ________________________________________ Telephone: ________________________________________ Facsimile: ________________________________________ If you do not intend to submit a proposal to the GCF, please indicate the reason:

[ ] We do not have the capacity to submit a proposal at this time. [ ] We cannot meet the requirements for this RFP. [ ] We do not think we can make a competitive offer at this time. [ ] Other (please specify): ____________________________________________________

Kindly return this acknowledgement letter immediately via e-mail to [email protected] NOTE: Due to current security arrangements, your authorized representative must present a completed copy of this letter in order to observe the public opening procedure.

Page 42: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 42 of 43

Annex 6 Timeline The Green Climate Fund will follow the timeline below for this RFP. Any changes to this timeline will be posted on the GCF website. Please note that the target dates and may be adjusted.

Event Responsible Party Date (and time, KST*)

1 Issuance of RFP GCF 11 February 2020 2 Last day to send completed

Acknowledgement Letter of RFP receipt

Tenderer 2 March 2020

3 Last date for requests for clarification of the RFP

Tenderer 2 March 2020 17:00 Hrs Korean Time

4 Last date to reply to questions received/ Last date for amendment

GCF 4 March 2020

5 Date by which proposal must be received in Korea by GCF

Tenderer 11 March 2020; 17:00 Hrs Korean Time

6 Date of opening of Technical Proposals GCF 11 March 2020; 17:30 7 Notice of successful provider GCF 30 April 2020 8 Contract signing GCF/Tenderer 4 May 2020 9 Work start Tenderer 11 May 2020

* KST: Korean Standard Time (Seoul Time)

Page 43: System Design and Implementationfor intelligent Business ... · experienced Firm to provide design and implementation for intelligent Business Process Management System for Accreditation

Page 43 of 43

Annex 7 GCF Model Contract By submitting a proposal to this RFP, Bidders are considered to have carefully reviewed the GCF Model Contract and be in agreement with all its terms and conditions. Where the bidder has specific issues of concern, those must be raised and indicated in the Technical proposal clearly for consideration during evaluation. Any request of amendments to GCF Model Contract and terms and conditions must be accompanied by detailed and compelling justification for review and consideration by GCF. It should be noted that request of amendments to GCF Model Contract and terms and conditions may negatively affect evaluation of the proposal and, in some cases, where such amendments are incompatible with GCF’s binding policies and rules, may prejudice the final award. NB: For this particular contract, the Performance Standards (Clause 8), Insurance (Clause 9), Performance Security (Clause 10) and Deductions Clauses (Clause 11) of the SCC will not be applicable. *Note: The Board adopted at the recent meeting a new policy on SEAH (Sexual Exploitation, Sexual Abuse and Sexual Harassment) and therefore the GCF is required to include new provisions in the General Conditions of Contract. While the specific wording is yet to be formulated, the eventual contract will need to include such new provisions.