+ All Categories
Home > Documents > T hanks to Benjamin Todd & Markus Zerlauth

T hanks to Benjamin Todd & Markus Zerlauth

Date post: 23-Feb-2016
Category:
Upload: chessa
View: 34 times
Download: 0 times
Share this document with a friend
Description:
T hanks to Benjamin Todd & Markus Zerlauth. Outline. LHC Machine Interlocks overview Powering Interlocks systems Beam Interlock system Characteristics & Layout Performance Monitoring & Operational checks Summary. Protection Functions. Beam Energy (360 MJ). Beam Dump. - PowerPoint PPT Presentation
Popular Tags:
33
LHC Machine Interlocks & Beam Operation ARW2011 Bruno PUCCIO (CERN) 13 th April 2011 1v0 Thanks to Benjamin Todd & Markus Zerlauth
Transcript
Page 1: T hanks to Benjamin Todd & Markus Zerlauth

LHC Machine Interlocks& Beam Operation

ARW2011Bruno PUCCIO (CERN) 13th April 2011

1v0

Thanks to Benjamin Todd & Markus Zerlauth

Page 2: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 2

2

Outline

LHC Machine Interlocks overview Powering Interlocks systems Beam Interlock system

Characteristics & Layout Performance Monitoring & Operational checks

Summary

Page 3: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 3

3

10-20x energy per magnet of TEVATRONmagnet quenched = hours downtime

many magnets quenched = days downtime

(few spares)

100x energy of TEVATRON

Emergency DischargeMagnet Energy (10 GJ)Powering Protection:

Beam DumpBeam Energy (360 MJ)Beam Protection:

magnet damaged = $1 million, months downtimemany magnets damaged = many millions, many months downtime

0.000005% of beam lost into a magnet = quench0.005% beam lost into magnet = damage

Failure in protection – complete loss of LHC is possible

Protection Functions

LHC is to a large extent a super-conducting machine: 1232 main dipoles, ~400 main quadrupoles and more than 8000 correctors

Page 4: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 4

What are the “Machine Interlocks”?

4

Beam Interlock System(VME based)

for protecting Normal Conducting Magnets

for protecting the Equipments for Beam Operation

BIS

Fast Magnet Current change Monitor

FMCM

Powering Interlock Controllers(PLC based)

+

PIC

Warm magnet Interlock Controllers(PLC based)

WIC+

Safe Machine Parameters

System(VME based)

SMP

or Super Conducting Magnets

Page 5: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 5

LHC Machine Interlocks Hierarchy

5

( Machine Interlocks systems in red )

EXPERIMENTS

Page 6: T hanks to Benjamin Todd & Markus Zerlauth

LHC Magnet & Powering Interlock Systems

Page 7: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 7

Key facts for Powering Interlock Systems

7

Both powering interlock systems use of industrial electronics (SIEMENS PLCs with remote I/O modules)

Distributed systems corresponding to LHC machine sectorization

All critical signals are transmitted using HW links (Fail safe signal transmission, built in redundancy)

All circuit related systems OK => Power Permit, else dump beams and activate Energy extraction (if any)

Reaction time: Reaction time:

36 controllers for Superconducting magnets (PIC system)

8 controllers for Normal Conducting

magnets (WIC)

~ 1mS 100 ms

~ 10’000 superconducting magnets:powered in 1600 electrical circuits

140 normal conducting magnets powered in 44 electrical circuits(in the LHC) And more than 1000 magnets in the injectors chain

Superconducting circuit protection: Normal Conducting circuit protection:

Page 8: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

SCADA application: monitoring views…

8

Magnets status

PowerConv.status

SPS Transfer Lines

SCADA: Supervisory Control and Data Acquisition

Courtesy of F.Bernard (CERN)

Permit A

Permit B

Page 9: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

SCADA application: History Buffer

9

Page 10: T hanks to Benjamin Todd & Markus Zerlauth

Beam Interlock System

1v0 10

Page 11: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 11

Beam Interlock System Function

BIS

User ‘Permit’ Signals

Dumping system orExtraction Kicker or

Beam Stopper orBeam source….

Targetsystem

Beam ‘Permit’ Signals

Σ(User Permit = “TRUE” ) => Beam Operation is allowed

IF one User Permit = “FALSE” => Beam Operation is stopped

Page 12: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Beam Interlock System: quick overview

12

User Interfaces

UserPermit

#1

#14

#2

(installed in User’s rack)

Beam Interlock Controller

(VME chassis)

copper cables

User System #1

User System #2

User System #14

frontrear

Opticaloutputs

copper cablesor

fiber optics links

Remote User Interfaces safely transmit Permit signals from connected systems to Controller

Controller acts as a concentrator

collecting User Systems Permits

generating local Beam Permit

Controllers could be daisy chained (Tree architecture) or could share Beam Permit Loops (Ring architecture)

JAVA Application

Configuration DB

Technical Network

Front End Software Application

local Beam Permit

Cupper links

Page 13: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 13

LHC Beam Permit Loops

Square wave generated at IR6:Signal can be cut and monitored by any Controller

When any of the four signals are absent at IR6, BEAM DUMP!

4 fibre-optic channels:1 clockwise & 1 anticlockwise for each beam

but they can be linked (or unlinked)

17 Beam Interlock Controllers per beam(2 per Insertion Region (IR) + 1 near Control Room)

Beam-1 / Beam-2 loops are independent

Page 14: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Beam Interlock Systems currently in Operation

50 Controllers

In total:

~ 370 connected systems

SPS to LHC Transfer lines

14 c.

SPS ring (since

2006)

6 c.4 c.

LHC Injection regions

LHC ring (since 2007)

34 controllers

14

Resistors 65’160Capacitors 32’612Connectors 9’543Inductors 72

Relays 1’204Optocouplers 4’816

Integrated Circuits 12’508

PLDs 884Diodes 32’007

Transistors 12’204Regulators 224

Fuses 1’204ELED Transm. 72PIN Receivers 72

All components

172’582

VME power supply & VME-bus Controller not taken into account

Page 15: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Performance (1/3)

Safe: (Safety Integrity Level 3 was used as a guideline).

Must react with a probability of unsafe failure of less than 10-7 per hour and,Beam abort less than 1% of missions due to internal failure (2 to 4 failures per year).  

Reliable: (whole design studied using Military and Failure Modes Handbooks)

Results from the LHC analysis are: P (false beam dump) per hour = 9.1 x 10-4

P (missed beam dump) per hour = 3.3 x 10-9

15

Fail Safe concept: Must go to fail safe state whatever the failure

Available: Uninterruptable Powering (UPS)) Redundant Power Supply for Controller (i.e. VME crate)Redundant Power Supply for Remote User Interface

Page 16: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Performance (2/3)

Critical process in Hardware: ♦ functionality into 2 redundant matrices♦ VHDL code written by different engineers following same specification.

Critical / Non-Critical separation: ♦ Critical functionality always separated from non-critical.♦ Monitoring elements fully independent of the two redundant safety channels.

16

Manager board

FPGA chip(Monitoring part)

CPLD chip(Matrix A)

CPLD chip(Matrix B)

Used CPLD: 288 macro-cells & 6’400 equivalent gates

Used FPGA: 30’000 macro-cells & 1 million gates + all the built in RAM ,etc.

FPGA: Field Programmable Gate ArrayCPLD: Complex Programmable Logic Device

Page 17: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Performance (3/3)

100% Online Test Coverage: Can be easily tested from end-to-end in a safe manner => recovered “good as new”

17

Fast: ~20μS reaction time from User Permit change detection

to the corresponding Local Beam Permit change

Modular

Page 18: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Control Room GUIs

18

Page 19: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Feature

YESFALSE

Within a fixed partition, half of User Permit signals could be remotely masked

“Flexible”: thanks to Input Masking

Masking automatically removed when

Setup Beam Flag= FALSE

Masking depends on an external condition: the Setup Beam Flag- generated by a separate &

dedicated system (Safe Machine Parameters)

- distributed by Timing

19

Page 20: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

History Buffer

time

Page 21: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Application: Timing Diagram

Courtesy of J.Wenninger (CERN)

Page 22: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Operational Checks

Post-Operation checks (included in Post Mortem analysis )

Pre-Operation checks (launched by Beam Sequencer)

configuration verification and integrity check

fault diagnosis

and monitoring

During Operation (DiaMon application)

response analysis

In order to ensure that safety is not compromised, the verification is carried out in three stages

Page 23: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 23

23

Operational experience

Originally designed for LHC and firstly installed in its pre-injector for validation. Fully operational since 2006 for the SPS ring and its transfer lines. Since restart in Nov.09, LHC-ring BIS extensively exercised with more than 1000

emergency dumps. Promising overall availability (only few failures with redundant VME Power Supplies

and with VME Processor boards)

Very high availability concerning in-house part (99.996%) with only one stop due to a failure.

Concerning the remote User Interfaces: as foreseen, some PSU failed; thanks to

redundancy, it has not lead to a beam operation disruption.

Beam Interlock System

Very good experience for both Powering Interlock Systems. Already > 4 years of operation (starting with initial LHC Hardware Commissioning)Highly dependable (only two failures in more than 4 years)

Powering Interlock Systems

Page 24: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 24

LHC 2010 run: downtime distribution

24

0 1 2 3 4 5 6

QPSCryogenics

PCEL+UPS

InjectorsAccess sys tem

LBDSCol l imators

ControlsRFOP

BLMCV

Q, Qp FeedbacksExperiments

NOFMKI

VacuumBICPIC

Alarm-fi re IT

IQCsetti ngs

BPMTiming

SoftQuench

%

Powering Interlock System Beam Interlock System

Warm Magnet Interlock System : 0

(percentage of total downtime)%

Page 25: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 25

Summary (1/2)

25

Core of the LHC machine protection Fail Safe concept Fast and modular Fully redundant and Critical process separated from Monitoring Redundant Power Supplies + UPS On-line Testable => recovered “As Good As New” end-to-end

Automated tools to perform regular and quick validation:- internal to Beam Interlock System - external in involving connected systems

 

Page 26: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 26

Summary (2/2)

26

Embedded features for monitoring and testing internal interlock process

Together with powerful GUI application:- it provides clear and useful information to Operation crew- it minimize machine downtime

 

3-stage verification:- Validation prior to beam operation (Pre-Operational checks)- On-line diagnostics during beam operation

- Post Operation checks

Reliable systems:

in operation since few years with a reduced number of aborted beam

operations due to internal failure. 

Page 27: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April [email protected] 27

CERN

Thank you for your attention

Page 28: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Spare

28

Page 29: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

Protection of NC magnets

29

based on Safety PLC collect input signals from: - thermo-switches, - flow meters,

- red buttons, … give Power Permit for the

corresponding converter

Magnet 1

Power Converter

Magnet 2

PC Status

Thermoswitches Water FlowRed button…

Several thermo-switches @ 60°C

Power Permit

PVSS Operator ConsoleEthernet

PLC + I/OsBeam Permit

BIS interface

WIC solution = PLC crate + remote I/O crates

Profibus-Safe link

remote I/Os

Configuration DB

NC = Normal Conducting

Page 30: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

WIC: remote test feature

30

- Facilitate as-good-as-new testing

- perform thanks to relays implanted into the magnet interlock boxes.

- simulate the opening of the thermo-switches or the flow sensors.

Guarantee the system integrity; in particular after an intervention on the magnet sensors or after a modification of the configuration file.

Thermo-Switch

Test Button

Test Relay

magnet interlock box

PLC OUTPUT

PLC INPUT

NE4 or NE8 cableWIC

WIC: remote test feature

Page 31: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 31

Protection of SC magnets / circuits

31

Magnet 1

Power Converter

Magnet 2

HTS Current Leads

sc busbar

DFB

Internal failures / Ground Faults

Cooling FailuresAUG, UPS, Mains Failures

Normal conductingcables

Quench Signal

Superconducting Diode

Energy Extraction

Quench-Heater

QPS + nQPS

Power Permit

Powering Interlock Controller

CRYO_OK

Beam PermitBIS interface

SC = Super Conducting Courtesy of M. Zerlauth (CERN)

Page 32: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011 32

Fast Magnet Current Change Monitors

Magnet 1

Power Converter

Magnet 2

Beam Dump to BIS

Fast Magnet Current Change Monitors are (strictly speaking) not interlocking powering equipment

Installed on nc magnets with << natural τ (injection/extraction septas, D1 magnets in IR1/IR5, …) and large impact on beam in case of powering failures

DESY invention which has been ported with great success to LHC and SPS-LHC transfer lines

U_circuit

Courtesy of M. Zerlauth (CERN)

Page 33: T hanks to Benjamin Todd & Markus Zerlauth

Bruno PUCCIO ARW2011 – 13th April 2011

BIS Hardware

CIBD

CIBMCIBT

CIBMD & CIBTD

CIBO

CIBG

CIBI

CIBS

CIBFu & CIBFc

CIBX

More than 2000 boards produced

(~85% in operation)

CIBU

CIBECIBP

CIBTD & CIBMD


Recommended