Date post: | 13-Jan-2016 |
Category: |
Documents |
Upload: | angel-dean |
View: | 214 times |
Download: | 0 times |
T2K Secondary Beamline – Status of RAL Contributions
Chris Densham, Mike Fitton, Vishal Francis, Matt
Rooney, Mike Woodward, Martin Baldwin, Dave Wark
Chris Densham UKNF Oxford 16 Sept 2008
Is T2K Target work relevant for a Neutrino Factory?
• Ken Long said (yesterday) of the UK Neutrino Factory effort:
”[we] need to exploit…partnership with T2K to enhance targetry work “
• So – here is what I did in Japan (instead of) summer holidays…
Chris Densham UKNF Oxford 16 Sept 2008
T2K Secondary Beam Line
DV
TS
BD
Hadron Absorber (Beam Dump)•graphite core in helium vessel
Target station (TS) •Target & horns in helium vessel •Helium vessel and iron shields cooled by water Decay Volume (DV)
•94m long helium vessel cooled by water•6m thick concrete shield
‘280 m’ neutrinodetector
50 GeV PS ring
Primary beam lineFast extraction
Kamioka
Chris Densham UKNF Oxford 16 Sept 2008
UK/RAL responsibilities on T2K Beamline
• Beam window
• Baffle
• Target
• Target support & remote handling
0.75 MW operation
“
“
• Beam dump 3-4 MW operation
Chris Densham UKNF Oxford 16 Sept 2008
5
BeamBeam
Aluminum cast Aluminum cast cooling modulescooling modules
Graphite Blocks
4,6
90
4,6
90
Beam Dump / Hadron Absorber
Displacement (max) = 8.5 mm
Chris Densham UKNF Oxford 16 Sept 2008
6
Hadron Absorber Module
• All 14 modules assembled • Frame production now on progress• Overall assembly will be in Sep.• Installation will be in Oct.
Jan.24’08
Apr.11’08
Chris Densham UKNF Oxford 16 Sept 2008
Target Station
Chris Densham UKNF Oxford 16 Sept 2008
T2K Target area
Inner iron shields
Inner concrete shields
Support structure= Helium vessel(being constructed by Mitsui Ship. Co.)
Baffle Target and 1st horns2nd horns
3rd horns
Beam window
Chris Densham UKNF Oxford 16 Sept 2008
Proton Beam Window + pillow seals
Chris Densham UKNF Oxford 16 Sept 2008
Installation check in TS using dummy window August 08
(Actual window installationOctober 08)
Chris Densham UKNF Oxford 16 Sept 2008
Baffle / Collimator – to be installed Oct 08
Chris Densham UKNF Oxford 16 Sept 2008
T2K Target basic requirements
• Phase I Beam power: 0.75 MW at 30-40 GeV– Graphite rod, 900 mm long = 2 interaction lengths– NB Only 3% of Beam Power is dissipated in target as
heat c.20 kW – Start-up date: 1st April 2009
• Phase II (SuperBeam) power: 3-4 MW– A future aspiration (still < 100 kW deposited in target)– The only components currently designed for 3-4 MW
operation are the hadron absorber (beam dump) and decay volume
Chris Densham UKNF Oxford 16 Sept 2008
Graphite to titanium diffusion bond
Graphite-to-graphite bond
Flow turns 180° at downstream
window
Inlet manifold
Outlet manifold
Upstream
Window
Target Design:
Helium cooling path
Chris Densham UKNF Oxford 16 Sept 2008
Steady state target temperature
30 GeV, 0.4735Hz, 750 kW beam
Radiation damaged graphite assumed (thermal conductivity 20 [W/m.K] at 1000K- approx 4 times lower than new graphite)
Maximum temperature = 736˚C
Chris Densham UKNF Oxford 16 Sept 2008
Pressures (gauge)Pressure drop = 0.792 bar
Helium cooling velocity streamlinesMaximum velocity = 398 m/s
Chris Densham UKNF Oxford 16 Sept 2008
Target Integration with 1st Magnetic Horn – 2 weeks ago!
Chris Densham UKNF Oxford 16 Sept 2008
Target installed within 1st magnetic horn
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Pulsed beam induced thermal stress waves in target graphite
Max. Von Mises Stress = 7 MPa - cf graphite strength
~37 MPa – should be OK
8 bunches/spill
Bunch length: 58ns (Full width)
Bunch spacing: ~600(300) ns
Rep. rate: 0.47 Hz
Spill width ~5s
Chris Densham UKNF Oxford 16 Sept 2008
IG 43 graphite
200 MeV proton fluence
~10^21 p/cm2
c. 1 year operation in T2K
Radiation Damage in IG43 Graphite - data from Nick Simos, BNL
Chris Densham UKNF Oxford 16 Sept 2008
Target exchange system – under construction
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Chris Densham UKNF Oxford 16 Sept 2008
Options for Neutrino Superbeams
• Static target difficult beyond 1 MW beam power – problems
include:
– Power dissipation
– Thermal stress
– Radiation damage
– High helium flow rate, large pressure drops or high temperatures
• Expect to replace target increasingly often as beam power
increases
• Is it possible to combine a moving target with a magnetic horn?
• New target technology may be necessary
• Difficult to combine liquid metal with a magnetic horn – how
about flowing powder?
Prototype Powder Jet Plant Status
Ottone Caretta, Tristan Davenne, Chris Densham, Peter Loveridge (Rutherford Appleton Laboratory),
Richard Woods (Gericke Ltd), Tom Davies (Exeter University)
Chris Densham UKNF Oxford 16 Sept 2008
Helium
Beam window
beam
Helium
Powder hopper
A flowing powder target for a Superbeam or Neutrino Factory?
Magnetic horn
Chris Densham UKNF Oxford 16 Sept 2008
A flowing powder target for a Superbeam or Neutrino Factory?
• Flowing powder can either be an open jet (a la Merit) or contained within a pipe
• T2K upgrade? Suitable materials – bulk density c.f. graphite, e.g. TiO2.
• Neutrino factory - tungsten powder? • First experiments conducted with open jet of
tungsten as most difficult case – lower density materials should be easier!
Chris Densham UKNF Oxford 16 Sept 2008
The prototype powder jet rig
Chris Densham UKNF Oxford 16 Sept 2008
=3/10bar=~atmwater supplycontains powder
1
2 34
5
7
8
6
91011
12
Powder jet plant – functional layout
Chris Densham UKNF Oxford 16 Sept 2008
Powder jet plant status
• Risk Assessment, interlocks and controls functional specification complete
• October 08: wiring of interlocks and control system (DL controls group)
• November 08: Start running!
Chris Densham UKNF Oxford 16 Sept 2008
Tungsten powder open jet first results:
(Thanks to EPSRC Intrument Loan Pool for use of a high speed video camera)
2
cm
30 cm
Chris Densham UKNF Oxford 16 Sept 2008
P0= 4.9 bar (abs)
P1= 1 bar (abs)
Initial bulk density
= 8660 kg/m3
= 45 % W (by volume)
Jet bulk density (approx. results):Jet velocity = 7-15 m/s(100 kg in 8 seconds)
~ 5000 kg/m3
~ 28 % W by vol.
(~ 2.5 x graphite density)
Tungsten powder jet – feasibility test results