Bund testing Additional information
1 Yes
2 Please provide integrity testing frequency period 3 years
3 Yes
Bund/Containment
structure ID Type Specify Other type Product containment Actual capacity Capacity required* Type of integrity test Other test type Test date
Integrity reports
maintained on
site? Results of test
Integrity test failure
explanation <50 words Corrective action taken
Scheduled date
for retest
Results of
retest(if in
current
reporting year)
PB001 reinforced concrete Diesel 2500 l 1000 l Hydraulic test 30/08/2010 Yes Pass
PB002 reinforced concrete Chemical 6.2 m3 5m3 Hydraulic test 30/08/2010 Yes Pass
PB003 reinforced concrete Chemical 83.5 m3 54 m3 Hydraulic test 16/05/2011 Yes Pass
PB004 reinforced concrete Chemical 46 m3 44 m3 Hydraulic test 30/09/2011 Yes Fail
The total permisable drop in
level exceded the parameter
set out in BS8007 over a 24
hour period.
Cleaned and repaired floor
of Bund Q2 2012
PB005 reinforced concrete Chemical 3.6 m3 1 m3 Hydraulic test 30/08/2010 Yes Pass
PB006 reinforced concrete Chemical 52 m3 49 m3 Hydraulic test 30/08/2010 Yes Pass
PB007 reinforced concrete Chemical 114 m3 50m3 Hydraulic test 30/06/2011 Yes Pass
PB008 reinforced concrete Chemical 484 m3 400 m3 Hydraulic test 30/03/2009 Yes Pass
PB009 reinforced concrete Chemical 1622 m3 1430 m3 Hydraulic test 28/01/2009 Yes Pass
PB010 reinforced concrete Chemical 18 m3 18 m3 Hydraulic test 23/07/2009 Yes Pass
PB012 reinforced concrete Chemical 18.7 m3 24.2 m3 Hydraulic test 16/05/2011 Yes Pass
PB013 reinforced concrete Chemical 30 m3 26m3 Hydraulic test 16/03/2009 Yes Pass
PB-011 reinforced concrete Chemical 5.5 m3 2.2 m3 Hydraulic test 17/07/2009 Yes Pass
* Capacity required should comply with 25% or 110% containment rule as detailed in your licence Commentary
4 bunding and storage guidelines Yes
5 Are channels/transfer systems to remote containment systems tested? Yes
6 Are channels/transfer systems compliant in both integrity and available volume? Yes
7 No
Not in place where overflow
mechanisms are on place
8 N/A
1 Yes
2 Please provide integrity testing frequency period 3 years
Structure ID Type system Material of construction:
Does this structure have
Secondary containment?
Type of secondary
containment
Type integrity testing
Integrity reports
maintained on site? Results of test
Integrity test failure
explanation <50
words
Corrective action
taken
Scheduled date
for retest
Results of retest(if in current
reporting year)
P74-P75 Process pvc No SELECT Hydraulic Yes Pass SELECT
P74 - WWTP Process concrete No Hydraulic Yes Pass
P54 - P54 A Process concrete No Hydraulic Yes Pass
P53 - P54 Process concrete No Hydraulic Yes Pass
P53-P53A Process concrete No Hydraulic Yes Pass
P52 - GA2 Process pvc No Hydraulic Yes Pass
P52 - GA1 Process pvc No Hydraulic Yes Pass
P51 - G10 Process pvc No Hydraulic Yes Pass
P52 - P51 Process pvc No Hydraulic Yes Pass
P52 - Int G Process pvc No Hydraulic Yes Pass
P50 - P51 Process pvc No Hydraulic Yes Pass
P50 - P49 Process pvc No Hydraulic Yes Pass
P48 - P49 Process pvc No Hydraulic Yes Pass
P46-P47 Process pvc No Hydraulic Yes Pass
P46-P46A Process pvc No Hydraulic Yes Pass
P46A - P45 Process pvc No Hydraulic Yes Pass
P43-P44 Process polypropylene No Hydraulic Yes Pass
P42-P43 Process polypropylene No Hydraulic Yes Pass
P41-P42 Process polypropylene No Hydraulic Yes Pass
P37-P38 Process pvc No Hydraulic Yes Pass
P37-P39 Process polypropylene No Hydraulic Yes Pass
P36-P37 Process pvc No Hydraulic Yes Pass
P35-P36 Process pvc No Hydraulic Yes Pass
P34-P35A Process polypropylene No Hydraulic Yes Pass
P34-P58 Process polypropylene No Hydraulic Yes Pass
P31-P32 Process pvc No Hydraulic Yes Pass
P32-P32A Process pvc No Hydraulic Yes Pass
P27-P27AJ Process pvc No Hydraulic Yes Pass
P27AJ - P28 Process pvc No Hydraulic Yes Pass
P28 - Floor Gully Process pvc No Hydraulic Yes Pass
P29-P25 Process concrete No Hydraulic Yes Pass
P27-P26 Process polypropylene No Hydraulic Yes Pass
P26-P25 Process polypropylene No Hydraulic Yes Pass
P25 - P24 Process concrete No Hydraulic Yes Pass
P24-P23 Process concrete No Hydraulic Yes Pass
P23-P34 Process polypropylene No Hydraulic Yes Pass
P24-P22 Process polypropylene No Hydraulic Yes Pass
P22-P21 Process polypropylene No Hydraulic Yes Pass
P19-P20 Process polypropylene No Hydraulic Yes Pass
P10-P19 Process polypropylene No Hydraulic Yes Pass
P19-P18 Process polypropylene No Hydraulic Yes Pass
P18-P9 Process polypropylene No Hydraulic Yes Pass
P17-P18 Process polypropylene No Hydraulic Yes Pass
P16-P17 Process polypropylene No Hydraulic Yes Pass
P15-P16 Process polypropylene No Hydraulic Yes Pass
P9-P10 Process polypropylene No Hydraulic Yes Pass
P11-P10 Process polypropylene No Hydraulic Yes Pass
P8-P9 Process polypropylene No Hydraulic Yes Pass
P8-P11 Process polypropylene No Hydraulic Yes Pass
P5-P7 Process polypropylene No Hydraulic Yes Pass
P7-P8 Process polypropylene No Hydraulic Yes Pass
P7-P6 Process polypropylene No Hydraulic Yes Pass
P4-P5 Process polypropylene No Hydraulic Yes Pass
P3-P4 Process polypropylene No Hydraulic Yes Pass
P2-P3 Process polypropylene No Hydraulic Yes Pass
P1-P2 Process polypropylene No Hydraulic Yes Pass
L1-L2 Process pvc No Hydraulic Yes Pass
L2-L3 Process pvc No Hydraulic Yes Pass
L3-L4 Process pvc No Hydraulic Yes Pass
L4-L5 Process pvc No Hydraulic Yes Pass
L5-L6 Process pvc No Hydraulic Yes Pass
L6-L7 Process pvc No Hydraulic Yes Pass
L10-L11 Process pvc No Hydraulic Yes Pass
L11-L17 Process pvc No Hydraulic Yes Pass
L11-L18 Process pvc No Hydraulic Yes Pass
L18-L19 Process pvc No Hydraulic Yes Pass
F13-F18 Foul pvc No Hydraulic Yes Pass
F7-F14 Foul pvc No Hydraulic Yes Pass
F8-F9 Foul pvc No Hydraulic Yes Pass
F6-F7 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
F4-F5 Foul pvc No Hydraulic Yes Pass
F3-F4 Foul pvc No Hydraulic Yes Pass
F2-F3 Foul pvc No Hydraulic Yes Pass
F1-F2 Foul pvc No Hydraulic Yes Pass
F13-F12 Foul pvc No Hydraulic Yes Pass
F16-F17 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
Sump - F17 Foul pvc No Hydraulic Yes Pass
Sump - F18 Foul pvc No Hydraulic Yes Pass
- Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
F11-F12 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
F10-F11 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
F8-F10 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
F7-F8 Foul pvc No Hydraulic Yes Fail Joints leaking
remediation work
planned for W/C
02/04/12
Retest scheduled
for Q2,2012
Yes No N/A
a)invest in capital improvementsb) operational improvements c)nothing 1 2 3 4 5 7 8
reinforced concrete general purpose concrete/masonryprefabricated other (please specify)
Pass Fail
Storm Foul Process
steel ceramic concrete pvc polypropylene other(please specify) Mix (please specify)
Double walled piping Pipe in channel Other (please specify)
CCTV Hydraulic Air Combination
Replaced section Relined Repaired crack Removed obstruction Other (please describe)
3 years Other (please specify)
Hydraulic test Structural assessment Other (please specify)
Are you required by your licence to undertake integrity testing on bunds and containment structures ? if yes please fill out table 1 below listing all bunds and
containment structures on site
Does the site maintain a register of bunds, underground pipelines (including stormwater and foul), Tanks, sumps and containers? (containers refers to "Chemstore"
type units and mobile bunds)
Table 1: Summary details of bund integrity test
Do all sumps and chambers have high level liquid alarms?
If yes to Q7 are these failsafe systems included in a maintenance and testing programme?
Table 2: Summary details of underground structures/pipeline integrity test
Has integrity testing been carried out in accordance with licence requirements and are all structures tested in
line with BS8007/EPA Guidance?
dropdown menu click to see options
Bund/pipe testing report summary ALL IPPC/WASTE licensed facilities
Please use commentary for additional details not answered by tables/ questions above
Pipeline/underground structure testing
Are you required by your licence to undertake integrity testing on underground structures e.g. pipelines or sumps etc ? if yes please fill out table 2 below listing all
underground structures and pipelines on site
Intensive agriculture facilities please use alternative template
Comments
1yes
2 no
3no
4yes
5yes Historic
6
7 yes Completed
8 yes
9 no
10 no
11 yes
12 no
Table 1: Upgradient Groundwater monitoring results
Date of
sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration++
Average
Concentration+ unit GTV's* IGV
% change in
average
concentration
previous year +/-
Upward trend in
pollutant
concentration over last
5 years of monitoring
data
29/11/2011 SP007 Sulphate ICP/Colometric Bi Annual 75 55 mg/l 187.5 200 -42 no
29/11/2011 SP007 Chloride ICP/Colometric Bi Annual 20 18.5 mg/l 24-187.5 30 -14 no
29/11/2011 SP007 Nitrate as No ICP/Colometric Bi Annual 3.7 3.1 mg/l 7.5 25 -77
29/11/2011 SP007 Nitrite as No ICP/Colometric Bi Annual below MRL below MRL mg/l 0.375 0.1 no
29/11/2011 SP007Ammoniacal
Nitrogen as NoICP/Colometric Bi Annual 0.03 0.025 mg/l - 0.12 -98.8 no
29/11/2011 SP007 Magnesium ICP/Colometric Bi Annual 11 5.5 mg/l - 50 49 no
29/11/2011 SP007 Calcium ICP/Colometric Bi Annual 118 112 mg/l - 200 27 no
29/11/2011 SP007 Potassium ICP/Colometric Bi Annual 3 2.5 mg/l - 5 -10 no
29/11/2011 SP007 Sodium ICP/Colometric Bi Annual 15 12.5 mg/l 150 150 -12 no
29/11/2011 SP007Total Alkalinity
as CaCO3ICP/Colometric Bi Annual 246 239 mg/l - 200 58 no
29/11/2011 SP007
Bicarbonate
alkalinity as
CaCO3
ICP/Colometric Bi Annual 246 239 mg/l - - 67 no
29/11/2011 SP007 Arsnenic ICP Bi Annual 0.001 0.001 mg/l 0.0075 0.01 0 no
29/11/2011 SP007 Cadmium ICP Bi Annual - - mg/l 0.00375 0.005 0 no
29/11/2011 SP007 Chromium ICP Bi Annual 0.004 0.0025 mg/l 0.0375 0.03 -56 no
29/11/2011 SP007 Copper ICP Bi Annual below MRL below MRL mg/l 1.5 0.03 0 no
29/11/2011 SP007 Mercury ICP Bi Annual below MRL below MRL mg/l 0.00075 0.001 0 no
29/11/2011 SP007 Nickel ICP Bi Annual below MRL below MRL mg/l - 0.02 0 no
29/11/2011 SP007 Lead ICP Bi Annual below MRL below MRL mg/l 0.01875 0.001 0 no
29/11/2011 SP007 Zinc ICP Bi Annual below MRL below MRL mg/l - 0.1 0 no
29/11/2011 SP007 Barium ICP Bi Annual below MRL below MRL mg/l - 0.1 -100 no
29/11/2011 SP007 Cobalt ICP Bi Annual 0.003 0.0015 mg/l - - -86 no
29/11/2011 SP007 Iron ICP Bi Annual below MRL below MRL mg/l - 0.2 0 no
29/11/2011 SP007 Manganese ICP Bi Annual 0.007 0.007 mg/l - 0.005 100 no
29/11/2011 SP007 Molybdenum ICP Bi Annual below MRL below MRL mg/l - - 0 no
29/11/2011 SP007Volatile Organic
CompoundsGCMS Bi Annual below MRL below MRL mg/l 0 no
29/11/2011 SP007Site Specific
SolventsGCMS/GCFID Bi Annual below MRL below MRL mg/l 0 no
.+ where average indicates arithmetic mean
.++ maximum concentration indicates the maximum measured concentration from all monitoring results produced during the reporting year
Table 2: Downgradient Groundwater monitoring results
Date of
sampling
Sample
location
reference
Parameter/
SubstanceMethodology Monitoring frequency
Maximum
Concentration
Average
Concentrationunit GTV's* IGV
% change in
average
concentration
previous year +/-
Upward trend in yearly
average pollutant
concentration over last
5 years of monitoring
data
29/11/2011 SP012 Sulphate ICP/Colometric Bi Annual 610 482 mg/l 187.5 200 -10 no
29/11/2011 SP012 Chloride ICP/Colometric Bi Annual 29 28 mg/l 24-187.5 30 6.5 no
29/11/2011 SP012 Nitrate as No ICP/Colometric Bi Annual 12.4 9.5 mg/l 7.5 25 -72 no
29/11/2011 SP012 Nitrite as No ICP/Colometric Bi Annual below MRL below MRL mg/l 0.375 0.1 0 no
29/11/2011 SP012Ammoniacal
Nitrogen as NoICP/Colometric Bi Annual 85.2 63.1 mg/l - 0.12 14 no
29/11/2011 SP012 Magnesium ICP/Colometric Bi Annual 27 17 mg/l - 50 -29 no
29/11/2011 SP012 Calcium ICP/Colometric Bi Annual 217 209 mg/l - 200 -2.5 no
29/11/2011 SP012 Potassium ICP/Colometric Bi Annual 16 13 mg/l - 5 -5 no
29/11/2011 SP012 Sodium ICP/Colometric Bi Annual 21 21 mg/l 150 150 7.6
29/11/2011 SP012Total Alkalinity
as CaCO3ICP/Colometric Bi Annual 349 340 mg/l - 200 45 no
29/11/2011 SP012
Bicarbonate
alkalinity as
CaCO3
ICP/Colometric Bi Annual 349 340 mg/l - - 45 no
29/11/2011 SP012 Arsnenic ICP Bi Annual 0.001 0.0005 mg/l 0.0075 0.01 -91 no
29/11/2011 SP012 Cadmium ICP Bi Annual below MRL below MRL mg/l 0.00375 0.005 no
29/11/2011 SP012 Chromium ICP Bi Annual 0.006 0.004 mg/l 0.0375 0.03 -33 no
29/11/2011 SP012 Copper ICP Bi Annual below MRL below MRL mg/l 1.5 0.03 0 no
29/11/2011 SP012 Mercury ICP Bi Annual below MRL below MRL mg/l 0.00075 0.001 0 no
29/11/2011 SP012 Nickel ICP Bi Annual 0.008 0.0075 mg/l - 0.02 7 no
29/11/2011 SP012 Lead ICP Bi Annual below MRL below MRL mg/l 0.01875 0.001 0 no
29/11/2011 SP012 Zinc ICP Bi Annual 0.008 0.004 mg/l - 0.1 -60 no
29/11/2011 SP012 Barium ICP Bi Annual 0.05 0.04 mg/l - 0.1 -6 no
29/11/2011 SP012 Cobalt ICP Bi Annual 0.006 0.0045 mg/l - - 50 no
29/11/2011 SP012 Iron ICP Bi Annual 0.12 0.06 mg/l - 0.2 -94 no
29/11/2011 SP012 Manganese ICP Bi Annual 7.96 6.8 mg/l - 0.005 -8 no
29/11/2011 SP012 Molybdenum ICP Bi Annual 0.005 0.0045 mg/l - - -21 no
29/11/2011 SP012Volatile Organic
CompoundsGCMS Bi Annual below MRL below MRL mg/l 0 no
29/11/2011 SP012Site Specific
SolventsGCMS/GCFID Bi Annual below MRL below MRL mg/l 0 no
Surface
water EQS
Groundwater
regulations
GTV's
Drinking water
(private supply)
standards
Drinking water (public
supply) standards
Interim Guideline
Values (IGV)
Table 3: Soil results
Date of
sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration
Average
Concentration unit
SELECT
SELECT
Has a Conceptual Site Model been developed for the site?
Have potential receptors been identified on and off site?
Is there evidence that contamination is migrating offsite?
* please note exceedance of a relevant Groundwater threshold value (GTV) at a representative monitoring point does not indicate non compliance, an exceedance triggers further investigation to confirm
whether the criteria for poor groundwater chemical status are being met.
**Depending on location of the site and proximity to other sensitive receptors alternative Receptor based Water Quality standards should be used in addition to the GTV e.g.
if the site is close to surface water compare to Surface Water Environmental Quality Standards (SWEQS), If the site is close to a drinking water supply compare results to the
Drinking Water Standards (DWS)
Where additional detail is required please enter it here in 200 words or less
Have actions been taken to address contamination issues?If yes please summarise remediation
strategies proposed/undertaken for the site yes
Remediation pumping of
SP003 and SP010 to
WWTP in 2008-2010.
Ceased with permssion
of the EPA.
Please specify the proposed time frame for the remediation strategy
Is there a licence condition to carry out/update ELRA for the site?
Has any type of risk assesment been carried out for the site?
Groundwater /Contaminated land summary report
Are you required to carry out groundwater monitoring as part of your licence requirements?
Are you required to carry out soil monitoring as part of your licence requirements?
Do you extract groundwater for use on site? If yes please specify use in comment section
Is there contaminated land and /or groundwater on site? If yes please answer q's 5-12
Is the contamination related to operations at the facility (either current and/or historic)
AER summary template-AIR emissions
Parameter
/Substance
Annual fugitive
emission (kg/annum)
Quantificaton
method M/C/E
TA Luft organic
substances class 366120 E
2
No
3Basic air
monitoring
checklist AGN2 Yes
Table 2: Licensed Mass Emissions/Ambient data-periodic monitoring (non-continuous)
Emission
reference no: Parameter/ Substance
Date of
Monitoring
ELV in licence
or any revision
therof Licence Compliance criteria Measured value
Unit of
measurement
Compliant with
licence limit Method of analysis
Annual mass
load (kg)
% change in
mass load
from
previous year
+/- Comments
EP005
TA Luft organic
substances class 3 04/05/2011 2000 100 % of values < ELV 261 mg/Nm3 yes EN 13649:2001 2582 -46.5
EP005 volumetric flow 04/05/2011 1000 100 % of values < ELV 693 Nm3/hour yes CEN 13284.6
EP005
TA Luft organic
substances class 3 04/05/2011 1 100 % of values < ELV 0.168 kg/hour yes EN 13649:2001
EP006
TA Luft organic
substances class 3 04/05/2011 2000 100 % of values < ELV 376 mg/Nm3 yes EN 13649:2001
EP006
TA Luft organic
substances class 3 04/05/2012 1 100 % of values < ELV 0.278 kg/hour yes EN 13649:2001
EP006 volumetric flow 04/05/2011 1000 100 % of values < ELV 739.9 Nm3/hour yes CEN 13284.6
EP005
TA Luft organic
substances class 3 15/08/2012 2000 100 % of values < ELV 225 mg/Nm3 yes EN 13649:2001
EP005
TA Luft organic
substances class 3 15/08/2011 1 100 % of values < ELV 0.151 kg/hour yes EN 13649:2001
EP005 volumetric flow 15/08/2012 1000 100 % of values < ELV 756.5 kg/hour yes CEN 13284.6
EP006
TA Luft organic
substances class 3 15/08/2011 2000 100 % of values < ELV 119.1 mg/Nm3 yes EN 13649:2001
EP006
TA Luft organic
substances class 3 15/08/2011 1 100 % of values < ELV 0.066 kg/hour yes EN 13649:2001
EP006 volumetric flow 15/08/2011 1000 100 % of values < ELV 709.56 Nm3/hour yes CEN 13284.6
EP005
TA Luft organic
substances class 3 08/11/2011 2000 100 % of values < ELV 30.6 mg/Nm3 yes EN 13649:2001
EP005
TA Luft organic
substances class 3 08/11/2011 1 100 % of values < ELV 0.026 kg/hour yes EN 13649:2001
EP005 volumetric flow 08/11/2011 1000 100 % of values < ELV 819 kg/hour yes CEN 13284.6
EP006
TA Luft organic
substances class 3 08/11/2011 2000 100 % of values < ELV 17.5 mg/Nm3 yes EN 13649:2001
EP006
TA Luft organic
substances class 3 08/11/2011 1 100 % of values < ELV 0.012 kg/hour yes EN 13649:2001
EP006 volumetric flow 08/11/2011 1000 100 % of values < ELV 760 Nm3/hour yes CEN 13284.6
EP005
TA Luft organic
substances class 3 15/02/2011 2000 100 % of values < ELV 41.4 mg/Nm3 yes EN 13649:2001
EP005
TA Luft organic
substances class 3 15/02/2011 1 100 % of values < ELV 0.038 kg/hour yes EN 13649:2001
EP005 volumetric flow 15/02/2011 1000 100 % of values < ELV 917.8 kg/hour yes CEN 13284.6
ep005
Total Organic Carbon (as
C) 07/02/2012 330 mg/Nm3 ASTM D6348-03 3233 -29.7
EP006
TA Luft organic
substances class 3 15/02/2011 2000 100 % of values < ELV 382 mg/Nm3 yes EN 13649:2001
EP006
TA Luft organic
substances class 3 15/02/2011 1 100 % of values < ELV 0.3247 kg/hour yes EN 13649:2001
EP006 volumetric flow 15/02/2011 1000 100 % of values < ELV 850 Nm3/hour yes CEN 13284.6
EP006
Total Organic Carbon (as
C) 07/02/2011 56 mg/Nm3 ASTM D6348-03
EP127 volumetric flow 08/11/2011 1100 100 % of values < ELV 974 Nm3/hour yes CEN 13284.6
EP127 Dust 08/11/2011 1 100 % of values < ELV 0.2 mg/Nm3 yes CEN 13284.6 58 -10.8
EP127 Pharmaceutical actives 08/11/2011 0.15 100 % of values < ELV 0.047 mg/Nm3 yes
Additional information
Yes
Periodic/Non-Continuous Monitoring
1
Was all monitoring carried out in accordance with EPA
guidance note AG2 and using the basic air monitoring
checklist?
Does your site have licensed air emissions? If yes please complete table 1, 2 and 3 below for the
current reporting year and answer further questions. If you do not have licenced emissions and do not
complete a solvent management plan (table 5 and 6) you only need to complete table 1 fugitive
emissions on site below
Are there any results in breach of licence requirements? If yes please provide brief details in the comment
section of Table 2 below
Table 1 Fugitive emissions
EP127 Dust 08/11/2011 1 100 % of values < ELV 0.19 g/hour yes CEN 13284.6
EP127
Particulate matter
(PM10) 08/11/2011 NA NA 0.006 mg/Nm3 NA CEN 13284.6 0.033 -89
EP037 volumetric flow 15/02/2011 1300 100 % of values < ELV 713 Nm3/hour yes CEN 13284.6
EP037 Dust 15/02/2011 10 100 % of values < ELV 2.6 mg/Nm3 yes CEN 13284.6
EP038 volumetric flow 16/02/2011 3100 100 % of values < ELV 2642 Nm3/hour yes CEN 13284.6
EP038 Dust 16/02/2011 5 100 % of values < ELV 0 mg/Nm3 yes CEN 13284.6
EP038 Total heavy metals 16/02/2011 0.5 100 % of values < ELV 0.01 mg/Nm3 yes EN 14385:2004
EP011 volumetric flow 15/02/2011 5000 100 % of values < ELV 2138 Nm3/hour yes CEN 13284.6
EP011 Dust 15/02/2011 5 100 % of values < ELV 1.11 mg/Nm3 yes EN 14385:2004
EP011 Total heavy metals 15/02/2011 0.5 100 % of values < ELV 0.0015 mg/Nm3 yes EN 14385:2004 0.171 -22
EP011
Total Organic Carbon (as
C) 09/02/2011 100 % of values < ELV 191 mg/Nm3 yes ASTM D6348-03
EP004 volumetric flow 16/02/2011 1200 100 % of values < ELV 500 Nm3/hour yes CEN 13284.6
EP004 Dust 16/02/2011 5 100 % of values < ELV 1.5 mg/Nm3 yes CEN 13284.6
EP027
Sulphur oxides
(SOx/SO2) 15/08/2011 N/A 2.3 mg/Nm3 EN 14791:2005 48 -83
EP027
Nitrogen oxides
(NOx/NO2) 15/08/2011 N/A 136.1 mg/Nm3 ISO 10849:1996 3898 -33
EP027 Carbon monoxide (CO) 15/08/2011 N/A 0 mg/Nm3 ISO 12039:2001 3 -97
EP108
Sulphur oxides
(SOx/SO2) 15/08/2011 N/A 0 mg/Nm3 EN 14791:2005
EP108
Nitrogen oxides
(NOx/NO2) 15/08/2011 N/A 148.9 mg/Nm3 ISO 10849:1996
EP108 Carbon monoxide (CO) 15/08/2011 N/A 0.4 mg/Nm3 ISO 12039:2001
Note 1: Volumetric flow shall be included as a reportable parameter
4 No
5SELECT
6SELECT
7Yes
Table 3: Summary of average emissions -continuous monitoring
Emission
reference no:
Parameter/ Substance
ELV in licence or
any revision
therof
Averaging
Period
Compliance Criteria Units of
measurement
Annual Emission Annual maximum Monitoring
Equipment
downtime (hours)
% compliance
current
reporting year
Comments
SELECT SELECT SELECT
note 1: Volumetric flow shall be included as a reportable parameter.
Table 4: Abatement system bypass reporting table Bypass protocol
Date* Duration** (hours) Location
13/12/2011 0.5 EP005/6
05/12/2011 1.3 EP005/6
29/11/2012 0.5 EP005/6
22/11/2011 0.8 EP005/6
18/11/2011 0.3 EP005/6
11/11/2011 0.1 EP005/6
07/10/2011 0.3 EP005/6
14/09/2011 0.5 EP005/6
01/09/2011 0.3 EP005/6
22/08/2011 1.6 EP005/6
05/04/2011 2.1 EP005/6
28/03/2011 1 EP005/6
25/03/2011 2 EP005/6
08/03/2011 1 EP005/6
03/02/2012 3 EP005/6
28/02/2012 2.4 EP005/6
21/02/2011 3.5 EP005/6
09/02/2011 9.3 EP005/6
31/01/2011 6 EP005/6
18/01/2011 3 EP005/6
Total 39.5
Corrective action
N/A
N/A
N/A
Reason for bypass
sequencing disruption
Unknown
steam boiler locked out
** an accurate record of time bypass beginning and end should be logged on site and maintained for future
Agency inspections please refer to bypass protocol link
Did your site experience any abatement system bypasses? If yes please detail them in table 4 below
* this should include all dates that an abatement system bypass occurred
Do you have a proactive service agreement for each piece of continuous monitoring equipment?
Did continuous monitoring equipment experience downtime? If yes please record downtime in table 3 below
If yes please review your continuous monitoring data and report the required fields below in Table 3 and
compare it to its relevant Emission Limit Value (ELV)
Does your site carry out continuous air emissions monitoring?
Continuous Monitoring
repair steamvalve to CAU Planned bypass - Extraction shutdown
sequencing disruption N/A
Water shutdown Planned by-pass - New cooling tower installed
sequencing disruption N/A
sequencing disruption N/A
sequencing disruption N/A
sequencing disruption N/A
Steam regulator replaced Planned bypass - Extraction shutdown
Repair work to steam line Planned bypass - Extraction shutdown
Boiler shutdown to replace temperature Planned bypass - Extraction shutdown
Loss of steam from Boilers Extraction Shutdown
Steam regulator repaired Extraction Shutdown
steam leak Unit1 Extraction Shutdown
New Steam regulator fitted to CAUs inlet Planned bypass - Extraction shutdown
steam leak Extraction Shutdown
Cooling fan malfunction Extraction shutdown
Boiler shutdown for repair of steam leaks Planned bypass - Extraction shutdown
8 Do you have a total Emission Limit Value of direct and fugitive emissions on site? if yes please fill out table 5Yes
Solvent
regulations
Reporting year Total solvent input on
site (kg)
Total VOC
emissions to Air
from entire site
(direct and
fugitive)
Total VOC
emissions as
%of solvent
input Total Emission Limit Value
(ELV) in licence or any revision
therof
Compliance
2011 16196689 84433 0.5 15Yes
SELECT
(I) Inputs (kg)
Solvent
(I) Inputs (kg)
Organic solvent
emission in
waste gases(kg)
Solvents lost in
water (kg)
Collected waste solvent (kg) Fugitive Organic
Solvent (kg)
Solvent released
in other ways e.g.
by-passes (kg)
Solvents destroyed
onsite through
physical reaction
e.g.
incineration(kg)
Total emission of
Solvent to air (kg)
Ethanol 1007168 2906 45000 60936 8222 0 0 11128
Acetone 11804003 10842 7712 62846 52507 280 0 63629
Methyl Ethyl
Ketone
1678616 4285 6641 50667 5130 0 0 9415
Heptane 1403489 0 4800 7641 261 0 0 261
Butanol 303413 0 9455 14266 0 0 0 0
Total 84433
Please refer to linked solvent regulations to
complete table 5 and 6
(O) Outputs (kg)
Table 6: Solvent Mass Balance summary
Table 5: Solvent Management Plan Summary
Total VOC Emission limit value
Additional information
No
Date Category
Other type (please
specify)
Brief description of
complaint (Free txt <20
words)
Corrective action< 20
words Resolution status Resolution date
Further
information
SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
Total complaints
open at start of
reporting year
Total new
complaints received
during reporting
year
Total complaints
closed during
reporting year
Balance of
complaints end of
reporting year
Additional information
Yes
What is an incident
Table 2 Incidents summary
Date of occurrence Incident nature Location of occurrence
Incident category*please
refer to guidance Receptor Cause of incident
Other
cause(please
specify)
Activity in
progress at time of
incident Communication Occurrence
Corrective
action<20
words
Preventative
action <20
words Resolution status
Resolution
date
Liklihood of
reoccurence
11/11/2011 Breach of ELV DP001 1. Minor SewerOther (add
details)
Spurious result
from external
laboratory.
Normal activities
EPA/Cork Co. Co.
New Not Applicable
Not
Applicable Complete 11/11/2011 Low
03/11/2011 Breach of ELV DP001 1. Minor SewerPlant or
equipment issuesNormal activities
EPA/Cork Co. Co.
New
Discharge
from DP001
ceased until
the sludge in
the clarifier
sellted.
MLSS in
aeration tank
to be reduced
Complete Q1 2012 Medium
09/09/2011 Monitoring equipment offline TOC meter 1. Minor WaterPlant or
equipment issuesNormal activities
EPA
New
Surface water
diverted to the
Fire Water
Retention
Pond
Not
Applicable
Complete 15/09/2011 Low
*For information on how to report and what constitutes
an incident
Complaints
Have you received any environmental complaints in the current reporting year? If yes please complete
summary details of complaints received on site in table 1 below
Incidents
Have any incidents occurred on site in the current reporting year? Please list all incidents for current reporting
year in Table 2 below
Table 1 Complaints summary
16/09/2011 Monitoring equipment offlineSump pump feeding the
TOC meter1. Minor Water
Plant or
equipment issuesNormal activities
EPA
New
Surface water
diverted to the
Fire Water
Retention
Pond
Not
Applicable
Complete 23/09/2011 Low
03/04/2011 Breach of ELV DP001 1. Minor SewerPlant or
equipment issuesNormal activities
EPA/Cork Co. Co.
New
discharge from
DP001 ceased
until the
sludge in the
clarifier
settled. Complete 04/04/2011 Low
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
Total number of
incidents current
year
5
Total number of
incidents previous
year
8
% reduction/
increase-38
Date
Facility Information Summary
Licence Register Number
Name of site
Site Location
P0017-02
Cara Partners
Little Island, Co. Cork
NACE Code
Class of Activity
RBME risk category
National Grid Reference (6E, 6 N)
2120
The use of a chemical or biological process for the production of
basic pharmaceutical products.
P-B1
E-837454, N519006
Signature
Group/Facility manager
(or nominated, suitably qualified and
experienced deputy)
A brief description of the activities/process at
the site for the reporting year. This should
include information such as production
increases or decreases on site, any
infrastructural changes, environmental
performance improvements which were
measured during the reporting year;
__________________________ ___________________________
Cara Partners produces API extracts from plant extracts. The process involves the use of Class 3 solvents, water
and some inorganic salts in a series of unit operations including extraction, precipitation and filtration steps to
produce a medicinal product according to GMP standards. The production plants are designed, constructed and
maintained to a high standard with stainless steel and glass processing equipment. Emissions abatement
equipment include controlled venting systems, dust control systems, a range of solvent recovery equipment and a
waste water treatment plant.
Cara Partners is committed to the protection of the environment by managing environmental matters as an
integral part of our business. It is our policy to utilise the best available environmental controls and systems to
achieve a high standard of environmental control throughout our operation and to prevent pollution.
Production decreased from 75101 kg in 2010 to 72390 kg in 2011.
Declaration:All the data and information presented in this report has been checked and certified as being accurate. The quality
of the information is assured to meet licence requirements.
Commentary
1Yes
2 Yes
Submitted in 2008 as part of the
IPPC licence review
3 2008
4 2012
5 Insurance
Environmental Impairment
Liability & Environmental
Liability Insurance
6 No
7 01/01/2013 renewed annually
8 2015
9 Please list the top 10 risks assessed on your site in table 1 below
Table 1 ELRA summary information
Click here to access EPA
guidance on ELRA Operational Risk Assessment Category SELECT
Action
Date of
implementation of
mitigation
measures Comment
Revised Risk score for
current reporting
year ELRA costing
e.g
5 Failure of WWTPdischarge of untreated effluent to
sewer9
The WWTP is continually
monitored and an alarm system
in place should wastewater
exceed a specific range
ongoingAll monitoring equipment and
instrumentation are calibrated
on a regular basis
9 €200,000 Yes
7 Failure of underground drainage networkLeakage of material to soil and
groundwater9
Ongoing program of testing and
remediation work on the site
drainage system
ongoing
9 €200,000 Yes
16 Site Closure Various ( see RMP) 9Preparation of a RMP and
revision of such report on an
annual basis
ongoing
9 €750,000 Yes
9
Uncontrolled release of contaminated surface water
runoff to surface waters
Contamination of off-site water
bodies.
8 Operational controls
ongoing
Control of Surface water
discharge SOP in place and
pH/TOC continuously
monitored 6 €100,000 Yes
15
Failure of procedures controlling off-site spreading of
liquid ammonium sulphate solution
Contamination of environmentally
sensitive locations
6 Operational controls
ongoing
Awareness information
supplied to clients with each
delivery.All recipents of the
Ammonium sulphate solution
are approved in advance and
issued with the landspreading
SOP designed with the Teagasc
guidelines 4 €250,000 Yes
2&3Failure of storage tanks resulting in a chemical spillage
& loss of integrity within a bunded area
Leakage of material to soil and
groundwater6
Ongoing program of testing and
remediation work on the site
bunding system and storage
tanks
ongoing
6 €1,000,000 Yes
11 Fire/Explosion
Uncontrolled release of contaminated
surface water emissions and air
emissions
5 Operational controls
Cara Partners has an emergency
plan that outlines the
procedures to be followed in
the event of minor/major and
critical emergencies.
5 >250000 Yes
4 improper classification & disposal of Waste improper disposal of waste 4 Operational controls ongoing 4 €250,000 Yes
13 Use of Volatile material on site Generation of fugitive emissions. 4
Operational controls &
implementation of findings from
a Fugitive emission study. ongoing 4 €20,000 Yes
8 Flooding on site
Uncontrolled release of contaminated
surface water emissions and air
emissions 3 Operational controls ongoing 3 €50,000 Yes
12 Monitoring and control Systems
Failure of on-site environmental
control and monitoring system 3 Operational controls ongoing 3 €50,000 Yes
1 Loading/unloading of materials
Spillage occuring during the
loading/unloading of chemical/fuel to
storage tanks onsite3
Operational controls & capital
investment ongoing
Bunded loading area
constructed 3 €50,000 Yes
SELECT SELECT
Total SELECT SELECT SELECT SELECT
1 Yes
2 Yes Submited to the Agency in 2008.
3 N/A
4
Parent company
guarantee
5 Open Ended
6 N/A
Table 2 CRAMP summary information (NON Landfill)
Date of submission of plan Risk category Closure plan in place Clean closure
Restoration Aftercare
Management Plan
Change in Risk
category since
previous year Increase in risk category
Does the current
financial provision
cover the risk score?
Value of current
financial provision
for site
2008 2(long term issues) Yes Yes Yes No No Yes €750,000.00
Environmental Liability Risk Assessment
Is it a requirement of your licence to complete an ELRA?
Has an initial ELRA been submitted to and approved by the Agency?
Please enter the date of submission of the initial ELRA
Date of most recent substantial ELRA update
What financial instrument/s do you have in place to cover unknown liabilities?
Mitigation measures to reduce risk ELRA
Does the current
financial provision
(FP) cover the risk
score?
Closure Restoration Aftercare Management Plan/ Restoration plan (CRAMP/RP)Was a closure or restoration plan a requirement of the licence?
Has this financial instrument/s been verified by the Agency?
What is the date of expiry of this financial instrument?
Date of next required review of the ELRA?
Risk ID Potential hazards
Has a closure plan submission been approved by the Agency?
What is the timescale for submission?
What financial instrument do you have in place to cover known liabilities?
What is the date of expiry of this financial instrument?
What is the status of implementation of the plan?
Previous risk scoreEnvironmental effect
Additional Information
1Yes
2 Yes
3 Yes
4 Yes
Environmental Management Programme (EMP) reportObjective Category Target Status (% completed) How target was progressed Responsibility Intermediate outcomes
Energy Efficiency/Utility conservation To further progress Energy
saving initiatives
50 Consolidation of site cooling
requirements from 2 separate
systems to a single cooling
tower along with the
installation of Variable Speed
Drives (VSD's) on water
recirculation pumps is
expected to reduce electricity
consumption by greater
than 200,000 . In 2012 it is
planned to reduce Gas usage
by Approx. 5% or 1,000,000
kWh through the upgrading
of steam generation facility.
Technical Support Improved Environmental
Management Practices
Energy Efficiency/Utility conservation To identify any potential
water reduction initiatives.
40 • Water monitoring to be
reviewed by SMT through site
metrics system and any
agreed actions followed up as
required.
• Establish a water mass
balance for the site in follow-
up to the water system
survey.
• Organise awareness
campaign for water usage
reduction
Environmental officer Improved Environmental
Management Practices
Reduction of emissions to Air Reduction in Fugitive
Emissions
50 Continue to execute the ‘3’
year plan to address any
findings from the Fugitive
emissions study and Solvent
management plan.
Environmental officer Reduced emissions
Waste reduction/Raw material usage
efficiency
To reduce the quantity (Kg)
of waste solvent shipped off-
site for disposal.
50 Projects implemented in 2011
to allow for the reuse of
waste acetone and MEK
streams will be reviewed in
2012 to ensure that they
continue to operate
effectively and to optimise
where possible.
A project planned to reduce
the quantity of
ethanol used will if successful
reduce the quantity of waste
generated by approximately
25,000 Kg in 2012.
Technical Support Increased solvent recovery
Additional improvements Undertake a Carbon Foot
print assessment at the
Cara Partners site in
conjunction with our
Corporate EHS group.
40 This involved ‘4’ phases as
follows: Phase 1- Analysis of
the site, Phase 2- Data
Collection, Phase 3- Carbon
calculation ,Phase 4 – Analysis
of results.The next step
involves the development of
a ‘5’ year plan for reduction
of the Site’s carbon footprint
with annual milestones. It
also involves an in depth
assessment of the
plantations.
Environmental officer Improved Environmental
Management Practices
Energy Efficiency/Utility conservation To review operations of the
Aeration tank within the
Waste Water Treatment
plant facility with a view to
maximising efficiency of
operation
20 Explore the option of
removing the surface aerators
and replacing with an air
diffusion system.
Environmental officer & Technical
Support
Installation of infrastructure
Environmental Management Programme (EMP)/Continuous Improvement Programme
IS0 14001
The Impact and Aspect manual is updated annually to reflect any
changes in the company.
Via Public Information File and the Annual Environmental Report
Do you maintain an environmental documentation/communication system to inform the public on
environmental performance of the facility, as required by the licence
Highlighted cells contain dropdown menu click to view
Does the EMS reference the most significant environmental aspects and associated impacts on-site
Does the EMS maintain an Environmental Management Programme (EMP) as required in accordance
with the licence requirements
Do you maintain an Environmental Mangement System for the site. If yes, please detail in additional
information
Waste reduction/Raw material usage
efficiency
To reduce the quantity (Kg)
of solvent used per Kg of
Ginkgo product produced.
50 Evaluate the quantity of
solvent used in the Ginkgo
processes with a view to
reducing its use, waste and
emissions generation
incorporating an Operational
Excellence program.In 2012 a
project is planned which it is
expected will reduce ethanol
usage by Approx. 0.5 Kg per
Kg of Product. This will result
is a saving of approximately
25,000kg of ethanol.
Technical Support Increased solvent recovery
1 Yes
2 Draft Noise
Guidance
Yes
3 No
4 N/A
5 No
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL
(if applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive noise was
identified was 5dB penalty
applied?
Comments (ex. main
noise sources on site, &
extraneous noise ex.
road traffic)
Is site compliant with
noise limits
(day/evening/night)?
9-10/11/11 0:11 - 00:41 North N/A 51 49 52 61
No N/A
General noise from
Plant. Neighbouring
Facility. Traffic, wind
Yes
10/11/2011 15:11-15:41 North N/A 55 49 56 73
No N/A
General noise from
Plant. Neighbouring
Facility. Traffic,
Birdsong
Yes
9-10/11/11 22:35-00:05 South N/A 54 53 54 61
No N/A
Unit 2 Tank farm.
Traffic, Neighbouring
Facility,Wind.
Yes
10/11/2011 14:22-14:52 South N/A 54 53 55 63
No N/A
Unit 2 Tank farm.
Traffic, Neighbouring
Facility,Birdsong.
Yes
9-10/11/11 23:16-23:46 East N/A 55 47 53 73
No N/A
General noise from
Plant. Neighbouring
Facility. Traffic,
Yes
10/11/2011 15:50-16:20 East N/A 64 47 59 84
No N/AGeneral noise from
Plant. Neighbouring
Facility. Traffic, Wind.
Yes
9-10/11/11 22:32-23:02 West N/A 59 59 60 66 No N/A Cara WWTP Yes
10/11/2011 13:18-13:48 West N/A 58 58 59 63 No N/A Cara WWTP Yes
9-10/11/11 23:53-01:23 off-site
St Lappins
Place 50 47 50 78
No N/A
Local facilities.Road
Traffic.Operations from
Cara not Audible at any
point during monitoring
period.
Yes
10/11/2011 16:27-16:57 off-site
St Lappins
Place 64 57 66 79
No N/A
Birdsong,Road
Traffic.Operations from
Cara not Audible at any
point during monitoring
period.
Yes
9-10/11/11 01:31 - 02:01 off-site North Esk 42 41 41 67
No Yes Road Traffic,Operations
from Cara not Audible
at any point during
monitoring period.
Yes
10/11/2011 17:09-17:39 off-site North Esk 64 56 65 81
No Yes Road Traffic,Operations
from Cara not Audible
at any point during
monitoring period.
Yes
*Please ensure that a tonal analysis has been carried out as per guidance note NG4. These records must be maintained onsite for future inspection
SELECT
When was the noise reduction plan last updated?
Was noise monitoring a licence requirement for the AER period?
If yes please fill in table 1 noise summary below
Have there been changes relevant to site noise emissions (e.g. plant or operational changes) since the last noise
survey?
** please explain the reason for not taking action/resolution of noise issues?
Any additional comments? (less than 200 words)
Noise Monitoring Report Summary
Table 1: Noise monitoring summary
If noise limits exceeded as a result of noise attributed to site activities, please choose the corrective action from the following options?
Was noise monitoring carried out using the EPA Guidance note including completion of the
"Checklist for noise measurement report" included in the guidance note as table 6?
Does your site have a noise reduction plan
Additional information
1
2
SEAI - Large Industry
Energy Network
(LIEN) yes
Cara Partners are Members of LIEN.
3 no
Cara Partners have not used Fuel Oil in the boilers since the
IPPC licence was granted. However we are aware of the
stipulation with regard to the sulphur content in our licence
should the need arise.
Energy Use Previous year kWh Current year kWh
Production +/- %
compared to
previous reporting
year**
Energy
Consumption +/- %
vs overall site
production*
Total 27660363 26190017 -3.6 -5.3
Electricity 6857680 6377839 -3.6 -7
Fossil Fuels: 0 0
Heavy Fuel Oil 0 0
Light Fuel Oil 0 0
Natural gas 20802682 19812178 -3.6 -4.76
Coal/Solid fuel 0 0
Renewable energy generated on site 0 0
* where consumption of energy can be compared to overall site production please enter this information as percentage increase or decrease compared to the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
Water use Previous year m3/yr. Current year m3/yr.
Production +/- %
compared to
previous reporting
year**
Energy
Consumption +/- %
vs overall site
production*
Groundwater 0 0
Surface water 0 0
Public supply 43387 39317
Total 43387 39317 -3.6 -9.4
* where consumption of water can be compared to overall site production please enter this information as percentage increase or decrease compared to the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
Date of audit Recommendations
Description of
Measures proposed Origin of measures
Predicted energy
savings % Implementation date Responsibility Completion date
Status and
comments
Aug-09 Reduce Compressed air
generation
Investigation and
reparatory project
energy audit 0.5 Q4 2010 Technical Services Q4 2010 Completed
Aug-09 Optimise Weekend
operations of water
chillers
Adjust set points on
temperature control
energy audit 0.9 Q4 2010 Technical Services Q4 2010 Completed
Aug-09 Reduce aeration in the
Balance tank No.1.
Place controller of
aerator on a timing
mechanism
energy audit 0.25 Q4 2010 Technical Services Q4 2010 Completed
Jan-09 Reduce boiler
discharge by one bar
Adjust set points on
pressure control
following assessment
of potential impact
energy audit 0.1 Q4 2010 Technical Services Q1 2011 Completed
Jan-09 Repair steam leaks Ongoing reparatory
work
energy audit 0.05 Q4 2010 Technical Services on-going on-going
Jan-09 Perform sitewide 'non-
production' survey
Assess the enery
usage on-site during
non-production
periods and act on
findings.
energy audit 3.3 Q4 2010 Technical Services on-going on-going
Jan-09 Review HVAC
operations at
weekends
Reduce air flowrate
during non-
production hours.
energy audit 0.2 Q4 2010 Technical Services on-going on-going
N/A Replace Nitrogen Plant Replace Nitrogen
Plant
Ongoing Energy
review program
0.6 Q4 2011 Technical Services Q1 2012 Completed
Aug-09 Review Chiller
operations
Replace Chiller units energy audit 1.9 Q4 2010 Technical Services Q1 2011 Completed
N/A Replace Cooling water
Tower operations
Replace 4 cooling
towers with
Ongoing Energy
review program
1.9 Q4 2010 Technical Services Q1 2011 Completed
SELECT
Table 3: Energy Audit finding recommendations
Resource usage/ Energy Efficiency
When did the site carry out the most recent energy efficiency audit? Please list the recommendations in table 3 below
Where Fuel Oil is used in boilers on site is the sulphur content compliant with licence conditions? Please state percentage in
additional information
Table 1 Energy usage on site
Table 2 Water usage on site
Is the site a member of any accredited programmes for reducing energy usage/water conservation such
as the SEAI programme linked to the right? If yes please list them in additional information
PRTR facility logon
Additional Information
1 No
2 No
3 N/A
Table 1 Details of waste accepted onto your site for recovery, disposal or treatment (do not include wastes generated at your site, as these will have been reported in your PRTR workbook)EWC code Description of waste
accepted
Please enter an accurate
and detailed description -
which applies to
Quantity of waste
accepted in current
reporting year (tonnes)
Reason for
reduction/increase
from previous
reporting year
Packaging Content (%)-
only applies if the waste
has a packaging
component
European Waste Catalogue EWC
codes
European Waste
Catalogue EWC codes
E.g. 07 05 04*
07- WASTES FROM ORGANIC
CHEMICAL PROCESSES
other organic solvents,
washing liquids and
mother liquors 22 12 83% 0% SELECT
Brought onto site
from sister IPPC
plant
E.g. 20 01 08
20- MUNICIPAL WASTES
(HOUSEHOLD WASTE AND
SIMILAR COMMERCIAL,
INDUSTRIAL AND
INSTITUTIONAL WASTES)
INCLUDING SEPARATELY
COLLECTED FRACTIONS
biodegradable kitchen
and canteen waste 10 20 -50% 0% SELECT
SELECT #DIV/0! SELECT
SELECT #DIV/0! SELECT
4 SELECT
SELECT
5 SELECT
6 SELECT
7 Do you have an odour management system in place for your facility? If no why? SELECT
8 Do you maintain a sludge register on site? SELECT
Table 2 Waste type and tonnage-landfill only
Waste types permitted
for disposal
Authorised/licenced annual intake
for disposal (tpa)
Actual intake for disposal in
reporting year (tpa)
Remaining licensed
capacity at end of
reporting year (m3) Comments
e.g. Household (residual) 30,000 22,000
e.g.
Industrial non
hazardous solids500 60
Table 3 General information-Landfill only
Total disposal
area occupied by
waste
Lined disposal
area occupied by
waste
Unlined area
SELECT UNIT SELECT UNIT SELECT UNIT
Cell 8
Table 4 Environmental monitoring-landfill onlyLandfill Manual-Monitoring Standards
Was meterological
monitoring in
compliance with Landfill
Directive (LD) standard
in reporting year +
Was leachate monitored in
compliance with LD standard in
reporting year
Was Landfill Gas monitored in
compliance with LD standard in
reporting year
Was SW monitored in
compliance with LD
standard in reporting
year
Have GW trigger levels
been established
Were emission limit values agreed with
the Agency (ELVs)
Was topography
of the site
surveyed in
reporting year
Has the statement
under S53(A)(5) of
WMA been
submitted in
reporting year Comments
.+ please refer to Landfill Manual linked above for relevant Landfill Directive monitoring standards
Table 5 Capping-Landfill only
Area uncapped* Area with temporary cap
SELECT UNIT SELECT UNIT
*please note this includes daily cover area
Table 6 Leachate-Landfill only9 Is leachate from your site treated in a Waste Water Treatment Plant? SELECT
10 Is leachate released to surface water? If yes please complete leachate mass load information below SELECT
Volume of leachate in
reporting year(m3)
Leachate (BOD) mass load
(kg/annum)
Leachate (COD) mass load
(kg/annum)
Leachate (NH4) mass
load (kg/annum)
Leachate (Chloride)
mass load kg/annum Leachate treatment on-site
Specify type of
leachate
treatment Comments
Table 7 Landfill Gas-Landfill only
Gas Captured&Treated
by LFG System m3 Power generated (MW / KWh) Used on-site or to national grid
Was surface emissions
monitoring performed
during the reporting
year? Comments
SELECT
SECTION A-PRTR WASTE TRANSFERS TAB- TO BE COMPLETED BY ALL IPPC AND WASTE FACILITIES dropdown list click to see options
Date landfilling commenced Area ID
Were any wastes accepted onto your site for recovery or disposal or treatment prior to recovery or disposal within the boundaries of your facility ?; (waste generated within your
boundaries is to be captured through PRTR reporting)
Area with final cap to LD
Standard m2 ha, a Area capped other
Area with waste that
should be permanently
capped to date under
licence What materials are used in the cap Comments
Source of waste accepted
Currently landfilling Date landfilling ceased Private or Public
Operated
Please ensure that all information reported in the landfill gas section is consistent with the Landfill Gas Survey submitted in conjunction with PRTR returns
SECTION D-TO BE COMPLETED BY LANDFILL SITES ONLY
Does your facility have relevant nuisance controls in place?
120,000
Accepted asbestos in reporting
year
Is there a separate cell
for asbestos?
Licence permits
asbestos
Predicted date
to cease
landfilling
Inert or non-hazardous
Comments - Quantity of waste accepted in previous
reporting year (tonnes)
Reduction/Incr
ease over
previous year
+/ - %
Quantity of
waste remaining
on site at the
end of reporting
year (tonnes)
Comments on
liner type
SECTION C-TO BE COMPLETED BY ALL WASTE FACILITIES (waste transfer stations, Composters, Material recovery facilities etc) EXCEPT LANDFILL SITES
Licenced annual
tonnage limit for your
site (total
tonnes/annum)
Is all waste storage infrastructure as required by your licence and approved by the Agency in place? If no please list waste storage infrastructure required on site
SECTION B- WASTE ACCEPTED ONTO SITE-TO BE COMPLETED BY ALL IPPC AND WASTE FACILITIES
Disposal/Recovery or treatment
operation carried out at your
site and the description of this
operation
Is all waste processing infrastructure as required by your licence and approved by the Agency in place? If no please list waste processing infrastructure required onsite
Was waste accepted onto your site that was generated outside the Republic of Ireland? If yes please state the quantity in tonnes in additional information
If yes please enter details in table 1 below
Did your site have any rejected consignments of waste in the current reporting year? If yes please give a brief explanation in the additional information
AER Monitoring returns summary template-WATER/WASTEWATER(SEWER)
2
No
Location
reference
Location
relative to site
activities
PRTR ParameterLicenced
Parameter
Monitoring
date
ELV or trigger
level in licence or
any revision
thereof*Licence Compliance
criteria Measured value
Unit of
measurement
Compliant with
licence Comments
SELECT SELECT SELECT SELECT SELECT SELECT
*trigger values may be agreed by the Agency outside of licence conditions
Location
Reference
Date of
inspectionSource of
contamination
SELECT
SELECT
3Yes
4 External /Internal
Lab Quality
checklist
Assessment of
results checklist No
Table 3: Licensed Emissions to water and /or wastewater (sewer)-periodic monitoring (non-continuous)
Emission
reference no:
Emission
released toParameter/
SubstanceNote 1 Type of sample
Date of
Monitoring Averaging period
ELV or trigger values
in licence or any
revision therofNote 2
Licence
Compliance
criteria Measured value
Unit of
measurement
Compliant with
licence Method of analysis
Procedural
reference source
Procedural
reference
standard numberAnnual mass load
(kg)
% change in mass
load from previous
year +/- Comments
DP001Wastewater/Se
werBOD composite 31/01/2011 24 hour 400 All values < ELV 118 mg/L yes Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard
Methods"5210B 373 -36
DP001Wastewater/Se
werSulphate composite 31/01/2011 24 hour 1000 All values < ELV 118 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4110 B 6666 -43
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 31/01/2011 24 hour 0.5 All values < ELV 0.121 mg/L yes
ICP / ICPMS
(Inductively Coupled I.S. (Irish Standard) INAB 111T 1.37 -83
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 31/01/2011 24 hour 0.5 All values < ELV 0.07 mg/L yes
iCP / ICPMS
(Inductively Coupled I.S. (Irish Standard) INAB 111T 1.38 -47
DP001wastewater/Sew
erTotal nitrogen composite 31/01/2011 24 hour 200 All values < ELV 8.4 mg/L yes
Spectrophotometry
(Colorimetry) ISO 11905-1:1998 162 -69
DP001wastewater/Sew
erTotal phosphorus composite 31/01/2011 24 hour 50 All values < ELV 1.46 mg/L yes Spectrophotometry
(Colorimetry) ISO 6838:2004 31.1 -38
DP001Wastewater/Se
werBOD composite 25/02/2011 24 hour 400 All values < ELV 32 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 25/02/2011 24 hour 1000 All values < ELV 208 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 25/02/2011 24 hour 0.5 All values < ELV 0.03 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 25/02/2011 24 hour 0.5 All values < ELV 0.04 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 25/02/2011 24 hour 200 All values < ELV 4.6 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
Licensed Emissions to water and /or wastewater(sewer)-periodic monitoring (non-continuous)
Comments
Additional information
Yes
Description of contamination
Table 2 Visual inspections-Please only enter details where contamination was observed.
Table 1 Ambient monitoring
Corrective action
Was there any result in breach of licence requirements? If yes please provide brief details in the
comment section of Table 3 below
1
See Table 3 below.
FWRP/surface water - do we send off site for
Was it a requirement of your licence to carry out visual inspections on any surface water
discharges or watercourses on or near your site? If yes please complete table 2 below
summarising only any evidence of contamination noted during visual inspections
Was all monitoring carried out in accordance with EPA
guidance and checklists for Quality of Aqueous Monitoring
Data Reported to the EPA? If no please detail what areas
require improvement in additional information box
Does your site have licensed emissions direct to surface water or direct to sewer? If yes
please complete table 3 and 4 below for the current reporting year and answer further
questions. If you do not have licenced emissions you only need to complete table 1 and
/table 2 below for ambient monitoring and visual inspections
DP001wastewater/Sew
erTotal phosphorus composite 25/02/2011 24 hour 50 All values < ELV 0.2 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 29/03/2011 24 hour 400 All values < ELV 15 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 29/03/2011 24 hour 1000 All values < ELV 228 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 29/03/2011 24 hour 0.5 All values < ELV 0.07 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 29/03/2011 24 hour 0.5 All values < ELV 0.07 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 29/03/2011 24 hour 200 All values < ELV 2.8 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 29/03/2011 24 hour 50 All values < ELV 1.01 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 29/04/2011 24 hour 400 All values < ELV 24 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 29/04/2011 24 hour 1000 All values < ELV 289 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 29/04/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 29/04/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 29/04/2011 24 hour 200 All values < ELV 20.4 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 29/04/2011 24 hour 50 All values < ELV 5.28 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 27/05/2011 24 hour 400 All values < ELV 19 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 27/05/2011 24 hour 1000 All values < ELV 463 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 27/05/2011 24 hour 0.5 All values < ELV 0.03 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 27/05/2011 24 hour 0.5 All values < ELV 0.02 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 27/05/2011 24 hour 200 All values < ELV 22.7 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 27/05/2011 24 hour 50 All values < ELV 0.1 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 17/06/2011 24 hour 400 All values < ELV 24 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 17/06/2011 24 hour 1000 All values < ELV 411 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 17/06/2011 24 hour 0.5 All values < ELV 0.05 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 17/06/2011 24 hour 0.5 All values < ELV 0.06 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 17/06/2011 24 hour 200 All values < ELV 6.3 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 17/06/2011 24 hour 50 All values < ELV 0.46 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 18/07/2011 24 hour 400 All values < ELV 38 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 18/07/2011 24 hour 1000 All values < ELV 448 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 18/07/2011 24 hour 0.5 All values < ELV 0.12 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 18/07/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 18/07/2011 24 hour 200 All values < ELV 2.8 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 18/07/2011 24 hour 50 All values < ELV 0.87 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 02/08/2011 24 hour 400 All values < ELV 13 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 02/08/2011 24 hour 1000 All values < ELV 393 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 02/08/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 02/08/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 02/08/2011 24 hour 200 All values < ELV 6.9 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 02/08/2011 24 hour 50 All values < ELV 3.52 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 01/09/2011 24 hour 400 All values < ELV 0 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 01/09/2011 24 hour 1000 All values < ELV 433 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 01/09/2011 24 hour 0.5 All values < ELV 0.04 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 01/09/2011 24 hour 0.5 All values < ELV 0.11 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 01/09/2011 24 hour 200 All values < ELV 11 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 01/09/2011 24 hour 50 All values < ELV 1.47 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 25/10/2011 24 hour 400 All values < ELV 9 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 25/10/2011 24 hour 1000 All values < ELV 419 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 25/10/2011 24 hour 0.5 All values < ELV 0.09 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 25/10/2011 24 hour 0.5 All values < ELV 0.09 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 25/10/2011 24 hour 200 All values < ELV 4.1 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 25/10/2011 24 hour 50 All values < ELV 0.56 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 24/11/2011 24 hour 400
All results < 1.2 x
ELV1 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 24/11/2011 24 hour 1000 All values < ELV 286 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 24/11/2011 24 hour 0.5 All values < ELV 0.03 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 24/11/2011 24 hour 0.5 All values < ELV 0.03 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 24/11/2011 24 hour 200 All values < ELV 1.3 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 24/11/2011 24 hour 50 All values < ELV 0.22 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werBOD composite 16/12/2011 24 hour 400 All values < ELV 20 mg/L yes
Dissolved Oxygen
Meter (Electrode)
APHA / AWWA
"Standard 5210B
DP001Wastewater/Se
werSulphate composite 16/12/2011 24 hour 1000 All values < ELV 255 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-SO4 E
DP001Wastewater/Se
wer
Lead and compounds (as
Pb)composite 16/12/2011 24 hour 0.5 All values < ELV 0.03 mg/L yes
ICP / ICPMS
(Inductively Coupled US EPA 200.8
DP001Wastewater/Se
wer
Zinc and compounds (as
Zn)composite 16/12/2011 24 hour 0.5 All values < ELV 0.02 mg/L yes
iCP / ICPMS
(Inductively Coupled US EPA 200.8
DP001wastewater/Sew
erTotal nitrogen composite 16/12/2011 24 hour 200 All values < ELV 4.7 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard APHA 4500-PJ
DP001wastewater/Sew
erTotal phosphorus composite 16/12/2011 24 hour 50 All values < ELV 3.45 mg/L yes
Spectrophotometry
(Colorimetry) ASTMD5176
DP001Wastewater/Se
werAmmonia (as N) composite Jan 2011 24 hour 40 All values < ELV 2.85 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent 68.8 -60
DP001Wastewater/Se
werCOD composite Jan 2011 24 hour 800 All values < ELV 300.25 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D 3691.1 -38
DP001Wastewater/Se
werSuspended Solids composite Jan 2011 24 hour 600 All values < ELV 225.5 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D 2114 -35
DP001Wastewater/Se
werpH composite Jan 2011 24 hour 6.0-9.0 All values < ELV 7.68 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Feb 2011 24 hour 40 All values < ELV 2.4 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Feb 2011 24 hour 800 All values < ELV 234 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Feb 2011 24 hour 600 All values < ELV 133.5 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Feb 2011 24 hour 6.0-9.0 All values < ELV 7.69 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Mar 2011 24 hour 40 All values < ELV 0.87 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Mar 2011 24 hour 800 All values < ELV 130 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Mar 2011 24 hour 600 All values < ELV 104 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Mar 2011 24 hour 6.0-9.0 All values < ELV 7.79 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite April 2011 24 hour 40 All values < ELV 1.045 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite April 2011 24 hour 800 All values < ELV 173.25 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite April 2011 24 hour 600 All values < ELV 53.5 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite April 2011 24 hour 6.0-9.0 All values < ELV 7.75 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite May 2011 24 hour 40 All values < ELV 9.9 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite May 2011 24 hour 800 All values < ELV 203 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite May 2011 24 hour 600 All values < ELV 150.1 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite May 2011 24 hour 6.0-9.0 All values < ELV 7.49 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite June 2011 24 hour 40 All values < ELV 9.5 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite June 2011 24 hour 800 All values < ELV 138.4 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite June 2011 24 hour 600 All values < ELV 44.8 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite June 2011 24 hour 6.0-9.0 All values < ELV 7.62 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite July 2011 24 hour 40 All values < ELV 10.59 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite July 2011 24 hour 800 All values < ELV 66.4 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite July 2011 24 hour 600 All values < ELV 73.9 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite July 2011 24 hour 6.0-9.0 All values < ELV 7.23 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Aug 2011 24 hour 40 All values < ELV 0.2214 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Aug 2011 24 hour 800 All values < ELV 65.8 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Aug 2011 24 hour 600 All values < ELV 127 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Aug 2011 24 hour 6.0-9.0 All values < ELV 8.01 mg/L yes
pH Meter (Electrode) I.S. (Irish Standard)EN 872:2005
DP001Wastewater/Se
werAmmonia (as N) composite Sept 2011 24 hour 40 All values < ELV 0.464 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Sept 2011 24 hour 800 All values < ELV 109.8 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Sept 2011 24 hour 600 All values < ELV 106.54 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Sept 2011 24 hour 6.0-9.0 All values < ELV 7.22 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Oct 2011 24 hour 40 All values < ELV 0.209 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Oct 2011 24 hour 800 All values < ELV 86.7 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Oct 2011 24 hour 600 All values < ELV 57.5 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Oct 2011 24 hour 6.0-9.0
No pH value shall
deviate from the 8.14 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Nov 2011 24 hour 40 All values < ELV 0.121 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Nov 2011 24 hour 800 All values < ELV 353 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Nov 2011 24 hour 600 All values < ELV 49.6 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Nov 2011 24 hour 6.0-9.0
No pH value shall
deviate from the 7.89 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werAmmonia (as N) composite Dec 2011 24 hour 40 All values < ELV 0.229 mg/L yes
Spectrophotometry
(Colorimetry) US EPA Nessler reagent
DP001Wastewater/Se
werCOD composite Dec 2011 24 hour 800 All values < ELV 326 mg/L yes
Digestion +
Spectrophotometry US EPA APHA 5220D
DP001Wastewater/Se
werSuspended Solids composite Dec 2011 24 hour 600 All values < ELV 85.3 mg/L yes
Gravimetric analysis
Other (please
specify)APHA 2540D
DP001Wastewater/Se
werpH composite Dec 2011 24 hour 6.0-9.0
No pH value shall
deviate from the 7.56 mg/L yes
pH Meter (Electrode)
APHA / AWWA
"Standard
DP001Wastewater/Se
werFats, Oils and Greases composite Feb 2011 24 hour 20 All values < ELV 4 mg/L yes
Gravimetric analysis
APHA / AWWA
"Standard 5520G 81 -76
DP001Wastewater/Se
werFats, Oils and Greases composite mAY 2011 24 hour 20 All values < ELV 4 mg/L yes
Gravimetric analysis
APHA / AWWA
"Standard 5520G
DP001Wastewater/Se
werFats, Oils and Greases composite Oct 2011 24 hour 20 All values < ELV 4 mg/L yes
Gravimetric analysis
APHA / AWWA
"Standard 5520G
DP001Wastewater/Se
werFats, Oils and Greases composite Nov 2011 24 hour 20 All values < ELV 4 mg/L yes
Gravimetric analysis
APHA / AWWA
"Standard 5520G
DP001Wastewater/Se
werDetergents (as MBAS) composite Mar 2011 24 hour 10 All values < ELV 0.21 mg/L yes
Spectrophotometry
(Colorimetry)
APHA / AWWA
"Standard 5540G 4 48
DP001Wastewater/Se
werOrganic solvents composite 2011 24 hour N/A N/A
< LOQ for all
solventsµg/L Yes
GC (Gas
Chromatography) US EPA 524.2
Note 1: Volumetric flow shall be included as a reportable parameter
Note 2: Where Emission Limit Values (ELV) do not apply to your licence please compare results against EQS for Surface water or relevant receptor quality standards
5 Yes
6No
7Yes
8No
Table 4: Summary of average emissions -continuous monitoring
Emission
reference no:
Emission
released to Parameter/ Substance
ELV or trigger
values in licence or
any revision
thereof Averaging Period
Compliance
Criteria
Units of
measurement
Annual Emission
for current
reporting year
(kg)
% change +/- from
previous reporting
year
Monitoring
Equipment
downtime (hours)
% compliance
current reporting
year
DP001Wastewater/Se
wervolumetric flow 240 24 hour
No flow value
shall exceed the
specific limit .
m3/day 20247 -35 0 100
note 1: Volumetric flow shall be included as a reportable parameter.
Table 5: Abatement system bypass reporting tableDate Duration (hours) Location Resultant
emissions
Reason for
bypass
Corrective
action*
Was a report
submitted to the
EPA?
When was this
report
submitted?
SELECT
*Measures taken or proposed to reduce or limit bypass frequency
Comments
Did abatement system bypass occur during the reporting year? If yes please complete table 5
below
Do you have a proactive service contract for each piece of continuous monitoring equipment on
site?
DP001 Volumetric Flow
Additional InformationContinuous monitoring
Did continuous monitoring equipment experience downtime? If yes please record downtime in
table 4 below
If yes please summarise your continuous monitoring data below in Table 4 and compare it to its
relevant Emission Limit Value (ELV)
Does your site carry out continuous emissions to water/sewer monitoring?