Tapestry Senior Living ‐ Wickliffe Tapestry Wickliffe, LLC Construction Status Report February 21, 2018 The OAC (Owner/Contractor/Architect) and draw meeting was held on January31, 2018. In attendance were Terry Sparrow Tapestry’s owner’s site representative, Greg LaSalle owner’s representative, Mike Shean, Higley Construction Project Manager, Bob Jensik, Higley Construction Superintendent, and Michael Knisely, architect. Construction progress is generally as follows: Sitework – Site utilities to commence the first of February Front one story structure – demolition is complete, the slab for the kitchen area has been removed, and steel has been delivered for the reconstruction of the building enclosure Atrium – The slab has been removed, regrading of the floor has been completed, existing windows were removed and frames are ready to receive the new windows, and the new elevator shaft is near completion Residential Floors o First – Framing and electrical and mechanical rough‐ins in process o Second – Shower enclosure drywall being completed and electrical and mechanical rough‐ins in process o Third – Rough‐ins complete, floor penetration in‐fill in progress o Fourth – Sheetrock near completion, electrical and mechanical roughs complete, and shower installation commencing Materials for the renovation have begun to arrive on site for staged installation. Change Order #2 has been signed in the amount of $98,161 for unforeseen work to create fire rated exhaust risers and provide access doors and dampers. To date the contractor has utilized approximately $72,000 of its $480,000 contract contingency and has utilized approximately $35,000 of its $230,000 of unforeseen conditions allowances contained in its GMP contract. Total change orders charged to the Owner to date are $161,089. Additional unforeseen items have been discovered and least costly solutions for remediation are under investigation, potential change order requests are currently estimated to be approximately $420,000 and are subject to change. The project has an overall owner contingency of $1,225,000 and the contractor has a contract contingency of $480,000 for such items. The construction draw in the was approved and will paid as required under the construction contract.
Transcript
Page 1: Tapestry Senior Living

Tapestry Senior Living ‐ Wickliffe Tapestry Wickliffe, LLC 

 Construction Status Report 

February 21, 2018   The OAC (Owner/Contractor/Architect) and draw meeting was held on January31, 2018.  In attendance were Terry Sparrow Tapestry’s owner’s site representative, Greg LaSalle owner’s representative, Mike Shean, Higley Construction Project Manager, Bob Jensik, Higley Construction Superintendent, and Michael Knisely, architect.    Construction progress is generally as follows: 

Sitework – Site utilities to commence the first of February 

Front one story structure – demolition is complete, the slab for the kitchen area has been removed, and steel has been delivered for the reconstruction of the building enclosure 

Atrium – The slab has been removed, regrading of the floor has been completed, existing windows were removed and frames are ready to receive the new windows, and the new elevator shaft is near completion 

Residential Floors o First – Framing and electrical and mechanical rough‐ins in process o Second – Shower enclosure drywall being completed and electrical and 

mechanical rough‐ins in process o Third – Rough‐ins complete, floor penetration in‐fill in progress o Fourth – Sheetrock near completion, electrical and mechanical roughs complete, 

and shower installation commencing  Materials for the renovation have begun to arrive on site for staged installation.  Change Order #2 has been signed in the amount of $98,161 for unforeseen work to create fire rated exhaust risers and provide access doors and dampers.  To date the contractor has utilized approximately $72,000 of its $480,000 contract contingency and has utilized approximately $35,000 of its $230,000 of unforeseen conditions allowances contained in its GMP contract.  Total change orders charged to the Owner to date are $161,089.  Additional unforeseen items have been discovered and least costly solutions for remediation are under investigation, potential change order requests are currently estimated to be approximately $420,000 and are subject to change.  The project has an overall owner contingency of $1,225,000 and the contractor has a contract contingency of $480,000 for such items.     The construction draw in the was approved and will paid as required under the construction contract. 

Page 2: Tapestry Senior Living

MONTHLY REPORT #03

TAPESTRY WICKLIFFE WICKLIFFE, OHIO

ZUMBRUNNEN, INC. PROJECT #2016-122

SITE VISIT DATE(S): JANUARY 31, 2018 RECEIPT OF EXECUTED PAYMENT APPLICATION: FEBRUARY 16, 2018

OTHER REQUIRED DOCUMENTS RECEIVED (LATEST DATE): FEBRUARY 9, 2018 REPORT DATE: FEBRUARY 16, 2018

This Report is Specially Prepared for

Mr. Richard Bienapfl Tapestry Wickliffe, LLC

Page 3: Tapestry Senior Living

February 16, 2018 Mr. Richard Bienapfl Tapestry Wickliffe, LLC 2001 Killebrew Drive, Suite 100 Minneapolis, MN 55425 RE: Tapestry Wickliffe Wickliffe, Ohio SUBJ: Monthly Report No. 03 zumBrunnen Project No. 2016-122 Dear Mr. Bienapfl: Attached for your use and review is the above-referenced report for the site visit conducted on Wednesday, January 31, 2018. The purpose of this report is to provide documentation of this project site visit and sufficient information to assist you in project finance administration. zumBrunnen reports feature a unique and proprietary Contingency Graph in Exhibit A, and a listing of construction terminology, definitions, and methodology in Exhibit G. These exhibits will assist you in gaining a more comprehensive understanding of the status of your project, and assurance that the reports provided by zumBrunnen utilize consistent and professional reporting and analysis tools from month-to-month and project-to-project. The data, conclusions, and recommendations contained in this report are based on information gathered during our project site visit. We trust this report is complete. Should you require additional information or wish to discuss this report, please contact this office. Sincerely, zumBrunnen, Inc.

Doug McMillan, P.E. President

Page 4: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 3

TABLE OF CONTENTS

I. EXECUTIVE SUMMARY .............................................................................................. 4

II. PROJECT DESCRIPTION ............................................................................................. 4

A. Site Work ................................................................................................................ 5 B. Structures ................................................................................................................ 5 C. Stored Materials ...................................................................................................... 6

III. ACTION ITEMS ............................................................................................................... 6

A. Outstanding Project Documents ............................................................................. 6 B. Project Issues to Be Monitored and Resolved ........................................................ 6 C. Status of Permits ..................................................................................................... 6

IV. CONSTRUCTION CONTRACT .................................................................................... 7

A. Changes to the Construction Contract .................................................................... 7 B. Construction Contract ............................................................................................. 7 C. Substantial Completion Terminology ..................................................................... 7

V. CHANGE ORDERS ......................................................................................................... 7

A. Approved and Executed Change Orders ................................................................. 7 B. Pending and Potential Change Orders .................................................................... 8

VI. BUDGET SUMMARY DATA & ANALYSIS ............................................................... 8

A. Budget Summary Data ............................................................................................ 8 B. Budget Summary Analysis .................................................................................... 10

VII. PROJECT SCHEDULE & ANALYSIS ....................................................................... 10

A. Project Schedule Data ........................................................................................... 10 B. Project Schedule Analysis ..................................................................................... 11 C. Project Closeout Certificates and Documents ....................................................... 12

VIII. GENERAL REMARKS ................................................................................................. 12

A. Site Visit and Attendees ........................................................................................ 12 B. Finish Quality, Compliance, Maintenance/Protection, and Reports ..................... 12 C. Site Security, Site Conditions, and Project Activities ........................................... 13 D. Miscellaneous Comments ..................................................................................... 13

IX. CONTRACTOR’S PAYMENT APPLICATION OVERVIEW ................................ 13

EXHIBITS: A. Project Completion and Contingency Graphs, CPM Schedule B. Payment Application Documentation C. Stored Material Documentation and Requirements D. Change Order Documentation E. Project Directory and Other Miscellaneous Information F. Contract Summary; Closeout Documents & Requirements G. Definitions; Disclaimers H. Site Plan & Photographs

Page 5: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 4

I. EXECUTIVE SUMMARY The following conclusions are based on information available at the time of the issuance of this report. A checked box ( ) denotes information in the body of this report is pertinent to a full understanding of the referenced subject. Action Items: • Are there outstanding project documents to be expedited: Yes • Are there issues requiring Project Team’s attention at this time: No • Have all permits for construction been received: Yes

See Section III for further details. Budget Analysis and Sufficiency of Funds: • Total change orders recommended for approval this month: $161,089 (CO #1 & CO #2) • Total executed change orders to date: $161,089 • Total pending and potential change orders: $353,638 • The remaining construction contingency as a % of zumBrunnen estimated cost-to-

complete is 4.9% and the total committed construction contingency is 42.0%, which is a significant increase from the previous month, but consistent with our projected curve at this time. We consider the available contingency reasonable to complete the project. See Construction Contingency Graph included in Exhibit A.

• See Section VI, Paragraph B for further details. Time Extensions & Schedule Status: • Based on cash flow and our observation of the work completed to date, the project is

21% complete and on schedule for substantial completion by the contractual date shown below. See Project Completion Graph included in Exhibit A.

• Time extension approved this month: 0 calendar days • Original contract substantial completion date: September 1, 2018 • Current contract substantial completion date: September 1, 2018 • Contractor’s Projected Substantial Completion Date: September 1, 2018 See Section VII, Paragraphs A and B for further details.

Quality & Compliance Status: • Are finish quality issues noted in this report: No • Are construction or compliance issues noted in this report: No

See Section VIII, Paragraph B for further details. Payment Approval: • Contractor Payment Application #6 for Pay Period ending 01/31/18 requests a current

payment of $1,222,500.21. Retainage in the amount of $376,499.03 is being withheld, which is 10.3% of completed work and materials stored. Retainage released this month: $0.00. zumBrunnen recommends disbursement of funds as requested.

See Section IX for further details.

II. PROJECT DESCRIPTION The Project is the rehabilitation of an early 1970s Holiday Inn with Holidome located at 28500 Euclid Avenue, Wickliffe, Ohio. The project consists of an “L” shaped hotel room structure containing approximately 121,610 square feet of space to be converted to a combination of assisted living and memory care units.

Page 6: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 5

Distyle Design, of Minneapolis, Minnesota, is providing the professional design and consulting services. The Albert M. Higley Co. LLC, of Cleveland, Ohio (the Construction Manager), will construct the Project.

A. Site Work • Contractor has mobilized on site and set a construction trailer, perimeter fencing, and

gates. • Site clearing and grubbing is complete along with removal of trees. • Overall site demolition is now complete. • Site earthwork and cut/fill continued this month and is estimated to be 18% complete.

B. Structures

Existing Building • Exterior demolition is essentially complete with the existing high and low roof removed

and a temporary waterproofing membrane installed to dry in the building during the upcoming winter months.

• Mass demolition at the front of the building is essentially complete along with the removal of the mansard roof.

• Interior demolition of the suites is complete on the 2nd through 4th floors and nearing completion on the 1st floor.

• Exterior light gage framing and installation of sheathing continued this month with work accomplished this month along the north wall of the Atrium with window/glass installation scheduled to begin in early February in this location.

• Atrium slab has been demolished and removed. • Placement of interior footings on the 1st floor commenced this month and is estimated to

be 50% complete. • New elevator pit was previously placed and concrete masonry walls for the elevator pit

are now constructed to the underside of the roof deck. • Structural steel erection commenced this month and is continuing at this time at the north

exterior wall of the one-story portion of the building. • Underground plumbing rough-in continued on the 1st floor this month and is

approximately 80% complete. Concrete placement at utility trenches is now underway on the 1st floor.

• Interior sanitary and water pipe rough-in for the interior suites also continued this month and is approximately 80% complete overall with the 2nd floor complete and work underway on the 1st, 3rd, and 4th floor at this time.

• Installation of interior gas piping is unchanged from last month and is approximately 40% complete.

• Fire sprinkler pipe rough-in continues on all floors. • Delivery of sheet metal duct and accessories has commenced, with rough-in just

beginning in the interior suite areas. • Electrical boxes, low voltage conduit rough-in, and installation of cabling is underway in

all areas.

Page 7: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 6

• Interior light gage framing continued this month in the interior suite areas on all floors. Second floor bathroom framing is essentially complete with work continuing on the other floors at this time.

• Drywall installation behind prefabricated shower units commenced this month and is underway at this time.

• Installation commenced for resident suite unit entry door frames on the 4th floor this month and is continuing at this time.

C. Stored Materials

Stored Material Inventory Log is enclosed: N/A Materials Stored On-Site • Materials added this month: Underground MEP materials, light gage framing, sanitary,

water, and gas pipe, HVAC duct, prefabricated tub/shower units, structural steel, low voltage wiring and conduit, and exterior sheathing

• Materials are observed to be secured from theft: Construction fence is installed around the project site

• Materials are observed to be protected from the weather: N/A Materials Stored Off-Site The requirements for off-site stored material documentation are detailed in Exhibit C. See Section IX of this Report for recommendations pertaining to funding approval and detail of any outstanding documentation. • New materials added this month: Structural steel is stored off site and is in the process of

being delivered to the site

III. ACTION ITEMS A. Outstanding Project Documents

The following documents are required:

• Outstanding documents to be provided to zumBrunnen as required for financial closing: None

• Other: o None

B. Project Issues to Be Monitored and Resolved

• Status of Transmittal and Shop Drawing Log: Unknown; not provided during site visit • Status of RFI Log: Unknown; not provided during site visit • Other: None

C. Status of Permits

• Outstanding permit status: o The City of Wickliffe and Lake County have issued the building permits. Copies of

these permits were included in our Monthly Report #1 in December 2017.

Page 8: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 7

See Section VII, Paragraph C pertaining to status of certificates of occupancy.

IV. CONSTRUCTION CONTRACT A. Changes to the Construction Contract

For this month’s reporting period, have changes been made to the construction contract terms and conditions as detailed below or in Exhibit F: No

B. Construction Contract

Construction Contract Type and Amount: The Owner, Lake County Ohio Port and Economic Development Authority, has entered into a construction agreement with The Albert M. Higley Co. LLC, of Cleveland, Ohio, for the construction of the Tapestry Wickliffe project. The Lake County Ohio Port and Economic Development Authority is acting as the issuer of the bonds and will own the property that Tapestry will lease from them. LaSalle Development Group, Ltd will act as the construction agent for this project and control all aspects of project development and construction. • Standard Form of Agreement between Owner and Contractor: AIA Document A102-

2007 and AIA A201-2007 serves as General Conditions • Basis of Payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price. • Original contract amount: $17,220,882.00 • Contractor’s fee: $501,579 (3.0% of Cost of Work)

C. Substantial Completion Terminology Please note that zumBrunnen or others in verbal or written reports may make reference to various activities or construction of various components of work for the Project as substantially complete. Only when the reference includes the term "contract" can these references to substantially complete (or substantial completion) be interpreted as compliance with the requirements for the construction contract substantial completion schedule, as defined in the project construction contract documents. When the term "contract" is not included, it is then interpreted that the work per the construction contract referenced is simply "nearly complete" and has no direct relationship to the construction contract schedule for substantial completion.

V. CHANGE ORDERS

A. Approved and Executed Change Orders This month’s change order(s) approved by the Owner, Architect, and Contractor are submitted for approval with zumBrunnen’s recommendations as detailed below: • Change Order No. 1; (+) $62,928.01; time extension: 0 calendar days;

o Description/comments: Additional asbestos abatement, ductwork, and support rails for RTUs 5 & 6, and re-routing of underground hot water lines to be above ground

o Reason for the change order: Mandatory o Recommended to be funded from: Project Contingency

• Change Order No. 2; (+) $98,161.06; time extension: 0 calendar days;

o Description/comments: Insulation, dampers and fire access to bathroom walls, and

Page 9: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 8

change hollow metal door frames in concrete masonry walls to solid welded frames o Reason for the change order: Mandatory o Recommended to be funded from: Project Contingency

CHANGE ORDER LOG*

C.O. No. Amount Previous total through N/A $0

1 - 2 This month's executed changes $161,089 Total $161,089

*Where applicable and available, the Contractor's change order log is included in Exhibit D. • A copy of each change order executed this month is enclosed with this report: Yes • zumBrunnen recommends approval of the following change orders submitted by the

Borrower for approval by the Lender: COs #1 and #2 • Change orders included in this month’s payment application: CO #1

B. Pending and Potential Change Orders Total pending and potential change orders: $353,638; see Exhibit D for the Contractor’s Change Order / Contingency Log • The following pending changes may be in dispute:

o None • zumBrunnen may recommend that the following pending changes not be approved:

o None This log does not include estimates or an allowance for unknown future change orders. An estimated allowance for these change orders is included in the zumBrunnen estimated cost-to-complete in Section VI, Paragraph A.

VI. BUDGET SUMMARY DATA & ANALYSIS A. Budget Summary Data

The following summary table includes an analysis of the total committed hard cost project funds to date, including executed change orders and estimated values for pending changes. These costs are compared to the hard cost project budget, to determine, in zumBrunnen’s opinion, if the remaining HC contingency will be sufficient to complete the project. This analysis helps provide the earliest possible notice of a hard cost construction budget overrun.

Page 10: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 9

Original Construction Budget $17,220,882.00Combined (Hard Cost/Soft Cost) Project Contingency¹ $1,225,000.00

Total Hard Cost Budget $18,445,882.00

Original Construction Contract $17,220,882.00Executed Change Order(s) #1 & #2 $161,089.00Pending & Potential Change Orders $353,638.00

Total Projected Hard Costs $17,735,609.00

Remaining HC Contingency (Balance) $710,273.00Committed (Encumbard) HC Contingency Funds $514,727.00zumBrunnen Estimated Cost-To-Complete* $14,438,319.00Remaining HC Contingency as a % of zumBrunnen Cost-To-Complete 4.9%Committed HC Contingency as a % of HC Contingency Budget 42.0%

BUDGET SUMMARY TABLEProject Hard Cost Budget

Project Hard Costs

*zumBrunnen Estimated Cost-To-Complete: Calculated based on data and assumptions as detailed in Exhibit G - Definitions. ¹ The amount currently shown in the chart reflects the full hard and soft cost contingency for the project. zumBrunnen will confirm each month as to whether any of this contingency amount was allocated for use other than hard cost constructions. History of budget transfers/adjustments between HC Contingency and Soft Cost Contingency or the Total Project Budget: • No changes to date Contractor’s G702 and G703 Contract Budget Update: • Percentage of buyout completed: Unknown at time of site visit • Remaining contractor contingency including any projected buyout savings:

o In total dollars: $469,525.86 o As a percentage of zumBrunnen Estimated Cost-to-Complete: 3.3%

• Has the Contractor made any significant changes in his scope of "self-performed" work? No

HC Contingency Chart: See Exhibit A (for an explanation of the chart see Exhibit G – Definitions). • Projected project HC contingency usage through this month: 40% • Actual Committed (Encumbered) HC Contingency through this month: 42% • See below paragraph B for further discussions for significant variances or month to

month changes

Page 11: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 10

B. Budget Summary Analysis

The following Analysis includes Conclusions, Supporting Comments, and Actions/ Precautions/ Recommendations based on the above Budget Data, the current payment application, and zumBrunnen’s observations and interviews. Conclusions/Recommendations: Based on evaluation of the estimated cost-to-complete, HC Contingency funds, including any other funds, or pertinent information as may be discussed below, zumBrunnen concludes that sufficient funds remain in the project hard cost budget to complete construction of the project, with the following qualifications: fund all mandated change orders as can be reasonably anticipated, fund only those discretionary change orders as approved by zumBrunnen when a source of funds has been identified other than the HC contingency, and no extraordinary events occur. Actions/Precautions: • The highest risk of encountering unknown conditions that may result in cost changes to

the contract generally occurs during sitework, grading, and underground construction operations.

• No immediate action is required. The amount of Owner-held contingency appears to be adequate to complete the project at this time.

VII. PROJECT SCHEDULE & ANALYSIS

A. Project Schedule Data The construction contract allows after N-T-P: 304 calendar days The Notice-to-Proceed was issued: November 1, 2017 Contract substantial completion date based on the N-T-P date: September 1, 2018 zumBrunnen's Pre-Closing Report concluded that the 304-calendar-day duration was sufficient to complete the project.

Project Substantial Completion (SC) Dates Building Interim

SC Dates Original SC Date

Approved Time

Extensions

Contract SC Date

Contractor Estimated SC Date

Actual SC Date

Overall Contract N/A 9/1/18 0 9/1/18 9/14/18 N/A Total Project Contract Dates 9/1/18 0 9/1/18 9/14/18 N/A

Executed Time Extension Change Orders: • None to date Approved, Pending and Potential Time Extensions in Calendar Days: • Approved, in process to be executed: None • Pending and potential; under review or disputed: None

Page 12: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 11

Schedule: • Copy of the Contractor’s schedule is enclosed: Yes • Does the schedule include approved time extensions? N/A • Are actual critical path activities within the projected completion dates? No • Comments: The updated schedule this month indicates a delay in substantial completion

of 2 weeks from the contractual date of September 1, 2018. Current projected substantial completion is September 14, 2018.

B. Project Schedule Analysis

The following Analysis, Conclusions, Supporting Comments, and Actions/ Precautions/ Recommendations are based on the above Project Schedule Data, the current payment application, and zumBrunnen’s observations and interviews. Project Completion Status Curve (S-Curve): See Exhibit A (for an explanation of the chart see Exhibit G – Definitions). • Based on "forecasted" cash flow analysis for this month, the Project Completion S-Curve

forecast indicates the project should be 16% complete. Based on "actual" cash flow analysis of this months’ approved payment application period, project completion is estimated at approximately: 21%.

• A variance between the above two numbers of "forecasted" and "actual" is an indicator of the actual schedule status; is the project on schedule, ahead or behind schedule? The variance this month reflects: The cash flow curve indicates the project is tracking on schedule, although the updated schedule shows the project as 2 weeks behind.

• zumBrunnen estimates the project completion at: 21% • See below paragraph “Supporting Comments” for further discussions pertaining to

significant variances. Analysis: • Once the project reaches the month of March 2018, the average month-to-month rate of

completion should be relatively consistent; the Contractor should achieve on average 14% to 16% a month for the next 5 months after reaching this point. See the enclosed Project Completion Status Curve in Exhibit A. o The percent completed for just this month is: 8.0% or $1M; the project is still in the

startup phase and should reach the desired rate of completion by March 2018. o Comments: None

• Issues noted that may affect the schedule: o Inclement weather and unforeseen conditions during sitework activities

Conclusions: • zumBrunnen’s estimated contract substantial completion date: 9/1/18 • Variance in calendar days between the zumBrunnen estimated contract substantial

completion date and contract substantial completion: None; there is sufficient time left in the project to make up the current 2-week schedule delay.

Page 13: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 12

Supporting Comments: • The project is properly managed and the delays encountered to date are manageable, and

there is sufficient time left in the project to make up the current 2-week deficit. Actions/Precautions/Recommendations: • The Contractor meets weekly with subcontractors to review progress, issues, and critical

schedules and coordination. Ensure the Architect is keeping up with timely responses to submittals and RFIs.

• Keep a close watch on the weekly schedules; ensure the Contractor is monitoring and expediting submittals, and that the Owner is kept fully apprised of all critical items.

C. Project Closeout Certificates and Documents

As the Project approaches completion, this Section will track the required documents such as those noted in Exhibit F.

VIII. GENERAL REMARKS A. Site Visit and Attendees

The site visit was conducted on the date(s) as noted on the report cover sheet. The attendance list is as follows: Tapestry Wickliffe, LLC Terry Sparrow, Owner’s Rep. Distyle Design Michael Knisely, Project Architect (not present) AM Higley Construction, LLC Michael Shean, Project Manager Timothy Lorion, Project Engineer Robert Jensik, Sr. Superintendent Visitors: None zumBrunnen Doug McMillan, President

B. Finish Quality, Compliance, Maintenance/Protection, and Reports Finish Quality: List any observations regarding finish quality: • No issues noted this month Compliance: The following items and observations were reviewed with the project team pertaining to compliance with contract documents and industry standards:

Page 14: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 13

• No issues noted this month Project Maintenance/Protection: • Is completed work properly maintained and protected from damage? Yes • Is the Contractor keeping the project sufficiently clean and clear of trash? Yes Test and Other Reports: Based on site observations and interviews, zumBrunnen will review and receive copies of field test reports as deemed necessary. • Soil test reports: No issues were noted requiring review of field test reports • Concrete test lab reports: No issues were noted requiring review of field test reports

C. Site Security, Site Conditions, and Project Activities

Site Security: • The property site appears to be properly secured: Yes, construction fence is installed

around the project site • Security service: None Site Conditions: • Weather: 42° with partly cloudy skies • Precipitation: None • Condition of the project site: Stable Project Activities: • Interior MEP rough-in, and CMU and light gage/steel erection was observed during the

site visit. • Do management and work force levels appear appropriate? Yes

o Comments: None

D. Miscellaneous Comments • The next zumBrunnen site visit is scheduled for Tuesday, March 6, 2018, at 9:00 AM,

ET. Any interested parties wishing to attend this meeting should coordinate with either AM Higley Construction or zumBrunnen.

IX. CONTRACTOR’S PAYMENT APPLICATION OVERVIEW

Contractor Payment Application #6 for Pay Period ending 01/31/18 requests a current payment of $1,222,500.21. Retainage in the amount of $376,499.03 is being withheld, which is 10.3% of completed work and materials stored. Retainage released this month: $0.00. zumBrunnen recommends disbursement of funds as requested. See Exhibit B for the Contractor’s signed and executed Payment Application form G702 and G703 that summarizes: change orders executed this month, total contract amount, work completed and materials stored to date, retainage, previous payments, and funds remaining to be dispersed including retainage.

Page 15: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project 2016-122

Page 14

Comments pertaining to interpretation of, or adjustments to, the payment application: • None Stored materials (see Section II, Paragraph C for summary list of stored materials): • zumBrunnen recommends payment for the stored materials as submitted: N/A • If "No", provide list of any missing documentation required for approval, explanation,

and recommendation: N/A Adjustments for liquidated damages: • N/A Retainage: • Percentage of total work completed and stored materials withheld as retainage last

payment period: 9.8% • Percentage of total work completed and stored materials withheld as retainage this

payment period: 10.6% • Retainage released this month: $0.00 • Notice to surety required and copy enclosed: N/A Based on review of each budget item in the payment application, it is concluded: • Each budget line item drawn against is less than or equal to the status of completion for

that item based on percent complete: Yes • No one item has been funded beyond 100% of the current budget line item: Yes • Sufficient funds remain budgeted to complete work currently under contract: Yes • Please note that sufficiency of funds to complete the construction contract requires

analysis of the project hard cost budget. For this analysis, see Section VI, Paragraphs A and B.

Lien waivers provided: • The Contractor has provided executed unconditional lien waiver for payments received

prior to this payment application: Yes • The Contractor has provided material invoices and subcontractor billings complete with

executed unconditional lien waivers for payments received prior to this payment application: N/A; previous application did not include any subcontractor billing

• The Contractor has provided executed conditional lien waiver for payments requested in the current payment application: Yes

• Material invoices and subcontractor billings are complete, with executed conditional lien waivers for payments including this payment application: Yes

• Have there been any liens filed against the project: No Based on the site visit observations, interviews, and the above review and conclusions, zumBrunnen recommends disbursement of funds in the amount of: $1,222,500.21

Page 16: Tapestry Senior Living

EXHIBIT A

Page 17: Tapestry Senior Living

*Each line represents 1st day of the month **All Percentage tied to the Notice To Proceed Date (± 1 week)

0

10

20

30

40

50

60

70

80

90

100

N-2017 D J-2018 F M A M J J A S O

• Notice to Proceed: 11/01/17 Original Date of Substantial Completion: 304 days; 09/1/18 date Revised Date of Substantial Completion: _____ days _____date

Notes: None

% C

ompl

ete

Projected Actual

Project Completion Graph Tapestry Wickliffe, Project #2016-122, Date: 02/01/18

Construction Monitor's Estimated Percent Complete: 21%

Page 18: Tapestry Senior Living

Hard Cost Construction Contingency Graph

* Each line represents the first day of the month

0102030405060708090

100110120130140150

N/2017 D J/2018 F M A M J J A S O N

Original Hard Cost Contingency Budget: $1,225,000Current Hard Cost Contingency Budget: _________

% H

ard

Cos

tCon

stru

ctio

n C

ontin

genc

y En

cum

bere

d

Projected Actual

Project schedule: 11-month substantial completion and 12-month completion

Tapestry Wickliffe, Project #2016-122 Date: 02/01/18 Encumbered Hard Cost Contingency: 42.0%

Page 19: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

TAPESTRYTAPESTRYTAPESTRYTAPESTRYTAPESTRYTAPESTRYTAPESTRYPRE-CONSPRE-CONSTRUCTIONPRE-CONSTRUCTIONPRE-CONSTRUCTIONPRE-CONSTRUCTIONPRE-CONSTRUCTIONPRE-CONSTRUCTION

PRE-110 CONSTRUCTION PERMIT 21d 08-28-17 A 09-26-17 A AMH

PRE-130 COMPILE GMP 3d 09-11-17 A 09-13-17 A AMH

PRE-140 OWNER REVIEW GMP / FINANCING 32d 09-14-17 A 10-27-17 A OWN

PRE-160 AWARD SUBCONTRACTS 9d 10-19-17 A 12-08-17 A AMH

PRE-170 PREVIOUS OWNER ITEMS REMOVED 0d 10-31-17 A OWN

PRE-150 GMP APPROVAL AND NOTICE TO PROCEED 0d 10-31-17 A OWN

PROCUREMEPROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENTPROCUREMENTSTRUCTURALSTRUCTURAL STEELSTRUCTURAL STEELSTRUCTURAL STEELSTRUCTURAL STEELSTRUCTURAL STEELSTRUCTURAL STEEL

PRE-370 STEEL SUBMITTALS 10d 11-01-17 A 11-24-17 A ELEV

PRE-380 STEEL APPROVAL 5d 11-27-17 A 11-29-17 A ELEV

PRE-390 STEEL LEAD TIME 10d 12-08-17 A 01-05-18 A ELEV

SHOWER UNITSHOWER UNITSSHOWER UNITSSHOWER UNITSSHOWER UNITSSHOWER UNITSSHOWER UNITS

PRE-180 SHOWER UNIT SUBMITTALS 5d 11-02-17 A 11-09-17 A AMH

PRE-190 SHOWER UNIT APPROVAL 5d 11-10-17 A 11-21-17 A ARC

PRE-350 SHOWER UNIT REVISE AND RESUBMIT 5d 11-13-17 A 11-21-17 A AMH

PRE-200 SHOWER UNIT LEAD TIME 4TH FLOOR 20d 11-22-17 A 12-29-17 A AMH

PRE-410 SHOWER UNIT LEAD TIME 3RD FLOOR INITIAL 40d 11-22-17 A 01-19-18 A

PRE-420 SHOWER UNIT LEAD TIME 2ND FLOOR PARTIAL 5d 11-22-17 A 02-12-18 20d

PRE-430 SHOWER UNIT LEAD TIME 2ND FLOOR REMAINING 5d 11-22-17 A 02-28-18 16d

PRE-221 SHOWER UNIT LEAD TIME 3RD FLOOR REMAINING & PA 40d 11-22-17 A 01-30-18 A

PRE-440 SHOWER UNIT LEAD TIME 1ST FLOOR INITIAL 5d 11-22-17 A 03-14-18 -3d

PRE-450 SHOWER UNIT LEAD TIME 1ST FLOOR REMAINING 5d 11-22-17 A 03-28-18 -3d

ELEVATORELEVATORELEVATORELEVATORELEVATORELEVATORELEVATOR

PRE-240 ELEVATOR SUBMITTALS 10d 11-03-17 A 11-16-17 A ELEV

PRE-250 ELEVATOR APPROVAL 10d 11-17-17 A 11-28-17 A ELEV

PRE-260 ELEVATOR LEAD TIME 65d 11-29-17 A 04-02-18 -9d ELEV

FIBERGLASS FIBERGLASS WINDOW SUBMITTALFIBERGLASS WINDOW SUBMITTALFIBERGLASS WINDOW SUBMITTALFIBERGLASS WINDOW SUBMITTALFIBERGLASS WINDOW SUBMITTALFIBERGLASS WINDOW SUBMITTAL

PRE-330 WINDOW SUBMITTALS 3d 11-03-17 A 11-16-17 A V

PRE-340 WINDOW APPROVAL 2d 11-17-17 A 11-22-17 A ARC

PRE-360 WINDOW LEAD TIME 50d 11-24-17 A 01-29-18 A PELLA

TOILETSTOILETSTOILETSTOILETSTOILETSTOILETSTOILETS

PRE-210 2 PIECE WATER CLOSET SUBMITTALS 5d 11-03-17 A 11-10-17 A HP

PRE-220 2 PIECE WATER CLOSET APPROVALS 5d 11-13-17 A 11-20-17 A ARC

PRE-230 2 PIECE WATER CLOSET LEAD TIME 50d 11-21-17 A 01-15-18 A HP

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

CONSTRUCTION PERMIT

COMPILE GMP

OWNER REVIEW GMP / FINANCING

AWARD SUBCONTRACTS

PREVIOUS OWNER ITEMS REMOVED

GMP APPROVAL AND NOTICE TO PROCEED

STEEL SUBMITTALS

STEEL APPROVAL

STEEL LEAD TIME

SHOWER UNIT SUBMITTALS

SHOWER UNIT APPROVAL

SHOWER UNIT REVISE AND RESUBMIT

SHOWER UNIT LEAD TIME 4TH FLOOR

SHOWER UNIT LEAD TIME 3RD FLOOR INITIAL

SHOWER UNIT LEAD TIME 2ND FLOOR PARTIAL

SHOWER UNIT LEAD TIME 2ND FLOOR REMAINING

SHOWER UNIT LEAD TIME 3RD FLOOR REMAINING & PARTIAL 2ND

SHOWER UNIT LEAD TIME 1ST FLOOR INITIAL

SHOWER UNIT LEAD TIME 1ST FLOOR REMAINING

ELEVATOR SUBMITTALS

ELEVATOR APPROVAL

ELEVATOR LEAD TIME

WINDOW SUBMITTALS

WINDOW APPROVAL

WINDOW LEAD TIME

2 PIECE WATER CLOSET SUBMITTALS

2 PIECE WATER CLOSET APPROVALS

2 PIECE WATER CLOSET LEAD TIME

Print Date: 02-01-18Page 1 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 20: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

LVLLVLLVLLVLLVLLVLLVL

PRE-270 LVL SUBMITTALS 8d 11-01-17 A 11-15-17 A O

PRE-280 LVL APPROVAL 5d 11-16-17 A 12-04-17 A ARC

PRE-400 LVL RESUBMITTAL 5d 11-27-17 A 12-01-17 A O

PRE-290 LVL LEAD TIME 5d 12-08-17 A 12-14-17 A O

FIRE DAMPERFIRE DAMPERSFIRE DAMPERSFIRE DAMPERSFIRE DAMPERSFIRE DAMPERSFIRE DAMPERS

PRE-300 FIRE DAMPER SUBMITTALS 5d 11-02-17 A 11-10-17 A V

PRE-310 FIRE DAMPER APPROVAL 5d 11-13-17 A 11-17-17 A ARC

PRE-320 FIRE DAMPER LEAD TIME 20d 11-20-17 A 02-01-18 A V

ISSUESISSUESISSUESISSUESISSUESISSUESISSUES

ISSUE - 1060 ELECTRIC CO. WORK ORDER/APPLICATION & LEAD TIM 5d 11-01-17 A 04-05-18 4d

ISSUE - 1030 ATRIUM UG & ARCH REDESIGN PR#2 / PRICING & APPR 5d 11-24-17 A 02-14-18 -6d

ISSUE - 100 SINGLE STORY STRUCTURAL VARIATIONS - PR # 1CL 13 5d 12-05-17 A 02-07-18 154d AMH

ISSUE - 1010 PIPE CHASE RE-DESIGN & PARTIAL AUTHORIZATION 5d 12-11-17 A 12-28-17 A

ISSUE - 1050 PIPE CHASE RE-DESIGN : DRYWALL & DAMPER AUTHOR 5d 12-11-17 A 01-18-18 A

ISSUE - 1020 MISSING STEEL AT X LINE & RESOLUTION 5d 12-19-17 A 01-11-18 A

ISSUE - 1000 KITCHEN REDESIGN /PRICING & APPROVAL 5d 12-20-17 A 02-09-18 -9d

ISSUE - 120 OWNER TELE DATA& SECURITY ROUGH IN : IN WALL 10d 01-10-18 A 02-16-18 1d

ISSUE - 1040 OWNER TELE DATA& SECURITY ROUGH IN : UNDERGR 10d 01-10-18 A 02-16-18 -5d

ISSUE - 130 SOMD EXPANSION JOINT DESIGN, PRICING & APPROVA 5d 01-10-18 A 02-07-18 -4d

ISSUE - 110 FABRICATE PR1 MISC STEEL ON CL 13 10d 01-18-18 A 01-25-18 A AMH

CONSTRUCCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONSITEWORKSITEWORKSITEWORKSITEWORKSITEWORKSITEWORKSITEWORK

EXT-100 FENCING & MAKE SAFE 2d 11-01-17 A 11-10-17 A PL

MILE-100 CONSTRUCTION START 0d 11-01-17 A OWN

EXT-130 MAT'L ACCESS BAYS 5d 11-02-17 A 11-08-17 A AMH

EXT-105 DEMO POOL AREA 3d 11-07-17 A 11-07-17 A PL

EXT-115 INFILL POOL AREA 5d 11-07-17 A 11-07-17 A PL

EXT-135 BUILDING DEMO AT POOL 3d 11-16-17 A 11-20-17 A K

EXT-145 REMAINING POOL AREA INFILL 1d 11-30-17 A 11-30-17 A PL

EXT-140 SITE UTILITIES 20d 02-05-18* 03-02-18 0d PL

EXT-125 EMERGENCY GENERATOR 5d 02-05-18 02-09-18 78d Z

EXT-150 DEMO SITE PAVEMENTS 10d 02-19-18 03-02-18 63d PL

EXT-250 SITE DUCTBANKS & PAD 15d 02-23-18 03-15-18 19d Z

EXT-280 SITE STRUCTURES 20d 02-26-18 03-23-18 63d T

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

LVL SUBMITTALS

LVL APPROVAL

LVL RESUBMITTAL

LVL LEAD TIME

FIRE DAMPER SUBMITTALS

FIRE DAMPER APPROVAL

FIRE DAMPER LEAD TIME

ELECTRIC CO. WORK ORDER/APPLICATION & LEAD TIME

ATRIUM UG & ARCH REDESIGN PR#2 / PRICING & APPROVAL

SINGLE STORY STRUCTURAL VARIATIONS - PR # 1CL 13 INCLUDING APPROVAL

PIPE CHASE RE-DESIGN & PARTIAL AUTHORIZATION

PIPE CHASE RE-DESIGN : DRYWALL & DAMPER AUTHORIZATION

MISSING STEEL AT X LINE & RESOLUTION

KITCHEN REDESIGN /PRICING & APPROVAL

OWNER TELE DATA& SECURITY ROUGH IN : IN WALL

OWNER TELE DATA& SECURITY ROUGH IN : UNDERGROUND

SOMD EXPANSION JOINT DESIGN, PRICING & APPROVAL

FABRICATE PR1 MISC STEEL ON CL 13

FENCING & MAKE SAFE

CONSTRUCTION START

MAT'L ACCESS BAYS

DEMO POOL AREA

INFILL POOL AREA

BUILDING DEMO AT POOL

REMAINING POOL AREA INFILL

SITE UTILITIES

EMERGENCY GENERATOR

DEMO SITE PAVEMENTS

SITE DUCTBANKS & PAD

SITE STRUCTURES

Print Date: 02-01-18Page 2 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 21: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

EXT-360 NEW SERVICE AND TRANSFORMER 5d 04-06-18 04-12-18 4d Z

EXT-260 CONCRETE CURBS 10d 04-13-18 04-26-18 34d T

EXT-270 CONCRETE PAVING / WALKS 10d 04-20-18 05-03-18 34d T

EXT-290 STONE & ASPHALT 10d 05-04-18 05-17-18 34d PRE

EXT-300 DECORATIVE FENCING & RAILINGS 5d 05-18-18 05-24-18 34d T

EXT-310 SITE LIGHTING 15d 05-18-18 06-08-18 39d Z

EXT-320 SITE FURNISHINGS 10d 05-25-18 06-08-18 34d T

EXT-330 LANDSCAPING 15d 06-04-18 06-22-18 34d L-1

EXT-340 SIGNAGE 5d 06-18-18 06-22-18 34d T

PORTE COCHPORTE COCHEREPORTE COCHEREPORTE COCHEREPORTE COCHEREPORTE COCHEREPORTE COCHERE

EXT-180 FOOTERS 5d 02-07-18* 02-13-18 0d T

EXT-190 STEEL 5d 02-14-18 02-20-18 18d L

EXT-200 CARPENTRY 8d 02-21-18 03-02-18 18d O

EXT-210 ROOFING 7d 03-05-18 03-13-18 18d W

EXT-220 MASONRY 5d 03-14-18 03-20-18 18d V-1

EXT-230 EIFS 5d 04-16-18* 04-20-18 0d O

EXT-240 PAINTING 5d 04-23-18 04-27-18 78d A

EXTERIOR FAEXTERIOR FACADEEXTERIOR FACADEEXTERIOR FACADEEXTERIOR FACADEEXTERIOR FACADEEXTERIOR FACADEEAST ELEVATEAST ELEVATIONEAST ELEVATIONEAST ELEVATIONEAST ELEVATIONEAST ELEVATIONEAST ELEVATION

E-1000 REMOVE STOREFRONTS FOR TEMP ACCESS 2d 11-01-17 A 11-02-17 A PI

E-1020 FRAMING & SHEATHING 15d 11-10-17 A 12-07-17 A O

E-1010 EXTERIOR DEMO 4d 11-30-17 A 12-06-17 A K

E-1040 SIDING & TRIM 20d 04-16-18* 05-11-18 0d O

E-1050 PAINT & SEALANTS 25d 05-14-18 06-18-18 43d A

NORTH ELEVANORTH ELEVATIONNORTH ELEVATIONNORTH ELEVATIONNORTH ELEVATIONNORTH ELEVATIONNORTH ELEVATION

N-1000 REMOVE STOREFRONTS FOR TEMP ACCESS 2d 11-01-17 A 11-02-17 A PI

N-1020 FRAMING & SHEATHING 8d 11-29-17 A 12-13-17 A O

N-1010 EXTERIOR DEMO 8d 12-06-17 A 12-13-17 A K

N-1040 SIDING & TRIM 20d 05-14-18 06-11-18 23d O

N-1050 PAINT & SEALANTS 25d 06-12-18 07-17-18 23d A

WEST ELEVATWEST ELEVATIONWEST ELEVATIONWEST ELEVATIONWEST ELEVATIONWEST ELEVATIONWEST ELEVATION

W-1000 PAINT & SEALANTS 15d 06-12-18 07-02-18 33d A

SOUTH ELEVASOUTH ELEVATIONSOUTH ELEVATIONSOUTH ELEVATIONSOUTH ELEVATIONSOUTH ELEVATIONSOUTH ELEVATION

S-1050 MISC STEEL ON CL 13 5d 01-26-18 A 02-01-18 A L

S-1000 FRAMING & SHEATHING 15d 02-05-18 02-23-18 30d O

S-1010 STOREFRONT 10d 02-19-18 03-02-18 30d PI

S-1020 DOORS 10d 02-19-18 03-02-18 30d F

S-1030 EIFS 10d 04-16-18* 04-27-18 0d O

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

NEW SERVICE AND TRANSFORMER

CONCRETE CURBS

CONCRETE PAVING / WALKS

STONE & ASPHALT

DECORATIVE FENCING & RAILINGS

SITE LIGHTING

SITE FURNISHINGS

LANDSCAPING

SIGNAGE

FOOTERS

STEEL

CARPENTRY

ROOFING

MASONRY

EIFS

PAINTING

REMOVE STOREFRONTS FOR TEMP ACCESS

FRAMING & SHEATHING

EXTERIOR DEMO

SIDING & TRIM

PAINT & SEALANTS

REMOVE STOREFRONTS FOR TEMP ACCESS

FRAMING & SHEATHING

EXTERIOR DEMO

SIDING & TRIM

PAINT & SEALANTS

PAINT & SEALANTS

MISC STEEL ON CL 13

FRAMING & SHEATHING

STOREFRONT

DOORS

EIFS

Print Date: 02-01-18Page 3 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 22: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

S-1040 PAINT & SEALANTS 10d 04-30-18 05-11-18 68d A

ROOFINGROOFINGROOFINGROOFINGROOFINGROOFINGROOFINGUPPERUPPERUPPERUPPERUPPERUPPERUPPER

ROOF-180 UPPER: REMOVE GAS LINES 10d 11-01-17 A 11-02-17 A HP

ROOF-170 UPPER: REMOVE RTU'S 5d 11-02-17 A 11-03-17 A V

ROOF-360 UPPER:: REMOVE ROOF & INSTALL TEMP ROOF 10d 11-06-17 A 11-22-17 A W

ROOF-200 UPPER: REWORK ROOF DRAINS 5d 11-20-17 A 11-22-17 A HP

ROOF-190 UPPER: REPLACE ROOF 20d 05-07-18 06-04-18 13d W

ROOF-210 UPPER: MODIFY BLOCKING 20d 05-07-18 06-04-18 13d O

ROOF-340 UPPER: NEW GAS LINE 10d 06-05-18 06-18-18 13d HP

ROOF-350 UPPER: HVAC UNITS 10d 06-05-18 06-18-18 13d V

INTERMEDIATINTERMEDIATEINTERMEDIATEINTERMEDIATEINTERMEDIATEINTERMEDIATEINTERMEDIATE

ROOF-110 INTERMEDIATE: REMOVE GAS LINES 8d 11-01-17 A 11-02-17 A HP

ROOF-100 INTERMEDIATE: REMOVE RTU'S 5d 11-02-17 A 11-03-17 A V

ROOF-280 INTERMEDIATE:: REMOVE ROOF & INSTALL TEMP ROOF 10d 11-06-17 A 11-22-17 A W

ROOF-220 INTERMEDIATE :REWORK ROOF DRAINS 5d 11-20-17 A 11-22-17 A HP

ROOF-120 INTERMEDIATE: REPLACE ROOF 25d 04-02-18* 05-04-18 0d W

ROOF-230 INTERMEDIATE: MODIFY BLOCKING 25d 04-02-18 05-04-18 92d O

LOWERLOWERLOWERLOWERLOWERLOWERLOWER

ROOF-140 LOWER: REMOVE GAS LINES 15d 11-01-17 A 11-01-17 A HP

ROOF-240 LOWER: REMOVE RTU'S 10d 11-01-17 A 11-01-17 A V

ROOF-130 LOWER: REMOVE SLOPED 10d 11-02-17 A 11-06-17 A W

ROOF-270 LOWER: REMOVE ROOF & INSTALL TEMP ROOF 25d 11-22-17 A 01-19-18 A W

ROOF-250 LOWER: REWORK ROOF DRAINS 10d 12-04-17 A 01-19-18 A HP

ROOF-320 LOWER : NEW & MODIFIED STEEL 5d 01-15-18 A 01-16-18 A L

ROOF-160 LOWER: REPLACE ROOF 25d 04-02-18* 05-04-18 0d W

ROOF-260 LOWER: MODIFY BLOCKING 25d 04-02-18 05-04-18 82d O

ROOF-290 LOWER: NEW GAS LINE 10d 05-07-18 05-18-18 82d HP

ROOF-300 LOWER: SCREEN WALL 10d 05-07-18 05-18-18 82d L

ROOF-310 LOWER: HVAC UNITS 10d 05-07-18 05-18-18 82d V

ATRIUMATRIUMATRIUMATRIUMATRIUMATRIUMATRIUMX LINEX LINEX LINEX LINEX LINEX LINEX LINE

ATR-110 ABATEMENT 3d 11-03-17 A 11-07-17 A PER

X-121 DEMO X LINE 5d 12-11-17 A 12-15-17 A K

X-100 REWORK STEEL 5d 12-28-17 A 12-29-17 A L

X-120 LVL, FRAMING & SHEATHING 15d 01-04-18 A 02-01-18 A O

X-110 ADDITIONAL MISSING STEEL WORK 2d 01-10-18 A 01-11-18 A

X-150 ALUMINUM CLADDING & WINDOWS AT 8.75 LINE 12d 02-05-18 02-20-18 -7d T

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

PAINT & SEALANTS

UPPER: REMOVE GAS LINES

UPPER: REMOVE RTU'S

UPPER:: REMOVE ROOF & INSTALL TEMP ROOF

UPPER: REWORK ROOF DRAINS

UPPER: REPLACE ROOF

UPPER: MODIFY BLOCKING

UPPER: NEW GAS LINE

UPPER: HVAC UNITS

INTERMEDIATE: REMOVE GAS LINES

INTERMEDIATE: REMOVE RTU'S

INTERMEDIATE:: REMOVE ROOF & INSTALL TEMP ROOF

INTERMEDIATE :REWORK ROOF DRAINS

INTERMEDIATE: REPLACE ROOF

INTERMEDIATE: MODIFY BLOCKING

LOWER: REMOVE GAS LINES

LOWER: REMOVE RTU'S

LOWER: REMOVE SLOPED

LOWER: REMOVE ROOF & INSTALL TEMP ROOF

LOWER: REWORK ROOF DRAINS

LOWER : NEW & MODIFIED STEEL

LOWER: REPLACE ROOF

LOWER: MODIFY BLOCKING

LOWER: NEW GAS LINE

LOWER: SCREEN WALL

LOWER: HVAC UNITS

ABATEMENT

DEMO X LINE

REWORK STEEL

LVL, FRAMING & SHEATHING

ADDITIONAL MISSING STEEL WORK

ALUMINUM CLADDING & WINDOWS AT 8.75 LINE

Print Date: 02-01-18Page 4 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 23: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

X-160 ALUM CLADDING & WINDOWS X LINE 24d 02-21-18 03-26-18 7d PELLA

X-140 EIFS 20d 04-09-18* 05-04-18 0d O

INTERIORINTERIORINTERIORINTERIORINTERIORINTERIORINTERIOR

ATR-100 DUCTWORK DEMO 10d 11-06-17 A 11-09-17 A K

ATR-240 DEMO INTERIOR BLDG FACADE 12d 11-07-17 A 11-16-17 A K

ATR-350 FRAMING & SHEATHING 9d 11-17-17 A 12-04-17 A O

ATR-490 1ST FLOOR STOREFRONT REMOVAL 2d 11-23-17 A 11-23-17 A PI

ATR-120 DEMO 3 SLABS @ ELEVATOR 5d 12-04-17 A 12-04-17 A K

ATR-140 CONSTRUCT ELEVATOR PIT & FOOTERS 10d 12-08-17 A 12-15-17 A T

ATR-430 MECHANICAL WALL ROUGH IN 15d 12-08-17 A 01-27-18 A V

ATR-450 PLUMBING WALL ROUGH IN 15d 12-08-17 A 01-22-18 A HP

ATR-130 DEMO INTERIOR SOG 5d 12-18-17 A 12-19-17 A K

ATR-320 OH SPRINKLER 5d 12-18-17 A 12-21-17 A BS

ATR-470 INFILL SUPPORTING SLAB - STEEL 5d 01-02-18 A 01-18-18 A L

ATR-150 ELEVATOR CMU SHAFT TO DECK 15d 01-08-18 A 01-26-18 A V-1

ATR-250 DEMO ROOF AT ELEVATOR 5d 01-29-18 A 02-01-18 A K

ATR-340 EXPANSION JOINT REWORK 3d 02-01-18 A 02-05-18 -4d

ATR-260 ELEVATOR CMU SHAFT ABOVE ROOF 5d 02-02-18 02-08-18 44d V-1

ATR-180 UNDERSLAB UTILITIES ELECTRICAL 20d 02-06-18 03-05-18 -6d Z

ATR-460 UNDERSLAB UTILITIES PLUMBING 20d 02-06-18 03-05-18 -6d HP

ATR-480 INFILL SUPPORTING SLAB - CONCRETE 3d 02-06-18 02-08-18 -4d PL

ATR-270 ELEVATOR ROOF DECK 2d 02-09-18 02-12-18 44d L

ATR-280 ROOFING AT ELEVATOR SHAFT 3d 02-13-18 02-15-18 44d W

ATR-190 REPLACE SOG FIRST HALF 15d 02-21-18 03-13-18 -7d T

ATR-200 SOG CURE 20d 03-14-18 04-10-18 14d T

ATR-1000 SIDING & TRIM 20d 03-14-18 04-10-18 26d O

ATR-330 FRAMING AT 1ST FLOOR 5d 03-14-18 03-20-18 11d O

ATR-210 PLANTERS & FEATURES 25d 03-16-18 04-19-18 14d T

ATR-290 REPLACE SOG SECOND HALF 15d 03-20-18 04-09-18 17d

ATR-360 GLASS & GLAZING 20d 03-21-18 04-17-18 16d PI

ATR-370 STANDING SEAM ROOF 20d 03-21-18 04-17-18 16d W

ATR-380 HANG DRYWALL 15d 03-27-18 04-16-18 7d O

ATR-220 OVERHEAD DECK PREP & INSULATION 5d 04-10-18 04-16-18 17d A

ATR-390 TAPE & FINISH 15d 04-10-18 04-30-18 7d O

ATR-1010 PAINT & SEALANTS FACADES 25d 04-11-18 05-15-18 26d A

ATR-300 OH MECHANICAL 10d 04-17-18 04-30-18 17d V

ATR-310 OH ELECTRICAL 10d 04-17-18 04-30-18 17d Z

ATR-400 MECHANICAL FIXTURES & FINISHES 20d 05-01-18 05-29-18 17d V

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

ALUM CLADDING & WINDOWS X LINE

EIFS

DUCTWORK DEMO

DEMO INTERIOR BLDG FACADE

FRAMING & SHEATHING

1ST FLOOR STOREFRONT REMOVAL

DEMO 3 SLABS @ ELEVATOR

CONSTRUCT ELEVATOR PIT & FOOTERS

MECHANICAL WALL ROUGH IN

PLUMBING WALL ROUGH IN

DEMO INTERIOR SOG

OH SPRINKLER

INFILL SUPPORTING SLAB - STEEL

ELEVATOR CMU SHAFT TO DECK

DEMO ROOF AT ELEVATOR

EXPANSION JOINT REWORK

ELEVATOR CMU SHAFT ABOVE ROOF

UNDERSLAB UTILITIES ELECTRICAL

UNDERSLAB UTILITIES PLUMBING

INFILL SUPPORTING SLAB - CONCRETE

ELEVATOR ROOF DECK

ROOFING AT ELEVATOR SHAFT

REPLACE SOG FIRST HALF

SOG CURE

SIDING & TRIM

FRAMING AT 1ST FLOOR

PLANTERS & FEATURES

REPLACE SOG SECOND HALF

GLASS & GLAZING

STANDING SEAM ROOF

HANG DRYWALL

OVERHEAD DECK PREP & INSULATION

TAPE & FINISH

PAINT & SEALANTS FACADES

OH MECHANICAL

OH ELECTRICAL

MECHANICAL FIXTURES & FINISHES

Print Date: 02-01-18Page 5 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 24: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

ATR-410 ELECTRICAL FIXTURES & FINISHES 20d 05-01-18 05-29-18 17d Z

ATR-420 PLUMBING FIXTURES & FINISHES 20d 05-01-18 05-29-18 17d HP

ATR-160 ELEVATOR CAB 25d 05-02-18 06-06-18 -9d ELEV

ATR-170 VERTICAL FINISHES 30d 05-23-18 07-05-18 -9d A

ATR-230 FLOOR FINISHES 40d 06-14-18 08-09-18 -9d C-1

ELEVATOR M&ELEVATOR M&A WINGELEVATOR M&A WINGELEVATOR M&A WINGELEVATOR M&A WINGELEVATOR M&A WINGELEVATOR M&A WINGELEVATORELEVATORELEVATORELEVATORELEVATORELEVATORELEVATOR

A&M 100 RENOVATE ELEVATOR N 25d 05-02-18 06-06-18 45d ELEV

A&M 110 RENOVATE ELEVATOR S 25d 06-07-18 07-12-18 45d ELEV

4TH FLOOR4TH FLOOR4TH FLOOR4TH FLOOR4TH FLOOR4TH FLOOR4TH FLOORA WINGA WINGA WINGA WINGA WINGA WINGA WING

4A-1000 ALL DEMO 10d 11-02-17 A 11-09-17 A K

4A-1270 WALL FRAMING 15d 11-15-17 A 12-29-17 A O

4A-1530 SANITARY STACKS 10d 11-21-17 A 12-05-17 A HP

4A-1350 IN WALL PLUMBING ROUGH IN 15d 11-22-17 A 01-23-18 A HP

4A-1280 IN WALL ELECTRICAL ROUGH IN 15d 11-22-17 A 12-15-17 A Z

4A-1310 OH ELECTRICAL ROUGH IN 15d 12-04-17 A 02-19-18 20d Z

ISSUE-30 AUTHORIZATION & MODIFY CORRIDOR WALL 10d 12-04-17 A 12-12-17 A O

4A-1290 FRAME CEILING AND SOFFITS 5d 12-06-17 A 02-12-18 20d O

4A-1320 OH PLUMBING 8d 12-07-17 A 12-15-17 A HP

4A-1300 OH MECHANICAL ROUGH IN BEFORE CLG 10d 12-26-17 A 02-01-18 A V

4A-1540 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 12-27-17 A 01-26-18 A O

4A-1330 SPRINKLER 5d 01-08-18 A 01-25-18 A BS

ISSUE-4A-157 FIRE RATING BOXES FOR SHOWER UNIT PIPING 5d 01-29-18 A 02-08-18 18d

4A-1340 SHOWER UNITS 5d 02-01-18 A 02-09-18 18d HP

4A-1560 POCKET DOOR FRAMES 5d 02-06-18 02-12-18 18d O

4A-1580 STOCK FLOOR 2d 02-13-18 02-14-18 18d

4A-1370 REMAINING DRYWALL 5d 02-19-18 02-23-18 16d O

4A-1390 FLOOR LEVELING 2d 02-26-18 02-27-18 16d T

4A-1550 TAPE & FINISH 5d 02-28-18 03-06-18 16d

4A-1380 PREP & PRIME PAINT WALLS 10d 03-07-18 03-20-18 16d A

4A-1360 CAULK & PAINT EXPOSED CEILING 10d 03-07-18 03-20-18 16d A

4A-1400 TOILET ROOM FLOORING 10d 03-21-18 04-03-18 16d C

4A-1410 CASEWORK / MILLWORK 15d 03-28-18 04-17-18 16d O

4A-1420 PLUMBING FIXTURES & FINISHES 10d 04-11-18 04-24-18 16d HP

4A-1430 ELECTRICAL FIXTURES & FINISHES 10d 04-11-18 04-24-18 16d Z

4A-1440 DOORS & HARDWARE 10d 04-11-18 04-24-18 16d F

4A-1450 FINISH PAINT 10d 04-18-18 05-01-18 16d A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

ELECTRICAL FIXTURES & FINISHES

PLUMBING FIXTURES & FINISHES

ELEVATOR CAB

VERTICAL FINISHES

FLOOR FINISHES

RENOVATE ELEVATOR N

RENOVATE ELEVATOR S

ALL DEMO

WALL FRAMING

SANITARY STACKS

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

OH ELECTRICAL ROUGH IN

AUTHORIZATION & MODIFY CORRIDOR WALL

FRAME CEILING AND SOFFITS

OH PLUMBING

OH MECHANICAL ROUGH IN BEFORE CLG

DRYWALL & TAPE BEFORE SHOWER UNITS

SPRINKLER

FIRE RATING BOXES FOR SHOWER UNIT PIPING

SHOWER UNITS

POCKET DOOR FRAMES

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

Print Date: 02-01-18Page 6 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 25: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

4A-1460 FLOORING & BASE 10d 04-25-18 05-08-18 16d C-1

4A-1470 PTAC / VTAC / GRILLES 10d 05-02-18 05-15-18 16d V

4A-1480 TOILET ROOM ACCESSORIES 5d 05-02-18 05-08-18 21d O

4A-1490 COORIDOR CEILING 5d 05-02-18 05-08-18 21d O

4A-1500 COORIDOR LIGHTING 5d 05-02-18 05-08-18 21d Z

4A-1510 COORIDOR SPECIALTIES 10d 05-02-18 05-15-18 16d O

4A-1520 COORIDOR FLOORING 5d 05-16-18 05-22-18 16d C-1

M WINGM WINGM WINGM WINGM WINGM WINGM WING

4M-1000 ALL DEMO 10d 11-06-17 A 11-13-17 A K

4M-1010 WALL FRAMING 15d 11-30-17 A 01-05-18 A O

4M-1270 SANITARY STACKS 10d 11-30-17 A 12-07-17 A HP

4M-1030 IN WALL PLUMBING ROUGH IN 10d 12-01-17 A 01-25-18 A HP

4M-1040 IN WALL ELECTRICAL ROUGH IN 15d 12-01-17 A 12-26-17 A Z

4M-1080 OH PLUMBING 8d 12-07-17 A 12-15-17 A HP

ISSUE-40 MODIFY CORRIDOR WALL 2d 12-15-17 A 12-18-17 A O

4M-1060 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 10d 12-26-17 A 02-02-18 28d V

4M-1090 SPRINKLER 3d 01-12-18 A 02-02-18 17d BS

4M-1280 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 01-26-18 A 02-05-18 20d O

4M-1020 SHOWER UNITS 5d 02-06-18 02-12-18 22d HP

4M-1300 POCKET DOOR FRAME 3d 02-09-18 02-13-18 22d O

4M-1050 FRAME CEILING AND SOFFITS 3d 02-13-18 02-15-18 22d O

4M-1070 OH ELECTRICAL ROUGH IN 3d 02-14-18 02-16-18 26d Z

4M-1310 STOCK FLOOR 2d 02-14-18 02-15-18 22d

4M-1110 REMAINING DRYWALL 5d 02-19-18 02-23-18 21d O

4M-1130 FLOOR LEVELING 2d 02-26-18 02-27-18 21d T

4M-1290 TAPE & FINISH 5d 02-28-18 03-06-18 21d

4M-1120 PREP & PRIME PAINT WALLS 10d 03-07-18 03-20-18 21d A

4M-1100 CAULK & PAINT EXPOSED CEILING 10d 03-07-18 03-20-18 21d A

4M-1140 TOILET ROOM FLOORING 10d 03-21-18 04-03-18 21d C

4M-1150 CASEWORK / MILLWORK 15d 03-28-18 04-17-18 21d O

4M-1160 PLUMBING FIXTURES & FINISHES 10d 04-11-18 04-24-18 21d HP

4M-1170 ELECTRICAL FIXTURES & FINISHES 10d 04-11-18 04-24-18 21d Z

4M-1180 DOORS & HARDWARE 10d 04-11-18 04-24-18 21d F

4M-1190 FINISH PAINT 10d 04-18-18 05-01-18 21d A

4M-1200 FLOORING & BASE 10d 04-25-18 05-08-18 21d C-1

4M-1210 PTAC / VTAC / GRILLES 10d 05-02-18 05-15-18 21d V

4M-1220 TOILET ROOM ACCESSORIES 5d 05-02-18 05-08-18 26d O

4M-1230 COORIDOR & COMMON AREA CEILING 5d 05-02-18 05-08-18 26d O

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

COORIDOR FLOORING

ALL DEMO

WALL FRAMING

SANITARY STACKS

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

OH PLUMBING

MODIFY CORRIDOR WALL

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

DRYWALL & TAPE BEFORE SHOWER UNITS

SHOWER UNITS

POCKET DOOR FRAME

FRAME CEILING AND SOFFITS

OH ELECTRICAL ROUGH IN

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR & COMMON AREA CEILING

Print Date: 02-01-18Page 7 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 26: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

4M-1240 COORIDOR & COMMON AREA LIGHTING 5d 05-02-18 05-08-18 26d Z

4M-1250 COORIDOR & COMMON AREA SPECIALTIES 10d 05-02-18 05-15-18 21d O

4M-1260 COORIDOR & COMMON AREA FLOORING 5d 05-23-18 05-30-18 16d C-1

3RD FLOOR3RD FLOOR3RD FLOOR3RD FLOOR3RD FLOOR3RD FLOOR3RD FLOORA WINGA WINGA WINGA WINGA WINGA WINGA WING

3A-1010 ALL DEMO 6d 11-15-17 A 12-01-17 A K

3A-1280 SANITARY STACKS 10d 11-21-17 A 12-05-17 A HP

3A-1090 OH PLUMBING 8d 12-01-17 A 12-07-17 A HP

3A-1020 WALL FRAMING 15d 12-06-17 A 01-05-18 A O

3A-1040 IN WALL PLUMBING ROUGH IN 10d 12-12-17 A 01-23-18 A HP

3A-1050 IN WALL ELECTRICAL ROUGH IN 15d 12-12-17 A 01-24-18 A Z

3A-1060 FRAME CEILING AND SOFFITS 3d 12-13-17 A 02-09-18 6d O

AL62200 MODIFY CORRIDOR WALL 2d 12-19-17 A 12-20-17 A O

3A-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 10d 01-08-18 A 02-06-18 6d V

3A-1100 SPRINKLER 3d 01-16-18 A 02-02-18 17d BS

3A-1290 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 01-24-18 A 01-31-18 A O

ISSUE 3A1000 FIRE RATING BOXES FOR SHOWER UNIT PIPING 5d 01-29-18 A 02-08-18 3d

3A-1030 SHOWER UNITS 5d 02-05-18 02-09-18 3d HP

3A-1080 OH ELECTRICAL ROUGH IN 3d 02-08-18 02-12-18 10d Z

3A-1310 POCKET DOOR FRAMES 3d 02-08-18 02-12-18 3d O

3A-1320 STOCK FLOOR 2d 02-13-18 02-14-18 3d

3A-1120 REMAINING DRYWALL 5d 02-19-18 02-23-18 1d O

3A-1140 FLOOR LEVELING 2d 02-26-18 02-27-18 1d T

3A-1300 TAPE & FINISH 5d 02-28-18 03-06-18 1d

3A-1130 PREP & PRIME PAINT WALLS 10d 03-07-18 03-20-18 1d A

3A-1110 CAULK & PAINT EXPOSED CEILING 10d 03-07-18 03-20-18 1d A

3A-1150 TOILET ROOM FLOORING 10d 03-21-18 04-03-18 1d C

3A-1160 CASEWORK / MILLWORK 15d 03-28-18 04-17-18 1d O

3A-1170 PLUMBING FIXTURES & FINISHES 10d 04-11-18 04-24-18 1d HP

3A-1180 ELECTRICAL FIXTURES & FINISHES 10d 04-11-18 04-24-18 16d Z

3A-1190 DOORS & HARDWARE 10d 04-11-18 04-24-18 16d F

3A-1200 FINISH PAINT 10d 04-18-18 05-01-18 16d A

3A-1210 FLOORING & BASE 10d 04-25-18 05-08-18 1d C-1

3A-1220 PTAC / VTAC / GRILLES 10d 05-02-18 05-15-18 16d V

3A-1230 TOILET ROOM ACCESSORIES 5d 05-02-18 05-08-18 21d O

3A-1240 COORIDOR CEILING 5d 05-02-18 05-08-18 21d O

3A-1250 COORIDOR LIGHTING 5d 05-02-18 05-08-18 21d Z

3A-1260 COORIDOR SPECIALTIES 10d 05-02-18 05-15-18 16d O

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

COORIDOR & COMMON AREA LIGHTING

COORIDOR & COMMON AREA SPECIALTIES

COORIDOR & COMMON AREA FLOORING

ALL DEMO

SANITARY STACKS

OH PLUMBING

WALL FRAMING

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

FRAME CEILING AND SOFFITS

MODIFY CORRIDOR WALL

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

DRYWALL & TAPE BEFORE SHOWER UNITS

FIRE RATING BOXES FOR SHOWER UNIT PIPING

SHOWER UNITS

OH ELECTRICAL ROUGH IN

POCKET DOOR FRAMES

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

Print Date: 02-01-18Page 8 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 27: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

3A-1270 COORIDOR FLOORING 5d 05-16-18 05-22-18 16d C-1

M WINGM WINGM WINGM WINGM WINGM WINGM WING

3M-1010 ALL DEMO 4d 11-15-17 A 11-22-17 A K

3M-1280 SANITARY STACKS 10d 11-29-17 A 12-07-17 A HP

3M-1090 OH PLUMBING 5d 12-07-17 A 12-13-17 A HP

3M-1020 WALL FRAMING 10d 12-12-17 A 12-22-17 A O

AL62210 MODIFY CORRIDOR WALL 2d 12-21-17 A 12-22-17 A O

3M-1040 IN WALL PLUMBING ROUGH IN 10d 12-27-17 A 02-02-18 22d HP

3M-1050 IN WALL ELECTRICAL ROUGH IN 15d 12-27-17 A 01-05-18 A Z

3M-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 10d 01-02-18 A 02-07-18 2d V

3M-1100 SPRINKLER 3d 01-17-18 A 01-26-18 A BS

3M-1290 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 01-29-18 A 02-02-18 14d O

ISSUE 3A1010 FIRE RATING BOXES FOR SHOWER UNIT PIPING 5d 01-29-18 A 02-08-18 12d

3M-1030 SHOWER UNITS 5d 02-06-18 02-12-18 12d HP

3M-1310 POCKET DOOR FRAME 3d 02-09-18 02-13-18 12d O

3M-1060 FRAME CEILING AND SOFFITS 3d 02-12-18 02-14-18 13d O

3M-1080 OH ELECTRICAL ROUGH IN 3d 02-13-18 02-15-18 17d Z

3M-1320 STOCK FLOORS 2d 02-14-18 02-15-18 12d

3M-1120 REMAINING DRYWALL 5d 02-20-18 02-26-18 10d O

3M-1140 FLOOR LEVELING 2d 02-27-18 02-28-18 10d T

3M-1300 TAPE & FINISH 5d 03-01-18 03-07-18 10d

3M-1130 PREP & PRIME PAINT WALLS 10d 03-08-18 03-21-18 10d A

3M-1110 CAULK & PAINT EXPOSED CEILING 10d 03-08-18 03-21-18 10d A

3M-1150 TOILET ROOM FLOORING 10d 03-22-18 04-04-18 10d C

3M-1160 CASEWORK / MILLWORK 15d 03-29-18 04-18-18 10d O

3M-1170 PLUMBING FIXTURES & FINISHES 10d 04-12-18 04-25-18 10d HP

3M-1180 ELECTRICAL FIXTURES & FINISHES 10d 04-12-18 04-25-18 20d Z

3M-1190 DOORS & HARDWARE 10d 04-12-18 04-25-18 20d F

3M-1200 FINISH PAINT 10d 04-19-18 05-02-18 20d A

3M-1230 TOILET ROOM ACCESSORIES 5d 05-03-18 05-09-18 25d O

3M-1240 COORIDOR CEILING 5d 05-03-18 05-09-18 25d O

3M-1250 COORIDOR LIGHTING 5d 05-03-18 05-09-18 25d Z

3M-1260 COORIDOR SPECIALTIES 10d 05-03-18 05-16-18 20d O

3M-1210 FLOORING & BASE 10d 05-09-18 05-22-18 1d C-1

3M-1220 PTAC / VTAC / GRILLES 10d 05-16-18 05-30-18 11d V

3M-1270 COORIDOR FLOORING 5d 05-31-18 06-06-18 11d C-1

2ND FLOOR2ND FLOOR2ND FLOOR2ND FLOOR2ND FLOOR2ND FLOOR2ND FLOORA WINGA WINGA WINGA WINGA WINGA WINGA WING

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

COORIDOR FLOORING

ALL DEMO

SANITARY STACKS

OH PLUMBING

WALL FRAMING

MODIFY CORRIDOR WALL

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

DRYWALL & TAPE BEFORE SHOWER UNITS

FIRE RATING BOXES FOR SHOWER UNIT PIPING

SHOWER UNITS

POCKET DOOR FRAME

FRAME CEILING AND SOFFITS

OH ELECTRICAL ROUGH IN

STOCK FLOORS

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

FLOORING & BASE

PTAC / VTAC / GRILLES

COORIDOR FLOORING

Print Date: 02-01-18Page 9 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 28: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

2A-1280 SANITARY STACKS 10d 11-21-17 A 12-05-17 A HP

2A-1010 ALL DEMO 6d 11-23-17 A 12-05-17 A K

2A-1090 OH PLUMBING 5d 12-18-17 A 12-22-17 A HP

2A-1020 WALL FRAMING 10d 12-20-17 A 12-29-17 A O

2A-1040 IN WALL PLUMBING ROUGH IN 10d 12-28-17 A 01-26-18 A HP

2A-1050 IN WALL ELECTRICAL ROUGH IN 15d 12-28-17 A 01-04-18 A Z

2A-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 10d 01-29-18 A 02-12-18 22d V

2A-1100 SPRINKLER 3d 01-29-18 A 02-05-18 32d BS

2A-1290 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 01-31-18 A 02-07-18 20d O

2A-1030 SHOWER UNITS 5d 02-08-18 02-14-18 20d HP

2A-1060 FRAME CEILING AND SOFFITS 3d 02-13-18 02-15-18 22d O

2A-1310 POCKET DOOR FRAME 3d 02-13-18 02-15-18 20d O

2A-1080 OH ELECTRICAL ROUGH IN 3d 02-14-18 02-16-18 26d Z

2A-1320 STOCK FLOOR 2d 02-16-18 02-19-18 20d

2A-1120 REMAINING DRYWALL 5d 02-20-18 02-26-18 20d O

2A-1140 FLOOR LEVELING 2d 02-27-18 02-28-18 20d T

2A-1300 TAPE & FINISH 5d 03-01-18 03-07-18 20d

2A-1130 PREP & PRIME PAINT WALLS 10d 03-08-18 03-21-18 20d A

2A-1110 CAULK & PAINT EXPOSED CEILING 10d 03-08-18 03-21-18 20d A

2A-1150 TOILET ROOM FLOORING 10d 03-22-18 04-04-18 20d C

2A-1160 CASEWORK / MILLWORK 15d 03-29-18 04-18-18 20d O

2A-1170 PLUMBING FIXTURES & FINISHES 10d 04-12-18 04-25-18 20d HP

2A-1180 ELECTRICAL FIXTURES & FINISHES 10d 04-12-18 04-25-18 25d Z

2A-1190 DOORS & HARDWARE 10d 04-12-18 04-25-18 25d F

2A-1200 FINISH PAINT 10d 04-19-18 05-02-18 25d A

2A-1210 FLOORING & BASE 10d 04-26-18 05-09-18 20d C-1

2A-1220 PTAC / VTAC / GRILLES 10d 05-03-18 05-16-18 25d V

2A-1230 TOILET ROOM ACCESSORIES 5d 05-03-18 05-09-18 30d O

2A-1240 COORIDOR CEILING 5d 05-03-18 05-09-18 30d O

2A-1250 COORIDOR LIGHTING 5d 05-03-18 05-09-18 30d Z

2A-1260 COORIDOR SPECIALTIES 10d 05-03-18 05-16-18 25d O

2A-1270 COORIDOR FLOORING 5d 05-31-18 06-06-18 16d C-1

M WINGM WINGM WINGM WINGM WINGM WINGM WING

2M-1280 SANITARY STACKS 10d 11-29-17 A 12-04-17 A HP

2M-1010 ALL DEMO 3d 11-30-17 A 12-04-17 A K

2M-1090 OH PLUMBING 5d 12-26-17 A 01-02-18 A HP

2M-1020 WALL FRAMING 10d 01-02-18 A 01-10-18 A O

2M-1040 IN WALL PLUMBING ROUGH IN 10d 01-05-18 A 01-30-18 A HP

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

SANITARY STACKS

ALL DEMO

OH PLUMBING

WALL FRAMING

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

DRYWALL & TAPE BEFORE SHOWER UNITS

SHOWER UNITS

FRAME CEILING AND SOFFITS

POCKET DOOR FRAME

OH ELECTRICAL ROUGH IN

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

COORIDOR FLOORING

SANITARY STACKS

ALL DEMO

OH PLUMBING

WALL FRAMING

IN WALL PLUMBING ROUGH IN

Print Date: 02-01-18Page 10 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 29: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

2M-1050 IN WALL ELECTRICAL ROUGH IN 15d 01-05-18 A 01-24-18 A Z

2M-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 8d 01-31-18 A 02-12-18 30d V

2M-1290 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 02-01-18 A 02-08-18 29d O

2M-1100 SPRINKLER 3d 02-06-18 02-08-18 42d BS

2M-1060 FRAME CEILING AND SOFFITS 5d 02-13-18 02-19-18 30d O

2M-1080 OH ELECTRICAL ROUGH IN 3d 02-14-18 02-16-18 36d Z

2M-1030 SHOWER UNITS 5d 02-28-18 03-06-18 16d HP

2M-1310 POCKET DOOR FRAME 3d 03-05-18 03-07-18 16d O

2M-1320 STOCK FLOOR 2d 03-08-18 03-09-18 16d

2M-1120 REMAINING DRYWALL 5d 03-12-18 03-16-18 16d O

2M-1140 FLOOR LEVELING 2d 03-19-18 03-20-18 16d T

2M-1300 TAPE & FINISH 5d 03-21-18 03-27-18 16d

2M-1130 PREP & PRIME PAINT WALLS 10d 03-28-18 04-10-18 16d A

2M-1110 CAULK & PAINT EXPOSED CEILING 10d 03-28-18 04-10-18 16d A

2M-1150 TOILET ROOM FLOORING 10d 04-11-18 04-24-18 16d C

2M-1160 CASEWORK / MILLWORK 15d 04-18-18 05-08-18 16d O

2M-1170 PLUMBING FIXTURES & FINISHES 10d 05-02-18 05-15-18 16d HP

2M-1180 ELECTRICAL FIXTURES & FINISHES 10d 05-02-18 05-15-18 16d Z

2M-1190 DOORS & HARDWARE 10d 05-02-18 05-15-18 16d F

2M-1200 FINISH PAINT 10d 05-09-18 05-22-18 16d A

2M-1210 FLOORING & BASE 10d 05-16-18 05-30-18 16d C-1

2M-1220 PTAC / VTAC / GRILLES 10d 05-23-18 06-06-18 16d V

2M-1230 TOILET ROOM ACCESSORIES 5d 05-23-18 05-30-18 21d O

2M-1240 COORIDOR CEILING 5d 05-23-18 05-30-18 21d O

2M-1250 COORIDOR LIGHTING 5d 05-23-18 05-30-18 21d Z

2M-1260 COORIDOR SPECIALTIES 10d 05-23-18 06-06-18 16d O

2M-1270 COORIDOR FLOORING 5d 06-07-18 06-13-18 16d C-1

1ST FLOOR1ST FLOOR1ST FLOOR1ST FLOOR1ST FLOOR1ST FLOOR1ST FLOORA WINGA WINGA WINGA WINGA WINGA WINGA WING

1A-1310 ABATEMENT 3d 11-01-17 A 11-17-17 A PER

1A-1010 REMAINING DEMO 10d 11-06-17 A 11-15-17 A K

1A-1300 SELECT DEMO FOR UNDERSLAB 5d 11-06-17 A 11-15-17 A K

1A-1280 UNDERSLAB PLUMBING 10d 11-08-17 A 11-28-17 A HP

1A-1290 SANITARY STACKS 10d 12-04-17 A 12-08-17 A HP

1A-1090 OH PLUMBING 5d 12-26-17 A 01-25-18 A HP

1A-1340 INFILL SLAB AT UNDERSLAB AREAS 6d 01-11-18 A 01-30-18 A

1A-1020 WALL FRAMING 15d 01-26-18 A 02-07-18 5d O

1A-1040 IN WALL PLUMBING ROUGH IN 15d 01-31-18 A 02-12-18 12d HP

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

IN WALL ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

DRYWALL & TAPE BEFORE SHOWER UNITS

SPRINKLER

FRAME CEILING AND SOFFITS

OH ELECTRICAL ROUGH IN

SHOWER UNITS

POCKET DOOR FRAME

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

COORIDOR FLOORING

ABATEMENT

REMAINING DEMO

SELECT DEMO FOR UNDERSLAB

UNDERSLAB PLUMBING

SANITARY STACKS

OH PLUMBING

INFILL SLAB AT UNDERSLAB AREAS

WALL FRAMING

IN WALL PLUMBING ROUGH IN

Print Date: 02-01-18Page 11 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 30: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

1A-1050 IN WALL ELECTRICAL ROUGH IN 10d 01-31-18 A 02-12-18 20d Z

1A-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 8d 02-05-18* 02-14-18 0d V

1A-1100 SPRINKLER 3d 02-06-18 02-08-18 32d BS

1A-1320 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 02-13-18 02-20-18 12d O

1A-1060 FRAME CEILING AND SOFFITS 3d 02-15-18 02-19-18 20d O

1A-1080 OH ELECTRICAL ROUGH IN 3d 02-16-18 02-20-18 24d Z

1A-1030 SHOWER UNITS 4d 03-14-18 03-19-18 -3d HP

1A-1360 POCKET DOOR FRAME 3d 03-16-18 03-20-18 -3d O

1A-1330 STOCK FLOOR 2d 03-21-18 03-22-18 -3d

1A-1120 REMAINING DRYWALL 5d 03-23-18 03-29-18 -3d O

1A-1140 FLOOR LEVELING 2d 03-30-18 04-02-18 -3d T

1A-1350 TAPE & FINISH 5d 04-03-18 04-09-18 -3d

1A-1130 PREP & PRIME PAINT WALLS 10d 04-10-18 04-23-18 -3d A

1A-1110 CAULK & PAINT EXPOSED CEILING 5d 04-10-18 04-16-18 -3d A

1A-1150 TOILET ROOM FLOORING 10d 04-17-18 04-30-18 -3d C

1A-1160 CASEWORK / MILLWORK 15d 04-24-18 05-14-18 -3d O

1A-1170 PLUMBING FIXTURES & FINISHES 10d 05-08-18 05-21-18 2d HP

1A-1180 ELECTRICAL FIXTURES & FINISHES 10d 05-08-18 05-21-18 7d Z

1A-1190 DOORS & HARDWARE 10d 05-08-18 05-21-18 7d F

1A-1200 FINISH PAINT 10d 05-15-18 05-29-18 7d A

1A-1210 FLOORING & BASE 10d 05-23-18 06-06-18 1d C-1

1A-1230 TOILET ROOM ACCESSORIES 5d 05-30-18 06-05-18 12d O

1A-1240 COORIDOR CEILING 5d 05-30-18 06-05-18 12d O

1A-1250 COORIDOR LIGHTING 5d 05-30-18 06-05-18 12d Z

1A-1260 COORIDOR SPECIALTIES 10d 05-30-18 06-12-18 7d O

1A-1220 PTAC / VTAC / GRILLES 10d 05-31-18 06-13-18 6d V

1A-1270 COORIDOR FLOORING 5d 06-14-18 06-20-18 6d C-1

M WINGM WINGM WINGM WINGM WINGM WINGM WING

1M-1010 REMAINING DEMO 10d 11-06-17 A 11-15-17 A K

1M-1300 SELECTIVE DEMO FOR UNDERSLAB 5d 11-06-17 A 11-15-17 A K

1M-1280 UNDERSLAB PLUMBING 10d 11-21-17 A 12-15-17 A HP

1M-1290 SANITARY STACKS 10d 11-29-17 A 12-04-17 A HP

1M-1090 OH PLUMBING 5d 01-26-18 A 02-02-18 46d HP

1M-1070 OH MECHANICAL ROUGH IN BEFORE CLG FRAMING 8d 02-06-18 02-15-18 44d V

1M-1100 SPRINKLER 3d 02-09-18 02-13-18 39d BS

1M-1020 WALL FRAMING 15d 02-26-18 03-16-18 -7d O

1M-1040 IN WALL PLUMBING ROUGH IN 15d 03-05-18 03-23-18 -7d HP

1M-1050 IN WALL ELECTRICAL ROUGH IN 15d 03-05-18 03-23-18 6d Z

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

IN WALL ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

DRYWALL & TAPE BEFORE SHOWER UNITS

FRAME CEILING AND SOFFITS

OH ELECTRICAL ROUGH IN

SHOWER UNITS

POCKET DOOR FRAME

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

PTAC / VTAC / GRILLES

COORIDOR FLOORING

REMAINING DEMO

SELECTIVE DEMO FOR UNDERSLAB

UNDERSLAB PLUMBING

SANITARY STACKS

OH PLUMBING

OH MECHANICAL ROUGH IN BEFORE CLG FRAMING

SPRINKLER

WALL FRAMING

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

Print Date: 02-01-18Page 12 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 31: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

1M-1060 FRAME CEILING AND SOFFITS 3d 03-14-18 03-16-18 11d O

1M-1080 OH ELECTRICAL ROUGH IN 3d 03-15-18 03-19-18 15d Z

1M-1331 DRYWALL & TAPE BEFORE SHOWER UNITS 6d 03-26-18 04-02-18 -7d O

1M-1030 SHOWER UNITS 4d 04-03-18 04-06-18 -7d HP

1M-1320 POCKET DOOR FRAME 3d 04-05-18 04-09-18 -7d O

1M-1330 STOCK FLOOR 2d 04-10-18 04-11-18 -7d

1M-1120 REMAINING DRYWALL 5d 04-12-18 04-18-18 -7d O

1M-1140 FLOOR LEVELING 2d 04-19-18 04-20-18 -7d T

1M-1310 TAPE & FINISH 5d 04-23-18 04-27-18 -7d

1M-1130 PREP & PRIME PAINT WALLS 10d 04-30-18 05-11-18 -7d A

1M-1110 CAULK & PAINT EXPOSED CEILING 10d 04-30-18 05-11-18 -7d A

1M-1150 TOILET ROOM FLOORING 10d 05-14-18 05-25-18 -7d C

1M-1160 CASEWORK / MILLWORK 15d 05-21-18 06-11-18 -7d O

1M-1170 PLUMBING FIXTURES & FINISHES 10d 06-05-18 06-18-18 -7d HP

1M-1180 ELECTRICAL FIXTURES & FINISHES 10d 06-05-18 06-18-18 -7d Z

1M-1190 DOORS & HARDWARE 10d 06-05-18 06-18-18 -7d F

1M-1200 FINISH PAINT 10d 06-12-18 06-25-18 -7d A

1M-1210 FLOORING & BASE 10d 06-19-18 07-02-18 -7d C-1

1M-1220 PTAC / VTAC / GRILLES 10d 06-26-18 07-10-18 -7d V

1M-1230 TOILET ROOM ACCESSORIES 5d 06-26-18 07-02-18 -2d O

1M-1240 COORIDOR CEILING 5d 06-26-18 07-02-18 -2d O

1M-1250 COORIDOR LIGHTING 5d 06-26-18 07-02-18 -2d Z

1M-1260 COORIDOR SPECIALTIES 10d 06-26-18 07-10-18 -7d O

1M-1270 COORIDOR FLOORING 5d 07-11-18 07-17-18 -7d C-1

SINGLE STORSINGLE STORYSINGLE STORYSINGLE STORYSINGLE STORYSINGLE STORYSINGLE STORY

SS-100 STRUCTURAL DISCONNECT & DEMO 3d 11-01-17 A 11-02-17 A K

EXT-120 PLUMBING DISCONNECT & DEMO 2d 11-01-17 A 11-02-17 A HP

EXT-160 ELECTRICAL DISCONNECT & DEMO 2d 11-01-17 A 11-02-17 A Z

EXT-350 MECHANICAL DISCONNECT & DEMO 2d 11-01-17 A 11-02-17 A V

SS-150 ABATEMENT 5d 11-06-17 A 11-10-17 A PER

EXT-110 DEMO BLDG & WALLS 5d 11-13-17 A 11-24-17 A K

EXT-170 CONCRETE FOOTERS ON "13" 5d 12-13-17 A 12-19-17 A T

EASTEASTEASTEASTEASTEASTEAST

SS-130 EAST HALF PATCH / REPAIR SOG 5d 01-25-18 A 01-31-18 A

SSE-180 LAYOUT 3d 02-05-18* 02-07-18 -7d

SSE-100 WALL FRAMING 10d 02-08-18 02-21-18 -7d O

SSE-110 OH PLUMBING ROUGH IN 13d 02-08-18 02-26-18 31d HP

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

FRAME CEILING AND SOFFITS

OH ELECTRICAL ROUGH IN

DRYWALL & TAPE BEFORE SHOWER UNITS

SHOWER UNITS

POCKET DOOR FRAME

STOCK FLOOR

REMAINING DRYWALL

FLOOR LEVELING

TAPE & FINISH

PREP & PRIME PAINT WALLS

CAULK & PAINT EXPOSED CEILING

TOILET ROOM FLOORING

CASEWORK / MILLWORK

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

DOORS & HARDWARE

FINISH PAINT

FLOORING & BASE

PTAC / VTAC / GRILLES

TOILET ROOM ACCESSORIES

COORIDOR CEILING

COORIDOR LIGHTING

COORIDOR SPECIALTIES

COORIDOR FLOORING

STRUCTURAL DISCONNECT & DEMO

PLUMBING DISCONNECT & DEMO

ELECTRICAL DISCONNECT & DEMO

MECHANICAL DISCONNECT & DEMO

ABATEMENT

DEMO BLDG & WALLS

CONCRETE FOOTERS ON "13"

EAST HALF PATCH / REPAIR SOG

LAYOUT

WALL FRAMING

OH PLUMBING ROUGH IN

Print Date: 02-01-18Page 13 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 32: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

SSE-120 OH ELECTRICAL ROUGH IN 13d 02-08-18 02-26-18 31d Z

SSE-130 OH MECHANICAL ROUGH IN 13d 02-08-18 02-26-18 -7d V

SSE-140 SPRINKLER ROUGH IN 13d 02-08-18 02-26-18 31d BS

SSE-150 IN WALL PLUMBING ROUGH IN 10d 02-22-18 03-07-18 -7d HP

SSE-160 IN WALL ELECTRICAL ROUGH IN 10d 02-22-18 03-07-18 -7d Z

SSE-170 IN WALL MECHANICAL ROUGH IN 10d 02-22-18 03-07-18 -7d V

SSE-190 BOARD & SAND 13d 03-08-18 03-26-18 -7d O

SSE-200 CERAMIC / QUARRY TILE 10d 03-27-18 04-09-18 6d C

SSE-210 CEILING GRID 5d 03-27-18 04-02-18 11d O

SSE-220 PREP & PRIME PAINT 10d 04-10-18 04-23-18 6d A

SSE-240 CASEWORK & MILLWORK 10d 04-24-18 05-07-18 6d O

SSE-250 ELECTRICAL FIXTURES & FINISHES 8d 05-08-18 05-17-18 8d Z

SSE-260 MECHANICAL FIXTURES & FINISHES 8d 05-08-18 05-17-18 8d V

SSE-270 PLUMBING FIXTURES & FINISHES 10d 05-08-18 05-21-18 6d HP

SSE-280 FINISH PAINT 8d 05-22-18 06-01-18 6d A

SSE-290 FLOORING & BASE 8d 06-04-18 06-13-18 6d C-1

SSE-300 ACT TILE 5d 06-14-18 06-20-18 11d O

SSE-310 DOORS & HARDWARE 5d 06-14-18 06-20-18 11d F

SSE-320 SPECIALTIES 10d 06-14-18 06-27-18 6d O

CENTRAL & WCENTRAL & WESTCENTRAL & WESTCENTRAL & WESTCENTRAL & WESTCENTRAL & WESTCENTRAL & WEST

SS-110 UNDERSLAB UTILITIES ELECTRICAL 15d 11-27-17 A 02-21-18 -9d Z

SS-390 UNDERSLAB UTILITIES PLUMBING 15d 11-27-17 A 02-21-18 -9d HP

EXT-370 DEMO SLAB ON GRADE DUE TO REWORK 3d 02-12-18 02-14-18 -9d

SS-120 REMAINING PATCH/ REPLACE SOG 5d 02-22-18 02-28-18 -9d T

SS-140 WALL FRAMING 10d 03-01-18 03-14-18 -9d O

SS-290 OH PLUMBING ROUGH IN 12d 03-01-18 03-16-18 -6d HP

SS-300 OH ELECTRICAL ROUGH IN 12d 03-01-18 03-16-18 -6d Z

SS-310 OH MECHANICAL ROUGH IN 12d 03-01-18 03-16-18 -6d V

SS-320 SPRINKLER ROUGH IN 12d 03-01-18 03-16-18 16d BS

SS-260 IN WALL PLUMBING ROUGH IN 10d 03-15-18 03-28-18 -9d HP

SS-270 IN WALL ELECTRICAL ROUGH IN 10d 03-15-18 03-28-18 -9d Z

SS-280 IN WALL MECHANICAL ROUGH IN 10d 03-15-18 03-28-18 -9d V

SS-380 BUILD MARKETING SUITES (2) 15d 03-15-18 04-04-18* 19d AMH

SS-170 BOARD & SAND 12d 03-29-18 04-13-18 -9d O

SS-190 CERAMIC / QUARRY TILE 10d 04-16-18 04-27-18 -9d C

SS-330 CEILING GRID 5d 04-16-18 04-20-18 -4d O

SS-180 PREP & PRIME PAINT 10d 04-30-18 05-11-18 -9d A

SS-250 KITCHEN EQUIPMENT 25d 04-30-18 06-04-18 -6d OWN

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

OH ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN

SPRINKLER ROUGH IN

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

IN WALL MECHANICAL ROUGH IN

BOARD & SAND

CERAMIC / QUARRY TILE

CEILING GRID

PREP & PRIME PAINT

CASEWORK & MILLWORK

ELECTRICAL FIXTURES & FINISHES

MECHANICAL FIXTURES & FINISHES

PLUMBING FIXTURES & FINISHES

FINISH PAINT

FLOORING & BASE

ACT TILE

DOORS & HARDWARE

SPECIALTIES

UNDERSLAB UTILITIES ELECTRICAL

UNDERSLAB UTILITIES PLUMBING

DEMO SLAB ON GRADE DUE TO REWORK

REMAINING PATCH/ REPLACE SOG

WALL FRAMING

OH PLUMBING ROUGH IN

OH ELECTRICAL ROUGH IN

OH MECHANICAL ROUGH IN

SPRINKLER ROUGH IN

IN WALL PLUMBING ROUGH IN

IN WALL ELECTRICAL ROUGH IN

IN WALL MECHANICAL ROUGH IN

BUILD MARKETING SUITES (2)

BOARD & SAND

CERAMIC / QUARRY TILE

CEILING GRID

PREP & PRIME PAINT

KITCHEN EQUIPMENT

Print Date: 02-01-18Page 14 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 33: Tapestry Senior Living

Activity ID Activity Name OriginalDuration

Start Finish Total Float RESPONS

SS-200 CASEWORK & MILLWORK 8d 05-14-18 05-23-18 -9d O

SS-240 MECHANICAL FIXTURES & FINISHES 15d 05-22-18 06-12-18 -7d V

SS-360 PLUMBING FIXTURES & FINISHES 20d 05-22-18 06-19-18 -9d HP

SS-220 ELECTRICAL FIXTURES & FINISHES 8d 05-31-18 06-11-18 -6d Z

SS-210 FINISH PAINT 8d 06-15-18 06-26-18 -9d A

SS-230 FLOORING & BASE 8d 06-27-18 07-09-18 -9d C-1

SS-340 ACT TILE 5d 07-10-18 07-16-18 -6d O

SS-350 DOORS & HARDWARE 5d 07-10-18 07-16-18 -6d F

SS-370 SPECIALTIES 8d 07-10-18 07-19-18 -9d O

CONSTRUCCONSTRUCTION COMPLETIONCONSTRUCTION COMPLETIONCONSTRUCTION COMPLETIONCONSTRUCTION COMPLETIONCONSTRUCTION COMPLETIONCONSTRUCTION COMPLETION

PC-110 CONTROLS & BALANCING 30d 07-20-18 08-30-18 -9d V

PC-100 ELEVATOR INSPECTIONS 5d 08-10-18 08-16-18 1d ELEV

PC-120 FINAL CLEAN 10d 08-17-18 08-30-18 -4d AMH

PC-130 INSPECTIONS 5d 08-29-18 09-05-18 -7d AMH

PC-140 FINAL PUNCHLIST 10d 08-31-18 09-14-18 -9d AMH

PC-150 CERTIFICATE OF OCCUPANCY 5d 09-06-18 09-12-18 -7d AMH

PC-170 SUBSTANTIAL COMPLETION (8/31/18) 0d 09-14-18* -9d AMH

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May2018 2019

CASEWORK & MILLWORK

MECHANICAL FIXTURES & FINISHES

PLUMBING FIXTURES & FINISHES

ELECTRICAL FIXTURES & FINISHES

FINISH PAINT

FLOORING & BASE

ACT TILE

DOORS & HARDWARE

SPECIALTIES

CONTROLS & BALANCING

ELEVATOR INSPECTIONS

FINAL CLEAN

INSPECTIONS

FINAL PUNCHLIST

CERTIFICATE OF OCCUPANCY

SUBSTANTIAL COMPLETION (8/31/18)

Print Date: 02-01-18Page 15 of 15

TAPESTRY WICKLIFFEPROGRESS UPDATE SCHEDULE 02-02-18

Page 34: Tapestry Senior Living

EXHIBIT B

Page 35: Tapestry Senior Living
Page 36: Tapestry Senior Living
Page 37: Tapestry Senior Living
Page 38: Tapestry Senior Living
Page 39: Tapestry Senior Living
Page 40: Tapestry Senior Living

THE ALBERT M. HIGLEY CO.TAPESTRY SENIOR LIVING - WICKLIFFESCHEDULE OF VALUESAS OF JANUARY 31, 2018

Line

ItemDescription Retention

Original Schedule

of Values Pay App # SOV Adjustments

Change Order

#1Contract to Date

-$ 930 Preconstruction Labor 24,132.00$ 24,132.00$ 24,132.00$

931 Preconstruction Material 500.00$ 500.00$ 500.00$

-$ -$

200 Demolition - KMU Trucking 10% 426,250.00$ 426,250.00$ 426,250.00$ 205 Earthwork / Site Utilites - Platform 10% 243,300.00$ 243,300.00$ 243,300.00$ 210 Asphalt Paving / Signage Premier 10% 210,000.00$ 210,000.00$ 210,000.00$ 215 Landscaping & Site Furnishings 10% 150,000.00$ 150,000.00$ 150,000.00$ 220 Fencing 10% 10,000.00$ 10,000.00$ 10,000.00$ 225 Concrete & Site Concrete 10% 320,087.00$ 320,087.00$ 320,087.00$ 230 Cast Underlayment - Ritenour 10% 220,000.00$ 220,000.00$ 220,000.00$ 235 Masonry - Valentine 10% 150,500.00$ 150,500.00$ 150,500.00$ 240 Structural Steel - LIVI 10% 310,282.00$ 310,282.00$ 310,282.00$ 245 General Trades / Carpentry - Oppenheim 10% 1,505,508.00$ 1,505,508.00$ 1,505,508.00$ 250 Waterproofing 10% 1,989.00$ 1,989.00$ 1,989.00$ 255 Roofing - Warren Roofing 10% 927,500.00$ 927,500.00$ 927,500.00$ 260 Doors Frames Hardware Mat. - Functional 10% 239,795.00$ 239,795.00$ 239,795.00$ 265 Sectional Doors & Grille - Advance 10% 7,125.00$ 7,125.00$ 7,125.00$ 270 Fire Sectional Doors - Won Doors 10% 52,504.00$ 52,504.00$ 52,504.00$ 275 Fiberglass Windows - Pella 10% 113,755.00$ 113,755.00$ 113,755.00$ 280 Aluminum Entrances Storefronts - Pioneer 10% 290,495.00$ 290,495.00$ 290,495.00$ 285 Gypsum Assemblies /EIFS - Oppenheim 10% 1,520,500.00$ 1,520,500.00$ 1,520,500.00$ 290 Ceramic Tile 10% 80,000.00$ 80,000.00$ 80,000.00$ 300 Carpeting & Resilinet Flooring - Corporate Floors 10% 522,100.00$ 522,100.00$ 522,100.00$ 305 Painting & Concrete Sealer - Alexander Coatings 10% 344,000.00$ 344,000.00$ 344,000.00$ 310 Elevator - KONE 10% 337,000.00$ 337,000.00$ 337,000.00$

315 Pneumatic Trash Chute 10% 14,457.00$ 14,457.00$ 14,457.00$

320 Plumbing - Harner 10% 1,715,000.00$ 1,715,000.00$ 37,797.82$ 1,752,797.82$ 325 Showers & Spa Baths - Best Bath 10% 295,500.00$ 295,500.00$ 295,500.00$

Internal Zero Dollar Adjustments Owner Change Orders

Page 41: Tapestry Senior Living

330 Fire Protection - Brown Sprinkler 10% 334,780.00$ 334,780.00$ 334,780.00$ 335 HVAC - Vadakin 10% 1,200,000.00$ 1,200,000.00$ 15,600.00$ 1,215,600.00$ 340 Electrical / Fire Alarm / Technology - Zenith 10% 1,920,267.00$ 1,920,267.00$ 1,920,267.00$ 345 Abatement - Precision Environmental 10% 57,150.00$ 57,150.00$ 6,310.13$ 63,460.13$ 350 Liquidated Damages 10% 378,000.00$ 378,000.00$ 378,000.00$

355 Utility Fee Allowance 10% 40,000.00$ 40,000.00$ 40,000.00$

360 Repairs to Firestopping Allowance 10% 15,000.00$ 15,000.00$ 15,000.00$

365 Patching Allowance 10% 30,000.00$ 30,000.00$ 30,000.00$

370 Painting Touchup Allowance 10% 25,000.00$ 25,000.00$ 25,000.00$

375 Electrical Allowance 10% 30,000.00$ 30,000.00$ 30,000.00$

380 Moisture & Mold Remediation Allowance 10% 45,000.00$ 45,000.00$ 45,000.00$

385 Schedule Acceleration Allowance 10% 45,000.00$ 45,000.00$ 45,000.00$

390 Atrium Design Development Allowance 10% 400,000.00$ 400,000.00$ 400,000.00$

400 Subcontractor Default Insurance 10% 178,414.00$ 178,414.00$ 716.49$ 179,130.49$

910 General Requirements 10% 758,002.00$ 758,002.00$ 758,002.00$ 940 Construction Staff & Staff Support 10% 478,917.00$ 478,917.00$ 478,917.00$ 960 Construction Contingency 10% 479,034.00$ 479,034.00$ 479,034.00$ 970 General Liability Insurance 10% 182,560.00$ 182,560.00$ 670.71$ 183,230.71$ 975 Payment & Performance Bond 10% 89,900.00$ 89,900.00$ 89,900.00$ 980 CM Fee 10% 501,579.00$ 501,579.00$ 1,832.86$ 503,411.86$

-$ -$ 17,220,882.00$ -$ 17,220,882.00$ -$ 17,283,810.01$

Page 42: Tapestry Senior Living

2926 Chester Avenue TEL 216-861-2050

Cleveland, OH 44114-4414 FAX 216-861-0038

Application No.: 6

To: Lake County Ohio Port & Economic Development Authority Period To: 1/31/2018

One Victoria Place AMH Job No.: 171865

Suite 265A Customer No.: 44575

Painesville, OH 44077 Date: 2/9/2018

Tapestry Senior Living - Wickliffe

Subcontractors Stored Materials Total

200 KMU Trucking & Excavating, Inc. Pay Application No. 3 22,421.75$

235 Valentine Contractors, Inc. Pay Application No. 2 44,950.00$

240 Livi Steel Inc. Pay Application No. 2 35,469.98$ 70,128.70$

245 Oppenheim Construction Co. Pay Application No. 1 41,002.77$

255 Warren Roofing & Insulating Co. Pay Application No. 3 24,000.00$

260 Functional Building Supply Pay Application No. 1 4,800.00$

285 Oppenheim Construction Co. Pay Application No. 1 687,734.00$

320 Harner Plumbing, Inc. Pay Application No. 3 290,603.45$ Subcontractors Misc. Lines 1,221,110.65$

General RequirementsLabor Position Hours Rate Total

Laborer REG 199.50 62.53$ 12,474.74$

199.50 12,474.74$

Material

amHigley Expense Voucher, R. Jensik 1/18/18-2 175.83$

amHigley Expense Voucher, R. Jensik 1/18/18-3 173.91$

amHigley Expense Voucher, R. Jensik 1/18/18 73.65$

amHigley Expense Voucher, T. Lorion 1/22/18-1 142.96$

amHigley Yard Invoice 12-25R17 3,310.31$

amHigley Yard Invoice 01-22R18 3,282.31$

Aris Company 251517 513.60$

Dominion Energy 180901 4,752.29$

Herc Rentals 29746178-001 1,746.07$

Herc Rentals 29746178-002 826.04$

The Illuminating Company 110128403893 61.58$

The Illuminating Company 110128402549 2,549.35$

Pete & Pete 81183 355.00$

Pete & Pete 81369 1,477.25$

The Chas E. Phipps Co 5379854 25,920.00$

United Rentals 152088803-002 88.81$

United Rentals 152735717-001 174.41$

45,623.37$

General Requirements (Line 910) 58,098.11$

LINE ITEM DETAIL

Page 43: Tapestry Senior Living

Staffing & SupportLabor Position Hours Rate Total

David Meehan Project Executive 13.00 95.00$ 1,235.00$

Michael Shean Project Manager 120.00 75.00$ 9,000.00$

Robert Jensik Project Superintendent 112.00 85.00$ 9,520.00$

David Knab Assistant Superintendent 40.00 75.00$ 3,000.00$

Timothy Lorion Project Engineer 160.00 58.00$ 9,280.00$

Maria Spencer Scheduling 10.50 75.00$ 787.50$

Kyle Haines Scheduling 6.00 60.00$ 360.00$

461.50 33,182.50$

Laborer REG 16.00 62.53$ 1,000.48$

16.00 1,000.48$

Materials Invoice No. Total

amHigley Expense Voucher, R. Jensik 1/18/18-2 30.50$

amHigley Expense Voucher, R. Jensik 1/18/18 85.36$

amHigley Expense Voucher, T. Lorion 1/22/18-1 39.97$

amHigley Expense Voucher, S. Spencer 1/26/18-1 45.45$

amHigley Site Technology Invoice Jan-18 1,707.63$

Apple Mobile Leasing 1001-64893 342.40$

Apple Mobile Leasing 1001-65304 449.40$

Apple Mobile Leasing 1001-65352 342.40$

Apple Mobile Leasing 1001-65573 112.35$

ARC 51OH19002686 31.80$

The Distillata Company 0500434 7.50$

The Distillata Company 0521360 11.88$

The Distillata Company 0565590 11.88$

The Distillata Company 0554333 56.90$

Logmein USA Inc 1207096060 12.85$

Oracle America Inc. - Sales Tax 1/31/2018 734.04$

4,022.31$

Staff & Support (Line 940) 38,205.29$

Subcontractor Default Insurance (Line 400) 1,356.42$

Taxes & Insurance (Line 970) 1.11% 15,077.50$

Construction Management Fee (Line 980) 3.00% 39,563.11$

Total Expense 1,373,411.08$

Page 44: Tapestry Senior Living

A-A-1

ATTACHMENT A

CERTIFICATE OF CONTRACTOR

[Required for Disbursement Requests for Hard Costs under Section 3.2(b) of the Disbursement Agreement, Section 5.04 of the Indenture and Section 4.03 of the Loan Agreement]

To: Tapestry Wickliffe, LLC, as Construction Agent - and -

zumBrunnen, Inc., as Construction Consultant - and -

U.S. Bank National Association, as Trustee

The undersigned, as Contractor, certifies to the Construction Consultant and the Trustee that:

(1) the representations made in paragraphs 5 (with respect to Hard Costs only), 6, 7, 8 (to the extent of Contractor’s actual knowledge as of the date hereof), 9 (to the extent of Contractor’s actual knowledge as of the date hereof) and 18 (to the extent of the Contractor’s actual knowledge as of the date hereof) in the Disbursement Request dated ______, 20__ (the “Disbursement Request”) are true, correct and complete; and

(2) the items set forth on Schedule A (with respect to Hard Costs only) to the Disbursement Request are true, correct and complete.

THE ALBERT M. HIGLEY CO. LLC

By: ____________________________________ Name: ____________________________________

Dated: ______________, ____ Title: ____________________________________

1/31 18

Michael SheanProject ManagerFebruary 9 2018

Page 45: Tapestry Senior Living

F-1

ATTACHMENT B

CERTIFICATE OF CONSTRUCTION CONSULTANT

[Required for Disbursement Requests for Hard Costs under Section 3.2(c) of the Disbursement Agreement, Section 5.04 of the Indenture and Section 4.03 of the Loan Agreement]

To: Tapestry Wickliffe, LLC, as Construction Agent - and - U.S. Bank National Association, as Trustee

The undersigned, as the Construction Consultant, certifies to the Construction Agent and the Trustee that

(1) the statements made in paragraphs 4 (with respect to Hard Costs only), 5 (with respect to Hard Costs only), 6 and 10(b) in the Disbursement Request dated January 31, 2018 (the “Disbursement Request”) are true, correct and complete to the best of its knowledge;

(2) the Construction Consultant has received copies of bills, paid invoices, invoices, payroll records or other evidence to its satisfaction supporting each item of the Hard Costs covered by the Disbursement Request, and satisfactory lien releases and waivers from the Contractor and subcontractors for the work for which funds are requested (which may be subject to receipt of payment of the funds requested); and

(3) the undersigned hereby approves the Disbursement Request.

ZUMBRUNNEN, INC.

By:

Name: Doug McMillan

Title: President

Date: February 9, 2018

Page 46: Tapestry Senior Living

EXHIBIT C

Page 47: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Project #2016-122

Page 1

EXHIBIT C OFF-SITE STORED MATERIAL REQUIREMENTS • Photographed and attested to by an approved inspector • Easy to locate, labeled for the project, and tagged to match up to invoices • Segregated from materials of other ownership; protected from theft and weather as necessary • Bill of Sale to the Borrower and Invoices complete with each item listed and priced • Borrower and/or Lender named on the certificate of property insurance as additional insured for

material in storage and transit • Partial and/or conditional waiver of lien for full value or conditional lien waivers are sent directly

to the title company when required • Stored in a bonded warehouse, or provide Uniform Commercial Code (UCC-1) Form for

materials or products stored by the manufacturer or a vendor on their property. Exceptions may be granted with prior approval for those materials covered by a payment and performance bond, stored in a warehouse that is not bonded, or can be replaced without significant impact to the schedule.

Page 48: Tapestry Senior Living

TRA. .. l

NSFER OF TITLE - BILL OF SALE

Project: Tapestry Senior Living- Wickliffe

Project Owner:

Subcontractor I Supplier: Liv.i Steel, Inc.

\1\!HEREAS Owher and The Albert M. Higley Co. have entered into an Agreement and The Albert M. H1gley Co. and Subcontractor/Supplier have entered into an ~greement relative to the aboVe­captioned Rrojec~ it is hereby. agreed that upon Subcontractor/~upplier's receipt of funds from The Albert M. Higley vo. for matenals and or equ1pment as set forth m 'the attached mvo1ces:

Invoice No. Date

PAYAPP 2 1/15/.2018

THAT said materials and/or equipment shall be the property of·The Albert M. Higley Co .. and The Albert M. Higley Co. shall hold title to and interest in the materials and/or equipment to the extent paid for by The Albert M. Higley Co. Subcontractor/Supplier shall isolate all stored materials and/or equipment referenced by this BILL OF SALE from all other materials, equipment and ir'wentory at the storage location and shall designate each item of material and/or equipment with an indication that it is the property of The Albert M. Higley Co. Subcontractor/Supplier shall be fully responsible for the proper and safe storage of the materials and/or equipment, shall Keep said materials and/or: €qUipment fully insured against loss or damage by fire, theft and other such ·hazards, and .shall provfde a Loss Payable Endorsement naming The Albert M. Higley Co. ·as a Loss Payee as its interest may appear. '

Dated this l'lr:P- day of

Subcontractor I Supplier: Livl Steel, Inc.

By: ~fkmq/ Titile: ~·

Page 49: Tapestry Senior Living

c STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX 2217 WARREN, OH 444840217

Customer P.O.#: 3016

Terms: 1/2% 10 N30 Salesperson 1 : Karen Durbin

Qty Ordered Qty

36 __ ~hlpf>ed_ . E_e~_cn_et~~"- ..

36

Messages: overlength

JOB; 17-17

Remit to address: 1648 Reliable Parkway Chicago, IL 60686 Phone: 734-452-3200

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

December 21, 2017 11:41:00AM Page 2 of2

Invoice No: 1035693

Ship To: LIVI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

!:--·,;;>:-:;-~ ,._. ·: 12120/17

Sales Order No: 99984 Ship Date: 12/20/17 Ship Via: Our Truck

Wid~h- _ _ -----~~_ngt~ _________ .. _VIfelgh~ .... _P!1ce UM Extension

Totals 30,675

Subtotal Non Taxable $15,232.74

Total $15,232.74

$76.16 may be deducted If paid before 12130/2017

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A.P .R. All documents other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

Page 50: Tapestry Senior Living

CoN STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX2217

WARREN, OH 444840217

Remit to address: 1648 Reliable Parkway Chicago, IL £0686 Phone:734-452-3200

..

.December 21, 2017 11:41:00AM Page 1 of2

Invoice No: 1035693

Ship To: LIVI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

---·-·-··~- . ------ -----· ----------~--.- ~ .. ---- ----·-·-·-"'-.~--------------------·-··----·------- ----------Customer P.O.#: 3016 F.O.B.: Delivered !nvclcc ua~o: 12120/17 Terms: 1/2% 10 N30 Sales Order No: 99984 Salesperson 1: Karen Durbin Salesperson 2: Jessica Pugliese Ship Date: 12/20/17

Ship Via: Our Truck

Ordered Qty _Q_ty __ !~!l_lped __ ~e_s~~P.!'()_ry ______________ . _

------~dt~ ______ L~_ng!~---. __ ...• W~!gh~- ------ __ _f'!:!c~-~~-----~~~~l~n --BOL No: 82038--

18" WF BEAM 65# 30' o·~ 1,950 $40.50 c $789.75

A992 LOC; v-11

2 2 18" WF BEAM 46# eo·o·: 5,520 $40.50 c $2,235.60

A992 LOC; w-2

6 X 6 X 5/16" TUBE 48'0" 1,120 $52.90 c $592.48

A500GRB

6 X 6 X 5116" TUBE 40'0" 934 $52.90 c $494.09

ASOOGRB

2 2 12" WF BEAM 26# 50'0". 2,600 $39.90 c $1,037.40

A992 loc

3 X 3 X 5/16" TUBE 40'0" 423 $52.90 c $223.n

ASOOGRB LOC; 1-3-8

1 12" CHANNEL 30# 30'0" 900 $40.95 c $368.55

A992

4 4 16" WF BEAM 31# 35' 0" 4,340' $40.50 c $1,757.70

A992 loc w-13

10 10 5 X 3 1/2 X 5/16" ANGLE 40'0" 3,480 $37.95 c $1,320.66

A36

12 12 8 X 4 X 1/2" ANGLE 40' 0" 9,408 $67.95 c $6,392.74

A36

TRANSPORTATION 0 $20.00 E $20.00 SURCHARGE

Page 51: Tapestry Senior Living

Bill To:

~ METALS INTERNATIONAL

~~t=? v··

Livi Steel, Inc. 1245 Burton St. S.E. Warren, OH 44484

Customer PO: 17-17 Terms: 1/2% 10 Days Net 30

Contract:

Sales 1: Scott Lynch

BO Qty Qty Shipped UM Description

0 2 p 8 x 8 x 5/8 HR Tube A500 GR B A500GRB domestic

0 p 10 x 6 x 3/8 HR Tube A500 GR B A500 GR B domestiC·

0 3 p 12 x 6 x 1/2 HR Tube A500 GR B A500GRB domestic

0 7 ·p 4 x 4 X 5/16 HR Tube A500 GR 8 A500 ORB domestic

0 6 p 4 x 4x 1/4 HR TubeA500 GR B A500 GR B domestic

0 2 p 12 x 6 x 1/4 HR Tube A500 GR B A500GR B

1 Village Road. Horsham, PA 19044 Phone: (215} 784-0240 Fax: (215} 784-0180 Website: www.triadmetals.com

F.O.B.:Dellvered

Page 1 of2

Invoice No: 692746

Ship To: Livi Steei, Inc. 1245 Burton St. I.E. Warren, OH 44484

Ship Via: TMT Transportation, LLC

Order#: 378985 ;~:-.... ~.:::.I.'):~. C'.~··:n; 12120/17

Sales 2: Scott Lynch

Width Length Weight Price UM EKtension Tax

BOL No: 274140- Load#: 267939 50' 0" 5,932.00 50.90 c $3,019.39 E

60' o· 2,261.40 51.90 c $1,173.67 E

50'0" 8,349.00 51.90 c $4,333.13 E

40' 0" 4,152.40 49.90 c $2,072.05 E

48'0" 3,516.48 49.90 c $1,754.72 E

60' 0" 3;507.60 .51.90 c ~1,820.44 E

Page 52: Tapestry Senior Living

~ METALS INTERNATIONAL

"<J~~-·· .( :~=:~-~> .--<~-~\ ...

1 Village Road. Horsham, PA 19044 Phone: (215) 784-0240 Fax: (215) 784-0180 Website: www.triadmetals.com

Page 2 of2

Invoice No: 692746

Bill To:

Livi Steel, Inc. 1245 Burton St. S.E. Warren, OH 44484

Ship To: Llvi Steel, Inc. 1245 Burton St. I.E. Warren, OH 44484

Customer PO: 17-17 F.O.B.:Delivered Ship Via: TMT Transportation, LLC

80 Qty

Terms: 1/2% 10 Days Net 30

Contract: Order#: 378985 1.-:vc!:::e D1.1.t0: 12/20/17

Sales 1: Scott Lynch

Qty

Sales 2: Scott Lynch

Shipped UM Description Width

Total Weight

Remit Payment To: Triad Metals International 1 Village Road Horsham, PA 19044-3800

Length Weight Price UM Extension Tax ......... ~ ........ _ .. -····~ . .-- ........ ·~

27,718.88 Subtotal Non taxable

Total $14,173.40

$14,173.40

70.87 may be deducted If paid before 12130/2017

REFER TO TRIAD METALS MSOS DATED 4nt88 AND \.ABEL ATTACHED TO INVOICE

PAYMEI'IT AFTER DUE DATE V'IILL 61:; SUBJECT TO IV-IY INTEREST CHARGE AT THE RfTE OF 12.0% PER ANNUM OR THE MAXIMUM ALL0\11/ED BY LAW

SUBJECT TO TERMS & CONDITIONS AGREED TO ON MASTER INVOICE FILE I l

Page 53: Tapestry Senior Living

1 Village Road. Horsham, PA 19044 Phone: (215) 784-0240 Fax: (215) 784-0180 Website: www.triadmeb~ls.com i

Page 1.(lf 1

Invoice No: 693106

Bill To:

Livi Steel, Inc. 1245 Burton St. S.E. Warren, OH 44484

Ship To: Livi Steel, Inc. 1245 Burton St. I.E. Warren, OH 44484

Customer Po: 17-17 F.O.B.:Delivered Ship Via: Material logistics Managemer~t, Inc.

BO Qty

0

0

0

Terms: 1/2% 1 0 Days Net 30

Contract:

Sales 1: Scott Lynch

Qty

Shipped UM Description

'Order#: 378986 1!TJ01~ :>z!o:: 12/26/17

Sales 2: Scott lynch

WrdU1 Length Weight Price UM Extension Tax

------SOL No: 274438- Load#: 268197 2

2

2

P 12 x 20.7 HR Channel A36 exact domestic

p 6 X 6 x 5/16 HR Tube ASOO GR B ASOO GR i3

p 8 x 8 x 3/8 HR.TubeASOO GR B A500 GR B domestic

60' 0" ·2,484.00 40.90 c si,61s.s6 E

45'0" 2,100.60 49.90 c ·$1,048.20 E

45' 0" 3,392.10 49;90 c .$1,692.66 E

_..._ .. ..- .......... __ .. - - ..................... ; .... --·· Total Weight·

/

Remit Payment To: Triad Metals International 1 Village Road Horsham, PA 19044-3800

j.

7,976.70 Subtotal Non taxable $3,756.82

$3,756.82 Total

18.78 may be deducted If paid before '1/5/2018

REFER TO TRIAD METALS MSDS DATED 4n/88 AND LABELAITACHED TO INVOICE I .

'PAYMENT AFTER DUE DATE Vv1Ll BE SUBJECT TO ANY INTEREST CHARGE At THE RATE OF 12.0% PER ANNUM OR THE MAXIMUM ALLOWED BY LAW

SUBJECT TO TERMS & CONDITIONS AGREED TO ON MASTER INVOICE FILE

Page 54: Tapestry Senior Living

CoN STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX2217 WARREN, OH 444840217

Customer P.O.#: 3022

Terms: 1/2% 10 N30 Salesperson 1: Lawrence Svoboda

Ordered Qty

.. Oty__ _ ~~ip!JeE __ -~escrtptlon

Messages:

3 X 3 X 5/16" TUBE

A500GRB

J? -'( 7

Remit to address: S 1648 Reliable Parkway

Chicago, IL 60686 Phone: 734-452-3200

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

. _ V~i~th_ _ _ __ !,(!n_gth __ .

---BOL No: 82450 ~--

24'0"

Totals

December 22, 2017 10:19:59AM Page 1 of 1

Invoice No: 1036154

Ship To: LIVI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

::·-~-; , .... '-;:: 12/21/17

Sales Order No: 101080 Ship Date: 12/21/17 Ship Via: Our Truck

Weight Price UrJl Extension . -- --· ·- ·- -

254 $59.90 c

254

Subtotal Non Taxable

Total

$152.15

$152.15

$152.15

$0.76 may be deducted If paid before 12/31/2017

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A.P.R. All documents other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

Page 55: Tapestry Senior Living

1 Village Road. Horsham, PA 19044 Phone: (215) 784-0240 Fax: (215) 784-0180 Website: www.triadmetals.com

Page 2 of2

Invoice No: 692931

Bill To:

Livi Steel, Inc. 1245 Burton St. S.E. Warren, OH 44484

Ship To: Livi Steel, Inc. 1245 Burton St I.E. Warren, OH 44484

Customer PO: 17-17 F.O.B.:Delivered Ship Via: TMT Transportation, LLC

BO Qty

Terms: 1/2% 10 Days Net 30

Contract:

Sales 1: Scott Lynch

Qty Shipped UM Description

Order#: 378986

Sales 2: Scott Lynch

Width Length Weight ~........ .. . . ... -- ............... ,

Total Weight 12,493.00

':'"C:';~, =>~':l: 12/21/17

PriceUM 'Extension Tax

Subtotal Non taxable Total

$5,030.14

$5,030.14

Remit Payment To: Triad Metals International 1 Village Road Horsham, PA 19044-3800

REFER TO TRIAD METALS MSDS DATED 417188 AND LABEL ATTACHED TO INVOICE

25.15 may be deducted If paid before 12131/2017

PAYMENT AFTER DUE DATE WILL BE SUBJECT TO ANY INTEREST CHARGE AT THE RATE OF 12.0% PER ANNUM OR THE MAXIMUM ALLOWED BY LAW

SUBJECT TO TERMS & CONDITIONS AGREED TO ON MASTER INVOICE FILE

Page 56: Tapestry Senior Living

Bill To:

~ METALS INTERNATIONAL

~·-\1;;-· / .... · •.· ... ~.:.:-<~-· t_ .. ;~f\.··

Livi Steel, Inc. 1245 Burton St. S.E. Warren, OH 44484

Customer PO: 17-17

Terms: 1/2% 1 0 Days Net 30

Cohtract:

Sales 1: Scott Lynch

BO Qty Qty Shipped UM Description

0 2 p 21 x 44 HR WF Beam A992

0 p 12 x 19 HR WF Beam A992

0 p 12 x 19 HR WF Beam A992

0 p 12 x 30 HR Channel A36 domestic

0 p 12 x 20.7 HR Channel A36 exact domestic

0 5 p 12 x 20.7HR Channel A36

1 Village Road. Horsham, PA 19044 Phone: (215) 784-0240 Fax: (215) 784-0180 Website: www.triadmetals.com

I I Page1of2

Invoice No: 692931

Ship To: Livl Steel, Inc. 1245 Burton St. ~.E. Warren, OH 44484

F.O.B.:Delivered Ship Via: TMT Transportation, LLC

Order#: 378986 ~f~·'JG~C-~ S:-::~:;t; 12/21117

Sales 2: Scott Lynch

Width · Length Weight flrice UM E~tenslon Tax

--~- SOL No: 274160 -Load#: 268b37 -----45' 0" 3,960.00 39.90 c $1,580.04 .E

30'0" 570.00 37.90 c $216.03 E

40' o·• 760.00 37.90 c $288.M .E

40'.0" 1,200.00 40.90 c $490.80 E

40' 0" '828.00 40.90 c S338.65 E

:so· o· 5,11'5~00 40.90 c $2,116.:58 E

Page 57: Tapestry Senior Living

NUCCR VULCRAFT-ST. JOE

EIN: 13-1860817

Telephone: 260-337-1800

BILL TO:

LIVl STEEL INCORPORATED P.O. Box 2217 WARREN, OH 44484

Please Remit To:

VULCRAFT INDIANA

Page 1 of 1

Invoice No: 9000377431

Billing Date: Dec 22. 2017

Job No: 025-17-4437

Cust No: 11lli 75 Remittance Dr, Suite 1095, Chicago, IL, 60675-1095

SHIP TO:

TAPESTRY SENIOR LIVING 1245 BURTON SOUTH EAST WARREN, OH 44484

P.O. Number State Sales Tax Number Terms

• P0#1758

1 Shipments for this Invoice

6000429406 (1-4 E SH)

OH State Tax:

TRUMBULL County Tax:

WARREN City Tax:

Other Tax:

Description

***••••••••••••••••• ... ••••• DECK .............................. ....

Steel Deck and Accessories per Contract

59.43

10.33

0.00

0.00

5.750 %)

1.000 %)

0.000 %)

0.000 %)

Freight:

Tax amount:

If your state does not include tax on freight, this tax amount is on MATERIAL ONLY.

Total Due:

INVOICE

Amount

916.40USD

$1,103.24 USD

Discount of $5.17- may be taken if postmar~ed by 01/01/2018. (/,- '2 t!f Otherwise Net 30 from date of invoice. No retainage permitted. Discount must be earned ;·

1 /} 'j"/1 7

No discount on tax. ·

Rev: 01/25/2016

Page 58: Tapestry Senior Living

CON'r

STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX2217

WARREN, OH 444840217

Customer P.O.#: 3016

Terms: 1/2% 10 N30

Salesperson 1: Karen Durbin

Ordered Qty

_Q~ -·· ___ Shlppe?_ O~scrt~tion__ .. _

2

2

Messages: JOB# 17-17

2

2

12" CHANNEL 30#

A992

PART OF# LARGER

Remit to address: ~-'----S 1648 Reliable Parkway

Chicago, IL 60686 Phone:734-452-3200

December 22, 2017

10:19:59AM

Page 1 of 1

Invoice No: 1036151 --------------·------

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

Width Lenuth

----· BOL No: 82363 ---

30' 0"

Totals

Ship To: LIVI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

~:-·:r. '; :, : :·:·'::';: 12/21/17

Sales Order No: 100793 Ship Date: 12/21/17 Ship VIa: Our Truck

Wel_ght Price UM

1,800 $40.95 c

1,800

Subtotal Non Taxable

Total

Extension

$737.10

$737.10

$737.10

$3.69 may be deducted if paid before 12131/2017

Late payment penalty of 1% per month will be added to all invoices more than 40 days 'Old, equivalent to 12% A. P.R. All doc~ments other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

----·--------

Page 59: Tapestry Senior Living

CONT

STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX 2217 WARREN, OH 444840217

Customer P.O.#: 1779

Terms: 1/2% 10 N30 Salesperson 1: Karen Durbin

Ordered Qty ____ Qty ~hlppe!l ___ Oes~rl~tion .

3 3

Messages: JOB 17-17

8" CHANNEL 18.75#

A36/A529

8" CHANNEL 18. 75#

A36/A529

TRANSPORTATION SURCHARGE

Remit to address: 1648 Reliable Parkway Chicago, IL 60686 Phone:734-452-3200

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

__ _ .. ... . Width _!..eng~h.

---· BOL No: 82363---

20' 0"

50'0"

Totals

December 22, 2017 10:19:59AM Page 1 of 1

Invoice No: 1036152

Ship To: LNI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

;;·~1:11;;:) :::~·-·:; ·12121/17

Sales Order No: 100871 Ship Date: 12/21/17 Ship Via: Our Truck

~ei~h~- _ Price

375 $43.74

938 $43.74

0 $20.00

1,313

Subtotal Non Taxable Total

UM

c

c

E

Extension

$164.03

$410.28

$20.00

$594.31 $594.31

$2.97 may be deducted If paid before 12/31/2017

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A.P.R. All do_~uments other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml 48151-3364

Page 60: Tapestry Senior Living

CON STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX 2217

WARREN, OH 444840217

Customer P.O.#: 8/0 1779

Terms: 1/2% 10 N30

Salesperson 1: Karen Durbin

Ordered Oty Qty Shlpp_ed Description

8" CHANNEL 18.75#

A36/A529 cut from larger

1 1

Messages: backorde sh # 100871

Remit to address: 1648 Reliable Parkway Chicago, IL 60686 Phone:734-452-3200

December 22, 2017

10:19:59AM Page 1 of 1

Invoice No: 1036153 ----------------------------

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

Width __ _ LC!_lgth

---SOL No: 82450 ----

30' 0"

Totals

Ship To; LIVI STEEL, INC

1245 BURTON ST SE WARREN, OH 44484

~c:·,·:::~,·.· · ··!·'·': 12/21/17

Sales Order No: 101 055 Ship Date: 12/21/17 Ship Via: Our Truck

563 $43.74 c

563

Subtotal Non Taxable

Total

Extension

$246.26

$246.26 $246.26

$1.23 may be deducted If paid before 12/31/2017

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A. P.R. All documents other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

Page 61: Tapestry Senior Living

CoN,_ ____ ..---

STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX 2217 WARREN, OH 444840217

.. ' .. ·- ---

Customer P.O.#: PO# 3035/JOB#1717

Terms: 1/2% 10 N30 Salesperson 1: Eric Jensen

Ordered Qty

. S'ltY .. ShiJ.l.p~d _[)_e~cription_

4 4

7 7

Messages:

1 0" CHANNEL 15.3#

A992

1 0" CHANNEL 15.3#

A992

8" CHANNEL 18.75#

A36/A529

8 X 4 X 1/2" ANGLE

A36

Remit -to address: 1648 Reliable Parkway

.,...._ ___ ,..._...,. Chicago, IL 60686 I'

Phone: 734-452-3200

F.O.B.: Delivered

Salesperson 2: Jessica Pugliese

Width . ~engt~- .

SOL No: 84335 ---

50' 0"

40'0"

40' 0"

40' 0"

Totals

January 05, 2018 1:06:30PM

Page 1 of 1

Invoice No: 1038702

Ship To: PICKUP

8383 BOYLE PKWY TWINSBURG, OH 44087

~:~~.r~ : .. ., ;·:· ·::: 1/4/18 Sales Order No: 103201 Ship Date: 1/5118 Ship Via: Our Truck

We_lght Price

765 $44.26

612 $44.26

3,000 $39.72

784 $74.30

5,161

Subtotal Non Taxable

Total

UM

c

c

c

c

Extension

$338.59

$270.87

$1,191.60

$582.51

$2,383.57 $2,383.57

$11.92 may be deducted if paid before 1/14/2018

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A.P .R. All documents other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

Page 62: Tapestry Senior Living

. . '

' . ' I ' II

. I 'I

l:

I . ' '. I

I . l

TIM POTTS 12950 WOODIN RD. CHARDON, OHIO 44024 (440) 285-5926

BILLED TO: LIVI STEEL INC. 1245 BURTON S.E. P.O. BOX 2217 WARREN, OHIO 44484

Order Your Choice of Headings Number

--·- .

] Description--of Se~i~es

TAPESTRY WICKLIFFE 17-17

CRN 17-17-03 CRN 17-17-05

I appreciate your business!

---

Invoice Number: 1801002 Invoice Date: 01/15/18

Sf11PPED TO: (If other than Billed To:)

Date Terms C.ompleted ..

30 DAYS - ][' -· Amount

$300 $800

TOTAL $1,100

INVOICE DUE TERMS INDICATED: 5% LATE CHARGEAFTERTERMS, AND 5% COMPOUNDED FOR EVERY 30 DAYS AFTER TERMS.

"

Page 63: Tapestry Senior Living

CoN STEEL

COMPANY

Bill To: LIVI STEEL, INC

P 0 BOX 2217 WARREN, OH 444840217

·--· -- -· ----·-------- -----.---. Customer P.O.#: 5378

Terms: 1/2% 10 N30 Salesperson 1: Gineen Nelson

Ordered Oty

.. _ 91}1. Sh_lpped . P~s.crlptlon _ _ __ -·

2 2 12" Wf: BEAM 26#

A992

Job 17;2)?

2 2

Messages:

Remit to address: S 1648 Reliable Parkway

Chicago, IL 60686 Phone:734-452-3200

F.O.B.: OurWH- Twinsburg

Salesperson 2: Jessica Pugliese

Width Length

---BOL No: 85809---

50'0"

Totals

January 12, 2018 3:41:46PM Page 1 of 1

Invoice No: 1040752

Ship To: LIVI STEEL, INC

CUSTOMER PICK UP TWINSBURG, OH

·.·; ':.:·' ~: '\.:~: 1/11/18 Sales Order No: 104766 Ship Date: 1/12/18 Ship Via: Pick Up

Price UM

2,600 $41.90 c

2,600

Subtotal Non Taxable

Total

Extension

$1,089.40

$1;089.40 $1,089.40

$5.45 may be deducted If paid before 1/21/2018

Late payment penalty of 1% per month will be added to all invoices more than 40 days old, equivalent to 12% A. P.R. All documents other than payments can be sent to: Credit Department P.O. Box 3364 Livonia, Ml48151-3364

Page 64: Tapestry Senior Living

l I 'tS~flD EVIDENCE OF PROPERlY ~NSURANCE f o~~~M=

THIS EVIDENCE OF PROPERTY INSURANCE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIOHT8 UPON THE ADDITIONAL INTEREST NAMED BELOW. THIS EVIDENCE DOES NOT AFFIRMAllVELY'OR NEOATIVB.Y AMEND EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. lMIS EVIDENCE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTA1M! OR PRODUCER, AND THE ADbiTIONAL INTeREST.

AGENCY I ::g_': •. I' oft· cuo1 su -·uta COMPAN'I' ' L. calvin Jones & company Westfield Insurance Co 3744 Staz:~ cent~e Drivv I' 0 Box !00.1 P.O. Box 159 canfield OH 44406-0159 Westfield cent.ex OH 44251-5001

I ft~ Nu>. tuou.u-nu I ~:,e:;,..,.. bba~taglGlealvinjonea.eo CODE: 13400918 I SU8C:OCE:

1~3~~1'Aino· 00007548 INSURED LOAN HUMBER I POLICY NIHBER Livi steel, Ina. TAA024P358 1245 Burton st. sz EFFECTIVE DA ll! 1 ElCPIRA110N DAn! b CONTINUED UNTil

1/27/2017 1/27/2018 TBIMINATEO IF CHEO<EO

warnn OH 44484

PROPERTY INFORMATION •nr.Ann~Ar.A~nnN

Loc# 00001/Bldgl 00001 1245 Buxton st. SE ~ar%eD, OH 44484

I tGIIIQ:J'UI~III'IOUN I:VIUI:f'A,:b UA 11:\1:

THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ~y REQUIREMENT. TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS EVIOCNCE OF PROPERTY INSURANCE MAY BE ISSUED OR MAY PERTAIN, THE INSUR~CE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO AU. THE TERMS, EXCLUSIONS ~0 CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAWs.

COVERAGE INFORMATION COVERAO&IP~81f0RM9 AMDU'fT OF INliL.RANce DEDUCniU.&

Blanket ~e~aonal P%operty Others, Replacement Coat, Special fOJ:m $488,000 2,50C

REMARKS flncludlnq Special Conditions) RE: Materials fabricated and stored at ~ivi steel, Inc. facility valu~ at $$35,469.98

~he Albe%t M. Higley co., LLC is included as Loss Payee regardin9 stored Materials. 30 Days•

Notice of cancellation except for 10 Days• for Don-payment of premium.

CANCELLATION SHOULD ANV OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE 1ME I!XPIRAl10N DATE THI!REOP, N0l1CE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.

ADDITIONAL INTI! REST

'l'be Albert M. Higlel( Co. , LLC fx1 MORTGAGE£

lOSS PAYEE

H ..OOITIONI'l. ftSUREO

2926 Cheater Avenue ~O.AN •

Cleveland, OK 44114 A\ITttOIUUO llei'IU!IImi'A11VI!

' ~o). ~ Gwendolyn Hardin/GSH

<i> 1993-2009 ACORD CORPORAT10N. All rights reserved. ACORD 27 (2009/12) INS027 lm91ll02 The ACORD name and logo are registered marke of AC:ORO

Page 65: Tapestry Senior Living

I 1 '

DEPARTMENT OF HOMELAND SECURITY Federal Emergency Management Agency · .

STANDARD FLOOD HAZARD DETERMINATION FORM.(SFHDF) OMB Control No. 1660.0040

Expires: 10/31118

1. LENOERISERVICER NAME AND ADDRESS

SBLBCTIVB INSURANCB COMPANY OF AMBRICA

2. COLLATERAL mOte information.)

(Building/Mobile Home/Propeity) (See lnslructlons for

40 Wantage Avenue Branchville, NJ 07890

3. LENDERISERVICER 10 #

1. NFIP Map Number or Communily·Panel Number (Communily name, If not the same as "A")

39155C 0381D

4. Flood Zone

X

1245 BURTON ST SB WARRBN, OK 44484

[!) NO

OF FLOOD INSURANCE REQUIRED

4. NF~P Communily Number

390541

06/18/10 0 YES (if yes, and LOMC dato/no. Is available, onter date and ease no. below).

S, No NFIP Map

Date Case No.

1. [!] Federal Flood Insurance Is avaHable (community participates In the NFIP).[!J Regular Program 0 Emergency Program of NFIP

2. D Federal flood Insurance is not available (community does not participate in the NFIP).

3. O Building/Mobile Home Is In a Coastal Barrier Resources Area (CBRA) or Otherwise Protected Area (OPA). Federal Flood lns·u;ence ~t~ay not be available.

CBRAIOPA Designation Date:

IS BUILDING/MOBILE HOME IN SPECIAL FLOOD HAZARD AREA (ZONES CONTAINING THE LETTERS "A" OR "V1? 0 YES (!] NO

If yes. need Insurance i!l required by the Flood Disaster Protection Acl of 1973. If no, ncod insurance is not required by l/'le Flood Disaster Protec;tion Act of 1973 .. F'loaao nolo, tho risk of nooding In lhia area Is: only reduced. nol removed.

This determination Is based on examining the NFIP map, any Federal Emergency Management Agency revisions 10· and any other lnfcrmelion needed to locale the building/mobile home on the NFIP map.

DATE OF

09/19/17 at 01:25 PM COT

VloodCert #1 1709774625

Page 66: Tapestry Senior Living

FEMA Flood Zone Definitions 1 Common Flood Zone Map Te~s/ Page3 of4

Moderate risk areas within the 0.2-percent-annual-chance floodplain, areas of 1-percent-annual-chance flooding where average depths are less than 1 foot, areas

B, X (shaded) of 1-percent-annual-chance flooding where the contributing drainage area is less than 1 square mile, and areas protected from the 1-percent-annual-chance flood

by a levee. No BFEs or base flood depths are shown within these zones. (Zone X (shaded) is used on new and revised maps in place of Zone B.)

c,x Minimal risk areas outside the 1-percent and .2-percent-annual-chance

(unshaded) floodplains. No BFEs or base flood depths are shown within these zones. (Zone X (unshaded) is used on new and revised maps in place of Zone C.)

Undetermined Risk Areas

ZONE DESCRIPTION

Unstudied areas where flood hazards are undetennined, but flooding is possible. D No mandatory flood insurance purchase requirements apply, but coverage is

available in participating communities.

Get u Flood Zone Report and sec your Flood Zone- Clic1< here.

http://www.secondlookflood.com/floodzonedefinitionsl 9/19/2017

Page 67: Tapestry Senior Living

l 1 PARTIAL WAIVER & RELEASE

FOR SECOND TilER SUBCONTRACTORS a, SUPPUERS

To: THE ALBERT M. HIGL.EY CO. (Contractor)

Owner: LaSalle Group Ltd.

Project: Tapestry Senior Living -Wickliffe

Subcontractor: Uvi Steel, Inc.

The undersigned Company, a subcontractor or supplier to the Subcontractor named above, and hereinafter referred to as the "Company", in consideration of payments previously received and conditional upon paynient for work performed tlu·ough the current date set forth below, hereby waives and releases all mechanics, ·n1atel'ialman's, or other liens and, to the fullest extent permitted by law, all rights to file any such liens In the future, and :any and all claims 11nd demands against the Ow1~er, the Contractor and the real property on which the Project is located, and any claims arising out of any work, labor, services, equipment or materials, performed or fumished by the Company, its subcontractors and suppliers, in connection with the Project and any subcontract or purchase order related to the Project, through the period covered by the cuJTent invoice.

Except as noted below, the Company further acknowledges and represents that all persons and entities which have provided any labor or material, or rented equipment, for or through the Company in connection with the Project and any subcontract or purchase order related to the Project have been paid in full for the periods covered by previous payments, that previous payments to the Company have been prope1·ly applied to pay all outstanding invoices relating to the Project, that the Company is not aware of any claims, or circumstances which could give rise to future claims, against the Owner, the Contractor or the Project, and that all payroll, withholding and other taxes, union benefits; insurance premiums or other amounts required by law, regulation or agreement to be paid in connection with labor for the Project have been paid in full through the last date of work covered by the cutTent invoice.

Note exceptions, if any:

The Company, in consideration of payments previously ·received aud in consideration of payment for work performed through the current date set forth below, agrees to indemnify, hold harmless, reimburse and defend the Ownet· and/or the Contractor fi·om 111l direct or indirect loss cost and expense (including attorney's fees and expenses) which arise out of or relate to any claims, demands and causes ~faction fi"om all persons and entities which have provided any labor or materials or rented equipment, for or through the Company, in connection with the·Pt·ojcct or any subcontract or purchase order related to the Project which allege that the Company has failed or refused to pay any or 1111 payments due or to become due to any such person and entity for such labor or materials or rented equipment through the cun·ent date set forth below. The Company agrees to assume the defense of any such claims, demands and ~auses of action and. to pay, on behalf of the Owner and/or the Contractor, the an1ount of any such judgment or award that niay be entered against the Owner and/or the Contractor or any settlement that may be agreed to by the Owner and/or the Corttractor in such 11ction or proceeding.

Last date of work period co1:ed by current Invoice:

Cunent Payment Due: ~ ',6l.a 1 100 .{)0 company: FlYcstC'Jh( S'cciorS ~~

~4~.~ By:

CuD\ A ~~{Cl>trivoJit/' (Printed Name alrd Title)

· Swom to before me and subscribed in my presence this

LORRI J. SROt<A Notary PL!!Jiic - St<..'o ol Ohio

Cm;;lllJ of Cuy;:;;ocJ My Commission Expires 12/09/2013

-------·--· ·------ ·---~-·------·

Page 68: Tapestry Senior Living

I :I PARTIAL WAIVER & RELEASE

FOR SECOND TIER SUBCONTRACTORS & SUPPLIERS

To: THE ALBERT M. HIGLEY CO. {Contractor)

Owner: LaSalle Group Ltd.

Project: Tapestry Senior Living- Wickliffe

Subcontractor: Livi Steel, Inc. ----~~----------------

The undersigned Company, a subcontractor or supplier to the Subcontractor named above, and hereinafter referred to as the "Company", in consideration of payments previously received and conditional upon payment for work performed through the current date set forth below, hereby waives and releases all mechanics, materialman's, or other liens and, to the fullest extent permitted by law, all rights to file any such liens in the future, and any and all claims and demands againSt the Owner, the Contractor and the real property on which the Project is located, and any claims arising out of any work, labor, services, equipment or materials, performed or furnished by the Company, its subcontractors and suppliers, in connection with the Project and any subcontract or purchase order related to the Project, through the period covered by the current invoice.

Except as noted below, the Co.mp_anyJurther acknowledges and represents that all persons and entities which have provided any labor or material, or rented equ'ipment, for or through the Company in connection with the Project and any subcontract or purchase order related to the Project have been paid in full for the periods covered by previous payments, that previous payments to the Company have been properly applied to pay all outstanding invoices relating to the Project, that the Company is not aware of any claims, or circumstances which could give rise to future claims, against the Owner, the Contractor or the Project, and that all payroll, withholding and other taxes, union benefits, insurance premiums or other amounts required by law, regulation or agreement to be paid in connection with labor for the Project have been paid in full t1_1rough the last date of work covered by the current invoice.

Note exceptions, if any;

~he Company, in consideration of payments previously received and in consideration of payment· for work performed · through the ·current date set forth below, agrees to indemnify, hold harmless, reimburse and defend the Owner and/or the COI\~ctor fi·om all direct or indirect loss, cost and expense (including attorney's fees and expenses) which arise out of or relate'to any claims, demands and causes of action from all persons and entities which have provided any labor or materials or rented equipment, for or through the Company, in connection with the Pr~ject or any subcontract or purchase order related to the Project which allege that the Company has failed or refused to pay any or all payments due or to become due to imy such person and entity for such labor or materials or rented equipment through the current date set forth below. The Company agrees to assume the defense of any such claims, demands and causes of action and to pay, on behalf of the Owner and/or the Contractor, tbe amount of any such judgment or award that may be entered against the Owner and/or the Col)p-act9r or 811Y settlement that may be agreed t~ by the Owner and/or the Co~tractor in.such action or proceeding.

. .. . ... . ! . .

J.,ast date of work period covered by current Invoice:

Cun:ent Payment Due: . &, L \ 0 ~ . ~ Y Co:npany:\)~ oFJ:,lu.wc CQCi1: !lY; · . •

(Signature)

"DreW P. U nt4c Assr. S£L. ··.J·: •. (Printed Name and Title)

~worn to before me and subscribed in my presence this \ <6~ day of ~~!:="'"""-=+- , 20 I ~ . .· _... _.... - -. - - . _... d0u.lJJJ_ ~-A.:.:;z!...~F------

KATHLEEN DOUGLAS ~ 1%faly Public Seal

• Notary Public - State of Indiana Allen County

• My Commission Expires Dec 20, 2024

Page 69: Tapestry Senior Living

EXHIBIT D

Page 70: Tapestry Senior Living
Page 71: Tapestry Senior Living

Trade Total

SDI Cost 1.2%

Insurance 1.11%

Subtotal

AMH Overhead & Profit @ 3%

Change Order Request Total

Precision:  Additional abatement of HVAC pipe fittings found above ceiling

6,650.44$                    

6,310.13$                    

75.72$                          

70.88$                          

6,456.73$                    

193.70$                        

810.13$                        

Tapestry Senior Living of Wickliffe

Change Order Request #001

Description: Additional Asbestos Abatement

Contractor:

5,500.00$                    Precision:  Additional drywall removal in kitchen

The Albert M. Higley Co. | 2926 Chester Avenue, Cleveland, Ohio 44114‐4414 | Phone: 216.861.2050 Fax: 216.861.0038 

Page 72: Tapestry Senior Living
Page 73: Tapestry Senior Living
Page 74: Tapestry Senior Living
Page 75: Tapestry Senior Living
Page 76: Tapestry Senior Living
Page 77: Tapestry Senior Living
Page 78: Tapestry Senior Living
Page 79: Tapestry Senior Living

Ductwork for supply and return transitions per unit $4,800

Exterior insulation at $2,000 per unit

Structural support rails to span joists 8 @ $250 each

Trade Total

SDI Cost 1.2%

Insurance 1.11%

Subtotal

AMH Overhead & Profit @ 3%

Change Order Request Total

478.87$                        

16,441.31$                  

15,600.00$                  

187.20$                        

175.24$                        

15,962.44$                  

2,000.00$                    

Vadakin: Labor & Material to furnish ductwork on the RTUs 5&6 to consist of following:

9,600.00$                    

4,000.00$                    

Tapestry Senior Living of Wickliffe

Change Order Request #002

Description: RTU's 5 & 6 ductwork & support rails

Contractor:

The Albert M. Higley Co. | 2926 Chester Avenue, Cleveland, Ohio 44114‐4414 | Phone: 216.861.2050 Fax: 216.861.0038 

Page 80: Tapestry Senior Living

Z:\DOCUMENTS\WILLIAM R. VADAKIN\CORRESPONDENCE-CURRENT\TAPESTRY RFI002.DOC

VADAKIN REFRIGERATION

& AIR CONDITIONING INC. 18222 Lanken Avenue Cleveland, Ohio 44119

PHONE (216) 812-3760 FACSIMILE (216) 759-2512 www.vadakin.com

Established 1935 email: [email protected] OCILB # 23257

Michael Sean

The Albert M. Higley Company

2926 Chester Avenue

Cleveland, Ohio 44114-4414

Re: Tapestry RTU revision pricing

Michael,

Per RFI -002

Labor and material to furnish ductwork on the RTU 5&6 to consist of

Ductwork for supply and return transitions- $4,800 per unit for a total of $9,600

Exterior insulation at $2,000 per unit for a total of $4,000

Structural support rails to span joists 8 @ $250 each for a total of $2,000

TOTAL NET PRICE $ 15,600

Sincerely,

William R. Vadakin

President

Page 81: Tapestry Senior Living

CPVC & Copper Material

Pipe Insulation

Labor 168 Hours @ $54.52hr

Trade Total

SDI Cost 1.2%

Insurance 1.11%

Subtotal

AMH Overhead & Profit @ 3%

Change Order Request Total

1,160.28$

39,836.26$

37,797.82$

453.57$

424.59$

38,675.98$

10,075.30$

Harner Plumbing:  

21,782.52$

5,940.00$

Tapestry Senior Living of Wickliffe

Change Order Request #007

Description: Abandon underground hot water lines due to them failing to hold any pressure and reroute 

aboveground

Contractor:

The Albert M. Higley Co. | 2926 Chester Avenue, Cleveland, Ohio 44114‐4414 | Phone: 216.861.2050 Fax: 216.861.0038 

Page 82: Tapestry Senior Living

Tapestry PCO #: 2Date: 11/30/2017

RE: Abandon UG hot water and reroute aboveground.

Price for the following: Abandon UG hot water and reroute aboveground.

Material/Equipment QTY Cost MU (10%) PriceCPVC & Copper material for new Hot water line - Cleveland Plumbing 1 19,802.29$ 1.1 21,782.52$ Subcontractor - Insulation - Thermo Tech 1 5,400.00$ 1.1 5,940.00$

Total Material 27,722.52$

Labor/Subcontractor Hours Cost MU (X%) PricePiping (CPVC & Copper) Labor 168 54.52 1.1 10,075.30

-$

10,075.30$

Total Labor & Material 37,797.82$

Total Proposed Change Order 37,797.82$

Page 83: Tapestry Senior Living

.A.Cleveland 9Plumbing

Supply CLEVELAND PLUMBING SUPPLY MENTOR 7272 MENTOR A VENUE MENTOR OH 44060 440.946. 7072 Fax 440.946. 7828

QLOTE TO: HARNER PLUMBING INC. 2480 BARTLETT RD . MANTUA, OH 44255

Quotation

:y:::::::~~tt}~:j:k/:::::;:::::::·1::::::::::::=r::=:::O:iJ~~t::~~tji:::::;:;:::=:}::::.

11 / 30/17 S100973666 RtMff TO: -r-::::f.~f:~?::::::: The Cleveland Plurrb1ng Supply Co. ··~-~:,:.;~-~:,:,.~.;,:,;,;. 143 E. wash1ngton St . CHAGRIN FALLS OH 44022 1 of 4 440-247-2555 Fax 440-247-2116 -------- -------- ------------~----- ------ -

SHIP TO: HARNER PLUMBING INC. TAPESTRY SENIOR LIVING 28500 EUCLID AVE WICKLIFFE, OH 44092

::::;r1c-m~1mimMrni@iL!::::~!~t!:t~:!~!~trn1m1rnz;~imt~rnmmrn1L::~:::fBiiM& ::;:~~!:j':~1;~~::::mnxmrntt!1:!!~r::::1!:1~~10;&rntm1L::~::~~!tlt~;~mi~t1

:~:{Jt~1~12tit{J: :i:{Jt{Jt{Jt{Ji{jJ{jfilrjttit~f~~tt~~tttt{Jttutttt~tJ{Jt{Jt~iJt~ ~Jr~ijJtjfrj~§jtttJ{j. :::~~t'.j: :::{ttt{J~~t~t{jJ~iJt: 120ft 4 X 20 CPVC SCH 80 PIPE PLAIN END 16.220 ft 1946.40

Nonstock Special Order No Return lOEA SPEARS 806-040C 4" CPVC ELL 90 SCH 52.560 EA 525.60

80 Nonstock Special Order No Return

2EA SPEARS 809-040C 4" CPVC SCH. 80 70.080 ea 140 . 16 ST . 90 Nonstock Special Order No Return

4EA SPEARS 817-040C 4 CPVC SCH80 43.430 EA 173.72 SOCKET 45 Nonstock Special Order No Return

4EA SPEARS 827-040C 4 CPVC SCH 80 ST 45 43.430 ea 173.72 Nonstock Special Order No Return

lOea SPEARS 829-040C 4 " CPVC SCH80 26. 180 ea 261.80 SOCKET COUPLING Nonstock Special Order No Return

lea SPEARS 829-422C 4X3 CPVC SKT CPLG 61.610 ea 61 . 61 SCH 80 CPVC Nonstock Special Order No Return

4ea SPEARS 801 - 418C 4Xl-l/4 CPVC SCH80 86.350 ea 345.40 RED TEE Nonstock Special Order No Return

200ft 3 X 20 CPVC SCH 80 PLAIN END PIPE 10.560 ft 2112.00 2EA SPEARS 806-030C 3" CPVC SCH80 SOC 29.190 1 58.38

90 Nonstock Special Order No Return

2EA SPEARS 809 - 030C 3 CPVC SCH80 90 ST 38.920 ea 77.84 ELL SPIGOTXSOC Nonstock Special Order No Return

4EA SPEARS 817-040C 4 CPVC SCH80 43.430 EA 173.72 SOCKET 45

*** Continued on Next Page***

Page 84: Tapestry Senior Living

A Cleveland •Plumbing

Supply CLEVELAND PLUMBING SUPPLY MENTOR 7272 MENTOR A VENUE MENTOR OH 44060 440.946. 7072 Fax 440.946. 7828

QlXHE TO : HARNER PLUMBING INC . 2480 BARTLETT RD . MANTUA , OH 44255

Quotation

LLJ~~!~%:~~1tt/f=~=t>:/:/:/~~W~~W:?)<:?<

11/30/17 J s100973666

The Cleveland Pl un't>1ng Supply Co. ::::: .. :·.·.·.-.:: .. -/::::::::: 143 E. Wash1ngton St . CHAGRIN FALLS OH 44022 2 of 4 440-247-2555 Fax 440-247-2116

REM[T TO· ----------- -----------------r:-:-~~f:iro:-:~0:

----------------------------------------- -------------SHIP TO: HARNER PLUMBING INC. TAPESTRY SENIOR LIVING 28500 EUCLID AVE WICKLIFFE, OH 44092

::::;n:i~(ii!Jt , t' ,,, [~~:;:::~~:: [:~!:~:~?': j''''?t: :itlii~~(!i~(l 't::?,::rtL:::;:::~!'it> ~:!::~!!l:!s;~~!~::iliLBWiliiilll\!!J~!!~;::::1::!ill!!iillbM1UfaL~~~~:~~~iri~~~E~~eiJ

<>>,i~%~f:?? :/?/:/:\J:?/:J?}JtJt<:~~Wt~~f?/:~fat1Lili/J<:tttttJJ?/:??!!~/~ft?L>L~!?:]J:?<tr~H~t>=ft/ Nonstock Special Order No Return

4ea SPEARS 827-030C 3 SCH80 CPVC 45 ST 31.640 ea 1 26.56 ELL SPIGOTXSOC Nonstock Special Order No Return

8EA SPEARS 829-030C 3" CPVC SOC 80 COUPLING Nonstock Special Order No Ret urn

lEA SPEARS 829-339C 3X212 CPVC SCH.80 REDUCING CPLG Nonstock Special Order No Return

lea SPEARS 801-337C 3X3Xl- l /2 SKT RED T SCH 80 CPVC Nonstock Special Order No Return

lOea SPEARS 801 - 336C 3Xl - l / 4 CPVC SCH80 RED TEE Nonstock Special Order No Return

120ft 2 - 1 /2 X 20 CPVC SCH 80 PLAIN END PIPE Nonstock Special Order No Return

2EA SPEARS 806-025C 2-1/2" CPVC 80 SOC. 90 ELL

2ea SPEARS 809-025C 2-1/2 CPVC ST EL Nonstock Special Order No Return

2ea SPEARS 817-025C 2-1/2 SCH80 CPVC SKT 45D ELBOW Nonstock Special Order No Return

2ea SPEARS 827 - 025C 2-1/2 CPVC 45 ST EL Nonstock Special Order No Return

6ea SPEARS 801-290C 2-l/2Xl - l /4 CPVC S80 TEE

19.980

51.870

56.780

68.100

8.520

25 . 780

28.270

24.620

26.670

31.960

EA 159.84

EA 51.87

ea 56.78

ea 681.00

ft 1022.40

ea 51 .56

ea 56.54

ea 49.24

ea 53.34

ea 191 . 76

------------------- _ Nons tock __ s12ec ial __ Order _ No __ Return -----------1--------L---f----------1 *** Continued on Next Page***

Page 85: Tapestry Senior Living

.&Cleveland 'It Plumbing

Supply CLEVELAND PLUMBING SUPPLY MENTOR 7272 MENTOR A VENUE MENTOR OH 44060 440.946. 7072 Fax 440.946. 7828

QOOTE TO : HARNER PLUMBING INC. 2480 BARTLETT RD. MANTUA , OH 44255

Quotation

>>>:J~m~~w:<::<::q:tr=>t:~~r:t:,~mt<>>< 11/30/ 17 l s100973666

The Cl eve land Pl UJTt>1 ng Supply Co . ·-·.:-~:.-.:.,;,:.~:.-.:.,;,:.~:.-.:.,;-143 E. wash1ngton st. CW>.GRIN FALLS OH 44022 3 of 4 440-247-2555 Fax 440-247-2116

REMfT 10: r·::::f~ii:::1~~:::::::::

----------------------------------------- -------------SHIP TO: HARNER PLUMBING INC. TAPESTRY SENIOR LIVING 28500 EUCLID AVE WICKLIFFE, OH 44092

:>:<<:<I:?<::<~~~~::~n:<<:>::tt<Jt=p:t:t:r}~w~r~~~)1;111~rt>t<I!<L<<<t>J!t~~~~J\1,~>>:=>:=>:ttt:p<1>:1w~!i~t>:1>:> ALBERT LTAPESTRY HW (REV4) LBARTHOOl

:::::tJ11r~t=<<<:j:>=>=<:>:<:>t~:!t:~w:<:tttttt{!:<:t:U?<=<<:t<t:>:D~~>:>:<1<:>::>>:=>:::<:>:::::::p:<:>~:!r:=~~t:trn:=:pJ~~:~~~:m~~~f=:< HEIBIL02 PK PICK-UP 2% 10TH PROX NET 30 L11/ 30/ 17 L No

:/L~~~::~1~:1: <~:J:mM2::::i:gi::~::~:~:~:g>i~ijj~:p~:g:J:Jg::::::i:~::6::::::\:/::<?::: :rn::?::t):%~i~%:~::g:J~~::::::fa:::::::/:::::~:~t~~r~:~:~:: TEE Nonstock Special Order No Return

2ea SPEARS 801-288C 2-1 /2X3/4 CPVC SCH80 TEE Nonstock Special Order No Return

60ft 2 X 20 CPVC SCH 80 PLAIN END PIPE 6ea SPEARS 801-250C 2Xl- l /4 CPVC SCH80

RED TEE Nonstock Special Order No Return

lEA SPEARS 3629-015C 112 CPVC SCH80 TRUE UNION BALL VLV Nonstock Special Order No Return

28ea SPEARS 2329- 012C 1-1/ 4 CPVC TRUE UNION BALL VLV SOC/ FPT EPDM Nonstock Special Order No Return

lea SPEARS 3639-0lOC lIN CPVC TRUE UNION BALL VLV SOC/ FPT FKM Nonstock Special Order No Return

2ea SPEARS 1839-007C 3 / 4 CPVC BALL VLV SCH 80 TRUE UN FKM THRD & SOCK ENDS Nonstock Special Order No Return

24ea ANVIL 69-ZP 4 GALV SWIVEL RING LOOP HGR

50ea ANVIL 69-ZP 3 GALV SWIVEL RING LOOP HGR

24ea ANVIL 69-ZP 2-1/2 GALV SWIVEL RING LOOP HGR

12ea ANVIL 69-GAV 2 GALV SWIVEL RING LOOP HGR

6ea 160Z CPVC CEMENT HEAVY DUTY *** Continued on Next Page***

31.960 ea

5.910 ft 38.560 ea

120.040 ea

163.630 ea

79.450 ea

83 . 430 ea

1.150 ea

0.710 ea

0.670 ea

0.370 ea

14.800 ea

63.92

354.60 231.36

120.04

4581. 64

79.45

166.86

27.60

35.50

16.08

4.44

88.80

Page 86: Tapestry Senior Living

A Cleveland tit Plumbing

Supply CLEVELAND PLUMBING SUPPLY MENTOR 7272 MENTOR A VENUE MENTOR OH 44060 440.946.7072 Fax 440.946.7828

Ql.X)TE TO: HARNER PLUMBING INC . 2480 BARTLETT RD. MANTUA, OH 44255

Quotation

:}i?Y~~l:~~!:~:::/{):l: \i(t/~~W~~~i}/:/j:

11/ 30 / 17 Sl00973666 REMIT TO: [:\f~(:~~::::::::: The Cleveland Plurrb1ng Supply Co . -~-~=~·~...-.w ..... -143 E. wash1ngton St . CHAGRIN FALLS OH 44022 4 of 4 440-247-2555 Fax 440-247-2116 [ _________________________________________ -------------

SHIP TO : HARNER PLUMBING INC . TAPESTRY SENIOR LIVING 28500 EUCLID AVE WICKLIFFE, OH 44092

:::~~<!!<'~~ wz:::t:::ii '' '[:::::::~!::~:~:=~~~ 12 ::::: f''!i~!i~i!i!i~i i : dFr::~::~:i!'~::::::::t,tt ::~:•:::~1 ::s~ ~~:~::%@id ! ::1~::: ;::::~:: : : : i&L~~~:~~~~Lli ::!it ~~~%

::::<t~~~)tt?:<: ::::t:t::t?t:>::>::>::::rns>t(t~~wn~~:::::::2t:rncr:::>:t::::>>>::::::::::::::::::::: >:t::::t:2i:~r~~:::::::::::::::::::> t ~~<: :>:t>:d~t~(J?>K 4ea QUART PRIMER CLEAR 12.190 ea 48.7 6 4ea QUART PVC CLEANER CLEAR 7.700 ea 30.80

340f t 1 - 1 / 4 X 20 COPPER PIPE L 5.960 ft 2026. 4 0 56ea VIEGA VPRO 77032 l-1 / 4Xl - l / 4 90D 15.990 ea 895.44 1

PXP SMART CONNECT CU ELBOW 28ea VIEGA 77033 l-1 / 4Xl-1 / 4 45 15.970 ea 447 .161

PROPRESS PXP cu ELBOW I 28ea VIEGA 77063 1-l/ 4Xl-l / 4 ST45D 15.970 ea 447 . 16 1

PXFTG PROPRESS CU ELBOW 24ea VIEGA VPRO 77442 1 -1 / 4 PXPXP SMART 20 .54 0 ea 492.96 !

CONNECT CU TEE I 28ea VIEGA VPRO 79260 1-l/4Xl-l/4 PXM 21.0 00 ea 588.001

SMART CONNECT LF MALE ADP l ea VIEGA VPRO 79275 l-l /2Xl - l /2 PXM 29.440 ea 29.441

SMART CONNECT LF MALE ADP 2ea VIEGA VPRO 7 9230 3/4X3/4 NPT PXM 5.140 ea 10.28

SMART CONNECT LF MALE ADP 84EA ANVIL CT69 1 -1 / 4 COPPER SWIVEL 0 . 850 ea 71.40

RING LOOP HGR Nons t ock Special Order No Return

100ft ANVIL 146 3 / 8 X 10 PLATED THREADED 0.350 ft 35.00 ROD

200ea SAMMY CST - 20 3 / 8 X 2 THREADED 1.630 ea 326.00 ROD X SELF TAPPING CONCRETE SCREW

Subtotal ------ 19802.29

--- ----- --------- --------- ------------------------------------------------- ---· --------··---~~~~~~~~~~~~~~~-~ Subtotal 1 98 02.29 This is a Quotation .

Quote exp1res after 30 days. pr1ces subject to change w1thout not1ce. App11cable taxes apply.

S&H CHGS 0.00 Sales Tax 0 . 0 0

--------------------------------- -------------------------Total Due 19802.29

Page 87: Tapestry Senior Living

Thermo Tee Insulation

1415 E. 222nd Street

Euclid OH 44117

(216) 663-3842 ( ) -customerservice@thermotecinsulatic

Proposed To: Harner Plumbing 2480 Bartlett Road

Mantua

Job Address:

Tapestry

OH 44255

Main Corridor

Descri tion

Accepted By:

- -----Cost to insulate 4", 3", 2 1/2" and 1 1/4" domestic water lines per specifications.

Thank You For Your Business!

Terms: Net 30

Proposal ' Proposal No.: 156619

Date: 11/28/2017

Sign and return upon acceptance

Unit Price 5,400.00

Total:

Extended Price 5,400.00

5,400.00

Page 88: Tapestry Senior Living

Tapestry Wickliffe a m HIGLEY Beyond Bricks and Mortar

PAYMENT & PERFORMANCE BOND

Payment & Performance Bond — additional cost to base bid

$ (49 oo

COMBINATION BID OPTION (bidders may submit a bid for multiple bid packages at a discounted quote in the section below):

1.

2.

3. $

4.

5.

Total Combined Lump Sum Bid Amount: $

ALTERNATES:

HVAC Alternate 1 — Per Specification Section 01 1000 — 1.02.B.2 the HVAC Base Bid should be based upon the Owner furnishing the PTAC Units and the HVAC Contractor will receive, handle and install the units. HVAC Alternate 1 is for the HVAC Contractor to furnish the PTAC units.

Add $

LABOR RATES (include line items for overtime rates)

Please provide hourly labor rates for all trades to be utilized at the Project site. Rates should be based on the contract year May 2017 — May 2018. Include each level of the trades to be employed at the site (i.e. journeyman, foreman, etc.). Attach additional pages if necessary.

Payroll Trade Base Rate Fringes Taxes & Ins OH&P Total

Ant&W 31. ‘-?' 9. G 9 G. 72

$

$

$

$

July 2, 2017 The Albert M. Higley Co. Page 3 of 4

Page 89: Tapestry Senior Living
Page 90: Tapestry Senior Living

Oppenheim:

MaterialLaborOH&P

Vadakin:

MaterialLaborOH&P

Trade Total

SDI Cost 1.2%

Insurance 1.11%

Subtotal

AMH Overhead & Profit @ 3%

Change Order Request Total‐ Not To Exceed

90,738.11$                   

1,088.86$                     

1,019.28$                     

92,846.25$                   

2,785.39$                     

95,631.63$                   

7,358.00$                     

18,493.00$                   

4,006.00$                     

22,657.00$                   

32,689.46$                   

5,534.65$                     

Tapestry Senior Living of Wickliffe

Change Order Request #010

Description: Per RFI#51,install insulation in stud walls (move framing and drywall in CE010), furnish and install new fire rated access doors and dampers, fabricate new exhaust risers.

Contractor:

The Albert M. Higley Co. | 2926 Chester Avenue, Cleveland, Ohio 44114‐4414 | Phone: 216.861.2050 Fax: 216.861.0038 

Page 91: Tapestry Senior Living

OPPENHEIM CONSTRUCTION CO., INC.

35585 Curtis Blvd., Unit K

Eastlake, Ohio 44095

Date: Project:

To:

ATTN:

Item No.

1

Material 9,223.00$

Labor 42,855.00$

OH&P 8,072.09$

Total 60,150.09$

General Contractor:

By: Alex Urbancsik By:

Date: 12/29/2017 Date:

Oppenheim Construction Co., Inc.

Michael Shean

Description

CHANGE ORDER TOTAL:

Higley Change Order Description:

7

Amount

$60,150.09

12/29/2017

$60,150.09

RFI #051 Chase Wall

CHANGE

ORDER-P: 440.266.1662 / F: 440.266.1665

Tapestry Wickliffe

mshean
Typewritten Text
Insulation: $ 29,857.00
mshean
Underline
mshean
Line
mshean
Typewritten Text
Framing Removal & Drywall: $30,293.09
mshean
Callout
Owner's Contingency
mshean
Callout
CM's Contingency
Page 92: Tapestry Senior Living

Condition Detail

Insulation for Chase Wall

Bid No.49

Condition No.:

Name:

Type:

Area:

Quantity 1:

Quantity 2:

Quantity 3:

Height:

Count:

Mat. Lab. Unit TotalSection

07200 2.03 6.07 8.10 8,586

07840 5.98 14.08 20.06 21,271

Total 8.02 20.14 28.16 29,857

1

Insulation for Chase Wall

(unassigned)

1,060.25LF

0

0

8' 0"

0

Notes:

No. Section Mat. Code Mat. TotalLabor CostMaterial PriceSizeQuantityLayersLabor Code Crew

Hours

Item TotalLabor Total

1 07200 R11UN16" INSUN-FAC

ED

1.00 8,482.00 SF 1' 4" x 8' 0.22 /1 SF 0.66 84.0 5,5681,866 7,434

2 07840 4"FIRESAFI

NG24"

FIRESAFIN

G

2.00 1,060.25 SF 2' x 4' 0.98 /1 SF 1.75 28.0 1,8561,039 2,895

3 07840 FIRECAULKI

NG

FIRECAULKI

NG

4.00 4,241.00 LF 25' 1.05 /1 LF 2.61 167.0 11,0694,453 15,522

Total 279.0 7,358 18,493 25,851

9:42:13 am Page 1 of 312/29/2017

Page 93: Tapestry Senior Living
Page 94: Tapestry Senior Living
Page 95: Tapestry Senior Living
Page 96: Tapestry Senior Living
Page 97: Tapestry Senior Living
Page 98: Tapestry Senior Living
Page 99: Tapestry Senior Living

Functional Building Supply.

Qty. 32 Welded HM Frames

Qty. 32 Rediframes

Trade Total

SDI Cost 1.2%

Insurance 1.11%

Subtotal

AMH Overhead & Profit @ 3%

Change Order Request Total- Not To Exceed

2,400.00$

28.80$

26.96$

2,455.76$

73.67$

2,529.43$

4,320.00$

(1,920.00)$

Tapestry Senior Living of Wickliffe

Change Order Request #022

Description: Change Qty. (32) frames from the specified rediframe to hollow metal welded masonry frames. The

knock down rediframes will not work due to existing masonry opening dimensions and wall thickness.

Contractor:

The Albert M. Higley Co. | 2926 Chester Avenue, Cleveland, Ohio 44114-4414 | Phone: 216.861.2050 Fax: 216.861.0038

Page 100: Tapestry Senior Living

18598 Cranwood Parkway Cleveland, Ohio 44128 Phone: (216) 587-4666 Fax: (216) 587-4668

PROPOSAL SUBMITTED TO HIGLEY

FAX NUMBER

DATE 1-3-18

ATTENTION MICHAEL SHEAN

JOB NAME TAPESTRY FRAME SWAP

SUBMITTED BY Brad Graves

JOB LOCATION

We hereby submit specifications and estimates for: CHANGE 32 FRAMES FROM SPECIFIED REDIFRAME TO HOLLOW METAL WELDED MASONRY

FRAMES DUE TO EXISTING WALL CONDITIONS. PUNCH AND DIMPLED WHERE NEEDED

INCLUDING EXPANSION BOLTS.

PRICE FOR STD REDIFRAME……………………………………………$60.00 PRICE FOR WELDED 16GA HM FRAME PUNCH AND DIMPLED….$135.00 DIFFERENCE PER FRAME………………………………………………..$75.00 TOTAL PRICE………………………………………………………………..$2,400.00+TAX

We Propose hereby to furnish material – complete in accordance with above specifications, for the sum of: dollars ( ).

All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents or delay beyond our control. Owner to carry fire, tornado and other necessary insurance. Our workers are fully covered by Workmen’s Compensation Insurance.

Authorized Signature:

Note: This proposal may be withdrawn by us if not

accepted within 30 days.

Acceptance of Proposal – The above prices, specifications and conditions are satisfactory and are hereby accepted. You’re a authorized to do the work as specified. Payment will be made as outlined above.

SIGNATURE

DATE OF ACCEPTANCE: SIGNATURE

Proposal

Page 101: Tapestry Senior Living
Page 102: Tapestry Senior Living

Tapestry Senior Living of Wickliffe Change Order Request Log 2/7/2018

COR# Date

Description Contractor EstimatePending Change Order Request

Amount

Approved Owner Change Order

Status Reason Code

Date Approved

CO/AL Num.

COR#

001 12/5/2017 Additional Asbestos Abatement Precision -$ 6,650.44$ Approved 12/26/2017 CO#001 001002 12/5/2017 RTU's 5 & 6 ductwork & support rails Vadakin -$ 16,441.31$ Approved 12/26/2017 CO#001 002003 2/5/2018 Suite Mockups for sales duplicate suites 405 & 445 Multiple 63,669.62$ 003

004 Repair existing waterline on exterior of building and potentially replace water meter Harner 10,231.33$ T&M 004

005Repair Window storefronts at PTAC bump-outs head, jamb and sill details RFI-043. Replace windows in lieu of repairing windows.

Pioneer / Oppenheim

Fix $292,052 Replace $397,940 -$ 005

006 1/15/2018 RFI 17 Additional footer and columns LIVI / Eclipse Voided 006

007 12/7/2017 Abandon underground hot water lines and reroute aboveground Harner -$ 39,836.26$ Approved 12/26/2017 CO#001 007

008 Sprinkler re-routing on exterior of building to inside of building KMU 31,823.42$ T&M Not to

Exceed 008

009 2/6/2018 Install big fans in Atrium Zenith 1,188.19$ 009

010 1/16/2018

Per RFI#51,install insulation in stud walls (move framing and drywall in CE010), furnish and install new fire rated access doors and dampers, fabricate new exhaust risers.

Oppenheim / Vadakin 95,631.63$ Approved CO#002 010

011 Proposal Request #1 Eclipse / LIVI -$ 011

012 1/29/2018 Revise fire sprinkler system components not in original scope of work to bring up to code Brown 33,467.55$ 012

013 1/9/2018 Core drill through bathroom load bearing walls for conduit feeders lines Zenith 6,354.97$ Approved 013

014 2/6/2018 RFI-062 No CMU at Single Story Infill Valentine 7,149.36$ 014015 1/16/2018 Cut curb at X-Line KMU 3,424.12$ Approved 015

016 RFI-040 Infill door opening on X-line Eclipse 5,000.00$ T&M Not to Exceed 016

017 Proposal Request #2 Multiple -$ 017

018 1/9/2018 RFI-058 Additional Blocking Required at X-Line & 9 Line Oppenheim 11,360.97$ Approved 018

019 2/6/2018 RFI-071 Light Switch Height at Entryway of Units Zenith 1,355.34$ T&M 019020 2/5/2018 Electrical VE Zenith (20,632.21)$ 020021 2/1/2018 RFI-022 Night Light & Fixture Switch Zenith 13,619.63$ 021

022 1/11/2018 Change Door Frames to Hollow Metal Welded Masonry Frames Functional 2,529.43$ Approved CO#002 022

023 2/6/2018 RFI -069 Grout CMU Block Valentine 629.06$ T&M 023024 RFI-69 & 70 Connection of C10 & Reattached W LIVI T&M 024025 1/24/2018 RFI-073 CMU Wall in Rm 20 Valentine 1,196.70$ 025

026 2/7/2018 RFI-086 Shower Valve/Fire RatingOppenheim/Vada

kin/Harner 26,568.37$ 026

027 1/24/2018 RFI-079 2nd Fl. Mech Rm Exterior Wall Valentine 2,387.98$ 027028 Alternate louvers for PTAC Units Vadakin Voided 028029 1/24/2018 RFI-063 Chase Wall in Atrium Oppenheim 1,886.80$ 029

Page 1 of 2

Page 103: Tapestry Senior Living

Tapestry Senior Living of Wickliffe Change Order Request Log 2/7/2018

COR# Date

Description Contractor EstimatePending Change Order Request

Amount

Approved Owner Change Order

Status Reason Code

Date Approved

CO/AL Num.

COR# 030 1/24/2018 RFI-077 Exhaust trunk line wall chase Oppenheim 1,551.39$ 030031 1/29/2018 RFI-068 Corridor ceiling access to shut valves Oppenheim 16,095.62$ 031032 1/24/2018 Storm Repair & Sanitary Re-route Harner 2,528.98$ Approved 032

033 2/7/2018 Single Story SOG Demo & InfillEclipse / KMU /

Harner 45,326.63$ T&M Not to Exceed 033

034 1/25/2018 RFI-066 Laundry Rm. Walls Oppenheim 847.36$ 034035 RFI-100 MC Activity Rm Openings LIVI 035

036 2/1/2018RFI-096 Trough masonry to allow PTAC power to be installed to outside wall Zenith 13,827.08$ 036

037 Drawing Revision 6: Underground Plumbing Harner 037

038Infill window locations where windows vary in location with bronze aluminum closure piece to ensure plumbness. Oppenheim

038

039 2/1/2018 Backfill of underpinnig Eclipse 6,075.55$ 039

040 2/1/2018Demo unforseen footer & excavate for sanitary relocation Eclipse 5,139.73$ 040

041 2/5/2018 RFI-089 Bathroom Chase Relocation Vadakin 3,598.15$ 041

042 RFI-060 5X Line ModificationsLIVI/Oppenheim

/Eclipse 042

043 2/7/2018 RFI-015 Kitchen Beams LIVI/Valentine (3,036.94)$ 043044 RFI-016 Steel infill on lower roof LIVI/Valentine 044045 2/7/2018 RFI-076 Epansion Joints Between A & M LIVI 11,003.33$ 045046 046047 047048 048049 049050 050051 051052 052053 053054 054055 055

Totals: 5,000.00$ 274,969.04$ 184,758.11$

Reason Code Legend:

SC - Scope ClarificationUF- Unforeseen Condition

Alternate Options AvailableCO Issued to Sub

FC - Field CoordinationOR - Owner Requested DC - Document Clarification LEGEND

Approved / VoidedPending Approval

Page 2 of 2

dmcmillan
Text Box
Total Pending Changes (priced above) = $303,638 zBI Estimate for Unpriced Changes = $ 50,000 Total Pending Changes = $353,638
Page 104: Tapestry Senior Living

Tapestry Senior Living of Wickliffe Cost Event Allowance Summary Log 2/7/2018

CE# Date

Description Contractor Estimate Pending AmountConstruction Contingency ($479,034)

Allowance: Utility Fee ($40,000)

Allowance: Repairs to

Firestopping ($15,000)

Allowance: Drywall Patching ($30,000)

Allowance: Painting Touchup ($25,000)

Allowance: Electrical ($30,000)

Allowance: Moisture &

Mold Remediation

($45,000)

Allowance: Schedule

Acceleration ($45,000)

Allowance: Atrium Design Development

($400,000)

Sub Allowance:

Remove Waste Concrete ($10,000)

Sub Allowance: Additional

Steel ($10,000)

Sub Allowance: Additional

Drywall ($15,000)

Sub Allowance:

Elevator Re-Inspections

($7,500)

Status Reason Code

Date Approved

CO/AL Num.

001 10/17/2017 Oracle Submittal Exchange Software AMH 9,175.50$ Approved OR 10/29/2017

002 12/5/2017 Corridor walls metal stud and drywall repair and patching Oppenheim 24,633.00$ 15,000.00$ Approved FC 12/12/2017

003 12/11/2017 Remove moldy drywall at 1st floor low roof area and install new drywall and tape

Oppenheim / KMU 25,451.34$ Approved FC 12/12/2017

004 1/22/2017

Wings at MC to be1hr rated metal stud wall in lieu of masonry Type “X” and/or “D1” Type walls of the MC Suites to a “1 hour rated metal stud assembly that is 10 5/8” wide w/ a STC =50”

Oppenheim (961.00)$ Approved

005 1/22/2018 Wood Blocking ILO Masonry at Parapets Oppenheim 23,100.00$ Approved FC 2/1/2018

006 1/3/2018 Additional sawcut at Atrium floor to allow work to proceed on elevator pit KMU 1,463.96$ Approved FC 1/10/2018

007 1/9/2018 Temp Enclosure around Water Riser Oppenheim 1,778.08$ Approved FC 1/10/2018008 1/16/2018 Steel Allowance Deducted per COR-006 LIVI 10,000.00$ Approved FC009 1/19/2018 Sales Tax for Submittal Exchange Software AMH 734.04$ Approved OR 10/29/2017

010 1/22/2018 RFI#51 move bathroom chase wall stud framing & ceiling, install drywall along side showers Oppenheim 30,293.09$ Approved FC 1/18/2018

011 1/23/2018 Temporary Stairwell Doors & Enclosure Oppenheim 787.45$ Approved FC 1/23/2018012 Additional CMU infill work at Elevator C Valentine 5,772.00$ 013 1/31/2018 Underpinning at Elevator Shaft Eclipse 3,271.71$ Approved FC 1/31/2018 CO#1014 1/31/2018 Backfill existing ramp at X Line to subgrade Eclipse 1,242.80$ Approved FC 1/31/2018 CO#1015 1/31/2018 Jack Hammer Frozen Ground Eclipse 1,653.44$ Approved FC 1/31/2018 CO#1016 1/31/2018 Delete porch footers and slab on grade Eclipse (9,548.37)$ 017 2/7/2018 Provide additional water onsite Valentine 403.00$ 018 2/7/2018 Cold weather protection Valentine 5,136.00$ 019 2/7/2018 Cut rebar and relocate in footer Valentine 1,428.00$ 020021022023024025

Totals: 5,772.00$ -$ 69,957.70$ -$ -$ 24,633.00$ -$ -$ 25,451.34$ -$ -$ -$ 10,000.00$ 15,000.00$ -$ 409,076.30$ 40,000.00$ 15,000.00$ 5,367.00$ 25,000.00$ 30,000.00$ 19,548.66$ 45,000.00$ 400,000.00$ 10,000.00$ -$ -$ 7,500.00$

Reason Code Legend:

SC - Scope ClarificationUF- Unforeseen Condition

Alternate Options AvailableCO Issued to Sub

FC - Field CoordinationOR - Owner Requested DC - Document Clarification LEGEND

Approved / VoidedPending Approval

Page 1 of 1

Page 105: Tapestry Senior Living

EXHIBIT E

Page 106: Tapestry Senior Living

Project Directory Tapestry Wickliffe zumBrunnen Project #2016-122

Lender:

U.S. Bank National Association 225 East Robinson St. Suite 250 Orlando, FL 32801 Corporate Trust Dept

T 407-835-3814

Owner: Lake County Ohio Port and Economic Development Authority

One Victoria Place, Suite 265A Painesville, OH 44077

Construction Agent/Developer: Tapestry Wickliffe, LLC 2001 Killebrew Drive, Suite 100 Bloomington, MN 55425 Richard Bienapfl Chief Operating Officer T. 952-854-4434 C. 612-803-1029 [email protected] Terry Sparrow Owner’s Representative [email protected]

Architect: Distyle Design

3410 Winnetka Avenue North Suite 103

Minneapolis, MN 55427 Michael Knisely

T. 763-591-0996 C. 612-532-8598 [email protected]

Contractor: The Albert M. Higley Co., LLC

2926 Chester Ave Cleveland, OH 44114

Michael Shean Project Manager [email protected] Timothy Lorion Project Engineer C. 216-659-8583 [email protected] Robert Jensik Senior Superintendent T. 216-970-4996 [email protected]

Construction Consultant: zumBrunnen, Inc. 5881 Glenridge Drive, Suite 110 Atlanta, GA 30328 Doug McMillan President T. 404-601-4054 F. 404-601-4051 C. 404-606-1342 [email protected]

Page 107: Tapestry Senior Living

EXHIBIT F

Page 108: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Projec #2016-122

Page 1

EXHIBIT F

1.0 SECTION IV.A: CONSTRUCTION CONTRACT SUMMARY Construction Contract Features: • Builder’s Risk Insurance for 100% of the insurable value of the Contract: Provided by the Owner • Payment and performance bonds: Provided in the full amount of the construction contract and a

copy has been provided for our records. • Bonds require consent of surety when retainage is released: No • Bonds require consent of surety for final payment: Yes • Bonds require consent of surety for off-site material storage or prepayments: No • Progress payment schedule: Monthly with payments submitted no later than the 1st day of the

month and payments due by the last day of the month. • Contractor’s payments are subject to retainage of 10% until the project is 50% complete. • No additional retainage withheld for the final 50% of the project, subject to approval of the

Architect and Owner. • Contract substantial completion requirements: 304 calendar days from NTP • Number of days beyond contract substantial completion not subject to LDs: N/A • Liquidated damages per calendar day: $8,900.00 with a cap of $623,000.00 (70 days) • Savings and Bonus:

o If the actual Cost of Work plus the Contractor’s fee is less than the GMP, the savings shall be accrued at 100% to the Owner and 0% to the Contractor

• Contractor bonus: N/A • Tax exempt status: No • Non-for Profit Corporation: Yes – 501-C(3) • Exempt from state sales taxes: No Construction Contract Attachments and Enclosures: • General Conditions: AIA Document A201-2007 • Amendments or Addenda: N/A • Attachments:

o None • Drawing list

o Exhibit I • Exhibits:

o A through I containing Construction Manager Pre-Construction Services, Construction Manager Billable Staff and Rates, Construction Manager’s Insurance Limits, Port Supplementary Contract Provisions, List of Alternates, List of Allowances, Assumptions and Clarifications, Schedule, and List of GMP Documents.

• Supplementary General Conditions: o Port Supplementary Conditions contained in Exhibit D.

Page 109: Tapestry Senior Living

© zumBrunnen, Inc. 2015 All Rights Reserved Tapestry Wickliffe zumBrunnen, Inc. Projec #2016-122

Page 2

2.0 SECTION VII.C: PROJECT CLOSEOUT CERTIFICATES AND DOCUMENTS As the Project approaches completion, this tracking list of documents is required to be produced by the Project Team prior to closeout and final payment. The status of each is as follows: • Temporary Certificates of Occupancy: These should be approximately the same dates as the

estimated contract substantial completion dates detailed in Section VII, Paragraph A • Certificates of Occupancy: This should occur within one month of the last issued TCO • Certificates of Substantial Completion: These should be completed within approximately two

weeks of the contract substantial completion dates for each phase and will include the following: o Architect punch list o Estimated value of punch list

• Evidence of transmittal to the Owner of: Assembly of these documents should begin when the project is two months from the first TCO o HVAC test and balance reports o As-built drawings o Warranties – Contractor and Vendor o Maintenance Manuals

• Owner Training Schedule: Training schedules should be developed two to three months prior to the first TCO

• Final Payment Application: This should occur within 60 days of the issuance of the final Certificate of Occupancy

• Consents of Surety for final payment and final waivers of lien: This should occur within 60 days of the issuance of the final Certificate of Occupancy

Page 110: Tapestry Senior Living

EXHIBIT G

Page 111: Tapestry Senior Living

EXHIBIT G

1.0 DEFINITIONS

- A -

ACM – Additional Construction Management

ADA - The Americans with Disabilities Act which gives civil rights protection to individuals with disabilities similar to those provided to individuals on the basis of race, color, sex, national origin, age, and religion. It guarantees equal opportunity for individuals with disabilities in public accommodations, employment, transportation, State and local government services, and telecommunications.

Addendum - (Addenda) Written information adding to, clarifying or modifying the bidding documents. An addendum is issued by the Owner to the Contractor during the bidding process and as such, addenda are intended to become part of the contract documents when the construction contract is executed.

A/E - Architect/Engineer; the design professional hired by the Owner to provide design and design-related services.

Agency CM (ACM) - (CM Without Risk). A contractual form of the CM system exclusively performed in an agency relationship between the Construction Manager and Owner. ACM is the form from which other CM forms and variations are derived.

Agent - One authorized by a client (principal) to act in his/her stead or behalf and owes the client a "fiduciary duty" (Trust). Example: Construction Manager for fee but classified as an independent contractor for tax purposes. A construction manager for fee does not have any financial responsibility whereas a construction manager at-risk does have financial risk similar to a general contractor.

AIA - American Institute of Architects

Application for Payment - Contractor's written request for payment for completed portions of the work and, for materials delivered or stored and properly labeled for the respective project. (e.g., American Institute of Architects – AIA, Forms G-702 and G-703)

Arbitration (Binding) – A method by which processes for bringing about agreement or reconciliation between opponents in a dispute is designated. Arbitration involves a formal deliberation, it being understood that the results will be binding on the contending parties. Arbitration (Non-Binding) – A method by which processes for bringing about agreement or reconciliation between opponents in a dispute is designated. Arbitration involves a formal deliberation, it being understood that the results are not binding on the contending parties and relief in the court system is an additional remedy if desired.

Architect - An individual or firm who designs and supervises the professional design for the construction of buildings or other structures.

Architect-Engineer (A/E) - An individual or firm offering professional services as both architect and engineer.

Architect’s Supplemental Instructions (ASI) A document written by the Architect containing additional instructions regarding the Contract specifications or drawings. Generally, the Architect uses an ASI when the information is not anticipated to cause a change to the Contract. If the Contractor believes these instructions are a change to the Contract, he can write a COP.

Page 112: Tapestry Senior Living

As-Built Drawings - Drawings marked up to reflect changes made during the construction process or after construction that amend the contract drawings to show the exact location, geometry, and dimensions of the constructed project. It is good practice to make as-built drawings by marking the changes as the project unfolds. As-built drawings are not the same as Record Drawings.

- B -

Bank Inspector – An independent consultant engaged by a construction lender to provide periodic site inspections, to opine on construction schedule and general compliance, and to make recommendations for contractor payment application. Inspections are made during the construction phase of a project development, expansion or renovation and are performed for the benefit of the bank. Bank Inspector scope-of-services are not the same as a Construction Monitor.

Beneficial Occupancy – The point wherein the project is substantially complete in nature to allow the Owner to utilize the project for its intended use. The mechanical systems, life safety systems, telecommunications systems and any other systems which are required to properly utilize the project are complete and in good working order. The remaining items to be completed shall be such that the correction does not cause inconvenience to the Owner or disruption to the Owner's normal operations.

Bid Bond - A written form of security executed by the bidder as principal and by a surety for the purpose of guaranteeing that the bidder will sign the contract, if awarded the contract, for the stated bid amount. The Surety is a third-party that makes a pledge to pay damages to the Owner if the bonded contractor declines an award offered by the Owner.

Bid Documents - The documents distributed to contractors by the Owner for bidding purposes. They include drawings, specifications, form of contract, general and supplementary conditions, proposal forms, and other information including addenda.

Bond - A written form of security from a surety company, on behalf of a prime contractor or subcontractor, guaranteeing execution of the contract and all supplemental agreements pertaining thereto and for the payment of all legal debts pertaining to the construction of the project. (See Bid Bond, Payment Bond, Performance Bond, Labor and Material Payment Bond, or Subcontractor Bond.)

Bonding Company - A properly licensed surety willing to execute a surety bond, or bonds, payable to the Owner, securing the performance on a contract either in whole or in part; or securing payment for labor and materials. Budget Analysis - Budget analysis as to sufficiency of funds takes into consideration various factors. A cost-to-complete estimate must be developed and compared to the balance of funds. This analysis may include consideration for (i) contractor performance; (ii) percent completion and schedule status; (iii) status of contract buyout and contingency; (iii) potential for shared savings; and (iv) various other risk factors as deemed pertinent. This estimate typically does not include projections for discretionary change orders, unless otherwise noted.

Building Code - The legal requirements established by the various governing agencies covering the minimum acceptable requirements for all types of construction. (See also Codes.)

Building Envelope - (1) The elements of a building which enclose conditioned spaces and intended to keep water from entering. (2) The outer structure of the building. (sometimes referred to as "Building Shell")

Building Inspector/Official - A government representative authorized to inspect construction for compliance with applicable building codes, regulations and ordinances. Courts have ruled that government agencies’ building inspectors are exempt from errors and omissions liabilities.

Page 113: Tapestry Senior Living

Building Permit - A written document issued by the appropriate governmental authority permitting construction to begin on a specific project.

Budget Summary Table - A table summarizing the hard cost budget funds and committed hard cost contingency to date to determine the remaining (balance) hard cost contingency. The purpose of this table is to help provide the earliest possible notice of a budget overrun.

- C -

Change Order - A written document between the Owner and the Contractor signed by the Owner, Architect, and the Contractor authorizing a change in the project documents, adjustment in the contract sum and/or the contract time. Proper contract administration requires the contract terms, scope, sum and the contract time to be changed only by change order. The recommended document for this is the AIA Document G701.

Change Order Proposal (COP) - A written change document before it has been approved by the Contractor, Architect, and Owner. A change order proposal can be issued by the Contractor, Architect, or the Owner. The change order proposal becomes a change order only after it has been approved and by the Contractor, Owner, and Architect.

Change Order Request (COR) - A written document requesting an adjustment to the contract sum or an extension of the contract time; issued by the Architect, Owner, or Contractor.

Changed Conditions - Conditions or circumstances, physical or otherwise, which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based, i.e., Concealed Conditions or Latent Conditions.

Chart of Accounts - An alpha/numeric accounting system used by the Contractor to ensure that the project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.

Claim - A formal notice sent by a Contractor to an Owner asserting the fact that the terms of the contract have changed and compensation is being sought by the Contractor from the Owner.

Clerk-of-the-Works - An individual employed by an Owner to represent him on a project at the site of the work. The clerk-of-the-work's abilities, credentials, and responsibilities vary at the discretion of the Owner.

CM - The abbreviation for Construction Management and Construction Manager (a firm that provides CM services or persons who work for a CM firm).

CM Fee Plus Reimbursables - A form of payment for CM services where the construction manager is paid a fixed or percentage fee for CM expertise, plus pre-established hourly, daily, weekly, or monthly costs for field personnel and equipment.

CM Partnering - A contractual commitment by the Owner, A/E, and CM to achieve a common goal, and doing so without a stake holder’s exposure to a potential for conflict of interest in pursuit of that goal.

CM Services - The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.

Codes - Prevailing regulations, ordinances or statutory requirements set forth by governmental agencies associated with building construction practices and owner occupancy, adopted and administered for the protection of public health, life safety and welfare. (See Building Code.)

Page 114: Tapestry Senior Living

Commissioning - The process at or near construction completion when various mechanical, electrical, and plumbing systems are tested and checked for compliance with the design, and are operating properly.

Committed HC Contingency – See “HC Contingency Committed”

Completion Schedule Analysis – See “Project Completion Graph (S-Curve)”

Constructability - The optimizing of cost, time, and quality factors with the material, equipment, construction means, methods, and techniques used on a project; accomplished by matching owner values with available construction industry practices.

Construction Budget - The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors, construction support items other purchased labor, material and equipment, and the construction manager's cost but not the cost of land, A/E fees, or consultant fees.

Construction Change Directive (CCD) - A construction change directive is a written order signed by the Owner and Architect directing the Contractor to make a change in the work and stating a proposed basis for any appropriate adjustment in the contract sum or the contract time. This may result in a change order if an agreement is reached between the Contractor and the Owner. But even in the absence of total agreement, the construction change directive by itself constitutes a change in the contract documents, with determination of any appropriate adjustment in contract sum or contract time being handled in accordance with specified detailed procedures at a later date.

Construction Documents - All drawings, specifications and addenda associated with a specific construction project. These documents delineate and graphically represent the physical construction requirements established by the A/E.

Construction Documents Phase - The third phase of the Architect's basic services wherein the Architect prepares working drawings, specifications and bidding information.

Construction Document Review - One party’s review of another party’s construction documents for the purpose of confirming that these documents and estimates are feasible and are in accordance with the proposed loan or project appraisal.

Construction Management (CM) – (1) A project delivery system that uses a construction manager to facilitate the design and construction of a project by organizing and directing men, materials, and equipment to accomplish the purpose of the design. (2) A professional service that applies effective management techniques to the planning, design, and construction of a project from inception to completion for the purpose of controlling time, cost and quality, as defined by the Construction Management Association of America (CMAA).

Construction Management Contract - A written agreement wherein responsibilities for coordination and accomplishment of overall project planning, design and construction are given to a construction management firm. The building team generally consists of the Owner, Contractor, and Designer or Architect.

Construction Manager - A business organization with the expertise and resources to manage the design, contracting, and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.

Construction Monitor – An independent construction consultant engaged by a member(s) of the financial team to observe and report pertaining to the current status of a construction project schedule, project budget, hard cost payment approvals, and contract administration compliance, and tracks critical action items. The Construction Monitor acts as an independent facilitator and reports all findings in an objective manner.

Page 115: Tapestry Senior Living

Construction Schedule - A graphic, tabular or CPM representation or depiction of the construction portion of the project-delivery process, showing activities, durations, and projected completion dates.

Contingency - Line-item amounts in the project budget, or contractor’s schedule of values intended to cover costs of unknown, unforeseeable, or missed cost items. Contingency may be owner-controlled or contractor-controlled.

Contingency within the GMP (GMP Contingency) – Contractor-controlled contingency; see Contingency

Contingency Graph – See Project HC Contingency Graph

Contract Administration - The contractual duties and responsibilities of the A/E, Contractor, or CM during the construction phase of a project for servicing the interactive provisions in the contract for construction.

Contract Document Phase - The final phase of design on an architectural project when construction documents are completed and bidding documents are formulated. See also "Construction Documents Phase".

Contract Documents - A term used to represent all documents (any general, supplementary, or other contract conditions, the drawings and specifications, all bidding documents, addenda issued prior to execution of the contract and post-award Change Orders, and any other items specifically stipulated as being included in the contract documents) which collectively form the contract between the Contractor and the Owner.

Contract Performance Bond - A written form of security from a surety company to the Owner, on behalf of an acceptable prime or main contractor or subcontractor, guaranteeing the completion of the work in accordance with the terms of the contract.

Contract Substantial Completion – The project contract documents will define substantial completion, which is the contract substantial completion requirement. Contract substantial completion may or may not have additional requirements to be achieved before a project is deemed substantially complete by the Architect and Owner. Typically, substantial completion is achieved when the facility is complete enough to be used for its intended use. The Architect will issue a certificate of Substantial Completion, which is typically an AIA Document G704.

Contract Sum - The total dollar amount payable by the Owner to the Contractor for the performance of the work under the contract documents.

Contract Time - The time period set forth and established in the contract documents for completing a specific project; usually stated in working days or calendar days. The contract time can only be adjusted by valid time extensions through change order.

Contractor's Option - A written provision in the contract documents giving the Contractor the option of selecting certain specified materials, methods or systems without changes in the contract sum.

Contractor's Qualification Statement - A written statement of the Contractor's experience and qualifications submitted to the Owner during the Contractor selection process. The American Institute of Architects publishes a standard Contractor's Qualification Statement form for this purpose.

Cost Breakdown - A financial statement furnished by the Contractor delineating the portions of the contract sum allotted for the various parts of the work and used as the basis for reviewing the Contractor's applications for progress payments. See also "Schedule of Values".

Cost Codes - A numbering system given to specific kinds of work for the purpose of organizing the cost control process of a specific project.

Page 116: Tapestry Senior Living

Cost of Construction - The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors, construction support items other purchased labor, material and equipment, and the construction manager's cost but not the cost of land, A/E fees, or consultant fees.

Cost-of-Work - All costs incurred by the Contractor in the proper performance of the work required by the plans and specifications for a specific project. The term is more specifically defined in all GMP contracts.

Cost-Plus Contract - A form of contract usually between an Owner and Contractor, A/E design professional, or CM, under which the Contractor, A/E, or CM is reimbursed for direct and indirect costs plus a fee for services. The fee is usually stated as a stipulated sum or as a percentage of cost.

Cost Plus Fee Agreement - A written agreement under which services are provided by a Contractor, Architect, Engineer, or CM for the cost of work plus a specified fee.

Cost-To-Complete - All costs remaining to complete construction of the project to obtain a certificate of occupancy and occupy the project for its intended use. These costs can be further defined as Contract, Owner, hard or soft cost-to-complete.

Critical Path – (1) The continuous chain of activities from project-start to project-finish, whose durations cannot be exceeded if the project is to be completed on time. (2) A sequence of activities that collectively require the longest duration to complete (the duration of the sequence is the shortest possible time from the start event to the finish event). Activities on the critical path have no float time.

Critical Path Method (CPM) - A planning scheduling and control line and symbol diagram drawn to show the respective activities involved in constructing a specific project. A CPM schedule shows activity duration and inter-dependence.

CSI - Abbreviation for the Construction Specification Institute

CSI Master Format - The CSI Master Format is a system of numbers and titles for organizing construction information into a regular, standard order or sequence. By establishing a master list of titles and numbers Master Format promotes standardization and thereby facilitates the retrieval of information and improves construction communication. It provides a uniform system for organizing information in project manuals, for organizing project cost data, and for filing product information and other technical data.

- D -

Daily Construction Report - A written document and record that has two main purposes: (1) Furnish information to off-site persons concerning important details of events as they occur daily and hourly, and (2) Furnish historical documentation that might later have a legal bearing in cases of disputes. Daily reports should be as factual and impersonal as possible, free from the expression of personal opinions and feelings. Each report should be numbered to correspond with the working days established on the progress schedule. In the event of no-work days, a daily report should still be made, stating "no work today" (due to rain, strike, or other causes). The report includes a description of the weather; a record of the total number of employees, subcontractors by name, work started and completed today, equipment on the job site, job progress today, names and titles of visitors, accidents and/or safety meetings, and a remarks column for other job related information.

Date of Agreement - (1) Usually on the front page of the agreement; (2) If not on front page it may be the date opposite the signatures when the agreement was actually signed; (3) or when it was recorded; (4) or the date the agreement was actually awarded to the Contractor.

Date of Commencement of the Work - The date established in a written notice to proceed from the Owner to the Contractor.

Page 117: Tapestry Senior Living

Date of Substantial Completion - The date certified by the Architect when the work or a designated portion thereof is substantially complete. The Architect will document this date on an AIA Document G704.

Demising Walls - The boundaries that separate your space from your neighbors' or from the public spaces.

Design-Build (D-B) - A project delivery method where a design-build contractor (contractor-led D-B), A/E design professional (design-led D-B) or CM (CM-led D-B) is directly responsible for both the total project design and construction of the project. Design-Build liability can be explicitly conveyed through the contract documents or implicitly conveyed through the assumption of project-specific design liability, via performance specifications.

Design Development Phase – (1) The second phase of the Architect's basic services wherein the Architect prepares drawings and other presentation documents to fix and describe the size and character of the entire project as to architectural, structural, mechanical, and electrical systems; materials; and other essentials as may be appropriate; and prepares a statement of probable construction cost. (2) The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document Phase during design.

Design-XCM - A variation of the extended services form of CM, where the A/E also provides the CM function.

Direct Costs - The costs directly attributed to a work-scope, such as labor, material, equipment, and subcontracts but not the cost of operations overhead and the labor, materials, equipment, and subcontracts expended in support of the undertaking. Direct Costs, Hard Costs, and Construction Costs are synonymous.

Discretionary Change Order – Owner directed change order not required for completion of the project for the projects’ intended use and in accordance with the construction contract.

Division of Work - A portion of the total project reserved for contractors for bidding and performance purposes, i.e., Bid Division or Work-Scope.

- E -

Engineer - A professional individual who is licensed by the state to practice a specific engineering discipline.

Escrow Account - (1) Money put into the custody of the third party by the first party for disbursement to the second party. (2) A brief temporary depository for progress payments until authorized for release according to the depositor’s explicit instructions.

Estimated Cost-to-Complete - An estimate of the cost yet to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.

Estimated Final Cost - An estimate of the final cost of a work item based on its Cost-to-Date and the estimated cost to complete it. The sum of the Cost-to-Date and the Estimated Cost-to-Complete.

Estimate of Construction Cost - A calculation of costs prepared on the basis of (1) A detailed analysis of materials and labor for all items of work, or (2) On current area, volume, or similar unit costs.

Extended Services-CM - A form of CM where other services such as design, construction, and contracting are included with ACM services provided by the construction manager.

- F -

Fast Track Construction - A method of construction management which involves a continuous design-construction operation. This usually involves a prime or main contractor starting the construction work before the plans and

Page 118: Tapestry Senior Living

specifications are complete.

Feasibility Phase - The conceptual phase of a project preceding the Design Phase used to determine from various perspectives whether a project should be constructed or not.

Fee Enhancement - The awarding of an additional fee, over and above the basic fee for services, based on the performance quality of the party providing the basic service.

FF&E - (1) An abbreviation for furniture, fixtures and equipment; (2) Items classified as personal property rather than real property; (3) An abbreviation generally associated with interior design and planning of retail stores or office facilities.

Field Order (FO) - A written order issued to a Contractor by the Owner, or Owner's Representative, i.e., A/E design professional, effecting a minor change or clarification with instructions to perform work not included in the contract for construction. The work will eventually become a Change Order. A Field Order is an expedient process used in an emergency or need situation, which in many cases does not involve an adjustment to the contract sum or an extension of the contract time. See also "Construction Change Directive.”

Field Schedule - A graphic, tabular or narrative representation or depiction of the construction portion of the project-delivery process, showing field activities and durations in sequential order. A short-interval, field-based schedule that plans contractor and subcontractor activities on a month-to-month, week-to-week, or day-to-day basis from the project milestone schedule.

Field Work Order (FWO) - A written request to a subcontractor or vendor, usually from the general or main contractor, for services or materials.

Final Acceptance - The action of the Owner accepting the work from the Contractor when the Owner deems the work completed in accordance with the contract requirements. Final acceptance is confirmed by the Owner when making the final payment to the Contractor.

Final Completion - The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.

Final Design Phase - The designation used by engineers for the last portion of the design process prior to bidding.

Final Inspection - A final site review of the project by the Contractor, Owner or Owner’s Authorized Representative prior to issuing the final certificate for payment.

Final Payment - The last payment from the Owner to the Contractor of the entire unpaid balance of the contract sum as adjusted by any approved change orders.

Financial and Management Control System - A manual or computerized management control system used by the project team to guide the course of a project and record its status and progress.

Fixed Fee - A set contract amount for all labor, materials, equipment and services; and contractors’ overhead and profit for all work being performed for a specific scope of work.

Fixed Limit of Construction Costs - A construction cost ceiling agreed to between the Owner and Architect or Engineer for designing a specific project.

Float - A scheduling term indicating that an activity or a sequence of activities does not necessarily have to start or end on the scheduled date to maintain the schedule on the critical path. The difference between the early start and late finish of an activity, minus the activities duration.

Page 119: Tapestry Senior Living

- G -

General Conditions - A written portion of the contract documents set forth by the Owner stipulating the Contractor’s minimum acceptable performance requirements including the rights, responsibilities and relationships of the parties involved in the performance of the contract. General conditions are usually included in the book of specifications but are sometimes found in the architectural drawings.

General Condition Items - Purchases, services, or materials required to facilitate construction at the site. As part of the construction budget, these are financial obligations of the Owner and the logistic responsibility of the CM.

General Conditions (of the Contract for Construction) - The part of the contract that prescribes the rights, responsibilities, and relationships of the parties signing the agreement and outlines the administration of the contract for construction, e.g., American Institute of Architects (AIA) Document A201.

General Contractor (GC) - A properly licensed individual or company having "primary" responsibility for the work. A GC can perform work with its own contractors or can perform the project work as an independent contractor, providing services to owners through the use of subcontractors when using the general contracting system. In the latter case, the GC is referred to as "Paper Contractor".

GMP Contingency (Contingency within the GMP) – Contractor-controlled contingency.

Guaranteed Maximum Price-Construction Management (GMP-CM) - A form of the CM system where the construction manager guarantees, in addition to providing ACM services, a ceiling price to the Owner for the cost of construction.

- H -

Hard Costs - All items of expense directly incurred by or attributable to a specific project, assignment or task. Direct Costs, Hard Costs, and Construction Costs are synonymous.

Hard Cost Contingency ("HC Contingency") - Owner-controlled contingency limited to project Hard Costs; see Contingency. Direct Contingency Costs and Construction Contingency Costs are synonymous.

HC Contingency Balance – Owner-controlled contingency that has not been committed to an approved, pending, or potential project change order; unencumbered or remaining contingency.

HC Contingency Committed – Owner-controlled contingency that has been committed to an approved, pending, or potential change order; committed or encumbered contingency. HC Contingency Graph – See Project HC Contingency Graph - I -

Independent Contractor - One free from the influence, guidance, or control of another or others and does not owe a "fiduciary duty". e.g., an architect, engineer, prime or main contractor, construction manager at-risk.

Indirect Costs - Costs for items and activities other than those directly incorporated into the building or structure but considered necessary to complete the project. A contractor’s or consultant’s overhead expense; expenses indirectly incurred and not chargeable to a specific project or task. The terms indirect costs and soft costs are synonymous.

International Building Code (IBC) -The IBC is one of the family of codes and related publications published by the International Conference of Building Officials (ICBO) and other organizations, such as the International Association of Plumbing and Mechanical Officials (IAPMO) and the National Fire Protection Association (NFPA),

Page 120: Tapestry Senior Living

which have similar goals as far as code publications are concerned. The IBC is designed to be compatible with these other codes, as together they make up the enforcement tools of a jurisdiction. More and more governing authorities are accepting the IBC (with edits) as their standard, in most cases replacing the Southern Building Code or Uniform Building Code.

IRFP - The abbreviation for Initial Request for Proposal; The first request for uniform detailed information from prospective CM practitioners being screened for a project.

- J -

Job-Site Overhead - Supportive and necessary on-site construction expense, such as construction support costs, supervision, bonus labor, field personnel, and office expense.

Joint Venture Partner - A party that contracts with another similar party on a project basis to provide greater financial strength, improved services or more acceptable performance qualifications as a combined organization to design, bid, and/or constructs a specific project.

- K -

K - Used as an abbreviation for Contract or Contracts in the legal sector.

- L -

Labor and Material Payment Bond - (1) A written form of security from a surety (bonding) company to the Owner, on behalf of an acceptable prime or main contractor or subcontractor, guaranteeing payment to the Owner in the event the Contractor fails to pay for all labor, materials, equipment, or services in accordance with the contract, and (2) to pay any claims against the Owner from contractors and suppliers who have not been paid for labor, material, and equipment incorporated into the project.

LEED (Leadership in Energy and Environmental Design) - An internationally recognized green building certification system, providing third-party verification that a building or community was designed and built using strategies aimed at improving performance across all the metrics that matter most: energy savings, water efficiency, CO2 emissions reduction, improved indoor environmental quality, and stewardship of resources and sensitivity to their impacts. LEED-EBOM (LEED for Existing Buildings: Operations & Maintenance) - Rating system helps building owners and operators measure operations, improvements and maintenance on a consistent scale, with the goal of maximizing operational efficiency while minimizing environmental impacts. LEED for Existing Buildings addresses whole-building cleaning and maintenance issues (including chemical use), recycling programs, exterior maintenance programs, and systems upgrades. It can be applied both to existing buildings seeking LEED certification for the first time and to projects previously certified under LEED for New Construction, Schools, or Core & Shell.

Letter of Intent - A notice from an Owner to a Contractor stating that a contract will be awarded to the Contractor providing certain events occur or specific conditions are met by the Contractor. The letter can sometimes serve as a formal Notice to Proceed on the project.

Lien, Mechanic's or Material - The right to take and hold or sell an Owner’s property to satisfy unpaid debts for labor, materials, equipment, or services to improve the property.

Lien Release - A written document from the Contractor to the Owner that releases the Lien, Mechanic’s or Material following its satisfaction.

Page 121: Tapestry Senior Living

Lien Waiver - (1) A written document from a contractor, subcontractor, material supplier or other construction professional, having lien rights against an Owner’s property, relinquishing all or part of those rights. (2) Lien waivers are generally used for processing progress payments to prime or main or subcontractors as follows: Conditional Lien Waiver, Unconditional Lien Waiver, and Final Lien Waiver.

Liquidated Damages (LD’s) – An amount of money specified in a contract to be awarded in the event that the agreement is violated. The fixed amount (usually on a per-day basis) which a party to an agreement promises to pay to the other in case one party does not fulfill some or all portions of an agreement.

Lump Sum Contract - A written contract between the Owner and Contractor wherein the Owner agrees the pay the Contractor a specified sum of money for completing a scope of work consisting of a variety of unspecified items or work. (See also "Stipulated Sum Agreement".)

Lump Sum Fee - A fixed dollar amount which includes all costs of services including overhead and profit.

- M -

Mandated Change Order – Change orders required to complete the work as directed by governing authorities or others to accomplish a certificate of occupancy allowing the Owner to take occupancy of the Project and utilize it for its intended use.

Mediation – The action of mediation between parties to effect an agreement or reconciliation. Mediation implies deliberation that results in solutions that may or may not be accepted by the contending parties.

Mechanic’s Lien - A legal claim against an Owner’s property by a project participant to the value of monies earned but not paid for by the Owner or an employing contractor.

Meeting Attendance Form - A generic form used to record presence of persons attending a specific meeting.

Meeting Notes - A written report consisting of a project number, project name, meeting date and time, meeting place, meeting subject, a list of persons attending, and a list of actions taken and/or discussed during the meeting. Generally, this report is distributed to all persons attending the meeting and any other person having an interest in the meeting.

Milestone - An activity with a duration of zero (0) and by which progress of the project is measured. A milestone is an informational marker only; it is used to delineate strategic events of signal importance to monitor progress on the construction milestone schedule. It marks a specific point in time, which point may be contractual.

Milestone Schedule - A schedule of milestones spanning from the start of construction to occupancy, used as the main measure of progress to keep the project on schedule. It is usually summary in nature.

Minor Change in Work – A minor change in work is a written order by the Architect to make a change that does not involve adjustment in the contract sum or extension of the contract time and is not inconsistent with the intent of the contract documents. - N -

Notice of Award - A letter from an Owner to a Contractor stating that a contract has been awarded to the Contractor and a contract will be forthcoming. It may also function as a Notice to Proceed.

Notice to Proceed - A notice from an Owner directing a Contractor to begin work on a contract, subject to specific stated conditions.

Page 122: Tapestry Senior Living

- O -

OAC Meeting - Meeting of the Owner, Architect and Contractor.

Occupancy Phase - A stipulated length of time following the construction phase, during which contractors are bonded to ensure that materials, equipment, and workmanship meet the requirements of their contracts, and that supplier- and manufacturer-provided warranties and guarantees remain in force.

Occupancy Schedule - A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.

On-Site Supervision - Site-based personnel with supervisory responsibilities.

Open Bid - A specific term used where any qualified bidder or estimator is given access to the prescribed project information. Open bid project information is not private.

Owner-Architect Agreement - A written form of contract between Architect and Client for professional architectural services.

Owner-Builder - A term used to describe an Owner who takes on the responsibilities of the general contractor to build a specific project.

Owner Contingency – Owner-controlled contingency; see Contingency

Owner-CM Agreement - Contract between construction manager and client for professional services.

Owner-Construction Agreement - Contract between Owner and Contractor for a construction project.

Owner's Representative (OR) – An "Agent" of the Owner engaged to provide project management of design and construction activities. The OR acts in the absence of and/or interest of the Owner to facilitate the chosen design and construction delivery method. Scope of services sometimes includes management of non-construction components, such as equipment procurement and low voltage performance specification; refer to RA and RE.

- P -

Payment Bond - A written form of security from a surety company to the Owner, on behalf of an acceptable prime or main contractor or subcontractor, guaranteeing payment to all persons providing labor, materials, equipment, or services in accordance with the contract.

Pending and Potential Change Orders – Unexecuted change order or items identified to have a cost or time impact to the project which may result in a change order.

Preliminary Drawings - (1) The drawings that precede the final approved drawings. (2) Usually these drawings are stamped or titled "PRELIMINARY", or "PRELIMINARY/NOT FOR CONSTRUCTION"; and the "PRELIMINARY" is removed from the drawings upon being reviewed and approved by the Architect and/or Owner and/or code official.

Preliminary Lien Notice - A written notice given to the Owner by the subcontractors, suppliers, etc. The notice states if bills are not paid for the labor, services, equipment, or materials furnished or to be furnished, a mechanic's lien may be placed against the property even though the Owner has paid the prime contractor. The notice may explain how the Owner can protect himself against this consequence by (1) requiring the prime contractor to furnish a release by the person giving the Owner notice before making payment to the prime contractor or (2) any other

Page 123: Tapestry Senior Living

method or device which is appropriate under the circumstances. Some states (known as "lien notice states") require lien notices to be filed and some do not. Failure to file a lien notice in a lien-notice state usually results in forfeiture of one's lien rights.

Pre-qualification - A screening process of prospective bidders wherein the Owner gathers background information from a contractor or construction professional for selection purposes. Qualifying considerations include competence, integrity, dependability, responsiveness, bonding rate, bonding capacity, work on hand, similar project experience, and other specific owner requirements.

Prime Contractor - (1) Any contractor having a contract directly with the Owner. (2) Usually the main (general) contractor for a specific project.

Professional Engineer – A designation reserved, usually by law, for a person or organization professional qualified and duly licensed to perform such engineering services as structural, mechanical, electrical, sanitary, civil, etc.

Professional Liability Insurance - Insurance provided for design professionals and construction managers that protect the Owner against the financial results and liability of negligent acts by the insured. Usually referred to as Errors and Omissions (E&O) insurance.

Professional Services - Services provided by a professional, in the legal sense of the word, or by an individual or firm whose competence can be measured against an established standard of care.

Program Schedule - A schedule that spans from the start of design to occupancy; includes the signal activities which control the progress of the project from start to finish.

Progress Meeting - A meeting dedicated essentially to contractor progress during the construction phase.

Progress Payment - Partial payments on a Contractor’s contract amount, periodically paid by the Owner for work accomplished by the Contractor to date determined by calculating the difference between the completed work and materials stored and a predetermined schedule of values or unit costs.

Progress Schedule - A line diagram showing proposed and actual starting and completion times for the respective project activities.

Project - A word used to represent the overall scope of work being performed to complete a specific construction job.

Project Budget - The target cost of the project established by the Owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee, plus any other line-item costs (land, legal fees, interest, design fees, CM fees, etc.) that the Owner wishes to have included in the budget.

Project Completion Graph (S-Curve) - A Project Completion Graph, commonly referred to as an "S-Curve Graph;” The graph resembles an “S” and projects the estimated cash flow through project completion; exclusive of retainage. The graph is based on a direct relationship of cash flow to the percentage of project completion. For a typical single-phase construction project, the first and last stages of construction represented by 15-20% each of the construction schedule, makes up less then an equal amount of percentage of completion. This allows for ramping up and down of the construction process. The remaining interim period, representing 60-80% of the schedule is generally a straight line, which connects the ramping up and down sections of the schedule; this straight-line portion of the S-curve will normally pass through approximately 50% completion at approximately 50% of the construction schedule.

Project Contingency Graph – A graph projecting the use of hard cost contingency through project completion. Each month the committed hard cost contingency is plotted as a percentage of total hard cost contingency against

Page 124: Tapestry Senior Living

the project schedule. The projected hard cost contingency line provides a baseline for analysis. It is assumed for the typical project that up to 40% of the hard cost contingency will be committed during the first 30% of the project schedule; the remaining 60% is a straight-line projection to the end of the project. The 40% allows for the high-risk period during project startup: completion and outstanding governing approvals of design documents, earthwork, and foundations. Where the total cost for mandated change orders falls below the projected graph line, it may be assumed, unless otherwise noted, that sufficient funds remain to complete the project, assuming no extraordinary event(s) occurs.

Project Cost - All costs for a specific project including costs for land, professionals, construction, furnishings, fixtures, equipment, financing and any other project related costs

Project Directory - A written list of all parties connected with a specific project. The list usually includes a classification or description of the party (i.e., Owner, Architect, Attorney, General Contractor, Civil Engineer, Structural Engineer, etc.); name, address, e-mail, telephone and FAX numbers opposite their respective classifications or description. It is particularly important that the emergency or after hour telephone numbers are included. These numbers should be kept confidential if requested by the respective parties.

Project Manager - A qualified individual or firm authorized by the Owner to be directly responsible for the day-to-day management and administration, and for coordinating time, equipment, money, tasks and people for all or specified portions of a specific project.

Project Manual - An organized book setting forth the bidding requirements, conditions of the contract and the technical work specifications for a specific project that documents and augments the drawings. The Project Manual contains the General Conditions, Supplementary and Special Conditions, the Form of Contract, Addenda, Change Orders, Bidding Information and Proposal Forms as appropriate, and the Technical Specifications.

Project Meeting - A meeting dedicated essentially to contractor performance and progress payments, involving supervisors from the Contractor’s home offices and the on-site project team; sub-contractors may be included.

Project Site - The place where a structure or group of structures was, or is to be located, i.e., a construction site.

Project Team - Consists of the Architect/Engineer, Construction Manager, and Owner, represented by their Level 1, 2, and 3 Persons, plus the designated leaders of contracted constructors.

Punch List - A list prepared by the Owner or his/her Authorized Representative of items of work requiring immediate corrective or completion action by the Contractor.

Pure CM - A contractual form of the CM system exclusively performed in an agency relationship between the Construction Manager and Owner. (CM Without Risk). ACM is the form from which other CM forms and variations are derived.

- Q -

Quality Assurance (QA) - The procedure established by the Project Team to inject and extract the level of quality designated by the Owner.

Quality Control (QC) - That part of the Quality Assurance procedure that determines if specified quality is attained.

Quality Engineering - That part of the Quality Assurance procedure where the required level of quality is accurately inserted into the construction documents by the A/E.

Page 125: Tapestry Senior Living

- R -

Record Drawings - A set of contract document drawings, marked up as construction proceeds to reflect changes made during the construction process, which show the exact location, geometry, and dimensions of all elements of the constructed project as installed. It is good practice to make As-Built Drawings by marking the changes on reproducible drawings such a mylar, vellum or sepias for the duplication purposes later.

RFI - Request for Information. A written request, usually a form, from the Contractor addressed to the Architect requesting additional information on an issue in the contract specification or drawings. The answer to an RFI can result in a COP if either the Architect or Contractor believes there is a change in the contract terms.

RFP - Request for Proposal. 1) A request for uniform detailed information from prospective CM practitioners being screened for a project; 2) A document generated by the Architect requesting a cost proposal for a potential change to the Contract. Generally an RFP is used when no determination has been made whether or not the change will be executed.

Reimbursable Expense - Charges to the Owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.

Reimbursable Expenses (or Costs) - Amounts expended for or on account of the project which, in accordance with the terms of the appropriate agreement, are to be reimbursed by the Owner.

Release of Lien - A written action properly executed by an individual or firm supplying labor, materials or professional services on a project which releases his mechanic's lien against the project property.

Resident Architect (RA) - An architect permanently assigned at a job site who supervises the construction work for the purpose of protecting the Owner's interests during construction.

Resident Engineer (RE) (inspector) - An individual permanently assigned at a job site for the purpose of representing the Owner's interests during the construction phase, i.e., Owner's Rep.

- S -

S-Curve – See “Project Completion Graph”

Safety Report - The Occupational Safety and Health Act (OSHA) of 1970 clearly states the common goal of safe and healthful working conditions. A Safety Report is prepared following a regularly scheduled project safety inspection of the specific project.

Schedule of Values - The breakdown of a contract price into sub-items and sub-costs for identifiable construction elements, which can be evaluated by examination for contractor progress payment purposes.

Schematic Design Phase - The first phase of the A/E design professional's basic services in which he consults with the Owner to ascertain the requirements of the project and prepares schematic design studies consisting of drawings and other documents showing the scale, project components, and delineates the Owner’s needs in a general way for the Owner’s approval.

Scope of Work (SOW) - A written range of view or action; outlook; hence, room for the exercise of faculties or function; capacity for achievement; all in connection with a designated project.

Shared Savings - Contractor controlled contingency or buyout savings remaining after all approved contract cost-of–work has been accounted for, from which a percentage of the savings, as defined in the construction contract, is returned to the Owner.

Page 126: Tapestry Senior Living

Shop Drawings - Detailed information and/or drawings provided by material/ equipment suppliers or subcontractors demonstrating that the item provided meets the requirements of the contract documents, or how it is to be installed.

Soft Cost - Cost items in addition to the direct construction cost. Soft Costs generally include architectural and engineering, legal, permits and fees, financing fees, construction interest and operating expenses, leasing and real estate commissions, advertising and promotion, and supervision.

Soft Cost Contingency – Owner-controlled contingency limited to project Soft Costs; see Contingency. Hard cost contingency plus the soft cost contingency generally represent the total Owner’s contingency for the Project, unless specific contingency accounts are established for unique budget items the Owner wishes to track and report separate from the hard and soft cost contingency accounts.

Source and Use Budget – Budget detailing the funds for all project-related costs and how they are to be expended.

Special Conditions - (1) Amendments to the General Conditions that change standard requirements to unique requirements, appropriate for a specific project. (2) A section of the conditions of the contract, other than the General Conditions and Supplementary Conditions, which may be prepared for a particular project. (3) Specific clauses setting forth conditions or requirements peculiar to the project under consideration, and covering work or materials involved in the proposal and estimate, but not satisfactorily covered by the General Conditions.

Specifications - A detailed statement of particulars, especially statements prescribing materials and methods, and quantitative information pertaining to material, products, and equipment to be incorporated into a specific project. The most common arrangement for specifications substantially parallels the Construction Specification Institute (CSI) format.

Standard Details - A drawing or illustration sufficiently complete and detailed for use on other projects with minimum or no changes. Non-project-specific details.

Start Date - The date that an activity or project begins.

Statute of Limitations - The period of time in which legal action must be brought for an alleged damage or injury. The period commences with the discovery of the alleged damage or injury; or in construction industry cases with completion of the work or services performed. Legal advice should be obtained.

Stipulated Sum Agreement - A written agreement in which a specific dollar amount is set forth as the total payment for performing the contract. (See also "Lump Sum Contracts")

Structural Systems - The load bearing frame assembly of beams and columns on a foundation; the most common materials are wood, cement block, re-enforced concrete, or steel. Steel beams and columns are generally fabricated off-site and assembled on site. Other systems such as non-load bearing walls, floors, ceilings and roofs are generally constructed within and on the structural system.

Subcontractor - A qualified subordinate contractor who has a contract with the prime or main contractor.

Subcontractor Bond - A written document from a subcontractor given to the prime or main contractor by the subcontractor guaranteeing performance of his/her contract and payment of all labor, materials, equipment and service bills associated with the subcontract agreement.

Substantial Completion - The stage in the progress of the work when the work, or designated portion of the work, is sufficiently complete in accordance with the contract documents so that the Owner can occupy or utilize the work for its intended use. (See also "Beneficial Occupancy"). This date is normally documented by the Owner and Architect on an AIA Document G704.

Page 127: Tapestry Senior Living

Sub-surface Investigation - (1) A term used to represent an examination of soil conditions below the ground. (2) Investigations include soil borings and geotechnical laboratory tests for structural design purposes.

Superstructure The part of a building or other structure above the foundation.

Supplemental Conditions - Supplements or modifies the standard clauses of the general conditions to accommodate specific project requirements. (synonymous with Supplementary Conditions).

Surety Company or Surety - A properly licensed firm or corporation willing to execute a surety bond, or bonds, payable to the Owner, securing the performance on a contract either in whole or in part; or securing payment for labor and materials.

- T -

Technical Inspection - Matching technical specification criteria with visual or mechanical tests on the project site, or in a remote location or laboratory, to ascertain conformance.

Technical Review - The critique of design solutions, or criteria used for design solutions, by a party other than the one providing the solutions or criteria, to determine adequacy and suitability of purpose.

T&M - (1) An abbreviation for a contracting method called Time and Materials (2) A written agreement between the Owner and the Contractor wherein payment is based on the Contractor's actual cost for labor, equipment, materials, and services plus a fixed add-on amount to cover the Contractor’s overhead and profit.

Time is of the Essence - A provision in a construction contract by the Owner that punctual completion within the time limits or periods in the contract is a vital part of the contract performance and that failure to perform on time is a breach and the injured party is entitled to damages in the amount of loss sustained. e.g., "time is of the essence in the completion of the construction contract".

Total Project Budget - All costs, hard and soft, necessary to achieve completion of a project.

Transmittal - A written document used to identify information being sent to a receiving party. The transmittal is usually the cover sheet for the information being sent and includes the name, telephone/FAX number, e-mail, and address of the sending and receiving parties. The sender may include a message or instructions in the transmittal. It is also important to include the names of other parties the information is being sent to on the transmittal form.

Travel Time - Wages paid to workmen under certain union contracts and under certain job conditions for the time spent in traveling from their place of residence to and from the job.

- U -

Underwriter's Laboratories (UL) Label - A label on a product or manufactured item showing the material is regularly tested by, and complies with the minimum standards of the Underwriter's Laboratories specification for safety and quality.

Uniform Building Code (UBC) - The Uniform Building Code is one of the family of codes and related publications published by the International Conference of Building Officials (ICBO) and other organizations, such as the International Association of Plumbing and Mechanical Officials (IAPMO) and the National Fire Protection Association (NFPA), which have similar goals as far as code publications are concerned. The Uniform Building Code is designed to be compatible with these other codes, as together they make up the enforcement tools of a jurisdiction.

Page 128: Tapestry Senior Living

Unit Prices - A predetermined price for a measurement or quantity of work to be performed within a specific contract. The designated unit price would include all labor materials, equipment or services associated with the measurement or quantity established.

- V -

Value Engineering - A technical review process whereby the design documents are reviewed in an effort to reduce the overall construction cost by implementing alternate materials, processes, and/or equipment while maintaining the original design intent and overall quality of the Project.

Verbal Quotation - A written document used by the Contractor to receive a subcontract or material cost proposal over the telephone prior to the subcontractor or supplier sending their written proposal via mail, e-mail or facsimile.

- W -

Warranty - Assurance by a providing party that the work, material, and equipment under warranty will perform as promised or as required by contract.

Warranty Phase - The time period during which a warranty is in force.

Working Drawing - A drawing sufficiently complete with plan and section views, dimensions, details, and notes so that whatever is shown can be constructed and/or replicated.

Work Order (WO) - A written order (directive), signed by the Owner or his Representative, of a contractual status requiring performance by the Contractor.

- X -

XCM - An abbreviation for "Extended Services -CM"; a form of Construction Management (CM) where other services such as design, construction, and contracting are included with Additional Construction Management (ACM) services provided by the Construction Manager.

- Z -

Zoning - Restrictions of areas or regions of land within specific geographical areas based on permitted building size, character, and uses as established by governing urban authorities.

zumBrunnen Cost-To-Complete – An estimate provided to account for all committed costs and a reasonable allowance for projected future costs to complete construction of a project. This estimate includes the following specific costs and projected estimates:

• Contractor’s cost-to-complete (G702 Line 3 -Total Contract Sum To Date minus G702 Line 4- Total Completed and Stored To Date)

• Pending and potential change orders • Assume any potential shared savings at zero-dollars, unless otherwise noted • Assume balance of HC Contingency to be required for future change orders • Projected budget shortfall to complete the project, when applicable.

zumBrunnen, Inc. – The nation’s leading independent construction consultant providing construction monitoring, facility assessment, and capital replacement budget services to the senior living and healthcare fields, and commercial real estate industry.

Page 129: Tapestry Senior Living

NOTES AND DISCLAIMER: The addressee of this report is the sole Client and obligee of the Construction Monitor. At the direction or with the consent of the Client, the Construction Monitor will provide copies of its reports to (i) other banks that are the Client’s participants or for which the Client is acting as agent (which shall be entitled to rely on such reports, but shall have no recourse to the Construction Monitor other than by and through the Client), (ii) the developer and the architect for the Project as an accommodation for informational purposes only, and (iii) the Project owner as an accommodation for informational purposes only and subject to execution of an access agreement in a form satisfactory to the Construction Monitor and the Client. It is understood the Construction Monitor has no contractual obligation to any of the foregoing parties other than the Client. The Construction Monitor is an independent consultant preparing reports objective in nature with conclusions and recommendations based on observations, interviews, and other documentation as may be provided to the Construction Monitor. Although intended to be comprehensive and objective in nature, these reports are subject to errors and omissions, and variations in interpretation. In the event a reader of these reports becomes aware of any such error or omission, such reader is directed to immediately contact the Construction Monitor. No representation is made by zumBrunnen or its Client to the project developer, the Project architect, or the Project owner (or any other person who gains access to the Construction Monitor’s reports by or through the Project owner, developer, or architect, or their agents) as to the accuracy, adequacy, completeness or reliability of such reports. The Construction Monitor’s reports are not intended for use by investors in deciding whether to buy, hold, or sell bonds or other securities. Neither the Construction Monitor nor its Client shall have any liability whatsoever to the Project developer, the Project architect, the Project owner, or any person who gains access to the Construction Monitor’s reports by or through the Project developer, the Project architect, or the Project owner; and the Project developer, the Project architect, the Project owner, and such other persons shall have no recourse whatsoever to the Construction Monitor or its Client with respect to such reports.

Page 130: Tapestry Senior Living

EXHIBIT H

Page 131: Tapestry Senior Living

Sun Avenue 45'(A Public Right-of-Way)

Euclid

Avenue

(State R

oute 2

0)

(A P

ublic

Rig

ht-o

f-W

ay)

T.B.M. #1Top Nut of HydrantElevation - 700.99'

T.B.M. #2Top Nut of HydrantElevation - 711.24'

©2015 The Riverstone Company©2015 The Riverstone Company N:\2016 JOBS\16-498\dwg\16-498.dwg 1/25/2017 11:18:17 AM EST

Plan Revisions:

Page Revisions:

Issued For:

LAN

D S

UR

VEYIN

G - E

NG

INEER

ING

- D

ES

IGN

3800 L

AKES

IDE A

VEN

UE - S

UIT

E 1

00

CLEVELAN

D - O

HIO

- 4

4114

PH

ON

E: (2

16) 491-2

000 FAX: (2

16) 491-9

640

WW

W.R

IVER

STO

NES

UR

VEY.C

OM

OGPUPSOhio Oil & Gas Producers Underground Protection Service

OH

OF

E

I

PIETRANTONE

ER

OTE

R

PR

STA

E-61756

DAVID A.

INGNIS T E

AL EE

SSION

R

OF

EEG D

Call (614) 715-2984 or 811

stone

riv

er

16-498

Tapestry S

enio

r H

ousin

gO

f W

icklif

fe

28

50

0 E

uclid

Avenue

Wic

klif

fe,

Ohio

PermitJune 09, 2017

Ohio Utilities Protection Service

before you dig

C3.01

Sit

e P

lan

AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
SLOPE DN
AutoCAD SHX Text
W
AutoCAD SHX Text
W
AutoCAD SHX Text
W
AutoCAD SHX Text
G
AutoCAD SHX Text
G
AutoCAD SHX Text
W
AutoCAD SHX Text
N 49°23'35" E 1011.34' Obs.
AutoCAD SHX Text
S 41°23'00" E 220.00' Rec.-Meas.
AutoCAD SHX Text
S 41°23'00" E 111.31' Rec.-Meas.
AutoCAD SHX Text
S 42°02'00" E 108.86' Rec.-Meas.
AutoCAD SHX Text
10.00'
AutoCAD SHX Text
x
AutoCAD SHX Text
Guard Rail
AutoCAD SHX Text
Guard Rail
AutoCAD SHX Text
Pole Sign
AutoCAD SHX Text
W
AutoCAD SHX Text
Concrete Walk
AutoCAD SHX Text
Grass
AutoCAD SHX Text
Grass
AutoCAD SHX Text
Grass
AutoCAD SHX Text
Grass
AutoCAD SHX Text
1 Story Brick & Frame Building F.F. 698.59'
AutoCAD SHX Text
P.P.N. 29-B-010-0-00-015-0 BPM Enterprises, LTD
AutoCAD SHX Text
P.P.N. 29-B-010-0-00-009-0 Four Star Management Group, LLC
AutoCAD SHX Text
P.P.N. 29-B-010-0-00-016-0 BPM Enterprises, LTD
AutoCAD SHX Text
P.P.N. 29-B-010-0-00-022-0 Lakewick Hotel LLC.
AutoCAD SHX Text
14" Tree
AutoCAD SHX Text
16" Tree
AutoCAD SHX Text
30" Tree
AutoCAD SHX Text
30" Tree
AutoCAD SHX Text
24" Tree
AutoCAD SHX Text
14" Tree
AutoCAD SHX Text
12" Tree
AutoCAD SHX Text
G
AutoCAD SHX Text
R=15.00'
AutoCAD SHX Text
R=32.5'
AutoCAD SHX Text
R=8.50'
AutoCAD SHX Text
R=15.00'
AutoCAD SHX Text
R=15.00'
AutoCAD SHX Text
R=28.00'
AutoCAD SHX Text
R=52.00'
AutoCAD SHX Text
PROPOSED LANDSCAPING
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=3.00'
AutoCAD SHX Text
R=20.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=10.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=2.00'
AutoCAD SHX Text
R=2.00'
AutoCAD SHX Text
R=2.00'
AutoCAD SHX Text
FIN FLOOR = 701.90
AutoCAD SHX Text
FIN FLOOR = 701.75
AutoCAD SHX Text
10
AutoCAD SHX Text
FIN FLOOR = 701.90
AutoCAD SHX Text
FIN FLOOR = 701.90
AutoCAD SHX Text
R=28.00'
AutoCAD SHX Text
R=28.00'
AutoCAD SHX Text
R=52.00'
AutoCAD SHX Text
R=28.00'
AutoCAD SHX Text
R=52.00'
AutoCAD SHX Text
R=24.00'
AutoCAD SHX Text
R=28.00'
AutoCAD SHX Text
24.00'
AutoCAD SHX Text
24.00'
AutoCAD SHX Text
24.00'
AutoCAD SHX Text
4-STORY MASONRY AND CONCRETE STRUCTURE FOR ASSISTED LIVING AND MEMORY CARE
AutoCAD SHX Text
25' FRONT PARKING SETBACK
AutoCAD SHX Text
50' FRONT BUILDING SETBACK
AutoCAD SHX Text
25' SIDEYARD BUILDING/PARKING SETBACK
AutoCAD SHX Text
25' SIDEYARD BUILDING/PARKING SETBACK
AutoCAD SHX Text
75' REAR BUILDING SETBACK
AutoCAD SHX Text
25' SIDEYARD BUILDING/PARKING SETBACK
AutoCAD SHX Text
25' SIDEYARD BUILDING/PARKING SETBACK
AutoCAD SHX Text
25' SIDEYARD BUILDING/PARKING SETBACK
AutoCAD SHX Text
13
AutoCAD SHX Text
6
AutoCAD SHX Text
11
AutoCAD SHX Text
21
AutoCAD SHX Text
25
AutoCAD SHX Text
24.00'
AutoCAD SHX Text
LOADING AREA
AutoCAD SHX Text
ELECTRIC GENERATOR
AutoCAD SHX Text
25' REAR PARKING SETBACK
AutoCAD SHX Text
NEW CURB
AutoCAD SHX Text
MON SIGN
AutoCAD SHX Text
Existing Fire Department Connection
AutoCAD SHX Text
Existing Fire Department Connection
AutoCAD SHX Text
Existing Fire Department Connection
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NO PARKING FIRE LANE SIGN
AutoCAD SHX Text
NEW CONCRETE CURB TO MATCH EXISTING
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
R=5.00'
AutoCAD SHX Text
FIN FLOOR = 701.90
AutoCAD SHX Text
FIN FLOOR = 701.90
AutoCAD SHX Text
RETAINING WALL
AutoCAD SHX Text
PROPOSED TRANSFORMER
AutoCAD SHX Text
PROPOSED FENCE SEE ARCHITECTURAL PLANS
AutoCAD SHX Text
PROPOSED FENCE SEE ARCHITECTURAL PLANS
AutoCAD SHX Text
Riverstone
AutoCAD SHX Text
GRAPHIC SCALE
AutoCAD SHX Text
( IN FEET )
AutoCAD SHX Text
0
AutoCAD SHX Text
1 inch = ft.
AutoCAD SHX Text
30
AutoCAD SHX Text
15
AutoCAD SHX Text
30
AutoCAD SHX Text
45
AutoCAD SHX Text
30
AutoCAD SHX Text
Original Lot Line
AutoCAD SHX Text
Guardrail
AutoCAD SHX Text
Dudley PS6747
AutoCAD SHX Text
Capped Riverstone Company
AutoCAD SHX Text
= 5/8" Iron Pin Set and
AutoCAD SHX Text
= Electric Box
AutoCAD SHX Text
LEGEND
AutoCAD SHX Text
= Telephone Box
AutoCAD SHX Text
= Hydrant
AutoCAD SHX Text
= Spot Elevation Tag
AutoCAD SHX Text
= Monument Box Found
AutoCAD SHX Text
PROPOSED
AutoCAD SHX Text
= Curb Inlet
AutoCAD SHX Text
= Catch Basin
AutoCAD SHX Text
= Iron Pin or Pipe Found
AutoCAD SHX Text
= Bollard
AutoCAD SHX Text
= Cable Box
AutoCAD SHX Text
= Water Service Valve
AutoCAD SHX Text
= Property Line
AutoCAD SHX Text
= Guy Anchor & Line
AutoCAD SHX Text
= Light Pole
AutoCAD SHX Text
= Utility Pole
AutoCAD SHX Text
= Gas Meter
AutoCAD SHX Text
= Gas Valve
AutoCAD SHX Text
= Water Valve
AutoCAD SHX Text
= Water Meter
AutoCAD SHX Text
= Sanitary Manhole
AutoCAD SHX Text
= Storm Manhole
AutoCAD SHX Text
= P.K. Nail
AutoCAD SHX Text
Railroad Tracks
AutoCAD SHX Text
Fence Line (Wooden)
AutoCAD SHX Text
Centerline
AutoCAD SHX Text
Waterline
AutoCAD SHX Text
Property Line
AutoCAD SHX Text
Right-of-way Line
AutoCAD SHX Text
Gas Line
AutoCAD SHX Text
Electric Line
AutoCAD SHX Text
Sanitary/Combination Sewer
AutoCAD SHX Text
Storm Sewer
AutoCAD SHX Text
Easement Line
AutoCAD SHX Text
Original Sublot Line
AutoCAD SHX Text
Ex. Parcel line
AutoCAD SHX Text
Fence Line (Chain-Link)
AutoCAD SHX Text
Existing
AutoCAD SHX Text
C
AutoCAD SHX Text
G
AutoCAD SHX Text
G
AutoCAD SHX Text
CABLE
AutoCAD SHX Text
TELE
AutoCAD SHX Text
ELEC
AutoCAD SHX Text
W
AutoCAD SHX Text
G
AutoCAD SHX Text
= Reducer
AutoCAD SHX Text
R/W
AutoCAD SHX Text
= Centerline
AutoCAD SHX Text
Ac.Acres Acres Adj.Adjacent Adjacent A.F.N.Auditor's File Number Auditor's File Number Asp.Asphalt Asphalt B.F.Basement Floor Basement Floor BWBottom of Wall Bottom of Wall Calc./C.Calculated Calculated CBCatch Basin Catch Basin C.C.M.RCuyahoga County Map Cuyahoga County Map Records C.L.F.Chain-link Fence Chain-link Fence Clr.Clears Clears C.O.Clean Out Clean Out Comb.Combination Combination Conc.Concrete Concrete Conn.Connection Connection D.H.Drill Hole Drill Hole D.I.W.M.Ductile Iron Water Main Ductile Iron Water Main ElecElectric Electric ElevElevation Elevation Encr.Encroaches Encroaches Ex.Existing Existing F.F.Finished Floor Finished Floor GUTGutterGutter
AutoCAD SHX Text
InvInvert Invert L.C.A.Limited Common Area Limited Common Area L.F.Lineal Feet Lineal Feet Meas./M.Measured Measured MHManhole Manhole Obs.Observed Observed Pg.Page Page P.P.N.Permanent Parcel Number Permanent Parcel Number PropProposed Proposed Rec./R.Record Record R/WRight-of-way Right-of-way San.Sanitary Sanitary S.F.Square Feet Square Feet S/LSublot Sublot Stm.Storm Storm T.B.M.Temporary Bench Mark Temporary Bench Mark TBRTo Be Removed To Be Removed T/CTop of Curb Top of Curb TeleTelephone Telephone T.F.Top Of Footer Top Of Footer T.T.Test Tee Test Tee TWTop of Wall Top of Wall Typ.Typical Typical Vol.Volume Volume WatWater Water
AutoCAD SHX Text
PROPOSED
AutoCAD SHX Text
Existing
AutoCAD SHX Text
= Cleanout / Test Tee
AutoCAD SHX Text
L
AutoCAD SHX Text
L
AutoCAD SHX Text
P
AutoCAD SHX Text
C
AutoCAD SHX Text
GENERAL NOTES: CONTRACTOR TO VERIFY BUILDING DIMENSIONS WITH ARCHITECTURAL PLANS PRIOR TO CONSTRUCTION. CONTRACTOR TO COORDINATE LIGHT POLE LOCATIONS WITH SITE ELECTRICAL PLANS BY OTHERS. PARKING STRIPES SHALL HAVE A MINIMUM WIDTH OF 4". EXISTING CONCRETE WALK WITHIN THE RIGHT-OF-WAY SHALL BE INSPECTED BY THE CITY OF WICKLIFFE BUILDING DEPARTMENT. ANY WALK FOUND TO BE IN NON-COMFORMANCE OF CITY CODE SHALL BE REMOVED AND REPLACED. SITE PLAN NOTES: 1TYPE 6 CONCRETE CURB TO MATCH EXISTING CURB. TYPE 6 CONCRETE CURB TO MATCH EXISTING CURB. 2END CONCRETE CURB PER END CURB DETAIL ON SHEET C6.01. END CONCRETE CURB PER END CURB DETAIL ON SHEET C6.01. 3CONCRETE PAD WITH DUMPSTER ENCLOSURE. SEE ARCHITECTURAL CONCRETE PAD WITH DUMPSTER ENCLOSURE. SEE ARCHITECTURAL PLANS FOR DUMPSTER ENCLOSURE. 4ADA PARKING SPACE WITH SIGN PER LATEST ADA REQUIREMENT. ADA PARKING SPACE WITH SIGN PER LATEST ADA REQUIREMENT. SEE DETAIL ON SHEET C6.01. 5CONTRACTOR TO REFER TO STRUCTURAL DRAWINGS FOR LAYOUT OF CONTRACTOR TO REFER TO STRUCTURAL DRAWINGS FOR LAYOUT OF SIDEWALK CONTROL JOINTS, FROST SLABS AND BOLLARDS ADJACENT TO BUILDING PERIMETER. COORDINATE FINAL LAYOUT OF BUILDING ADDITIONS WITH ARCHITECTURAL PLANS.
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
REQUIRED
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
PROPOSED
AutoCAD SHX Text
FRONT BUILDING SETBACK
AutoCAD SHX Text
REAR YARD BUILDING SETBACK
AutoCAD SHX Text
SIDEYARD BUILDING SETBACK: EAST
AutoCAD SHX Text
FRONT PARKING SETBACK
AutoCAD SHX Text
REAR YARD PARKING SETBACK
AutoCAD SHX Text
SIDEYARD PARKING SETBACK: EAST
AutoCAD SHX Text
50'
AutoCAD SHX Text
75'
AutoCAD SHX Text
25'
AutoCAD SHX Text
25'
AutoCAD SHX Text
25'
AutoCAD SHX Text
25'
AutoCAD SHX Text
SIDEYARD BUILDING SETBACK: WEST
AutoCAD SHX Text
25'
AutoCAD SHX Text
SIDEYARD PARKING SETBACK: WEST
AutoCAD SHX Text
25'
AutoCAD SHX Text
112.87'
AutoCAD SHX Text
76.85'
AutoCAD SHX Text
114.94'
AutoCAD SHX Text
2.78'
AutoCAD SHX Text
9.47'
AutoCAD SHX Text
0.21'
AutoCAD SHX Text
52.58'
AutoCAD SHX Text
1.88'
AutoCAD SHX Text
133.90'
AutoCAD SHX Text
76.85'
AutoCAD SHX Text
114.94'
AutoCAD SHX Text
21.14'
AutoCAD SHX Text
9.54'
AutoCAD SHX Text
3.92'
AutoCAD SHX Text
52.58'
AutoCAD SHX Text
4.12'
AutoCAD SHX Text
UNITS
AutoCAD SHX Text
CODE REQUIREMENT
AutoCAD SHX Text
REQUIRED
AutoCAD SHX Text
MEMORY CARE (NON-DRIVERS)
AutoCAD SHX Text
ASSISTED LIVING (SOME DRIVERS)
AutoCAD SHX Text
VISITORS
AutoCAD SHX Text
TOTAL
AutoCAD SHX Text
64
AutoCAD SHX Text
103
AutoCAD SHX Text
STAFF
AutoCAD SHX Text
20
AutoCAD SHX Text
0 SPACES
AutoCAD SHX Text
1 PER 3 DWELLINGS
AutoCAD SHX Text
1 PER 7 DWELLINGS
AutoCAD SHX Text
20
AutoCAD SHX Text
0
AutoCAD SHX Text
35
AutoCAD SHX Text
24
AutoCAD SHX Text
79
AutoCAD SHX Text
20
AutoCAD SHX Text
PROVIDED
AutoCAD SHX Text
86
AutoCAD SHX Text
PARKING SUMMARY
AutoCAD SHX Text
SETBACK SUMMARY
AutoCAD SHX Text
EXISTING
AutoCAD SHX Text
PROPOSED
AutoCAD SHX Text
LOT AREA
AutoCAD SHX Text
BUILDING COVERAGE
AutoCAD SHX Text
PAVED AREA
AutoCAD SHX Text
PERCENT IMPERVIOUS
AutoCAD SHX Text
4.12 Acres
AutoCAD SHX Text
31%%%
AutoCAD SHX Text
2.41 Acres
AutoCAD SHX Text
GRASS/LANDSCAPE AREA
AutoCAD SHX Text
0.43 Acres
AutoCAD SHX Text
AREA SUMMARY
AutoCAD SHX Text
90%%%
AutoCAD SHX Text
4.12 Acres
AutoCAD SHX Text
27%%%
AutoCAD SHX Text
1.78 Acres
AutoCAD SHX Text
1.22 Acres
AutoCAD SHX Text
70%%%
AutoCAD SHX Text
0
AutoCAD SHX Text
35
AutoCAD SHX Text
31
AutoCAD SHX Text
20
AutoCAD SHX Text
BUILDING AREA
AutoCAD SHX Text
1.28 Acres
AutoCAD SHX Text
1.12 Acres
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
03.21.17 Engineer & Fire Comments
dmcmillan
Typewritten Text
SITE PLAN AND PHOTOGRAPHS TAPESTRY WICKLIFFE WICKLIFFE, OHIO DATE: January 31, 2018
dmcmillan
Callout
1
dmcmillan
Callout
2
dmcmillan
Callout
3
dmcmillan
Callout
4
dmcmillan
Callout
5
dmcmillan
Callout
6
dmcmillan
Callout
7
dmcmillan
Callout
8
dmcmillan
Callout
9
dmcmillan
Callout
10
dmcmillan
Callout
11
dmcmillan
Callout
12
dmcmillan
Callout
13
dmcmillan
Callout
14
dmcmillan
Callout
15
dmcmillan
Callout
16
dmcmillan
Callout
17
dmcmillan
Callout
18
dmcmillan
Callout
30
dmcmillan
Callout
32
dmcmillan
Callout
33
dmcmillan
Callout
34
Page 132: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 1 of 17

1. Southeast corner of building

2. View looking west along south drive and parking area

Page 133: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 2 of 17

3. View looking north along rear parking and drive area

4. South elevation of building

Page 134: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 3 of 17

5. 1st floor common area in northeast corner of building

6. Underground MEP rough in area of 1st floor kitchen area

Page 135: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 4 of 17

7. West front elevation of building with new steel in place

8. View looking west out main entry

Page 136: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 5 of 17

9. Underground MEP rough in area of 1st floor kitchen area

10. 1st floor lobby/atrium area

Page 137: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 6 of 17

11. Exterior wall framing underway along north atrium wall

12. Exterior wall framing underway along north atrium wall

Page 138: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:42

Page 7 of 17

13. North elevation of building

14. Northeast corner of building

Page 139: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 8 of 17

15. View of north elevation of building

16. Northeast corner elevation of building

Page 140: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 9 of 17

17. View of north parking lot and drive area

18. View of rear parking and drive area

Page 141: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 10 of 17

19. 1st floor corridor in memory care area

20. 1st floor resident suite in memory care area

Page 142: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 11 of 17

21. 2nd floor corridor in assisted living area

22. 2nd floor resident suite in assisted living area

Page 143: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 12 of 17

23. 3rd floor corridor in assisted living area

24. 3rd floor resident suite in assisted living area

Page 144: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 13 of 17

25. 4th floor hallway in memory care area

26. Entry to 4th floor memory care resident suite

Page 145: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 14 of 17

27. 4th floor memory care suite

28. Tub/shower units for resident suites stored inside building

Page 146: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 15 of 17

29. 4th floor activity room

30. View of atrium/lobby area from 4th floor

Page 147: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 16 of 17

31. New elevator shaft at 4th floor

32. View of atrium/lobby area from 4th floor

Page 148: Tapestry Senior Living

2016-122: Tapestry Wickliffe, Wickliffe, OH

Photo ReportAll Reports

FacilityForecast® Technology and Software Patent PendingVersion: 5.5.12.0, Licensed User: SDM©1999-2016 FacilityForecast®, Inc. All rights reserved.

C:\Users\dmcmillan\Desktop\Monthly Projects\2016-122 Tapestry ...\2016-122M03 Pictures.fafPrinted: 11 Feb 2018 04:43

Page 17 of 17

33. View looking towards north and east side of building from entry drive from Euclid Ave

34. Front entry elevation of building


Recommended