+ All Categories
Home > Documents > Target Incentive

Target Incentive

Date post: 14-Apr-2018
Category:
Upload: sm-al-amoudi
View: 219 times
Download: 0 times
Share this document with a friend

of 90

Transcript
  • 7/30/2019 Target Incentive

    1/90

    Development of KPIs for the ElectricitySector in the Kingdom of Saudi Arabia

    Targets & Incentives Report

    Submitted to: Electricity & Co-generation Regulatory Authority of the

    Kingdom of Saudi Arabia

    Submitted by: KEMA International B.V., The Netherlands

    Arnhem 22 May 2009

  • 7/30/2019 Target Incentive

    2/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 2

    TABLE OF CONTENTS

    1 INTRODUCTION ....................................................................................................................................... 4

    1.1 BACKGROUND ........................................................................................................................................... 4

    1.2 REPORT OUTLINE ....................................................................................................................................... 4

    2 DEVELOPMENT KPI FRAMEWORK ............................................................................................................ 6

    2.1 IDENTIFICATION OF KPITARGETS .................................................................................................................. 7

    2.2 REGULATORY INCENTIVE MECHANISMS ............................................................. ............................................. 9

    2.3 SELECTION OF INCENTIVE MECHANISMS ....................................................................................................... 12

    3 GENERATION ......................................................................................................................................... 15

    3.1 KPIOVERVIEW ........................................................................................................................................ 15

    3.2 DEVELOPMENT OF TARGETS ....................................................................................................................... 16

    3.2.1 International Comparisons.............................................................................................................. 16

    3.2.2 Comparisons of power generation in Saudi Arabia versus International ........................................ 21

    3.2.3 Power Generation of SEC ................................................................................................................ 22

    3.2.4 Power Generation of Marafiq ......................................................................................................... 293.2.5 Power Generation of Saudi Aramco and SWCC .............................................................................. 32

    3.2.6 Summary of KPI Targets .................................................................................................................. 34

    3.3 INCENTIVE MECHANISMS........................................................................................................................... 35

    3.4 RECOMMENDATIONS GENERATION.............................................................................................................. 37

    4 TRANSMISSION ..................................................................................................................................... 39

    4.1 KPIOVERVIEW ........................................................................................................................................ 39

    4.2 DEVELOPMENT OF TARGETS ....................................................................................................................... 41

    4.2.1 International Comparisons.............................................................................................................. 41

    4.2.2 Comparisons Saudi versus International ......................................................................................... 42

    4.2.3 Conclusions ..................................................................................................................................... 44

    4.3 INCENTIVE MECHANISMS........................................................................................................................... 45

    4.3.1 Selection of Incentive Mechanism ................................................................................................... 45

    4.3.2 Incentive Mechanism Conclusions .................................................................................................. 49

    4.4 RECOMMENDATIONS TRANSMISSION ........................................................................................................... 50

    5 DISTRIBUTION ....................................................................................................................................... 51

    5.1 KPIOVERVIEW ........................................................................................................................................ 51

    5.2 DEVELOPMENT OF TARGETS ....................................................................................................................... 525.2.1 International Comparisons.............................................................................................................. 52

  • 7/30/2019 Target Incentive

    3/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 3

    5.2.2 Comparisons Saudi versus International ......................................................................................... 53

    5.2.3 Conclusions ..................................................................................................................................... 54

    5.3 INCENTIVE MECHANISMS........................................................................................................................... 55

    5.3.1 Selection of Incentive Mechanism ................................................................................................... 55

    5.3.2 Incentive Mechanism Conclusions .................................................................................................. 59

    5.4 RECOMMENDATIONS DISTRIBUTION ............................................................................................................ 61

    6 CUSTOMER SERVICE .............................................................................................................................. 63

    6.1 KPIOVERVIEW ........................................................................................................................................ 63

    6.2 DEVELOPMENT OF TARGETS ....................................................................................................................... 64

    6.3 INCENTIVE MECHANISMS........................................................................................................................... 666.4 RECOMMENDATIONS CUSTOMER SERVICE..................................................................................................... 67

    ANNEXES

    ANNEX 1: DATA FOR TRANSMISSION KPIs

    ANNEX 2: DATA FOR DISTRIBUTION KPIs

    ANNEX 3: DATA FOR CUSTOMER SERVICE KPIs

    ANNEX 4: PROCESS FOR SETTING LOCAL TARGETS

    ANNEX 5: DETERMINATION OF THE COST OF INTERRUPTIONS

  • 7/30/2019 Target Incentive

    4/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 4

    1 INTRODUCTION

    1.1 BACKGROUND

    The Electricity & Co-generation Regulatory Authority of the Kingdom of Saudi Arabia

    (hereafter ECRA) has initiated a project to develop Key Performance Indicators (KPIs) for

    the Saudi power sector. KEMA has been asked to assist ECRA in the implementation of the

    KPI project. The main objectives of this project are to develop KPIs for generation,

    transmission, distribution, and customer service.

    As part of this project, a KPI Report has been produced setting out the recommendations for

    the KPIs to be implemented. This Targets & Incentives Report builds further on the KPI

    Report and assesses the desired level for these KPIs in terms of performance targets. In

    doing so, use is made of internationally available datasets and comparable performance

    statistics.

    A distinction has been made between long-term (to be achieved in 6 years) and short-term

    targets (to be achieved in 3 years). The long-term target reflects the desired level of the KPI.

    However, one also needs to take into account the time frame required to improveperformance and therefore, for the short-run at least, it will not be practical to apply long-

    term targets. To bridge this gap, this report also makes recommendations on short-term

    targets, which act as an intermediate between the existing performance level and the future

    desired performance level.

    Once targets have been determined, the next step is to identify how deviations in

    performance relative to the target should be treated. A number of options exist for

    implementing such incentives. In this report we develop recommendations on the type of

    incentive approach which would best fit a given type of KPI. Also, where incentives are foundto be applicable, we provide recommendations on the size and limitations of such incentives.

    1.2 REPORT OUTLINE

    This Report is structured as follows:

    Chapter 2 presents a general overview of the conceptual background of deriving the targets

    for the different KPIs. Also, this chapter sets out the options for designing regulatory

    incentive mechanisms and the factors that would drive the choice for a particular approach.

  • 7/30/2019 Target Incentive

    5/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 5

    Chapters 3, 4, 5, and 6 respectively deal with the development of targets for the KPIs

    related to generation, transmission, distribution, and customer service. Each chapter starts

    with an overview of the KPIs that were selected and present the results of the international

    comparisons that have been performed in order to arrive at suitable targets. Further, each

    chapter assesses the preferred regulatory incentive mechanism to be used for inducing

    target performance.

  • 7/30/2019 Target Incentive

    6/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 6

    2 DEVELOPMENT KPI FRAMEWORK

    In developing a KPI framework there are three key issues that need to be considered. First,

    a selection of the performance areas to be included in the framework need to be identified

    and the performance indicators to be used for quantifying the utilitys performance should be

    selected. This issue has been the central theme for the KPI Report that has previously been

    produced and in which the final set of KPIs were recommended. An overview of the selected

    KPIs is provided in the following table.

    Table 2.1. Overview of KPIs to be included in the KPI Framework.

    Generation Transmission

    G1 Availability Factor (AF) T1 ENS

    G2 Forced Outage Factor (FOF) T2 SAIDI-T

    G3 Scheduled Outage Factor (SOF) T3 SAIFI-T

    G4 Equivalent Forced Outage Rate (EFOR) T4 MAIFI-T

    G5 Starting Reliability (SR) T5 Out100 km

    G6 Gross Capacity Factor (GCF) T6 Voltage Dips

    G7 Net Capacity Factor (NCF) T7 Network Losses

    Distribution Customer Service

    D1 SAIDI

    C1Average Time to Supply ExistingConnections (ATSE)D2 SAIFI

    D3 MAIFI

    C2Average Time to Supply NewConnections (ATSN)D4 Network Losses

    C3Average Time to Reconnect AfterPayment (ATRAP)

    C4 Notification of Interruption of Supply (NIS)

    C5 Frequency of Complaints (FC)

    C5 Frequency of Billing Complaints (FBC)

    C7Average Time to Resolve BillingComplaints (ATRBC)

    C8Average Waiting Time Call Center(AWTCC)

    The second issue is the identification of a proper target level performance for the selected

    KPIs. Thirdly and finally, there is the issue of choosing an appropriate regulatory incentive

    mechanism to induce the utility to reach the target performance level.

  • 7/30/2019 Target Incentive

    7/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 7

    This chapter deals with the two latter issues and approaches these from a conceptual point

    of view. The subsequent chapters 3 till 6 will deal with each of the four respective

    performance areas (generation, transmission, distribution, and customer service) and detail

    the issues in the context of the specific set ofKPIs.

    2.1 IDENTIFICATION OF KPI TARGETS

    Once the KPIs have been identified the next step is to formulate the desirable level of

    performance. This is expressed in terms of the targeted performance level for the KPI.Typically, for setting the target, regulators consider the historical performance of the utility

    and an assessment of this performance in, for example, a regional or international context.

    The general idea is that historical performance should be something that the utility is

    expected to achieve, however historic performance is not always necessarily the optimal

    performance level. Comparisons with (international) counterparts can provide useful

    information for the regulator in order to identify the potential for improvement and to

    formulate long-term targets which the utility should achieve. Starting from the historical

    situation, the utility is expected to gradually increase its performance towards this long-term

    target.

    Acknowledging the fact that performance improvement is difficult to achieve overnight, a

    distinction can be made between long-term and short-term targets. We recommend to apply

    6 years for the long-term target and 3 years for the short-term target.

    The short-term target acts as an intermediate performance target for the utility which should

    be achieved in 3 years. After this, the utility can improve further aiming towards the level of

    the long-term target in the next 3 years. The short-term target can thus be interpreted as the

    period of time considered reasonable for the utility to improve up to the final target. The

    expected performance level can be gradually increased each year over the duration of thetime-period in which the long-term target should be achieved.

    For identifying the KPI target we have selected the following approach based on the central

    limit theorem. This states that the distribution of a sum of many independent, identically

    distributed random variables tends towards the normal distribution theory of normal

    distributions. This is illustrated in Figure 2.1. The mean value is equal to the median value in

    a normal distribution and about 68% of the values are within 1 standard deviation of the

    mean (mathematically, , where is the arithmetic mean and is the standard

    deviation), about 95% of the values are within two standard deviations ( 2), and about

  • 7/30/2019 Target Incentive

    8/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 8

    99.7% lie within 3 standard deviations ( 3). This is known as the 68-95-99.7 rule or the

    empirical rule.

    The standard deviation () is defined as:

    =1/N (x I - )

    Figure 2.1 Overview of normal distributions

    It is common to define the following quartiles:

    first quartile (designated Q1) = lower quartile = cuts off lowest 25% of data = 25thpercentile ( 0.6745)

    second quartile (designated Q2) = median= cuts data set in half = 50th percentile

    third quartile (designated Q3) = upper quartile = cuts off highest 25% of data, orlowest 75% = 75th percentile ( + 0.6745 )

  • 7/30/2019 Target Incentive

    9/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 9

    For deriving the benchmark target, international data samples have been used. Information

    about performance of the sample is used as a reference to set the target. Even though one

    could opt for the best performing utility in the sample, this is generally problematic as

    sometimes this can be driven by data issues or the best utility simply being an outlier. On the

    other hand, the mean generally provides a more realistic indication of the target but at the

    same time, performance better than the mean should also be considered.

    A pragmatic approach is to focus on the so-called peer group which is defined as the

    companies that are located two quartiles around the mean outside the standard deviation ()

    as basis for setting the target. The principle is given in the following figure. This approach

    provides more robust information about the range where the target should be located. We

    should note however that the process of setting the target is not a mechanic one and will

    involve utilization of the consultants experience and knowledge.

    Statistical Analysis

    Quartile

    (25%)

    Performance Indicator

    Standard

    Methodology

    Data Base

    PeerG

    roup Quartile

    (25%)

    median

    Figure 3.2 Flow scheme of statistical analysis of Key Performance Indicators

    2.2 REGULATORY INCENTIVE MECHANISMS

    Once the KPI targets have been identified, the next step is to consider the methods that can

    be used to encourage the utility to achieve these targets. There are three main methods

    which such incentives can be provided namely; (1) performance publication, (2) minimum

    standards, and (3) penalty/reward schemes. These three methods are now described in

    more detail.

    Performance Publication

  • 7/30/2019 Target Incentive

    10/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 10

    Performance publication is when the regulator requires the company to disclose information

    about (trends in) its performance to the regulator and/or the general public. Overviews of the

    companys performance are reported to the regulator and published, for example, in the

    companys annual reports, in dedicated regulatory publications, or on the companys or

    regulators website.

    Performance publication is relatively simple to implement and does not require the regulator

    to develop a view on what should be an appropriate performance target. Such an approach

    can be useful in the case where the formulation of a meaningful target is difficult. Even

    through there are no financial incentives, the fact that the company is exposed by making

    public its performance already creates incentives to maintain a high level of performance.

    Overall Standards

    An overall standard relates to the performance of the utility averaged over all customers

    being served. Here, a minimum target level to be achieved is specified for a certain

    performance indicator. However, the utility is generally not exposed to any financial penalties

    in case of not meeting the targets. The idea of the overall standard is that the specification of

    a target level provides the utility with a tangible objective to achieve that is in line with

    regulatory expectations.

    Guaranteed Standards

    A guaranteed standard relates to the level of performance as experienced by the individual

    customer. Here, a minimum target level is specified by the regulator and consequently each

    customer is expected to be served according to this target. In the case that a particular

    customer is served at a sub-standard level, that customer becomes entitled to a financial

    compensation.

    Penalty/Reward Schemes

    Under a penalty/reward scheme, a more continuous relation is imposed between price and

    performance. Each performance level results in a financial incentive, which varies with the

    gap between actual performance level and some predefined target level. In case the

    company performs below the target, the incentive is a financial penalty, while if the company

    exceeds the target the incentive comes in the form of a financial reward. This financial

    incentive is proportional to the gap between the actual and targeted performance.

  • 7/30/2019 Target Incentive

    11/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 11

    Different types of penalty/reward schemes exist. Price and performance can be mapped

    continuously or in a discrete fashion, the level of the penalty or reward can be capped, dead

    bands may be applied, etc. Some examples are provided in Figure 2.2.

    Quality Level (q)

    Low High

    Reward

    Penalty

    1. Minimum Standard

    2. Continuous

    4. Dead Band

    3. Capped

    Financial Incentive ()

    Figure 2.2: Examples of penalty/reward schemes. The horizontal axis represents the actual

    performance, the vertical axis the financial incentive.

    Under the first scheme (minimum standard), after reaching a certain performance

    level, a fixed penalty is imposed. This is essentially an ordinary minimum standard.

    In the second example the continuous scheme there is a continuous relation

    between price and performance. For each level of performance, there is a

    corresponding penalty or reward which is proportional to the gap between actual and

    target performance.

    The third scheme is similar to the second but now with a cap on the level of penalty

    and reward. Essentially then, the scheme is only linear within a predefined band;

    outside this band, the scheme is similar to a minimum standard and has similar

    problems. If performance decreases beyond some minimum level, the penalty paid

    by the company does not increase further. Similarly, performance levels exceeding

    the maximum level would not generate any additional rewards to the firm.

    The fourth scheme has a dead band; performance variations within this band do not

    lead to financial consequences. The reason for this is to prevent shocks in the level

  • 7/30/2019 Target Incentive

    12/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 12

    of the financial incentive due to stochastic variations in performance. Stochastic

    effects can lead to performance fluctuations and consequently also a fluctuation in

    the level of penalties and rewards.

    2.3 SELECTION OF INCENTIVE MECHANISMS

    When comparing the different incentive mechanisms, we can note that the strength of the

    incentive is progressively increased when moving from performance publication to overall

    standards, then minimum standards, and finally penalty/reward schemes. At the same time

    however, the degree of complexity involved and the implementation costs and risks also

    increase. In the implementation of performance incentive mechanism a trade-off should thus

    be made between the effectiveness of the mechanism and its costs and risks.

    Table 2.2: Comparisons of the design and risks and costs of the different incentive

    mechanisms

    PerformancePublication

    OverallStandard

    GuaranteedStandard

    Penalty/RewardScheme

    Scheme characteristics

    PerformanceScope

    Average Average IndividualCustomer

    Average

    Target involved No Yes Yes Yes

    Penalty Involved No No Yes Yes

    Reward Involved No No No Yes

    Incentives and Risks

    Incentives Weak Moderate Strong Very Strong

    Financial Risks None None Yes Yes

    Implement. Costs Low Low High High

    Performance publication is the least complex option and in the context of this project, can be

    considered the default mechanism that will be applied to all KPIs. It is envisaged that once

    the KPI system has been implemented, ECRA will collect performance data of the

    companies on a regular basis and make this information available to the general public.

    An important limitation of performance publication is that there are no regulatory targetsdefined. Thus, even though information about performance is available, it is unclear as to

  • 7/30/2019 Target Incentive

    13/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 13

    which target performance this should be compared with. To overcome this limitation, the

    overall standard can be applied which does clearly promulgate the desired target level. In

    case of not meeting that target, no penalties are however involved in general and thus the

    utility is not f inancially exposed.

    Guaranteed standards are one step further and do expose the utility financially as they

    involve penalties to be paid to customers in the form of compensation payments. An

    important characteristic of guaranteed standards thus is that they provide direct benefits to

    customers who experience low performance levels. This however also involves higher

    administrative costs.

    Finally, the penalty/reward scheme imposes a more direct link between performance and

    financial outcome as well as the possibility of symmetric incentives. That is both inferior as

    superior performance lead to financial incentives in the form of penalties or rewards

    respectively.

    An important question is the type of incentive mechanism ECRA should adopt for each of the

    selected KPIs. As mentioned, performance publication can be considered the default

    approach and where targets can be clearly specified, this can be extended into overall

    standards. The question however is whether it is desirable to move further into the directionof guaranteed standards and then further to penalty/reward schemes. Doing so would

    introduce an element of risk to the utility and also lead to a higher regulatory burden. If, for

    some reason, the company is not able to meet the target levels, this can trigger high

    penalties and could cause financial trouble. Such a situation may occur if the standard level

    is set at too high a level or if performance levels have a stochastic nature with large

    fluctuations around the average performance over time.

    Clearly, the introduction of financial risks would need to be justified by the expected benefits

    from implementing more intrusive schemes as opposed to only performance publication or

    overall standards. If the latter two mechanisms would be expected to provide sufficient

    assurance on their own in that performance will be high, it is probably not worth opting for

    more complex schemes, as these are more difficult to implement and administer and also

    they introduce an element of financial risk for the utility. In particular if the existing price-

    control regime is not very focused on cost reductions, regulators generally have no real

    concern that performance will be low.

    For example, under rate-of-return systems where the utility is assured of a sufficiently high

    remuneration, there is no natural incentive to cut costs on performance. In contrast, under

    so-called cap regulation there are very strong incentives to cut costs and some of this can

    come at the expense of performance degradation. In such circumstances, the use of stricter

  • 7/30/2019 Target Incentive

    14/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 14

    effective means of regulatory incentive mechanisms can then be justified. Simply stated,

    regulators are more willing to take the risks of introducing more complex and intrusive

    mechanisms if there are sufficient concerns that the utility will not improve performance on

    its own or that performance may even be reduced.

    In this report, in the following respective chapters, recommendations have been developed

    on the most appropriate incentive mechanism to be applied for each of the selected KPIs. In

    doing so, we have taken into consideration the existing and future state of affairs regarding

    the regulation of the Saudi power sector. This information has been combined with our

    experience from other countries and is used to formulate what we believe is an appropriate

    and balanced choice of incentive mechanisms for the different KPIs under consideration.

  • 7/30/2019 Target Incentive

    15/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 15

    3 GENERATION

    3.1 KPI OVERVIEW

    Based on discussions with the different stakeholders of the electricity sector in Saudi Arabia

    a list of KPIs for the generation sub-sector was selected. We believe these are relevant for

    ECRA to include in its KPI measurement framework. In developing our recommendations,

    we have taken into account the fact that the generation market in Saudi Arabia is currently

    not liberalized. It therefore becomes more important and relevant to include certain

    indicators that would not be considered so important in liberalized markets.

    The following table provides an overview of our recommended KPIs. All KPIs are to be

    measured on an annual basis and reported, by each relevant utility, on an aggregated basis

    per technology (Simple Cycle (SC), Steam Cycle, Combined Cycle (CCGT), Diesel

    Generator (DG) and Cogeneration) and for each administrative region. Note however that at

    this point in time, the data received from the utilities is not available at administrative region

    level but only by operational area.

    Table 3.1 Recommended KPIs for Generation.

    Generation KPI Unit Target Level Freq.

    G1 Availability Factor (AF) % Yes

    Per Admin

    Region and

    per

    Technology

    Annual

    G2 Forced Outage Factor (FOF) % Yes

    G3 Scheduled Outage Factor (SOF) % No

    G4 Equivalent Forced Outage Rate (EFOR) % Yes

    G5 Starting Reliability (SR) % Yes

    G6 Gross Capacity Factor (GCF) % No

    G7 Net Capacity Factor (NCF) % No

    In the table it is also indicated for which KPI s it will be practical to apply a target and for

    which it is not. It should also be noted that the targets are not projected to be applied for

    cogeneration plants where steam and water production rather than electricity production is

    leading. For instance the design capacity, location and operation of Saudi Aramco and

    SWCC plants are determined based on the steam requirements for hydrocarbon facilities

  • 7/30/2019 Target Incentive

    16/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 16

    and desalination facilities. Thus power generation and dispatching criteria for these

    cogeneration units will not be subject to any form of dispatching and scheduling instructions

    by the system operator.

    In addition to the above KPI list, there is some supporting information that would need to be

    collected for the purpose of cross-checking. These are shown in the following table.

    Table 3.2 Supporting information to be collected for Generation.

    Data Unit Target Level Freq.

    Service Factor (SF) % No

    Gross Maximum Capacity (GMC) MW NoPer Admin

    Region and

    per

    Technology

    Annual

    Net Maximum Capacity (NMC) MW No

    Gross Actual Generation (GAG) MWh No

    Net Actual Generation (NAG) MWh No

    Gross Annual Heat Rate (GAHR) BTU/kWh No

    3.2 DEVELOPMENT OF TARGETS

    3.2.1 International Comparisons

    The KPIs for which a target is projected will be based on the comparison with international

    peer groups. In order to assure comparability, the peer group was selected for different sub-

    groups, consisting of units of similar technologies, similar capacity ranges and similar fueltypes as in Saudi Arabia. The following KPIs was investigated and compared with

    international values of peer groups:

    Availability Factor (AF);

    Forced Outage Factor (FOF);

    Starting Reliability (SR);

    Equivalent Forced Outage Rate (EFOR).

  • 7/30/2019 Target Incentive

    17/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 17

    Targets of these KPIs will be derived for the long term and short term based on

    comparisons with the values of the peer groups and utilization of the consultants experience

    and knowledge.

    The data base of NERC-GADS (Generation Availability Data System) was used to carry out

    the statistical analysis of key performance indicators of the different peer groups. This

    NERCGADS reporting system, initiated by the electric utility industry in 1982, maintains

    complete operating histories on more than 5000 generating units representing 72% of the

    installed generating capacity in the United States supplemented by other units in Canada

    and in other parts of the world.

    The NERC-GADS system is using clearly defined indicators according to the IEEE-762

    definitions and is fully in line with the definitions used in the KPI-Report. Before selecting the

    different peer groups it is important to compare the dispatch of different units of the peer

    group of the NERC-GADS and the units in Saudi Arabia. Peaking units will have other

    operational characteristics and requirements than base load units. A comparison is made in

    the following table.

    Table 3.3 Characteristics of peaking, cycling and base load units

    Peaking Cycling Base load

    Starting reliability High High Low

    Running reliability Low Medium Very High

    Thermal efficiency Low Medium Very high

    O&M costs High Medium Low

    Base load units require low O&M costs, high efficiency (low fuel costs) and a high operating

    reliability. This implies a high availability factor and low forced outages.

    Peaking units will have low operational hours, which implies that the efficiency of these units

    is less important. Peaking units require a high starting reliability because these units must

    ramp-up very quickly. Peaking units will have a low capacity factor. Simple cycles are

    normally used as peaking units.

  • 7/30/2019 Target Incentive

    18/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 18

    It should be noted that the NERC-GADS sample for simple cycle units represents low

    service factors and low net capacity factors and this implies that the NERC-GADS data base

    for simple cycle units is a group of peaking units. For this reason the service factor and the

    net capacity factor was investigated from the NERC-GADS data base and this was

    compared with the units of SEC.

    The capacity factor is related to the dispatch of the unit; in very simple terms it shows the

    extent to which the generator is used. A high capacity factor implies that the unit is used as

    base load unit while a low capacity factor indicates that a unit is used as peak load unit.

    Table 3.4 Net Capacity Factor (NCF) and weighted Service Factor (SF) of different technologiesin Saudi Arabia compared to peer group

    Technology NCF of SEC

    units in 2007

    NCF (median of

    peer group

    Weighted SF

    of SEC units

    in 2007

    SF (median

    peer group)

    Simple cycle 38 2 58 2

    Steam cycle 72 19 78 50

    Combined cycle 57 24 71 35

    Diesel Generator 17 6 35 9

    From this table it can be concluded that the simple cycle units of SEC in Saudi Arabia are

    used as base load units and probably also as peaking units.

    According to General Electric

    1

    it turns out that using FOR (Forced Outage Rate) and EFOR(Equivalent Forced Outage Rate) creates an unrealistic, optically poor, misleading

    measurement for simple cycle units used as peak load units. The main reason is that there is

    no credit for available standby reserve time; and worse, all forced outage hours (nights,

    weekends, holidays, unapplied time etc.) are counted. The gas turbine industry is focused on

    the FOF (Forced Outage Factor) instead of EFOR. The simple cycle units of SEC have a

    service factor and a capacity factor that is comparable with base load units and this means

    that EFOR and FOR data of the simple cycle units in the NERC-GADS data base (peaking

    1GE Power Systems, Predicted Reliability, Availability, Maintainability for the General Electric 7H gas turbine,

  • 7/30/2019 Target Incentive

    19/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 19

    units) cannot be compared with the data of simple cycle units (base load units) in Saudi

    Arabia. Unfortunately, NERC separates simple cycle plants from combined cycle plants and

    does not separate out the gas turbine portion of the combined cycle plants.

    As a first conservative approach we propose to use the equivalent forced outage rate of the

    peer group of combined cycles for simple cycle units that are used as base load and cycling

    units. For instance 2/3 of the capacity of combined cycles is contributed by gas turbines.

    Combined cycles in the range of (50-125 MW) are corresponding to gas turbines in the

    range of 30-90 MW. It is well known that gas turbines contribute significantly to forced

    outages in combined cycles due to the complicated technology that is sensitive to forced

    outages.

    The results of the statistical analysis of the different peer groups are given in next tables

    Table 3.5 Overview of quartile spread of weighted availability factor of different peer groups

    Weighted Availability factor (%)

    Technology-Peer group Q1 Median Q3

    Simple cycle (10-125 MW) 83.6 91.2 95.4

    Steam plant (100-700 MW 79.4 86.4 90.9

    Combined cycle (100-500 MW) 86.2 90.5 95.0

    Diesel generator (2-35 MW) 93.4 98.9 99.8

    Table 3.6 Overview of quartile spread of weighted forced outage factor of different peer groups

    Weighted Forced Outage Factor (%)

    Technology-Peer group Q1 Median Q3

    Simple cycle (10-125 MW) 5.4 2.0 0.8

    Steam plant (100-700 MW 4.4 2.2 1.2

    Combined cycle (100-500

    MW)

    4.3 1.6 0.5

  • 7/30/2019 Target Incentive

    20/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 20

    Diesel generator (2-35 MW) 0.5 0.1 0.01

    The starting reliability is much more important for peaking units than for base load units

    because peak load have to ramp up very quickly in case of forced outages of the units. If a

    unit has many starting problems this may also lead to frequency and voltage changes in the

    system. Simple cycle units are often used as peaking units and therefore the statistical

    analysis of starting reliability will be only carried out for simple cycle units.

    Table 3.7 Overview of quartile spread of starting reliability of different peer groups

    Starting Reliability (%)

    Technology-Peer group Q1 Median Q3

    Simple cycle (10-125 MW) 93.5 98.4 100

    Units can be derated due to forced or planned outage. It is very common for a unit to be

    partially derated due to technical problems. The equivalent outage factor refers to the

    conversion of partial outages including capacity constraints to equivalent full outages. For

    this reason the equivalent forced outage rate is defined. The disadvantage is that the

    equivalent forced outage rate is more difficult to calculate and this may lead to

    misunderstandings if the definitions are not correctly applied or if some data are not

    available.

    The next table presents the median value of the equivalent forced outage rate of differentpeer groups.

    Table 3.8 Overview of quartile spread of weighted equivalent forced outage rate of different

    peer groups

    Weighted Equivalent Forced Outage Rate

    Technology-Peer group Q1 Median Q3

  • 7/30/2019 Target Incentive

    21/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 21

    Simple cycle (10-125 MW)

    Peer group of NERC-GADS

    Combined cycle (50-125 MW)

    9.5 4.0 1.8

    Steam plant (100-700 MW 14.0 6.9 3.4

    Combined cycle (100-500 MW) 15.4 6.5 2.0

    Diesel generator (2-35 MW) 12.0 5.1 1.4

    The presented equivalent forced outage rate of the peer group for simple cycles (4.0) is in

    line with the weighted EFOR as reported by ISO New England for gas turbines23.

    From the statistical analysis it can be concluded that the availability factors and forced

    outage factors of simple cycles and combined cycles do not differ substantially. The main

    reason is that the gas turbine in combined cycles is the most advanced and complicated

    equipment and therefore sensitive to forced outages.

    3.2.2 Comparisons of power generation in Saudi Arabia versus International

    The key performance indicators were investigated based the information received from SEC,

    Marafiq, Saudi Aramco and SWCC. Key performance indicators per unit and per group of

    units were received from the different companies were compared with the statistical values

    of the KPIs of the different peer groups Simple Cycle (SC), Steam Cycle (ST), Combined

    Cycle (CCGT), Diesel Generator (DG) and Cogeneration (COGEN).

    Data of SEC were obtained per operating area:

    Central Operational Area (COA)

    Eastern Operational Area (EOA)

    Southern Operational Area (SOA)

    Western Operational Area (WOA)

    Note that in future, data will need to be reported per administrative region.

    22 Interim Review of Resource Adequacy, ISO New England, 2005

  • 7/30/2019 Target Incentive

    22/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 22

    3.2.3 Power Generation of SEC

    3.2.3.1 Availability factor

    The weighted availability factors of the generation units in different areas of SEC were

    compared with the median values of the peer group. The weighted availability factors of the

    simple cycle units in WOA and COA were lower than the median value of the peer group.

    The weighted availability factor of simple cycle units in EOA and in SOA were almost equal

    to median value of the peer group.

    Weighted Availability Factor- SC

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007 2008

    Year

    WAF(%) WOA

    COA

    EOA

    SOA

    median value of peer group

    Figure 3.1 Weighted availability factor of simple cycle units of SEC compared to a peer group

    The weighted availability factor of steam cycles in WOA was lower than the median value of

    the peer group and the weighted availability factor in EOA was equal to the median value

    (See Figure 3.2).

  • 7/30/2019 Target Incentive

    23/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 23

    Weighted Availability Factor- Steam Cycle

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007 2008

    Year

    WAF(%)

    WOA

    EOA

    median value of peer group

    Figure 3.2 Weighted availability factor of steam cycle units of SEC compared to a peer group

    The weighted availability factors of the combined cycles operating in COA and WOA were

    low compared to the median value of the peer group (see Figure 3.3).

    Weighted Availability Factor- CCGT

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007 2008

    Year

    WAF(%)

    WOA

    COA

    median value of peer group

    Figure 3.3 Weighted availability factor of combined cycle units of SEC compared to a peer

    group

  • 7/30/2019 Target Incentive

    24/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 24

    Weighted Availability Factor- DG

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007 2008

    Year

    WAF(%)

    EOA

    SOA

    median value of peer group

    Figure 3.4 Weighted availability factor of diesel generators of SEC compared to a peer group

    From Figure 3.4 it can be concluded that the weighted availability factor of diesel generators

    in SOA was lower than the median value of the peer group and in EOA equal to the median

    value of the peer group.

    3.2.3.2 Forced outage factor

    The weighted forced outage factors of the generation units of SEC were compared with the

    median values of the peer group. (See Figures 3.5-3.8)

    Weighted Forced Outage Factor- SC

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    2005 2006 2007 2008

    Year

    WFOF(%) WOA

    COA

    EOA

    SOA

    median value of peer group

    Figure 3.5 Weighted forced outage factor of simple cycle units of SEC compared to a peer

    group

  • 7/30/2019 Target Incentive

    25/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 25

    Weighted Forced Outage Factor- Steam Cycle

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    2005 2006 2007 2008Year

    WFOF(%)

    WOA

    EOA

    median value of peer group

    Figure 3.6 Weighted forced outage factor of steam cycle units of SEC compared to a peer

    group

    Weighted Forced Outage Factor- CCGT

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    2005 2006 2007 2008

    Year

    WFOF(%)

    WOA

    COA

    median value of peer group

    Figure 3.7 Weighted forced outage factor of combined cycle units of SEC compared to a peer

    group

  • 7/30/2019 Target Incentive

    26/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 26

    Weighted Forced Outage Factor- DG

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    2005 2006 2007 2008

    Year

    WFOF(%)

    EOA

    SOA

    median value of peer group

    Figure 3.8 Weighted forced outage factor of diesel generators of SEC compared to a peer

    group

    From these figures it can be concluded that:

    The weighted forced outage factors for simple cycles and combined cycles in COA

    were higher than the median value of the peer group;

    The weighted forced outage factor for simple cycles and combined cycles in WOA

    were lower than the median values of the peer group;

    Steam cycles in all relevant operating areas have a lower weighted forced outage

    factor than the median value of the peer group;

    Diesel generators in EOA and SOA have a higher weighted forced outage factor than

    median value of the peer group.

    3.2.3.3 Starting reliability

    The starting reliability of peaking units was compared to the values of the peer group. From

    Figure 3.9 it can be concluded that the starting reliability of the simple cycle units in SOA is

    substantially lower than in other regions. The starting reliability of all other units is close to

    the median value of the peer group.

  • 7/30/2019 Target Incentive

    27/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 27

    Starting Reliability- SC

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007 2008

    Year

    SR(%)

    WOA

    COA

    EOA

    SOA

    median value of peer group

    Figure 3.9 Starting reliability of simple cycle units of SEC compared to a peer group

    3.2.3.4 Equivalent forced outage rate

    Equivalent forced outage rates were recently implemented by SEC and for that reason SEC

    could only provide data of each quarter of the year 2008. It should be noted that the south

    operating area (SOA) was not able to submit data on equivalent forced outage rate onsimple cycles and diesel generators at this moment. The equivalent forced outage rate of the

    peer group was compared for the different technologies in the year 2008.

    Weighted Equivalent Forced Outage Rate- SC

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    1Q-2008 2Q-2008 3Q-2008 4Q-2008

    Quarter of Year 2008

    WEFO

    R(%)

    WOA

    COA

    EOA

    median value of peer group

    Figure 3.10 Weighted equivalent forced outage rate of simple cycle units of SEC

    compared to a peer group

  • 7/30/2019 Target Incentive

    28/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 28

    Weighted Equivalent Forced Outage Rate- Steam Cycle

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    1Q-2008 2Q-2008 3Q-2008 4Q-2008Quarter of year 2008

    WEFOR(%)

    WOA

    EOA

    mean value of peer group

    Figure 3.11 Weighted equivalent forced outage rate of steam cycle units of SEC compared to a

    peer group

    Weighted Equivalent Forced Outage Rate-CCGT

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    1Q-2008 2Q-2008 3Q-2008 4Q-2008

    Quarter of year 2008

    WEFOR(%)

    WOA

    COA

    median value of peer group

    Figure 3.12 Weighted equivalent forced outage rate of combined cycle units of SEC compared

    to a peer group

  • 7/30/2019 Target Incentive

    29/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 29

    Weighted Equivalent Forced Outage Rate- DG

    0.0

    10.0

    20.0

    30.0

    40.0

    50.0

    1Q-2008 2Q-2008 3Q-2008 4Q-2008

    Quarter of year 2008

    WEFOR(%)

    EOA

    mean value of peer group

    Figure 3.13 Weighted equivalent forced outage rate of diesel generator units of SEC compared

    to a peer group

    From these figures it can be concluded that the weighted equivalent forced outage rates of

    simple cycles of SEC in COA and EOA and diesel generators of SEC in EOA were higher

    than the median vales of the peer group. The weighted equivalent forced outage rates of

    simple cycles of SEC in WOA were considerable lower than the median values of the peer

    group. For combined cycles and steam cycles, the weighted equivalent forced outage rates

    were much lower than the median values of the peer group.

    3.2.4 Power Generation of Marafiq

    Marafiqs core business is the operation, maintenance, management, expansion and

    construction of power and water systems to provide essential utility services to industrial,

    commercial and residential customers in the industrial cities of Jubail and Yanbu. The power

    generation units are consisting of steam cycles fuelled with HFO and of gas turbines

    provided with heat recovery steam generators to produce steam for desalination plants.

    Each heat recovery steam generator can receive exhaust gases from only one gas turbine

    while the other gas turbine is either operating in simple cycle mode or on standby. It was

    agreed that the gas turbines have to be considered as simple cycles and not as co-

    generation units.

    3.2.4.1 Availability factor

    Gas turbines were considered as simple cycle units and the weighted availability factor ofthe gas turbines units were compared with the median value of the peer group. From figure

  • 7/30/2019 Target Incentive

    30/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 30

    3.14 it can be seen that the weighted availability factor of simple cycle units is equal tomedian value of the peer group.

    Weighted Availability factor-SC

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007

    Year

    WAF(%)

    Marafiq

    median value of peer group

    Figure 3.14 Weighted availability factor of simple cycle units of Marafiq compared to

    a peer group

    The weighted availability factor of steam cycles of Marafiq is lower than the median value of

    the peer group.

    Weighted Availability Factor-Steam Cycle

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007

    Year

    WAF(%)

    Marafiq

    median value of peer group

    Figure 3.15 Weighted availability factor of steam cycle units of Marafiq compared to

    a peer group

  • 7/30/2019 Target Incentive

    31/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 31

    3.2.4.2 Forced outage factor

    The forced outage factor of the units of Marafiq was compared to the median value of the

    peer group. (See Figure 3.16 and Figure 3.17)

    Weighted Forced Outage Factor-SC

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    2005 2006 2007

    Year

    WFOF

    (%)

    Marafiq

    median value of peer group

    Figure 3.16 Weighted forced outage factor of simple cycles of Marafiq compared to

    a peer group.

    Weighted Forced Outage Factor-Steam Cycle

    -

    1.0

    2.0

    3.0

    4.0

    5.0

    2005 2006 2007

    Year

    WFOF(%)

    Marafiq

    median value of peer group

    Figure 3.17 Weighted forced outage factor of steam cycle units of Marafiq compared

    a peer group.

    From these figures it can be concluded that the forced outage factors of simple cycles and of

    steam cycles are lower than the median value of the peer group.

  • 7/30/2019 Target Incentive

    32/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 32

    3.2.4.3 Starting reliability

    The starting reliability is important for the simple cycle units because these units are acting

    as peaking units. The starting reliability of the simple cycles is lower than the median value

    of the peer group. The reason for this low starting reliability is the decreasing quality of the

    fuel and the fluctuating quality of the fuel.

    Starting Reliability-SC

    50.0

    60.0

    70.0

    80.0

    90.0

    100.0

    2005 2006 2007

    Year

    SR(%)

    Marafiq

    median value of peer group

    Figure 3.18 Starting reliability of simple cycle units of Marafiq compared to a peer

    group.

    3.2.5 Power Generation of Saudi Aramco and SWCC

    The power generation units of Saudi Aramco and SWCC are cogeneration units producing

    besides steam for the hydrocarbon facilities and desalination facilities also electricity. In

    these types of units the production of steam and water is leading and electricity isconsidered as by-product. The design capacity, location and operation of these plants are

    based on the steam requirements. The dispatching criteria for these cogeneration units are

    not subject to any form of dispatching and scheduling instructions by the system operator.

    Data were received from Saudi Aramco and SWCC. It should be noted that a complete set

    of data was only available of the year 2007. Data of previous years were not complete.

    Moreover, data of Yanbu and Riyadh refinery of Saudi Aramco were not available and were

    not incorporated in the figures below.

  • 7/30/2019 Target Incentive

    33/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 33

    The availability factor and forced outage factor was investigated based on the data received

    and the results are plotted in next figures.

    Weighted Availability Factor

    75.0

    80.0

    85.0

    90.0

    95.0

    100.0

    WAF

    (%)

    Saudi Aramco

    SWCC

    Figure 3.19 Weighted availability factors of cogeneration units of Saudi Aramco and SWCC

    in Saudi Arabia

    Weighted Forced Outage Factor

    -

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    WFOF(%)

    Saudi Aramco

    SWCC

    Figure 3.20 Weighted forced outage factor of cogeneration units of Saudi Aramco and

    SWCC in Saudi Arabia

  • 7/30/2019 Target Incentive

    34/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 34

    3.2.6 Summary of KPI Targets

    Targets for cogeneration units (Saudi Aramco, SWCC) cannot be applied because steam

    production for hydrocarbon facilities and desalination facilities are business driving factors

    instead of electricity. For this reason we will focus the targets on those units where electricity

    is the main product.

    Based on the results the following targets for the short term can be determined for the

    different technologies.

    Table 3.9 Short term targets for KPIs in generation.

    KPI (Weighted) Simplecycle(SC)

    Steamcycle(ST)

    Combinedcycle

    (CCGT)

    Dieselgenerator

    (DG)

    Weighted Availability Factor (WAF) > 85% > 85% > 85% >93%

    Weighted Forced Outage Factor (WFOF) < 4%

  • 7/30/2019 Target Incentive

    35/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 35

    Long term targets which are based on the median values of the different peer groups. It

    should be noted that the peer groups will also improve the operational aspects such as

    availability and forced outages in the coming years as a result of investments in efficient

    technologies and reducing operational & maintenance costs. This implies that long term

    targets have to change as a result of a continuous improvement of the availability and

    decrease of the forced outage of power generation plants.

    Table 3.10 Long term targets for KPI's in generation.

    KPI (Weighted)Simplecycle(SC)

    Steamcycle(ST)

    Combinedcycle

    (CCGT)

    Dieselgenerator

    (DG)

    Weighted Availability Factor (WAF) > 90% > 85% > 90% >95%

    Weighted Forced Outage Factor(WFOF)

  • 7/30/2019 Target Incentive

    36/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 36

    not apply penalties or awards in fully liberalized markets for generators. Rather, the

    incentives for high performance are inherently present and/or are contained in Power

    Purchasing Agreements (PPAs). In Saudi Arabia, a Single Buyer system is envisaged to be

    implemented in the near future which will also be accompanied by a (updated) set of PPAs.

    The basic information contained in a Power Purchase Agreement includes the following

    items:

    Definitions

    Purchase and Sale of Contracted Capacity and Energy (such as steam, hot water

    and/or chilled water in the case of cogeneration and trigeneration plants

    Operation of the Power Plant

    Guarantees of Performance

    Penalties

    Payments

    Force Majeure

    Default and Early Termination

    Liquidated damages

    Miscellaneous

    The PPAs also prescribe the performance targets to be met by the generator and the

    penalties applicable in case of under-performance. In this light, the application of regulatory

    penalties will be less desirable. Nevertheless, the targets for the various KPIs formulated

    here can act as a useful reference.

    Furthermore there is often performance standards (unit availability) tied to rewards orpenalties for meeting the availability criteria. In PPAs sometimes penalties are applied for

    de-rating due to the difference, if any, between the dependable capacity, as measured by a

    test (being either an acceptance test or a dependable capacity test, as the case may be),

    and contract capacity, such difference is defined as deficit capacity.

    The penalty mechanism in PPAs is typically used as tools to safeguard the availability of

    power plants. Penalties are depending on the requirements of buyer of the electricity. The

    buyer may require a high availability and low forced outages. High requirements of the buyer

    regarding availability and forced outages will result in the higher operational andmaintenance costs and thus in higher tariffs.

  • 7/30/2019 Target Incentive

    37/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 37

    As an example the Power and Water Purchase Agreement for a 2,600 MW and 55 MIGD in

    Ras Laffan C in Qatar is given. In this PPA, there are stringent values for forced outages and

    availability. For instance penalties will be applied if capacity is reduced in a given period with

    be more than 4%. These penalties will depend on the period of a year. Penalties in summer

    time will be higher than in winter time in the Middle East.

    In conclusion, for generation, our recommendation is not to apply any penalty regimes but

    rather limit regulatory incentives to the publication of performance as compared to the

    targets. These targets can be formulated in terms of overall standards that indicate the

    desired minimum level of performance however without imposing any penalties in case of

    sub-standard performance.

    3.4 RECOMMENDATIONS GENERATION

    We summarize the recommendations with respect to the targets and incentive mechanisms

    for generation in the following table.

  • 7/30/2019 Target Incentive

    38/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 38

    Table 3.11. Summary of recommendations regarding targets and incentive mechanisms forGeneration. SC=Simple Cycle, ST=Steam Cycle, CCGT=Combined Cycle, DG= Diesel

    Generator.

    KPI (Weighted) Short-Term Targets Long-Term TargetsIncentive

    Mechanism

    SC ST CCGT DG SC ST CCGT DG

    G1: WeightedAvailabilityFactor (WAF)

    > 85% > 85% > 85% >93% > 90% > 85% > 90% >95%Overall

    Standard,No penalty

    G2: WeightedForced OutageFactor (WFOF)

    < 4%

  • 7/30/2019 Target Incentive

    39/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 39

    4 TRANSMISSION

    4.1 KPI OVERVIEW

    Based on discussions with the different stakeholders of the electricity sector in Saudi Arabia

    a list of KPIs for the Transmission sub-sector was selected that we believe is relevant for

    ECRA to include in its KPI measurement framework. The following table provides an

    overview of the recommended KPIs for transmission. All KPIs are measured on an annual

    basis and reported, by each relevant utility. Since SEC Transmission supplies at voltage

    levels down to 13.8 kV and the peer group consist of transmission utilities (voltages above

    50 kV), the KPIs related to interruptions are limited to the voltage levels above 50 kV,

    namely 69 kV, 110 kV, 115 kV, 230kV, 380 kV.

    Table 4.1 Recommended KPIs for Transmission.

    Transmission KPI Unit Target Freq.

    T1Energy Not Supplied

    (ENS)

    % Yes Voltage Level:

    69 kV, < 69 kV

    Type: Planned,

    Unplanned,

    Generation,

    Force MajeureAnnual

    T2 SAIDI-T Min/year No

    T3 SAIFI-T Int/year No

    T4 MAIFI-T Int/year No

    T5Out100km

    Outages/ye

    ar per 100

    km

    No

    T6 Voltage Dips Nr/year NoTotal, Affecting

    load

    T7 Network Losses % No System

  • 7/30/2019 Target Incentive

    40/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 40

    The KPIs related to interruptions and voltage dips should also be broken down into four

    types: Planned, Unplanned, Generation, Force Majeure8.

    In case of tie-lines between two utilities, the Consultant suggests that the contribution to the

    KPI (that is the duration, frequency and energy lost) related to the tie-line to be divided by

    two and share among the companies.

    In addition to the above KPI list, there is some supporting information that would need to be

    collected for the purpose of cross-checking or for calculation of other indices. These are

    shown in the following table.

    Table 4.2 Supporting information to be collected for Transmission

    Data Unit Level Frequency

    Energy Injected GWh Two classes of voltage levels:

    69380 kV and < 69 kV

    Annual

    Energy Supplied GWh Two classes of voltage levels:

    69380 kV and < 69 kV

    Annual

    Peak Power MW Global (delivered to the

    transmission network)

    Annual

    Date and time of the

    peak power

    Date, time Global Annual

    Length of networks km Two classes of voltage levels:

    380 kV and below 380 kV

    Annual

    Number of Delivery

    Points

    Nr Two classes of voltage levels:

    69380 kV and < 69 kV

    Annual

    Nb of Voltage Dips

    That Reduced Load

    Nr Two classes of voltage levels:

    69380 kV and < 69 kV

    Annual

    8For SEC T, if a fault occurs at distribution, it may be the case that the distribution operator closes the

    breaker that tripped while the fault is still there and as a consequence, the main breaker in

    transmission trips, causing a large interruption to many customers (this consist in a human error). In

    that case, the behaviour has been out of control of the transmission company and should be classified

    as Force Majeure.

  • 7/30/2019 Target Incentive

    41/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 41

    4.2 DEVELOPMENT OF TARGETS

    4.2.1 International Comparisons

    The regulatory request for monitoring the continuity performance is relatively recent for both

    transmission and distribution activities. This regulatory process started out by using the data

    collected by the utilities with their own criteria and rules for measurement and calculation.

    Consequently there is remains little harmony in the monitoring of continuity performance

    around the world.

    Some efforts for progressive harmonization are however ongoing, notably in Europe with the

    Council of European Energy Regulators (CEER) and European Regulators' Group for

    Electricity and Gas (ERGEG). When comparing globally all countries, the diversity of the

    transmission contexts and their supply continuity results makes the drafting of a conclusion a

    delicate process. On the opposite, when focusing on those countries having set up a

    regulatory process for improving the continuity performance, there is more ground for

    launching a comparison process.

    Comparing does not mean that all values are expected to be equal: this is why even a long

    term target is not proposed to be at the level of the best continuity performance but rather atthe level of an average continuity performance. Also, depending on the societal cost of the

    non-continuity (often expressed by the value of the Energy Not Supplied, in currency per

    kWh), a target can be set higher or lower.

    The following tables consist of data from the most recent years of availability9.

    Table 4.3 Overview of quartile spread of Transmission KPIS of different countries (for later

    comparison with Saudi Arabia values). Note that only ENS will be provided a target.

    KPI Q1 Median Q3

    T1: ENS 0.00015% 0.0005% 0.0012%

    T2: SAIDI-T (min) 0.8 2.1 2.6

    T3: SAIFI-T 0.04 0.06 0.09

    T4: MAIFI-T (values for T&D) 0.07 0.85 6.0

    9As a consequence, some data may refer to different years.

  • 7/30/2019 Target Incentive

    42/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 42

    T5: Outages100km n.a. n.a. n.a.

    T6: Nr Voltage Dips 77 146 257

    T7: Network losses (%) 2.9% 4.8% 6.85%

    n.a.: not available

    Targets for transmission KPIs will only apply to ENS. The international statistics on this KPI

    come from a set of statistics issued by the CEER 3 rd Benchmarking report dealing with

    transmission only for 9 countries. The list of other KPIs (without target) has been prepared

    from a set of 7 countries (for SAIFI-T and MAIFI-T) and 11 countries (for SAIDI-T). The

    annexes contain the raw data and their country of origin.10 Since the data availability is

    increasing during the years and the number of countries participating in benchmarking

    studies is increasing as well, it is recommended that the above statistics are to be revised at

    regular time intervals (say, every two to four years).

    4.2.2 Comparisons Saudi versus International

    The following table compares the values from SAUDI ARABIA to those found for the

    international peer group.

    Table 4.4 Comparison of continuity performance for the Energy not Supplied (ENS)

    KPI SEC

    Trans

    Marafiq

    Trans

    Q1 Median Q3

    T1: ENS 0.00081% n.a. 0.00015% 0.0005% 0.0012%

    T2: SAIDI-T (min) 3.67 n.a. 0.8 2.1 2.6

    T3: SAIFI-T 0.068 n.a. 0.04 0.06 0.09

    T4: MAIFI-T (T&D) n.a. n.a. 0.07 0.85 6.0

    10 The countries included in the sample are: Finland, Hungary, United Kingdom, France, Spain, Italy, Portugal,

    Norway, Australia, Lithuania, Denmark, Canada, Netherlands.

  • 7/30/2019 Target Incentive

    43/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 43

    T5: Outages100km n.a. n.a. n.a. n.a. n.a.

    T6: Nr Voltage Dips n.a. n.a. 77 146 257

    T7: Losses (%) 2.66% n.a. 2.9% 4.8% 6.85%

    The ENS value of SEC for 2007 has been derived from the SIMLI ( Total energy lost divided

    by system peak, reaching 2.57 minutes in 2007) and the peak of 2007 (34,953 MW) for the

    whole country: an ENS value of 1,497 MWh is then found for the SEC Transmission System.Then, considering the Energy Supplied by the Transmission network (185,471 GWh in 2007)

    a figure of 0.00081% can be derived for the ENS of SEC Transmission in 2007. This figure is

    higher than the international median (0.0005%) but less than the international Q3 (0.0012

    %).

    The SAIDI-T of SEC-Transmission (3.67minutes) appears to be above the median and the

    Q3 of international values (2.6 minutes).

    The SAIFI-T value of SEC-Transmission (0.068) and of Marafiq (0.81) are also above the

    international median found (0.06) but SEC-Transmission is below the international Q3 (0.09).

    The number of voltage dips is reported by seven countries11 out of the data collected and the

    diversity of the values is higher than for the others KPIs values collected (see Annex). From

    Saudi Arabia no value has been submitted (yet) by the companies. Comparisons would only

    make sense at a later stage of the benchmarking process.

    The transmission losses (2.66%) seem to be a good performance when compared to

    international data. This is probably linked to the fact that in Saudi Arabia generators are

    relatively close to consumption centers.

    The comparisons provided here indicate possible improvements of the performance in Saudi

    Arabia since:

    - exceptional events (i.e. Force Majeure and Generation failures) have been excluded

    from all above statistics,

    11Namely Norway, the Netherlands, Australia Queensland, Italy, Portugal, Hungary, France

  • 7/30/2019 Target Incentive

    44/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 44

    - the TSO of the compared countries are supposed to adapt their network to the

    context they face in terms of non-exceptional events.

    As a consequence, the above set of continuity data presents some homogeneity and

    presents a reasonable basis for a regulatory authority to set targets for continuity of supply.

    For long term target, the median value of the ENS parameters is proposed.

    4.2.3 Conclusions

    The median of the international ENS performance (0.0005%) is proposed as a long term

    target, which represents an improvement expectation of 0.00031%. Long-term here can be

    interpreted as a period of 10 years, which takes into account the high capital intensity of the

    transmission business and the long lead times necessary to implement structural

    improvements. On the short run, while progressing towards the long-run target, the

    intermediate target is based on half this improvement (0.00015%) is deemed to be a

    reasonable milestone for setting a short term target of 0.00065%.

    To much extent, the time scope for defining the short term can be negotiated taking into

    account the implementation delays of the actions that are felt necessary to reach the short

    term target.

    The continuity KPIs that are without targets like SAIDI-T and SAIFI-T confirm the position of

    the Transmission continuity of supply relatively in Saudi Arabia to the international median,

    indicating that some improvements are needed if the international median level is to be met.

    Other KPIs like voltage dips are more difficult to compare since this is not measured by

    most countries, and therefore no comparison will be presented here on this issue. Losses of

    SEC Transmission appear to indicate a good performance for a country as large as Saudi

    Arabia.

    The only transmission KPI to be subject to a target scheme in Transmission is the Energy

    Not Supplied (ENS). The long term target is proposed to be the median value of the peer

    group, which is 0.0005% of the Energy Supplied.

    Note that the target for ENS only applies to the unplanned interruptions category. Events

    associated with planned, generation, and force majeure are not subject to a target.

    The short term target is a value well above the long term target. This allows sufficient time

    for the transmission companies of Saudi Arabia to adapt their means in order to meet the

    long term target: The short term target is proposed here at 0.00065%.

  • 7/30/2019 Target Incentive

    45/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 45

    Table 4.5 Short and long term targets for KPIs in Transmission

    KPI Present Short Term Long Term

    T1: ENS 0.00081% 0.00065% 0.0005%

    The targets are set here for the ENS computed from unplanned interruptions of the voltage

    range 69 to 380 kV so that the performance can be compared to transmission networks

    consisting HV and EHV levels. For the ENS computed from interruptions originating below

    69 kV (hence concerning HV/MV transformers of SEC Transmission), the target should be

    set at the historical average of SEC Transmission (3 last years), international data not beingavailable on this specific component and voltage levels.

    4.3 INCENTIVE MECHANISMS

    4.3.1 Selection of Incentive Mechanism

    As discussed in Chapter 2, in the context of a cost plus regulation, which is the context of

    Saudi Arabia in 2009, there is usually no immediate need for incentives scheme on quality ofservice because the companies are not limited in their investments by a cap on their

    revenues and consequently on their costs. On the contrary, in context of a price-cap

    regulation, some control of the quality supply is to be implemented. In this light, the use of an

    overall standard seems to be the most appropriate approach at this point in time.

    Nevertheless, in the future ECRA may wish to adopt stricter incentive mechanisms if a

    change towards a stricter form of price control is adopted. Anticipating such a transition in

    future, it may however be worthwhile to investigate here the specifications of a

    penalty/reward scheme to be applied at that point in time.

    In terms of setting a penalty/incentive scheme for ENS, two main schemes are usually

    considered: the minimum standard and the penalty/reward system. The drawbacks and

    advantages of both are summarized in the table below:

    Advantages Disadvantages

    Minimum Standard

    Scheme

    All customers benefit from a

    same Guaranteed Service

    Level (GSL)

    The verification that the GSL

    is met at each customer

    location implies a the

  • 7/30/2019 Target Incentive

    46/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 46

    presence of a meter able to

    count the interruptions

    Penalty/Reward Scheme Is compatible with the classic

    type of meters

    Tends to avoid that the utility

    profits from too low

    investment in reliability

    Customers are treated as

    the average customer

    enjoying an average

    continuity of supply

    Since the two schemes do not counter each other out, they can be implemented to

    complement each other. However, as may be observed, the penalty/reward scheme is in

    principle more desirable. International experience has been gained in this field in several12

    countries.

    The penalty/reward schemes are all based on the following principle: the allowed revenues

    of the TSO are modified upwards or downwards depending on the continuity performance

    achieved. The experience of countries having set a penalty/reward system suggests two

    additional criteria:

    in order to avoid every year a computation of financial transfers and their realization

    for performances that are in fact close to the target, a dead-band should be

    considered around the target: in that way, no penalty and no reward is applied if the

    performance observed is within the dead-band.

    In order to limit the financial exposure of both the TSO and the public financing the

    scheme, a cap is applied to the penalty and to the reward for the reporting period (the

    year, normally). This cap is usually between 1% and 2% of the turnover.

    Based on the above concepts, the following characteristics are proposed for the scheme to

    be implemented in Saudi Arabia:

    1. The dead-band is proposed to be at levels 95 % and 105% of the target.

    2. The cap on the reward and on the penalty to be at 1% of the company turnover

    3. Smoothing the performance by using the average performance on 3 years for the

    incentive scheme

    12Great Britain, Hungary, Italy, Estonia

  • 7/30/2019 Target Incentive

    47/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 47

    With respect to the level of the financial penalty/reward, economic theory suggests that this

    should be set equal to the societal costs of the average interruption CENS expressed by

    the value of the ENS (in Riyals per kWh not supplied). At country level, this value is usually

    between 1 USD/kWh and 10 USD/kWh and varies from one country to another. Within a

    country and from one type of customer to another, the cost of interruptions CENS varies

    even more. For this reason it should preferably be set on the basis of a customer survey. For

    specific customers with a high sensitivity to the electricity supply13, this value can be very

    high particularly if no back-up supply is implemented.

    An initial estimate is often proposed as the GDP divided by the gross electricity demand. For

    2007, the energy sold to the customers in 2007 has been 169,750 GWh and the GDP has

    been 1 401.3 billion SR14 or 374.2 billion USD. Hence, for Saudi Arabia in 2007, the value

    CENS has been 8.255 SR/kWh, equivalent to 2.203 USD/kWh. However, we should point

    out that this estimate is only indicative because by essence it includes the economic product

    of activities that are almost independent from the electricity consumption (in many countries,

    the agriculture does not depend on electricity but only on some types of fuel for the

    transportation). Also, it hides the diversity of the consumers and their willingness to pay for

    an improved continuity. The CENS concept also ignores the difference between short and

    long interruptions, while in fact the incurred costs vary a lot with the interruption duration.

    Basically, the CENS concept assumes that all economic activities depend on the availability

    of electricity: the idea is that every kWh represents a fraction of the electricity consumption

    and makes possible the creation of economic activities on average up to the same fraction of

    the GDP. As a whole and although imperfect, the above estimate of CENS is the most

    practical value to start with in the frame of this project. The annex 5 proposes a basic

    questionnaire for a customer survey to assess the willingness to pay for avoiding

    interruptions, so that estimates of the CENS can be developed.

    The financial transaction can then be represented as a function of the continuity

    performance (the average ENS on 3 years, as indicated above, expressed in percent of theenergy supplied to the delivery points), where ENSt is the target level and TO is the turnover

    of the utility. This function is represented by the graphic below.

    As can be observed, the incentive scheme only translates into monetary terms the actual

    level of performance when it is outside the dead band of +/- 5% around the target level.

    Furthermore, the level of the penalty or reward is capped at 1% of the turnover.

    13hospitals, airports, banks, industries that may lose the daily batch production in case of an interruption 14

    http://www.economist.com/Countries/SaudiArabia/profile.cfm?folder=Profile-Economic%20Structure

  • 7/30/2019 Target Incentive

    48/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 48

    Figure 4.1: Proposed incentive scheme for ENS in Saudi Arabia

    Having defined the cap and the dead band by Cap and db, and a base revenue

    allowance Ro independent from the quality performance, the revenue allowance R of each

    transmission company would then typically be adjusted by its quality performance by the

    following expression:

    If ENS < ENSS*(1- db) a reward

    G= (ENSs-ENS)* CENS > 0

    is given, so that the total revenue of the utility becomes

    )*)();1(*max( CENSENSENSsRoCapRoR

    If ENS > ENSS*(1+ db) a penalty

    P= (ENS-ENSs)* CENS > 0

    High Performance

    Reward

    Penalty

    0.95*ENSt ENSt 1.05*ENSt ENS (% of ES)

    0.01*TO

    0

    0.01*TO

    Low Performance

  • 7/30/2019 Target Incentive

    49/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 49

    is applied, so that the total revenue of the utility becomes

    )*)();1(*max( CENSENSsENSRoCapRoR

    4.3.2 Incentive Mechanism Conclusions

    In Saudi Arabia, the regulation in place in 2009 is cost plus regulation. Under cost plus

    regulation, companies may introduce in their eligible costs for tariff setting all their

    investments costs plus an agreed rate of return: in such a context, there is no factor

    encouraging the utility to under invest for preserving the quality of supply. Therefore, there is

    no real need for an incentive scheme as far as the regulation regime remains as cost plus:

    A proposed incentive scheme is only recommended when another regulation regime (for

    example price-cap) is put in place.

    The incentive scheme described above will however only become important if price-cap

    regulation is introduced and where companies tend to be investing in too low amounts in the

    quality of supply. This scheme is configured such that around the target, i.e. beyond a

    certain dead-band, a reward proportional to the excess of quality is awarded to the

    company, while a penalty proportional to the deficit of quality is imposed to the company for

    any such deficit of quality. These rewards and penalties are also limited by a cap, and the

    whole scheme can be summarized by the following three characteristics:

    Smoothing by using the average performance on 3 years for the incentive scheme

    (but the yearly performance is to be reported)

    The dead-band is proposed to be at levels 95 % and 105% of the target.

    The cap on the reward and on the penalty is set at 1% of the turnover of the

    regulated company

    The slope of the reward and of the penalty should be equal to the value attributed to

    the ENS namely 8.255 SRD/kWh

    In terms of implementation, the scheme can consider the filling of a so-called account where

    companies can record the financial sums i.e. penalties/reward as a result of the incentive

    scheme over a certain period. This could be done for example every three or four years. In

    this way, the low quality in one year and its related penalty can be compensated by high

    quality of the next year and its related reward, and the difference would be subject to the

    financial transaction as the end of the period.

  • 7/30/2019 Target Incentive

    50/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 50

    As per the experience gained in countries that applied the scheme, these characteristics

    proved to be successful and has to lead to the continuity of improvements while limiting the

    financial exposure of the company to the scheme.

    As already stated above, this scheme could be applied from the moment when the regulation

    in place changes from the existing cost plus to a possible price -cap regulation regime.

    4.4 RECOMMENDATIONS TRANSMISSION

    We can now summary the recommendations with respect to the targets and incentivemechanisms for transmission in the following Table.

    Table 4.6 Summary of recommendations regarding targets and incentive mechanisms for

    Transmission.

    KPIUnit

    Short-Term

    Target

    Long-Term

    Target

    IncentiveMechanism

    T1

    Energy Not Supplied (ENS) MWh/year 0.00065% 0.0005%

    Overall Standard(now)

    Penalty/Reward(in future)

    T2 SAIDI-T Min/Year

    T3SAIFI-T Int/Year

    T4 MAIFI-T Int/Year

    T5Out100km

    Outages/year per

    100 km

    T6 Voltage Dips Nr/year

    T7Network Losses %

  • 7/30/2019 Target Incentive

    51/90

    Targets & Incentives Report Development of KPIs for the SaudiElectricity Sector

    22 May 2009 51

    5 DISTRIBUTION

    5.1 KPI OVERVIEW

    Based on discussions with the different stakeholders of the electricity sector in Saudi Arabia

    a list of KPIs for the distribution sub-sector was selected. This list has been complied based

    on its relevancy for ECRA to include in its KPI measurement framework. The following table

    provides an overview of the recommended KPIs for distribution. All KPIs are measured on

    an annual basis and reported, by each relevant utility.

    Table 5.1 Recommended KPIs for Distribution.

    Distribution KPI Unit Target Lev


Recommended