Task 3.5 Tests and Task 3.5 Tests and Integration Integration (http://ific.uv.es/grid/CROSSGRID-IFIC/) (http://ific.uv.es/grid/CROSSGRID-IFIC/) Wp3 kick-off meeting, Poznan, 29 th -30 th January 2002 Santiago González de la Hoz Institut de Física Corpuscular Universitat de Valencia - CSIC Spain
Transcript

Task 3.5 Tests and IntegrationTask 3.5 Tests and Integration(http://ific.uv.es/grid/CROSSGRID-IFIC/)(http://ific.uv.es/grid/CROSSGRID-IFIC/)

Wp3 kick-off meeting, Poznan, 29th-30th January 2002

Santiago González de la Hoz

Institut de Física Corpuscular

Universitat de Valencia - CSIC

Spain

SummarySummary

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 1

GoalsPartners of this task and Integration TeamInfrastructureTasks softwareDependencies between this task and other WP's or Grid projectsIFIC's Infrastructure as CrossGrid testbed (http://ific.uv.es/grid/)Time schedule

GoalsGoals

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 2

To deliver a release version of WP3 before each prototype.To combine the Crossgrid middleware and Globus

services to provide a functional Computing platformTest all tools and services of WP3The integration and validation phase will require

significant effort from all of the tasks

Partners and Integration TeamPartners and Integration Team

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 3

Partners

CYFRONET PSNC

UAB CSIC CSIC Santander

CSIC Valencia

U. A. Barcelona

PSNC, Poznan

CYFRONET, Cracow

Partners and Integration TeamPartners and Integration Team

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 4

Who?

Miroslaw Kupczyk 3.1Miquel A. Senar 3.2Brian A. Coghlan 3.3Jacek Kitowski 3.4S. González 3.5????

Where is information available ? http://www......

When are the meetings? (For example, via VRVS)

InfrastructureInfrastructure

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 5

CVS Repository

Package Repository

Support Tools

Task3.1: Portal, What is the Delivery?Task3.2: Grid resource managementTask3.3: Grid monitoringTask3.4: Large data manipulation

Source and binary RPM'sAccess via HTTP

DocsContac listBug/incident tracking system (Bugzilla)

CVS project database management, where??see for example:http://datagrid.in2p3.fr/cgi-bin/cvsweb.cgi/

http://marianne.in2p3.fr/datagrid/testbed1/repositories/pkg-repository.html

Tasks SoftwareTasks Software

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 6

Task 3.1: Portal access to the Grid independetly from the user location: It will use existing tools developed by other projects: GRAM, MDS, etc.. (standard elements from Globus), LDAP, XML, etc... From the integration point of view, important to define interfaces between two parties (to connect all tools developed in the WP3 and in WP2 and providing easy access to the applications deployed by WP1).Task 3.2: Construction of new resource management

techniques for parallel applications submitted to a Grid based on scheduling agents.Task 3.3: Design specification of the monitoring tool.Task 3.4: Data management and archiver systems.

DependenciesDependencies

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 7

WP4 (International Testbed Organisation): This task is very stronly correlated with the prototypes released in WP4 because the testbed will provide the framework to run the applications made in the differents WP's. WP1 (CrossGrid Application Development) and WP2

(Grid Application Programming Environment): All tools and services of WP3 will be used by the aplications. European DataGrid project: The WP6 (Testbed and

Demonstrators) and more concretly with the Integration Team because they are doing the tests and integration of the DataGrid middleware at the moment. (http://marianne.in2p3.fr).

IFIC's InfrastructureIFIC's Infrastructure

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 8

The IFIC is participating in the DataGrid project. We are working togheter other Spanish groups in the WP6 (http://ific.uv.es/grid/DATAGRID-SPAIN/). So, the IFIC is working in a DataGrid testbed at the

moment, with the corresponding software.134 Pc's running Linux 6.2 with 40 Gb disk space per

machine.Globus 2 (beta 21 version) is running.Condor 6.2.1 as batch system is running.

IFIC's InfrastructureIFIC's InfrastructureOur farmOur farm

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 9

The IFIC has the minimum hardware required for the deployment of a local CrossGrid testbed:

GIIS (Grid Index Information Service) machine, Dedicated 100 Mbps switch, More than three machines (standard type,

PIII>1GHz, 512 Mb RAM, HD40GB), One CA (Certification Authority) machine per

country.

Our farmOur farm

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 10

Our farmOur farm

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 11

K7 @1.4 Ghz, 1Gb RAM, 40 GBytes, network 100 and 2U height

100 Mbps switch for each rack

Our farmOur farm

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 12

GIIS (Grid Index Information Service) machine:The Globus host is the GIIS of a country or an institut. We recommed to install the Institut GIIS on a machine without gatekeeper (IFIC GIIS mds.ific.uv.es). This GIIS has to register itself to the Spanish (Country ) GIIS. The Spanish GIIS is the top level of Proyecto Datagrid España. The Spanish GIIS is grid001.ifca.unican.es, port 2166 and it is registered to the European GIIS (tesbed001.cern.ch) .

CA (Certification Authority) machine per country:In Spain the Certification Authority is IFCA (Instituto de Física de Cantabria) in Santander. The IFIC has personal certificates for the users and machine certificates for the gatekeepers.

Time ScheduleTime Schedule

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 13

Milestones:

Month 3: To define The integration team and the CVS database.Month 6: Co-ordination established with other WP and projects (WP4 Testbed Organisation).Month 10-12: First delivery version of WP3 prototype running in distributed local mode (First tests of the alpha software versions).Month 18: Component integrations on local grid (monitors, managers, applications and tests of the beta versions).Month 24: Integration on the International CrossGrid Testbed Month 33: Final deployment in CrossGrid.

Time ScheduleTime Schedule

Wp3 kick-off meeting, Poznan, 29th-30th January 2002 Santiago González de la Hoz 14

Deliverable documents:

Installation Guide (by The Integration Team); The aim of this document is to give an overview of the WP3 Middleware released for Prototype 0 and 1 as well as to lead site administrators through the whole installation, configuration and customization process.

Crossgrid WP3 Reports; The correspondent deliverable reports of the WP3 (Current situation, issues, partner details, meetings, etc..)