Date post: | 16-Aug-2015 |
Category: |
Documents |
Upload: | sai-sandeep |
View: | 57 times |
Download: | 1 times |
Guided by: Mr. Gaurav Tiwari
(Manager, A-F Blast Furnace)
Sai SandeepNIT ROURKELA
Study of Poor Life of High Pressure Pumps and
Suggest Recommendations
Project Process Flow:
• Process Flow of Slag granulation system of C BF & D BF• Specifications of HP Pumps
1. Introduction
• Analysis of Pump Life
2. Data Collection and Analysis
• Shop floor brainstorming on key issues • Look for other potential reason for failures
3. Constructing Fault Tree
• Detail out the set of selected recommendations • Check the feasibility
4. Recommendations
Process Flow of Slag Granulation System of C BF & D BF:
C-BF
D-BFSlag
Hot MetalBLOW BOX SLURRY HOUSE
Slurry PumpAgitation Tank
Slurry PumpAgitation Tank
SLAG PROCESSING
PLANT
Slag
Hot Metal
HIGH PRESSURE
PUMP
PRESSURIZED WATER
PRESSURIZED WATER
Specifications of High Pressure Pumps:
Total Number of High Pressure Pumps used = 6 ( 3 Each for C-BF & D-BF)
Pump Details
1 Flow capacity (m3/hour) 900
2 Head of pump(mWC) 50
3 Motor Rating (KW) 220
4 Make Mather & Platt
5 Water Temperature (◦C) 50
• Expected life of HP Pump is 3 to 4 years.
• In actual practice, maximum life is only 2.3 years, average life being 1.8 years.
Analysis of Life of HP Pumps:
D1 D2 D3 C1 C2 C30
0.5
1
1.5
2
2.5
2
1.6
2.32.1
1.7
1.2
1.7 1.8
HIGH PRESSURE PUMP LIFE(in Years)
1st pump 2nd Pump
Pum
p Li
fe (i
n ye
ars)
Maximum
• Cost of a single pump = Rs 5,53,000/-
• Cost of different parts of the pump bought in a single year
= Rs 57,550/-
• Total expenditure for Pumps and spare parts (2012 to 2016)
= Rs 8525200/-=Rs 85,25,200/-
Analysis of Poor Life of HP Pumps:
2015 2014 2013 2012
6
3
1
5
Number of Pumps consumed on yearly basis
Num
ber o
f Pum
ps
Fault Tree Analysis of Pump:Failure of Pumps
No yield
Pump obstructed
Broken shaft
Insufficient yield
Damaged impeller
Worn casing
Unusual behavior
Pump leaks
Pump heats up
Pump vibrates
Fault Tree Analysis of Pump:No yield
Pump obstructed
Strainer blocked due to thrash and Slurry
Vibration due To bad fit
Wrong direction of rotation
Insufficient yield
Damaged impeller
Corrosion
Due to Slurry
Crevice Corrosion
Erosion
Due to Slurry
Cavitation
Low suction
pressureSlur
ry clogged strainer
Resistance too
high due to slurry
Air in
waterMa
noeuvring(Design
)
Fault Tree Analysis of Pump:
Fault Tree Analysis of Pump:Unusual Behavior
Pump Leaks
Damaged Gland
Wear due to slurry
Wrong Assembly
Thermal Shock
Vibration
Pump heats up
Pumping with closed Valve
On 28 /05/2015,HP Pump Room was filled with
slurry water due to leakage by gland
failure
Reasons for Pump failure:
Pump Failure
Pump leakage due to gland
failure
Bearing damage
Pump jam occurs due to blockage
in strainer
Rotating elements like impeller etc.
worn out
Worn Casing due to erosion
The primary cause for failure of pump is the slurry present in the
feed water of HP pump.
What is the source of slurry present in
HP Pump feed water ?
3. HP PUMP RESERVOIR SLAG PROCESSING
PLANT
Suction Tank
P P P P
HP
HP
HP
Make Up Water
CHANNEL
HP PUMP RESERVOIR
Settling Tank
HP
HP
HP
TO C-BF
Blow Box
Flow Diagram Of Slag Processing Plant:
TO D-BF
Blow Box
About 1200 tons per day of slag mixed with pressurized water at blow-box reaches SPP through Slurry pump.
1. Settling Tank
2. Suction Tank
1
2
3
Observations:
In each sample ,it is found that TSS in HP Reservoir input is more than critical value.
On an average 383 ppm of TSS enters High Pressure Pump which is undesirable.
Most of the time ,it is found that TSS in HP Pump Reservoir input is more than Suction tank input.
Study of Samples:
29/05/2015 6/6/2015 11/6/2015 23/06/20150
100
200
300
400
500
600
700
800
900
1000
521
72224
120114 63 131
241
931
177
290
133
Total Suspended Solids (in ppm)
SETTLING TANK INPUT
SGDP SUCTION TANK INPUT
HP PUMP RESERVOIR INPUT
TSS
(in p
pm)
Critical Line for safe
operation of pumps
120 PPM
Substantially High Value
Sample Analysis:Why very high amount of TSS is present in the HP Pump Reservoir input ?
DEPTH=2.35m DEPTH=2.2m
DEPTH=7.2m DEPTH=6.8m
Current system has two settling tanks connected in parallel with a combined volume of 570 metre cube. This gives a retention time of 19 minutes which is inadequate for slurry-water separation.
Frequent cleaning of suction tank is not possible.
Low Pressure pumps present in SPP suck water from the bottom of the suction tank . This is the main reason for presence of high amount of TSS in HP Pump reservoir input.
Dimensions of Settling tank and Suction Tank
Problems caused due to slurry need to be solved not only for the safe operation of HP pumps but also for effective slag granulation keeping the cost and safety issues in mind.
HP PUMP ROOMFloating Particles present in the HP Pump Reservoir
Further problems caused due to slurry:
Recommendations:
Diversion of flow from Parallel to Series in Settling Tank
Use of Coagulants and Flocculants in Settling Tank
Dewatering Silos
Automatic Self Cleaning Strainer
Suction Tank Suction Tank
1.Diversion of flow from Parallel to Series in Settling Tank
SLAG PROCESSING
PLANT
CHANNEL
Settling Tank
Mixture of Slurry and
water From
Slurry House
SLAG PROCESSING
PLANT
CHANNEL
Slurry water
Parallel Flow Series Flow
Settling Tank
2.Use of Coagulants and Flocculants in Settling Tank
Suction Tank
SLAG PROCESSING
PLANT
CHANNEL
P P P P
TO HP PUMP
RESERVOIR
Slurry water
Coagulants will be
dosed here
Settling TankFlocculants
will be dosed here
Visual without chemical addition
Visual with Chemical addition
Observations: The slurry sample with chemical aid showed a much rapid
and better settling as compared to the other one. Initially the slurry had a TSS content of 212 ppm which
was reduced to 52 ppm after the addition of chemical.
3.Dewatering Silos
Suction Tank
Make Up Water
HP PUMP RESERVOIR
P P P P
Dewatering Silos
Slurry goes to
Drier in SPP
Discharge to the Tank = 1500 m3 per hour
Assumptions:Detention Period = 1 hourMaterial is Stainless Steel
Dimensions of the Tank:
Diameter = 16 mHeight of the circular part = 5 mHeight of the conical part = 8 mSurface Area of the tank= 524 m2
CAD MODEL:
4.Automatic Self-Cleaning Strainer
Function:• Continuous removal of entrained abrasive solids
from liquids in pipeline systems
• Integral backwash process controlled by automatic control system monitoring the strainer operation
Straining Cycle: Backwashing Cycle:
Cost
Qua
lity
LOW
HIG
H
Needs Detailed AnalysisInnovative
Trial Purpose
LOW HIGH
1.Diversion of Flow from parallel to series in settling tank
2.Use of Chemicals in Settling Tank
3.Dewatering Silos
4.Automatic Self Cleaning Strainer
Feasibility Study on the basis of PQCDSM:
Productivity (P) Reduction in breakdownsQuality (Q) Extent of Slurry-water
separationCost (C) Initial investment Maintenance CostDelivery (D) Reduced inventory stockSafety (S) Zero accidentsMorale (M) Increase in improvement
ideas Increase in small group
meetings
Learnings of the Project:
Got brief idea about Blast Furnace Operation and Slag Granulation System
Doing Fault Tree Analysis
Learned how to utilize and take information from the people of shop floor
Application of MATLAB and CATIA to solve practical problems
Thank You
UnderGround Tunnel
SLAG PROCESSING
PLANT
Process Flow:Charge
Hot Air + Coal Injection
Hot Metal Torpedo
Slag
Blow Box
AgitationTank
SP
SP
Suction Tank
P P P P
HP
HP
HP
Make Up Water
CHANNELHP PUMP RESERVOIR
PRESSURIZED WATER
Settling Tank
D-BF
HP
HP
HP
TO C-BF
Blow Box
D-1 H. Pr.Pump 9-Feb-12 9-Jan-14Rotating eliment 4-Sep-15
D-1 NRV
D-1 NRV Ball
D-1 Del valve 1-Aug-14D-1 Del bend 13/09/14
D-2 H. Pr.Pump 7-Jul-12 20-Jan-14 26-Sep-15D-2 NRV 14/05/15
D-2 NRV Ball 16/12/13 26/03/15
D-2 SUC VALVE 16/01/14
D-2 Del bend 27/09/14 2 no.
D-3 H. Pr.Pump 23-Feb-11 25-May-13 25-Feb-15D-3 NRV
D-3 NRV Ball 25.03.15D-3 Del bend 29.09.14 2 no
D1 Line
D2 Line
D3 Line
C-1 H.Pr. Pump 31.08.12 26.09.14C-1 NRV 04.11.13C-1 NRV Ball 31.12.12 23.10.13 08.05.15
C-2 H.Pr. Pump 16.02.12 26.10.13C-2 NRV 25.02.14C-2 NRV Ball
C-2 DELV VALVE 21.03.14
C-3 H.Pr. Pump 10.09.11 10.11.12Rotating eliment 10.06.14
C-3 NRV 20.02.13C-3 NRV Ball 13.11.12
C1 Line
C2 Line
C3 Line
39%
21%
16%
15%6%3%
Breakdown of D Furnace since NOV 2014(in terms of hours)
CAST HOUSE STOVES CHARGING SGDPSTOCK HOUSE OTHERS
SGDP
33%
26% 15%
12%11%
3%
Breakdown of D Furnace since NOV 2014(in terms of frequency)
CAST HOUSE CHARGING STOVESSTOCK HOUSE SGDP OTHERS
SGDP
Feasibility Study on the basis of PQCDSM:
Recommendations 1.Diversion of Flow 2.Use of Chemicals in Settling Tank 3.Dewatering Silos 4.Automatic Self
Cleaning Strainer
Productivity (P) Reduction in breakdowns 5 9 10 8
Quality (Q) Extent of Slurry-water separation 5 9 8 7
Cost (C) Initial investment Maintenance Cost
10 4 6 7
Delivery (D) Reduced inventory stock 6 9 9 7
Safety (S) Zero accidents 10 7 9 10
Morale (M) Increase in improvement ideas Increase in small group meetings
5 9 9 9
Total 41 47 51 48
Design and Calculations for Dewatering Silos:
Given:Material of the tank is Stain less steelDischarge to the tank (Q) =1500m3 per hourVolume of the tank (V) = Q × t…………………………………………...eqn (1)where, t is the detention period.Generally, Detention Period is 1-3 hours.Assumption:t= 1 hourD be the diameter of the tankh be the height of the conical part of the tankH be the height of the circular part of the tankTVH be the total vertical height of the dewatering silos Cross sectional area of the circular tank (A) = (Π/4) × (D2)…..eqn(2)
Total Volume of the tank = Volume of the conical part + Volume of the circular part V= Taking common in RHS,V= From eqn (1) & eqn(2) ,We getQ By rearranging the above eqn,h=TVH= H+h
By assuming different values of D and H we can design the tank. To optimize the size, height and surface area of the tank, MATLAB program has been executed which is shown below.
The above program gives following results:D=16m,H=5m,h=8m,TVH= 13m,Surface Area = 524 m2
From design tables with reference to Underwriters Laboratory, Inc., UL 142, "steel aboveground Tanks for Flammable and Combustible Liquids." (1984)We get the thickness of the tank = 2 cm CHECK-1:Hoop’s stress on the walls of the tank:Ϭ= (ρ ×g × h× D) / (2×t)Where, Ϭ= hoop’s stress ρ= density of the water, 1000 kg per m3
g= acceleration due to gravity, 9.81 m/s2
h= TVH, 13m Ϭ hoop’s stress found to be 51 MPa which implies that it is a safe design.
CHECK-2:Settling Velocity of the slurry particles:Density of suspended particles (ρp) =2650 kg/m3;Density of water (ρ) =984 kg/m3;Dia of particles (Dp) = 0.5mm;Viscosity (µ) =0.4658 milli Pa-sec;
Settling Velocity of particles in Laminar Flow
18
)()(
2pp
s
DgV
Reynold’s Number (Re)=514.728As 1<Re<104, the flow is transitional.
Coefficient of Drag (Cd)= +0.34=0.5189
24
Re 21
)(
3
eR
Settling Velocity of Spherical Particles =0.1461m/s
Cd
Dg pps 3
)(4)(
After several iterations, we found the value of converges as 0.1175m/s.Minimum up flow velocity (Vu) =Q/A=0.00207m/sAs Vs>Vu, sedimentation of particles will occur easily.Hence, our design is safe.
CAD MODEL & DRAWINGS: