+ All Categories
Home > Documents > TAURON Group’s Q1-Q3 2014 financial...

TAURON Group’s Q1-Q3 2014 financial...

Date post: 28-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
32
TAURON Group’s Q1-Q3 2014 financial results November 13, 2014
Transcript
Page 1: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

TAURON Group’s Q1-Q3 2014 financial results

November 13, 2014

Page 2: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Q1-Q3 2014 key financial parameters

TAURON Group’s Q1-Q3 2014 financial results

[PLN m] Q1-Q3 2014

Sales revenue 13 603 (-4.3% yoy)

EBITDA 2 915 (-2.8% yoy)

Net profit* 1 049 (-13.8% yoy)

CAPEX 2 010 (-15.1% yoy)

Net debt/EBITDA 1.73x (up 0,3)

Key segments’ Q1-Q3 2014 results

[PLN m] Distribution Supply Heat Generation Mining

Segment’s revenue 4 529 11 267 967 2 305 871

EBITDA 1 778 501 182 200 83

EBIT 1 071 479 71 (154) 5

CAPEX 1 286 2.2 225 235 125

2 * Net profit attributable to the parent company’s shareholders

Page 3: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Q3 2014 key financial parameters

TAURON Group’s Q3 2014 financial results

[PLN m] Q3 2014

Sales revenue 4 377 (-3.6% yoy)

EBITDA 921 (-2.8% yoy)

Net profit* 318 (-13.3% yoy)

CAPEX 760 (-25.4% yoy)

Net debt/EBITDA 1.73x (up 0,3)

Key segments’ Q3 2014 results

[PLN m] Distribution Supply Heat Generation Mining

Segment’s revenue 1 480 3 692 249 832 341

EBITDA 608 110 17 73 55

EBIT 371 105 (21) (44) 29

CAPEX 444 1.4 127 109 43

3 * Net profit attributable to the parent company’s shareholders

Page 4: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Highlights

Date Event

July 22 Signature with the European Investment Bank of a PLN 295m loan agreement for CAPEX projects in the renewable

energy sources and distribution segments

October 24 Fitch Ratings agency reaffirmed TAURON’s BBB rating with a stable outlook. Company’s bond issue was granted A

level domestic rating

November 4 Settlement of the PLN 1.75bn bond issue as part of the bond issue program launched in July 2013. Bond issue funds

will be used to finance TAURON Group’s CAPEX projects

November 5 TAURON Ekoenergia signed agreement with Iberdrola group companies for the construction of the second stage of

Marszewo Wind Farm (18 MW). Contract’s net value: PLN 101.3m

TAURON

MARKET

Date Event

September 27

Publishing by PSE (TSO) of the Transmission Grid Operational Manual (Grid Code) update draft – planned modification

of the Operational Capacity Reserve (Operacyjna Rezerwa Mocy – ORM) and reduction of the ORM price in 2014 to

PLN 17/MW-h

October 24

European Council agreed on the climate policy framework until 2030. The main target: reducing CO2 emission by at

least 40 percent by 2030. Past 2020 the Polish power sector will be able to use a pool of free of charge CO2 emission

allowances – its allocation details have not been established yet

September Continued works by the Parliament (Sejm) on the government’s draft law on renewable energy sources. Planned

coming into force of the law: January 2016

4

Page 5: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

46

47

48

49

50

51

52

53

54

55

56

0%

1%

2%

3%

4%

5%

Q1 2

011

Q2 2

011

Q3 2

011

Q4 2

011

Q1 2

012

Q2 2

012

Q3 2

012

Q4 2

012

Q1 2

013

Q2 2

013

Q3 2

013

Q4 2

013

Q1 2

014

Q2 2

014

Q3 2

014

Q4 2

014

Poland’s GDP growth rate* and manufacturing PMI (quarterly average)

GDP growth rate Manufacturing PMI2

+0.3 p.p.

-4%

-2%

0%

2%

4%

6%

8%

10%

12%

Q1 2

011

Q2 2

011

Q3 2

011

Q4 2

011

Q1 2

012

Q2 2

012

Q3 2

012

Q4 2

012

Q1 2

013

Q2 2

013

Q3 2

013

Q4 2

013

Q1 2

014

Q2 2

014

Q3 2

014

Q4 2

014

Increase of manufacturing production sold and electricity consumption (yoy change)*

increase of production sold change of domestic electricity consumption

+0.8 p.p.

forecast increase of production sold

Macroeconomic and market situation

62.63 58.95

42.29 40.57

5.73 7.17

9.09 8.38

0

20

40

60

80

100

120

Q1-Q3 2013 Q1-Q3 2014

other

renewable energysources

lignite fired thermalpower plants

hard coal firedthermal power plants

115.1 119.7

-3.9%

Yearly BASE contract prices on the Polish Power Exchange (TGE)

* Source: GUS, IBnGR , PSE

-5.9%

-4.1%

+25.1%

-7.9%

Structure of electricity generation in Poland [TWh]

PMI GDP

TWh

52.3%

35.3%

4.8%

7.6%

51.2%

35.2%

6.2%

7.3%

Average electricity sales prices on the competitive market (acc. to ERO):

2011: PLN 198.30/MWh

2012: PLN 201.36/MWh

2013: PLN 181.55/MWh

5

GDP growth rate forecast

Average price

[PLN/MWh]

Volume

[GWh]

Y-13 182.75 184 615

Y-14 164.24 225 263

Y-15 170.89 141 438

Y-16 175.79 20 918

Y-17 184.14 359

Page 6: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

13.37

9.94

0.91

1.33

10.59

8.78

0

2

4

6

8

10

12

0

2

4

6

8

10

12

14

electricity electricity - RES heat

14.28

11.27

3 572 35.74

5 324

5 369

5 200

5 250

5 300

5 350

5 400

0

5

10

15

20

25

30

35

electricity distribution number of customers

2.88 2.53

1.41

1.00

4.26 3.99

0,0

1,0

2,0

3,0

4,0

intra-Group hard coal sales hard coal sales outside the Groupcommercial hard coal production

Q1-Q3 2014 key operating data

Q1-Q3 2013 Q1-Q3 2014

Electricity [TWh] and heat [PJ] generation

Q1-Q3 2013 Q1-Q3 2014

Hard coal production and sales [tons m]

Q1-Q3 2013 Q1-Q3 2014

Electricity distribution [TWh] and number of customers [‘000]

30.71 28.39

0

7

14

21

28

electricity supply

-7.6 %

Q1-Q3 2013 Q1-Q3 2014

Electricity supply [TWh]

-12.2%

-29.1%

-6.3%

-25.7%

46.2%

-17.1%

0,1% 45 thou.

Mg m

customers TWh

TWh PJ

TWh

6

Page 7: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

11.74 11.86

5 324

5 369

5 200

5 250

5 300

5 350

5 400

0

2

4

6

8

10

12

electricity distribution number of customers

4.22 3.56

0.31

0.42

1.16

0.95

0

1

0

1

2

3

4

5

electricity electricity - RES heat

4.53

3.98

0.83 0.93

0.50 0.42

1.26 1.44

0,0

1,0

intra-Group hard coal sales hard coal sales outside the Grouphard coal commercial production

Q3 2014 key operating data

Q3 2013 Q3 2014

Electricity [TWh] and heat [PJ] generation

Q3 2013 Q3 2014

Hard coal production and sales [tons m]

Q3 2013 Q3 2014

Electricity distribution [TWh] and number of customers [‘000]

9.85 9.13

0

7

electricity supply

-7.3%

Q3 2013 Q3 2014

Electricity supply [TWh]

12.0%

-16.0%

14.3% -15.6%

35.5%

-17.6%

1.0% 45 thou.

Mg m

customers TWh

TWh PJ

TWh

7

Page 8: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

1 264

1 053

0

200

400

600

800

1 000

1 200

1 400

8 349 7 765

4 166 4 327

1 699 1 511

0

2 000

4 000

6 000

8 000

10 000

12 000

14 000

16 000

I-III kw. 2013 I-III kw. 2014

electricity distribution and commercial services other revenue

14 214 13 603

Q1-Q3 2014 key financial data

Q1-Q3 2013 Q1-Q3 2014

Sales revenue [PLN m]

Q1-Q3 2013 Q1-Q3 2014

Net profit [PLN m]

-16.7% -7.0%

3.9%

-11.1%

3 001

+237 +42 +19 3 298

2 915

0

500

1 000

1 500

2 000

2 500

3 000

3 500

Q1-Q3 2013 EBITDAreported

Asset impairmentcharge

Inventory impairmentcharge

LTC (PPA) revenue(final settlement)

Q1-Q3 2013 EBITDAcomparable

Q1-Q3 2014 EBITDAreported

/comparable

No one-off events occurred in Q1-Q3 2014

Q1-Q3 2013 EBITDA vs Q1-Q3 2014 EBITDA [PLN m]

-11.6%

8

6% 3% 4% 7%

3% 5% 5% 6%

57% 61%

25% 17% 2% 3%

0.5% 0.8%

-2% -3%

-500

0

500

1 000

1 500

2 000

2 500

3 000

3 500

Q1-Q3 2013 Q1-Q3 2014

Mining Generation RESHeat Distribution SupplyCustomer service Other Unassigned items

2 915 3 001 mln -2.8%

Q1-Q3 2013 EBITDA vs Q1-Q3 2014 EBITDA structure

Page 9: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

947 +19 966 921

0

500

1 000

1 500

Q3 2013 EBITDA reported LTC (PPA) compensationrevenue (final settlement)

Q3 2014 EBITDA comparable Q3 2014 EBITDA reported/comparable

No one-off events occurred in Q3 2014

372

319

0

50

100

150

200

250

300

350

400

2 692 2 529

1 347 1 400

468 448

0

1 000

2 000

3 000

4 000

5 000

6 000

Q3 2013 Q3 2014

electricity distribution and commercial services other revenue

4 5 4 377

Q3 2014 key financial data

Q3 2013 Q3 2014

Sales revenue [PLN m]

Q3 2013 Q3 2014

Net profit [PLN m]

-14.3% -6.1%

3.9%

-10.6%

Q3 2013 EBITDA vs Q3 2014 EBITDA [PLN m] Q3 2013 EBITDA vs Q3 2014 EBITDA structure [PLN m]

-4.7%

9

3% 6% 9% 8% 2% 5%

3% 2%

63% 66%

16% 12% 4% 3%

0.8% 1.2%

-2% -3%

-200

0

200

400

600

800

1 000

1 200

Q3 2013 Q3 2014

Mining Generation RESHeat Distribution SupplyCustomer service Other Unassigned items

921 947 -2.8%

Page 10: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

1 713 1 547

1 287 1 368

83 59 17 77

15

-15 -85 -246

9

21.1% 9.6% 8.7% 65.9% 18.8% 39.3% 4.5% 19.0% 11.3% - 21.4%

0

500

1 000

1 500

2 000

2 500

3 000

3 500

4 000

Q1-Q3 2013EBITDA

Mining Generation RES Heat Distribution Supply Customerservice

Other Unassigneditems

Q1-Q3 2014EBITDA

EBIT Depreciation Growth per segment Drop per segment EBITDA margin

2 915

Q1-Q3 2014 EBITDA

Most important factors affecting Q1-Q3 2014 EBITDA:

Mining – declining thermal coal price and sales volume along with the drop of own costs of coal sold

Generation – lower wholesale electricity prices, lower electricity and heat sales volume, lower CO2 provision cost, lower variable unit cost (lower fuel

prices), higher revenue from Regulatory System Services (RUS) and operational reserve, asset impairment charge in H1 2013

Distribution – increase of distribution service sales price and volume, lower balancing difference factor and lower cost of purchasing electricity to cover

the balancing difference

RES – higher volume of sales of electricity and property rights from wind farms, higher property rights sales price, lower electricity prices

Heat – lower electricity sales price, higher heat sales price, lower heat supply and distribution volume, higher margin on certificates, red and yellow

property rights impairment charge in the first half of 2013

Supply – higher redemption obligation and prices of green, violet and white property rights, restoration of the obligation to redeem red and yellow

certificates; lower volume and retail sales price of electricity, lower electricity purchase price had a beneficial impact

PLN m -2.8%

3 001

10

Page 11: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Q3 2014 EBITDA

Most important factors affecting Q3 2014 EBITDA:

Mining – declining hard coal market prices, slight increase of the hard coal sales volume, along with the drop of the unit cost of coal sold

Generation – lower electricity prices, lower electricity and heat sales volume, lower CO2 provision cost, higher revenue from the operational capacity

reserve

RES – higher volume of sales of electricity and property rights from hydroelectric power plants (favorable hydrological conditions) and wind farms

(impact of Wicko and Marszewo wind farms)

Heat – higher variable unit generation costs (higher prices of purchasing blast furnace gases), lower electricity sales price, higher CO2 cost

Distribution – lower cost of purchasing electricity to cover the balancing difference, increase of distribution service sales price and volume, rising

transition fee charged by the TSO

Supply – higher redemption obligation and prices of green and violet property rights, reinstatement of the obligation to redeem red and yellow

certificates, lower electricity supply volume and higher margin on electricity retail sales

524 464

423 456

25 24 12 3

-16 -16 -42 -7 -10

20.9% 16.2% 8.8% 64.3% 6.7% 41.1% 3.0% 20.1% 14.1% - 21.0%

0

200

400

600

800

1 000

1 200

1 400

Q3 2013EBITDA

Mining Generation RES Heat Distribution Supply Customerservice

Other Unassigneditems

Q3 EBITDA2014

EBIT Depreciation Growth per segment

921

PLN m -2.8%

947

11

Page 12: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Q1-Q3 2014 prime costs structure

Declining costs in Q1-Q3 2014 are mainly due to:

consumption of materials (lower fuel costs)

depreciation including impairment charges

taxes and fees

employee benefit costs – mainly the result of the Voluntary

Redundancy Programs implemented and the lower headcount

Cost structure:

In Q1-Q3 2014: variable costs (excluding the value of goods and materials sold)

approx. 37%, fixed costs approx. 63%

In Q1 –Q3 2013: variable costs approx. 38%, fixed costs approx. 62%

Most important reasons for the changed cost structure:

lower fuel cost

lower cost of CO2 emission allowances

higher cost of energy certificates of origin

12

20%

19%

23%

21%

24%

27%

7%

6%

25%

26%

1%

1%

0% 20% 40% 60% 80% 100% 120%

Q1-Q32013

Q1-Q32014

Depreciation Consumption of materials and energy External services Taxes and fees Employee benefit costs Other prime costs

Prime costs structure PLN m

7 292

7 773

-6.2%

Fixed costs 62%

Variable costs 37% Fixed costs 63%

Variable costs 38%

1 373 1 501 1 944 467 1 895

1 532 1 786 1 837 580 1 925

Page 13: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Q3 2014 prime costs structure

Q3 2014 costs comparable to Q3 2013 costs as a result of:

declining costs of consumption of materials and energy

rising costs of:

depreciation

external services

employee benefit costs – implementation of the remuneration

agreement in Q3 2014

Cost structure:

In Q3 2014: variable costs (excluding the value of goods and materials sold)

approx. 36%, fixed costs approx. 64%

In Q3 2013: variable costs approx. 40%, fixed costs approx. 60%

Most important reasons for the changed cost structure:

lower fuel cost

lower cost of CO2 emission allowances’ provision

higher cost of energy certificates of origin

13

18%

19%

23%

20%

26%

27%

7%

7%

24%

25%

2%

2%

0% 20% 40% 60% 80% 100% 120%

Q32013

Q32014

Depreciation Consumption of materials and energy External services Taxes and fees Employee benefit cost Other prime costs

Prime costs structure PLN m

2 440

2 441

0.0%

Fixed costs 60%

Variable costs 36% Fixed costs 64%

Variable costs 40%

456 489 655 179 619

432 553 645 179 593

Page 14: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Debt and financing

Structure of TAURON Group’s debt [PLN m]

Financing available toTAURON Group [PLN m]

TAURON Group’s debt maturity [PLN m]

financial debt (debt due to investment loans, loans, leases and bonds)

as of September 30, 2014: PLN 6 552m

average weighted debt maturity as of September 30, 2014:

including all BGK bonds – 43 months

EUR debt constitutes 0.04% of the total debt

structure of debt by interest rate:

19% – fixed interest rate, i.e. PLN 1 226m

81% – floating interest rate, i.e. PLN 5 326m, including:

- unsecured amount – PLN 1 886m

- secured amount – PLN 3 440m

6 552

3 445

14

86

1 453

3 153

150 158 240 240 240 189 182 161 100 100 100 -

500

1 000

1 500

2 000

2 500

3 000

3 500

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

obligacje kredyty, pożyczki i leasingibonds

5 198 79%

1 226 19%

60 1%

68 1%

obligacje

kredyty z EBI

pożyczkipreferencyjne zNFOŚiGW/WFOSiGW

pozostałe kredyty,pożyczki i leasingi

bonds

EIB loans

National/Regional

Environment Protection

and Water

Management Fund

loans on preferential

terms

other credits, loans

and leases

2 750 80%

100 3%

295 8%

300 9%

obligacje obejmowaneprzez konsorcjumbanków

obligacje BGK

kredyt EBI

cashpooling

EIB loans

bonds underwritten by

the consortium of

banks

BGK bonds

Net debt / EBITDA:

1.73x

credits, loans and leases

Page 15: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

CAPEX – key projects’ work progress

Investment project

Capaci

ty

(MWe)

Capac

ity

(MWt)

Project status Work progress Planned

completion date

Construction of the hard coal-fired unit

at Jaworzno III Power Plant 910 -

In the first half of November RAFAKO-Mostostal consortium will hand over the

unit’s basic design. At the same time TAURON Generation is planning to formally

hand over the unit’s construction site to the General Contractor. The process of

selecting contractors that will install the unit’s auxiliary systems and installations –

ash removal and stoking (coal feeding) systems – is underway. Design works and

obtaining of successive administrative approvals are underway

9% 2019

Construction of the CCGT unit at

Stalowa Wola Combined Heat and

Power Plant

450 240

Installations of the gas and steam turbogenerator sets are underway. Installation of

the pressurized part of the recuperation boiler is underway. Basic installation of the

stack is completed. The upgrade of the pressure increase stage is close to

completion. Main machines and devices of the gas and steam unit are at the

construction site

64% 2015

Construction of the hard coal-fired co-

generation unit at ZW Tychy 50 86

Boiler’s steel structure’s installation completed, boiler drum’s water tests

conducted. Foundations of the inclined coal conveyor’s support completed, works

related to installing cooling water ducts and cooling water pump station completed 26% 2016

Construction of the TG 50 ZW Nowa

turbogenerator 50 -

Turbine’s delivery completed, assembly works in the machine room underway.

Partial acceptance of the power offtake completed. Works on cooling water

installations underway 61% 2015

Jaworzno III Power Plant – installing of

the flue gas denitrification systems

and upgrading of the 200 MW units

- -

Upgrade of two of six units to be upgraded is planned in 2015-16. Units no. 1 and 5

– tender procedure underway. Unit no. 3 – optimization works underway following

the commissioning of the unit after the upgrade and preparations of the warranty

measurements

66% 2016

Łaziska Power Plant installing of the

flue gas denitrification systems and

upgrading of the 200 MW units

- - Upgrade of the last one (no. 9) of the four units underway. According to the

project’s assumptions starting from 2015 all 200 MW units will reduce NOx

emissions to less than 200 mg/Nm3

85% 2015

Construction of the CCGT unit at

Łagisza Power Plant 413 266

Design has been prepared and the process of approving a sector wide notice on

the construction of the CCGT unit is underway. Environmental impact assessment

report has been compiled. Process of preparing documentation required to obtain

the construction permit and design works related to the generation unit have been

commenced. Deadline for submission of Contract Engineer bids elapses on

November 3

1% 2018

Construction of the 800m level at

Janina coal mine - -

Janina VI shaft deepening and drilling of the development headings underway. As

part of the Hard Coal Mechanical Processing Unit’s upgrade the construction of the

stone transportation and storage system is carried out 14% 2019

Construction of Grzegorz shaft at

Sobieski coal mine - -

Drilling of the 830 m deep test exploration borehole completed. Construction of the

electric distribution sub-station commenced. Investment project’s basic design

accepted 15% 2022

15

Page 16: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

CAPEX – by segment

CAPEX by segment [PLN m]

2 368

2 010

* CAPEX does not include PLN 330m of capital costs including PLN 310m spent to purchase TAURON Mining shares

Main investment projects completed in Q1-

Q3 2014:

Distribution – construction of new

connections (PLN 338m) and upgrade

and restoration of grid assets (PLN

803m)

RES – construction of the Marszewo

wind farm’s 2nd stage (PLN 20m),

upgrade of hydroelectric power plants

(PLN 54m)

Generation – construction of the NOx

emission reduction system (PLN 130m)

Heat – construction and upgrades of the

heat transmission pipeline networks

(PLN 56m), restoration of ZW Tychy’s

capacity (PLN 91m) and construction of

the 50 MW turbogenerator set at ZW

Nowa (PLN 28m)

Mining – construction of the 800 m level

and launch of the fourth coal face at the

Janina coal mine (PLN 55m)

16

173 125

403

235

439

80

116

225

1 192

1 286

46

59

Q1-Q3 2013 Q1-Q3 2014Mining Generation RES Heat Distribution Supply and other

-15.1%

Page 17: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Segment Savings realized

in 2013 and in Q1-Q3 2014

Savings planned in

2013-2015 Progress % Main initiatives

Distribution PLN 272m PLN 416m 65%

Implementation of the ultimate business model, elimination of the redundant functions

Change of the way expenses are classified as CAPEX or OPEX

Optimization of the balancing difference

IT processes optimization

Integration of business functions in the support (maintenance) area

Optimization of external services

Generation

(including RES) PLN 279m PLN 387m 72%

Employment restructuring and process optimization

Reduction of upgrades (maintenance) for the least efficient units

Overhead cost optimization

Outsourcing of some functions, mainly in the maintenance area

Improvement of the devices’ efficiency, optimization of the production volume and operating

expenses at hydroelectric power plants

Reduction of the costs of support and maintenance of the wind farm’s operation

Heat PLN 35m PLN 33m 107%

Employment restructuring

Compressed air losses reduction

Asset restructuring

External services’ costs optimization

Procurement policy optimization

Mining PLN 24m PLN 28m 85%

Nitrogen production system construction

Coal sludge (slurry) dewatering station expansion

Potable water treatment

Electronic auctions in public procurement

Use of the mechanical lining when drilling headings

Other segments PLN 29m Employment restructuring, reduction of external services’ costs

Total PLN 639m PLN 864m 74%

OPEX reduction program

17

In 2013 and Q1-Q3 2014 the voluntary redundancy program (PDO) covered 556 persons. Over that period employment contracts were terminated with 1 131 persons (3 625

persons in total since the program’s launch in 2010). Savings resulting from redundancies, decreased by costs incurred to generate those savings, are included in the amounts

presented per segment

No threat for the plan’s implementation is envisaged

Structure of savings in 2013 and Q1-Q3 2014: 60% comes from employment restructuring, 40% from the other initiatives

Estimated structure of savings in the 2013-2015 time frame: 73% to come from employment restructuring, 27% from the other initiatives

Page 18: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Legal disclaimer

This presentation serves for information purposes only and should not be treated as investment-related advice.

This presentation has been prepared by TAURON Polska Energia S.A. (“the Company”).

Neither the Company nor any of its subsidiaries shall be held accountable for any damage resulting from the use of this presentation or a

part thereof, or its contents or in any other manner in connection with this presentation.

The recipients of this presentation shall bear exclusive responsibility for their own analyses and market assessment as well as evaluation of

the Company’s market position and its potential results in the future based on information contained in herein.

To the extent this presentation contains forward-looking statements related to the future, in particular such terms as ”designed”, ”planned”,

”anticipated”, or other similar expressions (including their negation), they shall be connected with the known and unknown risks, uncertainty

and other factors which might result in actual results, financial situation, actions and achievements being materially different from any future

results, actions or achievements expressed in such forward-looking statements.

Neither the Company nor any of its subsidiaries shall be obliged to provide the recipients of this presentation with any additional information

or to update this presentation.

18

Page 20: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

1 093

871

168 83 89

5

-100

100

300

500

700

900

1 100

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

89

5

-3

138

-183

-35 -150

-100

-50

0

50

100

Q1-Q3 2013 EBIT Hard coal salesvolume

Hard coal sales price Own cost of hard coalsold

Other factors Q1-Q3 2014 EBIT

Mining

Q1-Q3 2014 financial data [PLN m] Q1-Q3 2014 EBIT bridge [PLN m]

344 341

31 55

4 29

0

100

200

300

400

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

Q3 2014 financial data [PLN m] Q3 2014 EBIT bridge [PLN m]

20

4

29

5

28

-6

1

0

5

10

15

20

25

30

35

Q3 2013 EBIT Hard coal salesvolume

Hard coal sales price Own cost of hard coalsold

Other factors Q3 2013 EBIT

-94.3%

+570.9%

Page 21: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

-24

-44

21

29

19 3

-34

-12

-46 -100

-80

-60

-40

-20

0

EBITIII kw. 2013

Cenasprzedażyenergii el.

Wolumensprzedażyenergii el.

Jednostkowykoszt zm.energii el.

Marża naobrocie energią

el.

Koszty CO2 Odpisaktualizującynależności ztyt. KDT (3Q

2013)

Pozostałeczynniki

EBITIII kw. 2014

-254

-154

-176

237

10

34 116 16

-137

-350

-300

-250

-200

-150

-100

-50

0

Q1-Q3 2013EBIT

Generationassets

impairmentcharge

(Q2 2013)

Electricity salesprice

Electricity salesvolume

Variable unitelectricity cost

Margin onelectricity

trading

CO2 costs Other factors Q1-Q3 2014EBIT

Generation (conventional sources)

3 340

2 305

117 200

-254 -154 -500

0

500

1 000

1 500

2 000

2 500

3 000

3 500

4 000

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

Q1-Q3 2014 financial data [PLN m]

1 069

832

89 73

-24 -44 -200

0

200

400

600

800

1 000

1 200

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

Q3 2014 financial data [PLN m] Q3 2014 EBIT bridge [PLN m]

21

-84.7%

Q1-Q3 2014 EBIT bridge [PLN m]

+39.3%

Electricity

sales price

Q3

2013

EBIT

Q3 2014

EBIT Electricity

sales volume

Variable

unit

electricity

cost

Margin on

electricity

trading

CO2

costs

LTC (PPA)

receivables

impairment

charge (Q3

2013

Other

factors

Page 22: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

57

82 32

28

37

- 2

- 1

- 7

- 33

- 27

0

20

40

60

80

100

120

140

160

Q1-Q3 2013EBIT

Electricitysales volumehydroelectricpower plants

Electricitysales volumewind farms

Property rightssales volumehydroelectricpower plants

Property rightssales volumewind farms

Property rightssales price

Electricitysales price

Depreciation Other Q1-Q4 2014EBIT

Renewable Energy Sources (RES)

129

216

84

142

57

82

0

50

100

150

200

250

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

+44.8%

Q3 2014 EBIT bridge [PLN m]

Q1-Q3 2014 financial data [PLN m]

Q1-Q3 2014 EBIT bridge [PLN m]

36

71

22

46

13

26

0

10

20

30

40

50

60

70

80

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

Q3 2014 financial data [PLN m]

+99.1%

22

13

26 9

2 6

7

11

- 11

- 13

0

10

20

30

40

50

60

EBITIII kw. 2013

Wolumensprzedaży

energiiel. wodne

Wolumensprzedaży

energiiel.wiatrowe

Wolumensprzedaży PM

el. wodne

Wolumensprzedaży PM

el.wiatrowe

Cenasprzedaży PM

Amortyzacja Pozostałeczynniki

EBITIII kw. 2014

Q3 2013

EBIT

Q3 2014

EBIT

Electricity

sales volume

wind farms

Electricity

sales volume

hydroelectric

power plants

Property

rights sales

volume

hydroelectric

power plants

Property

rights sales

volume

wind farms

Property

rights

sales

price

Depreciation Other

factors

Page 23: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

1

-21

2

- 3

2

-8

-8

-7

-30

-20

-10

0

10

Q3 2013 EBIT Electricity salesvolume

Electricity salesprice

Variable unitgeneration costs

CO2 costs Depreciation Other factors Q3 2014 EBIT

76 71

33 11

8

18

2

- 8

- 27 - 20

- 22

0

20

40

60

80

100

120

Q1-Q3 2013EBIT

Red and yellowproperty rights

impairmentcharge (H1

2013)

Heat supply anddistribution

volume

Electricity salesvolume

Electricity salesprice

Heat sales price Margin oncertificates

Otheroperations

balance

Depreciation Other Q1-Q3 2014EBIT

Heat

926 967

165 182

76 71

0

200

400

600

800

1 000

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

Q3 2014 EBIT bridge [PLN m]

Q1-Q3 2014 financial data [PLN m] Q1-Q3 2014 EBIT bridge [PLN m]

Q3 2014 financial data [PLN m]

242 249

32 17

1

-21 -50

0

50

100

150

200

250

300

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

23

-6.5%

Page 24: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Distribution

4 451 4 529

1 701 1 778

1 024 1 071

0

1 000

2 000

3 000

4 000

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

1 024 1 071

64

147

8 36

-170 -31 -8

0

200

400

600

800

1 000

1 200

1 400

Q1-Q3 2013 EBIT Distributionservice price

Balancingdifference

DSO/TSOservices purchase

OPEX Depreciation Other operations Other Q1-Q3 2014 EBIT

+4.5%

Q1-Q3 2014 financial data [PLN m] Q1-Q3 2014 EBIT bridge [PLN m]

1 440 1 480

597 608

368 371

0

400

800

1 200

1 600

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

Q3 2014 financial data [PLN m]

368 371 20 13

41

-53 -12 -6

0

100

200

300

400

500

Q3 2013 EBIT Distribution serviceprice

Distribution servicevolume

Cost of grid losses- price

DSO/TSO servicespurchase

Connection fees Other factors Q3 2014 EBIT

Q3 2014 EBIT bridge [PLN m]

+0.7%

24

Page 25: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Distribution – volumes

10 392

11 427

1 985

3 013

7 260

Group A

Group B

Group C2

Group C1+R+D

Group G

Q1-Q3 2014 electricity distribution [GWh]

3 596

3 851

654

941

2 269

Group A

Group B

Group C2

Group C1+R+D

Group G

34 077

11 311

Q3 2014 electricity distribution [GWh]

10 236

11 090

1 946

3 078

7 430

Group A

Group B

Group C2

Group C1+R+D

Group G

Q1-Q3 2013 electricity distribution [GWh]

3 529

3 705

626

934

2 333

Group A

Group B

Group C2

Group C1+R+D

Group G

33 778

11 127

Q3 2013 electricity distribution [GWh]

Data related to the distribution of electricity to end users 25

Page 26: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

142

105 4

-12

29

-5 -13

-40

0

20

40

60

80

100

120

140

160

180

Q3 2013 EBIT Electricity salesvolume

Electricity price Price of green,violet and whiteproperty rights

Increased greenand violet property

rights obligation

Red and yellowproperty rights

obligation

Otherrevenue/costs

Q3 2014 EBIT

721

479

61

-51

-152 -44

-80

23

0

100

200

300

400

500

600

700

800

Q1-Q3 2013 EBIT Electricity salesvolume

Electricity price Price of green,violet and whiteproperty rights

Increased greenand violet property

rights obligation

Red and yellowproperty rights

obligation

Otherrevenue/costs

Q1-Q3 2014 EBIT

4 308

3 692

151 110 142 105

0

1 000

2 000

3 000

4 000

5 000

Q3 2013 Q3 2014Sales revenue EBITDA EBIT

Supply

13 301

11 267

747 501 721 479

0

2 000

4 000

6 000

8 000

10 000

12 000

14 000

Q1-Q3 2013 Q1-Q3 2014Sales revenue EBITDA EBIT

-33.6%

Q3 2014 EBIT bridge [PLN m]

Q1-Q3 2014 financial data [PLN m] Q1-Q3 2014 EBIT bridge [PLN m]

Q3 2014 financial data [PLN m]

-26.1%

26

Page 27: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

7 356

7 706

4 408

7 356

3 657

Grupa A

Grupa B

Grupa C2+C1+R+D

Grupa G

Sprzedaż pozostała**

Q1-Q3 2013 electricity supply* [GWh]

Group A

Group B

Group C2+C1+R+D

Group G

Other supply**

Supply – volumes

27

30 483

* Volumes of electricity supply to the strategic customers (key accounts) of TAURON Polska Energia S.A. are included in groups A and B

** Own needs and balancing differences of the Group’s subsidiaries, balancing differences to other DSOs, other

6 497

7 676 4 094

7 134

2 717

Grupa A

Grupa B

Grupa C2+C1+R+D

Grupa G

Sprzedaż pozostała**

Q1-Q3 2014 electricity supply* [GWh]

Group A

Group B

Group C2+C1+R+D

Group G

Other supply**

28 118

2 530

2 621 1 306

2 311

1 027

Grupa A

Grupa B

Grupa C2+C1+R+D

Grupa G

Sprzedaż pozostała**

Q3 2013 electricity supply* [GWh]

Group A

Group B

Group C2+C1+R+D

Group G

Other supply**

9 795

2 380

2 557

1 222

2 225

671

Grupa A

Grupa B

Grupa C2+C1+R+D

Grupa G

Sprzedaż pozostała**

Q3 2014 electricity supply* [GWh]

Group A

Group B

Group C2+C1+R+D

Group G

Other supply**

9 055

Page 28: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

33

19

11

7

2

-1

-32

0

10

20

30

40

50

60

Q3 2013 EBIT Revenue of CustomerService SharedServices Center

Revenue ofAccounting Shared

Services Center andHR Shared Services

Center

Revenue of IT SharedServices Center

Costs of servicesprovided

Other factors Q3 2014 EBIT

375

456

72 87 60 56

0

50

100

150

200

250

300

350

400

450

500

Q1-Q3 2013 Q1-Q3 2014

Sales revenue EBITDA EBIT

60 56 11

39

33

6

-92

0

20

40

60

80

100

120

140

160

Q1-Q3 2013 EBIT Revenue of CustomerService SharedServices Center

Revenues ofAccounting Shared

Services Center andHR Shared Services

Center

Revenue of IT SharedServices Center

Costs of servicesprovided

Other factors Q1-Q3 2014 EBIT

Customer service

-5.8%

Q1-Q3 2014 financial data [PLN m] Q1-Q3 2014 EBIT bridge [PLN m]

Q3 2014 financial data [PLN m] Q3 2014 EBIT bridge [PLN m]

-41.0%

140

155

38 31 33

19

0

30

60

90

120

150

180

Q3 2013 Q3 2014

Sales revenue EBITDA EBIT

28

Page 29: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

Electricity market price trends

* Sources: Point Carbon, TAURON 29

Electricity

Platforms: TGE, TFS, GFI,

GPW-POEE

2013 2014 (until 4.11.2014) 2014/2013

Price PLN/MWh Volume GWh Price PLN/MWh Volume GWh Price % Volume %

Forward BASE (Y+Q+M) 184.92 140 488 161.01 187 965 -12.9% 33.8%

Forward PEAK (Y+Q+M) 204.35 14 855 184.21 19 007 -9.9% 27.9%

Forward (weighted average) 186.78 155 343 163.14 206 972 -12.7% 33.2%

SPOT (TGE) 153.91 19 930 177.07 17 978 15.0% -9.8%

Weighted average total 183.04 175 273 164.26 224 950 -10.3% 28.3%

CO2 emission allowances (EUA/t) Property rights (PLN/MWh)

CO2 market analysts’ survey* Price (EUR/t) Certificate type Market prices (2014

average) (until 4.11.2014)

Substitution fee and

obligation for 2014

2013 average 4.48 EUR/t RES (green) 187.48 300.03 (13.0%)

2014 average 6.0 EUR/t Hard coal-fired cogeneration (red) 10.45 11.00 (23.2%)

2015 average 8.2 EUR/t Gas-fired cogeneration (yellow) 104.65 110.00 (3.9%)

Average 2014 EUA price forecast by

TAURON 6.0 – 6.5 EUR/t Methane (violet) 59.48 63.26 (1.1%)

Page 30: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

2015 BASE contracts

30

Average electricity price that takes into account 2015 one year BASE and PEAK contracts: PLN 170.89/MWh, total 2015 BASE and PEAK volume: 141 438 GWh

Average price

[PLN/MWh]

Volume

[GWh]

Total 167.03 126 004

including TGE 167.13 94 599

non TGE 166.74 31 405

Trading volume Price Average

price

PLN/MWh

Page 31: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

2016 BASE contracts

31

Average electricity price that takes into account 2016 one year BASE and PEAK contracts: PLN 175.79/MWh, total 2016 BASE and PEAK volume: 20 918 GWh

Average price

[PLN/MWh]

Volume

[GWh]

Total 175.39 20 774

including TGE 175.76 13 562

non TGE 174.69 7 212

Trading volume Average price Price

PLN/MWh

Page 32: TAURON Group’s Q1-Q3 2014 financial resultsen.tauron.pl/SiteCollectionDocuments/2014reports/Q3-2014...13.37 10 9.94 0.91 1.33 .59 8.78 0 2 4 6 8 10 12 0 2 4 6 8 10 12 14 electricity

TAURON's coverage by analysts

Institution Analyst

DB Securities Tomasz Krukowski

Dom Maklerski mBanku Kamil Kliszcz

Dom Maklerski Banku Handlowego Piotr Dzięciołowski

Dom Maklerski BZ WBK Paweł Puchalski

Dom Maklerski PKO BP Stanisław Ozga

J.P. Morgan Cazenove Michał Kuzawiński

Erste Group Tomasz Duda

Espirito Santo Investment Poland Maria Mickiewicz

Goldman Sachs Fred Barasi

HSBC Dmytro Konovalov

ING Securities Milena Olszewska

Institution Analyst

Ipopema Securities Piotr Zielonka

Raiffeisen Centrobank Teresa Schinwald

Renaissance Capital Vladimir Sklyar

Societe Generale Bartłomiej Kubicki

UBS Investment Research Michał Potyra

Patrick Hummel

Tomasz Walkowicz

UniCredit CAIB Flawiusz Pawluk

WOOD & Company Bram Buring

DM BOŚ Andrzej Bernatowicz

32


Recommended