Taylor Road Resurfacing Project
8/3/2019 Taylor Rd Public Meeting Presentation
2/25
2
General Inform ation:
Contractor: Perk Company, Inc.
Awarded: July 28, 2011
Signed Contract: August 25, 2011
Project Bid Price: $3,600,000
Project Length: 1.5 miles
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
3/25
3
General Inform ation:
Project Limits: Euclid HeightsBlvd. and Bayreuth Road
Project Administration:
ODOT District 12 ODOT Project Engineer:
Al Yost
ODOT Area Engineer:
Patrick McCafferty
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
4/25
4
W or k Schedule
Scheduled Start Date: April 2012
Scheduled Completion Date:September 30, 2012
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
5/25
5
W or k Schedule
Work will generally be from 7 a.m. - 3:30 p.m.
No night work
Weekend work only if needed to keep theproject on schedule
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
6/25
6
W or k Description
Repair the concrete base and resurfacewith asphalt from Euclid Heights Blvd toBayreuth Road
All of the existing asphalt will be removed Extensive concrete slab repair and
replacement from Euclid Heights Blvd to
Mayfield Road
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
7/25
7
W or k Description Additional concrete base repairs as
needed from Mayfield Road to BayreuthRoad
Resurface with approximately 5 inches
of asphalt
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
8/25
8
Eastern most lane (the
lane nearest to theshopping center) fromEuclid Heights Blvd to
Mayfield Road will beremoved
Road will be 5 lanes widein this area when work is
complete
New curbs and drainageinlets will be installed
W or k Description
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
9/25
9
W or k Description
Replace damaged portions of curb
throughout the project Approximately 40 driveway aprons will be
replaced (at locations marked for curb
replacement)
Upgrade curb ramps to ADA requirements
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
10/25
10
Traffic signals at Severance CenterAccess and Hollister Road will be removedpermanently
W or k Description
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
11/25
11
Phase 1
Shift all traffic to the East half of the road
and make repairs to the West half
Maintain both Northbound and Southboundtraffic
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
12/25
12
On Taylor Roadbetween Euclid
Heights Blvd andMayfield Road
1 Southbound lane
2 Northbound lanes
Phase 1
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
13/25
13
Phase 1
On Taylor Roadbetween MayfieldRoad and
Monticello Blvd1 Southbound lane
1 Northbound lane
1 Center turn lane
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
14/25
14
On Taylor Roadbetween Monticello
Blvd and BayreuthRoad
1 Southbound lane
1 Northbound lane
Phase 1
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
15/25
15
Phase 1 - Inter sections
Euclid Heights Blvd / Taylor RoadLeft turn lane for Northbound traffic
Left turn lane for Southbound traffic
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
16/25
16
Mayfield Road / Taylor Road
Right turn lane for Northbound trafficLeft turn lane for Southbound traffic
Lanes on Mayfield Road not changed
Phase 1 - Inter sections
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
17/25
17
Monticello Blvd. / Taylor Road
Left turn lane for Northbound traffic
Phase 1 - Inter sections
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
18/25
18
Phase 2
Shift all traffic to the West half of the roadand make repairs to the East half
Maintain both Northbound and
Southbound traffic
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
19/25
19
On Taylor Roadbetween EuclidHeights Blvd and
Mayfield Road1 Northbound lane
1 Southbound lane
1 Center turn lane
Phase 2
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
20/25
20
On Taylor Roadbetween MayfieldRoad and Bayreuth
Road1 Northbound lane
1 Southbound lane
Phase 2
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
21/25
21
Phase 2 - Inter sections
Euclid Heights Blvd / Taylor RoadRight turn lane for Northbound traffic
Left turn lane for Southbound traffic
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
22/25
22
Mayfield Road / Taylor RoadLeft turn lane for Northbound traffic
Lanes on Mayfield Road not changed
Phase 2 - Inter sections
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
23/25
23
Project Notes Please watch for construction
personnel and equipment whiletravelling through the work zones.
ODOT and City staff will work with you
to mitigate any concerns which willarise during the reconstruction.
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
24/25
24
Contact Us
City of Cleveland Heights: (216) 691-7311
ODOT Public Information Office:
(216) 584-2005 ODOT Construction Office:
(216) 584-2152
Al Yost & Pat McCafferty
Taylor Road Resurfacing
8/3/2019 Taylor Rd Public Meeting Presentation
25/25
25
Thank Y ou
Taylor Road Resurfacing